Property setting value changing system and property setting value changing method
The supervisory control system automates the recording and updating of property setting values in monitoring systems, addressing complexity and reducing errors by automating the change process.
Patent Information
- Application Number
- JP2023068530
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-19
- Publication Date
- 2024-10-31
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Changing property setting values in monitoring and control systems for facilities like water and sewage plants and power substations is complex, time-consuming, and prone to errors, with existing methods requiring manual on-site updates and increasing man-hours.
A supervisory control system that automatically records and stores property setting value changes with date and time information, allowing for automated retrieval and reflection of these changes during parameter updates, reducing the need for manual on-site adjustments.
Facilitates efficient and accurate updating of property settings by automating the process, reducing man-hours and minimizing errors, while ensuring timely reflection of changes during equipment modifications.
Smart Images

Figure 2024154609000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a property setting change system and a property setting change method. Regarding. [Background technology]
[0002] In the monitoring and control systems for water supply and sewage plants, buildings, and substations, Parameters are created for the equipment in use, and monitoring and control are carried out based on these parameters.
[0003] Here, for each device to be monitored and controlled (pump, flow meter, water level gauge, etc.), There are several signals to monitor and control the equipment. It acts as a container that combines all these signals into one, and can transmit signals, All information in this device, such as process numbers, process names, and equipment classifications, is managed. The parameters are used when equipment is expanded, or when equipment is replaced due to breakdown or aging. It is common for
[0004] In addition, the property settings of each parameter can be changed on-site at each facility such as a plant. Here, a property is an attribute of a signal that exists in a parameter. Usually, multiple attributes are attached to one signal. The flow of parameter modification is to collect parameter data from the site and then modify it at the factory. Then, the parameters are modified over a certain period of time.
[0005] However, from the time the parameter data is collected on-site until the modification of the parameters is completed During this period, the operation of the local facilities will continue, so some power stations will be shut down in accordance with the operation. The property settings of the parameters may be changed. This will cause the modified parameters There is a difference between the property settings of the parameter in the In order to eliminate this difference, the following two methods have been used in the past.
[0006] First, if there are many changes to property settings during on-site operation, it is necessary to modify them again on-site. The previous parameter data is collected, compared with the modified parameter data, and the Identify the parts where the property settings have been changed, and then reflect the changes in the modified parameters. In short, the data of the parameters after modification was further updated to reflect the changes in the field operation. The modified parameter data is then brought to the site and installed later.
[0007] The second is that when there are few changes to the property settings during on-site operation, the parameters after modification The meter can be installed directly on-site, and after installation is complete, the parameters can be directly adjusted on-site. This is a method for reflecting changes to property settings.
[0008] In addition, Patent Document 1 discloses a method for tracking changes in property settings in a process control system. A method to propagate and update the binding reference of a property, searching for the property setting value There is a description of the functions. [Prior art documents] [Patent documents]
[0009] [Patent Document 1] JP 2009-205672 A Summary of the Invention [Problem to be solved by the invention]
[0010] The process of changing the above property settings is complicated and time-consuming, increasing the amount of work required. However, there is a high possibility that changes will be overlooked. There is no description of how to solve the problem. [Means for solving the problem]
[0011] In order to solve the above problems, the monitoring and control system of the embodiment is a plant monitoring system. In a monitoring and control system for controlling a temperature and humidity, a property of a parameter of the monitoring and control system is Each time a property value is changed, the changed property value is stored along with the date and time of the change. and searching for property setting value change information stored in the first storage unit. A period setting unit that can set an arbitrary period for setting a period for the purpose of the A search is performed to search the first storage unit for information on changes in the property setting value during a specified period. a search unit, and a parameter searched for by the search unit, the parameter being a target for changing the property setting value; A selection section in which the parameter is selectably displayed, and a change in the parameter selected in the selection section an execution unit that reflects the property setting value thus determined in the parameter of the monitoring and control system; Equipped with.
[0012] The monitoring and control method of the embodiment is also applicable to a monitoring and control system for plant monitoring and control. Each time the property setting value of the parameter of the monitoring and control system is changed, the change The property setting value thus obtained is stored in a first storage unit, and the property setting value stored in the first storage unit is Search for property setting value change information within a given period and profile the searched property setting value change information. The parameters for which the property settings can be changed are displayed as selectable parameters. The property setting value changed in the above is reflected in the parameter of the monitoring and control system. do. [Brief description of the drawings]
[0013] [Figure 1] Configuration diagram of a property setting change system according to the present embodiment [Diagram 2] Flowchart of the property setting value change system according to the present embodiment [Diagram 3] An example of a mode for storing a property setting value change history stored in a first storage unit [Figure 4] An example of a message dialog asking whether to reflect changes to property settings [Diagram 5] An example of a dialog for selecting the parameters for which property setting changes are to be reflected DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0014] Hereinafter, embodiments for carrying out the invention will be described with reference to the drawings.
[0015] FIG. 1 shows the configuration of a property setting value changing system according to an embodiment. The stem flow is shown in Figure 2.
[0016] The embodiment has a monitoring control server 10 and a monitoring screen 20 for plant monitoring control. The monitoring and control server 10 includes a monitoring and control system 11, a first storage unit 12, and a second storage unit 13. The monitoring screen 20 includes a period setting section 16 and a selection section 17. Prepare.
[0017] The monitoring and control system 11 is software in which parameters are installed, In this embodiment, a plant monitoring and control system that supervises the monitoring and control of equipment installed in a plant is provided. It is a system.
[0018] The first storage unit 12 stores property setting values changed during on-site operation of the equipment and the date and time of the change. The property setting value change history (property setting value change information) is stored as shown in FIG. In this manner, the property is automatically stored each time it is changed. The property setting value and the date and time of the change, that is, the property change content, are stored. For example, Other property setting changes, such as the reason for the property setting change and who made the change The information may be stored.
[0019] The second storage unit 13 stores, for example, the monitoring and control system information due to the addition, failure, and aging of facilities. When updating 11, when modifying parameters, the parameters are transferred from the monitoring and control system 11. This is the part that acquires and stores the data.
[0020] In the embodiment, the second storage unit 13 stores the contents of the parameter data itself and Also, information on the date and time when the parameter data was acquired is stored. Other information regarding the acquisition of the parameter data may also be stored, such as the person who performed the acquisition.
[0021] The search unit 14 searches for properties that have been changed during a period designated by a period setting unit 16, which will be described later. The property setting value is sent to the first It can be searched from the memory unit 12.
[0022] The period setting unit 16 sets a period starting from the parameter data acquisition date and time stored in the second storage unit 13. It has a period setting function that allows you to set any fixed period as the period. For example, The date and time when the modified parameter data will be installed on-site based on the date and time when the meter data was acquired By setting the parameter, you can save the property that was changed on-site during the period when the parameter was modified. It is then possible to search for property settings.
[0023] In the embodiment, the property settings changed locally from the parameter data acquisition date and time. Since the target is a fixed value, the parameter data acquisition date and time are set as the start date of the period setting unit 16. However, it is also possible to specify any date and time for this start period.
[0024] The selection unit 17 selects a property setting value that is included in the changed property setting value. The parameters included in the parameter list are displayed on the monitoring screen 20 so that the parameters can be selected. For example, as shown in FIG. When installing the modified parameter data, the property setting value changes are applied to the parameter data. A message dialog box will be displayed asking whether to reflect the parameter data.
[0025] The execution unit 15 monitors and controls the property setting values of the parameters selected by the selection unit 17. When installing the software in the control system 11, the new parameters after modification will be reflected. While the parameters were modified at the factory, the properties changed during the field operation were It is possible to reflect the new parameter settings in the new parameter. If the number of parameters is small, install the modified parameter data and then It is also possible to reflect the property setting value in the new parameter.
[0026] Next, a system flow of the property setting value changing method according to the embodiment will be described. do.
[0027] First, parameter data is acquired in order to modify parameters for equipment updates, etc. When the acquisition date and time is received, the second storage unit 13 automatically acquires and stores the acquisition date and time (S101).
[0028] Next, when installing the modified parameters in the monitoring and control system 11, A message dialog box appears asking whether to reflect the change in the property setting value in the selection area 17 as shown in FIG. (S102)
[0029] If you select "Yes" here (Yes in S103), the property change history search period will be A setting dialog box will appear, and you can specify the search period (S104). Select "No." If so (No in S103), the flow of the embodiment ends.
[0030] In the embodiment, the start of the search period is set by default to the date and time when the parameter data was acquired. The end date can be set to any date and time. This is the date and time when the parameters are installed in the monitoring and control system. If the property setting value is changed during on-site operation, the change is reflected in the parameter. This is because the purpose of the embodiment is to project the image.
[0031] When you specify a search period, a dialog box appears asking whether you want to perform a search within the specified period. When "Yes" is selected in the dialogue (S105), the search unit 14 executes a search for the property change history stored in the first storage unit 12 (S107 If "No" is selected (No in S106), the flow of the embodiment ends.
[0032] When this search is completed, the selection unit 17 selects whether or not the property setting value change is reflected, as shown in FIG. A dialog box for selecting the target parameters is displayed, allowing you to select the parameters (S 108).
[0033] When the selection of parameters is completed, the execution unit 15 installs the parameters and The changed property setting value is reflected in the parameter (S109). The execution unit 15 reflects the change in the property setting value at the same time as the parameter is installed. However, this is not limited to the installation of the parameters at the same time, Even after stalling, property changes can be updated as needed even during normal plant operation. This completes the system flow in this embodiment. do.
[0034] As described above, according to the embodiment, the following effects can be obtained.
[0035] During the parameter modification of the monitoring and control system at the factory, The property settings that have been changed during on-site operation are automatically displayed, and the modified parameters can be installed. This allows you to reflect changes to property settings required when installing a property. This simplifies the process of changing property settings, reducing the amount of work required. This can be prevented.
[0036] Although an embodiment of the present invention has been described, this embodiment is presented by way of example only and is not intended to be limiting of the present invention. The present invention is not intended to limit the scope of the present invention. It is possible to carry out the present invention, and various omissions, substitutions, and modifications may be made without departing from the spirit of the present invention. Modifications may be made. This embodiment and its modifications are considered to be within the scope and spirit of the invention. These and other aspects are included in the scope of the invention as set forth in the claims and their equivalents. [Explanation of symbols]
[0037] 10: monitoring and control server, 11: monitoring and control system, 12: first storage unit, 13: second storage unit Memory section, 14...search section, 15...execution section, 16...period setting section, 17...selection section, 20...monitoring screen
Claims
1. In a monitoring and control system for plant monitoring and control, Each time the property setting value of the parameter of the monitoring and control system is changed, The property setting value that has been changed is stored as property setting value change information together with the change date and time information. A storage unit; A period setting for searching the property setting value change information stored in the first storage unit A period setting unit that can set an arbitrary period in the setting; The property setting value change information during the period set by the period setting unit is A search unit that searches the storage unit; The parameter searched for by the search unit and targeted for the property setting value change is selected. A selection section displayed to be selectable; The property setting value changed in the parameter selected in the selection unit is monitored. an execution unit for reflecting the parameter of a control system; A property setting change system with
2. In order to remodel the monitoring and control system, parameter data of the monitoring and control system is acquired. A second storage unit for storing the acquired information, The execution unit inputs the parameters stored in the second storage unit into the monitoring and control system. When installing the software, the property setting value change information is reflected in the parameters. The property setting change system according to claim 1 .
3. In order to remodel the monitoring and control system, parameter data of the monitoring and control system is acquired. A second storage unit for storing the acquired information, The execution unit inputs the parameters stored in the second storage unit into the monitoring and control system. After installation, property changes can be reflected in the parameters at any time. The property setting change system according to claim 1 .
4. In a monitoring and control system for plant monitoring and control, Each time the property setting value of the parameter of the monitoring and control system is changed, The property setting value is stored in a first storage unit, and the property setting value stored in the first storage unit is Search for property setting value change information within a given period and display the property setting value change information found. The parameters for which the property settings are to be changed are displayed as selectable parameters. The property setting value changed by the above method is reflected in the parameter of the monitoring and control system. 、 How to change property settings.
5. In order to remodel the monitoring and control system, parameter data of the monitoring and control system is acquired. The parameters are then stored in a second storage unit, and the parameters stored in the second storage unit are used for the monitoring and controlling When installing the software on a system, the property setting change information is reflected in the parameters. Let, The property setting change method according to claim 4.
6. In order to remodel the monitoring and control system, parameter data of the monitoring and control system is acquired. The parameters are then stored in a second storage unit, and the parameters stored in the second storage unit are used for the monitoring and controlling After installation on the system, the property setting value change information is reflected in the parameters. Let, The property setting change method according to claim 4.
Citation Information
Patent Citations
Method and apparatus to bind properties in process control system, and machine accessible medium
JP2009205672A
Cited By
Line length measuring device and fishing reel comprising the same
US20240164358A1