Apparatus and method for creating an operation plan for a battery system including a newly installed battery

The operation planning device balances battery performance by determining initial and sequential battery additions based on expected deterioration, reducing the total number of batteries required and enhancing system efficiency.

JP2024536599AActive Publication Date: 2024-10-04LG ENERGY SOLUTION LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2024523961
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Priority Date
2022-09-19
Filing Date
2023-07-13
Publication Date
2024-10-04
Estimated Expiration
2043-07-13

AI Technical Summary

Technical Problem

Existing energy storage systems face performance imbalances between old and new batteries due to performance degradation, leading to unnecessary increases in the number of new batteries required to meet discharge energy demands over time.

Method used

An operation planning device and method that determines the initial number of batteries and schedules the addition of new batteries based on expected deterioration, ensuring they operate with the same discharge time to minimize performance disparities.

Benefits of technology

Minimizes the total number of batteries needed and improves overall efficiency by balancing the performance of old and new batteries throughout the system's operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024536599000001_ABST
    Figure 2024536599000001_ABST
Patent Text Reader

Abstract

An operation planning device according to one embodiment of the present invention is a device that plans an operation plan for a battery system in which new batteries are combined with old batteries, and includes at least one processor and a memory that stores at least one instruction to be executed through the at least one processor. Here, the at least one instruction may include an instruction to derive the number of first batteries to be initially installed in the battery system based on a predetermined minimum required amount of discharge energy, and an instruction to derive operation plan information including a merging time and the number of second batteries to be sequentially merged with the first battery based on the minimum required amount of discharge energy and the predicted degree of deterioration of the first battery.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] This application claims the benefit of the filing date of Korean Patent Application No. 10-2022-0117636, filed with the Korean Intellectual Property Office on September 19, 2022, and all of the contents disclosed in the documents of that Korean patent application are incorporated herein by reference.

[0002] The present invention relates to an operation planning device and method for a battery system, and more specifically to an operation planning device and method for a battery system in which new batteries are augmented with old batteries and operated. [Background technology]

[0003] An energy storage system (ESS) is a system that connects renewable energy, batteries that store power, and existing grid power. In recent years, smart grids and renewable energy have become more widespread, and as the efficiency and stability of the power system are emphasized, the demand for energy storage systems is increasing to regulate power supply and demand and improve power quality. Depending on the purpose of use, the output and capacity of the energy storage system vary, and multiple battery systems can be connected to each other to form a large-capacity energy storage system.

[0004] In general, an energy storage system is installed in a specific area and operated for a long period of time. In order for the energy storage system to satisfy the amount of discharge energy required by a customer during the operation period, a large number of batteries more than necessary must be installed at the beginning, taking into account the deterioration of battery performance over time.

[0005] In order to solve such cost problems, an energy storage system has been proposed in which a minimum number of batteries are installed at the beginning of operation, and new batteries are added during the operation period. However, in such an energy storage system, a performance difference occurs between the existing batteries and the newly added batteries as time passes, and a problem occurs in that the new batteries follow the performance of the existing batteries. For example, if the discharge of the existing battery that has deteriorated first is completed first, the newly installed battery will end discharging even though additional discharge is possible. The problem of imbalance between the batteries becomes more serious as the operation period passes, and the number of new batteries added to meet the required amount of discharge energy may increase more than necessary. Summary of the Invention [Problem to be solved by the invention]

[0006] SUMMARY OF THE PRESENT DISCLOSURE In order to solve the above problems, an object of the present invention is to provide an operation planning device for a battery system including a newly installed battery.

[0007] Another object of the present invention to solve the above problems is to provide a method for creating an operation plan for a battery system including a newly installed battery.

[0008] Another object of the present invention to solve the above-mentioned problems is to provide a battery system including a newly installed battery that operates according to a planned operation plan. [Means for solving the problem]

[0009] In order to achieve the above-mentioned objective, an operation planning device according to one embodiment of the present invention is a device that plans an operation plan for a battery system in which new batteries are combined with old batteries, and includes at least one processor and a memory that stores at least one instruction to be executed through the at least one processor.

[0010] Here, the at least one instruction may include an instruction to derive the number of first batteries to be initially installed in the battery system based on a predetermined minimum required amount of discharge energy, and an instruction to derive operation plan information including a merging time and the number of second batteries to be sequentially merged with the first battery based on the minimum required amount of discharge energy and the predicted degree of deterioration of the first battery.

[0011] The instruction to derive the operation plan information may include an instruction to determine the number of second batteries to be merged at each merger time point based on the minimum required discharge energy amount and the discharge energy amount based on the predicted degree of deterioration of the existing batteries.

[0012] The instruction to derive the above operation plan information may include an instruction to calculate the discharge energy amount and discharge amount of the second battery for an Nth merged operation period defined as the period during which the existing battery and the second battery merged for the Nth time are both in operation.

[0013] The command to calculate the discharge energy amount and discharge amount of the second battery for the Nth combined operation period may include a command to calculate the discharge energy amount and discharge amount of the second battery having the same discharge time (back-up time) as the existing battery based on the discharge energy amount according to the predicted deterioration degree of the existing battery and a predetermined total discharge amount.

[0014] The instruction to calculate the discharge energy amount and discharge amount of the second battery for the Nth combined operation period may include an instruction to calculate the discharge energy amount and discharge amount of the second battery at the end of the Nth combined operation period based on the expected discharge energy amount of the existing battery at the end of the Nth combined operation period and a predetermined total discharge amount, so that the second battery has the same discharge time (back-up time) as the existing battery, and an instruction to determine the calculated discharge energy amount and discharge amount as the discharge energy amount and discharge amount of the second battery for the Nth combined operation period.

[0015] The at least one instruction may further include an instruction to transmit to the battery system the amount of discharge energy and the amount of discharge of the first battery and the second battery such that the first battery and the second battery operate with the same discharge time during the Nth combined operating period.

[0016] In order to achieve the above-mentioned another object, an operation plan development method according to one embodiment of the present invention is a method for developing an operation plan for a battery system in which new batteries are merged with old batteries, and can include a step of deriving the number of first batteries to be initially installed based on a predetermined minimum required discharge energy amount, and a step of deriving operation plan information including the merging time and the number of second batteries to be merged at each merging time for second batteries to be sequentially merged with the first battery based on the minimum required discharge energy amount and the predicted degree of deterioration of the first battery.

[0017] The step of deriving the operation plan information may include a step of determining the number of second batteries to be merged at each merger time point based on the minimum required discharge energy amount and the discharge energy amount based on the predicted degree of deterioration of the existing batteries.

[0018] The step of deriving the operation plan information may include a step of calculating the discharge energy amount and discharge amount of the second battery for an Nth merged operation period defined as a period during which the existing battery and the second battery merged for the Nth time are both in operation.

[0019] The step of calculating the discharge energy amount and discharge amount of the second battery for the Nth combined operation period may include a step of calculating the discharge energy amount and discharge amount of the second battery having the same discharge time (back-up time) as the existing battery based on the discharge energy amount according to the predicted deterioration degree of the existing battery and a predetermined total discharge amount.

[0020] The step of calculating the discharge energy amount and discharge amount of the second battery for the Nth combined operation period may include a step of calculating the discharge energy amount and discharge amount of the second battery at the end of the Nth combined operation period based on the expected discharge energy amount of the existing battery at the end of the Nth combined operation period and a predetermined total discharge amount, so that the second battery has the same discharge time (back-up time) as the existing battery, and a step of determining the calculated discharge energy amount and discharge amount as the discharge energy amount and discharge amount of the second battery for the Nth combined operation period.

[0021] The operation planning method may further include a step of transmitting the discharge energy amount and discharge amount of the first battery and the second battery to the battery system so that the first battery and the second battery operate with the same discharge time during the Nth combined operation period.

[0022] According to one embodiment of the present invention, a battery system in which a new battery is merged with an old battery includes a first battery that is initially installed, and a second battery that is sequentially merged with the first battery. Here, the first battery may be installed in a number determined based on a predetermined minimum required discharge energy amount, and the second batteries may be sequentially merged according to a merge time and a merge number for each merge time that are determined based on the minimum required discharge energy amount and an expected deterioration degree of the first battery.

[0023] The first battery and the second battery can be operated with respective discharge energy amounts and discharge amounts predefined to have the same discharge time.

[0024] The above-mentioned respective discharge energy amounts and discharge amounts may be determined based on a discharge energy amount according to an expected deterioration degree of the first battery and a predetermined total discharge amount. Effect of the Invention

[0025] According to the above-described embodiment of the present invention, it is possible to minimize the number of batteries installed in a battery system over the entire operating period of the battery system.

[0026] Additionally, embodiments of the present invention may minimize imbalance issues among batteries in a battery system over an entire operating period, improving overall efficiency. [Brief description of the drawings]

[0027] [Figure 1] FIG. 1 is a block diagram of an existing energy storage system. [Diagram 2] FIG. 1 is a block diagram of an energy storage system including an existing novel battery. [Diagram 3] 1 is a block diagram of a battery system according to an embodiment of the present invention. [Figure 4] FIG. 2 is a flow diagram of a method for creating an operation plan for a battery system according to an embodiment of the present invention. [Diagram 5] FIG. 2 is a flow diagram of an operation plan information derivation method according to the embodiment of the present invention. [Figure 6] and [Figure 7] 4 is an example of operation plan information according to an embodiment of the present invention. [Figure 8] 1 is an example of a battery system according to a comparative example of the present invention. [Figure 9] 1 is an example of a battery system according to an embodiment of the present invention. [Figure 10] 1 is a block diagram of an operation planning device according to an embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0028] The present invention can be modified in various ways and can have various embodiments, and specific embodiments are illustrated in the drawings and described in detail in the detailed description. This is not intended to limit the present invention to the specific embodiments. Rather, it is understood that the present invention includes all modifications, equivalents, and alternatives that fall within the spirit and technical scope of the present invention. Similar reference numerals are used for similar components while describing each drawing.

[0029] Terms such as first, second, A, B, etc. may be used to describe various components, but the components should not be limited by these terms. These terms are used only to distinguish one component from another. For example, a first component may be named a second component, and similarly, a second component may be named a first component, without departing from the scope of the invention. The term "and / or" includes a combination of multiple associated listed items or any of multiple associated listed items.

[0030] When a component is referred to as being "coupled" or "connected" to another component, it should be understood that the component may be directly coupled or connected to the other component, but there may also be other components in between. In contrast, when a component is referred to as being "directly coupled" or "directly connected" to another component, it should be understood that there are no other components in between.

[0031] The terms used in this application are merely used to describe certain embodiments and are not intended to limit the present invention. A singular expression includes a plural expression unless the context clearly indicates otherwise. In this application, the terms "include" or "have" are intended to specify the presence of a feature, number, step, operation, component, part, or combination thereof described in the specification, and are not intended to preclude the presence or additional possibility of one or more other features, numbers, steps, operations, components, parts, or combinations thereof.

[0032] Unless otherwise defined, all terms used herein, including technical or scientific terms, have the same meaning as commonly understood by a person of ordinary skill in the art to which the present invention belongs. Terms as defined in commonly used dictionaries should be interpreted as having a meaning consistent with the meaning they have in the context of the relevant art, and should not be interpreted as having an ideal or overly formal meaning unless expressly defined in this application.

[0033] Some terms used in this specification are defined as follows:

[0034] SOC (State of Charge) is the current charged state of the battery expressed as a percentage [%], and SOH (State of Health) is the current remaining state of the battery expressed as a percentage [%].

[0035] A battery rack refers to a system with a minimum single structure that can be monitored and controlled through a BMS by connecting module units set by a battery manufacturer in series / parallel, and may be composed of multiple battery modules and one BPU or protection device.

[0036] A battery bank can refer to a large-scale collection of battery rack systems consisting of multiple racks connected in parallel. The battery bank BMS can monitor and control the rack BMS (RBMS) for each battery rack.

[0037] A BSC (Battery System Controller) is a device that performs top-level control of a battery system including a battery system in units of a battery bank, and may be used as a control device in a battery system with a multiple bank level structure.

[0038] Nominal Capacity (Nominal Capa.) can refer to the set capacity [Ah] of a battery set by the battery manufacturer at the time of development.

[0039] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

[0040] FIG. 1 is a block diagram of an existing energy storage system.

[0041] The smallest unit of a battery that serves to store power in an energy storage system (ESS) is usually a battery cell. A series / parallel combination of battery cells forms a battery pack, and a number of battery packs can form a battery rack. In other words, a battery rack is a series / parallel combination of battery packs and can be the smallest unit of a battery system. Here, a battery pack can be called a battery module depending on the device or system in which the battery is used.

[0042] 1, one battery rack 10 may include a plurality of battery modules and one BPU or protection device. The battery rack can be monitored and controlled through a Rack BMS (RBMS). The RBMS can monitor the current, voltage, and temperature of each battery rack it manages, calculate the SOC (Status Of Charge) of the battery based on the monitoring results, and control charging and discharging.

[0043] Meanwhile, a Battery Protection Unit (BPU) is a device for protecting batteries from abnormal current and fault current in battery rack units. The BPU may include a main contactor (MC), fuses, circuit breakers (CB), or disconnect switches (DS), etc. The BPU can control the battery system in rack units by controlling the main contactors to turn on / off under the control of the RBMS. The BPU can also protect the batteries from short circuit current using fuses when a short circuit occurs. In this way, existing battery systems may be controlled through protection devices such as a BPU and switchgear.

[0044] Meanwhile, a battery system controller (BSC) 20 is provided in each battery section including a number of batteries and peripheral circuits and devices, and is capable of monitoring and controlling control targets such as voltage, current, temperature, and circuit breakers. The BSC is the highest-level control device of a battery system including a bank-based battery system including a number of battery racks, and may also be used as a control device in a battery system with a multiple bank-level structure.

[0045] In addition, a power conversion system (PCS) 40 provided for each battery section is a device that performs substantial charging and discharging based on a charge / discharge command from the EMS 30, and may include a power conversion unit (DC / AC inverter) and a controller. Meanwhile, the output of each BPU may be connected to a power generation device (e.g., a solar power generation device) and the PCS 40 via a DC bus, and the PCS 40 may be connected to a grid. In addition, the EMS (Energy Management System) 30 or a PMS (Power Management System) manages the ESS system as a whole.

[0046] In a conventional energy storage system as shown in Figure 1, multiple battery racks act as a voltage source, and the PCS charges and discharges the battery racks through CC (Constant Current) control or CP (Constant Power) control. When the battery racks are initially installed, their performance is almost similar (when expressed as equivalent resistance, similar resistance values ​​appear), and the charge and discharge current of each rack appears at a similar level. However, as time passes, the performance of some racks may deteriorate. In this case, new racks are added to compensate for the performance, which is called augmentation.

[0047] FIG. 2 is a block diagram of an energy storage system including an existing novel battery.

[0048] FIG. 2 shows an energy storage system (for example, the energy storage system shown in FIG. 1) including existing battery racks 10 (Old Racks) that are augmented with multiple new battery racks 10' (New Racks).

[0049] The new battery rack 10' may be electrically connected to the existing battery rack 10 and may be controlled for charging and discharging together with the existing battery rack 10 by the control device of the energy storage system. At this time, there may be a performance difference between the new battery rack 10' and the existing battery rack 10, which may cause a problem that the new battery rack 10' follows the deteriorated performance of the existing battery rack 10. In other words, even though a new rack has been added, it becomes impossible to fully utilize the maximum performance (e.g., rated capacity, usage period, etc.) possessed by the new rack.

[0050] This imbalance problem between battery racks becomes more serious as the operating period progresses, and new battery racks must be added to meet the required amount of discharge energy, which may result in an unnecessarily large number of battery racks being installed in the energy storage system over the entire operating period.

[0051] The present invention has been devised to solve the problems that arise in such existing energy storage systems, and proposes a method for minimizing the number of batteries installed in the battery system over the entire operating period of the energy storage system, while minimizing imbalance problems between new batteries and existing batteries, thereby improving power efficiency.

[0052] Hereinafter, with reference to Figs. 3 to 10, methods of a battery system operation planning device according to various embodiments of the present invention and a battery system that operates according to the created operation plan information will be described.

[0053] FIG. 3 is a block diagram of a battery system according to an embodiment of the present invention.

[0054] 3, a battery system according to an embodiment of the present invention includes a plurality of batteries and may be located in the energy storage system shown in FIG 1 or 2. Meanwhile, in the present invention, "battery" may refer to a battery cell, a battery module, a battery rack, or a battery bank.

[0055] The battery system includes an initially installed battery 100 (first battery) and a battery 200 (second battery) that is combined during the operation of the battery system.

[0056] Here, the second battery 200 may be sequentially combined with the first battery 100 in N-th order. Referring to FIG 3, the second battery 200 may include a first combined battery 200-1 to an N-th combined battery 200-N, which are sequentially combined from the first to the N-th order.

[0057] The battery system can be operated based on operation plan information derived by an operation plan creation device described later. The operation plan information according to the embodiment of the present invention can include the installed quantity of the first battery, the merging time of the second battery, the merging quantity of the second battery for each merging time, and the discharge energy amount (Wh) and discharge amount (W) of the first and second batteries for each operation section.

[0058] The number of first batteries to be installed, that is, the number of batteries to be initially installed in the battery system, may be determined based on a predetermined minimum required amount of discharge energy (eg, the amount of discharge energy required by a customer).

[0059] Also, the time point at which the second batteries are combined and the number of second batteries to be combined at each of the time points may be determined based on the minimum required discharge energy amount and the expected degree of deterioration of the batteries.

[0060] Also, the discharge energy amount and discharge amount of the first and second batteries can be defined for each N-th merged operation period, and may be determined as values ​​such that the first and second batteries have the same discharge time in each N-th merged operation period. Here, the N-th merged operation period means a period during which the existing battery and the second battery merged for the Nth time operate together. For example, the first merged operation period is a period during which the first battery 100 and the first merged battery 200-1 operate together, the second merged operation period is a period during which the first battery 100, the first merged battery 200-1, and the second merged battery 200-2 operate together, and the N-th merged operation period means a period during which the first battery 100 and the first to N-th merged batteries 200-1 to 200-N operate together.

[0061] In the battery system, the first battery may be installed and operated according to the number of initially installed batteries included in the operation plan information, and the second batteries 200-1 to 200-N may be sequentially merged according to the Nth merge time and merge quantity included in the operation plan information. Thereafter, during the Nth merge operation period, the first and second batteries may be controlled according to the discharge energy amount and discharge amount for each operation period included in the operation plan information. Here, the discharge energy amount and discharge amount included in the operation plan information are values ​​derived in advance so that the first battery and the second battery have the same discharge time in each operation period, and therefore, the performance imbalance phenomenon of the first battery and the second battery during the merge operation period may be minimized.

[0062] FIG. 4 is a flow diagram of a method for creating an operation plan for a battery system according to an embodiment of the present invention.

[0063] The operation planning device can determine the number of first batteries to be initially installed in the battery system (S410). Here, the operation planning device can determine the number of first batteries based on a predetermined minimum required discharge energy amount. For example, if the minimum required discharge energy amount is set to 1000 [MWh] and each battery rack has a capacity of 335 [KWh], the number of first batteries may be determined to be 3420 so as to satisfy the minimum required discharge energy amount during the initial operation period (period of operation using only the first batteries).

[0064] In an embodiment, the operation planning device may determine the number of first batteries in consideration of the minimum required discharge energy amount and the expected deterioration degree of the first batteries. For example, the number of first batteries may be determined as the minimum value of a natural number exceeding (minimum required discharge energy amount / discharge energy amount per battery)*a, where a may be defined as a specific value between 1.1 and 1.2. That is, in consideration of deterioration of the first batteries that progresses during an initial operation period (e.g., 5 years), the number of first batteries may be determined as a quantity that allows the first batteries to discharge more than the minimum required discharge energy amount even at the end of the initial operation period (e.g., after 5 years have passed).

[0065] The operation planning device may determine the merging time of the second battery to be sequentially merged with the first battery and the number of the second batteries to be merged at each merging time (S420). Here, the operation planning device may determine the merging time of the second battery and the number of the second batteries to be merged at each merging time based on the minimum required discharge energy amount and the expected deterioration degree of the first battery.

[0066] FIG. 6 is an example of operation plan information according to an embodiment of the present invention. Referring to FIG. 6, the operation plan planning device can calculate the expected discharge energy amount (1145.284, 1144.138, ..., 789.100) of the first battery (initial installation battery) for each unit period (year) of a predetermined total operation period (20 years). Here, the expected discharge energy amount may be calculated based on the capacity (335 KWh) of each of the first batteries, the total number of the first batteries (3420 pieces), and the expected deterioration degree of the first batteries that is defined in advance. The expected deterioration degree may be experimentally derived in advance or may be derived in advance using a deterioration model and stored in a storage device.

[0067] As shown in FIG. 6, the operation planning device can determine the point in time (the sixth year) when the predicted discharge energy amount of the first battery becomes less than the minimum required discharge energy amount (1000 MHh) as the first combination point in time.

[0068] The operation planning device may determine the number of first combined batteries to be combined at the first combination time. Here, the operation planning device may determine the number of first combined batteries based on the minimum required discharge energy amount and the expected discharge energy amount according to the expected deterioration degree of the battery. Referring to FIG. 6, the first combined operation period may be predefined as 5 years, and in this case, the operation planning device may determine the number of second batteries (270) such that the expected total discharge energy amount at the end of the first combined operation period (10th year) exceeds the minimum required discharge energy amount (1000 [MHh]).

[0069] Thereafter, the operation planning device can determine the number of Nth-order merged batteries to be merged at the Nth-order merge point in the above-described manner. In the example shown in Fig. 6, it can be confirmed that the first merge point is the 6th year, the first merged number is determined to be 270, the second merge point is the 11th year, the second merged number is determined to be 270, and the third merge point is the 16th year, the third merged number is determined to be 235.

[0070] The operation planning device can generate operation plan information including the number of first batteries determined in steps S410 and S420, the merging times of the second batteries (1st to Nth merging times), and the merging quantities of the second batteries for each merging time (S430).

[0071] The operation plan development device can transmit the generated operation plan information to an administrator terminal so that the battery system can be initially designed and operated based on the operation plan information.

[0072] Fig. 5 is a flow diagram of an operation plan information deriving method according to an embodiment of the present invention. Hereinafter, a method of calculating the discharge energy amount (Wh) and the discharge amount (W) of the first and second batteries for each of the Nth combined operation sections will be specifically described with reference to Fig. 5.

[0073] The operation planning device can confirm the Nth merged operation period (S510). Specifically, the operation planning device can confirm the merged operation period for each order set in advance. For example, the first merged operation period to the Nth merged operation period may be set to 5 years, as shown in FIG. 6.

[0074] Here, the operation planning device can determine the Nth merge time point based on the Nth merge operation period. For example, the merge time points by order may be determined as the 6th year (first merge time point), the 11th year (second merge time point), and the 16th year (third merge time point), as shown in FIG. 6.

[0075] The operation planning device can calculate the number of merged batteries at the Nth merge time (S520). Here, the operation planning device can determine the number of merged batteries based on the minimum required discharge energy amount and the expected discharge energy amount according to the expected deterioration degree of the existing batteries.

[0076] The operation planning device can calculate the discharge energy amount and discharge amount of the first and second batteries for the Nth combined operation period (S530). Here, the operation planning device can calculate the discharge energy amount and discharge amount of the first and second batteries such that the first and second batteries have the same discharge time based on the expected discharge energy amount of the existing battery and a predetermined total discharge amount.

[0077] In an embodiment, the operation planning device can calculate the discharge energy amount and the discharge amount of the first and second batteries for the Nth combined operation period based on the following Equation 1: [Formula 1] (E_(n-1) / T_backup) + (E_(n) / T_backup) = P_total Here, E_(n-1) is the expected discharge energy amount of the existing battery at the end of the Nth combined operation period, E_(n) is the discharge energy amount of the Nth combined battery at the end of the Nth combined operation period, T_backup is the discharge time, and P_total is the total discharge amount.

[0078] The operation planning device can derive the discharge energy amount (E_(n)) and discharge time (T_backup) of the Nth combined battery that satisfy the condition that the total discharge energy amount in the Nth combined operation period exceeds the minimum required discharge energy amount based on the above formula 1. The operation planning device can use the derived values ​​to calculate the discharge energy amount and discharge amount of the first and second batteries for the Nth combined operation period.

[0079] 7 is an example of operation plan information according to an embodiment of the present invention. Referring to FIG. 7, the total discharge amount in all combined operation sections may be preset to 300 [MW]. The number of primary combined cells may be determined to be 270, as described with reference to FIG. 4 and FIG. 6.

[0080] The operation planning device can calculate the discharge energy amount and discharge amount of the first and second batteries for the first combined operation period based on the above formula 1. (E_(0) / T_backup) + (E_(1) / T_backup) = P_total Here, E_(0) is 925.389 [MWh], which is the expected discharge energy amount of the existing battery (i.e., the initially installed battery) at the end of the first combined operation period, and P_total is 300 [MW].

[0081] The operation planning device derives the discharge energy amount (E_(1)) and discharge time (T_backup) of the primary combined battery that satisfy the condition that the total discharge energy amount (the sum of the discharge energy amounts of the initially installed battery and the primary combined battery) during the primary combined operation period exceeds the minimum required discharge energy amount (1000 [MWh]) as values ​​that satisfy the above formula 1. Here, the operation planning device repeats the process of substituting E_(1) and T_backup into the above formula 1 and the conditions while changing them, and can end the calculation process when values ​​that satisfy the formula 1 and the conditions are derived.

[0082] 6 and 7, it can be seen that the discharge energy amount (E_(1)) of the primary combined battery was derived to be 80.923 [MWh] and the discharge time (T_backup) was derived to be 3.35 [hr] through the above calculation process.

[0083] The operation planning device can use the derived values ​​to calculate the discharge amount of the first battery (275.87537 [MW]) (E_(0) / T_backup) and the discharge amount of the primary combined battery (24.12463 [MW]) (E_(1) / T_backup).

[0084] Thereafter, the operation planning device can calculate the discharge energy amount and discharge amount of the first battery (initially installed battery) and the second battery (combined 1st to 3rd battery) for the combined 2nd and 3rd operation periods using the method described above (see FIG. 7).

[0085] The operation plan creation device generates operation plan information including the discharge energy amount and discharge amount of the first and second batteries for each of the 1st to Nth combined operation periods, and transmits the information to the control device of the battery system so that the battery system operates according to the operation plan information. As a result, the battery system is controlled so that the old battery and the new battery have the same discharge time during all combined operation periods, thereby minimizing the performance imbalance phenomenon between the batteries and improving power efficiency.

[0086] FIG. 8 is an example of a battery system according to a comparative example of the present invention, and FIG. 9 is an example of a battery system according to an embodiment of the present invention.

[0087] The battery system in Fig. 8 is a battery system that operates only with the initially installed batteries without incorporating new batteries. In the battery system according to the comparative example, 4500 battery racks, each with a capacity of 335 [KWh], must be initially installed to satisfy the minimum required discharge energy amount (1000 [MHh]) per unit period during the total operating period (20 years).

[0088] In contrast, the battery system according to the embodiment of the present invention shown in Figure 9 operates with 3,420 battery racks during the initial operating period, making it possible to design an initial system with a number of battery racks that is 24% lower than the comparative example.

[0089] In addition, the battery system according to the embodiment of the present invention is installed and operated in succession with 270 battery racks in the 6th year, 270 in the 11th year, and 235 in the 16th year, resulting in a total of 4,195 battery racks being installed during the total operating period, making it possible to operate with a number of battery racks that is 6.7% lower than the comparative example.

[0090] FIG. 10 is a block diagram of an operation planning device according to an embodiment of the present invention.

[0091] The operation planning device 1000 according to an embodiment of the present invention may include at least one processor 1010, a memory 1020 for storing at least one instruction executed through the processor, and a transceiver device 1030 connected to a network for communication.

[0092] The at least one instruction executed by the at least one processor may include an instruction to derive the number of first batteries to be initially installed in the battery system based on a predetermined minimum required amount of discharge energy, and an instruction to derive operation plan information including a merging time and a number of merging times for second batteries to be sequentially merged with the first battery based on the minimum required amount of discharge energy and an expected degree of deterioration of the first battery.

[0093] The instruction to derive the operation plan information may include an instruction to determine the number of second batteries to be merged at each merger time point based on the minimum required discharge energy amount and the discharge energy amount based on the predicted degree of deterioration of the existing batteries.

[0094] The instruction to derive the above operation plan information may include an instruction to calculate the discharge energy amount and discharge amount of the second battery for an Nth merged operation period defined as the period during which the existing battery and the second battery merged for the Nth time are both in operation.

[0095] The command to calculate the discharge energy amount and discharge amount of the second battery for the Nth combined operation period may include a command to calculate the discharge energy amount and discharge amount of the second battery having the same discharge time (back-up time) as the existing battery based on the discharge energy amount according to the predicted deterioration degree of the existing battery and a predetermined total discharge amount.

[0096] The instruction to calculate the discharge energy amount and discharge amount of the second battery for the Nth combined operation period may include an instruction to calculate the discharge energy amount and discharge amount of the second battery at the end of the Nth combined operation period based on the expected discharge energy amount of the existing battery at the end of the Nth combined operation period and a predetermined total discharge amount, so that the second battery has the same discharge time (back-up time) as the existing battery, and an instruction to determine the calculated discharge energy amount and discharge amount as the discharge energy amount and discharge amount of the second battery for the Nth combined operation period.

[0097] The at least one instruction may further include an instruction to transmit to the battery system the amount of discharge energy and the amount of discharge of the first battery and the second battery such that the first battery and the second battery operate with the same discharge time during the Nth combined operating period.

[0098] The operation planning device 1000 may further include an input interface device 1040, an output interface device 1050, a storage device 1060, etc. The components included in the operation planning device 1000 are connected by a bus 1070 and can communicate with each other.

[0099] Here, the processor 1010 may refer to a central processing unit (CPU), a graphics processing unit (GPU), or a dedicated processor on which the method according to the embodiment of the present invention is performed. The memory (or storage device) may be composed of at least one of a volatile storage medium and a non-volatile storage medium. For example, the memory may be composed of at least one of a read only memory (ROM) and a random access memory (RAM).

[0100] The operation of the method according to the embodiment of the present invention can be embodied as a computer readable program or code in a computer readable recording medium. The computer readable recording medium includes all kinds of recording devices in which data that can be read by a computer system is stored. In addition, the computer readable recording medium may be distributed to computer systems connected via a network, so that the computer readable program or code may be stored and executed in a distributed manner.

[0101] Some aspects of the invention have been described in the context of an apparatus, but it may also be presented in terms of a corresponding method, where a block or apparatus corresponds to a method step or a feature of a method step. Similarly, aspects described in the context of a method may be presented in terms of a corresponding block or item or feature of a corresponding apparatus. Some or all of the method steps may be performed by (or using) a hardware apparatus, such as, for example, a microprocessor, a programmable computer, or an electronic circuit. In some embodiments, one or more of the most important method steps may be performed by such an apparatus.

[0102] Although the present invention has been described with reference to preferred embodiments thereof, those skilled in the art will understand that various modifications and variations of the present invention can be made without departing from the spirit and scope of the present invention as set forth in the following claims. [Explanation of symbols]

[0103] 100: First battery (initial battery) 200: Second battery (combined battery) 200-N: Nth-order combined battery 1000: Operational planning device

Claims

1. An apparatus for creating an operation plan for a battery system in which new batteries are combined with old batteries, At least one processor; and a memory for storing at least one instruction to be executed by the at least one processor; The at least one instruction: instructions for deriving a number of first batteries to be initially installed in the battery system based on a predetermined minimum required amount of discharge energy; and An operation planning device for a battery system, comprising: an instruction to derive operation plan information including a merger time and a merger number for each merger time for a second battery that is sequentially merged into the first battery based on the minimum required discharge energy amount and the predicted degree of deterioration of the first battery.

2. The command to derive the operation plan information is The battery system operation planning device of claim 1, further comprising an instruction to determine the number of second batteries to be merged at each merger time point based on the minimum required discharge energy amount and the discharge energy amount based on the predicted degree of deterioration of the existing batteries.

3. The command to derive the operation plan information is The battery system operation planning device of claim 1, further comprising an instruction to calculate the discharge energy amount and discharge amount of the second battery during an Nth merged operation period defined as the period during which the existing battery and the second battery merged for the Nth time are both in operation.

4. The instruction to calculate the discharge energy amount and the discharge amount of the second battery for the Nth combined operation period is:

4. The battery system operation planning device of claim 3, further comprising an instruction to calculate the discharge energy amount and discharge amount of the second battery so as to have the same discharge time (back-up time) as the existing battery based on the discharge energy amount based on the predicted deterioration degree of the existing battery and a predetermined total discharge amount.

5. The instruction to calculate the discharge energy amount and the discharge amount of the second battery for the Nth combined operation period is: A command to calculate the discharge energy amount and discharge amount of the second battery at the end of the Nth combined operation period based on the expected discharge energy amount of the existing battery at the end of the Nth combined operation period and a predetermined total discharge amount, so that the second battery has the same discharge time (Back-up time) as the existing battery; and The battery system operation planning device according to claim 4 , further comprising an instruction to determine the calculated discharge energy amount and discharge amount as the discharge energy amount and discharge amount of the second battery for the Nth combined operation period.

6. The battery system operation planning device of claim 4, further comprising an instruction to transmit to the battery system the discharge energy amount and discharge amount of the first battery and the second battery so that the first battery and the second battery operate with the same discharge time during the Nth combined operation period.

7. A method for creating an operation plan for a battery system in which new batteries are combined with old batteries, comprising: Deriving the number of first batteries to be initially installed based on a predetermined minimum required amount of discharge energy; and A method for developing an operation plan for a battery system, comprising: a step of deriving operation plan information for a second battery that is sequentially merged with the first battery, the operation plan information including a merger time and a merger number for each merger time, based on the minimum required discharge energy amount and the predicted degree of deterioration of the first battery.

8. The step of deriving operation plan information includes: The method for developing an operation plan for a battery system as described in claim 7, further comprising a step of determining the number of second batteries to be combined at each combination time point based on the minimum required discharge energy amount and the discharge energy amount due to the predicted degree of deterioration of the existing batteries.

9. The step of deriving operation plan information includes: The method for developing an operation plan for a battery system as described in claim 7, further comprising a step of calculating the discharge energy amount and discharge amount of the second battery during an Nth merged operation period defined as the period during which the existing battery and the second battery merged for the Nth time are both in operation.

10. The step of calculating the discharge energy amount and the discharge amount of the second battery for the Nth combined operation period includes:

10. The method for developing an operation plan for a battery system according to claim 9, further comprising a step of calculating the discharge energy amount and discharge amount of the second battery so as to have the same discharge time (back-up time) as the existing battery based on the discharge energy amount according to the predicted deterioration degree of the existing battery and a predetermined total discharge amount.

11. The step of calculating the discharge energy amount and the discharge amount of the second battery for the Nth combined operation period includes: A step of calculating the discharge energy amount and discharge amount of the second battery at the end of the Nth combined operation period based on the expected discharge energy amount of the existing battery at the end of the Nth combined operation period and a predetermined total discharge amount, the second battery having the same discharge time (Back-up time) as the existing battery; and The method for creating an operation plan for a battery system according to claim 10, further comprising a step of determining the calculated discharge energy amount and discharge amount as the discharge energy amount and discharge amount of the second battery for the Nth combined operation period.

12. 11. The method of claim 10, further comprising the step of transmitting the discharge energy amount and discharge amount of the first battery and the second battery to the battery system such that the first battery and the second battery operate with the same discharge time during the Nth combined operating period.

13. A battery system in which a new battery is combined with an old battery, an initially installed first battery; and a second battery that is sequentially merged with the first battery; The first batteries are installed in a number determined based on a predetermined minimum required discharge energy amount, The second batteries are sequentially merged according to a merge time and a merge number for each merge time determined based on the minimum required discharge energy amount and an expected deterioration degree of the first batteries.

14. The first battery and the second battery are 14. The battery system of claim 13, which operates with respective discharge energy amounts and discharge amounts predefined to have the same discharge time.

15. The respective discharge energy amounts and discharge amounts are The battery system according to claim 14 , wherein the amount of discharged energy according to an expected deterioration level of the first battery is determined based on a predetermined total discharge amount.

Citation Information

Patent Citations

  • Secondary battery system comprising a plurality of batteries and distribution method for charge / discharge power and the like

    JP2014171335A

  • Operation simulation device, operation simulation system, simulation method for storage battery facility for power generator and program

    JP2016208771A

  • Battery management system and method controlling battery

    KR1020170062132A

  • Method for controlling secondary cell and power storage device

    WO2011052314A1

  • Back-up power supply system and back-up battery rack for data center

    WO2019207852A1