Method for lifting and docking a nacelle when deploying an offshore wind turbine using a floating vessel

The method improves nacelle-tower docking precision and reduces costs by using a crane and positioning device with hand chain hoists and locating pins, addressing the challenges of offshore wind turbine deployment with floating vessels.

JP2024543366AActive Publication Date: 2024-11-21JIANGSU HENGTONG LAND OCEAN ENG CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2024527286
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Priority Date
2021-11-11
Filing Date
2022-03-25
Publication Date
2024-11-21
Estimated Expiration
2042-03-25

AI Technical Summary

Technical Problem

The challenge of securely docking a nacelle to a tower during offshore wind turbine deployment using a floating vessel is exacerbated by external environmental loads, leading to potential damage and increased costs and construction times with existing methods, particularly when using jack-up or floor-mounted platforms.

Method used

A method involving a crane with a spreader and a docking and positioning device, utilizing hand chain hoists and locating pins to align and connect nacelle and tower flange holes, ensuring precise alignment and secure docking without the need for expensive platforms.

Benefits of technology

Enhances docking certainty and reduces costs and construction times by allowing secure nacelle-tower connection using a floating vessel, avoiding the limitations of traditional platforms.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024543366000001_ABST
    Figure 2024543366000001_ABST
Patent Text Reader

Abstract

The present invention provides a method for lifting and docking a nacelle when a floating ship is used to deploy an offshore wind turbine, which can solve the problem of not being able to reliably dock the nacelle and tower when a floating ship is used to deploy an offshore wind turbine, and solves the problem of high cost and long construction period caused by using a jack-up offshore platform or a fixed-bottom offshore platform to deploy a large-scale offshore wind turbine. A crane is provided on the deck platform of the floating ship, and the crane uses a spreader to lift the nacelle, on which the docking and positioning device is previously installed, to a predetermined distance above the tower, and then connects the docking and positioning device to the tower via a hand chain hoist, manually operates the hand chain hoist to align the flange holes of the nacelle flange and the tower flange, and operates the crane to lower the nacelle to the nacelle flange hole and place it in place, and inserts the connecting bolt into the tower flange hole that corresponds to the one-to-one correspondence, and finally removes the docking and positioning device and the hand chain hoist, thus completing the docking operation of the nacelle and the tower.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to the technical field of offshore wind turbine deployment, in particular to the field of docking and deployment of a nacelle and tower of an offshore wind turbine, specifically to a method for lifting and docking a nacelle during deployment of an offshore wind turbine using a floating vessel. [Background technology]

[0002] The docking operation between the nacelle and the tower is an important step in the wind turbine deployment process. It is common to use a large lifting device to first lift the nacelle to the top of the tower, then connect the bottom flange of the nacelle to the top flange of the tower, and then connect and deploy it with bolts. In the deployment of offshore wind turbines, due to the severe impact of the external environmental loads on the ocean, the crane jib of the floating ship swings greatly when deploying the offshore wind turbine using a floating ship, causing the nacelle lifted by the jib hook to swing greatly, making it difficult to securely dock it to the tower of the wind turbine. If the docking is forced, the swinging nacelle and the tower are likely to collide, and in the case of a light case, the bolts that dock the two may bend, and in the case of a serious case, the nacelle may be damaged. For this reason, in most of the current deployment of offshore wind turbines, a jack-up offshore platform or a fixed-bottom offshore platform is used to lift the nacelle and dock it with the tower. However, jack-up or fixed-bottom offshore platforms are themselves expensive and have low maneuverability, and are not particularly satisfactory for deploying large offshore wind turbines due to the high cost and long construction period. Summary of the Invention [Problem to be solved by the invention]

[0003] In response to the above problems, the present invention provides a method for lifting and docking a nacelle when deploying an offshore wind turbine using a floating ship, which can solve the problem of not being able to reliably dock the nacelle and tower when deploying an offshore wind turbine using a floating ship, and resolves the problems of high costs and long construction periods associated with deploying a large-scale offshore wind turbine using a jack-up offshore platform or a fixed-bottom offshore platform. [Means for solving the problem]

[0004] The technical form is as follows: A crane is provided on the deck platform of a floating ship, a spreader for lifting a nacelle is provided on the main lifting jib of the crane, a nacelle flange and a tower flange are provided on the bottom surface of the nacelle and the top surface of the tower of the offshore wind turbine, respectively, the nacelle flange holes and the tower flange holes are opened evenly in the circumferential direction, respectively, and the nacelle flange holes and the tower flange holes correspond one-to-one to each other, in this method of lifting and docking a nacelle when disposing the offshore wind turbine using a floating ship, the method comprising the steps of: using a crane to lift the nacelle with the spreader; The docking and positioning device is mounted on the nacelle and is lifted up to a predetermined distance above the tower. The docking and positioning device is then connected to the tower via a hand chain hoist. The hand chain hoist is manually operated to align the flange holes of the nacelle flange and the tower flange, and the crane is operated to lower the nacelle to the nacelle flange hole and place it there. The connecting bolts are inserted into the one-to-one corresponding tower flange holes. Finally, the docking and positioning device and the hand chain hoist are removed, thus completing the docking operation between the nacelle and the tower.

[0005] Further, the docking and positioning device includes a positioning pin and a lifting plate attached to a center position of the bottom of the nacelle, and four lifting lugs arranged in a cross shape are provided on the bottom of the lifting plate, the four lifting lugs are a first lifting lug, a second lifting lug, a third lifting lug and a fourth lifting lug, respectively; the length of the positioning pin is longer than the length of the connecting bolt; before lifting the nacelle, three of the nacelle flange holes are selected as positioning pin holes, and the three positioning pin holes are inserted into the positioning pin holes. The locating pins are provided, and connecting bolts are provided for all remaining nacelle flange holes, the three locating pin holes are respectively a first locating pin hole, a second locating pin hole, and a third locating pin hole, the first locating pin hole and the second locating pin hole are aligned with the center of the bottom of the nacelle, and four of the tower flange holes are towing holes, respectively, the first locating pin hole, the second locating pin hole, the third locating pin hole, and the fourth locating pin hole, the first locating pin hole corresponds to the first locating pin hole, the second locating pin hole corresponds to the second locating pin hole, and the tower flange corresponding to the third locating pin hole is provided with a connecting bolt. Any tower flange hole between the flange hole and the first towing hole, any tower flange hole between the second towing hole are the third towing hole and the fourth towing hole, and the crane lifts the nacelle with the above-mentioned docking and positioning device arranged thereon to a predetermined distance above the tower, and then, using four hand chain hoists, connect the hanger hook ends on one side of the four hand chain hoists to the four lifting lugs respectively, and connect the hanger hook ends on the other side of the four hand chain hoists to the first towing hole, the second towing hole, the third towing hole and the fourth towing hole respectively via slings, and then, while manually operating the four hand chain hoists, lower the nacelle by the crane, and respectively insert the positioning pins in the three positioning pin holes into the corresponding tower flange holes of the tower to perform initial alignment between the nacelle and the tower, and then, further lower the nacelle by the crane until the connecting bolts in the remaining nacelle flange holes all extend into the corresponding tower flange holes one-to-one, and finally, remove the four hand chain hoists and the three positioning pins, and respectively install the connecting bolts in the three positioning pins.

[0006] Further, the positioning pins include a first positioning pin and a second positioning pin, the length of the first positioning pin is longer than the length of the second positioning pin, and the length of the second positioning pin is longer than the length of the connecting bolt, two second positioning pins are provided, the two second positioning pins are respectively mounted in the first positioning pin hole and the second positioning pin hole, the first positioning pin is mounted in the third positioning pin hole, and the four hand chain hoists are respectively a first hand chain hoist, a second hand chain hoist, a third hand chain hoist, a fourth hand chain hoist, a fifth hand chain hoist, a sixth hand chain hoist, a seventh hand chain hoist, a eighth ... The first hand chain hoist has a hanger hook end on one side connected to the first lifting lug and a hanger hook end on the other side connected to a first towing hole via a sling, the second hand chain hoist has a hanger hook end on one side connected to the second lifting lug and a hanger hook end on the other side connected to a second towing hole via a sling, and the third hand chain hoist has a hanger hook end on one side connected to the fourth lifting lug and a hanger hook end on the other side connected to a second towing hole via a sling. and connected to the third towing hole, and the fourth hand chain hoist has one side hanger hook end connected to the third lifting lug and the other side hanger hook end connected to the fourth towing hole through a sling; when installing the four hand chain hoists, the lengths of the hoists need to be adjusted simultaneously so that none of the four hand chain hoists properly installed will be subjected to force; then, while manually tightening the third hand chain hoist and the fourth hand chain hoist respectively, the nacelle is slowly lowered by the crane, and while adjusting the position of the first positioning pin, the first positioning pin is slowly put into the corresponding tower flange hole; then, while tightening the third hand chain hoist and the fourth hand chain hoist respectively, the positions of the two second positioning pins are adjusted by manually adjusting the first hand chain hoist and the second hand chain hoist respectively; at the same time, the nacelle is slowly lowered by the crane until the two second positioning pins are extended to align with the first towing hole and the second towing hole respectively, thereby completing the initial positioning of the nacelle and the tower.

[0007] Furthermore, the third positioning pin hole is located on a perpendicular bisector connecting the first positioning pin hole and the second positioning pin hole, and the tower flange hole corresponding to the third positioning pin hole forms an angle of 45° radially with both the third traction hole and the fourth traction hole.

[0008] Furthermore, each of the three positioning pins includes a pin body, a threaded end, a positioning end, and a positioning guide portion, one end of the pin body is the threaded end that fits into the nacelle flange hole, and the other end is integrally connected to the positioning end by the positioning guide portion, the positioning guide portion is a tapered cone extending from the threaded end toward the positioning end, and the positioning end is a regular rectangle.

[0009] Furthermore, the length of the hand chain hoist is calculated from the current roll angle and pitch angle of the floating ship before hoisting the nacelle by calculating the roll and pitch of the floating ship by: roll=roll angle x height of suspended object x π / 180, pitch=pitch angle x height of suspended object x π / 180. CAD lofting is performed from the calculated roll and pitch, and a margin of 0.5m to 1m is left based on the CAD lofting size to obtain the length of the hand chain hoist.

[0010] Furthermore, the force bearing capacity of the hand chain hoist is calculated by superimposing the lateral and vertical swaying calculated above to obtain the overall swaying, and then hoist force bearing capacity = [nacelle weight x (twice the overall swaying capacity) / distance of suspended object from boom top] x maximum length of hand chain hoist / horizontal distance from the towing hole of lifting lug.

[0011] Furthermore, before the nacelle lifting and docking operations are performed by a crane, it is necessary to observe and determine whether the weather, sea conditions and ship conditions at the construction site meet the specified lifting requirements.

[0012] Furthermore, before performing the nacelle lifting and docking operations by crane, observe and update the weather forecast for the construction site within the next 12 hours, and ensure that within 9 hours after the completion of the lifting of the wind turbine tower, the wind speed is less than 8 meters / second, there is no rainfall, the swell height is less than 0.5 meters, and both the roll angle and pitch angle of the floating vessel are maintained at 0.2°, and the inclination angle and trim angle of the floating vessel are maintained at 0.3°.

[0013] Furthermore, during the process of lifting the nacelle to a predetermined distance above the tower, the crane needs to be stopped twice for observation. The first stop observation is carried out after the nacelle is lifted by the crane, and the second stop observation is carried out after the nacelle is lifted and rotated to the top of the tower. In the two stop observations, it is observed whether the actual sway of the nacelle at the observation position after lifting is smaller than the preset safety lifting control sway γ and whether the pitching is less than 100 mm. The duration of the two stop observations is 2 to 10 minutes.

[0014] Furthermore, before the nacelle is hoisted by the crane, two guy lines are attached to the nacelle flange, each of which includes a main guy line and a sub-guy line, the main guy line is wound or unwound by the warping end of the windlass of the floating vessel, and the spare guy line is operated by manual operation.

[0015] Further, the spreader includes a hanger hook unit and a hoisting beam, the hanger hook unit is connected to the main lifting jib of the crane, the hoisting beam is suspended from the hanger hook unit via an upper sling, the nacelle is hoisted below the hoisting beam via rigging, the hoisting beam has one guy line connected to each end, and one guy line is wound around a pulley of the main lifting jib of the crane. After the docking operation between the nacelle and the tower is completed and before the spreader is removed, confirm that the wind speed at the construction site will not exceed 8 meters / second in the next hour, the cradle angle of the crane within 30 minutes before removing the spreader will not exceed 0.2 degrees, and the spreader sway will not exceed 0.4 meters. Effect of the Invention

[0016] The beneficial effects of the present invention are as follows: the nacelle is provided with a docking and positioning device, the docking and positioning device and the tower are connected by a hand chain hoist, during the process of the nacelle being lowered by the crane and docking with the tower, the angle and position of the nacelle can be adjusted by operating the hand chain hoist, and the connecting bolts pre-installed in the nacelle flange holes can be aligned with the corresponding tower flange holes, thereby effectively improving the reliability of docking; and the floating vessel is used to lift the nacelle and dock it with the tower, thereby avoiding the problems of high cost and long construction period caused by the use of a jack-up offshore platform or a fixed-bottom offshore platform. [Brief description of the drawings]

[0017] [Figure 1] FIG. 2 is a schematic diagram of docking between a nacelle and a tower using the docking and positioning device and hand chain hoist according to the present invention. [Diagram 2] FIG. 2 is a structural schematic diagram of the lifting plate of the docking and positioning device of the present invention. [Diagram 3] FIG. 2 is a structural schematic diagram of a positioning pin of the docking and positioning device according to the present invention. [Figure 4] FIG. 2 is a schematic diagram of the layout of three positioning pin holes on the bottom surface of a nacelle in the present invention. [Diagram 5] FIG. 2 is a plan view schematic diagram of the layout of four hand chain hoists in the present invention. [Figure 6] 5 is a schematic diagram of the docking flow between the nacelle and the tower shown along the line AA in FIG. 4. [Figure 7] FIG. 2 is a schematic diagram of docking between a nacelle and a tower using a floating vessel according to the present invention. [Figure 8] FIG. 1 is a schematic diagram of calculation of the force received by the hand chain hoist in the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0018] In the present invention, in the method for lifting and docking the nacelle during the deployment of an offshore wind turbine using a floating vessel, a crane 50 is provided on the deck platform 60 of the floating vessel, and as shown in FIG. 7, the main lifting jib 51 of the crane 50 is provided with a spreader for lifting the nacelle. Before the nacelle lifting and docking operation is performed by the crane 50, it is necessary to observe and judge whether the weather, sea conditions and ship conditions at the construction site meet the predetermined lifting requirements. Before the nacelle lifting and docking operation is performed by the crane, the weather forecast for the construction site within the next 12 hours is observed and updated, and within 9 hours after the completion of the lifting of the tower of the wind turbine, the wind speed is less than 8 meters / second, there is no rainfall, and the swell height is less than 0.5 meters, and it is also confirmed that both the roll angle and pitch angle of the floating vessel are maintained at 0.2°, and the inclination angle and trim angle of the floating vessel are maintained at 0.3°. In addition, before lifting the nacelle, the deckhand monitors the ship's attitude and the force on the anchor point in real time, and instantly adjusts the force on the anchor cable to keep the ship in a stable lifted state, thereby avoiding the impact of bad weather and sea conditions on the floating ship as much as possible, and the floating ship can lift the nacelle and tower in a relatively stable state and dock.

[0019] As shown in Fig. 1, a nacelle flange 11 is provided on the bottom surface of a nacelle 10 of an offshore wind turbine and on the top surface of a tower 20, respectively, and a nacelle flange hole and a tower flange hole are provided on the tower flange 21, the nacelle flange, and the tower flange, respectively, at equal intervals in the circumferential direction, and the nacelle flange hole and the tower flange hole correspond to each other one-to-one. The crane 50 uses a spreader to lift the nacelle 10, on which the docking and positioning device is previously arranged, to a predetermined distance above the tower 20, and then connects the docking and positioning device to the hand chain hoist 36 via the tower 20, and manually operates the hand chain hoist to align the flange holes of the nacelle flange and the tower flange, and operates the crane to lower the nacelle to the nacelle flange hole and place it in place, and then inserts the connecting bolt 33 into the tower flange hole corresponding to the one-to-one, and finally removes the docking and positioning device and the hand chain hoist, thus completing the docking operation between the nacelle and the tower.

[0020] Before the nacelle 10 is hoisted by the crane, two guy lines are attached to the nacelle flange 11, each of which includes a main guy line and a sub guy line. The main guy line is wound or unwound by the warping end of the windlass of the floating vessel, and the spare guy line is operated by manual operation. During operation, the front and rear windlasses are each equipped with a skilled crew member to operate the windlass, and there are two workers next to the windlass, one of whom is responsible for winding the rope on the warping end and controlling the winding and unwinding in real time, and the other follows the instructions from the tower platform and transmits the instructions to the crew member operating the windlass. Manual guy line operation is used for the spare guy line operation, and four people pull to perform the guy line operation control, and the guy line adjusts the guy line operation position according to the lifting angle of the site, to avoid the nacelle not turning at high altitude when the main guy line breaks. During the cabin hoisting process, the lifting commander observes the cabin posture in real time, gives timely instructions to the guy line operation control personnel, and at the same time observes the cabin position relative to the crane jib frame of the crane to ensure an effective safety distance.

[0021] Before the nacelle 10 is lifted, a docking and positioning device is attached to the center of the bottom surface of the nacelle 10 . As shown in Figures 2, 4 and 5, the docking and positioning device includes a positioning pin and a lifting plate 31 attached to the center position of the bottom of the nacelle, and four lifting lugs arranged in a cross shape are provided on the bottom of the lifting plate 31, the four lifting lugs are respectively a first lifting lug 32a, a second lifting lug 32b, a third lifting lug 32c and a fourth lifting lug 32d, the length of the positioning pins is longer than the length of the connecting bolts 33, before lifting the nacelle 10, three of the nacelle flange holes are selected as positioning pin holes, positioning pins are provided in the three positioning pin holes, and connecting bolts 33 are provided in all the remaining nacelle flange holes, and the three positioning pin holes are respectively a first positioning pin hole 34a, a second positioning pin hole 34b and a third positioning pin hole 34c, and the first positioning pin hole 34a and the second positioning pin hole 34b are aligned in the same line with the center of the bottom of the nacelle 10. In addition, four of the tower flange holes are designated as towing holes, namely, the first towing hole 22a, the second towing hole 22b, the third towing hole 22c, and the fourth towing hole 22d, respectively, with the first towing hole 22a corresponding to the first positioning pin hole 34a, the second towing hole 22b corresponding to the second positioning pin hole 34b, and any tower flange hole between the tower flange hole corresponding to the third positioning pin hole 34c and the first towing hole 22a, and any tower flange hole between the second towing hole 22b and the third towing hole 22c and the fourth towing hole 22d.After the crane lifts the nacelle 10 with the above-mentioned docking and positioning device arranged thereon to a predetermined distance above the tower, the four hand chain hoists are used to connect the hanger hook ends on one side of the four hand chain hoists to the four lifting lugs respectively, and connect the hanger hook ends on the other side of the four hand chain hoists to the first towing hole 22a, the second towing hole 22b, the third towing hole 22c, and the fourth towing hole 22d respectively through slings; then, the four hand chain hoists are manually operated while the crane is used to lower the nacelle, and the positioning pins in the three positioning pin holes are respectively inserted into the corresponding tower flange holes of the tower to perform the initial alignment between the nacelle and the tower; then, the crane is used to further lower the nacelle until the connecting bolts 33 in the remaining nacelle flange holes are all extended into the corresponding tower flange holes in one-to-one pairs; finally, the four hand chain hoists and the three positioning pins are removed, and the connecting bolts are respectively installed into the three positioning pins. Using the principle of triangulation, three of the nacelle flange holes are made into three positioning pin holes, and a positioning pin is provided in each of the three positioning pin holes. The four lifting lugs of the lifting plate 31 provided in the center of the bottom surface of the nacelle are respectively connected to the four towing holes of the tower flange 21 by the four hand chain hoists. During the docking process, the angle of the nacelle 10 relative to the tower 20 is adjusted by pulling the four hand chain hoists, and the three positioning pins are aligned with the corresponding flange holes of the tower, and the initial positioning of the nacelle and the tower is realized by the three positioning pins.

[0022] In a preferred technical solution, as shown in FIG. 3, FIG. 5 and FIG. 6, the positioning pin includes a first positioning pin 35a and a second positioning pin 35b, the length of the first positioning pin 35a is longer than the length of the second positioning pin 35b, and the length of the second positioning pin 35b is longer than the length of the connecting bolt 33, there are two second positioning pins 35b, the two second positioning pins 35b are respectively mounted in the first positioning pin hole 34a and the second positioning pin hole 34b, the first positioning pin 35a is mounted in the third positioning pin hole 35c, the four hand chain hoists are the first hand chain hoist 36a, the second hand chain hoist 36b, the third hand chain hoist 36c and the fourth hand chain hoist 36d, respectively, the first hand chain hoist 36a is mounted in the third hand chain hoist 36b, the fourth hand chain hoist 36c and the fourth hand chain hoist 36d are mounted in the first hand chain hoist 36b, the fourth hand chain hoist 36d and the fourth hand chain hoist 36c are mounted in the first hand chain hoist 36a. The hand chain hoist 36a has a hanger hook end on one side connected to the first lifting lug 32a and a hanger hook end on the other side connected to the first towing hole 22a via a sling, the second hand chain hoist 36b has a hanger hook end on one side connected to the second lifting lug 32b and a hanger hook end on the other side connected to the second towing hole 22b via a sling, the third hand chain hoist 36c has a hanger hook end on one side connected to the fourth lifting lug 32d and a hanger hook end on the other side connected to the third towing hole 22c via a sling, and the fourth hand chain hoist 36d has a hanger hook end on one side connected to the third lifting lug 32c and a hanger hook end on the other side connected to the fourth towing hole 22d via a sling. When installing the four hand chain hoists, the lengths of the hoists need to be adjusted simultaneously so that none of the four properly installed hand chain hoists is subjected to force. Thereafter, while manually tightening the third hand chain hoist 36c and the fourth hand chain hoist 36d, the nacelle is slowly lowered by the crane, and the first positioning pin 35a is slowly inserted into the corresponding tower flange hole while adjusting the position of the first positioning pin 35a.Next, while tightening the third hand chain hoist 36c and the fourth hand chain hoist 36d, the positions of the two second positioning pins 35b are adjusted by adjusting the first hand chain hoist 36a and the second hand chain hoist 36b, respectively, and at the same time, the nacelle is slowly lowered by the crane until the two second positioning pins 35b are extended and aligned with the first towing hole 22a and the second towing hole 22b, respectively, thereby completing the initial positioning of the nacelle and the tower. Based on the triangulation principle, the three positioning pins are configured so that one is long and the remaining two are short (i.e., the length of the first positioning pin 35a is longer than the length of the second positioning pin 35b, and the length of the second positioning pin 35b is longer than the length of the connecting bolt 33), so that when using the three positioning pins for docking and alignment, first the first positioning pin 35a is aligned with the tower flange, and then the two second positioning pins 35b are aligned, thereby improving the stability and reliability of docking between the nacelle and the tower.

[0023] In a further preferred technical solution, the third positioning pin hole 34c is located on the perpendicular bisector connecting the first positioning pin hole 34a and the second positioning pin hole 34b, and the three positioning pin holes are arranged in a right-angled isosceles triangle, as shown in Figure 4, and the tower flange hole corresponding to the third positioning pin hole 34c forms an angle of 45° with both the third towing hole 22c and the fourth towing hole 22d in the radial direction, thereby making the towing operation of the four hand chain hoists simpler and more labor-saving, and reducing the difficulties in docking and positioning the nacelle and the tower.

[0024] 3, each of the three positioning pins includes a pin body 351, a threaded end 352, a positioning end 353, and a positioning guide 354, one end of the pin body 351 is the threaded end 352 that fits into the nacelle flange hole, and the other end is integrally connected to the positioning end 353 by the positioning guide 354, the positioning guide 354 is a tapered cone extending from the threaded end 352 to the positioning end 353, and the positioning end 353 is a regular rectangle. The cone-shaped positioning guide 354 and the rectangle-shaped positioning end of the positioning pin can play an efficient guiding and positioning role in the initial stage of docking the positioning pin with the corresponding flange hole of the tower, and can further improve the reliability of the docking positioning.

[0025] The lengths of the above four hand chain hoists are calculated by the following method: before hoisting the nacelle, the roll and pitch of the floating vessel are calculated from the current roll angle and pitch angle of the floating vessel, using roll angle = roll angle × height of suspended object × π / 180 and pitch angle = pitch angle × height of suspended object × π / 180; then CAD lofting is performed based on the calculated roll and pitch, and a margin of 0.5m to 1m is left based on the CAD lofting size to obtain the length of the hand chain hoist. The force of the hand chain hoist is calculated by superimposing the lateral and vertical sway calculated above to obtain the overall sway, and is expressed as follows: Hoist force = [nacelle weight x (twice the overall sway) / distance of the suspended object from the boom top] x maximum length of hand chain hoist / horizontal distance from the towing hole of the lifting lug, as shown in Figure 8, where γ' is twice the sway, L is the distance from the boom top of the suspended object, l is the horizontal distance from the towing hole of the lifting lug, and D is the maximum length of the hand chain hoist.

[0026] In a further preferred technical solution, during the process of lifting the nacelle 10 to a predetermined distance above the tower 20, the crane needs to be stopped and observed twice, the first stop observation is carried out after the nacelle is lifted by the crane, and the second stop observation is carried out after the nacelle is lifted and rotated to the top of the tower, and the two stop observations are carried out to observe whether the actual sway of the nacelle at the observation position after lifting is smaller than the preset safe lifting control sway γ at the observation position, and whether the pitching is less than 100 mm, and the time for the two stop observations is 2 minutes to 10 minutes. The safe lifting control sway γ is obtained by calculating the lifting safe sway and pitch sway at the corresponding observation position from the roll angle, pitch angle, and height of the hanging object at the corresponding observation position, and then superimposing the lifting safe sway and pitch sway.

[0027] In the present invention, the spreader includes a hanger hook unit 41 and a hoisting beam 42, the hanger hook unit 41 is connected to the main lifting jib 51 of the crane 50, the hoisting beam 42 is hung on the hanger hook unit 41 through an upper sling, and the nacelle 10 is hoisted below the hoisting beam 42 through a rigging, and the hoisting beam 42 has one guy line connected to each end, and the guy line on one side is wound around the pulley 52 of the main lifting jib 51 of the crane 50. Thereby, the stability of the hoisting beam can be ensured when the spreader is removed after completing the docking of the nacelle with the tower. In addition, after completing the docking work of the nacelle with the tower but before removing the spreader, it is necessary to confirm that the wind speed at the construction site will not exceed 8 meters / second in the next hour, that the cradle angle of the crane within 30 minutes before removing the spreader will not exceed 0.2 degrees, and that the spreader sway will not exceed 0.4 meters. This ensures that the spreader removal process is not affected by external factors such as bad weather or sea conditions that could cause damage to the docked nacelle and tower.

[0028] Although the specific implementation of the present invention has been described in detail above, the contents are merely better embodiments of the present invention and are not considered to be used to limit the scope of the present invention. Equivalent modifications and improvements made within the scope of the application of the present invention are also subject to the patent of the present invention. [Explanation of symbols]

[0029] 10 Nacelle 11 Nacelle flange 20. Tower 21 Tower flange 22a 1st towing hole 22b 2nd towing hole 22c 3rd towing hole 22d 4th towing hole 31 Lifting board 32a First Lifting Lug 32b 2nd lifting lug 32c 3rd lifting lug 32d 4th lifting lug 33 Connection bolt 34a First positioning pin hole 34b Second positioning pin hole 34c 3rd positioning pin hole 35 Locating pin 35a First positioning pin 35b 2nd positioning pin 351 Pin body 352 Threaded End 353 Positioning end 354 Positioning guide 36 Hand Chain Hoist 36a No. 1 Hand Chain Hoist 36b 2nd Hand Chain Hoist 36c 3rd hand chain hoist 36d 4th Hand Chain Hoist 41 Hanger hook unit 42 Hoisting Beam 50 Crane 51 Main Lifting Jib 52 Pulley 60 Deck platform of floating vessel

Claims

1. A method for lifting and docking a nacelle when arranging an offshore wind turbine using a floating ship, the method comprising: providing a crane on a deck platform of a floating ship; providing a spreader for lifting a nacelle on a main lifting jib of the crane; providing a nacelle flange and a tower flange on a bottom surface of the nacelle and a top surface of the tower of the offshore wind turbine, respectively; providing nacelle flange holes and tower flange holes that are evenly opened in the circumferential direction, respectively, and providing a one-to-one correspondence between the nacelle flange holes and the tower flange holes, The method includes using a crane to lift the nacelle with the docking and positioning device previously arranged thereon by the spreader to a predetermined distance above the tower, then connecting the docking and positioning device to the tower via a hand chain hoist, manually operating the hand chain hoist to align the flange holes of the nacelle flange and the tower flange, and operating the crane to lower and arrange the nacelle to the nacelle flange holes, and inserting the connecting bolts into the one-to-one corresponding tower flange holes, and finally removing the docking and positioning device and the hand chain hoist, thus completing the docking operation between the nacelle and the tower.

2. The docking and positioning device includes a positioning pin and a lifting plate attached to a center position of the bottom of the nacelle, and four lifting lugs arranged in a cross shape are provided on the bottom of the lifting plate, the four lifting lugs are a first lifting lug, a second lifting lug, a third lifting lug, and a fourth lifting lug, respectively, and the length of the positioning pin is longer than the length of the connecting bolt; Before lifting the nacelle, select three of the nacelle flange holes as locating pin holes, provide the locating pins in the three locating pin holes, and provide connecting bolts in all of the remaining nacelle flange holes, the three locating pin holes being a first locating pin hole, a second locating pin hole, and a third locating pin hole, respectively, and the first locating pin hole and the second locating pin hole are aligned in the same line with the center of the bottom of the nacelle; In addition, four of the tower flange holes are designated as towing holes, respectively designated as a first towing hole, a second towing hole, a third towing hole, and a fourth towing hole, the first towing hole corresponds to the first positioning pin hole, the second towing hole corresponds to the second positioning pin hole, any tower flange hole between the tower flange hole corresponding to the third positioning pin hole and the first towing hole, and any tower flange hole between the tower flange hole corresponding to the second positioning pin hole are designated as the third towing hole and the fourth towing hole, After the crane lifts the nacelle with the above-mentioned docking and positioning device arranged thereon to a predetermined distance above the tower, use four hand chain hoists to connect the hanger hook ends on one side of the four hand chain hoists to the four lifting lugs respectively, and connect the hanger hook ends on the other side of the four hand chain hoists to the first towing hole, the second towing hole, the third towing hole and the fourth towing hole respectively through slings; then, while manually operating the four hand chain hoists, the crane lowers the nacelle, and the locating pins in the three locating pin holes are respectively inserted into the corresponding tower flange holes of the tower to perform the initial alignment between the nacelle and the tower; Then, the nacelle is further lowered by the crane until all of the connecting bolts in the remaining nacelle flange holes are extended into the one-to-one corresponding tower flange holes; The method for lifting and docking a nacelle when deploying an offshore wind turbine using a floating ship as described in claim 1, characterized in that, finally, the four hand chain hoists and the three positioning pins are removed, and connecting bolts are installed respectively into the three positioning pins.

3. The positioning pins include a first positioning pin and a second positioning pin, the length of the first positioning pin is longer than the length of the second positioning pin and the length of the second positioning pin is longer than the length of the connecting bolt, two second positioning pins are provided, the two second positioning pins are respectively mounted in the first positioning pin hole and the second positioning pin hole, the first positioning pin is mounted in the third positioning pin hole, the four hand chain hoists are a first hand chain hoist, a second hand chain hoist, a third hand chain hoist, and a fourth hand chain hoist, the first hand chain hoist is a first hand chain hoist, a second hand chain hoist, a third hand chain hoist, and a fourth hand chain hoist, the hanger hook end of the first hand chain hoist is connected to the first lifting lug and the hanger hook end of the other side is connected to the first towing hole via a sling, the second hand chain hoist is connected to the second lifting lug and the hanger hook end of the other side is connected to the second towing hole via a sling, the third hand chain hoist is connected to the fourth lifting lug and the hanger hook end of the other side is connected to the third towing hole via a sling, and the fourth hand chain hoist is connected to the third lifting lug and the hanger hook end of the other side is connected to the fourth towing hole via a sling, When installing the four hand chain hoists, the lengths of the hoists need to be adjusted simultaneously so that none of the four hand chain hoists are subjected to force when properly installed; Then, while manually tightening the third hand chain hoist and the fourth hand chain hoist, the nacelle is slowly lowered by the crane, and the first positioning pin is slowly inserted into the corresponding tower flange hole while adjusting the position of the first positioning pin; The method for lifting and docking a nacelle during deployment of an offshore wind turbine using a floating vessel according to claim 2, characterized in that: then, while fastening the third hand chain hoist and the fourth hand chain hoist, adjust the positions of the two second positioning pins by manually adjusting the first hand chain hoist and the second hand chain hoist, respectively; and at the same time, slowly lower the nacelle by the crane until the two second positioning pins are extended to align with the first towing hole and the second towing hole, respectively, thereby completing the initial positioning of the nacelle and the tower.

4. The method for lifting and docking a nacelle when deploying an offshore wind turbine using a floating ship as described in claim 2, characterized in that the third positioning pin hole is located on a perpendicular bisector connecting the first positioning pin hole and the second positioning pin hole, and the tower flange hole corresponding to the third positioning pin hole forms an angle of 45° with both the third towing hole and the fourth towing hole in the radial direction.

5. 3. The method for lifting and docking a nacelle when deploying an offshore wind turbine using a floating ship according to claim 2, characterized in that each of the three positioning pins includes a pin body, a threaded end, a positioning end, and a positioning guide, one end of the pin body is the threaded end that fits into a nacelle flange hole, and the other end is integrally connected to the positioning end by the positioning guide, the positioning guide is a tapered cone extending from the threaded end toward the positioning end, and the positioning end is a regular rectangle.

6. The selection of the hand chain hoist includes the selection of the length of the hand chain hoist and the selection of the force receiving force, among which, the length of the hand chain hoist is determined by calculating the roll and pitch of the floating vessel according to the current roll angle and pitch angle of the floating vessel before lifting the nacelle, as follows: roll=roll angle×height of the suspended object×π / 180, pitch=pitch angle×height of the suspended object×π / 180, and then performing CAD lofting according to the calculated roll and pitch, and then providing a margin of 0.5m to 1m according to the CAD lofting size.

3. The method for lifting and docking a nacelle when deploying an offshore wind turbine using a floating ship according to claim 2, characterized in that the force received by the hand chain hoist is calculated by superimposing the calculated lateral and vertical oscillations to obtain a total oscillation, and the force received by the hand chain hoist is calculated by: Hoist Force = [weight of nacelle x (twice the total oscillation) / distance of suspended object from boom top] x maximum length of hand chain hoist / horizontal distance from the towing hole of the lifting lug.

7. Before using a crane to lift the nacelle and perform docking operations, it is necessary to observe and determine whether the weather, sea conditions and ship conditions at the construction site meet the specified lifting requirements; The method for lifting and docking a nacelle during deployment of an offshore wind turbine using a floating vessel according to claim 1, characterized in that, before performing the nacelle lifting and docking work by the crane, observe and update the weather forecast for the construction site within the next 12 hours, and ensure that within 9 hours after completing the lifting of the wind turbine tower, the wind speed is less than 8 meters / second, there is no rainfall, the swell height is less than 0.5 meters, and both the roll angle and pitch angle of the floating vessel are maintained at 0.2°, and the inclination angle and trim angle of the floating vessel are maintained at 0.3°.

8. The method for lifting and docking a nacelle for deploying an offshore wind turbine using a floating ship according to claim 1, characterized in that during the process of lifting the nacelle to a predetermined distance above the tower, the crane needs to be stopped and observed twice, the first stop observation is performed after the nacelle is lifted by the crane, and the second stop observation is performed after the nacelle is lifted and rotated to the top of the tower, the two stop observations are performed to observe whether the actual sway of the nacelle at the observation position after lifting is smaller than the preset safe lifting control sway γ and whether the pitching is less than 100 mm, and the time for the two stop observations is 2 to 10 minutes.

9. The method for lifting and docking a nacelle when deploying an offshore wind turbine using a floating vessel, as described in claim 1, characterized in that before lifting the nacelle by a crane, two guy lines are attached to the nacelle flange, each guy line including a main guy line and a sub guy line, the main guy line is wound or unwound by a warping end of a windlass of the floating vessel, and the spare guy line is operated by manual operation.

10. 2. The method for lifting and docking a nacelle during deployment of an offshore wind turbine using a floating vessel according to claim 1, characterized in that the spreader includes a hanger hook unit and a hoisting beam, the hanger hook unit is connected to the main lifting jib of the crane, the hoisting beam is hung from the hanger hook unit via an upper sling, the nacelle is lifted below the hoisting beam via rigging, the hoisting beam has one guy line connected to each end, and the guy line on one side is wound around a pulley of the main lifting jib of the crane, and after the docking operation of the nacelle and the tower is completed and before removing the spreader, it is confirmed that the wind speed at the construction site will not exceed 8 meters / second in the next hour, the cradle angle of the crane will not exceed 0.2 degrees within 30 minutes before removing the spreader, and the sway of the spreader will not exceed 0.4 meters.