Estimation system
The estimation system addresses inaccuracies in initial project estimates by integrating project and human resource data, improving accuracy and reducing re-estimations through precise man-hour calculations and resource allocation.
Patent Information
- Application Number
- JP2023058284
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-31
- Publication Date
- 2024-10-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing estimation systems fail to accurately account for changing project risks, industry trends, and individual human resource factors such as motivation and productivity, leading to inaccurate initial estimates and frequent re-estimations during project execution.
An estimation system that incorporates project information, human resource skills, career plans, and productivity data to enhance estimation accuracy by considering project classification, human resource profiles, and career plans, using a database structure to support precise man-hour calculations and resource allocation.
Improves estimation accuracy by considering project risks, industry trends, and individual human resource factors, reducing the need for re-estimations and enhancing productivity through targeted resource allocation.
Smart Images

Figure 2024145787000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to an estimation system. [Background technology]
[0002] When estimating system development, it is necessary to calculate man-hours based on project information, human resource skills, and planned human resource deployment, etc. A system for making such estimates is the work man-hours estimation and human resource allocation system described in Patent Document 1.
[0003] This patent document 1 discloses a system that has the function of estimating the man-hours of new work by searching for similar work that has been performed in the past, and the function of calculating available man-hours and skill information of workers, and that searches for and assigns workers who have the available man-hours and skills required for the work within the working period of the new work. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2006-318331 A Summary of the Invention [Problem to be solved by the invention]
[0005] The system in Patent Document 1 creates estimates by allocating personnel based on the man-hours required for similar tasks in the past, the length of experience each personnel has in similar tasks, and the personnel's availability information (length of time engaged in each task).
[0006] If a project is carried out based on the above estimate results, there is a concern that the actual man-hours will increase, for example, because the risks and project difficulty that change due to the latest situation and industry trends are not taken into consideration. Furthermore, due to differences in the industries in which the personnel have worked and low productivity, the efficiency of veteran personnel who should have a lot of work experience may not increase, and there is also a possibility that personnel will not be able to work on the project at 100% due to family circumstances and a decrease in motivation. As a result, it is not uncommon for re-estimations to be made during the progress of the project.
[0007] The present invention has been made in consideration of the above problems, and has an object to improve estimation accuracy. [Means for solving the problem]
[0008] The invention for solving the above problem is an estimation system that assists in creating estimates for projects, and includes an input unit for inputting project information including the project classification and field, human resource skills including productivity, a human resource profile, and a human resource career plan, a memory unit for recording the project information, the human resource skills, the human resource profile, and the human resource career plan, a project size calculation unit for calculating the size of an estimate for the project to be estimated based on the information input from the input unit, a suitable talent search unit for searching for suitable talent having the skills required for the project to be estimated based on the information input from the input unit, and a talent allocation unit for assigning talent to the project to be estimated from among the suitable talents searched for. Effect of the Invention
[0009] According to the present invention, it is possible to improve the estimation accuracy. [Brief description of the drawings]
[0010] [Figure 1] FIG. 13 is a diagram showing an example of an outline of a quotation process. [Diagram 2] FIG. 1 is a diagram showing an example of the configuration of an estimate system. [Diagram 3] FIG. 2 is a diagram showing an example of the configuration of a case profile database. [Figure 4] FIG. 13 is a diagram showing an example of the configuration of a case classification master database. [Diagram 5] FIG. 13 is a diagram showing an example of the configuration of a skill category master database. [Figure 6] FIG. 2 is a diagram showing an example of the configuration of a human resources career master database. [Figure 7] FIG. 2 is a diagram showing an example of the configuration of a human resources information master database. [Figure 8] FIG. 2 is a diagram showing an example of the configuration of a project performance database. [Figure 9] FIG. 13 is a diagram showing an example of the configuration of a human resources basic skill performance database. [Figure 10] FIG. 13 is a diagram showing an example of the configuration of a human resources case skill performance database. [Figure 11] FIG. 13 is a diagram showing an example of the configuration of a human resources employment schedule database. [Figure 12] 11 is a flowchart showing an example of an estimate process (project size calculation). [Figure 13] 13 is a flowchart showing an example of an estimate process (suitable talent search). [Figure 14] 11 is a flowchart showing an example of an estimation process (human resource allocation). DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] Hereinafter, an embodiment of the quotation system according to the present invention will be described with reference to the drawings. Note that the embodiment described below does not limit the invention according to the claims, and all of the elements and combinations described in the embodiment are not necessarily essential to the solution of the invention. EXAMPLES
[0012] FIG. 1 is a diagram showing an example of an outline of an estimate process implemented in an estimate system described later.
[0013] For example, an estimate creator 1 performs a case estimate process 101 via the server 2. In order to make an estimate, it is necessary to register management information for making an estimate and past results of similar cases via the server 2. For this reason, for example, the management department 3 performs case category master registration 102, which is management information for making an estimate, and skill category master registration 103, via the server 2. Case-working personnel 4 performs human resource career master registration 104 and human resource information master registration 105, which are management information for human resource linking at the time of estimate, via the server 2. Each case leader 5 performs case result registration 106, human resource basic skill result registration 107, and human resource case skill result registration 108, which are result information for searching for similar cases at the time of estimate, via the server 2.
[0014] In this way, before creating an estimate, the management department 3 pre-registers master information for estimates, the project personnel 4 pre-registers management information for personnel linking, and the project leader 5 pre-registers project information for searching for similar projects. This allows the estimate creator 1 to obtain the estimate results.
[0015] FIG. 2 is a diagram illustrating an example of the configuration of the estimation system.
[0016] The estimation system 100 includes a server 2 and a terminal 13. The server 2 is a computer having a calculation device 6, a memory 7, a storage device 8 as an example of a "storage unit", and a communication interface (communication I / F) 11. The calculation device 6 is a device that loads a program stored in the storage device 8 into the memory 7, executes it, and performs estimation processing. The storage device 8 is configured by a large-capacity non-volatile recording device such as a magnetic storage device (HDD) or a semiconductor storage device (SSD) made of flash memory, etc., and stores the program executed by the calculation device 6 and various information.
[0017] The storage device 8 has an input / output processing unit 9 and a data processing unit 10 which is an example of a "case size calculation unit", "suitable human resource search unit" and "human resource allocation unit". The input / output processing unit 9 is a program for registering data, displaying the registered contents of each database and displaying the estimate results using a GUI (Graphical User Interface). The data processing unit 10 is a program for creating estimates. Furthermore, the case profile DB 21 to the human resource engagement schedule DB 29 are databases in which data is actually stored. The communication I / F 11 is a communication interface device which controls communication with the terminal 13 via the communication network 12 (network) in accordance with a predetermined protocol and transmits and receives data to and from the terminal 13.
[0018] The terminal 13 is a calculator (personal computer) having a communication interface (communication I / F) 14, a calculation device 15, a storage device 16, a memory 17, and an input / output device 18 as an example of an "input section" and an "output section." A web browser and a dedicated application that display a GUI run on the terminal 13.
[0019] The arithmetic unit 15 is a device that loads a program stored in the storage device 16 into the memory 17, executes it, and processes various types of information. The input / output unit 18 is, for example, a display device. The input / output unit 18 is a device that receives operation inputs from members as a touch panel, and outputs the results of the execution of the program in a visible format.
[0020] For example, when the estimate creator 1 performs the project estimate process 101, the estimate creator 1 issues an instruction to create an estimate using the input / output device 18 of the terminal 13. The instruction input from the input / output device 18 is sent to the input / output processing unit 9 of the server 2, and the estimate is created by the data processing unit 10. Thereafter, the input / output processing unit 9 transmits the created estimate results in a format that can be displayed on the input / output device 18 of the terminal 13.
[0021] The following describes each database used in the quotation system.
[0022] FIG. 3 is a diagram showing an example of the configuration of the case profile database.
[0023] The case profile database 21 is registered by the estimate creator 1 through the GUI of the input / output processor 9 when performing the case estimate process 101. This database 21 holds information for expressing the characteristics of a case.
[0024] The case profile database 21 includes a parent case number 201, a child case number 202, a case classification type 203, and a case classification 204. The parent case number 201 is a key for managing a case. The child case number 202 is a key for dividing the same case into multiple child cases. Cases in which a case is divided will be described later.
[0025] The case classification type 203 and the case classification 204 are items for indicating the characteristics of the case. For example, a case with a parent case number 201 of 00001 and a child case number 202 of 00001 is a case with the following characteristics: industry is automobiles, field is web system development, customer is Company A, main product used is AWS, scale is coding amount over 10K steps, and development content is new.
[0026] FIG. 4 is a diagram illustrating an example of the configuration of the case classification master database.
[0027] The case classification master database 22 is registered using the GUI of the input / output processing unit 9 . This database 22 holds management information for registering the characteristics (case classification) of the case to be estimated in the case profile database 21 when performing the case estimate process 101. This database 22 needs to be registered before performing the case estimate process 101.
[0028] The case category master database 22 includes a case category type 211, a case category 212, multiple selections within the same category 213, a case category difficulty 214, and difficulty grounds 215. The case category type 211 and the case category 212 express the characteristics of a case. For example, in the case of an automobile industry case, information that the case category type 211 is the industry type and the case category 212 is automobiles is registered in the case profile database 21.
[0029] The multiple selections within the same type 213 manages whether multiple case classifications 212 with the same case classification type 211 can be linked to one parent case number 201 of the case to be estimated. For example, if the case classification type 211 is industry, multiple industries such as automobiles and logistics cannot be linked to one parent case number 201 when the case classification type 211 is industry. If it is desired to manage multiple industries such as automobiles and logistics in one case, multiple child case numbers 202 are created when registering the case profile database 21, and when the child case number 202 is 00001, it is registered as the automobile industry, and when the child case number 202 is 00002, it is registered as the logistics industry.
[0030] By dividing the case in this manner, it is possible to prevent the characteristics of each case registered in the case profile database 21 from becoming too complicated and the characteristics of each registrant from varying, thereby improving the accuracy of the estimate.
[0031] The case classification difficulty 214 is an item for setting a unique difficulty for each case classification 212. The present estimation system 100 searches for cases similar to past cases based on the case classification 212, and can calculate man-hours based on past results. For each case classification 212, if the past results can be used as is, a difficulty level of 1 is registered, and if a unique difficulty level setting is to be added to the past results, a difficulty level from 0.0 to 2.0 (one decimal place) is registered. For example, if a new standard to be complied with is issued in the automobile industry and it is difficult to proceed with the work according to the man-hours of the past results, the case classification difficulty 214 is set to 1.2. Then, the estimation result is calculated with 1.2 times the man-hours of the past results. The difficulty level basis 215 registers the basis for setting the case classification difficulty 214. The present master database 22 may be added at any time according to the purpose and situation.
[0032] Previously, each estimator had this kind of risk analysis (analysis equivalent to the contents described in Difficulty Basis 215) and difficulty setting in their head, which was the cause of differences in the estimate results between veteran employees and junior employees. By setting the case classification difficulty 214, it is possible to improve the accuracy of estimates by considering the difficulty based on the latest industry trends.
[0033] FIG. 5 is a diagram illustrating an example of the configuration of the skill category master database.
[0034] The skill category master database 23 is registered using the GUI of the input / output processing unit 9. This database 23 holds skill categories that serve as the smallest unit key for registering the job performance database 26, the human resources basic skill performance database 27, and the human resources job skill performance database 28. This database 23 needs to be registered before the job estimate process 101 is performed.
[0035] The skill category master database 23 includes a skill category 221, a performance reflection flag 222, a productivity standard 223, and a review indication standard 224. The skill category 221 is an item for setting a classification when judging human resource skills. The skill category 221 sets a viewpoint for judging human resource skills, regardless of development skills and competencies. For example, when the skill category 221 called WEB system_requirements definition is registered, the case performance database 26 stores the performance required for the WEB system_requirements definition of each case.
[0036] One example of a perspective for dividing skill category 221 is the type of business in the IT industry. In recent years, with the increase in IoT projects, the number of companies promoting both web systems and embedded systems is on the rise. In such companies, if someone with experience in defining requirements for web systems is assigned to define requirements for embedded systems, there is a concern that the expected productivity will not be achieved due to differences in the perspectives of requirements definition. Therefore, the requirements definition process for web systems and embedded systems is registered separately. By registering in this way, it is possible to search for the skills of personnel at a finer level, regardless of the type of business in each industry (example of the IT industry: web systems, embedded systems, business systems, etc.).
[0037] The result reflection flag 222 is an item for determining in which database 26-28 the skill category 221 is to be registered among the case result database 26, the human resources basic skill result database 27, and the human resources case skill result database 28. For example, competency skills such as leadership and membership are difficult to measure with productivity. Furthermore, competency skills are not skills associated with cases, but skills associated with the human resources themselves. For such skill category 221, the result reflection flag 222 is set to OFF. When the result reflection flag 222 is OFF, the skill is registered only in the human resources basic skill result database 27. When the result reflection flag 222 is ON, the skill is registered in the case result database 26 and the human resources case skill result database 28. The case result database 26, the human resources basic skill result database 27, and the human resources case skill result database 28 will be described later.
[0038] Productivity standard 223 is an item for setting the measurement unit when measuring the productivity of skill category 221. Review comment standard 224 is an item for setting the review comment standard for the productivity standard 223 unit. For example, if the skill category 221 in FIG. 5 is WEB system_requirements definition, productivity is measured by page, and the review comment standard per page is two items. These items are used when judging the productivity of each human resource. Details of these items will be described later. Note that this master may be added at any time depending on the purpose and situation.
[0039] FIG. 6 is a diagram showing an example of the configuration of the human resources career master database.
[0040] The human resources career master database 24 is registered using the GUI of the input / output processing unit 9. This database 24 is used to register the case categories that a person wishes to work on in the future and the case categories that he or she does not wish to work on, based on his or her own career plan, so that when allocating human resources in an estimate, the database 24 allocates cases that are closest to the person's desire and does not allocate cases that are not desired. This database 24 must be registered before the case estimate process 101 is performed.
[0041] The human resource career master database 24 includes a human resource number 231, a case category type 232, a case category 233, and an engagement preference flag 234. The human resource number 231 is a key for uniquely representing each human resource. The case engagement human resource 4 registers the case category type 232 and the case category 233 that the human resource wishes to engage in or does not wish to engage in. The engagement preference flag 234 is set to YES if the human resource wishes to engage in the work, and NO if the human resource does not wish to engage in the work.
[0042] By making estimates that take into account not only the projects that employees wish to work on, but also the projects that employees do not wish to work on, it is possible to reduce the decline in productivity due to a decrease in employee motivation and the occurrence of employees being unable to work on projects, and to increase the accuracy of estimates.
[0043] FIG. 7 is a diagram illustrating an example of the configuration of the human resources information master database.
[0044] The human resources information master database 25 is registered using the GUI of the input / output processing unit 9. This database 25 is used to register the expected ratio at which project-working personnel 4 can work on projects and their own unit prices, and is used to make decisions on allocating personnel in estimates to allocate personnel who can provide the lowest unit price and the highest productivity, taking into account the unit prices, and to avoid allocating personnel who exceed the project-working ratio. The basis for such allocation will be described later in the explanation of the estimate process (search for suitable personnel) 316 in FIG. 13. This database 25 needs to be registered before performing the project estimate process 101.
[0045] The human resource information master database 25 includes a human resource number 241, a start 242, an end 243, a unit price 244, a case engagement rate 245, and a reason 246. The human resource number 241 is a key for uniquely representing each human resource. The start 242, the end 243, the unit price 244, the case engagement rate 245, and the reason 246 that is the basis for the case engagement rate are registered for each case-engaged human resource 4. The case engagement rate 245 is registered with a standard daily operation rate of 1.0, and if, for example, family care is required during a certain period or there is training, the case engagement rate is lowered and registered.
[0046] In this way, by making estimates based on the engagement ratio taking into account work outside of projects, it is possible to reduce declines in productivity due to family circumstances and situations where employees are unable to work on projects, and to improve the accuracy of estimates.
[0047] FIG. 8 is a diagram illustrating an example of the configuration of the case performance database.
[0048] The case performance database 26 is registered using the GUI of the input / output processing unit 9. This database 26 registers the performance scale of each case, and is used when calculating the case scale of similar cases in an estimate. This database 26 must be registered before the case estimate process 101 is performed.
[0049] The case result database 26 includes a parent case number 251, a child case number 252, a skill category 253, and a result scale 254. The case leader 5 registers the parent case number 251, the child case number 252, and the result scale 254 for each skill category 253. Note that only skill categories whose result reflection flag 222 in the skill category master database 23 is ON are registered in the skill category 253. Furthermore, the scale registered in the result scale 254 is the result scale (pages and number of steps) in accordance with the productivity standard 223 in the skill category master database 23.
[0050] FIG. 9 is a diagram illustrating an example of the configuration of the human resource basic skill performance database.
[0051] The personnel basic skill performance database 27 is used for registration via the GUI of the input / output processing unit 9. The basic skills of each personnel are registered in the database 27. These basic skills are not taken into consideration as productivity when allocating personnel in an estimate. The estimate creator 1 refers to the personnel basic skill performance database 27 and makes a final decision as to whether the personnel allocated in the estimate are suitable for the job. This database 27 must be registered before the job estimate process 101 is performed.
[0052] The human resource basic skill performance database 27 includes a human resource number 261, a skill category 262, and a level 263. The case leader 5 registers the human resource number 261 and the level 263 for each skill category 262. Note that only skill categories for which the performance reflection flag 222 in the skill category master database 23 is OFF are registered in the skill category 262.
[0053] In this way, by judging personnel based on basic skills such as competencies, for example, it is possible to reduce the occurrence of personnel assigned to a project that requires a lot of presentations being highly productive but having low expressiveness and therefore unable to produce results. This makes it possible to improve the accuracy of estimates.
[0054] FIG. 10 is a diagram illustrating an example of the configuration of the human resources case skill performance database.
[0055] The personnel case skill performance database 28 is registered using the GUI of the input / output processing unit 9. The database 28 registers the work performance of each case and each personnel, and is used to calculate the productivity when allocating personnel through estimates. This database 26 must be registered before the case estimate process 101 is performed.
[0056] The human resource case skill performance database 28 includes a parent case number 271, a child case number 272, a human resource number 273, a skill category 274, actual man-hours 275, actual scale 276, and a number of review comments 277. The case leader 5 registers the actual man-hours 275, actual scale 276, and number of review comments 277 for each of the parent case number 271, the child case number 272, the human resource number 273, and the skill category 274. When allocating human resources in an estimate, the productivity and work quality of the human resources are calculated from the contents registered above, and allocation is performed.
[0057] In this way, by judging personnel skills not by the length of time they have worked on a project, but by productivity and work quality, it is possible to reduce the occurrence of veteran workers who should have a lot of work experience not being productive. Furthermore, by incorporating the number of reviews, it is possible to reduce the occurrence of workers who have high productivity but low quality and are unable to achieve results, which results in improved accuracy of estimates.
[0058] FIG. 11 is a diagram showing an example of the configuration of the human resource work schedule database.
[0059] The personnel work schedule database 29 is registered from the contents of the job profile database 21 and the personnel information master database 25 when making an estimate. The personnel work schedule database 29 is used by the estimate system 100 to register the job work schedule for each assigned personnel and to determine whether or not to assign personnel when allocating personnel in an estimate. This database 29 must be registered before the job estimate process 101 is performed.
[0060] The human resource engagement schedule database 29 includes a parent case number 281 , a child case number 282 , a human resource number 283 , a start 284 , an end 285 , and an engagement rate 286 .
[0061] FIG. 12 is a flowchart showing an example of an estimate process (project size calculation).
[0062] The quotation process (calculation of the project size) when the estimate creator 1 performs the project quotation process 101 via the server 2 will be described.
[0063] First, the data processing unit 10 searches the case profile database 21 for similar cases that match one or more of the case classification types 203 and case classifications 204 based on the case classification type 203 and case classification 204 of the case to be estimated in the case profile database 21, and creates a similar case list 401 (S301). This similar case list 401 includes similar parent case numbers, similar child case numbers, similar case classification types, similar case classifications, and the number of case classification matches.
[0064] Next, the data processing unit 10 selects the similar case with the greatest number of case classification matches and the largest parent case number from the similar case list 401 as the quotation result. The data processing unit 10 searches the case performance database 26 for the skill classification 253 and performance scale 254 of similar cases, and creates quotation result 402 (S302). This quotation result 402 includes case classification 402(1) and case scale 402(2). Case classification 402(1) includes the estimated case classification type and estimated case classification, and case scale 402(2) includes the estimated parent case number, estimated child case number, estimate skill classification, and estimated scale.
[0065] Next, the data processing unit 10 searches the case classification difficulty 214 from the case classification master database 22 based on the estimate case classification type and estimate case classification of the case classification 402(1). The data processing unit 10 multiplies the estimated scale of the case scale 402(2) by the case classification difficulty 214 to determine the estimated scale. Thereafter, the data processing unit 10 outputs the current estimation result 402 through the GUI of the input / output processing unit 9 (S303). The case scale 402(2) of this current estimation result 402 includes the estimated parent case number, the estimated child case number, the estimation skill category, the updated estimated scale, and the unallocated scale (the same value as the new estimated scale).
[0066] The estimate creator 1 sets the work start date and end date for each estimation skill class based on the estimate result 402 output on the GUI (S304). As a result, the case size 402(2) of the estimate result 402 includes the estimate parent case number, estimate child case number, estimate skill class, estimate size, unallocated size, start date, and end date.
[0067] Thereafter, the data processing section 10 sorts the case size 402(2) in ascending order of start date (first sorting ascending order) and in ascending order of end date (second sorting ascending order) (S305).
[0068] FIG. 13 is a flowchart showing an example of the quotation process (suitable talent search).
[0069] The following describes the quotation process (search for suitable personnel), which is the subsequent process to the quotation process (calculation of project size).
[0070] After that, the data processing unit 10 performs a loop for S311 to S312 the number of lines of the case scale 402(2).
[0071] First, the data processing unit 10 searches the personnel case skill performance database 28 for the performance of the case in which each personnel was most recently engaged (the case with the largest parent case No. 271) based on the estimated skill category of the case scale 402(2), and creates the personnel skill performance 403 (S311). This personnel skill performance 403 includes the personnel No., skill category, performance man-hours, performance scale, and the number of review comments.
[0072] Next, the data processing unit 10 calculates the productivity / man-day for the human resource skill performance 403 based on the formula 404. Furthermore, the data processing unit 10 searches the human resource information master database 25 for the unit price based on the human resource number (S312). As a result, the human resource skill performance 403 includes the human resource number, skill category, actual man-hours, actual size, number of review comments, productivity / man-day, and unit price.
[0073] The productivity / person-day is the productivity / person-day in units of the productivity standard 223 defined in the skill classification master database 23. For example, in the case of WEB system_requirements definition, it is the productivity per page. The contents of the calculation formula 404 are described below. Productivity / man-day = Productivity (a) x Work quality coefficient (b) Productivity (a) = Scale of performance of human resource skill performance 403 ÷ Actual man-hours of performance of human resource skill performance 403 Work quality coefficient (b) = 1 - ((number of review comments per performance scale (c) - review comment criteria 224 of skill classification master database 23) x coefficient (d)) However, the maximum value of the work quality coefficient (b) shall be 1. If the calculation result is 1 or greater, the work quality coefficient (b) shall be 1. Number of review comments per achievement size (c) = Number of review comments for HR Skills Achievement 403 ÷ Achievement size for HR Skills Achievement 403 Coefficient (d) = 0.1
[0074] After that, the data processing unit 10 performs a loop of S313 to S315 for the number of rows of the human resource skill record 403.
[0075] First, the data processing unit 10 searches the case classification type 232, the case classification 233, and the engagement desire flag 234 from the human resource career master database 24 based on the human resource No. of the human resource skill record 403, and creates a human resource career 405 (S313). This human resource career 405 includes the case classification type, the case classification, and the engagement desire flag.
[0076] Next, the data processing unit 10 searches for the estimated case classification type and the estimated case classification from the case classification 402(1) based on the case classification type and the case classification of the human resources career 405. If there is one or more classifications with the engagement desire flag set to NO, the data processing unit 10 deletes the information of the corresponding human resources number from the human resources skill performance 403 (S314).
[0077] Next, the data processing unit 10 searches for the estimated case category type and the estimated case category from the case category 402(1) based on the case category type and the case category of the human resources career 405. If there is one or more categories in the human resources career 405 where the engagement preference flag is YES, the data processing unit 10 sets the engagement preference in the human resources skill performance 403 to YES (S315). As a result, the human resources skill performance 403 includes the human resources number, skill category, actual man-hours, actual scale, number of review comments, productivity / man-day, unit price, and engagement preference.
[0078] Next, the data processing unit 10 sorts the human resource skill performance 403 in ascending order of skill category (third sort ascending order), descending order of engagement preference (fourth sort ascending order), and ascending order of unit price÷productivity / man-day (fifth sort ascending order) (S316). By performing this sorting, it becomes possible to assign those who wish to engage in the work and the desired scale of work to human resources who can produce the lowest unit price and the highest productivity.
[0079] FIG. 14 is a flowchart showing an example of the estimation process (human resource allocation).
[0080] This section explains quotation process (talent allocation), which is the subsequent process of quotation process (suitable talent search).
[0081] Thereafter, the data processing unit 10 executes LOOP1 for S321 to S326 the number of lines of the case scale 402(2).
[0082] First, the data processing unit 10 searches the talent number and productivity / man-day from the talent skill performance 403 based on the estimated skill category of the job size 402(2) and creates a talent allocation candidate 406 (S321). This talent allocation candidate 406 includes the talent number and productivity / man-day.
[0083] Thereafter, the data processing unit 10 performs LOOP 2 the number of times corresponding to the number of rows of the talent allocation candidates 406 in S322 to S326.
[0084] First, the data processing unit 10 obtains the start 284, end 285, and engagement rate 286 in the human resource engagement schedule database 29, and the engagement rate 245 for which the start 242, end 243, and reason 246 are "project" in the human resource information master database 25, based on the human resource number and start and end dates of the project scale 402(2) of the human resource allocation candidate 406. The data processing unit 10 searches for the allocable engagement rate within the period using "project engagement rate 245 - engagement rate 286", and calculates the allocable scale from the allocable engagement rate (S322). As a result, the human resource allocation candidate 406 includes the human resource number, productivity / man-days, allocable engagement rate, and allocable scale. If the calculated allocable engagement rate is 0, the process proceeds to S326. If the allocable engagement rate is greater than 0, the process proceeds to S324 (S323).
[0085] Next, the data processing unit 10 registers the engagement rate to be allocated in the talent engagement schedule database 29 based on the talent number of the talent allocation candidate 406 (S324).
[0086] Next, the data processing unit 10 sets the skill category, start date, end date, allocation scale, and allocation engagement rate of the assigned human resources in the assigned human resources 402(3) of the estimate result 402, and subtracts the allocation scale from the unassigned scale of the case scale 402(2) (S325). This case scale 402 includes a case category 402(1), a case scale 402(2), and assigned human resources 402(3). The case scale 402(2) includes an estimated parent case number, an estimated child case number, an estimated skill category, an estimated scale, an updated unassigned scale, a start date, and an end date. The assigned human resources 402(3) include a skill category, a start date, an end date, an allocation scale, and an assignment engagement rate.
[0087] Finally, if the unallocated size is 0, the process exits from LOOP2 (S326). Through the above process, the estimate is finalized. EXAMPLES
[0088] In the second embodiment, the case leader 5 manually inputs data into the human resource case skill performance database 28 through the GUI of the input / output processing unit 9, but the data is automatically registered from the deliverables of the case. Changes from the first embodiment will be described below with reference to FIG. 1.
[0089] For example, in the first embodiment, when the case leader 5 performs the human resource case skill performance registration 108, he or she manually inputs all the registration contents through the GUI of the input / output processing unit 9.
[0090] In the second embodiment, each project employee 4 uploads the deliverables he or she created as files to the GUI through the GUI of the input / output processing unit 9. The uploaded files are read in text format by the data processing unit 10, and the scale of achievement is determined from the number of characters and the number of lines, and the achievement scale 276 of the human resource project skill achievement database 28 is registered.
[0091] Furthermore, by adding a keyword to the file to be uploaded, it becomes possible to automatically import the number of review comments 277. For example, a phrase such as "KEY: number of review comments" is entered in the portion of the file that corresponds to the number of review comments, and the file is uploaded. When the data processing unit 10 reads the file in text format, it searches for "KEY: number of review comments" and registers the number entered thereafter as the number of review comments 277.
[0092] In this way, in this embodiment, each project worker 4 can register his / her deliverables as files, which can be automatically registered in the human resource project skill performance database 28. This prevents the project leader 5 from forgetting to register data in the human resource project skill performance database 28 or from registering data incorrectly, thereby improving the accuracy of estimates. Furthermore, the workload of the project leader 5 is reduced, which can further improve the efficiency of work. [Explanation of symbols]
[0093] 8... storage device, 10... data processing unit, 18... input / output device, 100... estimation system
Claims
1. An estimate system for supporting the creation of estimates for projects, an input section for inputting case information including the case classification and field, human resource skills including productivity, a human resource profile, and a human resource career plan; A storage unit for recording the case information, the human resource skills, the human resource profile, and the human resource career plan; a project size calculation unit that calculates the size of an estimate for a project to be estimated based on the information input from the input unit; a suitable talent search unit that searches for suitable talent having skills required for the project to be estimated based on information input from the input unit; and a talent allocation unit that allocates talent to the project to be estimated from among the searched suitable talent.
2. the storage unit records a case classification that manages the characteristics of the case to be estimated, a case classification difficulty level in which a difficulty level is set for each case classification, a skill classification that manages the minimum unit of the estimate, the case classification and actual size of past cases, and the case classification of the case; the case size calculation unit searches the actual size of the past cases by skill class based on the number of matches of the case class of the case to be estimated, and calculates the size of the estimate based on the case class difficulty corresponding to the case class of the case to be estimated; The estimation system according to claim 1 .
3. the storage unit records the actual man-hours, actual scale, and number of review comments for each case and skill category of the human resource, a productivity standard that is a criterion for calculating the productivity of the actual scale, a review comment criterion for the productivity standard unit, and a unit price of the human resource; the suitable human resource search unit calculates the productivity of each of the human resources based on the actual man-hours and the actual scale, calculates the work quality of each of the human resources based on the number of review indications, the productivity standard, and the review indication standard, determines the productivity of each of the human resources based on the calculated productivity and the work quality, and searches for the suitable human resource based on the determined productivity and unit price. The estimation system according to claim 1 .
4. The storage unit records, for each of the personnel, a case category in which the personnel is willing to work and a case category in which the personnel is not willing to work, the human resource allocation unit preferentially allocates the human resources who wish to participate based on the case classification of the estimate target case and the participation desires of the human resources, and excludes the human resources who do not wish to participate from the allocation target; The estimation system according to claim 1 .
5. The storage unit records a project availability schedule including a non-project schedule for each of the personnel, and a current project engagement rate for each of the personnel; the human resource allocation unit allocates human resources to the projects to be estimated based on the project availability schedule and the current project engagement rate; The estimation system according to claim 1 .
6. The storage unit records competency skills for each of the human resources, The suitable human resource search unit causes an output unit to output the competency skills of each of the human resources. The estimation system according to claim 1 .
Citation Information
Patent Citations
System for work man-hour estimation and personnel allocation, and its method
JP2006318331A