The scaffold dismantling method uses pins to secure floorboards and facilitates efficient dismantling by connecting them to lifting tools, allowing safe and rapid removal of scaffolds without additional support structures.

JP2024165533APending Publication Date: 2024-11-28THE CHUGOKU ELECTRIC POWER CO INC
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023081810
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-17
Publication Date
2024-11-28

AI Technical Summary

Technical Problem

Existing scaffold dismantling methods are inefficient and require additional safety measures, such as temporarily constructing scaffolding below the dismantled scaffold, which increases time and effort.

Method used

A scaffold dismantling method involving the use of pins instead of bolts to secure floorboards, allowing for efficient dismantling by connecting pins to lifting tools and safely removing floorboards while maintaining stability, and then moving support members to non-floorboard support positions for easy extraction.

Benefits of technology

The method enables safe and efficient dismantling of scaffolds without the need for additional temporary scaffolding, reducing time and effort while ensuring worker safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024165533000001_ABST
    Figure 2024165533000001_ABST
Patent Text Reader

Abstract

To provide a scaffold disassembling method which can efficiently disassemble a scaffold while securing safety.SOLUTION: A scaffold disassembling method of a hood scaffold 1 having a plurality of support members 20, and a floor plate 40 which is bridged between the two different support members 20 and is fixed to the support members 20 through bolts 7 inserted into through holes 8 penetrating through themselves and the support members 20 includes: an insertion step of pulling out the bolts 7 from the through holes 8, and inserting pins 80 into the through holes 8 instead of the pulled out bolts 7; a connection step of connecting the pins 80 inserted into the through holes 8 to a suspension tool 9 for suspending the floor plate 40; and a suspension step of operating the suspension tool 9 to suspend the floor plate 40 together with the pins 80, thereby removing the floor plate 40 from the support members 20.SELECTED DRAWING: Figure 6D
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a scaffolding dismantling method. [Background technology]

[0002] Conventionally, there is known a method for dismantling scaffolding used in the construction of structures such as buildings. For example, cited document 1 describes a method in which scaffolding division points are set at positions on the side of the removal work area to divide the scaffolding into a plurality of separate scaffoldings, and the separate scaffolding is sequentially dismantled starting from the separate scaffolding closest to the removal work area. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2011-127377 A Summary of the Invention [Problem to be solved by the invention]

[0004] Incidentally, when dismantling scaffolding, workers often carry out dismantling work from a scaffolding that is set up below the scaffolding to be dismantled, as in Patent Document 1. Although this method allows workers to safely dismantle scaffolding, there is room for improvement in terms of dismantling scaffolding more efficiently.

[0005] An object of the present invention is to provide a scaffolding dismantling method that can efficiently dismantle scaffolding while ensuring safety. [Means for solving the problem]

[0006] (1) The present invention relates to a method for dismantling scaffolding including a plurality of support members and a floor panel that is stretched between two different support members and fixed to the support members via a bolt inserted into a through hole that passes through the support member and the floor panel, the method including an insertion step of removing the bolt from the through hole and inserting a pin into the through hole in place of the removed bolt, a connection step of connecting the pin inserted into the through hole to a lifting tool that lifts the floor panel, and a lifting step of operating the lifting tool to lift the floor panel together with the pin, thereby removing the floor panel from the support members.

[0007] (2) A scaffolding dismantling method as described in (1), in which the floor panels are arranged adjacent to each other, and after one of the floor panels is removed from the support member in the lifting process, the insertion process is started for the floor panel adjacent to the one of the floor panels.

[0008] (3) A scaffolding dismantling method as described in (2), in which each of the plurality of floor boards has a plurality of through holes through which bolts are inserted, and in the insertion step, the bolt is not removed from the through hole on the side of the floor board to be removed next in one of the floor boards, but the bolt is removed from the through hole on the opposite side of the floor board to be removed next and the pin is inserted, and after the connecting step, an extraction step is included in which the bolt is removed from the through hole on the side of the floor board to be removed next.

[0009] (4) The scaffolding further comprises a rod-shaped shaft member to which the multiple support members are connected, and is used by being placed inside the structure in the construction of a hollow structure, each of the multiple support members of the scaffolding extends in a direction perpendicular to the shaft member and is movable between a floor board support position where the floor board can be supported and a non-floor board support position extending along the shaft member, and the scaffolding dismantling method described in any of (1) to (3) further comprises a removal step of removing all of the floor boards fixed to the support members when they have been moved to the floor board support positions, and then moving the multiple support members to the non-floor board support positions and removing the shaft member and the support members from an opening provided in the upper part of the structure.

[0010] (5) A scaffolding dismantling method as described in (4), in which the floor plates are arranged adjacent to each other on the support member when it is moved to the floor plate support position, and the floor plates include a plurality of first floor plates arranged in a line along the inner surface of the structure at the tip side of the support member opposite the axial member, and a plurality of second floor plates arranged in a line between the axial member of the support member and the first floor plates in a direction perpendicular to the axial member, and after the plurality of first floor plates are removed from the support member, the plurality of second floor plates are removed from the tip of the support member toward the axial member. Effect of the Invention

[0011] According to the present invention, scaffolding can be dismantled efficiently while ensuring safety. [Brief description of the drawings]

[0012] [Figure 1] This is a cross-sectional view showing the silo to be constructed, and the scaffolding and automatic lifting device used in constructing the silo. [Diagram 2] 2 is an arrow diagram of the automatic lifting device as viewed along the direction of arrow A shown in FIG. 1. [Diagram 3] This is an arrow diagram of the Jinba scaffolding when viewed along the direction of arrow B shown in Figure 1. [Figure 4] A cross-sectional view showing a silo and a batten scaffolding positioned within the silo with the support members moved to the floor board support position. [Diagram 5] A cross-sectional view showing a silo and a batten scaffolding positioned within the silo with the support members moved to a non-floor board support position. [Figure 6A] FIG. 2 is a diagram for explaining the flow of a scaffolding dismantling method according to one embodiment of the present invention, and is a plan view showing a floor board and a support member before the insertion process. [Figure 6B] FIG. 2 is a diagram for explaining the flow of a scaffolding dismantling method according to one embodiment of the present invention, and is a plan view showing the floor board and support member after the insertion process. [Figure 6C]FIG. 2 is a diagram for explaining the flow of a scaffolding dismantling method according to one embodiment of the present invention, and is a plan view showing the floor board and support member after the extraction process. [Figure 6D] FIG. 1 is a diagram for explaining the flow of a scaffolding dismantling method according to one embodiment of the present invention, and is a perspective view showing the state of work in the lifting process. [Figure 7] This is an enlarged cross-sectional view showing a bolt being inserted into a through hole that passes through the floor plate and support member of the jinba scaffolding. [Figure 8] This is an enlarged cross-sectional view showing a state in which a pin is inserted instead of a bolt into a through hole that penetrates the floor plate and support member of the jinba scaffolding. [Figure 9A] FIG. 2 is a diagram for explaining the order of removing floor panels from support members in a scaffolding dismantling method according to one embodiment of the present invention, and is a plan view showing the state after the three first floor panels have been removed. [Figure 9B] This is a diagram for explaining the order of removing floor panels from support members in a scaffolding dismantling method according to one embodiment of the present invention, and is a plan view showing the state after eight first floor panels have been removed. [Figure 9C] FIG. 2 is a diagram for explaining the order of removing floor panels from support members in a scaffolding dismantling method according to one embodiment of the present invention, and is a plan view showing the state after one second floor panel has been removed. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0013] Hereinafter, preferred embodiments of the present invention will be described with reference to the drawings, however, the present invention is not limited to the following embodiments.

[0014] The scaffolding dismantling method according to the present embodiment is a method for dismantling scaffolding used in the construction of a structure such as a building. In this embodiment, an example will be described in which a scaffolding 1 used in the construction of a silo 100 as a hollow structure is dismantled and removed from inside the silo 100.

[0015] First, the scaffolding 1 to which the scaffolding dismantling method of the present embodiment is applied will be described with reference to Figs. 1 to 5. Fig. 1 is a cross-sectional view showing a silo 100 to be constructed, and a scaffolding 1 and an automatic lifting device 5 used in the construction of the silo 100. Fig. 2 is an arrow diagram when the automatic lifting device 5 is viewed along the direction of the arrow A shown in Fig. 1. Fig. 3 is an arrow diagram when the scaffolding 1 is viewed along the direction of the arrow B shown in Fig. 1. Fig. 4 is a cross-sectional view showing the silo 100 and the scaffolding 1 in a state in which the support member 20 is arranged in the silo 100 and has been moved to a floor board support position. Fig. 5 is a cross-sectional view showing the silo and the scaffolding 1 in a state in which the support member 20 is arranged in the silo 100 and has been moved to a non-floor board support position. In Fig. 4, a scaffolding 6 temporarily installed below the scaffolding 1 in order to dismantle the scaffolding 1 is shown by a dashed line.

[0016] The jinba scaffolding 1 is a scaffolding used during the construction of the silo 100. The jinba scaffolding 1 is used by being placed inside the silo 100 together with the automatic lifting device 5 during the construction of the silo 100.

[0017] The silo 100 is a tank for storing solid fuel such as biomass. The silo 100 includes a conical section 110 formed in a generally inverted cone shape with a hollow space on the lower side, a cylindrical section 120 extending from the upper end of the conical section 110 and formed in a cylindrical shape, and a lid section (not shown) that closes an opening (not shown) formed at the upper end of the cylindrical section 120.

[0018] In constructing the silo 100, after the conical section 110 of the silo 100 is constructed, a crest scaffolding 1 is temporarily set up inside the constructed conical section 110, and an automatic lifting device 5 for constructing the cylindrical section 120 is temporarily set up on top of the crest scaffolding 1.

[0019] The automatic lifting device 5 is a scaffold on which workers who construct the cylindrical section 120 stand. The automatic lifting device 5 includes a base 51 that can be connected to the upper part of the jinba scaffold 1, a plurality (three) of decks 52 that extend radially from the base 51, and a construction scaffold (not shown) that is supported by the decks 52 and can move from the end (hereinafter, the tip) of the decks 52 opposite the base 51 in a direction perpendicular to the decks 52.

[0020] The automatic lifting device 5 is disposed inside the cylindrical portion 120 so that the construction scaffold can move in the vertical direction Y. Specifically, as shown in FIG. 1 and FIG. 2, the automatic lifting device 5 is temporarily installed inside the silo 100 so that the base 51 is connected to the upper end of the shaft member 10 (described later) of the crooked scaffold 1, and the three decks 52 extend in the radial direction R of the silo at intervals approximately equal to the circumferential direction C of the silo 100. A worker climbs on the construction scaffold that can move in the vertical direction Y along the inner peripheral surface 101 of the silo 100, and constructs the cylindrical portion 120 from the inside of the silo 100 in order from the bottom. The vertical direction Y is also the axial direction of the silo 100. The circumferential direction C means the direction along the inner peripheral surface 101 of the silo 100 in a plan view, and the radial direction R means the radial direction of the conical portion 110 or the cylindrical portion 120. The automatic lifting device 5 is supported by the crooked scaffold 1 temporarily installed below it.

[0021] Next, the configuration of the batik scaffolding 1 will be described with reference to Figures 3 to 5, 6A, and 7. Figure 6A is a plan view showing an example of a floorboard 40 fixed to a support member 20. Figure 7 is an enlarged cross-sectional view showing a state in which a bolt 7 is inserted into a through-hole 8 penetrating the support member 20 and the floorboard 40 of the batik scaffolding 1.

[0022] The crest scaffolding 1 is temporarily installed inside the cone section 110 during construction of the silo 100. The crest scaffolding 1 includes an axis member 10, a plurality of support members 20, a moving mechanism 30, and a plurality of floor plates 40.

[0023] The shaft member 10 is a rod-shaped member, and multiple support members 20 are connected to it via a moving mechanism 30. The shaft member 10 is provided with a ladder (not shown) along which a worker can move in the length direction, and landings 11 arranged at predetermined intervals along the length direction. As shown in Figs. 1 and 4, when the silo 100 is constructed, the shaft member 10 is temporarily installed inside the cone section 110 of the silo 100 so as to extend in the vertical direction Y. A base 51 of the automatic lifting device 5 is attached to the upper end of the shaft member 10.

[0024] The support members 20 extend from the shaft member 10 and support the floorboards 40. The crane scaffolding 1 of this embodiment includes twelve support members 20. One end portion (hereinafter, the base end portion) 23 of each support member 20 is connected to the shaft member 10 via a moving mechanism 30.

[0025] The support member 20 can be moved by the moving mechanism 30 between a floor plate supporting position where it extends in a direction perpendicular to the shaft member 10 and can support the floor plate 40, and a non-floor plate supporting position where it extends along the shaft member 10 and does not support the floor plate 40. The support member 20 is temporarily installed inside the conical portion 110 of the silo 100 so that at the floor plate supporting position, it extends in the radial direction R from the shaft member 10 as shown in Fig. 3 or Fig. 4, and at the non-floor plate supporting position, it extends in the approximately vertical direction Y along the shaft member 10 as shown in Fig. 5.

[0026] 3, each of the multiple support members 20 is disposed at equal intervals in the circumferential direction C with respect to the shaft member 10 at the floor plate support position. Furthermore, the other end (hereinafter, tip) 24 of each support member 20, i.e., the end opposite the shaft member 10 at the floor plate support position, is located near the inner circumferential surface 101 of the silo 100. Note that the support member 20 can support the floor plate 40 only when it is moved to the floor plate support position.

[0027] 3 and 6A, the support member 20 has a rod-shaped main body portion 21 that extends from the shaft member 10 to the vicinity of the inner circumferential surface 101 of the silo 100 at the floor plate support position, and a flat fixing portion 22 that extends in a direction away from the main body portion 21 from both sides in the circumferential direction C of the main body portion 21. The fixing portion 22 is formed at a position where the floor plate 40 is fixed. The fixing portion 22 has a plurality of through holes 221 that penetrate the fixing portion 22 in its thickness direction and into which the bolts 7 can be screwed.

[0028] The movement mechanism 30 has a joint portion 33, a slide portion 31, and a plurality of rib portions 32, and moves the support member 20 between a floor board supporting position and a non-floor board supporting position.

[0029] The joint portion 33 is a member interposed between the shaft member 10 and the support member 20. The joint portion 33 is fixed to the base end portion 23 of the support member 20, and is rotatably connected to the shaft member 10. With this configuration, the support member 20 becomes rotatable with the joint portion 33 as a fulcrum.

[0030] The slide portion 31 is attached to the shaft member 10 so as to be slidable in the length direction of the shaft member 10 along the shaft member 10. The slide portion 31 is attached above the joint portion 33 of the shaft member 10.

[0031] Each of the multiple rib portions 32 is rod-shaped and connects the support member 20 and the sliding portion 31. Specifically, one end of each rib portion 32 is connected to the sliding portion 31, and the other end is connected to approximately the center of the support member 20 in the longitudinal direction.

[0032] According to the movement mechanism 30, as the slide part 31 slides upward from the state in Fig. 4, for example, the support member 20 is pulled by the support frame part 32, rotates about the joint part 33 to which the base end part 23 is connected as a fulcrum, and the tip part 24 moves closer to the shaft member 10. Conversely, as the slide part 31 slides downward from the state in Fig. 5, the support member 20 is pushed by the support frame part 32, rotates about the joint part 33 as a fulcrum, and the tip part 24 moves away from the shaft member 10 and closer to the inner circumferential surface 101 of the silo 100.

[0033] The floor panel 40 is flat, spans between two support members 20 that are in different states when moved to the floor panel support position, and is fixed to the support members 20 via bolts 7. In this embodiment, one floor panel 40 spans between two support members 20 adjacent in the circumferential direction C as shown in Fig. 3. Note that handrails 25 as shown in Figs. 1 and 4 are arranged on the floor panel 40.

[0034] As shown in FIG. 3, the plurality of floor plates 40 includes a plurality of first floor plates 41 and a plurality of second floor plates 42. The plurality of first floor plates 41 are arranged so as to line up along the inner peripheral surface 101 of the silo 100 on the tip end 24 side of the support member 20 when moved to the floor plate support position. The plurality of second floor plates 42 are arranged so as to line up in a direction perpendicular to the shaft member 10 (radial direction R in FIG. 3) between the shaft member 10 and the first floor plate 41 in the support member 20 when moved to the floor plate support position. In the example shown in FIG. 3, six second floor plates 42 are suspended between two support members 20 out of the twelve support members 20.

[0035] The configuration common to the first floor plate 41 and the second floor plate 42 of the floor plate 40 will be described with reference to Figs. 6A and 7, taking the first floor plate 41 as an example. The floor plate 40 is formed with a plurality of through holes 401 that penetrate in the thickness direction and into which the bolts 7 can be screwed, and is fixed to the fixing parts 22 of two different support members 20 via the bolts 7. In the first floor plate 41, a plurality of through holes 401 are formed at both ends of the floor plate 40 in the circumferential direction C, as shown in Fig. 6A, for example. The plurality of through holes 401 are formed at positions that overlap with the through holes 221 when the end of the floor plate 40 in the circumferential direction C is disposed in the fixing part 22. Similarly, in the second floor plate 42, a plurality of through holes 401 are formed at both ends of the floor plate 40 in the circumferential direction C.

[0036] 7, the floorboard 40 and the support member 20 are fixed by inserting a bolt 7 into the through hole 401 and the through hole 221 with their central axes substantially aligned, and screwing the bolt 7 into the through hole 401 and the through hole 221. In the following description, the through hole 401 and the through hole 221 with their central axes substantially aligned so that the through hole 401 and the through hole 221 form a single hole penetrating the support member 20 and the floorboard 40 are collectively referred to as the through hole 8. In other words, the floorboard 40 is fixed to the support member 20 via the bolt 7 inserted into the through hole 8 that penetrates the floorboard 40 and the support member 20.

[0037] 6A and 7, a hook portion 402 onto which a hook 91 provided at the tip of a lifting tool 9 can be hooked is formed near each through hole 401 of the floorboard 40. The lifting tool 9 is, for example, a part of a crane or the like, and is a tool for lifting the floorboard 40. When the hook 91 is hooked onto the hook portion 402 of the floorboard 40 from which the bolts 7 have been removed, the lifting tool 9 is operated, and the hook 91 is moved upward, the floorboard 40 is lifted up and separated from the support member 20.

[0038] Here, when the construction of the main structure of the silo 100, such as the cone section 110 and the cylindrical section 120, is completed, the automatic lifting device 5 is dismantled and removed from an opening (not shown) provided at the top of the silo 100, and then the batten scaffolding 1 is dismantled. At this time, for example, if a worker stands on the floor plate 40 and removes the bolts 7 from the floor plate 40, the floor plate 40 may slip off the support member 20. For this reason, in consideration of safety, a scaffolding 6 as shown by the dashed line in FIG. 4 is temporarily set up under the batten scaffolding 1 to be dismantled, and dismantling work is often carried out from the scaffolding. However, although this method can ensure safety, it is time-consuming to temporarily set up the scaffolding 6. According to the scaffolding dismantling method according to this embodiment, the scaffolding can be dismantled more efficiently while ensuring safety.

[0039] Next, the scaffolding dismantling method according to this embodiment will be described using an example of dismantling a jinba scaffolding 1.

[0040] Fig. 6A to Fig. 6D are diagrams for explaining the flow of the scaffolding dismantling method. Fig. 6A is a plan view showing the support member 20 and floor plate 40 before the insertion process. Fig. 6B is a plan view showing the support member 20 and floor plate 40 after the insertion process. Fig. 6C is a plan view showing the support member 20 and floor plate 40 after the extraction process. Fig. 6D is a perspective view showing the state of work in the lifting process. Fig. 8 is an enlarged cross-sectional view showing a state in which a pin 80 is inserted instead of a bolt 7 into a through hole 8 penetrating the support member 20 and floor plate 40 of the jinba scaffolding 1.

[0041] The scaffolding dismantling method of the present embodiment includes an inserting process, a connecting process, a removing process, a lifting process, and a taking-out process, and the dismantling work of the jinba scaffolding 1 is performed in this order. The floor boards 40 are removed from the support members 20 one by one.

[0042] First, the process of removing one floor plate 40 from the support member 20, i.e., the flow from the insertion process to the lifting process, will be described using as an example the case of removing the first floor plate 41G shown in Figures 6A to 6D from the support member 20. Note that there is no floor plate 40 at one end side in the circumferential direction C of the first floor plate 41G shown in Figures 6A to 6D (the right side of the paper in Figures 6A to 6D), and there is a first floor plate 41H to be removed after the first floor plate 41G at the other end side in the circumferential direction C (the left side of the paper in Figures 6A to 6D).

[0043] In the insertion step, the bolt 7 is removed from the through hole 8 that penetrates the support member 20 and the first floor panel 41G, and a pin 80 is inserted into this through hole 8 in place of the bolt 7, as shown in Fig. 8. The pin 80 has an elongated shape overall, and has a rod-shaped portion 81 that can be inserted into the through hole 8, and an annular portion 82 formed at one end of the rod-shaped portion 81.

[0044] The rod-shaped portion 81 has an outer diameter smaller than the diameter of the through hole 8, and its length is equal to or greater than the combined length of the thickness of the floor plate 40 and the thickness of the fixing portion 22. The ring-shaped portion 82 has an outer diameter larger than the diameter of the through hole 8, and is configured so that the pin 80 with the rod-shaped portion 81 inserted into the through hole 8 does not fall downward from the through hole 8. Unlike the bolt 7, the pin 80 is not screwed into the through hole 8, and the rod-shaped portion 81 is removably held in the through hole 8 by the ring-shaped portion 82 for use. The pin 80 restricts the horizontal movement of the floor plate 40 while being inserted into the through hole 8. By inserting the pin 80 into the through hole 8 instead of the bolt 7, the support member 20 can be prevented from coming off the floor plate 40 even if the bolt 7 is removed from the through hole 8. As a result, the worker is fixed to the support member 20 by the pin 80 instead of the bolt 7, and can stand on the stable first floor plate 41G to perform work.

[0045] As shown in Fig. 6B, in the insertion step of this embodiment, the bolts 7 are not removed from the through holes 8 on the side of the first floor plate 41H to be removed next in the first floor plate 41G, but the bolts 7 are removed from the through holes 8 on the opposite side to the first floor plate 41H in the circumferential direction C, and the pins 80 are inserted. In the example shown in Fig. 6B, the bolts 7 are removed from all the through holes 8 (four through holes 8 in Fig. 6B) formed on the opposite side to the first floor plate 41H, and the pins 80 are inserted into two of these four through holes 8.

[0046] In the connecting step, the pin 80 inserted into the through hole 8 in the inserting step is connected to the lifting tool 9. Specifically, as shown in FIG. 8, the hook 91 of the lifting tool 9 is hooked to the hooking portion 402 located near the pin 80 side. Then, the hook 91 hooked to the hooking portion 402 and the pin 80 are connected via a string-like curing material 92. For example, one end side of the curing material 92 is wound around the annular portion 82 of the pin 80, and the other end side of the curing material 92 is wound around the hook 91, thereby connecting the lifting tool 9 and the pin 80. At this time, the worker can stand on the stable first floor plate 41G whose one end side in the circumferential direction C is fixed to the support member 20 by the pin 80 and whose other end side is fixed to the support member 20 by the bolt 7, and perform the connecting step.

[0047] In the removal process, the bolt 7 is removed from the through hole 8 of the first floor plate 41G on the side of the first floor plate 41H. Specifically, a worker stands on the first floor plate 41H, which is adjacent to the first floor plate 41G and is to be removed next from the support member 20, removes the bolt 7 from the through hole 8, and hooks the hook 91 on the hook portion 402 located near the through hole 8 from which the bolt 7 was removed. The first floor plate 41H on which the worker stands during the removal process is stable because the bolt 7 has not been removed. Therefore, the worker can perform the removal process with stable feet.

[0048] In the lifting process, the lifting tool 9 is operated to lift the floorboard 40 together with the pin 80, thereby removing the floorboard 40 from the support member 20. At this time, as shown in Fig. 6D, the worker is fixed to the support member 20 via the bolt 7 and can operate the lifting tool 8 while standing on the first floorboard 41H with his / her feet stable.

[0049] The steps from the insertion step to the lifting step are also carried out for the other floor panels 40, and all floor panels 40 are removed from the support member 20. At this time, after one floor panel 40 is removed from the support member 20 in the lifting step, the insertion step is started for the floor panel 40 to be removed next from the support member 20. It is preferable that the next floor panel 40 to be removed is the floor panel 40 adjacent to the floor panel 40 currently being removed from the support member 20 (hereinafter referred to as the floor panel 40 being removed).

[0050] Here, an example of the order of removing the floorboards 40 from the support member 20 will be described with reference to Figs. 9A to 9C. Figs. 9A to 9C are diagrams for explaining the order of removing the floorboards 40 from the support member 20 in the scaffolding dismantling method. Fig. 9A is a plan view showing a state in which three first floorboards 41 have been removed. Fig. 9B is a plan view showing a state in which eight first floorboards 41 have been removed. Fig. 9C is a plan view showing a state in which one second floorboard 42 has been removed. In Figs. 9A to 9C, the first floorboard 41 and the second floorboard 42 are suffixed with alphabets in the order in which they are removed from the support member 20. In Fig. 9A, the three first floorboards 41A to 41C that have already been removed from the support member 20 are indicated by dashed lines.

[0051] In the scaffolding dismantling method of this embodiment, when the floorboards 40 of the jinba scaffolding 1 are arranged as shown in FIG. 3, the first floorboard 41 is removed and then the second floorboard 42 is removed from the support member 20.

[0052] As shown in FIG. 9A, in the scaffolding dismantling method of the present embodiment, the first floor plate 41A, which is disposed at a position facing the second floor plate 42 across the shaft member 10, is first removed. After removing the first floor plate 41A, the first floor plates 41 are sequentially removed along the circumferential direction C toward the first floor plate 41L, which faces the first floor plate 41A across the shaft member 10 and is adjacent to the second floor plate 42A. For example, as shown in FIG. 9A, the first floor plates 41 may be removed in the order of the first floor plates 41B, 41C, 41D, 41E, and 41F, which are clockwise in FIG. 9A. After removing the first floor plate 41F, the first floor plates may be removed in the order of the first floor plates 41H, 41I, 41J, and 41K, which are counterclockwise in FIG. 9A and FIG. 9B, from the first floor plate 41G, which is the farthest from the first floor plate 41L, as shown in FIG. 9B. In addition, after removing the first floor plate 41A from the support member 20, the first floor plates 41 may be removed in the following order: first floor plates 41G, 41H, 41I, 41J, 41K, 41B, 41DC, 41D, 41E, and 41F.

[0053] Next, the first floor plate 41L may be removed from the support member 20, and the second floor plate 42 may be removed toward the shaft member 10 in the order of the second floor plates 42A, 42B, 42C, 42D, 42E, and 42F, as shown in FIG. 9C. In this order, except for the second floor plate 42F, a stable floor plate 40 with the bolts 7 not removed is present in a position adjacent to the floor plate 40 being removed. The worker can stand on this floor plate 40 with the bolts 7 not removed and perform the lifting process and other operations with stable feet. When removing the second floor plate 42F, the worker can also perform the operation by standing on the shaft member 10 provided with the landing 11 or the like. Then, when removing the last floor plate 40, the worker is positioned on the shaft member 10 provided with a ladder or the like for descending to the ground, so that the worker can safely and smoothly complete the operation after removing the last floor plate 40.

[0054] In the removal process, after all the floor plates 40 fixed to the support members 20 in the state of being moved to the floor plate support position are removed from the support members 20, all the support members 20 are moved to the non-floor plate support position. Then, the batik scaffolding 1 in the state shown in FIG. 5 is removed from the opening (not shown) provided at the top of the silo 100. In this way, the batik scaffolding 1 can be easily removed from the opening of the silo 100 because the support members 20 have moved to the non-floor plate indication position along the shaft member 10 and the spread in the radial direction R is suppressed. Therefore, even if a large scaffolding is installed inside a structure such as the silo 100, the multiple support members 20 are deformed to extend in the axial direction of the silo 100 like the shaft member 10 when the scaffolding is dismantled, and are removed, so that the batik scaffolding 1 can be efficiently dismantled and removed.

[0055] The scaffolding dismantling method according to the present embodiment described above provides the following advantages.

[0056] The scaffolding dismantling method of this embodiment is a method for dismantling a jinka scaffolding 1 comprising a plurality of support members 20 and a floor board 40 that is stretched between two different support members 20 and fixed to the support members 20 via a bolt 7 that screws into a through hole 8 that passes through the floor board 40 and the support members 20, and includes an insertion process of removing the bolt 7 from the through hole 8 and inserting a pin 80 into the through hole 8 in place of the removed bolt 7, a connection process of connecting the pin 80 inserted into the through hole 8 to a lifting tool 9 that lifts the floor board 40, and a lifting process of removing the floor board 40 from the support members 20 by operating the lifting tool 9 to lift the floor board 40 together with the pin 80.

[0057] As a result, the pin 80 is inserted into the through hole 8 instead of the bolt 7 that fixed the floor plate 40 to the support member 20, so that even if the bolt 7 is removed, the floor plate 40 remains stable, and work can be performed safely while standing on the floor plate 40. In addition, since the pin is connected to the lifting tool 9, the pin 80 inserted into the through hole 8 can be removed from the support member 20 together with the floor plate 40. Therefore, there is no need to temporarily set up additional scaffolding to dismantle the scaffolding, and the scaffolding can be dismantled safely. Therefore, the scaffolding can be dismantled efficiently while ensuring safety.

[0058] In addition, in the scaffolding dismantling method of this embodiment, multiple floor panels 40 are arranged adjacent to each other, and after one floor panel 40 is removed from the support member 20 in the lifting process, the insertion process for the floor panel 40 adjacent to the one floor panel 40 is started.

[0059] As a result, a stable floor panel 40 with the bolts 7 not removed is present next to the floor panel 40 being removed, so a worker can stand on the floor panel 40 with the bolts 7 not removed to perform dismantling work.

[0060] Furthermore, in the scaffolding dismantling method according to this embodiment, each of the multiple floor panels 40 has multiple through holes 8 through which bolts 7 are inserted, and the insertion process includes a step in which the bolt 7 is not removed from the through hole 8 on the side of the floor panel 40 to be removed next in one floor panel 40, but the bolt 7 is removed from the through hole 8 on the opposite side of the floor panel 40 to be removed next and a pin 80 is inserted, and after the connection process, a removal process is included in which the bolt 7 is removed from the through hole 8 on the side of the floor panel 40 to be removed next.

[0061] This allows, for example, a worker to connect the pin 80 to the lifting tool 9 while standing on the floor board 40 being removed, at least the side of which is fixed with the bolt 7, and then stand on the floor board 40 to be removed next and remove the remaining bolt 7 of the floor board 40 being removed. This reduces the effort required for the process of removing the bolts 7 and inserting the pins 80, and allows the scaffolding to be dismantled safely and efficiently.

[0062] In addition, in the scaffolding dismantling method of this embodiment, the jinzai scaffolding 1 further comprises a rod-shaped shaft member 10 to which multiple support members 20 are connected, and is used by placing it inside the silo 100 in the construction of the hollow silo 100, and each of the multiple support members 20 of the jinzai scaffolding 1 extends in a direction perpendicular to the shaft member 10 and is movable between a floor board supporting position capable of supporting a floor board 40 and a non-floor board supporting position extending along the shaft member 10, and the scaffolding dismantling method further includes a removal process of removing all of the floor boards 40 fixed to the support members 20 when they have been moved to the floor board supporting positions, from the support members 20, moving the multiple support members 20 to the non-floor board supporting positions, and removing the shaft members 10 and the support members 20 from an opening provided at the top of the silo 100.

[0063] As a result, even if a large scaffolding is set up inside a structure such as a silo 100, the entire scaffolding can be deformed into a long and slender shape with multiple support members 20 extending along the axis member 10 when the scaffolding is dismantled, so that the scaffolding can be removed efficiently.

[0064] In addition, in the scaffolding dismantling method of this embodiment, the floor plates 40 are arranged adjacent to each other on the support member 20 when it is moved to the floor plate support position, and the multiple floor plates 40 include multiple first floor plates 41 arranged in a row along the inner surface 101 of the silo 100 on the tip 24 side of the support member 20 opposite the axial member 10, and multiple second floor plates 42 arranged in a row between the axial member 10 and the first floor plates 41 on the support member 20 in a direction perpendicular to the axial member 10, and after the multiple first floor plates 41 are removed from the support member 20, the multiple second floor plates 42 are removed from the tip 24 of the support member 20 toward the axial member 10.

[0065] As a result, after removing the floor board 40 on the inner peripheral surface 101 side of the silo 100, the worker removes the floor boards 40 in order toward the shaft member 10 that is movable in the vertical direction Y, and is positioned at the shaft member 10 when removing the last floor board 40. Therefore, the scaffolding can be removed safely and efficiently without setting up any extra scaffolding.

[0066] Although the embodiment of the present invention has been described above, the present invention is not limited to the above embodiment and can be modified as appropriate.

[0067] In the above embodiment, in the insertion process, the bolt 7 is not removed from the through hole 8 on the side of the floor board 40 to be removed next during the removal work, and the bolt 7 is removed in the extraction process. However, it is also possible to remove the bolt 7 from the through hole 8 on the side of the floor board 40 to be removed next during the insertion process without performing the extraction process, and to insert the pin 80 into the through hole 8 on the side of the floor board 40 to be removed next.

[0068] In the above embodiment, the first floor board 41 of the jinba scaffolding 1 was removed before the second floor board 42 was removed from the support member 20, but the first floor board 41 may also be removed from the support member 20 after the second floor board 42 is removed.

[0069] Also, for example, the first floor plate 41 may be removed from the first floor plate 41F adjacent to the first floor plate 41L in the circumferential direction C in the counterclockwise order in Fig. 9A or from the first floor plate 41K in the clockwise order in Fig. 9A, and after removing the first floor plate L, the second floor plate 42 may be removed from the first floor plate 41L in the order toward the shaft member 10. This allows the floor plate 40 to be removed in a single stroke, making it possible to more efficiently dismantle the scaffolding. [Explanation of symbols]

[0070] 1 Jinbasho Scaffolding 7 Volts 8 Through holes 20 Support member 40 Floorboards 80 pin

Claims

1. A method for dismantling scaffolding comprising: a plurality of support members; and a floor plate that is stretched between two different support members and fixed to the support members via a bolt that is inserted through a through hole that passes through the support member and the floor plate; an insertion step of removing a bolt from the through hole and inserting a pin into the through hole in place of the removed bolt; a connecting step of connecting the pin inserted into the through hole to a lifting tool for lifting the floor panel; a lifting process of operating the lifting tool to lift the floor panel together with the pins, thereby removing the floor panel from the support member.

2. The floor plates are arranged adjacent to each other, The scaffolding dismantling method according to claim 1 , wherein after one of the floorboards is removed from the support member in the lifting process, the insertion process is started for the floorboard adjacent to the one of the floorboards.

3. A plurality of the through holes through which bolts are inserted are formed in each of the plurality of floor plates, In the insertion step, the bolt is not removed from the through hole on the side of the floor board to be removed next in the first floor board, but the bolt is removed from the through hole on the opposite side to the floor board to be removed next and the pin is inserted; The scaffolding dismantling method according to claim 2, further comprising, after the connecting step, a removal step of removing the bolt from the through hole on the floor board to be removed next.

4. The scaffolding further includes a rod-shaped shaft member to which the plurality of support members are connected, and is used by being placed inside the structure in the construction of a hollow structure; Each of the plurality of support members of the scaffold extends in a direction perpendicular to the axis member and is movable between a floor board support position capable of supporting the floor board and a non-floor board support position extending along the axis member; The scaffolding dismantling method described in any of claims 1 to 3 further includes a removal process of moving a plurality of the support members to the non-floor board support positions after removing all of the floor boards fixed to the support members when they are moved to the floor board support positions, and removing the shaft members and the support members from openings provided at the top of the structure.

5. The floor panels are arranged adjacent to each other on the support member when the support member is moved to the floor panel support position, The plurality of floor plates include a plurality of first floor plates arranged along the inner peripheral surface of the structure on the tip side of the support member opposite to the shaft member, and a plurality of second floor plates arranged between the shaft member and the first floor plates on the support member in a direction perpendicular to the shaft member, The scaffolding dismantling method according to claim 4, wherein after removing the first floor panels from the support member, the second floor panels are removed from the tip of the support member toward the shaft member.

Citation Information

Patent Citations

  • Method for demolishing scaffold

    JP2011127377A