Power generation system, control device, control method, and program

The power generation system stabilizes generator operation through controlled power consumption adjustments using multiple simulated loads, addressing load fluctuations and maintaining power factor for prolonged stability.

JP7572459B2Active Publication Date: 2024-10-23JFE ENGINEERING CORP
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2022573381
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Priority Date
2021-11-04
Filing Date
2022-11-02
Publication Date
2024-10-23
Estimated Expiration
2042-11-02

AI Technical Summary

Technical Problem

Conventional power generation systems face challenges in stabilizing generator operation due to fluctuations in power load, leading to issues such as decreased power factor, generator failure, and reduced operational lifespan, particularly during transitions from commercial power sources.

Method used

A power generation system with a control device that manages power consumption using multiple simulated loads, adjusting their capacity steplessly or incrementally to match generator output, ensuring stable operation by maintaining power factor and preventing generator shutdown.

Benefits of technology

The system enables stable generator operation over extended periods by managing power load fluctuations, preventing generator trips and extending operational life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007572459000001
    Figure 0007572459000001
  • Figure 0007572459000002
    Figure 0007572459000002
  • Figure 0007572459000003
    Figure 0007572459000003
Patent Text Reader

Abstract

A purpose of the present invention is to activate and operate in a stable manner an electric power generator that is required after a supply of electric power from a commercial electric power grid or a commercial electric power supply has stopped. The present invention comprises: an electric power generator that controls generated electric power by being driven by an engine provided with a speed regulator; a dummy load having a load capacity that is set such that the dummy load is capable of consuming generated electric power of the electric power generator when the engine is driving, and is capable of regulating electric power consumption; a dummy-load-regulating unit configured so as to be capable of regulating the electric power consumption of the dummy load; and a control unit capable of controlling the electric power consumption of the dummy load by controlling the dummy-load-regulating unit. A plurality of pairs of dummy loads and dummy-load-regulating units are provided. At an activation time of the electric power generator, the control unit controls at least part of the dummy loads among the plurality of dummy loads, so as to power on said dummy loads with respect to the electric power generator, said dummy loads having a load capacity set to be equal to or greater than a load having a predetermined electric power consumption that does not cause tripping to occur in an activation operation of the electric power generator.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a power generation system, a control device, a control method, and a program. [Background technology]

[0002] In some facilities where electric loads such as electrical equipment are installed, a power generation system that generates power by connecting to a commercial power system and supplies the generated power to the power load is provided. Patent Document 1 discloses a technology for such a power generation system, in which, during a power outage when power reception from the commercial power system or a regular power source is stopped, the generator is disconnected from the commercial power system or the regular power source, and an internal combustion engine that drives the generator is started to operate the generator independently, and when the generator's generation voltage is established and stable power generation is possible, a specific load of part or all of the power load to be supplied during the power outage is input to the generator. In such a power generation system, it is required to be able to establish the generator's generation voltage and input the power load in a short time, for example, within 40 seconds, after power reception from the commercial power system or the regular power source is stopped (see Non-Patent Document 1).

[0003] Patent Document 2 discloses a technique for executing simulated load control that controls the power consumption of a first simulated load to be equal to that of a second simulated load by a simulated load control means, a first simulated load power consumption adjustment means, and a second simulated load power consumption adjustment means. Patent Document 3 discloses a configuration that includes a power load power consumption measurement means that measures the power consumption of a power load, a simulated load that consumes power generated by a generator, a simulated load power consumption adjustment means that can change the power consumption of the simulated load, and a simulated load control means that controls the simulated load power consumption adjustment means based on the measurement result of the power load power consumption measurement means so that the power generated by the generator is maintained at or above a predetermined reference power generation power that allows stable operation of the engine. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2007-6595 A [Patent Document 2] JP 2017-184485 A [Patent Document 3] JP 2015-109746 A [Non-patent literature]

[0005] [Non-Patent Document 1] Japan Internal Combustion Power Generation Equipment Association, "Technical Standards for Disaster Prevention Private Power Generating Equipment" (issued May 1, 2018), page 8 Summary of the Invention [Problem to be solved by the invention]

[0006] In the power generation system according to the above-mentioned conventional technology, the power load fluctuates due to the application or interruption of the power load. In order to stabilize the operation of the generator against the fluctuation of the power load, it is necessary to apply a load in advance using a dummy load. Here, when applying the dummy load in advance, in order to arbitrarily adjust the output of the dummy load, it is necessary to provide a power regulator between the generator and the dummy load for adjusting the power consumption of the dummy load, as disclosed in Patent Documents 2 and 3.

[0007] However, when the power regulator is provided and power regulation control is performed on the dummy load in the power generation system, harmonics that distort the current waveform are generated, which may lower the power factor of the generator. If the power factor of the generator is lowered, it becomes difficult to maintain the operation of the generator when starting it up or continuing its operation, and the generator may stop before inputting the actual power load that consumes the power from the generator.

[0008] Even if the power factor can be maintained, depending on how the power consumption of the simulated load is input, the mechanical load on the generator itself may increase, causing the generator to break down, or abnormal noise from the turbocharger or disturbances in the power waveform that may lead to a breakdown, and the stable operating life of the generator may be shortened, which may hinder stable operation. Therefore, there is a demand for a technology that can stably start and operate the generator for a long period of time after the reception of power from the commercial power system or normal power source is stopped.

[0009] The present invention has been made in consideration of the above, and an object of the present invention is to provide a power generation system, a control device, a control method, and a program that can stably start and operate a generator over a long period of time, as required after power reception from a commercial power system or a normal power source is stopped. [Means for solving the problem]

[0010] (1) In order to solve the above-mentioned problems and achieve the object, a power generation system according to one aspect of the present invention includes a generator that controls generated power by driving a power engine equipped with a governor, a simulated load that is capable of consuming the generated power of the generator while the power engine is operating and has a predetermined load capacity set so that the power consumption can be adjusted, a simulated load adjuster configured to adjust the power consumption of the simulated load so as to increase the power consumption of the simulated load from 0 to the set predetermined load capacity, and a control unit that is capable of controlling the power consumption of the simulated load by controlling the simulated load adjuster, wherein the simulated load and the simulated load adjuster are provided in a plurality of pairs, and the plurality of pairs of the simulated loads are configured such that a sum of the predetermined load capacities of the simulated loads constituting the plurality of pairs is approximately equal to a set output of the generator, and the simulated load adjuster is configured to adjust the power consumption of the simulated load. the control unit outputs an adjustment signal to each of the plurality of simulated load adjusting units to perform control including at least a first input control for inputting one of the plurality of simulated loads to the generator so as to instantaneously increase the load capacity of the generator from 0 to the predetermined load capacity in a stepless manner at the start of the generator, a maintenance control for maintaining the predetermined load capacity of the one simulated load from after the first input control until the generated power of the generator becomes stable, and a second input control for increasing another one of the plurality of simulated loads different from the one simulated load to the predetermined load capacity so as to satisfy a load increase rate greater than 0% / min and less than or equal to 60% / min after the maintenance control.

[0011] (2) In one embodiment of the power generation system of the present invention, in the above-mentioned (1) invention, the second input control is a control that increases the load of the dummy load in a stepped or linear manner to the specified load capacity.

[0012] (3) In a power generation system according to an aspect of the present invention, in the invention of (1) or (2) above, two or more pairs of the dummy load and the dummy load adjuster are provided.

[0013] (4) In one embodiment of the power generation system of the present invention, in the above-mentioned (3) invention, the load increase rate of the simulated load input by the second input control is increased to the specified load capacity so as to satisfy the conditions of greater than 0% / min and not exceeding 45% / min.

[0014] (5) In a power generation system according to one embodiment of the present invention, in any one of the above (1) to (4), after the application of the multiple simulated loads to the generator is completed, the control unit controls the simulated load adjustment unit to start supplying generated power by the generator to a power load different from the simulated load, and to increase or decrease the power consumption of the simulated load in response to fluctuations in power consumption due to the power load.

[0015] (6) A control device according to one aspect of the present invention is a control device including a control unit capable of controlling a plurality of simulated loads capable of consuming the generated power of a generator that controls the generated power by driving a power engine equipped with a governor and having a predetermined load capacity set so that the power consumption can be adjusted, and a plurality of simulated load adjustment units configured to be adjustable so as to increase the power consumption of the plurality of simulated loads individually from 0 to the set predetermined load capacity, and provided in pairs with the plurality of simulated loads, wherein the simulated loads and the simulated load adjustment units are provided as a plurality of pairs, the sum of the predetermined load capacities of the simulated loads constituting the plurality of pairs is approximately equal to the set output of the generator, and each pair of the simulated loads and the simulated load adjustment unit controls the generator. The control unit is configured to be able to supply adjusted loads independently of each other, and performs control including at least a first supply control for supplying one of the multiple simulated loads to the generator at startup so that the load capacity of the generator is instantaneously increased steplessly from 0 to the specified load capacity by outputting an adjustment signal to each of the multiple simulated load adjustment units, a maintenance control for maintaining the specified load capacity of the one simulated load from after the first supply control until the generated power of the generator stabilizes, and a second supply control for increasing another one of the multiple simulated loads, different from the one simulated load, to the specified load capacity so that a load increase rate is greater than 0% / min and is not greater than 60% / min after the maintenance control.

[0016] (7) A control method according to one aspect of the present invention is a control method executed by a control unit capable of controlling a plurality of simulated loads capable of consuming generated power of a generator that controls generated power by driving a power engine equipped with a speed governor and having a predetermined load capacity set so that power consumption can be adjusted, and a plurality of simulated load adjusters configured to adjust the power consumption of the plurality of simulated loads so as to increase the power consumption of each of the plurality of simulated loads from 0 to the set predetermined load capacity, the simulated loads and the simulated load adjusters being provided in pairs with the plurality of simulated loads, the plurality of simulated loads and the simulated load adjusters being provided in pairs, the sum of the predetermined load capacities of the simulated loads constituting the plurality of sets being approximately equal to a set output of the generator, and each pair of the simulated loads and the simulated load adjusters being configured to adjust the power consumption of the plurality of simulated loads to the generator, and the control unit outputs an adjustment signal to each of the plurality of simulated load adjusting units to perform control including at least a first input control for inputting one of the plurality of simulated loads at the start of the generator so as to instantaneously increase the load capacity of the generator from 0 to the predetermined load capacity in a stepless manner, a maintenance control for maintaining the predetermined load capacity of the one simulated load from after the first input control until the power generated by the generator becomes stable, and a second input control for increasing another one of the plurality of simulated loads, different from the one simulated load, to the predetermined load capacity so as to satisfy a load increase rate greater than 0% / min and equal to or less than 60% / min after the maintenance control.

[0017] (8) A program according to one aspect of the present invention is capable of controlling a plurality of simulated loads capable of consuming power generated by a generator that controls the generated power by driving a power engine equipped with a speed governor, the simulated loads having a predetermined load capacity set so as to adjust the power consumption, and a plurality of simulated load adjusters configured to adjust the power consumption of the plurality of simulated loads so as to increase the power consumption of each of the plurality of simulated loads from 0 to the predetermined load capacity set individually, the simulated loads and the simulated load adjusters being provided as a pair in a plurality of sets, the plurality of sets of the simulated loads being each provided as a pair, the sum of the predetermined load capacities of the simulated loads constituting the plurality of sets being approximately equal to a set output of the generator, and each pair of the simulated loads and the simulated load adjusters being adjusted to the generator. A control unit that can control the simulated loads to be turned on independently of each other outputs an adjustment signal to each of the multiple simulated load adjustment units to perform a first turning-on control for turning on one of the multiple simulated loads at the start of the generator so that the load capacity of the generator is instantaneously increased from 0 to the specified load capacity in a stepless manner, a maintenance control for maintaining the specified load capacity of the one simulated load from after the first turning-on control until the generated power of the generator stabilizes, and a second turning-on control for increasing another one of the multiple simulated loads, different from the one simulated load, to the specified load capacity so that a load increase rate is greater than 0% / min and is not greater than 60% / min after the maintenance control. Effect of the Invention

[0018] The power generation system, control device, control method, and program of the present invention make it possible to stably start up and operate the generator over a long period of time, as required after the reception of power from a commercial power system or a normal power source is stopped. [Brief description of the drawings]

[0019] [Figure 1] FIG. 1 is a block diagram showing a power generation system according to an embodiment of the present invention. [Diagram 2]FIG. 2 is a block diagram showing a control device for a power generation system according to an embodiment of the present invention. [Diagram 3] FIG. 3 is a graph showing an example of control by the control device of the power generation system according to the embodiment of the present invention. [Figure 4] FIG. 4 is a graph showing the relationship between the input rate of the dummy load and the power factor of the engine generator when one dummy load is controlled. [Diagram 5] FIG. 5 is a graph showing the relationship between the input rate of the dummy loads and the power factor of the engine generator when a plurality of dummy loads are controlled simultaneously. [Figure 6] FIG. 6 is a graph showing the relationship between the input rate of the dummy loads and the power factor of the engine generator when a plurality of dummy loads are individually controlled. [Figure 7] FIG. 7 is a flowchart for explaining a control method performed by the control device of the power generation system according to the embodiment of the present invention. [Figure 8] FIG. 8 is a graph for explaining a control method by the control device of the power generation system according to the first embodiment of the present invention. [Figure 9] FIG. 9 is a graph showing the input rate of a dummy load, the output of the generator, and the power factor of the generator, for explaining the effect of the power generation system according to the first embodiment of the present invention. [Figure 10] FIG. 10 is a graph showing the load setting rate and the power generation output for each load increase rate in the power generation system according to the first embodiment of the present invention. [Figure 11] FIG. 11 is a table for explaining the effects of the power generation system according to the first embodiment of the present invention. [Figure 12] FIG. 12 is a table explaining the definition of the table shown in FIG. [Figure 13] FIG. 13 is a graph for explaining a control method by the control device of the power generation system according to the second embodiment of the present invention. [Figure 14] FIG. 14 is a graph for explaining a control method by the control device of the power generation system according to the third embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0020] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. In all the drawings of the following embodiments, the same or corresponding parts are denoted by the same reference numerals. Furthermore, the present invention is not limited to the embodiment described below.

[0021] First, a power generation system according to an embodiment of the present invention will be described. The embodiment described below relates to a power generation system including an engine generator, a dummy load, and a control unit, but other power generation systems may also be used. The engine generator 20 generates power by driving an internal combustion engine 21 provided with a governor (not shown). During power generation in which the generated power is supplied to the power load 50, the engine generator 20 is controlled by a predetermined engine control unit (not shown) so that the output becomes an arbitrary output equal to or lower than the rated output. The power generation system according to the embodiment of the present invention is a system in which a control device 10 increases or decreases the power consumption of the dummy load so as to reduce changes in the generated power of the engine generator 20 due to the input or output of the power load 50, the cutoff operation, or a change in the operating load factor. FIG. 1 is a block diagram showing the configuration of the power generation system according to this embodiment.

[0022] As shown in FIG. 1, a power generation system 1 according to the embodiment includes a control device 10, an engine generator 20, a group of simulated loads 30 regulated by a simulated load power consumption regulator 31, a commercial power system 40, and a power load 50.

[0023] In the power generation system 1, a generated power measurement unit 61 capable of measuring the output power is provided on the output side of the engine generator 20. A power load power consumption measurement unit 62 capable of measuring the supplied power is provided on the input side of the power load 50. A simulated load power consumption measurement unit 63 capable of measuring the supplied power is provided on the input side of the simulated load power consumption regulator 31.

[0024] The engine generator 20 as a generator has an internal combustion engine 21 and a generator 22. The engine generator 20 is configured to generate power by generating rotational motion by an engine as an internal combustion engine using fuel to rotate a rotor of the generator 22. Note that the internal combustion engine 21 is not limited to the internal combustion engine 21 such as an engine, so long as it is an engine capable of generating power by the generator 22. Note that the internal combustion engine 21 is merely an example, and instead of the internal combustion engine 21, it is possible to employ an external combustion engine such as a steam turbine or a gas turbine, or another power engine equipped with a speed governor and capable of generating power.

[0025] The simulated load group 30 includes a plurality of simulated loads 301, 302, 303, and 304. Each of the simulated loads 301 to 304 is formed of, for example, a load resistor that consumes a predetermined amount of power. Each of the simulated loads 301 to 304 is a load that consumes at least a portion of the power generated by the engine generator 20 to suppress and stabilize the fluctuation of the power generated by the engine generator 20, and is provided independently of the power load 50. The simulated loads 301 to 304 are common to the power load 50 in that they are loads that consume the power generated by the engine generator 20.

[0026] The simulated load power consumption regulator 31 as a simulated load adjusting unit is a device that adjusts the power consumed by the simulated load group 30 based on an adjustment signal input from the control device 10. The simulated load power consumption regulator 31 is configured to have simulated load adjusters 311, 312, 313, and 314 corresponding to the simulated loads 301 to 304, respectively, and is configured to be able to control the multiple simulated loads 301 to 304 independently. That is, the simulated loads 301 to 304 are configured to be able to adjust the magnitude of the load by the simulated load adjusters 311 to 314, respectively. As a result, the simulated load adjusters 311 to 314 are configured to be able to adjust the power consumption of the simulated loads 301 to 304 based on an adjustment signal input from the control device 10, respectively. In other words, the simulated load power consumption regulator 31 is configured to be able to adjust the power consumption of the simulated load group 30 so as to increase it from 0 to a predetermined load capacity that has been set. The adjustment signal includes information for controlling the increase or decrease of the power consumption of the simulated loads 30 .

[0027] In this embodiment, the simulated load group 30 is configured to have four simulated loads 301 to 304, but may have a number other than four as long as it has a plurality of simulated loads. In addition, in order to efficiently execute a control method described later, the number of simulated loads is typically 2 to 10, preferably 3 to 6, and more preferably 4 or 5. In this case, the simulated load adjusters are also provided in correspondence with the number of installed simulated loads, and are provided in pairs with the simulated loads. That is, the number of pairs of simulated loads and simulated load adjusters is typically 2 to 10, preferably 3 to 6, and more preferably 4 or 5. In addition, each of the simulated loads 301 to 304 can be set to a predetermined load capacity so that it can consume the generated power of the engine generator 20 while the internal combustion engine 21 is running, and can adjust the power consumption.

[0028] The commercial power system 40 is, for example, a power system from a power company. In this specification, the commercial power system 40 also includes regular power sources. The power load 50 is a load to which power required to operate equipment is supplied, and is specifically, for example, a load such as a pump or a motor. The power load 50 is not limited to, for example, a pump or a motor, and various types of loads known in the art may be used.

[0029] The generated power measurement unit 61 is a power meter connected to a power supply line connected to the engine generator 20, and outputs a measurement value of the generated power output by the engine generator 20 to the control device 10. The power load power consumption measurement unit 62 is a power meter connected to a power supply line connected to the power load 50, and outputs a measurement value of the power consumption consumed by the power load 50 to the control device 10. The simulated load power consumption measurement unit 63 is a power meter connected to a power supply line connected to the simulated load group 30 or the simulated load power consumption regulator 31, and outputs a measurement value of the power consumption consumed by the simulated load group 30 to the control device 10. Note that a plurality of simulated load power consumption measurement units 63 may be provided on the input side of each of the simulated loads 301 to 304, corresponding to each of the simulated loads 301 to 304. In addition, the generated power measurement unit 61, the power load power consumption measurement unit 62, and the simulated load power consumption measurement unit 63 are not limited to power meters, and various measuring instruments such as ammeters can be adopted as long as they are measuring instruments capable of evaluating the increase and decrease of power.

[0030] The control device 10 is a device that acquires measured values ​​of the generated power of the engine generator 20, the power consumption of the power load 50, and the power consumption of the simulated load group 30, and controls the increase / decrease in the power consumption of the simulated load group 30 by a simulated load power consumption regulator 31. Fig. 2 is a block diagram showing the control device 10 of the power generation system 1 according to this embodiment.

[0031] 2, the control device 10 includes a judgment control unit 11, an adder unit 12, a difference calculation unit 13, a control sensitivity calculation unit 14, a control output calculation unit 15, and a memory unit 16. Measurement values ​​are input to the control device 10 from a generated power measurement unit 61, a power load power consumption measurement unit 62, and a simulated load power consumption measurement unit 63. The control device 10 outputs control signals (adjustment signals) to each of the simulated load adjusters 311-314 of the simulated load power consumption adjuster 31.

[0032] The judgment control unit 11, the addition unit 12, the difference calculation unit 13, the control sensitivity calculation unit 14, and the control output calculation unit 15 specifically include a processor having hardware, such as a CPU (Central Processing Unit), a DSP (Digital Signal Processor), or an FPGA (Field-Programmable Gate Array), and a main memory unit, such as a RAM (Random Access Memory) or a ROM (Read Only Memory) (none of which are shown).

[0033] The storage unit 16 is composed of a storage medium selected from a volatile memory such as a RAM, a non-volatile memory such as a ROM, an erasable programmable ROM (EPROM), a hard disk drive (HDD, Hard Disk Drive), and a removable medium. The removable medium is, for example, a universal serial bus (USB) memory, or a disk recording medium such as a compact disc (CD), a digital versatile disc (DVD), or a Blu-ray (registered trademark) disc (BD). The storage unit 16 may also be configured using a computer-readable recording medium such as an externally mountable memory card. The storage unit 16 can store an operating system (OS), various programs, various tables, various databases, and the like for executing the operation of the control device 10. Here, the various programs include a power increase / decrease control program for realizing the increase / decrease control of the power consumption of the simulated load group 30 according to this embodiment. These various programs can also be recorded on computer-readable recording media such as a hard disk, a flash memory, a CD-ROM, a DVD-ROM, and a flexible disk, and widely distributed.

[0034] In the control device 10, a program stored in the storage unit 16 is loaded into a working area of ​​the main storage unit, and executed, and each component unit is controlled through the execution of the program, thereby realizing a function that meets a predetermined purpose. In this embodiment, the control device 10 executes the program to perform the processes of the judgment control unit 11, the addition unit 12, the difference calculation unit 13, the control sensitivity calculation unit 14, and the control output calculation unit 15.

[0035] The determination control unit 11 determines and selects a control mode based on the measurement value of the generated power obtained from the generated power measurement unit 61 and the measurement value of the power consumption obtained from at least one of the power load power consumption measurement unit 62 and the simulated load power consumption measurement unit 63. The determination control unit 11 outputs a control signal (adjustment signal) to the simulated load power consumption regulator 31 to control it based on the selected control mode.

[0036] The determination control unit 11 in the power generation system 1 according to this embodiment has, for example, the following three power control mode units. The determination control unit 11 of the control device 10 included in the power generation system 1 according to this embodiment functions as a main control unit that executes the following power control modes. Specifically, first, the determination control unit 11 selects one control mode unit from, for example, the first power control mode unit 111, the second power control mode unit 112, and the third power control mode unit 113. Next, the determination control unit 11 controls each of the simulated load adjusters 311 to 314 of the simulated load power consumption adjuster 31 based on the power control mode executed by the selected power control mode unit. This controls the power consumption of each of the simulated loads 301 to 304, thereby controlling the overall power consumption of the simulated load group 30. Here, the details of each power control mode executed by the first power control mode unit 111, the second power control mode unit 112, and the third power control mode unit 113 will be described.

[0037] The first power control mode executed by the determination control unit 11 by selecting the first power control mode unit 111 is a power control mode in which the discharged power starts to decrease. That is, during a power outage in the commercial power system 40, the load power of the power load 50 may transiently increase, for example, from the start of input. In this case, the first power control mode unit 111 of the determination control unit 11 controls the simulated load power consumption regulator 31 to change the power consumption (discharged power) of the simulated load group 30 to decrease by an amount corresponding to an increase in the load power of the power load 50. As a result, the discharged power is reduced in accordance with the load power consumed by the power load 50, and the generated power of the engine generator 20 can be maintained substantially constant.

[0038] The second power control mode executed by the determination control unit 11 by selecting the second power control mode unit 112 is a power control mode in which the decrease or increase in the discharged power of the simulated load group 30 is stopped for a predetermined time, and the load of the simulated load group 30 is kept constant for a predetermined time. In other words, the second power control mode unit 112 controls the simulated load power consumption regulator 31 to keep the discharged power of the simulated load group 30 in a state where it does not decrease or is constant.

[0039] The third power control mode executed by the third power control mode unit 113 is a power control mode for increasing the discharge power of the simulated load group 30. That is, the third power control mode unit 113 controls the simulated load power consumption regulator 31 to increase the discharge power of the simulated load group 30. During a power outage in the commercial power system 40, the load power of the power load 50 may continue to decrease asymptotically. In this case, the third power control mode unit 113 controls the simulated load power consumption regulator 31 to increase the discharge power of the simulated load group 30 at an increase rate greater than the absolute value of the increase rate of the load power consumed by the power load 50, i.e., the decrease rate. In other words, the generated power, which has decreased following the decrease in the load power of the power load 50, is adjusted by making the increase rate of the discharge power of the simulated load group 30 greater than the decrease rate of the load power of the power load 50. This allows the generated power of the engine generator 20 to be maintained approximately constant.

[0040] The control for keeping the generated power by the engine generator 20 substantially constant by switching between the first power control mode, the second power control mode, and the third power control mode is referred to as power increase / decrease control for the engine generator 20.

[0041] The adder 12 acquires and adds the measurement value of the power load power consumption measurement unit 62 and the measurement value of the simulated load power consumption measurement unit 63, and outputs the sum to the difference calculation unit 13. In other words, the adder 12 outputs the total power consumption of the simulated load group 30 and the power load 50 to the difference calculation unit 13.

[0042] The difference calculation unit 13 calculates the difference between the total power consumption of the simulated loads 30 and the power load 50 and the power generated by the engine generator 20, and outputs the result to the control output calculation unit 15. In other words, the difference calculation unit 13 is a calculation unit that calculates the difference between the power consumption and the power generation. By calculating the difference between the power generation and the power consumption, the difference calculation unit 13 can calculate a control value for the power consumption of the simulated loads 30 that is required to keep the power generated by the engine generator 20 approximately constant.

[0043] The control sensitivity calculation unit 14 calculates the sensitivity at which the control value of the power consumption of the simulated load group 30 required to keep the generated power approximately constant, which is found by the difference calculation unit 13, is output to the simulated load power consumption regulator 31. That is, the control sensitivity calculation unit 14 calculates the sensitivity at which the control value of the power consumption of the simulated load group 30 should be output. The control sensitivity calculation unit 14 outputs information on the sensitivity obtained by the calculation to the control output calculation unit 15.

[0044] The control output calculation unit 15 generates control information including a control value of the power consumption of the simulated load group 30 required to keep the generated power approximately constant, obtained by the difference calculation unit 13, and sensitivity information obtained by the control sensitivity calculation unit 14. The control output calculation unit 15 outputs the generated control information to the judgment control unit 11. The judgment control unit 11 converts the control information obtained by the control output calculation unit 15 to be output to the simulated load power consumption regulator 31 into an appropriate control signal and outputs it to the simulated load power consumption regulator 31.

[0045] Next, a method for controlling power consumption (hereinafter referred to as discharged power) by the group of dummy loads 30 will be described as a control method executed by the control device 10 configured as described above. First, in order to facilitate understanding of the method for controlling power consumption by the group of dummy loads 30 according to this embodiment, the inventor's thorough investigation will be described. Fig. 3 is a graph showing an example of control of the engine generator 20 by the engine control unit (not shown) and the control device 10 of the power generation system 1 according to this embodiment.

[0046] First, as shown in FIG. 3, it is assumed that the engine generator 20 is disconnected from the power load 50 when a power outage is detected in a facility having the power load 50 or in a commercial power system 40. With the power load 50 disconnected from the engine generator 20, the engine control unit (not shown) operates the engine generator 20 at a no-load rated speed to stabilize it. Thereafter, the control device 10 starts a load-up operation of the engine generator 20 using a simulated load. In this specification, the load-up operation of the engine generator 20 using the simulated load group 30 from a state in which the power load 50 is disconnected from the engine generator 20 and the engine generator 20 is stable by operating at a no-load rated speed is referred to as "startup". As a result, the engine generator 20 starts discharging power and the output increases. When a predetermined startup time has elapsed from the startup start time T1 when the engine generator 20 starts to start up, the startup operation of the engine generator 20 ends. At the end of the startup operation, the engine generator 20 settles and the generated power becomes stable, making it possible to input the power load 50 (stable time T2). When the generated power of the engine generator 20 becomes stable and a stable time point T2 has passed, application of the power load 50 starts (load application start time point T3).

[0047] When the power load 50 is applied to the power generated by the engine generator 20 at the load application start time T3, the control device 10 executes power increase / decrease control and adjusts the discharged power according to the load power consumed by the power load 50. In this embodiment, the power generated by the engine generator 20 can be maintained approximately constant by increasing / decreasing the discharged power in response to an increase / decrease in the load power according to the following formula (A). As a result, in the power generation system 1, the engine generator 20 can be operated at a constant load by controlling the increase / decrease in the discharged power, thereby preventing the internal combustion engine 21 in the engine generator 20 from stalling due to large load fluctuations. Discharged power = generated power - load power ... (A)

[0048] Here, at the start of the startup of the engine generator 20, it is preferable to linearly increase the power consumption by the dummy load in order to increase the load only by the dummy load and to stably increase the load of the engine generator 20. However, the present inventor has found that when starting the engine generator 20 in a conventional power generation system, if the power consumption by the dummy load is linearly increased in order to increase the load only by the dummy load and to stably increase the load of the engine generator 20, the power factor may suddenly decrease and the engine generator 20 may trip. That is, the present inventor has found that when the engine generator 20 is started at the startup start time T1, the engine generator 20 may trip in the time period (start-up period δ1) shown in FIG. 3.

[0049] Therefore, the present inventor started the engine generator 20 with a predetermined load (hereinafter, initial load) applied in advance using a load equivalent to the power load 50, and conducted an experiment on the relationship between the load application rate MV (%) of the simulated load group 30 and the power factor of the engine generator 20. In this specification, the load application rate (MV) (%) is defined as the ratio (%) of the output of the simulated load to the set output, but since this is almost synonymous with the load setting rate, it will be referred to as the load setting rate (hereinafter, also referred to as MV) (%). Figures 4, 5, and 6 are graphs showing the relationship between the application rate of the simulated load and the power factor of the engine generator in experiments conducted by the present inventor on the power generation system 1 in the cases where one simulated load was provided, where multiple simulated loads were provided, and where multiple simulated loads were individually controlled, respectively.

[0050] First, the inventor performed an experiment using one of the simulated loads 301 in the group of simulated loads 30. Here, the initial load was set to 20%, 15%, 10%, and 5% of the set output of the engine generator 20, respectively. The results are shown in FIG. 4. The maximum load of the simulated load 301 was set to 150 kW. The set output is also called the specified output. Here, the set output is the total capacity of the group of simulated loads 30 required to stabilize the operation of the engine generator 20 against fluctuations in the power load when the power generation equipment is operated independently during a power outage. Moreover, unlike the power load 50 consumed when the facility is operated independently during a power outage, the group of simulated loads 30 is a load that is not necessarily required for the facility. In addition, when a load resistor is used, for example, the discharged power shown in FIG. 3 is converted into heat and discharged into the atmosphere, which is inefficient in terms of energy. As a result, the total capacity of the simulated load group 30 must be determined by, first, ensuring the total capacity of the power loads 50 consumed when the facility operates autonomously during a power outage, and second, the minimum capacity that can maintain stable operation of the power generation equipment even if a transient power fluctuation occurs due to the starting method of each power load. Furthermore, since the total capacity of the power loads 50 is the capacity that can reliably supply power in the power generation equipment, it is less than the rated output, and depending on the facility, when connected to the commercial power system 40, in addition to supplying power to the power loads 50 of the equipment, it may also sell power. Therefore, the set output does not necessarily match the rated output of the power generation equipment, and the set output may be less than the rated output (set output < rated output).

[0051] From FIG. 4, it can be seen that when the initial load is set to 20%, the power factor decreases from 1 as the MV of the simulated load 301 increases from 0%, and the power factor decreases to a minimum of about 0.93 at MV (%) of about 40% to 50%. It can also be seen that the power factor increases from 0.93 to 1 as the MV of the simulated load 301 increases from 40%. Similarly, when the initial load is set to 15%, it can be seen that the power factor decreases to a minimum of about 0.9 at MV (%) of about 40% and then increases to 1 while the MV of the simulated load 301 increases from 0% to 100%. When the initial load is set to 10%, it can be seen that the power factor decreases to a minimum of about 0.85 at MV (%) of about 40% and then increases to 1 while the MV of the simulated load 301 increases from 0% to 100%. Here, the present inventors conducted further investigation and discovered that the reason why the power factor becomes minimum when the MV (%) of the dummy load 301 is about 40% to 50% is due to the generation of harmonics.

[0052] Furthermore, when the initial load is set to 5%, if the MV of the simulated load 301 is increased from 0%, the serious fault notification condition cosθ min It was found that the engine generator 20 trips when the initial load is set to 30 kW or less when the set output of the engine generator 20 is 600 kW. Specifically, it was found that if the initial load is set to 30 kW or less, it becomes difficult to increase the MV (%) of the simulated load 301 and increase the load to 100% (hereinafter, referred to as load increase). In other words, the initial load should be set to 0%, but even if the initial load is set to 5%, the power factor drops sharply as the MV of the simulated load 301, i.e., the power consumption setting, is increased, and the engine generator 20 reaches a severe failure condition. Therefore, it was found that it is extremely difficult to increase the load of the engine generator 20 with the initial load set to 0%.

[0053] The inventors conducted an experiment in which a plurality of simulated loads, for example the plurality of simulated loads 301 and 302, were provided, and the simulated loads 301 and 302 were both increased in load to start the engine generator 20. The maximum load for the two simulated loads 301 and 302 was (2×150=) 300 kW. The results are shown in FIG. 5. From FIG. 5, it can be seen that even in this case, the tendency of the engine generator 20 in increasing the load is the same as that in FIG. 4. Furthermore, when the initial load is set to 10%, if the MV (%) of the simulated load 301 is increased from 0%, the serious fault alarm condition cosθ min It was found that the engine generator 20 would trip at or below this value. Specifically, it was found that when the set output of the engine generator 20 is 600 kW, it becomes difficult to increase the load of the engine generator 20 if the initial load is set to 60 kW or less.

[0054] Furthermore, the inventor conducted an experiment in which a plurality of simulated loads, for example the plurality of simulated loads 301-304, were provided, and the MV(%) of the simulated loads 301-304 was increased from 0% to 100% one by one to increase the load on the engine generator 20. The simulated loads 301-304 each had a load of 150 kW. The results are shown in FIG. 6. From FIG. 6, it can be seen that even in this case, the tendency of the load increase on the engine generator 20 is similar to that in FIG. 4. That is, when the MV(%) of the plurality of simulated loads 301-304 is increased one by one, the condition becomes equivalent to that in FIG. 4 at the stage of the first simulated load 301. Therefore, when the MV(%) of the simulated load 301 is increased from 0%, the serious fault alarm condition cosθ min If the temperature drops below this level, the engine generator 20 will trip.

[0055] Based on the above experiments, the inventor further conducted intensive research and came up with a control method for realizing load increase at startup without tripping the engine generator 20. That is, the inventor came up with a control method in which a plurality of dummy loads that can be independently applied to the engine generator 20 are provided, and when the plurality of dummy loads are applied to the engine generator 20, the load capacity of the first dummy load as a portion of the dummy loads is instantaneously increased steplessly to a preset load capacity, and the remaining dummy loads, that is, the second and subsequent dummy loads, are sequentially increased one by one to their preset load capacities. Here, the load capacity at which the first dummy load is increased steplessly is selected to be equal to or lower than the load capacity at which the engine generator 20 does not trip due to frequency drop or undervoltage caused by load application. In this embodiment, for example, when the dummy loads are each configured with a load resistor and the total load capacity is about 400 kW, the upper limit of the load capacity at which the engine generator 20 does not trip is 25% (about 145 kW) of the rated output (585 kW) in the case of the engine generator 20. Therefore, the total load capacity is equally shared among the four simulated loads, that is, each load capacity is about 100 kW. The present invention described below was devised by the inventor through the above-mentioned intensive studies.

[0056] Next, a control method by the control device 10 in the first embodiment of the present invention will be described. Fig. 7 is a flowchart for explaining the control method by the control device in the first embodiment. Fig. 8 is a graph showing an example of control corresponding to Fig. 7 by the control device 10 in the first embodiment. ST shown in Fig. 8 corresponds to the step shown in Fig. 7. The flowchart shown in Fig. 7 starts with the start-up of the engine generator 20 after the commercial power grid 40 goes into a power outage state and the engine generator 20 is disconnected from the power load 50.

[0057] As shown in FIG. 7 and FIG. 8, in step ST1, the control device 10 outputs an adjustment signal to the simulated load power consumption regulator 31 to apply a load to one of the multiple simulated loads 301 to 304 at the start of the engine generator 20. Note that "at the start of the engine generator 20" means a short time interval before and after a time when a predetermined engine control unit (not shown) issues an instruction to increase the load on the engine generator 20, and for example, a time interval of about ±1 second in the engine generator 20 according to the first embodiment, although it varies depending on the specifications and performance (specs) of the engine generator 20. That is, the control device 10 outputs an adjustment signal to the simulated load regulator 311 of the simulated load power consumption regulator 31 to apply the simulated load 301 to the engine generator 20. Here, in this embodiment, as the first application control, the load of the simulated load 301 is applied to the engine generator 20 so that it increases stepwise from 0% to 100%. That is, a first input control is performed to instantaneously increase the load capacity of the simulated load 301 input to the engine generator 20 from 0% to 100%. Here, in the example shown in FIG. 7, the 100% load capacity of the simulated load 301 is set to a load capacity of X% of the set output of the engine generator 20, so that a load of X% of the set output is input to the engine generator 20 in a stepped manner immediately before starting the engine generator 20. Note that various values ​​can be used for X% as long as it is equal to or less than the load capacity at which the engine generator 20 does not trip. In the first embodiment, the load capacities of the four simulated loads 301 to 304 are set equal to each other, and the total load capacity is set approximately equal to the set output of the engine generator 20. As a result, the load capacity of each of the simulated loads 301 to 304 is 25% of the set output of the engine generator 20. Note that it is also possible to set the load capacities of the simulated loads 301 to 304 to different load capacities.

[0058] Then, the process proceeds to step ST2, where the control device 10 determines whether or not the fluctuation in the output of the engine generator 20 associated with the application of the first dummy load 301 has stabilized. When the load capacity of the dummy load 301 is instantaneously applied to the engine generator 20 from 0% to 100%, it may take a certain period of time for the engine generator 20 to settle, that is, for the power generation output to stabilize. The control device 10 waits until the output of the engine generator 20 stabilizes in step ST2, until the output of the engine generator 20 stabilizes (step ST2: No). If the control device 10 determines that the output of the engine generator 20 is stable (step ST2: Yes), the process proceeds to step ST3.

[0059] In step ST3, the control device 10 inputs the second and subsequent loads (here, the second load 302) from among the multiple simulated loads 301-304 to the engine generator 20 linearly or stepwise from 0% to 100% of the load capacity. That is, the control device 10 outputs an adjustment signal to the simulated load adjuster 312 to control the load of the simulated load 302, thereby increasing the load of the simulated load 302 from 0% to 100%. As a result, the load capacity input to the engine generator 20 increases from X% to Y% of the set output of the engine generator 20. In the example shown in FIG. 8, the load of the simulated load 302 is linearly increased to input from X% to Y% of the set output of the engine generator 20. In the first embodiment, Y% is, for example, 50%.

[0060] Here, the load increase rate α (% / min) when the load of the dummy load 302 is increased to input the MV from X% to Y% of the set output of the engine generator 20 is set to be greater than 0% / min and equal to or less than 60% / min. Here, in the first embodiment, the load increase rate α is set to, for example, 60 (% / min). The reason for setting the load increase rate to 60 (% / min) or less will be described in detail later.

[0061] Here, the definition of the load increase rate α (% / min) in this specification will be described. First, the "%" in the load increase rate α means "%" of the load setting rate MV (%). Also, the time subject to the load increase rate α is the time T ST2 That is, the time from the time when MV is X% at the completion of step ST2 until the time when MV becomes a predetermined load at 100%, and it requires at least 10 seconds or more, although it depends on the output scale of the power generation equipment and the number of connected dummy loads. That is, the time from the time when MV becomes X% and stable until MV becomes 100%, the time from the time when MV becomes X% and stable until MV becomes Y%, the time from Y% to Z%, the time from Y% to 100%, and the time from the time when MV becomes X% and stable until MV becomes Z%, and the time is 10 seconds or more. In other words, the target time of the load increase rate α is any time from the time when the control device 10 judges that the output of the engine generator 20 is stable until MV becomes 100%, and the time is 10 seconds or more. Note that the load increase rate α is not a stepwise input, that is, a stepwise input in which the load is instantaneously input to MV, but an input method that requires a predetermined time until the load reaches the target MV (%). In step ST3, the load increase rate α is set to, for example, 60 (% / min), and the load of the simulated load 302 is increased linearly from 0% to 100%. In the first embodiment, specifically, for example, when X% is 25% and Y% is 50%, the time t for increasing from X% to Y% is preferably (50-25) / 60 (min) or less.

[0062] Next, the process proceeds to step ST4, and the control device 10 linearly or stepwise applies a load capacity of the second or subsequent loads (here, the third load 303) from among the multiple simulated loads 301-304 to the engine generator 20 from 0% to 100%. That is, the control device 10 outputs an adjustment signal to the simulated load adjuster 313 to control the load of the simulated load 303, thereby increasing the load of the simulated load 303 from 0% to 100%. As a result, the load capacity applied to the engine generator 20 increases from Y% to Z% of the set output of the engine generator 20. In this case, too, the load increase rate α is greater than 0% / min and is equal to or less than 60% / min (0<α≦60). In the example shown in FIG. 8, the load of the simulated load 303 is linearly increased to apply from Y% to Z% of the set output of the engine generator 20. In the first embodiment, Z% is, for example, 75%.

[0063] Next, the process proceeds to step ST5 shown in FIG. 7, and the control device 10 inputs the second and subsequent simulated loads 301-304 (here, the fourth simulated load 304) to the engine generator 20 linearly or stepwise from 0% to 100% of the load capacity. That is, the control device 10 outputs an adjustment signal to the simulated load adjuster 314 to control the load of the simulated load 304, thereby increasing the load of the simulated load 304 to the engine generator 20 from 0% to 100% while setting the load increase rate α (% / min) to 0<α≦60. As a result, the load capacity input to the engine generator 20 increases from Z% to 100% of the set output of the engine generator 20. In the example shown in FIG. 8, the load of the simulated load 304 is linearly increased to be input from Z% to 100% of the set output of the engine generator 20.

[0064] The above-mentioned X%, Y%, and Z% can be set arbitrarily. That is, an arbitrary control range is assigned to the simulated loads 301-304, and each of the simulated loads 301-304 is individually controlled, and the MV of each of the simulated loads 301-304 is increased from 0% to 100% while the load increase rate α is set to be greater than 0% / min and equal to or less than 60% / min (0<α≦60). As a result, when the MV of the simulated load group 30 is set to 100%, the load is applied up to the set output of the engine generator 20, for example, about 70% of the rated output.

[0065] Thereafter, the process proceeds to step ST6, where the control device 10 determines whether or not a condition (power load application condition) for applying a power load 50 provided in, for example, a facility to the engine generator 20 is satisfied, i.e., whether or not the output of generated power by the engine generator 20 is stable. The control device 10 waits for application of the power load 50 until the output of generated power from the engine generator 20 is stable (step ST6: No). On the other hand, if the control device 10 determines that the power load application condition for the engine generator 20 is satisfied (step ST6: Yes), the process proceeds to step ST7.

[0066] In step ST7, the control device 10 supplies the power load 50 to the engine generator 20 and starts power increase / decrease control for selecting and controlling the first, second, or third power control modes. In the power increase / decrease control in step ST7, the control device 10 outputs an adjustment signal to the simulated load adjusters 311-314 to adjust the loads of the simulated loads 301-304 according to the increase / decrease in the load power of the power load 50. This controls the generated power of the engine generator 20 to be approximately constant, as shown in the above formula (A). This completes the process of controlling the loads supplied to the engine generator 20 by the control device 10 according to the first embodiment, i.e., the process of controlling the simulated loads 30 and the simulated load power consumption adjuster 31.

[0067] Although the control process according to the above embodiment has been described by taking as an example a case where it is applied to the startup period δ1 shown in Fig. 3, the same control can also be executed in the operation period δ2 after the power load 50 is applied. That is, in the power increase / decrease control by the control device 10, other than the method of simultaneously controlling the simulated loads 301-304 in the simulated load group 30, these simulated loads 301-304 can be individually controlled and the simulated loads 301-304 that consume the required discharged power can be sequentially applied, thereby suppressing a decrease in the power factor of the engine generator 20, and thus enabling more stable control of the discharged power to be executed.

[0068] FIG. 9 shows a graph of the case where the engine generator 20 is started using four heaters having the same load capacity as the dummy loads 301 to 304 by the control method according to the first embodiment described above. The load increase rate α is set to 45 (% / min). In FIG. 9, the horizontal axis indicates the elapsed time (s) from the start of load increase of the second and subsequent dummy loads after the elapse of the maintenance period following the stepless load increase of the first unit, and the left vertical axis indicates the power output by the engine generator 20 as a dotted line, the total power output by the four heaters as a solid line, and the overall MV (here, MV (%) by heater current control) when the four heaters are controlled by the control method according to the first embodiment described above as a dashed line. The right vertical axis indicates the power factor of the engine generator 20 as a two-dot chain line. The two thick dashed lines show an example of the conditions for a major fault to be triggered. The upper thick dashed line indicates a power factor of 0.79 (triggering an alarm in 20 seconds), and the lower dashed line indicates a power factor of 0.7 (triggering an alarm in 5 seconds).

[0069] From Fig. 9, it can be seen that the load of the first heater (simulated load 301) is instantaneously increased from 0 to 100% and instantaneously turned on to 25% of the set output of the engine generator 20, so that the simulated load adjuster 311 of the first heater (simulated load 301) is in a pass-through state, and the drop in power factor can be eliminated. That is, from Fig. 9, it can be seen that even if the load of the second heater (simulated load 302) is increased linearly, the power factor of the engine generator 20 is only reduced to about 0.95. It can be seen that even if the loads of the third and fourth heaters (simulated loads 303 and 304) are increased linearly, it is possible to ensure a sufficient power factor margin for the severe fault alarm conditions by individually controlling the heaters.

[0070] According to the knowledge of the inventor, the power factor of the engine generator 20 is derived from the ratio of "active power" and "reactive power" consumed by the applied load. In addition, when the first simulated load 301 is instantaneously increased in a stepwise manner to X%, in the first embodiment described above to 25%, no drop in the power factor occurs at 0% and 100% in the simulated load adjuster 311 (see Figs. 4 to 6). Therefore, by setting the load capacity for applying the simulated load 301 by the first simulated load adjuster 311 to 100%, further simulated loads 302 to 304 can be applied without causing a drop in the power factor of the engine generator 20. Even when the second and subsequent simulated loads 302 to 304 are applied in a stepwise or linear manner, it is considered that no extreme drop in the power factor occurs even if the reactive power increases, because the loads that do not cause a drop in the power factor due to the simulated load 301 have already been applied. Furthermore, as the number of simulated loads 302-304 that are successively turned on increases, the ratio of loads with a power factor of 1 to the total number of simulated loads 301-304 increases, and therefore the effect of the power factor decreasing is mitigated as the number of turned-on simulated loads increases. Therefore, as shown in Fig. 9, when the second to fourth heaters corresponding to the simulated loads 302-304 are turned on as loads of the engine generator 20, it is considered that the amount of decrease in the power factor decreases as the number of heaters increases.

[0071] In addition, an experiment was performed by changing the load increase rate α to various values ​​under the experimental conditions using a gas engine as the internal combustion engine 21 and four heaters as the simulated loads 301 to 304 according to the control method of the first embodiment. In this experiment, the rated output of the gas engine as the internal combustion engine 21 is, for example, 585 kW, and the set output is 410 kW, which is about 70% of the rated output. FIG. 10 shows a graph in the case where the engine generator 20 is started under such experimental conditions. In FIG. 10, the left vertical axis shows the power output of the engine generator 20 for each load increase rate α as a solid line (94% / min), a dotted line (60% / min), a dashed line (45% / min), a two-dot chain line (24% / min), and a dashed line (12% / min), respectively. The upper graph corresponds to the left vertical axis. On the other hand, the right vertical axis shows the total MV (here, MV (%) by heater current control) when four heaters are controlled by the control method according to the first embodiment, for each load increase rate α, as a solid line (94% / min), a dotted line (60% / min), a dashed line (45% / min), a two-dot chain line (24% / min), and a dashed line (12% / min). Each graph shows the load increase while drawing an arc as the MV (%) increases. Since the load increase rate α is different, there is a difference in the time to reach an arbitrary power generation output, and the shape of the arc differs accordingly, but no difference in the graph shape due to factors other than the load increase rate α, such as the power generation output at an arbitrary MV (%) being lower than other conditions due to a decrease in the power generation voltage or power factor, or the occurrence of a mechanical malfunction such as knocking, causing the graph of the power generation output to fluctuate instantaneously or periodically, cannot be confirmed.

[0072] The inventor started the engine generator 20 under the five conditions shown in Fig. 10 and verified whether or not a failure occurred. The results are shown in Fig. 11. Here, the engine generator 20 was started under these five conditions, and an evaluation was performed to check whether or not a failure occurred and to evaluate the stability of the trends in the generated power (voltage, frequency, power factor), combustion chamber temperature, and coolant temperature, and the degree of impact of the load on the engine generator 20 was evaluated with ◎ (no failure), ◯ (minor failure), or △ (major failure). Fig. 12 shows the criteria for each evaluation item shown in Fig. 11.

[0073] From FIG. 11, it can be seen that when the load increase rate α is set to 12% / min, 24% / min, and 45% / min, the engine generator 20 can stably increase the load without any minor fault occurring. When the load increase rate is set to 60% / min, a transient minor fault, i.e., a temporary rise in the cooling water temperature due to the load fluctuation, was confirmed, but it was confirmed that the normal state was automatically restored after the load fluctuation was completed, and there was no problem in starting the engine generator 20. When the load increase rate α is set to 94% / min, not only did the engine generator 20 experience minor faults related to a rise in the combustion chamber temperature and the cooling water temperature, but it was also confirmed that the cooling water temperature continued to hunt even after the load fluctuation was completed, and the minor fault was repeatedly issued and automatically restored. In addition, it was confirmed that the voltage and frequency could not maintain their set values ​​due to the high load increase rate, and temporarily increased and decreased. In addition, although the power factor itself could be maintained, it was confirmed that the mechanical load was extremely large, such as the generation of surging noise from the turbocharger, and there was concern about the possibility of a serious malfunction. Taking into account the condition of the power generation equipment, it was confirmed that this was not a very favorable load increase rate.

[0074] Furthermore, the present inventors have also investigated a method of increasing the load in a stepped manner by setting the load increase rate to more than 60 (% / min) when increasing the MV (%) from X% to Y%, from Y% to Z%, or from Z% to 100% of the set output of the engine generator 20.

[0075] The present inventors have studied the case where a steam turbine is used as a power engine, and have noticed that when the load is increased in a stepwise manner, the steam turbine is subjected to a sudden load change. In this case, the sudden load change applied to the steam turbine increases the change in torque and enthalpy, and there is a high possibility of problems such as deterioration of materials due to thermal stress, vibration of the turbine shaft, and contact due to the expansion difference between the casing and the axle. Therefore, it has been found that it is not preferable to increase the load in a stepwise manner. In contrast, when the load is increased in a linear or stepwise manner as in the first embodiment, the load is increased in a fixed period that is not stepless, or a settling period is provided to stabilize the power generation equipment after the load is increased in a fixed period that is not stepless, so that it is possible to suppress problems that occur when the load is increased in a stepwise manner.

[0076] From the findings obtained as described above, the inventors have come to the conclusion that it is preferable that the load rise rate α (% / min) is greater than 0% / min and equal to or less than 60% / min (0<α≦60). Furthermore, when the inventors have carried out similar studies on steam turbines and other power plants, it has been confirmed that the load rise rate α is preferably greater than 0% / min and equal to or less than 60% / min (0<α≦60), and more preferably 45% / min or greater and equal to or less than 60% / min (45≦α≦60).

[0077] According to the first embodiment of the present invention described above, a plurality of independently controllable simulated loads 301-304 are connected to the engine generator 20 in a state in which the loads can be applied, and when the engine generator 20 is started up, the simulated load regulator 311 controlling at least one of the simulated loads 301 is instantly applied with a load capacity in steps from 0% to 100% so that at least the engine generator 20 will not trip. As a result, even when the remaining simulated loads 302-304 are each applied in increasing order from 0% to 100%, it is possible to stably start up the engine generator 20 while avoiding tripping.

[0078] (Control method according to the second embodiment) Next, a control method by the control device 10 in a second embodiment of the present invention will be described. The flowchart showing the control method according to the second embodiment is similar to that of the first embodiment shown in Fig. 7. As the control method according to the second embodiment, a case will be described in which the simulated loads 301 to 304 are increased at different load increase rates (linear).

[0079] Fig. 13 is a graph showing an example of control by the control device 10 in the second embodiment, corresponding to Fig. 7. ST shown in Fig. 13 corresponds to the step shown in Fig. 7. As in the first embodiment, the flowchart shown in Fig. 7 starts with the start-up of the engine generator 20 after the commercial power grid 40 goes into a power outage state and the engine generator 20 is disconnected from the power load 50.

[0080] In the second embodiment, as shown in Fig. 7 and Fig. 13, steps ST1 and ST2 are executed in the same manner as in the first embodiment. When the control device 10 judges that the output of the engine generator 20 is in a stable state (step ST2: Yes), the process proceeds to step ST3. In step ST3, the control device 10 performs a second input control by inputting the second and subsequent dummy loads, here the second dummy load 302, from the multiple dummy loads 301 to 304 to the engine generator 20 at time T ST2 From time T ST3The load capacity is inputted linearly or stepwise from 0% to 100% between the load capacity and the load capacity. That is, the control device 10 outputs an adjustment signal to the simulated load adjuster 312 to control the load of the simulated load 302, thereby increasing the load of the simulated load 302 to the engine generator 20 to Y% while keeping the load increase rate at 60 (% / min) or less. In FIG. 13, the thick dotted line indicates a load increase rate of 60 (% / min). As a result, the load capacity inputted to the engine generator 20 increases from X% to Y% of the set output of the engine generator 20. In the example shown in FIG. 13, the load of the simulated load 302 is linearly increased while keeping the slope at 60 (% / min) or less, for example, 45 (% / min), and inputted from X% to Y% of the set output of the engine generator 20. In the second embodiment, Y% is, for example, 50%.

[0081] Next, the process proceeds to step ST4, in which the control device 10 controls the second and subsequent units (here, the third unit 303) of the multiple dummy loads 301 to 304 to be connected to the engine generator 20 at time T ST3 From time T ST4 The load capacity is input linearly or stepwise from 0% to 100% between the load capacity and the load capacity. That is, the control device 10 outputs an adjustment signal to the simulated load adjuster 313 to control the load of the simulated load 303, thereby increasing the load of the simulated load 303 to the engine generator 20 from Y% to Z% of the set output of the engine generator 20 while keeping the load increase rate at 60 (% / min) or less. In the example shown in FIG. 13, the load of the simulated load 303 is increased linearly from Y% to Z% of the set output of the engine generator 20 while keeping the slope at 60 (% / min) or less, for example, 60 (% / min). In the second embodiment, Z% is, for example, 75%.

[0082] Next, the process proceeds to step ST5, in which the control device 10 controls the second and subsequent units (here, the fourth unit 304) of the multiple dummy loads 301 to 304 to be connected to the engine generator 20 at time T ST4 From time T 2A (T ST513, the load of the simulated load 304 is increased linearly or stepwise from 0% to 100% of the set output of the engine generator 20 while keeping the load increase rate at 60% / min or less by outputting an adjustment signal to the simulated load adjuster 314 to control the load of the simulated load 304. In other words, the control device 10 increases the load of the simulated load 304 on the engine generator 20 from Z% to 100% of the set output of the engine generator 20 while keeping the load increase rate at 45(% / min) or less, which is 60(% / min). In the example shown in FIG. 13, the load of the simulated load 304 is increased linearly from Z% to 100% of the set output of the engine generator 20 while keeping the load increase rate at 45(% / min) or less.

[0083] The above-mentioned X%, Y%, and Z% can be set arbitrarily. That is, an arbitrary control range is assigned to the simulated loads 301-304, and each of the simulated loads 301-304 is individually controlled to increase the MV, which is the load setting rate of each of the simulated loads 301-304, from 0% to 100%. As a result, when the MV of the simulated load group 30 is set to 100%, the load is input up to the set output of the engine generator 20.

[0084] In the above-mentioned steps ST3, ST4, and ST5, when the controller 10 increases the load, the load increase rates for the respective simulated loads 301 to 304 are set independently, as shown by the thick lines in Fig. 13. In this case, the tendency of the power generation output when the load increases is a broken line, as shown in Fig. 13. Here, the load increase rates are derived as shown in the following equations (1-1), (1-2), and (1-3), respectively. Step ST3 load increase rate = (YX) / (T ST3 -T ST2 )…(1-1) Step ST4 load increase rate = (ZY) / (T ST4 -T ST3 )…(1-2) Step ST5 load increase rate = (100-Z) / (T ST5 -T ST4 )…(1-3) In the second embodiment, the load increase rate shown in the formulas (1-1) to (1-3) is set to 60% / min or less of the upper limit ((100-X) / (T2-T ST2 ) or less.

[0085] Thereafter, steps ST6 and ST7 are executed in the same manner as in the first embodiment. Thus, the control process of the load applied to the engine generator 20 by the control device 10 according to the second embodiment, i.e., the control process of the simulated load group 30 and the simulated load power consumption regulator 31, is completed.

[0086] According to the second embodiment, when starting the engine generator 20, the load is input at a load increase rate of 60 (% / min) or less, so that the same effects as those of the first embodiment can be obtained.

[0087] (Control method according to the third embodiment) Next, a control method by the control device 10 in a third embodiment of the present invention will be described. A flowchart showing the control method according to the third embodiment is similar to that of the first embodiment shown in Fig. 7. As the control method according to the third embodiment, a case will be described in which the simulated loads 301 to 304 are increased stepwise at different load increase rates, that is, with load maintenance control for a predetermined time being interposed therebetween.

[0088] Fig. 14 is a graph showing an example of control by the control device 10 in the third embodiment, corresponding to Fig. 7. ST shown in Fig. 14 corresponds to the step shown in Fig. 7. As in the first embodiment, the flowchart shown in Fig. 7 starts with the start-up of the engine generator 20 after the commercial power grid 40 goes into a power outage state and the engine generator 20 is disconnected from the power load 50.

[0089] In the third embodiment, as shown in Fig. 7 and Fig. 14, steps ST1 and ST2 are executed in the same manner as in the first embodiment. When the control device 10 judges that the output of the engine generator 20 is in a stable state (step ST2: Yes), the process proceeds to step ST3. In step ST3, the control device 10 performs a second input control by inputting the second and subsequent dummy loads, here the second dummy load 302, from among the multiple dummy loads 301 to 304 to the engine generator 20 at time T ST2 From time T ST3e The load capacity is linearly input from 0% to 100% between the load capacity and the load capacity of the engine generator 20. That is, the control device 10 outputs an adjustment signal to the simulated load adjuster 312 to control the load of the simulated load 302, thereby increasing the load of the simulated load 302 to the engine generator 20 up to Y% while keeping the load increase rate at 60 (% / min) or less. In FIG. 14, the thick dotted line indicates a load increase rate of 60 (% / min). As a result, the load capacity input to the engine generator 20 increases from X% to Y% of the set output of the engine generator 20. In the example shown in FIG. 14, the load of the simulated load 302 is linearly increased while keeping the slope at 45 (% / min), which is less than 60 (% / min), and input from X% to Y% of the set output of the engine generator 20. In the third embodiment, Y% is 50%.

[0090] Next, the process proceeds to step ST4, in which the control device 10 controls the second and subsequent units (here, the third unit 303) of the multiple dummy loads 301 to 304 to be connected to the engine generator 20 at time T ST3e From time T ST4e The load capacity is input in a stepped manner from 0% to 100% between the time T and the time T. That is, the control device 10 outputs an adjustment signal to the simulated load adjuster 313 to control the load of the simulated load 303, thereby increasing the load of the simulated load 303 on the engine generator 20 from Y% to Z% of the set output of the engine generator 20 while maintaining a constant load maintenance control time and a load increase rate of 60 (% / min) or less. In the example shown in FIG. 14, ST3e From time T ST4sThe load increase rate is set to 0 (% / min) and the input load is kept constant until the time T ST4s From time T ST4e The simulated load rate of the simulated load 303 is increased linearly at 60 (% / min) until the set output of the engine generator 20 is input from Y% to Z%. In the third embodiment, Z% is 75%. In the third embodiment, a certain load maintenance control time is set as described above. Depending on the power generation equipment (steam turbine), a sudden increase in load can increase the difference in thermal expansion between the casing and the axle, which can cause contact or failure or increase the risk of fatigue failure of the material, so this may be necessary in order to acclimate the power generation equipment itself to the temperature environment.

[0091] Next, the process proceeds to step ST5, in which the control device 10 controls the second and subsequent units (here, the fourth unit 304) of the multiple dummy loads 301 to 304 to be connected to the engine generator 20 at time T ST4e From time T 2A (T ST5e 14 ), the load capacity is increased in a stepped manner from 0% to 100%. That is, the control device 10 outputs an adjustment signal to the simulated load adjuster 314 to control the load of the simulated load 304, thereby increasing the load of the simulated load 304 on the engine generator 20 from Z% of the set output of the engine generator 20 to 100%, while maintaining a constant load maintenance control time and a load increase rate of 60 (% / min) or less. In the example shown in FIG. 14 , ST4e From time T ST5s The load increase rate is set to 0% / min and the input load is kept constant until time T ST5s From time T ST2A (T ST5e ), the load of the dummy load 303 is increased linearly at an increase rate of 60 (% / min) to input from Y% to Z% of the set output of the engine generator 20.

[0092] The above-mentioned X%, Y%, and Z% can be set arbitrarily. That is, an arbitrary control range is assigned to the simulated loads 301-304, and each of the simulated loads 301-304 is individually controlled to increase the MV, which is the load setting rate of each of the simulated loads 301-304, from 0% to 100%. As a result, when the MV of the simulated load group 30 is set to 100%, the load is input up to the set output of the engine generator 20.

[0093] In the above-mentioned steps ST3, ST4, and ST5, when the controller 10 increases the load, the load increase rates for the respective simulated loads 301 to 304 are set independently, as shown by the thick lines in Fig. 14. In this case, the tendency of the power generation output when the load increases is a broken line, as shown in Fig. 14. Here, the load increase rates are derived as shown in the following equations (2-1), (2-2), and (2-3), respectively. Step ST3 load increase rate = (YX) / (T ST3e -T ST2 )…(2-1) Step ST4 load increase rate = (ZY) / (T ST4e -T ST4s )…(2-2) Step ST5 load increase rate = (100-Z) / (T ST5e -T ST5s )…(2-3) In the third embodiment, the load increase rate shown in the formulas (2-1) to (2-3) is set to 60% / min or less of the upper limit ((100-X) / (T2-T ST2 ) or less.

[0094] Thereafter, steps ST6 and ST7 are executed in the same manner as in the first and second embodiments. Thus, the control process of the load applied to the engine generator 20 by the control device 10 according to the third embodiment, i.e., the control process of the simulated load group 30 and the simulated load power consumption regulator 31, is completed.

[0095] According to the third embodiment, when starting the engine generator 20, the load is input at a load increase rate of 60% / min or less, so that the same effects as those of the first and second embodiments can be obtained.

[0096] Although the embodiment of the present invention has been specifically described above, the present invention is not limited to the above-mentioned embodiment, and various modifications based on the technical idea of ​​the present invention are possible. For example, the numerical values ​​given in the above-mentioned embodiment are merely examples, and numerical values ​​different from these may be used as necessary, and the present invention is not limited by the description and drawings that form a part of the disclosure of the present invention according to the present embodiment.

[0097] (Recording medium) In the above-described embodiment, a program for executing the processing method executed by the control device 10 can be recorded on a recording medium readable by a computer or other machine (hereinafter, referred to as a computer, etc.). By having a computer, etc. read and execute the program from the recording medium, the computer, etc. functions as the control device 10. Here, a recording medium readable by a computer, etc. refers to a non-transient recording medium that accumulates information such as data and programs by electrical, magnetic, optical, mechanical, or chemical action and can be read from a computer, etc. Among such recording media, those that can be removed from a computer, etc. include, for example, a flexible disk, a magneto-optical disk, a CD-ROM, a CD-R / W, a DVD, a BD, a DAT, a magnetic tape, and a memory card such as a flash memory. In addition, a hard disk, a ROM, etc. are examples of recording media fixed to a computer, etc. Furthermore, an SSD can be used as a recording medium that can be removed from a computer, etc., and as a recording medium fixed to a computer, etc.

[0098] Furthermore, the programs executed by the control device 10 according to the embodiment may be configured to be stored on a computer connected to a network such as the Internet and provided by being downloaded via the network.

[0099] (Other embodiments) In the above-described embodiment, the above-described "unit" can be read as a "circuit" etc. For example, a control unit can be read as a control circuit.

[0100] In the description of the flowcharts in this specification, the order of processing between steps is clearly indicated using expressions such as "first," "next," "after that," and "continue," but the order of processing required to implement this embodiment is not uniquely determined by these expressions. In other words, the order of processing in the flowcharts described in this specification can be changed as long as there is no contradiction.

[0101] Further advantages and modifications can be readily derived by those skilled in the art. The disclosure in its broader aspects is not limited to the specific details and representative embodiments shown and described above. Thus, various modifications may be made without departing from the spirit or scope of the general inventive concept as defined by the appended claims and equivalents thereof. [Industrial Applicability]

[0102] The power generation system, the control device, the control method, and the program according to the present invention are suitably applied to an engine generator equipped with a speed governor. [Explanation of symbols]

[0103] 1. Power generation system 10 Control device 11 Judgment control unit 12 Addition section 13 Difference calculation section 14 Control sensitivity calculation section 15 Control output calculation section 16 Memory section 20 Engine generator 21 Internal combustion engine 22 Generator 30 Simulated load group 31 Simulated load power consumption regulator 40 Commercial power system 50 power load 61 Power generation measurement section 62 Power Load Power Consumption Measurement Unit 63 Simulated load power consumption measurement section 111 First power control mode unit 112 Second power control mode unit 113 Third power control mode unit 301,302,303,304 Simulated load 311,312,313,314 Simulated load regulator

Claims

1. A power generation system capable of supplying generated power to a power load such as an electrical appliance together with a commercial power system, a generator capable of controlling generated power by driving a power engine having a speed governor and inputting the generated power to the power load; a dummy load capable of consuming the generated power of the generator while the power engine is in operation and having a predetermined load capacity set so that the power consumption can be adjusted; a simulated load power adjusting unit configured to adjust power so as to increase the power consumption of the simulated load from 0 to the set predetermined load capacity, the simulated load power adjusting unit including a power regulator that generates harmonics that distort a power waveform by adjusting the power; a control unit capable of controlling the power consumption of the dummy load by controlling the dummy load power adjusting unit; Equipped with the simulated load and the simulated load power adjusting unit are provided as a pair of a plurality of sets of the simulated load and the simulated load power adjusting unit, the plurality of sets of the simulated loads are configured such that a sum of the predetermined load capacities of the simulated loads constituting the plurality of sets is substantially equal to a set output of the generator, and the simulated load and the simulated load power adjusting unit are configured to be able to input an adjusted load to the generator independently of each other, The control unit is After the reception of power from the commercial power system is stopped, in a state in which the power load and the generator are disconnected, a first input control that outputs an adjustment signal to each of the plurality of simulated load power adjusting units to input, at the start of the generator, one of the plurality of simulated loads so as to instantaneously increase the load capacity of the generator from 0 to the predetermined load capacity in a stepless manner; a maintenance control for maintaining the predetermined load capacity of the one dummy load during a period from after the first input control until the generated power of the generator becomes stable; a second input control for increasing a load capacity of another simulated load different from the one simulated load among the plurality of simulated loads to the predetermined load capacity so that a load increase rate is greater than 0% / min and less than or equal to 60% / min after the maintenance control; Control including at least Power generation system.

2. The second supply control includes: The load of the dummy load is increased stepwise or linearly up to the predetermined load capacity. The power generation system according to claim 1 .

3. The number of pairs of the dummy load and the dummy load power adjusting unit is two or more. The power generation system according to claim 1 or 2.

4. The load capacity is increased to the predetermined load capacity so that a load increase rate of the simulated load applied by the second application control is greater than 0% / min and less than or equal to 45% / min. The power generation system according to claim 3 .

5. The load capacity is increased to the predetermined load capacity so that a load increase rate of the simulated load applied by the second application control satisfies 45% / min or more and 60% / min or less. The power generation system according to claim 3 .

6. a third supply control for increasing a load capacity of a third simulated load, which is different from both a first simulated load as the one simulated load that is a target of the first supply control and a second simulated load as the other one simulated load that is a target of the second supply control, to the predetermined load capacity so that a load increase rate is greater than 0% / min and is equal to or less than 60% / min, among the plurality of simulated loads after the second supply control; After the third supply control, a fourth supply control is performed for a fourth simulated load, which is different from any of the first simulated load, the second simulated load, and the third simulated load, among the plurality of simulated loads, to increase the load capacity to the predetermined load capacity so that a load increase rate is greater than 0% / min and is equal to or less than 60% / min, and the load increase rates of the second supply control, the third supply control, and the fourth supply control are different from each other. The power generation system according to claim 1 .

7. a second maintenance control for maintaining a load capacity of the other one of the simulated loads after the second supply control; a third supply control for increasing a load capacity of a third simulated load, which is different from both a first simulated load as the one simulated load that is a target of the first supply control and a second simulated load as the other one simulated load that is a target of the second supply control, to the predetermined load capacity so that a load increase rate is greater than 0% / min and is equal to or less than 60% / min, among the plurality of simulated loads after the second maintenance control; After the third supply control, a third maintenance control is performed to maintain a load capacity of the third dummy load. After the third maintenance control, a fourth supply control is performed for a fourth simulated load of the plurality of simulated loads, the fourth simulated load being different from any of the first simulated load, the second simulated load, and the third simulated load, to increase the load capacity to the predetermined load capacity so that a load increase rate is greater than 0% / min and is equal to or less than 60% / min, and the load increase rates of the second supply control, the third supply control, and the fourth supply control are different from each other. The power generation system according to claim 1 .

8. The control unit is After the application of the plurality of dummy loads to the generator is completed, the generator starts supplying generated power to a power load other than the dummy loads; The simulated load power adjusting unit is controlled so as to increase or decrease the power consumption of the simulated load in response to a change in power consumption due to the power load. The power generation system according to claim 1 .

9. A control device for controlling a power generation system capable of supplying generated power to a power load together with a commercial power system, comprising: a plurality of dummy loads capable of consuming generated power of a generator capable of controlling generated power by driving a power engine equipped with a speed governor and capable of supplying the generated power to the power load, the dummy loads having a predetermined load capacity set so that power consumption can be adjusted; and a plurality of dummy load power adjustment units provided in pairs with the plurality of dummy loads, the dummy loads comprising a power regulator configured to adjust power so as to increase the power consumption of the plurality of dummy loads individually from 0 to the predetermined load capacity set, and generating harmonics that distort a power waveform by adjusting the power, the simulated load and the simulated load power adjusting unit are provided as a pair in a plurality of sets, the sum of the predetermined load capacities of the simulated loads constituting the plurality of sets is substantially equal to a set output of the generator, and each pair of the simulated load and the simulated load power adjusting unit is configured to be able to input an adjusted load to the generator independently of each other, The control unit is After the reception of power from the commercial power system is stopped, in a state in which the power load and the generator are disconnected, a first input control that outputs an adjustment signal to each of the plurality of simulated load power adjusting units to input, at the start of the generator, one of the plurality of simulated loads so as to instantaneously increase the load capacity of the generator from 0 to the predetermined load capacity in a stepless manner; a maintenance control for maintaining the predetermined load capacity of the one dummy load during a period from after the first input control until the generated power of the generator becomes stable; a second input control for increasing a load capacity of another simulated load different from the one simulated load among the plurality of simulated loads to the predetermined load capacity so that a load increase rate is greater than 0% / min and is equal to or less than 60% / min after the maintenance control; Control including at least Control device.

10. A control method is executed by a control device that controls a power generation system capable of supplying generated power to a power load together with a commercial power system, the control method comprising: a plurality of dummy loads that can consume the generated power of a generator that can control generated power by driving a power engine equipped with a speed governor and can supply the generated power to the power load, the dummy loads having a predetermined load capacity set so that the power consumption can be adjusted; and a plurality of dummy load power adjustment units that are provided in pairs with the plurality of dummy loads, the dummy loads comprising a power regulator that is configured to adjust power so as to increase the power consumption of the plurality of dummy loads individually from 0 to the predetermined load capacity that is set, and that generates harmonics that distort a power waveform by adjusting the power, the control method comprising: the simulated load and the simulated load power adjusting unit are provided as a pair in a plurality of sets, the sum of the predetermined load capacities of the simulated loads constituting the plurality of sets is substantially equal to a set output of the generator, and each pair of the simulated load and the simulated load power adjusting unit can input an adjusted load to the generator independently of each other, The control unit: After the reception of power from the commercial power system is stopped, in a state in which the power load and the generator are disconnected, a first input control that outputs an adjustment signal to each of the plurality of simulated load power adjusting units to input, at the start of the generator, one of the plurality of simulated loads so as to instantaneously increase the load capacity of the generator from 0 to the predetermined load capacity in a stepless manner; a maintenance control for maintaining the predetermined load capacity of the one dummy load during a period from after the first input control until the generated power of the generator becomes stable; a second input control for increasing a load capacity of another simulated load different from the one simulated load among the plurality of simulated loads to the predetermined load capacity so that a load increase rate is greater than 0% / min and is equal to or less than 60% / min after the maintenance control; Control including at least Control methods.

11. a control unit that controls a power generation system capable of supplying generated power to a power load together with a commercial power system, the power generation system including a plurality of simulated load power adjustment units that are provided in pairs with the plurality of simulated loads, the simulated load power adjustment units being configured to be capable of adjusting power so as to increase the power consumption of the plurality of simulated loads individually from 0 to the set predetermined load capacity, and a power regulator that generates harmonics that distort a power waveform by adjusting power, the plurality of simulated loads being configured in a plurality of pairs of the simulated loads and the simulated load power adjustment units, the sum of the predetermined load capacities of the simulated loads constituting the plurality of pairs being approximately equal to a set output of the generator, and the respective pairs of the simulated loads and the simulated load power adjustment units being controllable so as to supply the adjusted loads to the generator independently of each other, a first input control that outputs an adjustment signal to each of the plurality of simulated load power adjusting units when the power load and the generator are in a disconnected state after the reception of power from the commercial power system is stopped, and inputs one of the plurality of simulated loads to the generator so that the load capacity is instantaneously increased steplessly from 0 to the predetermined load capacity when the generator is started; a maintenance control for maintaining the predetermined load capacity of the one dummy load during a period from after the first input control until the generated power of the generator becomes stable; a second input control for increasing a load capacity of another simulated load different from the one simulated load among the plurality of simulated loads to the predetermined load capacity so that a load increase rate is greater than 0% / min and is equal to or less than 60% / min after the maintenance control; Control including at least A program to make that happen.

Citation Information

Patent Citations

  • Feeding method of generated power fed from generator, and device for the method

    JP2006166551A

  • Operation method of private power generator set with power storage means

    JP2007006595A

  • Power generation system

    JP2015109746A

  • Power generation system

    JP2017184485A