ROBOT SIMULATION DEVICE, ROBOT SIMULATION SYSTEM, AND ROBOT SIMULATION METHOD
The robot simulation system addresses the challenge of simulating in unknown environments by using input distribution data to generate and evaluate output parameters, ensuring robust and accurate simulation results and optimized work processes.
Patent Information
- Application Number
- JP2021173174
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-10-22
- Publication Date
- 2024-10-31
- Estimated Expiration
- 2041-10-22
AI Technical Summary
Existing robot simulation techniques are inadequate for unknown environments, such as disaster sites, where physical property values and boundary conditions cannot be accurately determined, limiting their applicability and accuracy.
A robot simulation system that utilizes input distribution data to generate a set of input parameters, evaluates corresponding output parameters, and estimates output distribution data through stochastic simulation, allowing for robust evaluations in unknown environments.
Enables accurate and robust robot simulation in unknown environments by providing a simulation system that accommodates environmental flexibility, ensuring reliable simulation results and optimized work processes.
Smart Images

Figure 0007576531000001 
Figure 0007576531000002 
Figure 0007576531000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a robot simulation device, a robot simulation system, and a robot simulation method. [Background technology]
[0002] By simulating the behavior of a working robot on a computer before operating it, problems with its behavior in the real world can be discovered in advance.
[0003] Claim 1 of Patent Document 1 describes the following information processing device. a calculation unit that calculates an existence range of the flexible object based on the weight, length, and rigidity of the flexible object, the tolerances thereof, and the direction of gravity, and calculates an existence probability of the flexible object in the existence range based on a probability distribution of at least one of the weight, the length, and the rigidity; a display device that displays the existence range and displays an area with a low existence probability in a lighter color than an area with a high existence probability.
[0004] Claim 1 of Patent Document 2 describes the following robot work motion optimization device. a robot section including a robot and a surrounding working environment for the robot; a robot controller unit that operates the robot unit according to an input work command; a task result evaluation unit that observes a task result of the robot unit and evaluates whether the task result is appropriate; an improved work command candidate generating unit that generates work command candidates that are estimated to result in the most preferable operation of the robot unit; a work instruction unit that outputs a work command to the robot controller unit based on the work command candidates generated by the improved work command candidate generation unit, The improved work command candidate generation unit generates new work commands based on the evaluation results of the work result evaluation unit regarding the operational state of the robot unit as a result of generating work command candidates, and by repeating this process, an optimized work command is obtained.
[0005] According to Patent Document 1, the tolerance of the flexible object is reflected in the simulation. According to Patent Document 2, work instructions to the robot can be optimized based on the simulation results of the robot unit's operation. [Prior art documents] [Patent documents]
[0006] [Patent Document 1] JP 2019-70963 A [Patent Document 2] JP 2009-125920 A Summary of the Invention [Problem to be solved by the invention]
[0007] When robots work in unknown environments such as disaster sites, it is difficult to accurately determine the physical properties and boundary conditions that are input for the simulation. For example, a disaster site is littered with rubble, and the number and size of the rubble may not be known until the user actually visits the site. For this reason, simulation techniques such as those described in Patent Documents 1 and 2, which are based on a known environment with some tolerance, cannot be applied directly to unknown environments.
[0008] In other words, in a simulation that assumes an unknown environment, rather than accuracy of the simulation, it is required to have results that are robust (reasonable to some extent in any environment) in any unknown environment that may occur. A simulation system that can handle such environmental flexibility is required.
[0009] Therefore, a main object of the present invention is to provide a robot simulation that can handle unknown environments. [Means for solving the problem]
[0010] In order to solve the above problems, a robot simulation device of the present invention has the following features. The present invention relates to a distribution input unit that receives input parameters for a simulation that defines the operation of a robot as input distribution data; an input generator that generates a set of input parameters in accordance with the input distribution data; a simulation execution unit for evaluating a corresponding output parameter for each generated input parameter; a power distribution estimating unit that estimates power distribution data by stacking a set of the evaluated output parameters and updates the power distribution data until the power distribution data converges; and a result output unit that outputs the converged power distribution data. Other means will be described later. Effect of the Invention
[0011] According to the present invention, it is possible to provide a robot simulation that can handle unknown environments. [Brief description of the drawings]
[0012] [Figure 1] FIG. 1 is a configuration diagram of a robot simulation device according to an embodiment of the present invention. [Diagram 2] FIG. 2 is an explanatory diagram of a simulation execution unit according to the present embodiment. [Diagram 3] FIG. 1 is a configuration diagram of a robot simulation system according to an embodiment of the present invention. [Figure 4] 4 is a flowchart showing the operation of the robot simulation device according to the present embodiment. [Diagram 5] 11A and 11B are diagrams illustrating input screens of a distribution input section and an actual data input section according to the present embodiment. [Figure 6]1 is a graph showing an example of an input distribution according to the present embodiment. [Figure 7] 4 is a graph showing an example of input parameters related to the present embodiment. [Figure 8] 4 is a table showing an example of a simulation DB according to the present embodiment. [Figure 9] 11 is a graph showing the processing of a simulation result reading unit according to the present embodiment. [Figure 10] 4 is a histogram generated by an output distribution estimation unit according to the present embodiment. [Figure 11] 4 shows output distribution data estimated by an output distribution estimation unit according to the present embodiment. [Figure 12] 11 is a graph showing a convergence evaluation of power distribution data for this embodiment. [Figure 13] 11 is a graph showing point cloud data of experimental results stored in an experimental DB related to the present embodiment. [Figure 14] 14 is a graph showing a result of Bayesian estimation performed by a Bayesian estimation unit according to the present embodiment based on the experiment DB of FIG. 13. [Figure 15] 5 is an explanatory diagram of power distribution data estimated by a power distribution estimation unit according to the embodiment; FIG. [Figure 16] 11 is a Gantt chart showing an example of processing by a work process optimization unit according to the present embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0013] Hereinafter, one embodiment of the present invention will be described.
[0014] FIG. 1 is a configuration diagram of a robot simulation device 100. The robot simulation device 100 has, as processing units, a distribution input unit 11A, an actual data input unit 11B, a distribution estimation unit 11C, an input generation unit 12A, an output distribution estimation unit 13, a simulation execution unit 14A, a simulation result reading unit 14B, an experiment result reading unit 14D, a Bayesian estimation unit 14E, a work process optimization unit 15A, and a result output unit 16. The storage unit of the robot simulation device 100 stores an input distribution (input distribution data) 11D, an input parameter 12B, a simulation DB 14C, an experiment DB 14F, output distribution data 14, and optimal process data 15B.
[0015] The distribution input unit 11A receives an input of an input distribution 11D. The input distribution 11D is input data with variations according to the conditions of an unknown environment. Although the range of values that the input distribution 11D can take can be predicted to some extent, it is assumed that an accurate value corresponding to the unknown environment in which the simulation is performed cannot be specified.
[0016] The actual data input unit 11B accepts input of actual data (actual measurement data) acquired in advance under an assumed environment other than the unknown environment in which the current simulation is performed, instead of the input distribution 11D. For example, in the case of a simulation of rubble removal, a rubble model may be made under conditions (such as the original material of the rubble and the way it breaks) close to those of an actual disaster site, and the weight of the model may be measured as actual data and input from the actual data input unit 11B. In general, since preparation of actual data is costly, the number of pieces of actual data (such as 100 pieces) is less than the number of input parameters 12B (such as 10,000 pieces) for the simulation process described below. The distribution estimation unit 11C estimates an input distribution 11D from the actual data received by the actual data input unit 11B by using a kernel density estimation method (KDE) or the like.
[0017] The input generating unit 12A generates input parameters 12B for the current simulation according to the probability density of the specified input distribution 11D. This generation process is, for example, a process of generating random numbers a specified number of times (for example, 10,000 times) by the Monte Carlo method, and the generated random numbers have values different from other random numbers. Note that the more random numbers are generated, the closer they are to the input distribution 11D and the higher the accuracy, but on the other hand, the amount of calculation required for the simulation also increases. Therefore, it is advisable for the user to set the system to generate an appropriate number of random numbers in advance, taking into consideration the performance of the computer, etc.
[0018] The input parameters 12B are parameters used in this simulation, and examples of such parameters include, for example, when a robot grasps rubble scattered at a disaster site, the weight of the object to be grasped, the shape of the object to be grasped, the coefficient of friction of the ground on which the grasping operation is performed, the indoor temperature where the grasping operation is performed, etc. These input parameters 12B are parameters that affect the output distribution data 14 (such as the operation time and whether or not the working robot can perform the operation, such as tipping over due to the weight of the object it grasps) that is the result of this simulation.
[0019] The power distribution estimation unit 13 performs a robust evaluation of the power distribution data 14 by a probabilistic simulation for the unknown environmental conditions indicated by the input parameters 12B. The power distribution estimation unit 13 may use any one of the following (Method 1) to (Method 3) as a means for the probabilistic simulation. (Method 1) The simulation execution unit 14A receives the input parameters 12B, executes a simulation on a computer, and returns the result to the output distribution estimation unit 13.
[0020] (Method 2) Simulation result reading unit 14B receives input parameters 12B, refers to simulation DB 14C, reads the results of a simulation registered in advance by machine learning or the like, and returns the results to output distribution estimation unit 13. For this reason, simulation result reading unit 14B registers input parameters 12B and the results of a simulation executed in advance by simulation execution unit 14A in simulation DB 14C. (Method 3) Experiment result reading unit 14D receives input parameters 12B, acquires distribution data of the Bayesian estimation estimated by Bayesian estimation unit 14E, and returns the distribution data to output distribution estimation unit 13. For this reason, Bayesian estimation unit 14E registers actual data (actually measured data) under the experimental environment input in advance by actual data input unit 11B and the experimental results for the actual data in experiment DB 14F.
[0021] The output distribution estimation unit 13 estimates output distribution data 14 by stacking a set of evaluated output parameters using a kernel density estimation method (KDE) or the like, based on the output parameters evaluated by any one of (Method 1) to (Method 3) for each of a plurality of (e.g., 10,000) input parameters 12B. The result output unit 16 outputs the output distribution data 14 on a screen, thereby allowing the user to understand the robust simulation results corresponding to an unknown environment, which the user can use to consider the robot operation process.
[0022] Furthermore, the output distribution data 14 may not only be output directly to a screen, but may also be used as material for optimizing the process plan of the robot. The work process optimization unit 15A receives the output distribution data 14 as input, performs process optimization (eg, mixed integer programming, A* algorithm, etc.) on the robot process plan from the initial plan, and sets the result as optimal process data 15B. This optimization process is a process that, for example, starts from an initial plan to perform the same work and shortens the total work time by adjusting the individual work times or rearranging the order of the work without changing the content of the work. The result output unit 16 outputs the optimal process data 15B, which is optimized based on the output distribution data 14, on a screen in a Gantt chart format or the like. This allows the user to understand a reasonable work process that links multiple robust tasks that are compatible with an unknown environment.
[0023] FIG. 2 is an explanatory diagram of the simulation execution unit 14A. The simulation execution unit 14A simulates the work of a working robot 111B clearing away rubble 111A scattered at a work site. The output parameters (work time and whether the work can be done) as the result of this simulation vary depending on the number, size, etc. of the rubble 111A specified as the input parameters 12B. That is, the simulation execution unit 14A evaluates the corresponding output parameters for each of the generated input parameters 12B.
[0024] FIG. 3 is a configuration diagram of the robot simulation system. The robot simulation system is configured by connecting the computer 900 of the robot simulation device 100 and an input / output device 916 . The robot simulation device 100 is configured as a computer 900 having a CPU 901 , a RAM 902 , a ROM 903 , a HDD 904 , a communication I / F 905 , an input / output I / F 906 , and a media I / F 907 . The communication I / F 905 is connected to an external communication device 915. The input / output I / F 906 is connected to an input / output device 916. The media I / F 907 reads and writes data from a recording medium 917. Furthermore, the CPU 901 controls each processing unit by executing a program (also called an application or its abbreviation, an app) loaded into the RAM 902. This program can be distributed via a communication line, or can be recorded on a recording medium 917 such as a CD-ROM and distributed.
[0025] FIG. 4 is a flowchart showing the operation of the robot simulation device 100. The distribution input unit 11A receives an input of the input distribution 11D (S101). The input generating unit 12A generates the input parameters 12B (S102).
[0026] The output distribution estimation unit 13 branches depending on the type of simulation output to be acquired (S111). (Method 1) If "simulation execution" is selected in S111, output distribution estimation unit 13 acquires the output of the simulation executed by simulation execution unit 14A (S112; simulation execution). (Method 2) If "simulation (acquire)" is selected in S111, output distribution estimation unit 13 acquires the output of the simulation read by simulation result reading unit 14B from simulation DB 14C (S113; simulation acquisition). (Method 3) If "experimental acquisition" is selected in S111, the output distribution estimation unit 13 acquires the experimental results read by the experimental result reading unit 14D (the estimation results of the Bayesian estimation unit 14E) (S114; experimental result acquisition).
[0027] The power distribution estimation unit 13 estimates the power distribution data 14 from the results acquired in S112 to S114 (S115; estimation of power distribution). The power distribution estimation unit 13 determines whether the currently estimated power distribution data 14 has converged (S116, details in FIG. 12). If Yes in S116, proceed to S121, and if No, return to S111 to again estimate the power distribution data 14. That is, the power distribution estimation unit 13 updates the power distribution data 14 until the power distribution data 14 converges.
[0028] The result output unit 16 branches depending on the type of output result specified by the user (S121). When the output distribution data 14 is specified (distribution in S121), the result output unit 16 outputs a graph of the output distribution data 14 (S122). When optimization of the process is specified (Process in S121), the task process optimization unit 15A uses the output distribution data 14 to calculate the optimal process for the robot task, and outputs the result from the result output unit 16 (S123).
[0029] FIG. 5 is a diagram showing the input screen of the distribution input unit 11A and the actual data input unit 11B used in the input process of S101. The input screen 121 includes input fields for one or more input parameters (two in FIG. 5), an “Execute” button for confirming the input after inputting into each input field, and an “Exit” button for discarding the input. Each input field (input parameter 1, 2) contains the following input fields. · Parameter name input field: Here, input parameter 1 "Grasp object weight" and input parameter 2 "Grasp object size" are entered. Radio button to specify the input data format. Here, you can choose one of three data formats: a probability distribution name and its parameter group (mean, standard deviation), a data format to directly specify the probability distribution by specifying a CSV (Comma-Separated values) file, or a data format to directly specify the actual data by specifying a CSV file. Furthermore, the name of the probability distribution can be input on the input screen 121 by selecting one from a pull-down menu, and various distributions such as uniform distribution can be selected in addition to the normal distribution of a mountain curve.
[0030] The distribution input unit 11A accepts input for the input parameter 1 "grasped object weight" in a data format with a probability distribution name of "normal distribution." The actual data input unit 11B accepts input of the input parameter 2 “grasped object size” in a data format in which the actual data is directly specified by specifying a CSV file. In this case, the distribution estimation unit 11C estimates an input distribution 11D from the actual data accepted by the actual data input unit 11B by a kernel density estimation method or the like.
[0031] FIG. 6 is a graph showing an example of the input distribution 11D received by the distribution input unit 11A from the input screen of FIG. The horizontal axis of graph 131 is input parameter 1 "grabbed object weight," and the vertical axis indicates the probability density of debris generation for each weight. Distribution input unit 11A may accept a data format that directly specifies the probability distribution of graph 131 by specifying correspondence data 132 between the horizontal axis and the vertical axis, such as a CSV file. In addition, since this simulation is premised on an unknown environment, graph 131 is not premised on a specific environment, but is determined based on past experience, literature, expert opinions, etc. Therefore, the horizontal axis of graph 131 is not a fixed single value, but is distribution data including variation.
[0032] FIG. 7 is a graph showing an example of the input parameter 12B. The horizontal axis of graph 141 is the data number (No.) of the input parameter, and the vertical axis is the numerical value of input parameter 1 "weight of object held" corresponding to the data number. The input generating unit 12A generates a numerical value set (random number set) 142 of the weight of object held that matches the input distribution 11D. Graph 141 is a graph of the numerical value set 142.
[0033] FIG. 8 is a table showing an example of the simulation DB 14C. Table 151 of the simulation DB 14C associates, for each data number (No.) of an input parameter, the input parameter (here, the weight of the object to be held) with the execution result of the simulation for that input parameter (here, the work time and whether or not the work can be held). Note that, as a general tendency of the simulation, the heavier the weight of the object to be held, the longer the work time becomes or the work cannot be held. The simulation execution unit 14A creates in advance the data in the simulation DB 14C that is to be acquired by the simulation result reading unit 14B in S113.
[0034] FIG. 9 is a graph showing the processing of the simulation result reading unit 14B. The horizontal axis of graph 161 is input parameter 1 "grasped object weight," and the vertical axis is the execution result of the simulation corresponding to that weight (here, work time). Graph 161 is a curved graph. Each point on the line graph is the coordinates of the point indicated by the combination of "weight" and "work time" in FIG. 8.
[0035] The curve that complements each point on the graph 161 can be obtained by the simulation execution unit 14A using a simple interpolation method (for example, spline interpolation) since only one input parameter is used and the distribution is continuous. On the other hand, when dealing with multidimensional input parameters or complex (discontinuous) distributed input parameters, the simulation execution unit 14A executes an interpolation method using advanced machine learning such as random forest. This is because when the distribution is discontinuous or not smooth, even a small difference in the input parameters may result in completely different values of the output parameters.
[0036] The power distribution estimation unit 13 inputs a value for each data number (No.) ("120 kg" in FIG. 9) into the graph 161, finds an intersection with the graph 161, and finds the value of the output parameter corresponding to the intersection ("350 minutes" in FIG. 9) (see the arrow in FIG. 9). In other words, if there are 1000 input parameters 12B, the number of output parameters found by the power distribution estimation unit 13 will also be 1000. Note that, for ease of explanation, FIG. 9 illustrates the finding of one type of output parameter from one type of input parameter. However, in reality, there are often multiple types of input parameters and multiple types of output parameters.
[0037] FIG. 10 is a histogram generated by the output distribution estimation unit 13. The horizontal axis of the histogram 162 is the output parameter (task time), and the vertical axis is the frequency at which the task time is output. The output distribution estimation unit 13 generates the histogram 162 by accumulating the frequency for each value of the output parameter (e.g., "350 minutes") obtained in FIG. For the output of simulation execution unit 14A (method 1) and the output of simulation result reading unit 14B (method 2), output distribution estimation unit 13 generates a histogram 162 as shown in Fig. 10. On the other hand, for the output of experiment result reading unit 14D (method 3), a graph that stacks the distributions is generated instead of histogram 162 (see Fig. 15 for details).
[0038] FIG. 11 shows the power distribution data 14 estimated by the power distribution estimation unit 13. As shown in FIG. The output distribution estimation unit 13 generates a graph 163 of curves that smoothly connect the vicinity of each peak of the histogram 162 by using a kernel density estimation method or the like from a histogram 162 of the output distribution data 14 as shown in Fig. 10 (a histogram in which a set of evaluated output parameters is stacked). This graph 163 is the estimation result of the output distribution data 14. This output distribution data 14 allows a robust evaluation of the work time, such as "no matter what the unknown environment is, 90% of the work time will be within 350 minutes." In the example of Fig. 11, the graph 163 has one peak, but in other examples, there may be multiple peaks. In that case, an evaluation such as "there is a 20% chance that the work time will be about 350 minutes, and a 70% chance that the work time will be about 550 minutes" can be made.
[0039] FIG. 12 is a graph showing a convergence evaluation of the output distribution data 14 as an example of S116 in FIG. The horizontal axis of the graph 164 indicates the number of simulations (the number of times any one of S112, S113, and S114 was executed, also called the number of Monte Carlo methods), and the vertical axis indicates the convergence evaluation value of S116. The shape of the output distribution data 14 is updated every time the number of simulations is increased. Therefore, the output distribution estimation unit 13 compares the difference in the graph shape (convergence evaluation value such as KL divergence) between the output distribution data 14 of the previous simulation result and the output distribution data 14 of the current simulation result. Then, when the difference becomes sufficiently small (below the threshold value of the graph 164), the output distribution estimation unit 13 determines that the output distribution data 14 has converged (Yes in S116).
[0040] Above, the details of how the power distribution estimation unit 13 creates the power distribution data 14 for (Method 1) and (Method 2) have been described with reference to Figures 9 to 12. Next, the details of how the power distribution estimation unit 13 creates the power distribution data 14 for (Method 3) will be described with reference to Figures 13 to 15. 13 is a graph showing point cloud data of the experiment results stored in the experiment DB 14 F. The horizontal axis of the graph 171 is the input parameter 1 “grasped object weight”, and the vertical axis is the experiment result (here, the task time) corresponding to that weight.
[0041] FIG. 14 is a graph showing the results of Bayesian estimation performed by the Bayesian estimation unit 14E on the experiment DB 14F of FIG. The Bayesian estimation unit 14E reads the point cloud data of graph 171 in Figure 13, and generates graph 172 by Bayesian estimation, which estimates the relationship (regression) and variation between the input parameter (weight of grasped object) on the horizontal axis and the output parameter (work time) on the vertical axis.
[0042] In the example of Fig. 14, the Bayesian estimation unit 14E determines an interval 172W between two upper and lower wavy lines (a wavy line passing through point P1 and a wavy line passing through point P3) that includes 95% of the point cloud data as an estimated result of the variation. A solid line passing through point P2 in this interval 172W indicates a location where the occurrence frequency of the point cloud data is estimated to be a peak. In this way, by using Bayesian estimation, it is possible to evaluate the probability distribution even with a small amount of measured data. Then, the output distribution estimation unit 13 obtains the output parameter of the task time corresponding to one input parameter, for example, weight=350 kg, as a range of intersections "points P1-P2-P3" within the section 172W.
[0043] FIG. 15 is an explanatory diagram of the output distribution data 14 estimated by the output distribution estimation unit 13 based on the distribution read by the experiment result reading unit 14D from the graph of FIG. The horizontal axis of graph 173 is the output parameter (task time), and the vertical axis is the frequency (probability) of occurrence of that output parameter. The output distribution estimation unit 13 adds a distribution curve 173A indicating the variation (frequency of occurrence of point cloud data) of the work time (peaking at 120 minutes) within section 172W of the range of "points P1-P2-P3" obtained in Fig. 14 to the output distribution data 14 as a result of one simulation. This distribution curve 173A is obtained by projecting the output parameter of the work time corresponding to one input parameter of weight = 350 kg in Fig. 14 onto the vertical axis of Fig. 14. Similarly, power distribution estimation unit 13 creates graph 173B of power distribution data 14 by successively superimposing (adding) the results of each simulation on power distribution data 14.
[0044] FIG. 16 is a Gantt chart showing an example of the process of S123 in FIG. 4 by the operation process optimization unit 15A. Below, we will explain the initial plan Gantt chart 201, the non-optimized Gantt chart 202, and the optimized Gantt chart 203. Each of the Gantt charts 201 to 203 shows the work process for the robot R1 in charge of dismantling and gripping the rubble, and the robot R2 in charge of transporting the rubble.
[0045] The Gantt chart 201 of the initial plan does not reflect the output distribution data 14 as a result of the simulation, and the process is registered without taking into consideration the variation in work time, which is a factor in the risk of delay in the work process. Specifically, for robot R1, the process of dismantling rubble at point A, the process of loading the rubble onto robot R2, and the process of moving to point B are registered. For robot R2, the process of waiting for robot R1 to finish dismantling the rubble, the process of waiting for the loading of rubble from robot R1, the process of transporting the rubble, and the process of moving to point C are registered. The work time for each process, such as the rubble dismantling process at point A, is based on the average work time Ta registered in advance.
[0046] In the non-optimized Gantt chart 202, the output distribution data 14 as a result of the simulation is reflected in the work time of each process. For example, the work time for the rubble dismantling process at point A is calculated by adding the standard deviation (variation) time Tb indicated by the output distribution data 14 to the average work time Ta registered in advance. Similarly, the work times for tasks other than the rubble dismantling process at point A must also be changed in consideration of the variations in the power distribution data 14. However, for the sake of simplicity, FIG. 16 illustrates the work times for the other processes as if they were not changed.
[0047] In the Gantt chart 202 without optimization, the work time of each process is slightly longer or shorter than that of the initial plan Gantt chart 201, but the order of each process does not change, and each process is simply delayed. For example, when considering the variation in work time that occurs in the process of "demolishing rubble at point A" by robot R1, the waiting time for the subsequent process of "waiting for loading" by robot R2 will also be longer, and the work by robot R2 at point C (reference symbol 202C) will also be delayed.
[0048] The Gantt chart with optimization 203 is the Gantt chart without optimization 202, in which optimization has been performed to shorten the total work time by partially switching the processes of robot R2. Specifically, the work process optimization unit 15A recognizes from the non-optimized Gantt chart 202 that the variation in the “demolition of rubble at point A” by the robot R1 is large (high risk of delay), and therefore the waiting time of the robot R2 will be long.
[0049] Then, in order to effectively utilize the waiting time of robot R2, the work process optimization unit 15A executes the process of "moving to point C, transporting the rubble that has already been dismantled there, and returning to point A" before executing the process of waiting for the loading of rubble from robot R1 at point A. As a result, the work at time C (symbol 202C) in the Gantt chart 202 without optimization is brought forward to work at time C (symbol 203C) before the work at point A in the Gantt chart 203 with optimization, thereby shortening the total work time. In this way, the work process optimization unit 15A can improve the robot's work plan by performing "process optimization" that rearranges the order of the processes to be performed by the robot and rearranges the allocation of processes (tasks) to the robot, taking into account the variation (delay risk) in the output distribution data 14.
[0050] The robot simulation device 100 of the present embodiment described above evaluates output parameters such as task time and task feasibility as output distribution data 14 based on an input distribution 11D in which input conditions (physical properties, boundary conditions, etc.) of a probabilistic simulation are varied for unknown environmental conditions. This allows for robust evaluation even in an unknown environment in which physical properties, boundary conditions, etc., which are inputs to the simulation, cannot be accurately determined.
[0051] Furthermore, the input generating unit 12A generates an appropriate number of random numbers according to the input distribution 11D by the Monte Carlo method, which makes it possible to perform a number of simulations within a practical calculation time. Furthermore, the simulation execution unit 14A can perform simulation processing each time (Method 1), as well as read the results of simulations that have already been executed (Method 2) and read the results of experiments that have already been input (Method 3), thereby reducing the number of simulations and enabling evaluation within a practical amount of time.
[0052] It should be noted that the present invention is not limited to the above-described embodiment, but includes various modified examples. For example, the above-described embodiment has been described in detail to clearly explain the present invention, and the present invention is not necessarily limited to the embodiment having all of the described configurations. In addition, it is possible to replace part of the configuration of one embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of one embodiment. In addition, it is possible to add, remove, or replace a part of the configuration of each embodiment with another configuration. In addition, the above-mentioned configurations, functions, processing units, processing means, etc. may be realized in part or in whole by hardware, for example, by designing them as integrated circuits. Furthermore, each of the above configurations and functions may be realized in software by a processor interpreting and executing a program that realizes each function.
[0053] Information such as programs, tables, and files that realize each function can be stored in a memory, a hard disk, a recording device such as an SSD (Solid State Drive), or a recording medium such as an IC (Integrated Circuit) card, an SD card, a DVD (Digital Versatile Disc), etc. The cloud can also be used. In addition, the control lines and information lines shown are those that are considered necessary for the explanation, and not all control lines and information lines in the product are necessarily shown. In reality, it can be considered that almost all components are connected to each other. Furthermore, the communication means connecting the devices is not limited to wireless LAN, but may be changed to wired LAN or other communication means. [Explanation of symbols]
[0054] 11A distributed input section 11B Actual data input section 11C Distribution estimation part 11D Input distribution (input distribution data) 12A Input Generation Unit 12B Input parameters 13 Output distribution estimation section 14 Power distribution data 14A Simulation Execution Unit 14B Simulation result reading unit 14C Simulation DB 14D Experimental result reading section 14E Bayesian Estimation 14F Experimental Database 15A Work Process Optimization Department 15B Optimal process data 16 Result output section 100 Robot simulation device
Claims
1. a distribution input unit that receives input parameters of a simulation that defines the operation of the robot as input distribution data; an input generator that generates a set of input parameters in accordance with the input distribution data; a simulation execution unit for evaluating a corresponding output parameter for each generated input parameter; a power distribution estimating unit that estimates power distribution data by stacking a set of the evaluated output parameters and updates the power distribution data until the power distribution data converges; and a result output unit that outputs the converged power distribution data. Robot simulation device.
2. the input generation unit generates random numbers according to the input distribution data by a Monte Carlo method, and sets the set of random numbers as a set of input parameters; The output distribution estimation unit estimates the output distribution data by a kernel density estimation method from a histogram in which a set of evaluated output parameters is stacked. The robot simulation device according to claim 1 .
3. the robot simulation device further includes a simulation DB and a simulation result reading unit, The simulation DB stores data on correspondence between past input parameters and past output parameters as a result of a simulation performed in advance by the simulation execution unit, Instead of the process of evaluating the output parameters by the simulation execution unit, the simulation result reading unit executes a process of reading the corresponding output parameters from the simulation DB for each input parameter generated this time. The robot simulation device according to claim 1 .
4. the robot simulation device further includes an experiment result reading unit, a Bayesian estimation unit, and an experiment DB; The experiment DB stores a set of corresponding data between past input parameters and past output parameters, the Bayesian estimation unit creates distribution data of output parameters corresponding to input parameters by Bayesian estimation from a set of corresponding data read from the experiment DB; Instead of the process of evaluating the output parameters by the simulation execution unit, the experiment result reading unit executes a process of reading distribution data of the corresponding output parameters from the Bayesian estimation unit for each input parameter generated this time; The output distribution estimation unit creates the output distribution data by stacking the distribution data of the read output parameters. The robot simulation device according to claim 1 .
5. The robot simulation device further includes a work process optimization unit, The work process optimization unit refers to the output distribution data created by the output distribution estimation unit to change the work time of each process performed by the robot, and executes at least one of a process of rearranging the order of each process and a process of rearranging the allocation of processes to each robot for the changed work time, thereby shortening the total work time of each process performed by the robot. The robot simulation device according to claim 1 .
6. The simulation execution unit is characterized in that it evaluates the robot's work time or the robot's work capability as an output parameter. The robot simulation device according to claim 1 .
7. 7. A robot simulation device according to claim 1, further comprising: an input / output device having a means for transmitting input data to the distribution input unit and a means for receiving output data from the result output unit. Robot simulation system.
8. The robot simulation device includes a distribution input unit, an input generation unit, a simulation execution unit, an output distribution estimation unit, and a result output unit, The distribution input unit receives input parameters of a simulation that defines an operation of the robot as input distribution data; The input generation unit generates a set of input parameters according to the input distribution data; The simulation execution unit evaluates a corresponding output parameter for each generated input parameter; the power distribution estimation unit estimates power distribution data by stacking a set of evaluated power parameters, and updates the power distribution data until the power distribution data converges; The result output unit outputs the converged output distribution data. Robot simulation method.
Citation Information
Patent Citations
External environment recognition system
JP1996063581A
Robot work operation optimization device
JP2009125920A
Information processing device, flexible object display method and flexible object display program
JP2019070963A
Autonomous vehicle simulation using machine learning
US20200368906A1