Device to be operated
The operation target device optimizes dynamic characteristics of construction machines based on operator skill, improving operability and productivity by calculating and adjusting machine performance to match the operator's abilities.
Patent Information
- Application Number
- JP2021024859
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-02-19
- Publication Date
- 2024-10-16
- Estimated Expiration
- 2041-02-19
AI Technical Summary
Existing systems fail to provide operators with operability suitable for their skill level, leading to suboptimal productivity in construction machines.
An operation target device that calculates and adjusts the dynamic characteristics of a construction machine to optimize performance based on the operator's skill, using a dynamic characteristic updating unit and productivity acquisition unit to determine and update the optimal dynamic characteristics.
The device provides operators with operability tailored to their skills, enhancing productivity by calculating and adjusting dynamic characteristics to match the operator's proficiency.
Smart Images

Figure 0007567543000003 
Figure 0007567543000004 
Figure 0007567543000005
Abstract
Description
[Technical field]
[0001] The present invention relates to an operation target device, and more particularly to an operation target device that updates dynamic characteristics of an operation target to optimal dynamic characteristics in a specific task in which a specific operation is repeated. [Background technology]
[0002] Conventionally, construction machines having a machine control function for automatically or semi-automatically operating the construction machine are known (for example, Patent Document 1). Patent Document 1 discloses that the amount of automatic operation and the amount of manual operation are displayed on a display device while the machine control function is being executed.
[0003] In addition, in the field of autonomous driving technology, a technology is known that calculates the variance of a vehicle's travel trajectory for each travel scene (for example, Patent Document 2). Patent Document 2 discloses that the variance of the travel trajectory is calculated by a well-known method. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2019-108721 A [Patent Document 2] JP 2017-138282 A Summary of the Invention [Problem to be solved by the invention]
[0005] The invention described in the above-mentioned Patent Document 1 simply teaches the difference between automatic operation and manual operation to the operator, so if the operator's operation skill is low, there is a problem that the operator cannot operate as instructed. In other words, it is difficult for Patent Document 1 to provide the operator with operability suitable for the operator's operation skill. Therefore, the final productivity is not improved, and the operator's skill cannot be improved.
[0006] Therefore, an object of the present invention is to provide an operation target device that can provide an operator with operability suited to the operator's operating skill. [Means for solving the problem]
[0007] In order to achieve the above object, the present invention provides an operation target device comprising: a dynamic characteristic update unit that calculates optimal or suboptimal optimal dynamic characteristics of an operation target in a specific task in which a specific operation is repeated and updates the dynamic characteristic of the operation target to the optimal dynamic characteristic; and a productivity acquisition unit that acquires productivity when the specific task is performed, wherein the dynamic characteristic update unit sets a first dynamic characteristic to the dynamic characteristic, and the productivity acquisition unit acquires as a first productivity the productivity when the specific task is performed in a state in which the dynamic characteristic is set to the first dynamic characteristic, the dynamic characteristic update unit sets as the dynamic characteristic a second dynamic characteristic different from the first dynamic characteristic, and the productivity acquisition unit acquires as a second productivity the productivity when the specific task is performed in a state in which the dynamic characteristic is set to the second dynamic characteristic, and the dynamic characteristic update unit calculates the optimal dynamic characteristic based on the first dynamic characteristic, the second dynamic characteristic, the first productivity, and the second productivity.
[0008] Here, it is preferable that the system further includes a work trajectory variance calculation unit that calculates a work trajectory variance value using work trajectory data acquired while the specific work is being performed, wherein the work trajectory variance calculation unit calculates a first work trajectory variance value using work trajectory data acquired while the specific work is being performed with the dynamic characteristic set to the first dynamic characteristic, the productivity acquisition unit acquires the first work trajectory variance value as a first productivity, the work trajectory variance calculation unit calculates a second work trajectory variance value using work trajectory data acquired while the specific work is being performed with the dynamic characteristic set to the second dynamic characteristic, and the productivity acquisition unit acquires the second work trajectory variance value as a second productivity.
[0009] It is also preferable that the system further includes a work stability calculation unit that calculates work stability when the specific task is performed, wherein the work stability calculation unit calculates a first work stability when the specific task is performed with the dynamic characteristic set to the first dynamic characteristic, the productivity acquisition unit acquires the first work stability as a first productivity, the work stability calculation unit calculates a second work stability when the specific task is performed with the dynamic characteristic set to the second dynamic characteristic, and the productivity acquisition unit acquires the second work stability as a second productivity.
[0010] It is preferable that the system further includes a memory unit that stores, for each task, a set optimal dynamic characteristic, which is the optimal dynamic characteristic that was set in the past, and a task identification unit that identifies a task, and the dynamic characteristic update unit obtains from the memory unit one set optimal dynamic characteristic corresponding to the task identified by the task identification unit, and uses the one set optimal dynamic characteristic as the first dynamic characteristic. Effect of the Invention
[0011] According to the present invention, the optimal dynamic characteristic is calculated based on the first dynamic characteristic, the first productivity when a specific operation is performed with the first dynamic characteristic, and the second dynamic characteristic, and the second productivity when a specific operation is performed with the second dynamic characteristic. Therefore, it is possible to provide the operator with operability suited to the operator's operating skill. [Brief description of the drawings]
[0012] [Figure 1] FIG. 1 is a diagram showing a hydraulic excavator (operation target device) according to a first embodiment of the present invention. [Diagram 2] Functional block diagram of a hydraulic excavator. [Diagram 3] A conceptual diagram showing one cycle of operation during loading and excavation work (specific work). [Figure 4] 13 is a graph showing the work trajectory of a skilled worker in loading and excavation work. [Diagram 5] 1 is a graph showing a work trajectory of an unskilled worker in loading and excavation work. [Figure 6]1 is a graph showing the relationship between responsiveness (dynamic characteristics) and productivity (work trajectory variance value). [Figure 7] 4 is a flowchart showing a dynamic characteristic update process (first embodiment). [Figure 8] FIG. 11 is a block diagram showing a controller of a hydraulic excavator according to a second embodiment. [Figure 9] FIG. 4 is a diagram for explaining parameters used in a calculation formula for operational stability. [Figure 10] 1 is a graph showing the relationship between responsiveness (dynamic characteristics) and productivity (work stability). [Figure 11] 11 is a flowchart showing a dynamic characteristic update process (second embodiment). [Figure 12] FIG. 11 is a functional block diagram of a hydraulic excavator according to a modified example. [Figure 13] FIG. 13 is a diagram showing a set optimal dynamic characteristic table. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0013] <1. First embodiment> An operation target device according to a first embodiment of the present invention will be described with reference to Fig. 1 to Fig. 7. In the following, a construction machine (hydraulic excavator 1) shown in Fig. 1 will be illustrated as an example of the operation target device.
[0014] As shown in Fig. 1, the hydraulic excavator 1 is configured to include a lower traveling body 2, an upper rotating body 3 rotatably mounted on the lower traveling body 2, and an attachment 4 including a boom and an arm. A bucket 41 for excavating and discharging soil is provided at the tip of the attachment 4.
[0015] 2, the hydraulic excavator 1 is configured to include a controller 5. The controller 5 is a control device capable of executing a dynamic characteristic updating program for updating the dynamic characteristics of an operation target to optimal or suboptimal dynamic characteristics for an operator (hereinafter also simply referred to as "optimal dynamic characteristics").
[0016] As shown in FIG. 2, the controller 5 includes a dynamic characteristic update unit 51, a task trajectory variance value calculation unit 53, and a productivity acquisition unit 55.
[0017] The dynamic characteristic update unit 51 is a processing unit that calculates optimal dynamic characteristics of an operation object in a specific task in which a specific operation is repeated, and updates the dynamic characteristics of the operation object to the optimal dynamic characteristics.
[0018] In this embodiment, a loading and excavation work is illustrated as an example of the specific work. As shown in Fig. 3, the loading and excavation work is a work in which excavation, lifting and swinging, soil discharge, and return are repeated as one cycle of operations.
[0019] The work trajectory variance value calculation unit 53 is a processing unit that calculates a work trajectory variance value in the loading excavation work by using the work trajectory data acquired during the period in which the loading excavation work is being performed.
[0020] The work trajectory data acquired during the period when loading and excavation work is being performed is the movement trajectory of the toe of the bucket 41. Figures 4 and 5 are graphs depicting the movement trajectory of the toe of the bucket 41 during loading and excavation work. The graph in Figure 4 depicts the movement trajectory of a skilled worker, and there is little variation from cycle to cycle. On the other hand, the graph in Figure 5 depicts the movement trajectory of a non-skilled worker, and there is large variation from cycle to cycle.
[0021] The work trajectory variance calculation unit 53 calculates the variance of the movement trajectory in each cycle of the loading and excavation work as the work trajectory variance value based on the above-mentioned work trajectory data (the movement trajectory of the tip of the bucket 41). The variance of the movement trajectory in each cycle of the loading and excavation work is calculated by a well-known method.
[0022] The productivity acquisition unit 55 is a processing unit that acquires the productivity when a specific task (loading and excavation task) is performed. In this embodiment, the productivity acquisition unit 55 acquires the task trajectory variance value calculated by the task trajectory variance value calculation unit 53 as the productivity of the loading and excavation task.
[0023] Incidentally, in the above-mentioned loading and excavation work, it is known that the responsiveness (dynamic characteristic X) and productivity (work trajectory variance value Y) of the bucket 41 are approximated by a downwardly convex function F(X) regardless of the skill, as shown in Fig. 6. Therefore, the dynamic characteristic X for which the function F(X) is minimized (i.e., the work trajectory variance value Y is smallest) is the optimal dynamic characteristic.
[0024] As a known technique, the "steepest descent method" is known as one of the algorithms for searching for the minimum value of a function from only the slope (first derivative) of the function. Below, we will explain the procedure for calculating the optimal dynamic characteristics when the function of productivity (task trajectory variance value Y) with the dynamic characteristics as a variable is unknown, using the known "steepest descent method" algorithm.
[0025] In the following, a procedure for calculating the optimal dynamic characteristics of the operation object in a loading excavation operation and updating the dynamic characteristics of the operation object to the optimal dynamic characteristics will be described with reference to the flowchart shown in FIG.
[0026] First, in step S1, the dynamic characteristic update unit 51 sets the dynamic characteristic X1 as an initial value to the dynamic characteristic X. Note that a random initial value is set to the dynamic characteristic X1.
[0027] Next, a loading and excavation operation is performed with the dynamic characteristic X set to the dynamic characteristic X1. During the period in which the loading and excavation operation is being performed, the movement trajectory of the toe of the bucket 41 is acquired as work trajectory data. When the loading and excavation operation is completed, the work trajectory variance calculation unit 53 calculates the variance value of the movement trajectory in each cycle of the loading and excavation operation as the work trajectory variance value Y1. Then, the productivity acquisition unit 55 acquires the work trajectory variance value Y1 calculated by the work trajectory variance calculation unit 53 as the productivity of the loading and excavation operation in the dynamic characteristic X1 (step S2).
[0028] Next, in step S3, the dynamic characteristic update unit 51 sets a dynamic characteristic X2 different from the dynamic characteristic X1 (initial value) as a new dynamic characteristic X. Note that, here, it is assumed that a random value is set to the dynamic characteristic X2, but, for example, a value obtained by adding a predetermined value ΔX to the dynamic characteristic X1 may be set.
[0029] With the dynamic characteristic X set to the dynamic characteristic X2, the loading and excavation work is performed again. During the period in which the loading and excavation work is being performed, the movement trajectory of the toe of the bucket 41 is acquired as work trajectory data. When the loading and excavation work is completed, the work trajectory variance calculation unit 53 calculates the variance value of the movement trajectory in each cycle of the loading and excavation work as the work trajectory variance value Y2. Then, the productivity acquisition unit 55 acquires the work trajectory variance value Y2 calculated by the work trajectory variance calculation unit 53 as the productivity of the loading and excavation work in the dynamic characteristic X2 (step S4).
[0030] Then, in step S5, the dynamic characteristic update unit 51 calculates the dynamic characteristic X for update using the following formula 1: t+1 The initial value of "t" is "2".
number
[0031] In the above formula 1, "X t " is the currently set dynamic characteristic X2, and "X t-1 " is the previously set dynamic characteristic X1. Also, "Y t " is the work trajectory variance value Y2 in the dynamic characteristic X2, and "Y t-1 " is the task trajectory variance value Y1 in the dynamic characteristic X1. Note that "η" is the learning rate for determining the learning speed (update speed).
[0032] That is, the dynamic characteristic update unit 51 updates the increase in the dynamic characteristic X (X t -X t-1 ) to the increase in the work trajectory variance value Y (Y t -Y t-1 ) based on the gradient (Y t -Y t-1 / X t -X t-1 ) multiplied by the learning rate η to obtain the currently set dynamic characteristic X t Update the dynamic characteristic X for updating t+1 Calculate the following.
[0033] Here, the dynamic characteristic update unit 51 updates the currently set dynamic characteristic X2 by multiplying the gradient (Y2-Y1 / X2-X1) based on the increase (Y2-Y1) between the work trajectory variance value Y1 and the work trajectory variance value Y2 relative to the increase (X2-X1) between the dynamic characteristic X1 and the dynamic characteristic X2 by the learning rate η according to the above formula 1 to calculate the dynamic characteristic X3 for update. Then, the dynamic characteristic update unit 51 sets the dynamic characteristic X3 for update calculated in step S5 to the dynamic characteristic X (step S6).
[0034] In step S7, the dynamic characteristic update unit 51 determines whether the dynamic characteristic X3 for update has converged to the optimal dynamic characteristic. Note that whether the dynamic characteristic has converged to the optimal dynamic characteristic is determined based on, for example, whether the gradient is equal to or smaller than a predetermined value.
[0035] Here, if it is determined that the dynamic characteristic X3 has converged to the optimal dynamic characteristic, the process ends. Note that if it is determined that the dynamic characteristic X3 has converged to the optimal dynamic characteristic, the dynamic characteristic X3 becomes the optimal dynamic characteristic.
[0036] On the other hand, if it is determined that the dynamic characteristic X3 has not converged, the process proceeds to step S8.
[0037] In step S8, the loading and excavation work is performed again with the dynamic characteristic X set to the dynamic characteristic X3. During the period in which the loading and excavation work is being performed, the movement trajectory of the toe of the bucket 41 is acquired as work trajectory data. When the loading and excavation work is completed, the work trajectory variance calculation unit 53 calculates the variance value of the movement trajectory in each cycle of the loading and excavation work as the work trajectory variance value Y3. Then, the productivity acquisition unit 55 acquires the work trajectory variance value Y3 calculated by the work trajectory variance calculation unit 53 as the productivity of the loading and excavation work in the dynamic characteristic X3 (step S8).
[0038] After that, in step S9, "t" is incremented and set to "3".
[0039] Thereafter, the process returns to step S5, and the dynamic characteristic update unit 51 calculates the dynamic characteristic X4 for update using the above-mentioned formula 1. In detail, the dynamic characteristic update unit 51 updates the currently set dynamic characteristic X3 by multiplying the gradient (Y3-Y2 / X3-X2) based on the increase (Y3-Y2) between the operation trajectory variance value Y3 and the operation trajectory variance value Y2 with respect to the increase (X3-X2) between the dynamic characteristic X3 and the dynamic characteristic X2 by the learning rate η to calculate the dynamic characteristic X4 for update.
[0040] Then, in step S6, the dynamic characteristic update unit 51 sets the dynamic characteristic X4 for update calculated in step S5 to the dynamic characteristic X. Then, the dynamic characteristic update unit 51 determines whether the dynamic characteristic X4 for update has converged to the optimal dynamic characteristic (step S7). If it is determined that the dynamic characteristic X4 has converged to the optimal dynamic characteristic, the process ends, and if it has not converged, the process proceeds to step S8, and the above-mentioned process is executed again.
[0041] The above process is carried out in step S7 by using the dynamic characteristic X t+1 is determined to have converged to the optimal dynamics.
[0042] According to the first embodiment described above, the optimal dynamic characteristic X is calculated based on the dynamic characteristic X1, the work trajectory variance value Y1, the dynamic characteristic X2, and the work trajectory variance value Y2. t+1 Therefore, the optimum dynamic characteristic X that minimizes the work trajectory variance Y according to the operator's operation skill is calculated. t+1 It is possible to set the dynamic characteristic X to the dynamic characteristic X. Therefore, it is possible to provide the operator with operability suited to the operator's operation skill.
[0043] Furthermore, according to the above-described first embodiment, the work trajectory variance value Y of each cycle in the loading and excavation work is acquired as productivity. Then, the work trajectory variance value Y is calculated based on the movement trajectory of the tip of the bucket 41. The work trajectory variance value Y tends to be smaller as the operator's skill is higher and tends to be larger as the operator's skill is lower. Therefore, if the work trajectory variance value Y is acquired as productivity and used to calculate the optimal dynamic characteristic, there is a high possibility that a more appropriate optimal dynamic characteristic according to the operator's skill can be calculated.
[0044] <2. Second embodiment> Next, an operation target device according to a second embodiment of the present invention will be described with reference to FIGS.
[0045] In the above-described first embodiment, the case where the work trajectory variance value Y calculated by the work trajectory variance value calculation unit 53 is acquired as the productivity in the loading and excavation work has been exemplified.
[0046] In the second embodiment, a case will be illustrated in which the work stability Z indicating the work stability of the hydraulic excavator 1 is acquired as the productivity in loading and excavation work. In the following, differences from the above-mentioned first embodiment will be described, and descriptions of overlapping parts with the above-mentioned first embodiment will be omitted.
[0047] As shown in FIG. 8, in the second embodiment, the controller 5 is configured to include a dynamic characteristic update unit 51, a task stability calculation unit 54, and a productivity acquisition unit 55.
[0048] The work stability calculation unit 54 is a processing unit that calculates the work stability Z of the hydraulic excavator 1 during loading and excavation work.
[0049] The work stability Z is calculated by the formula "Z=M×g×L1-F×L2" where M is the vehicle weight of the hydraulic excavator 1, g is the gravitational acceleration, and F is the excavation force.
[0050] In the above-mentioned calculation formula, L1 is the length connecting the intersection point of the perpendicular line dropped from the center of gravity of the hydraulic excavator 1 and the ground surface to the front-most point of the part where the crawler comes into contact with the ground surface, as shown in FIG.
[0051] 9, L2 is the length connecting the position of the tip of the bucket 41 and the intersection point where a straight line that is perpendicular to the vector direction of the force generated at the tip of the bucket 41 and passes through the tip of the bucket 41 intersects with the ground.
[0052] When the value of Z calculated by the above-mentioned arithmetic expression becomes less than 0, the hydraulic excavator 1 becomes unstable. On the other hand, when the value of Z becomes greater than 0, the hydraulic excavator 1 becomes stable.
[0053] The work stability calculation unit 54 calculates the work stability z i (i=1, 2, 3, ...) at a predetermined interval. After the loading and excavation work is completed, the work stability calculation unit 54 calculates the work stability z i The work stability Z during loading and excavation work is calculated from
[0054] Here, the work stability calculation unit 54 calculates the work stability z i The average value is calculated as the work stability Z during loading and excavation work.
[0055] However, this is not limited to this, and the work stability calculation unit 54 may calculate the work stability z i The maximum work stability z max may be obtained as the work stability Z in the loading and excavation work.
[0056] The productivity acquisition unit 55 acquires the work stability Z calculated by the work stability calculation unit 54 as the productivity in the loading and excavation work.
[0057] Incidentally, in loading and excavation work, it is known that the responsiveness (dynamic characteristic X) and productivity (work stability Z) of the bucket 41 are approximated by an upwardly convex function G(X) regardless of the skill, as shown in Fig. 10. Therefore, the dynamic characteristic X for which the function G(X) is maximized (i.e., work stability Z is maximized) is the optimal dynamic characteristic.
[0058] In the following, as in the first embodiment, a procedure is illustrated for calculating optimal dynamic characteristics when the function of productivity (work stability Z) with dynamic characteristics as variables is unknown, using the known "steepest descent method" algorithm.
[0059] In the following, a procedure for calculating the optimal dynamic characteristics of an operation object in a loading excavation operation and updating the dynamic characteristics of the operation object to the optimal dynamic characteristics will be described with reference to the flowchart shown in FIG.
[0060] In the flowchart of Fig. 11, the processes of steps S20, S40, S50, and S80 differ from the processes of steps S2, S4, S5, and S8 in Fig. 6. Therefore, only the processes of steps S20, S40, S50, and S80 will be described below.
[0061] In step S20, the productivity acquisition unit 55 acquires the work stability Z1 calculated by the work stability calculation unit 54 as the productivity of the loading and excavation work in the dynamic characteristic X1.
[0062] In step S40, the productivity acquisition unit 55 acquires the work stability Z2 calculated by the work stability calculation unit 54 as the productivity of the loading and excavation work in the dynamic characteristic X2.
[0063] In step S50, the dynamic characteristic update unit 51 calculates the dynamic characteristic for update (dynamic characteristic X t+1 ) where the initial value of "t" is "2".
number
[0064] In the above formula 2, "Xt " is the currently set dynamic characteristic X2, and "X t-1 " is the previously set dynamic characteristic X1. Also, "Z t " is the work stability Z2 in the dynamic characteristic X2, and "Z t-1 " is the task stability Z1 in the dynamic characteristic X1. "η" is the learning rate for determining the learning speed (update speed).
[0065] That is, the dynamic characteristic update unit 51 updates the increase in the dynamic characteristic X (X t -X t-1 ) the inverse increase in work stability Z (1 / Z t -1 / Z t-1 ) multiplied by the learning rate η to obtain the current dynamics X t Update the dynamic characteristic X for updating t+1 Calculate the following.
[0066] In addition, in formula 2, "Z t The reciprocal of "1 / Z t " and "Z t-1 The reciprocal of "1 / Z t-1 " is used because it is known that the responsiveness (dynamic characteristic X) and productivity (work stability Z) of the bucket 41 are approximated by an upwardly convex function, as shown in FIG. 10.
[0067] In step S80, the productivity acquisition unit 55 calculates the work stability Z t+1 Dynamic characteristics X t+1 The productivity of loading and excavation work in the
[0068] According to the second embodiment described above, the optimal dynamic characteristic X is calculated based on the dynamic characteristic X1, the work stability Z1, the dynamic characteristic X2, and the work stability Z2. t+1 Therefore, the optimum dynamic characteristic X that maximizes the work stability Z according to the operator's skill is calculated. t+1 It is possible to set the dynamic characteristic X as the dynamic characteristic X. Therefore, it is possible to provide the operator with operability suited to the operator's operating skill.
[0069] According to the second embodiment described above, the work stability Z in the loading and excavation work is acquired as productivity. The work stability Z is calculated by the formula "Z=M×g×L1-F×L2". The work stability Z tends to be larger as the operator's skill is higher and smaller as the operator's skill is lower. Therefore, by acquiring the work stability Z as productivity and using it to calculate the optimal dynamic characteristics, it is highly likely that the optimal dynamic characteristics appropriate for the operator's skill can be calculated. Furthermore, the work stability Z tends to be smaller if the scaffolding of the machine is poor and larger if the scaffolding of the machine is good. Therefore, by acquiring the work stability Z as productivity and using it to calculate the optimal dynamic characteristics, it is highly likely that the optimal dynamic characteristics appropriate for the scaffolding of the machine can be calculated.
[0070] <3. Modifications> The operation target device according to the present invention is not limited to the above-described embodiment, and various modifications and improvements are possible within the scope of the claims.
[0071] For example, in each of the above-described embodiments, a random value is set as the dynamic characteristic X1 (initial value) in step S1, but this is not limited thereto, and an optimal dynamic characteristic that was previously set may be set as the initial value of the dynamic characteristic X1.
[0072] Specifically, as shown in FIG. 12, the hydraulic excavator 1 may be configured to include a controller 5 and a storage unit 7.
[0073] Here, the controller 5 includes a dynamic characteristic update unit 51, a task identification unit 52, and a productivity acquisition unit 55.
[0074] The work identification unit 52 is a processing unit that identifies the current work (excavation work, lifting work, etc.) being performed by the hydraulic excavator 1. Specifically, the work identification unit 52 identifies the current work of the hydraulic excavator 1 by using a learned program that has undergone machine learning using values from sensors provided in the hydraulic excavator 1 as input values and the type of work as an output value.
[0075] The storage unit 7 is a storage device that stores a set optimal dynamic characteristic table TB (see FIG. 13) in which optimal dynamic characteristics previously set (hereinafter also simply referred to as "set optimal dynamic characteristics") are stored for each task.
[0076] As shown in FIG. 13, in the set optimum dynamic characteristic table TB, work (specifically, work content) and set optimum dynamic characteristics are stored in association with each other.
[0077] Then, in step S1 of FIG. 7 and FIG. 11, the dynamic characteristic update unit 51 sets the already-set optimal dynamic characteristic associated with the task identified by the task identification unit 52 as the dynamic characteristic X1.
[0078] According to this modified example, an initial dynamic characteristic suitable for the task is set, so that the dynamic characteristic can be converged to the optimal dynamic characteristic more quickly than when a random value is set as the initial value of the dynamic characteristic X1 (in each of the above embodiments). [Industrial Applicability]
[0079] As described above, the operation target device according to the present invention is suitable for setting the dynamic characteristics of a hydraulic excavator. [Explanation of symbols]
[0080] 1. Hydraulic excavator 2 Undercarriage 3. Upper rotating body 4 Attachment 5. Controller 7 Memory section 41 Bucket 51 Dynamic characteristics update section 52 Work Type Identification Section 53 Work trajectory variance value calculation unit 54 Work stability calculation section 55 Productivity Acquisition Department TB Pre-configured optimal dynamic characteristics table
Claims
1. An operation target device, a dynamic characteristic update unit that calculates optimal or suboptimal dynamic characteristics of an operation object in a specific task in which a specific operation is repeated, and updates the dynamic characteristics of the operation object to the optimal dynamic characteristics; a work trajectory variance calculation unit that calculates a work trajectory variance value using work trajectory data acquired while the specific work is being performed; a productivity acquisition unit that acquires the work trajectory variance value calculated by the work trajectory variance value calculation unit as productivity; Equipped with The dynamic characteristic is a responsiveness, which is a variable related to the level of a reaction of the operation object to an operation by an operator; The dynamic characteristic update unit sets a first dynamic characteristic to the dynamic characteristic; the work trajectory variance calculation unit calculates a first work trajectory variance value using work trajectory data acquired while the specific work is being performed in a state in which the dynamic characteristic is set to the first dynamic characteristic; The productivity acquisition unit acquires the first work trajectory variance value as a first productivity, the dynamic characteristic update unit sets a second dynamic characteristic different from the first dynamic characteristic as the dynamic characteristic; the work trajectory variance calculation unit calculates a second work trajectory variance value using work trajectory data acquired while the specific work is being performed in a state in which the dynamic characteristic is set to the second dynamic characteristic; The productivity acquisition unit acquires the second work trajectory variance value as a second productivity, The operation target device, wherein the dynamic characteristic update unit calculates the optimal dynamic characteristic based on the first dynamic characteristic, the second dynamic characteristic, the first productivity, and the second productivity.
2. An operation target device, a dynamic characteristic update unit that calculates optimal or suboptimal dynamic characteristics of an operation object in a specific task in which a specific operation is repeated, and updates the dynamic characteristics of the operation object to the optimal dynamic characteristics; A work stability calculation unit that calculates work stability when the specific work is performed; a productivity acquisition unit that acquires the work stability calculated by the work stability calculation unit as productivity; Equipped with The dynamic characteristic is a responsiveness, which is a variable related to the level of a reaction of the operation object to an operation by an operator; The dynamic characteristic update unit sets a first dynamic characteristic to the dynamic characteristic; the task stability calculation unit calculates a first task stability when the specific task is performed in a state in which the dynamic characteristic is set to the first dynamic characteristic, The productivity acquisition unit acquires the first work stability as a first productivity, the dynamic characteristic update unit sets a second dynamic characteristic different from the first dynamic characteristic as the dynamic characteristic; the task stability calculation unit calculates a second task stability when the specific task is performed in a state in which the dynamic characteristic is set to the second dynamic characteristic, The productivity acquisition unit acquires the second work stability as a second productivity, The operation target device, wherein the dynamic characteristic update unit calculates the optimal dynamic characteristic based on the first dynamic characteristic, the second dynamic characteristic, the first productivity, and the second productivity.
3. A storage unit that stores a previously set optimal dynamic characteristic for each task, the optimal dynamic characteristic being a previously set optimal dynamic characteristic; A task identification unit that identifies a task; Further comprising: The operation target device according to claim 1 or 2, characterized in that the dynamic characteristic update unit acquires from the memory unit a set optimal dynamic characteristic corresponding to the task identified by the task identification unit, and uses the set optimal dynamic characteristic as the first dynamic characteristic.
Citation Information
Patent Citations
Control device for hydraulic drive machine
JP2007051781A
Automatic operation system
JP2017138282A
Construction machine
JP2019108721A
Automatic travel control apparatus, automatic travel control method and automatic travel controlling program
JP2020082752A
System and method for calculating instantaneous placement corrections to achieve towed implement placement on curved paths
US20080004778A1