Junction structure between deck composite slab and beam
The joint structure between a deck composite slab and a beam using a stress transmission member between the flashing and beam addresses inefficiencies in existing methods, enabling faster and more efficient construction and improved load resistance.
Patent Information
- Application Number
- JP2023050653
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-27
- Publication Date
- 2024-10-09
AI Technical Summary
Existing methods for joining deck composite slabs to beams, such as stud welding and temperature plug welding, are time-consuming and inefficient when flashings are present, as they require additional steps and equipment, particularly when flashings are installed on both sides of the beam.
A joint structure that integrates a deck composite slab with a beam using a stress transmission member spanning between a flashing and the beam, which is fixed to the beam and embedded in concrete, allowing for easy construction and efficient transfer of in-plane shear forces.
This structure facilitates quicker construction by eliminating the need for headed studs and stud welding, while maintaining stability and enhancing the load resistance of the deck composite slab.
Smart Images

Figure 2024139621000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a joint structure between a composite deck slab and a beam. [Background technology]
[0002] Composite deck slabs, which are made by integrating deck plates and concrete, are joined to beams and used in a variety of buildings, including houses, stores, offices, parking lots, warehouses, and large offices. When a gap forms between the deck plates that make up the composite deck slab and the beams, flashing is used to adjust the gap. Flashing is usually not joined to the beams, and its only function is to fill the gap between the deck plate and the beams.
[0003] Known techniques for joining a deck composite slab to a beam include, for example, the technique of stud welding headed studs to the beam as shown in Non-Patent Documents 1 and 2, and the technique of burn-out plug welding the deck plate itself to the beam.
[0004] When headed studs are stud welded to beams, the in-plane shear force acting on the deck composite slab can be transmitted to the beams via the headed studs, regardless of whether flashing is used or not. However, stud welding has the problem that it takes time to install.
[0005] Since burn-out plug welding can be performed at the construction site using a general-purpose shielded metal arc welding machine, the construction can be easily performed. In addition, when the deck plate itself is burn-out plug welded to the beam, the in-plane shear force acting on the deck composite slab can be transmitted to the burn-out plug welded beam. However, for example, when flashing is provided on both sides of the beam in the width direction, or when flashing is provided on the beam that constitutes the outer periphery, the deck plate itself has a gap from the beam, so burn-out plug welding cannot be applied to these beams. For this reason, in order to transmit the in-plane shear force to the beam, headed stud welding may be required for the beam on which the flashing is provided. For this reason, there is a problem that construction takes a long time. [Prior art documents] [Non-patent literature]
[0006] [Non-Patent Document 1] Architectural Institute of Japan, "Guidelines and Commentary on Composite Structure Design", November 2010, pp.8-11, Part 1: Composite Beam Structural Design Guidelines, Chapter 5: Design of Shear Connectors, Chapter 6: Shear Strength of Shear Connectors [Non-Patent Document 2] Architectural Institute of Japan, "Technical Guidelines for Steel Construction - Construction Site Edition", January 2018, pp.316-354, Chapter 7: Deck Plates and Headed Studs Summary of the Invention [Problem to be solved by the invention]
[0007] Therefore, the present invention has been devised in consideration of the above-mentioned problems, and its object is to provide a joint structure between a deck composite slab and a beam that can be easily constructed. [Means for solving the problem]
[0008] The joint structure between a composite deck slab and a beam of the present invention is a joint structure between a composite deck slab and a beam in which a deck plate and concrete are integrated, wherein the beam is arranged along the longitudinal direction of the deck plate, and the composite deck slab comprises: a deck plate having a widthwise end portion intersecting the longitudinal direction of the deck plate with a gap therebetween; flashing arranged in the gap between the widthwise end portion of the deck plate and the beam; the concrete arranged above the deck plate and the flashing; and a stress transfer member arranged between the flashing and the beam, the stress transfer member being fixed to an upper surface of the beam and embedded in the concrete. Effect of the Invention
[0009] According to the present invention, a joint structure between a deck composite slab and a beam can be provided, which can be easily constructed. [Brief description of the drawings]
[0010] [Figure 1] FIG. 1 is a plan view showing an example of a joint structure between a deck composite slab and a beam in the first embodiment. [Diagram 2] FIG. 2 is a perspective view showing, in a partially cutaway form, an example of a joint structure between a composite deck slab and a beam in the first embodiment. [Diagram 3] Figure 3 shows an example of a joint structure between a deck composite slab and a beam in the first embodiment, where Figure 3(a) is a plan view showing the joint portion with a beam having flashing at one end in the width direction, and Figure 3(b) is a front view showing the joint portion with a beam having flashing at one end in the width direction. [Figure 4] Figure 4 shows an example of the joint structure between a deck composite slab and a beam in the first embodiment, where Figure 4(a) is a plan view showing the joint portion with a beam having flashing provided at both ends in the width direction, and Figure 4(b) is a front view showing the joint portion with a beam having flashing provided at both ends in the width direction. [Diagram 5] FIG. 5 is a side view showing an example of the deck plate structure in the first embodiment. [Figure 6] FIG. 6 is a side view showing an example of a deck plate structure in the second embodiment. [Figure 7] FIG. 7 is a side view showing an example of a deck plate structure in the third embodiment. [Figure 8] FIG. 8 is a side view showing an example of a deck plate structure in the fourth embodiment. [Figure 9] FIG. 9 is a side view showing an example of a deck plate structure in the fifth embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] Hereinafter, the embodiment of the joint structure between the composite deck slab and the beam according to the present invention will be described in detail with reference to the drawings. In each drawing, the vertical direction is Z, the width direction of the deck plate intersecting the vertical direction Z is width direction X, and the length direction of the deck plate intersecting the vertical direction Z and width direction X is length direction Y.
[0012] (First embodiment) The joint structure 100 between a deck composite slab and a beam is used in buildings such as houses, stores, offices, parking lots, warehouses, large offices, etc. Hereinafter, the joint structure 100 between a deck composite slab and a beam will also be referred to as a joint structure 100. As shown in Figs. 1 and 2, the joint structure 100 includes a deck composite slab 1 and a beam 8.
[0013] For example, H-shaped steel is used for the beam 8. The beam 8 has a plurality of beams 81 arranged along the length direction Y and a plurality of beams 82 arranged along the width direction X. As shown in FIG. 1, the span length of the beam 81 is Ly, and the span length of the beam 82 is Lx. The span length Ly is the distance between the fulcrums and the distance between the axes of two adjacent beams 82 connected to the beam 81. The span length Lx is the distance between the fulcrums and the distance between the axes of two adjacent beams 81 connected to the beam 82. The plurality of beams 8 are combined in a rectangular shape and joined to the deck composite slab 1. Of the beams 81 arranged along the length direction Y, a pair of beams 81a are arranged on the outer periphery of the deck composite slab 1, and of the beams 81 arranged along the length direction Y, a beam 81b is arranged between the pair of beams 81a.
[0014] As shown in Fig. 2, the deck composite slab 1 is a deck composite slab in which a deck plate 2 and concrete 4 are integrated together. The deck composite slab 1 includes the deck plate 2, a flashing 3, concrete 4, and a stress transfer member 5.
[0015] The deck plate 2 is a known deck plate formed by bending a steel plate into a corrugated shape, as shown in Figures 3(a) and 4(a). The deck plate 2 is disposed with a gap between the end 21 in the width direction X and the beam 81, as shown in Figures 3(b) and 4(b). The deck plate 2 has joints formed at both end parts 21 in the width direction X. The joints formed at the end part 21 of one deck plate 2 can be joined with the joints of the end part 21 of another adjacent deck plate 2. In addition, the joints formed at the end part 21 of one deck plate 2 can be joined with the joint part 31 of the flashing 3.
[0016] The flashing 3 is provided in the gap between the end 21 in the width direction X of the deck plate 2 and the beam 81. A known flashing can be used as the flashing 3. The flashing 3 can fill the gap between the end 21 in the width direction X of the deck plate 2 and the beam 81, and can prevent the concrete 4 poured upward from falling.
[0017] The flashing 3 is formed by bending a thin steel plate, for example with a thickness of about 1.2 mm to 1.6 mm, into a predetermined shape. The flashing 3 has a joint portion 31 that joins with the end portion 21 of the deck plate 2, and a flat plate portion 32 that is continuous with the joint portion 31. The flashing 3 is placed such that the joint portion 31 is placed on the upper surface of the end portion 21 of the deck plate 2, and the flat plate portion 32 is placed on the beam 81.
[0018] As shown in Fig. 3(b), the deck composite slab 1 is placed on one end of the beam 81a constituting the outer periphery in the width direction X. As shown in Fig. 4(b), the flashing 3 is placed on both ends of the beam 81b provided between the pair of beams 81a in the width direction X.
[0019] The concrete 4 is poured onto the deck plate 2, the flashing 3, the stress transfer members 5, and the upper side of the beams 81. The concrete 4 is formed into a rectangular shape in a plan view. As shown in Fig. 5, the concrete 4 has an end face 41 along a plane intersecting with the longitudinal direction Y. As shown in Fig. 3(b), the concrete 4 has a side face 42 along a plane intersecting with the width direction X.
[0020] 3 and 4, the stress transfer member 5 is placed on the upper surface of the flashing 3 and the upper surface of the beam 81, and is bridged between the flashing 3 and the beam 81. The stress transfer member 5 is fixed to the upper surface of the beam 81 by, for example, shielded metal arc welding, and embedded in the concrete 4. This allows the in-plane shear force acting on the deck composite slab 1 to be transferred to the beam 81 via the stress transfer member 5 embedded in the concrete 4.
[0021] The stress transmission member 5 may be further fixed to the upper surface of the flashing 3. In this case, the stress transmission member 5 can function as a displacement stopper for the flashing 3 when the concrete 4 is poured. The stress transmission member 5 and the upper surface of the flashing 3 are fixed to each other by, for example, shielded metal arc welding.
[0022] The length along the width direction X of the stress transfer member 5 fixed to the beam 81 is defined as W1. When the stress transfer member 5 is fixed to the beam 81 and the flashing 3 by shielded metal arc welding, if the length along the width direction X of the stress transfer member 5 provided on the flashing 3 is defined as W2, then the fixed length W along the width direction X at which the stress transfer member 5 is fixed to the beam 81 and the flashing 3 is given by fixed length W=W1+W2.
[0023] It is sufficient that the stress transmission member 5 is fixed at least to the beam 81. Therefore, the stress transmission member 5 may simply be placed on the upper surface of the flashing 3 without being fixed to the upper surface of the flashing 3. When the stress transmission member 5 is fixed only to the beam 81 by shielded metal arc welding, the fixed length W of the stress transmission member 5 is the weld length, and for example, the fixed length W=W1.
[0024] 5, the thickness of the stress transfer member 5 is t, and the thickness t is, for example, 1.6 mm to 12 mm. The height of the stress transfer member 5 in the vertical direction Z is h, and the height h of the stress transfer member 5 is, for example, 20 mm to 300 mm.
[0025] For example, an angle iron is used as the stress transfer member 5. The stress transfer member 5 has a first plate portion 51 and a second plate portion 52.
[0026] The first plate portion 51 is provided along a plane intersecting with the longitudinal direction Y and approximately perpendicular to the upper surface of the beam 81.
[0027] The second plate portion 52 is provided approximately parallel to the upper surface of the beam 81 along a plane intersecting with the up-down direction Z. The second plate portion 52 is provided at the lower end of the first plate portion 51 approximately perpendicular to the first plate portion 51. The second plate portion 52 spans between the flashing 3 and the beam 81. The second plate portion 52 is fixed to the upper surface of the beam 81 by, for example, shielded metal arc welding. The second plate portion 52 may be fixed to the upper surface of the flashing 3 by, for example, shielded metal arc welding. The second plate portion 52 may be fixed to the beam 81 and the flashing 3 by welding its entire outer periphery.
[0028] In addition, the second plate portion 52 may be welded to the beam 81, for example, at three sides of the periphery of the portion that directly contacts the beam 81.
[0029] 5, the distance in the longitudinal direction Y from the end face 41 of the concrete 4 to the stress transfer member 5 closest to the end face 41 is defined as the edge clearance e. The edge clearance e can be expressed as the distance from the end face 41 to the center line of the plate thickness of the first plate portion 51 in the longitudinal direction Y.
[0030] A plurality of stress transfer members 5 are provided at a predetermined interval B in the longitudinal direction Y. The interval B in the longitudinal direction Y can be expressed as the distance from the center line of the plate thickness of the first plate portion 51 of one adjacent stress transfer member 5 to the center line of the plate thickness of the first plate portion 51 of the other adjacent stress transfer member 5.
[0031] According to this embodiment, a stress transfer member 5 is provided that is bridged between the flashing 3 and the beam 81, and the stress transfer member 5 is fixed to the upper surface of the beam 81 and embedded in the concrete 4. As a result, when an in-plane shear force acts on the deck composite slab 1, it can be transferred from the concrete 4 to the beam 81 via the stress transfer member 5. This makes it unnecessary to use headed studs or a stud welding machine, facilitating construction.
[0032] According to this embodiment, the stress transfer member 5 may be further fixed to the flashing 3. This allows the stress transfer member 5 to function as a slip prevention device for the flashing 3 when pouring the concrete 4. This allows the quality of the deck composite slab 1 to be improved.
[0033] According to this embodiment, the stress transfer member 5 has a first plate portion 51 along a plane intersecting with the longitudinal direction Y. As a result, when an in-plane shear force acts on the deck composite slab 1, the first plate portion 51 can resist the force as a bearing surface. Therefore, it can resist even a larger in-plane shear force.
[0034] According to this embodiment, the stress transmission member 5 has a first plate portion 51 along a plane intersecting with the longitudinal direction Y and a second plate portion 52 along a plane intersecting with the vertical direction Z at the lower end of the first plate portion 51, and the second plate portion is fixed to the upper surface of the beam 81. As a result, even if the worker releases the stress transmission member 5 spanning the beam 81 and the flashing 3 when fixing the stress transmission member 5 to the beam 81, the stress transmission member 5 can be maintained in a stable state without falling over. This facilitates the work of fixing the stress transmission member 5 to the beam 81 by shielded metal arc welding or the like.
[0035] According to this embodiment, the stress transmission member 5 is fixed to the beam 81 by shielded metal arc welding. This allows the construction to be completed in a short time compared to stud welding.
[0036] According to this embodiment, as shown in Fig. 2, the flashings 3 are provided on both ends in the width direction X of the upper surface of the beam 81. This makes it possible to transmit the in-plane shear force of the deck composite slab 1 from the concrete 4 via the stress transmission member 5 to the beam 81 having the flashings 3 on both ends in the width direction X of the upper surface. This makes it possible to further increase the live load that the deck composite slab 1 can resist.
[0037] The flashing 3 can also be provided at one end of the upper surface of the beam 81 in the width direction X. In this case, the in-plane shear force of the composite deck slab 1 can be transmitted from the concrete 4 to the beam 81 constituting the outer periphery, for example, via the stress transmission member 5. This makes it possible to further increase the live load that the composite deck slab 1 can resist.
[0038] Second embodiment Next, a joint structure 100 according to a second embodiment will be described. Detailed description of the same configuration as the above-mentioned embodiment will be omitted below. As shown in FIG. 6, the joint structure 100 according to the second embodiment is different from the above-mentioned embodiment in that the second plate portion 52 is provided at the upper end of the first plate portion 51.
[0039] For example, an angle iron is used as the stress transfer member 5. The stress transfer member 5 has a first plate portion 51 and a second plate portion 52.
[0040] The first plate portion 51 is provided approximately perpendicular to the upper surface of the beam 81 along a plane intersecting with the longitudinal direction Y. The first plate portion 51 spans between the flashing 3 and the beam 81. The first plate portion 51 is fixed to the upper surface of the beam 81 by, for example, shielded metal arc welding. The first plate portion 51 may be fixed to the upper surface of the flashing 3 by, for example, shielded metal arc welding, as necessary.
[0041] The second plate portion 52 is provided approximately parallel to the upper surface of the beam 81 along a plane intersecting with the vertical direction Z. The second plate portion 52 is provided on the upper end of the first plate portion 51 at a distance from the beam 81.
[0042] The edge distance e in the longitudinal direction Y can be expressed as the distance from the end face 41 to the center line of the plate thickness of the first plate portion 51.
[0043] The interval B in the longitudinal direction Y can be expressed as the distance from the center line of the thickness of the first plate portion 51 of one adjacent stress transfer member 5 to the center line of the thickness of the first plate portion 51 of the other adjacent stress transfer member 5.
[0044] Third embodiment Next, a joint structure 100 according to a third embodiment will be described. As shown in Fig. 7, in the joint structure 100 according to the third embodiment, the stress transfer member 5 differs from the above-described embodiments in that it has a pair of first plate portions 51.
[0045] For example, an angle iron is used as the stress transfer member 5. The stress transfer member 5 has a pair of first plate portions 51 arranged substantially perpendicular to each other.
[0046] The pair of first plate portions 51 are provided at an inclination of approximately 45° with respect to the upper surface of the beam 81 along a plane intersecting with the longitudinal direction Y. The first plate portions 51 are bridged between the flashing 3 and the beam 81. The upper end of one first plate portion 51 is provided on the upper end of the other first plate portion 51. The lower end of the first plate portions 51 is fixed to at least the beam 81.
[0047] The edge distance e in the longitudinal direction Y can be expressed as the distance from the end face 41 to the connecting portion of the pair of first plate portions 51.
[0048] The interval B in the longitudinal direction Y can be expressed as the distance from the connecting portion of the first plate portions 51 of one adjacent stress transmission member 5 to the connecting portion of the first plate portions 51 of the other adjacent stress transmission member 5.
[0049] According to this embodiment, the stress transmission member 5 has a pair of first plate portions 51 along a plane intersecting with the longitudinal direction Y, and the lower ends of the pair of first plate portions 51 are fixed to the upper surface of the beam 81. As a result, even if the worker releases the stress transmission member 5 spanning the beam 81 and the flashing 3 when fixing the stress transmission member 5 to the beam 81, the stress transmission member 5 will not fall over and can be maintained in a stable state. This facilitates the work of fixing the stress transmission member 5 to the beam 81 by shielded metal arc welding or the like.
[0050] (Fourth embodiment) Next, a joint structure 100 according to a fourth embodiment will be described. As shown in Fig. 8, in the joint structure 100 according to the fourth embodiment, the stress transfer member 5 differs from the above-described embodiments in that a pair of first plate portions 51 are fixed to a beam 81.
[0051] For example, a channel steel is used as the stress transfer member 5. The stress transfer member 5 has a pair of first plate portions 51 spaced apart in the longitudinal direction Y, and a second plate portion 52 connecting the pair of first plate portions 51.
[0052] The first plate portion 51 is provided approximately perpendicular to the upper surface of the beam 81 along a plane intersecting with the longitudinal direction Y. The first plate portion 51 spans between the flashing 3 and the beam 81. The first plate portion 51 has the second plate portion 52 provided at its upper end, and at least the beam 81 is fixed to its lower end.
[0053] The second plate portion 52 is provided approximately parallel to the upper surface of the beam 81 along a plane intersecting with the vertical direction Z. The second plate portion 52 is spaced apart from the beam 81 in the vertical direction Z and connects the pair of first plate portions 51 together.
[0054] The edge distance e in the longitudinal direction Y can be expressed as the distance from the end face 41 to the center of the pair of first plate portions 51.
[0055] The interval B in the longitudinal direction Y can be expressed as the distance from the center of a pair of first plate portions 51 in one adjacent stress transmission member 5 to the center of a pair of first plate portions 51 in the other adjacent stress transmission member 5.
[0056] According to this embodiment, the stress transmission member 5 has a pair of first plate portions 51 along a plane intersecting with the longitudinal direction Y, and the lower ends of the pair of first plate portions 51 are fixed to the upper surface of the beam 81. As a result, even if the worker releases the stress transmission member 5 spanning the beam 81 and the flashing 3 when fixing the stress transmission member 5 to the beam 81, the stress transmission member 5 will not fall over and can be maintained in a stable state. This facilitates the work of fixing the stress transmission member 5 to the beam 81 by shielded metal arc welding or the like.
[0057] Fifth embodiment Next, a joint structure 100 according to a fifth embodiment will be described. As shown in Fig. 9, in the joint structure 100 according to the fifth embodiment, the stress transfer member 5 is different from the above-described embodiments in that it includes a first plate portion 51 connecting a pair of second plate portions 52.
[0058] For example, a channel steel is used as the stress transfer member 5. The stress transfer member 5 has a pair of second plate portions 52 spaced apart in the vertical direction Z, and a first plate portion 51 between the pair of second plate portions 52.
[0059] The first plate portion 51 is provided approximately perpendicular to the upper surface of the beam 81 along a plane intersecting with the longitudinal direction Y. The first plate portion 51 spans between the flashing 3 and the beam 81. The first plate portion 51 connects a pair of second plate portions 52 spaced apart in the vertical direction Z.
[0060] The second plate portion 52 is provided along a plane intersecting with the vertical direction Z. The second plate portion 52 spans between the flashing 3 and the beam 81. A pair of second plate portions 52 are provided spaced apart in the vertical direction Z. The lower second plate portion 52 is fixed to at least the beam 81.
[0061] The edge distance e in the longitudinal direction Y can be expressed as the distance from the end face 41 to the center line of the plate thickness of the first plate portion 51.
[0062] The interval B in the longitudinal direction Y can be expressed as the distance from the center line of the thickness of the first plate portion 51 of one adjacent stress transfer member 5 to the center line of the thickness of the first plate portion 51 of the other adjacent stress transfer member 5.
[0063] According to this embodiment, the stress transmission member 5 has a pair of first plate portions 51 along a plane intersecting with the longitudinal direction Y, and the lower ends of the pair of first plate portions 51 are fixed to the upper surface of the beam 81. As a result, even if the worker releases the stress transmission member 5 spanning the beam 81 and the flashing 3 when fixing the stress transmission member 5 to the beam 81, the stress transmission member 5 will not fall over and can be maintained in a stable state. This facilitates the work of fixing the stress transmission member 5 to the beam 81 by shielded metal arc welding or the like.
[0064] In the above-described embodiment, an angle iron and a channel iron are used as examples of the stress transmission member 5. In addition, the stress transmission member 5 may include at least one of a flat plate, a square steel pipe, a square steel bar, a steel pipe, a round steel bar, and a reinforcing bar.
[0065] Although several embodiments of the present invention have been described above, these embodiments are presented as examples and are not intended to limit the scope of the invention. Furthermore, the present invention can be implemented in various novel forms in addition to the above-mentioned embodiments. Therefore, the above-mentioned embodiments can be variously omitted, replaced, and modified without departing from the gist of the present invention. Such novel forms and modifications are included within the scope and gist of the present invention, and are included in the scope of the invention described in the claims and the equivalents of the invention described in the claims. EXAMPLES
[0066] Table 1 shows examples of welding equipment required for a deck composite slab using flashing when a conventional joining method is applied (conventional example) and when the present invention is applied (invention example) with a stress transfer member 5. Cases 1 to 3 show cases where a beam is joined using flashing at one end in the width direction. Cases 4 to 9 show cases where a beam is joined using flashing at both ends in the width direction.
[0067] [Table 1]
[0068] In Table 1, "Joint between deck composite slab and beam in normal portion" refers to the joint between deck composite slab and beam in the portion where flashing is not used.
[0069] In Case 1 and Case 7, the purpose is a parking lot, and the load is 5400 (N / m 2 In this case, the in-plane shear force acting on the deck composite slab is, for example, 1.346 (N / m 2 )~4.487(N / m 2 ) In normal sections, headed studs are used for the joints between the composite deck slab and the beams.
[0070] In Case 2 and Case 8, the purpose is a warehouse, and the load is 9800 to 20000 (N / m 2 In this case, the in-plane shear force acting on the deck composite slab is, for example, 2.36 (N / m 2 )~13.76(N / m 2 ) In normal sections, headed studs are used for the joints between the composite deck slab and the beams.
[0071] In Case 3 and Case 9, the building is used as a large office, and the load capacity is 4900 (N / m 2 In this case, the in-plane shear force acting on the deck composite slab is, for example, 1.136 (N / m 2 )~3.786(N / m 2) In normal sections, headed studs are used for the joints between the composite deck slab and the beams.
[0072] In Case 4, the purpose is residential and the load is 1800 (N / m 2 In this case, the in-plane shear force acting on the deck composite slab is, for example, 0.926 (N / m 2 )~3.087(N / m 2 ) The joints between the deck composite slab and the beams in the normal sections are made by using burn-out plug welding.
[0073] In Case 5, the purpose is a store, and the load is 2900 (N / m 2 In this case, the in-plane shear force acting on the deck composite slab is, for example, 1.136 (N / m 2 )~3.787(N / m 2 ) The joints between the deck composite slab and the beams in the normal sections are made by using burn-out plug welding.
[0074] In Case 6, the building is used as an office and the load is 2900 (N / m 2 In this case, the in-plane shear force acting on the deck composite slab is set to, for example, 0.986 (N / m 2 )~3.287(N / m 2 ) The joints between the deck composite slab and the beams in the normal sections are made by using burn-out plug welding.
[0075] <Case1~Case3について> In the conventional examples of Cases 1 to 3, the flashing was simply placed on one end of the beam in the width direction and not fixed. In addition, headed studs were stud-welded to the beam on which the flashing was provided. In the conventional examples, since the flashing was simply placed on the beam, arc spot welding is required when temporarily fixing the flashing. In the conventional examples, stress is transmitted between the beam on which the flashing is provided and the deck composite slab via headed studs. For this reason, in the conventional examples, the welding equipment prepared is a shielded metal arc welder and a stud welder.
[0076] In the present invention examples of Cases 1 to 3, flashing was placed on one end of the beam in the width direction. In addition, a stress transfer member that spans between the flashing and the beam was fixed to the beam and flashing by shielded metal arc welding. In the present invention examples, the flashing is fixed to the stress transfer member, so temporary fastening by arc spot welding is not required. In the present invention examples, stress is transferred between the beam on which the flashing is provided and the deck composite slab via the stress transfer member 5. Therefore, in the present invention examples, at the location where the beam on which the flashing is provided and the deck plate are joined, a shielded metal arc welder is used as the welding equipment to be prepared, and a stud welder is not required.
[0077] In the examples of the present invention in Cases 1 to 3, where the live load is relatively large, headed studs are used in the joints between the deck composite slab and the beams in the normal sections. As described above, where the beams where flashing is provided are joined to the deck plate, stress transfer members are used, so headed studs are not required. In this way, in the examples of the present invention in Cases 1 to 3, where the live load is relatively large, it is possible to reduce the number of headed studs when joining the deck composite slab and the beams. This makes construction even easier.
[0078] <Case4~Case6について> In the conventional examples of Cases 4 to 6, the flashing was simply placed on both ends of the beam in the width direction and not fixed. In addition, headed studs were stud welded to the beam on which the flashing was provided. In the conventional examples, since the flashing was simply placed on the beam, arc spot welding is required to temporarily fasten the flashing. In the conventional examples, stress is transmitted between the beam on which the flashing is provided and the deck composite slab via headed studs. For this reason, the welding equipment prepared in the conventional examples is a shielded metal arc welder and a stud welder.
[0079] In the present invention examples of Cases 4 to 6, flashings were placed on both ends of the beam in the width direction. In addition, stress transfer members that span the flashings and the beams were fixed to the beams and flashings by shielded metal arc welding. In the present invention examples, the flashings are fixed to the stress transfer members, so temporary fastening by arc spot welding is not required. In the present invention examples, stress is transferred between the beams on which the flashings are provided and the deck composite slab via the stress transfer members 5. Therefore, in the present invention examples, the welding equipment to be prepared is a shielded metal arc welder, and a stud welder is not required.
[0080] In particular, in the present invention examples of Cases 4 to 6, since the live load is relatively small, headed studs are not used in the joints between the deck composite slab and the beams in the normal sections, but rather burnt plug welding is used. In other words, in the present invention examples of Cases 4 to 6, headed studs are not required at all when joining the deck composite slab and the beams. In this way, in the present invention examples of Cases 4 to 6, where the live load is relatively small, construction can be carried out significantly easier.
[0081] <Case7~Case9について> In the conventional examples of Cases 7 to 9, the flashing was simply placed on both ends of the beam in the width direction and not fixed. In addition, headed studs were stud welded to the beam on which the flashing was provided. In the conventional examples, since the flashing was simply placed on the beam, arc spot welding is required when temporarily fixing the flashing. In the conventional examples, stress is transmitted between the beam on which the flashing is provided and the deck composite slab via headed studs. For this reason, the welding equipment prepared in the conventional examples is a shielded metal arc welder and a stud welder.
[0082] In the present invention examples of Cases 7 to 9, flashings are placed on both ends of the beam in the width direction, and stress transfer members that span the flashings and the beams are fixed to the beams and flashings by shielded metal arc welding. In the present invention examples, the flashings are fixed to the stress transfer members, so temporary fastening by arc spot welding is not required. In the present invention examples, stress is transferred between the beams on which the flashings are provided and the deck composite slab via the stress transfer members 5. For this reason, in the present invention examples, at the locations where the beams on which the flashings are provided and the deck plate are joined, a shielded metal arc welder is used as the welding equipment to be prepared, and a stud welder is not required.
[0083] In the examples of the present invention in Cases 7 to 9, where the live load is relatively large, headed studs are used in the joints between the deck composite slab and the beams in the normal sections. As described above, where the beams where flashing is provided are joined to the deck plate, stress transfer members are used, so headed studs are not required. In this way, in the examples of the present invention in Cases 7 to 9, where the live load is relatively large, it is possible to reduce the number of headed studs when joining the deck composite slab and the beams. This makes construction even easier.
[0084] As described above, according to the present invention, since headed studs or stud welding machines are not required for the beams on which the flashing is provided, a joint structure between a deck composite slab and a beam can be provided that can be easily constructed. [Explanation of symbols]
[0085] 100: Joint structure between deck composite slab and beam 1: Deck composite slab 2: Deck plate 21: End 3: Flashing 31: Engagement part 32: Flat plate part 4: Concrete 41: End face 42: Side 5: Stress transmission member 51: 1st plate part 52:Second plate part 8: Beam 81: Beam 82: Beam X: Width direction Y: Length direction Z: Vertical direction
Claims
1. A joint structure between a deck composite slab in which the deck plate and concrete are integrated and a beam, The beam is provided along the longitudinal direction of the deck plate, The deck composite slab is The deck plate has a width direction end portion intersecting with a length direction of the deck plate, the width direction end portion being spaced from the beam; A flashing provided in a gap between the end portion in the width direction of the deck plate and the beam; The concrete provided on the upper side of the deck plate and the flashing; A stress transmission member is provided between the flashing and the beam, The stress transfer member is fixed to the upper surface of the beam and embedded in the concrete. A joint structure between a composite deck slab and a beam.
2. The stress transmission member is further fixed to the flashing.
2. The joint structure between a composite deck slab and a beam according to claim 1.
3. The stress transfer member includes at least one of a flat plate, an angle iron, a channel iron, a square steel pipe, a square steel, a steel pipe, a round steel, and a reinforcing bar.
2. The joint structure between a composite deck slab and a beam according to claim 1.
4. The stress transfer member has a first plate portion along a plane intersecting the longitudinal direction.
2. The joint structure between a composite deck slab and a beam according to claim 1.
5. The stress transfer member is fixed to the beam by shielded metal arc welding.
2. The joint structure between a composite deck slab and a beam according to claim 1.
6. The flashing is provided at both ends in the width direction of the upper surface of the beam.
2. The joint structure between a composite deck slab and a beam according to claim 1.
7. The flashing is provided at one end in the width direction of the upper surface of the beam.
2. The joint structure between a composite deck slab and a beam according to claim 1.
Citation Information
Patent Citations
Method for welding steel plate
JP1995323373A
Deck plate support member, deck plate support structure, and deck plate support method
JP2021105311A
Flashing
JP2021143471A
Junction structure of beam and slab
JP2022069920A
Composite construction
JP2022154280A