Manufacturing evaluation apparatus and manufacturing evaluation method
The manufacturing evaluation device addresses the lack of environmental impact prediction at the design stage by identifying processes and estimating load, allowing for sustainable product design through energy consumption and environmental load visualization.
Patent Information
- Application Number
- JP2023079780
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-15
- Publication Date
- 2024-11-27
AI Technical Summary
Existing technologies fail to measure and predict environmental impact at the product design stage, which is crucial for achieving energy savings and sustainability in manufacturing.
A manufacturing evaluation device that uses shape and configuration data to identify manufacturing processes, calculate lead time, and estimate environmental load, providing a screen for designers to visualize and reduce environmental impact during product design.
Enables product design with predicted energy consumption and environmental load assessment, facilitating sustainable design decisions.
Smart Images

Figure 2024164362000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a production evaluation device and a production evaluation method. [Background technology]
[0002] Now that companies are being asked to solve environmental issues such as carbon neutrality, manufacturers are being asked to carry out environmental assessments at the time of product design and clarify the environmental impact of the product. Traditionally, designers have usually designed products using product quality, cost, delivery date, etc. as evaluation KPIs. However, environmental assessment will also be required as a KPI in the future, which may place an additional burden on designers. Meanwhile, in recent years, the manufacturing industry has been promoting energy saving and visualization of manufacturing equipment. Specifically, as shown in Patent Document 1, it is becoming possible to obtain actual values of environmental impact information such as power consumption of manufacturing equipment and direct greenhouse gas emissions in the manufacturing process, which is downstream of the engineering chain.
[0003] Patent Document 1 describes an energy consumption measurement data processing device that collects measurement data related to energy consumption based on measurement point setting data, and aggregates and processes the measurement data, and is equipped with an energy system aggregate data processing unit that processes energy system aggregate data, which is aggregate data along an energy system, and the energy system aggregate data processing unit generates the energy system aggregate data from energy system setting data and energy system measurement point correspondence setting data that sets a correspondence between the energy system setting data and the measurement point setting data, or outputs settings for generating the energy system aggregate data.
[0004] By using such equipment, it will be possible to actually measure the energy consumption of the actual manufacturing process and equipment, and it will be possible to grasp the current state of energy consumption in the manufacturing environment. However, there is no mention of measuring such environmental loads at the product design stage, which is further upstream in the engineering chain. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] JP 2013-44589 A Summary of the Invention [Problem to be solved by the invention]
[0006] In this context, in order to achieve even more advanced energy conservation, it is important to provide a mechanism that helps reduce the environmental load of the manufacturing environment at the upstream design stage.
[0007] An object of the present invention is to provide technology that brings us closer to realizing a sustainable society by making it possible to carry out design while predicting the energy consumption and environmental load of the manufacturing environment at the product design stage. [Means for solving the problem]
[0008] The present application includes a plurality of means for solving at least a part of the above problems, examples of which are as follows: A manufacturing evaluation device according to one aspect of the present invention for solving the above problems is characterized by comprising: a manufacturing process identification unit that identifies a manufacturing process of a part using shape data including at least the shape and dimensions of the part and part configuration data including the material of the part, a lead time calculation unit that calculates a lead time in the manufacturing process, a process time identification unit that identifies a process time according to the lead time, an environmental load identification unit that identifies an environmental load according to the process time, and a screen generation unit that generates a screen showing the environmental load. Effect of the Invention
[0009] According to the present invention, it is possible to provide a technology that enables a design to be carried out while predicting the energy consumption and environmental load of the manufacturing environment at the product design stage. Problems, configurations and effects other than those described above will become apparent from the following description of the embodiment of the invention. [Brief description of the drawings]
[0010] [Figure 1] FIG. 2 is a diagram illustrating an example of the configuration of a manufacturing evaluation device. [Diagram 2] FIG. 13 is a diagram illustrating an example of a process flow of manufacturing evaluation processing. [Diagram 3] FIG. 13 is a diagram showing an example of a process flow within a manufacturing process identification step of the manufacturing evaluation process. [Figure 4] FIG. 13 is a diagram showing an example of a process flow in an environmental load identification step of the manufacturing evaluation process. [Diagram 5] FIG. 13 is a diagram showing an example of a manufacturing evaluation screen. [Figure 6] FIG. 11 is a diagram illustrating an example of parts configuration data. [Figure 7] FIG. 11 is a diagram illustrating an example of manufacturing equipment data. [Figure 8] FIG. 2 illustrates an example of a hardware configuration of a production evaluation device. [Figure 9] FIG. 13 is a diagram showing a modified example of the process flow of the manufacturing evaluation process. [Figure 10] FIG. 13 is a diagram illustrating an example of the use of manufacturing evaluation data. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. The examples are illustrative for explaining the present invention, and are omitted and simplified as appropriate for clarity of explanation. The present invention can be implemented in various other forms. Unless otherwise specified, each component may be singular or plural.
[0012] In order to facilitate understanding of the invention, the position, size, shape, range, etc. of each component shown in the drawings may not represent the actual position, size, shape, range, etc. Therefore, the present invention is not necessarily limited to the position, size, shape, range, etc. disclosed in the drawings.
[0013] As examples of various information, the various information may be described using expressions such as "table", "list", and "queue", but the various information may be expressed using data structures other than these. For example, various information such as "XX table", "XX list", and "XX queue" may be expressed as "XX information". When describing identification information, expressions such as "identification information", "identifier", "name", "ID", and "number" are used, but these are mutually interchangeable. Furthermore, in the embodiments, the identification information described using these expressions is represented using symbols, numbers, natural language, or a combination thereof, but the identification information may be in a form other than these.
[0014] When there are multiple components having the same or similar functions, they may be described by using the same reference numerals with different subscripts, or when there is no need to distinguish between these multiple components, the subscripts may be omitted.
[0015] In the embodiments, a process performed by executing a program may be described. Here, a computer executes the program using a processor (e.g., CPU, GPU), and performs the process defined by the program while using a storage resource (e.g., memory) and an interface device (e.g., communication port), etc. Therefore, the subject of the process performed by executing the program may be the processor. Similarly, the subject of the process performed by executing the program may be a controller, device, system, computer, or node having a processor. The subject of the process performed by executing the program may be a calculation unit, and may include a dedicated circuit that performs specific processing. Here, the dedicated circuit is, for example, an FPGA (Field Programmable Gate Array), an ASIC (Application Specific Integrated Circuit), or a CPLD (Complex Programmable Logic Device), etc.
[0016] The program may be installed in the computer from a program source. The program source may be, for example, a program distribution server or a computer-readable storage medium. When the program source is a program distribution server, the program distribution server may include a processor and a storage resource that stores the program to be distributed, and the processor of the program distribution server may distribute the program to be distributed to other computers. In addition, in the embodiment, two or more programs may be realized as one program, and one program may be realized as two or more programs.
[0017] Furthermore, although the present invention is typically realized by an information processing device, it may also be realized as a platform having the functions of the present invention.
[0018] 1 is a diagram showing an example of the configuration of a manufacturing evaluation device 100. For example, the manufacturing evaluation device 100 is an information processing device including a storage unit 110, a processing unit 120, an input receiving unit 130, an output processing unit 140, and a communication unit 150.
[0019] The manufacturing evaluation device 100 predicts energy consumption and environmental load according to the time required to carry out an efficient manufacturing process, mainly using product design information such as production volume, parts configuration, part shape, and dimensions. This allows the designer to change the design information by referring to the predicted environmental load. In other words, the product can be designed while suppressing the environmental load in the manufacturing process.
[0020] The storage unit 110 includes part configuration data 111, part shape data 112, facility power data 113, and environmental load conversion coefficient 114. The part configuration data 111 is, for example, part configuration information (BOM: Bill of Materials) including at least the parts that constitute the part and the materials of the parts. The part configuration data 111 will be described in detail later.
[0021] The part shape data 112 is, for example, shape data including at least the shape and dimensions of the part. Specifically, the part shape data 112 is various so-called three-dimensional CAD data, but is not limited to this and may be two-dimensional CAD data.
[0022] The facility power data 113 is information including at least information for identifying the amount of power consumption per operating hour of each manufacturing facility. Note that the facility power data 113 is not limited to this, and for example, the amount of power consumption per operating hour may be set for each predetermined date and time division (e.g., month, etc.).
[0023] The environmental load conversion coefficient 114 is information that includes information specifying at least the environmental load per unit of power consumption (e.g., greenhouse gas emissions). Note that the environmental load conversion coefficient 114 is not limited to this, and for example, the environmental load per unit of power consumption may be set for each predetermined time period (e.g., daytime, nighttime, etc.). This is because clean energy includes energy that utilizes natural phenomena, and many of these have power generation capacities that are affected by the time of day. For example, since solar power generation cannot be expected to be used at night, it is desirable to convert the environmental load to a higher value.
[0024] Greenhouse gases include gases that are considered to have various greenhouse effects. Representative examples include carbon dioxide (CO2), methane (CH4), nitrous oxide (N2O), hydrofluorocarbons (HFCs), perfluorocarbons (PFCs), and sulfur hexafluoride (SF6), but are not limited to these. Also, it does not necessarily have to include these, and it can be any of them, or the greenhouse effect can be converted to any of these gases.
[0025] The processing unit 120 includes a manufacturing process specifying unit 121 , a lead time calculation unit 122 , an environmental load specifying unit 123 , a process time specifying unit 124 , a power consumption specifying unit 125 , and a screen generation unit 126 .
[0026] The manufacturing process specifying unit 121 specifies a manufacturing process for a part using shape data including at least the shape and dimensions of the part, and part configuration data including the material of the part. The manufacturing process specifying unit 121 also accepts design specifications for the part including either or both of the tolerance and surface roughness of the part. The manufacturing process specifying unit 121 also determines a manufacturing process that satisfies the shape and dimensions of the part using the material of the part, and determines processing conditions that apply the manufacturing process to satisfy the design specifications. The processing conditions include control parameters of the equipment used in the manufacturing process (e.g., the rotation speed and rotation angle of the rotating part, cutting speed, etc.).
[0027] The lead time calculation unit 122 calculates the lead time in the manufacturing process. Specifically, the lead time calculation unit 122 calculates the processing time required to realize the material of the part and the shape and dimensions of the part in the design specifications as the lead time. If the above-mentioned processing conditions (equipment control parameters) are specified, the lead time calculation unit 122 calculates the processing time under those processing conditions.
[0028] The environmental load identifying unit 123 identifies the environmental load according to the process time. Specifically, the environmental load identifying unit 123 identifies the environmental load according to the power consumption calculated by the power consumption identifying unit 125 and the process time identified by the process time identifying unit 124.
[0029] The process time specifying unit 124 specifies the process time according to the lead time. Specifically, the process time specifying unit 124 specifies the process time using the lead time, the preparation time, and the waiting time.
[0030] The power consumption amount specifying unit 125 specifies the power consumption amount during the process time.
[0031] The screen generator 126 generates a screen showing the environmental load. The screen generator 126 includes information showing parts or manufacturing processes that have a large impact on the environmental load in the screen showing the environmental load.
[0032] The input receiving unit 130 receives input of various data. Specifically, the input receiving unit 130 receives input of design information such as part configuration data 111 and part shape data 112 from a product designer.
[0033] The output processing unit 140 outputs to the designer a screen or the like including information on the environmental load in the input design information.
[0034] The communication unit 150 communicates with other devices via a network.
[0035] 2 is a diagram showing an example of a process flow of the manufacturing evaluation process. The manufacturing evaluation process is started when the manufacturing evaluation device 100 receives a start instruction from a designer or the like. Alternatively, the manufacturing evaluation process may be started at a predetermined date and time (e.g., 1:00 p.m. every day) or at predetermined intervals (e.g., once a week).
[0036] The manufacturing evaluation process mainly includes a manufacturing process identification step S01 for accepting input of design information such as part configuration data 111, such as a BOM, and part shape data 112, such as a CAD, and identifying the manufacturing process and lead time; a manufacturing data adding step S02 for adding information on the manufacturing process and lead time to the part configuration data 111; an environmental load identification step S03 for identifying the process time based on the process lead time and the power consumption based on the process time, and identifying the environmental load based on the power consumption; an environmental data adding step S04 for adding environmental load data to the part configuration data 111; and an environmental data visualization step S05 for visualizing and displaying the environmental load data.
[0037] 3 is a diagram showing an example of a process flow of the manufacturing process identification step of the manufacturing evaluation process. First, the manufacturing process identification unit 121 reads the part configuration data 111 and the part shape data 112 as inputs (step S011).
[0038] In addition, the manufacturing process specification unit 121 accepts input of a production plan for the product as premise information before calculation (step S012). The production plan is information that specifies the planned value of the production volume of the product for each predetermined period. This is because the time for operating the manufacturing line changes depending on the planned value of the production volume.
[0039] Then, the manufacturing process specifying unit 121 accepts the selection of a rough process for each part (step S013). Examples of processes include "cutting (forming the part by cutting)", "near net shape (printing with a 3D printer)", "forging", etc. The manufacturing process specifying unit 121 accepts the settings here so that the manufacturing process of the product can be roughly planned.
[0040] Then, the manufacturing process specifying unit 121 receives input of design specifications such as tolerance, surface roughness, etc. (Step S014). In general, if the tolerance or the surface roughness value in finishing is set low, it is estimated that additional processes such as finishing processing and polishing will be required, which will affect the lead time.
[0041] Then, the manufacturing process specifying unit 121 generates a plurality of (N) realistic process candidates (step S015). Specifically, the manufacturing process specifying unit 121 uses the shape and dimensions of the part to design a plurality of manufacturing process candidates in cooperation with a CAM (Computer Aided Manufacturing) tool or the like.
[0042] At this time, the manufacturing process specifying unit 121 determines a manufacturing process that satisfies the shape and dimensions of the part using the material of the part, and determines processing conditions that apply the manufacturing process and satisfy the design specifications.
[0043] Then, the lead time calculation unit 122 selects the i-th (i is an integer equal to or greater than 1) process candidate (step S016), and calculates the equipment lead time (step S017). Then, the process of steps S016 and S017 is repeated while incrementing i until i coincides with N (step S018).
[0044] Then, the manufacturing process specifying unit 121 specifies a candidate process that has the shortest lead time (step S019).
[0045] The above is an example of the process flow of the manufacturing process identification step of the manufacturing evaluation process. According to the manufacturing process identification step, a candidate process that has the shortest lead time can be identified.
[0046] FIG. 4 is a diagram showing an example of a process flow in the environmental load identification step of the manufacturing evaluation process. First, the process time identification unit 124 calculates and identifies the process time according to the lead time (step S031). Specifically, the process time identification unit 124 identifies the process time for each process included in the selected process candidate by using the lead time, preparation time, and waiting time. More specifically, the process time identification unit 124 determines the process time by adding, for example, the statistical values of the preparation time and waiting time of a process similar to the process to the lead time calculated by the lead time calculation unit 122 in step S017. Note that the process time identification unit 124 is not limited to using the statistical values of the preparation time and waiting time of a process similar to the process, and may use a predetermined preparation time and waiting time.
[0047] Then, the power consumption specifying unit 125 calculates the process power consumption (step S032). Specifically, the power consumption specifying unit 125 refers to the equipment power data 113 to specify information for specifying the power consumption per operating time of the manufacturing equipment carrying out each process included in the selected process candidate. The power consumption specifying unit 125 then calculates the process power consumption of each process by taking the process time specified by the process time specifying unit 124 in step S031 as the operating time. Specifically, the power consumption specifying unit 125 calculates the product of the process time and the power consumption for each process, and specifies the result as the process power consumption.
[0048] Then, the environmental load identifying unit 123 calculates an index value indicating the environmental load (step S033). Specifically, the environmental load identifying unit 123 converts the process power consumption of each process included in the selected process candidate into an environmental load by referring to the environmental load conversion coefficient 114. Specifically, the environmental load identifying unit 123 calculates the product of the power consumption and the environmental load conversion coefficient for each process, and sets it as the environmental load. For example, when converting into the amount of CO2 emissions, which is one of the indicators indicating the environmental load, the environmental load identifying unit 123 calculates the product of the power consumption and the CO2 emission coefficient, which are included in the environmental load conversion coefficient 114, and sets it as the index value of the environmental load.
[0049] The above is an example of the process flow of the environmental load identification step of the manufacturing evaluation process. According to the environmental load identification step, it is possible to identify the environmental load for a candidate process that has the shortest lead time.
[0050] 5 is a diagram showing an example of a manufacturing evaluation screen. The manufacturing evaluation screen 40 is generated by the screen generation unit 126 throughout the manufacturing evaluation process and is displayed by the output processing unit 140. The manufacturing evaluation screen 40 accepts various inputs and updates the display accordingly to reflect the results of the inputs. The manufacturing evaluation screen 40 includes an input setting acceptance area 41, an analysis procedure acceptance area 42, and an analysis result display area 43.
[0051] The input setting reception area 41 is an area for receiving input information. The input information includes a project file name, part configuration data for receiving input for designating the storage location of part configuration data 111, part shape data for receiving input for designating the storage location of part shape data 112, facility power data for receiving input for designating the storage location of facility power data 113, and environmental load conversion coefficient for receiving input for designating the storage location of environmental load conversion coefficient 114.
[0052] The analysis procedure reception area 42 is an area for receiving instructions for the analysis procedure. The instructions for the analysis procedure are received by inputting to buttons or the like according to a processing procedure that is provided in advance. For example, the analysis procedure reception area 42 has seven procedure steps, which respectively receive instructions for start, drawing number selection, process identification, adding manufacturing data, identifying environmental load, adding environmental data, and saving. The user, or designer, can obtain the results of estimating the environmental load from the design information by operating these buttons in order according to the analysis procedure.
[0053] For example, when an input is made to the process identification button, the processing of manufacturing process identification step S01 is started, the analysis result display area 43 is updated, and candidate manufacturing processes are displayed. When an input is made to the environmental load identification button, the processing of environmental load identification step S03 is started, the analysis result display area 43 is updated, and information indicating the environmental load is displayed. In particular, the information indicating the environmental load includes information indicating parts or manufacturing processes that have a large impact on the environmental load. It is desirable to use a Pareto chart or a pie chart for such information. By showing the information using a Pareto chart or a pie chart, it becomes easier to grasp the points for improvement, and the visualization effect is high.
[0054] The analysis result display area 43 is an area that displays the results of processing performed by the analysis procedure. The analysis result display area 43 includes a process candidate display area 44 that displays candidate manufacturing processes, and an environmental load data display area 45 that displays the environmental load. The environmental load data display area 45 includes a Pareto chart and a pie chart, as described above. In particular, the Pareto chart shows the elements with the greatest influence on the horizontal axis and the cumulative results on the vertical axis, making it possible to grasp at a glance which parts or process elements dominate the cumulative results of the environmental load.
[0055] FIG. 6 is a diagram showing an example of parts configuration data. In the parts configuration data 111, a product name 111a, a part name 111b, a type 111c, a manufacturer name 111d, a quantity 111e, a specification 111f, a material 111g, and a drawing number 111h are associated with each other. In general, a product name 111a is provided for each product, and a type 111c, a manufacturer name 111d, a quantity 111e, a specification 111f, a material 111g, and a drawing number 111h are provided for each part constituting the product and each part constituting the part. In particular, the material 111g is one of the important decision-making factors when examining and selecting a manufacturing process. Also, the drawing number 111h is a number for referring to a drawing file of the part. The parts configuration data 111 can be a general BOM.
[0056] 7 is a diagram showing an example of manufacturing equipment data. The manufacturing equipment data is data that is added to the parts configuration data 111 as additional information by being associated with the parts configuration data by a drawing number 111h. The manufacturing equipment data may be data of a system generally called BOP (Bill Of Process). The manufacturing equipment data is associated with environmental data 111r in addition to BOP data, such as a drawing number 111h, a process 111j, a location 111k, a building 111m, equipment 111n, and equipment information 111p. The environmental data 111r is information on the environmental load identified by the environmental load identification unit 123.
[0057] Of these, the BOP data is information that was added or supplemented in the manufacturing data addition step S02, and the environmental data 111r is information on the environmental load that was added or supplemented in the environmental data addition step S04.
[0058] The information on the process 111j, the location 111k, the building 111m, the equipment 111n, and the equipment information 111p is information that specifies the part manufacturing process indicated by the drawing number, the location where the process is performed, and the building, equipment, and other equipment that are the details of the process. Since this information is determined according to the manufacturing environment of each manufacturer, it is determined in advance or supplemented in advance according to the past performance.
[0059] 8 is a diagram showing an example of the hardware configuration of the manufacturing evaluation device. The manufacturing evaluation device 100 can be realized by a general computer 900 including a processor 901, a hardware memory 902 such as a RAM (Random Access Memory), an external storage device 903 such as a hard disk drive (HDD) or a solid state drive (SSD), a reading device 905 for reading information from a portable storage medium 904 such as a CD (Compact Disk) or a DVD (Digital Versatile Disk), an input device 906 such as a keyboard, a mouse, a barcode reader, or a touch panel, an output device 907 such as a display, and a communication device 908 for communicating with other computers via a communication network such as a LAN or the Internet, or a network system including a plurality of such computers 900. The reading device 905 may be capable of not only reading but also writing to the portable storage medium 904.
[0060] The processor 901 is, for example, a central processing unit (CPU) or a graphics processing unit (GPU). The processor 901 executes various processes by executing various predetermined programs loaded from an external storage device 903 to a memory 902. The programs are, for example, application programs that can be executed on an operating system (OS) program. The programs may be installed in the external storage device 903 from a portable storage medium 904 via a reading device 905, or may be downloaded from a network via a communication device 908 and executed by the processor 901.
[0061] For example, the manufacturing process identification unit 121, the lead time calculation unit 122, the environmental load identification unit 123, the process time identification unit 124, the power consumption identification unit 125, and the screen generation unit 126 can be realized by loading a program stored in an external storage device 903 into the memory 902 and executing it on the processor 901.
[0062] The input reception unit 130 can be realized by the processor 901 using the input device 906 and the communication device 908. The output processing unit 140 can be realized by the processor 901 using the output device 907 and the communication device 908. The storage unit 110 can be realized by the processor 901 using the memory 902 or the external storage device 903. The communication unit 150 can be realized by the processor 901 using the communication device 908.
[0063] The above is an example of the manufacturing evaluation device 100 according to the embodiment of the present invention. Note that the present invention is not limited to the above-mentioned embodiment, and various modified examples are included. For example, the above-mentioned embodiment has been described in detail to explain the present invention in an easy-to-understand manner, and is not necessarily limited to having all of the configurations described. It is possible to replace a part of the configuration of the embodiment with another configuration, and it is also possible to add the configuration of another embodiment to the configuration of the embodiment. It is also possible to delete a part of the configuration of the embodiment.
[0064] For example, in the above embodiment, the part configuration and part shape data are exemplified as design information to be input, but the input is not limited to this, and it is also possible to input a manufacturing process and a lead time (or process time) calculated separately corresponding to the design information. In addition, the indicator of environmental load is not limited to CO2, but includes various greenhouse gases.
[0065] Also, for example, in the above-described embodiment, the data stored in the storage unit 110 is used in the production evaluation apparatus 100, but this is not limiting. For example, the production evaluation apparatus 100 may be communicably connected to other apparatuses via the network 50, and any or all of the information in the storage unit 110 may be made accessible, i.e., sharable, or data shared with other apparatuses via cloud storage or the like may be used.
[0066] 9 is a diagram showing a modified example of the processing flow of the manufacturing evaluation processing. In this modified example, a case where data is shared with other devices using cloud storage or the like as described above will be described. After processing the environmental data visualization step S05, the processing unit 120 performs a data sharing step S06. Specifically, the processing unit 120 copies the manufacturing process candidates identified in the manufacturing process identification step S01 and the environmental loads identified in the environmental load identification step S03 to the cloud storage.
[0067] FIG. 10 is a diagram showing an example of the use of manufacturing evaluation data. A designer 10 is a person in charge of designing a product and a user of the manufacturing evaluation device 100. In addition to part configuration data 111, part shape data 112, equipment power data 113, and environmental load conversion coefficient 114 shared from the manufacturing evaluation device 100, an environmental load 61 and a manufacturing process candidate 62 are stored and shared in the cloud storage 60. The data in the cloud storage 60 can be accessed by personnel such as an equipment operator 11 who operates the manufacturing equipment, a line maintenance person 12 who performs maintenance of the production equipment, a process designer 13 who is in charge of designing and developing the production process, a procurement person 14 who negotiates material procurement and costs, and a product sales person 15 who is in charge of sales of the completed products.
[0068] For example, a process designer 13 can refer to the environmental load 61 and use it to improve the efficiency of a process that has a large amount of CO2 emissions. Or, if an effective reduction effect in CO2 emissions can be found, a product sales representative 15 can use it as a selling point during sales.
[0069] In addition, when new equipment is introduced, data such as the power consumption of the new equipment can be added to the parts configuration data 111 and equipment power data 113 by the line maintenance staff 12 and equipment operator 11, and this data can be shared with the designer 10 and process designer 13 so that environmental load analysis and process program creation can be performed using the latest data. In this way, using this system makes the supply chain seamless, further reducing the overall environmental load and leading to effective design and manufacturing.
[0070] The above-mentioned units, configurations, functions, processing units, etc. may be realized in part or in whole by hardware, for example by designing them as integrated circuits. Also, the above-mentioned units, configurations, functions, etc. may be realized in software by a processor interpreting and executing a program that realizes each function. Information such as the programs, tables, files, etc. that realize each function can be stored in a memory, a recording device such as a hard disk, or a recording medium such as an IC card, an SD card, or a DVD.
[0071] The control lines and information lines in the above-described embodiment are those considered necessary for the explanation, and do not necessarily show all the control lines and information lines in the product. In reality, it may be considered that almost all the components are connected to each other. The present invention has been described above with a focus on the embodiment. [Explanation of symbols]
[0072] 100: manufacturing evaluation device, 110: memory unit, 111: part configuration data, 112: part shape data, 113: equipment power data, 114: environmental load conversion coefficient, 120: processing unit, 121: manufacturing process identification unit, 122: lead time calculation unit, 123: environmental load identification unit, 124: process time identification unit, 125: power consumption identification unit, 126: screen generation unit, 130: input reception unit, 140: output processing unit, 150: communication unit.
Claims
1. a manufacturing process identification unit that identifies a manufacturing process of the part using shape data including at least a shape and a size of the part and part configuration data including a material of the part; A lead time calculation unit that calculates a lead time in the manufacturing process; A process time specification unit that specifies a process time according to the lead time; an environmental load identifying unit that identifies an environmental load according to the process time; a screen generating unit for generating a screen showing the environmental load; A manufacturing evaluation device comprising:
2. The manufacturing evaluation device according to claim 1 , The manufacturing process specifying unit receives a design specification of the part, the lead time calculation unit calculates, as the lead time, a processing time required to realize the material of the part and the shape and dimensions of the part in the design specifications; A manufacturing evaluation device comprising:
3. The manufacturing evaluation device according to claim 2, The manufacturing process specifying unit accepts at least one or both of a tolerance and a surface roughness of the part as the design specification. A manufacturing evaluation device comprising:
4. The manufacturing evaluation device according to claim 3, the manufacturing process specifying unit determines a manufacturing process that satisfies the shape and dimensions of the part using the material, and determines processing conditions that apply the manufacturing process to satisfy the design specifications; The processing conditions include control parameters of the equipment used in the manufacturing process; A manufacturing evaluation device comprising:
5. The manufacturing evaluation device according to claim 4, The lead time calculation unit calculates the processing time under the processing conditions. A manufacturing evaluation device comprising:
6. The manufacturing evaluation device according to claim 1 , the process time specifying unit specifies the process time by using the lead time, a preparation time, and a waiting time. A manufacturing evaluation device comprising:
7. The manufacturing evaluation device according to claim 1, a power consumption specifying unit that specifies the power consumption during the process time, The environmental load specifying unit specifies the environmental load according to the power consumption calculated by the power consumption specifying unit. A manufacturing evaluation device comprising:
8. The manufacturing evaluation device according to claim 1, the screen generator includes, on the screen showing the environmental load, information indicating the part or the manufacturing process having a large impact on the environmental load. A manufacturing evaluation device comprising:
9. The manufacturing evaluation device according to claim 1, a storage unit that stores the manufacturing process, the shape data, the parts configuration data, or the environmental load in a manner that allows the data to be shared with other devices; A manufacturing evaluation device comprising:
10. A manufacturing evaluation method using an information processing device, comprising: The information processing device includes: a manufacturing process identification step of identifying a manufacturing process of the part using shape data including at least a shape and a size of the part and part configuration data including a material of the part; A lead time calculation step of calculating a lead time in the manufacturing process; A process time specifying step of specifying a process time according to the lead time; An environmental load identification step of identifying an environmental load according to the process time; a screen generating step of generating a screen showing the environmental load; The manufacturing evaluation method is characterized by carrying out the steps.
Citation Information
Patent Citations
Energy consumption measurement data processor
JP2013044589A
Cited By
Estimation device and estimation method
WO2026210773A1