Battery monitoring system for railway vehicles, on-board device for railway vehicles, and battery monitoring method for railway vehicles

The battery monitoring system for railway vehicles addresses high communication costs by generating and transmitting daily report data with key battery characteristics, effectively reducing data volume and enhancing life estimation and failure analysis.

JP7587712B2Active Publication Date: 2024-11-20HITACHI LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2023550462
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Priority Date
2021-09-28
Filing Date
2022-08-24
Publication Date
2024-11-20
Estimated Expiration
2042-08-24

AI Technical Summary

Technical Problem

Existing battery monitoring systems for railway vehicles face high communication costs and data capacity challenges due to large time-series data transmission, particularly through mobile phone base station lines like LTE, which are not effectively addressed by existing technologies.

Method used

A battery monitoring system that generates and transmits daily report data, comprising maximum, minimum, and average values of battery characteristics, along with time-series data of selected battery modules, to reduce communication volume and focus on significant data points, using a combination of on-board and ground server processing.

Benefits of technology

Reduces communication costs and data volume by prioritizing daily report data with notable changes, allowing efficient life estimation, predictive diagnosis, and failure analysis while minimizing communication burden.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007587712000001
    Figure 0007587712000001
  • Figure 0007587712000002
    Figure 0007587712000002
  • Figure 0007587712000003
    Figure 0007587712000003
Patent Text Reader

Abstract

According to the present invention, a battery monitoring system that monitors a plurality of storage batteries generates and records daily report data that is at least one of a maximum value, a minimum value, an average value, and an integrated value for battery characteristic values for all of the storage batteries for one day and transmits the daily report data to a ground server. The battery monitoring system also generates and records time series data for the battery characteristic values for a portion of the storage batteries for one day and transmits the time series data for the portion of the storage batteries to the ground server in conjunction with the daily report data for all of the storage batteries. Target storage batteries for which the time series data is acquired are switched every day. The target storage batteries that are switched every day are from series groups. The same number of target storage batteries that are switched every day are selected from all of the series groups. The battery characteristic values for the storage batteries represent one or more of current, voltage, temperature, and state of charge. The present invention thereby provides a rolling stock battery monitoring system that can reduce communication traffic for transmitting data needed for life estimation, predictive diagnosis, failure factor analysis, and the like from rolling stock to a ground server.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a battery monitoring system for railway vehicles, an on-board device for railway vehicles, and a battery monitoring method for railway vehicles. [Background technology]

[0002] Because the battery systems installed in railway vehicles are required to have high voltage and large capacity, a battery module is made by combining multiple battery cells, and then multiple battery modules are connected in series and in parallel to form a high-capacity battery system.

[0003] Battery systems are typically equipped with a battery monitoring system that includes a controller to properly manage the current and temperature of the storage battery for safe use, and in recent years, methods have been developed to monitor the status of battery systems from remote locations using mobile phone base station lines such as LTE (3G Long Term Evolution).

[0004] More specifically, a technique is known for transmitting time series data of battery characteristic values ​​of a storage battery to a ground server via a mobile phone base station line (for example, Patent Document 1). Patent Document 1 describes a method for transmitting a first battery characteristic value (for example, current during discharge) and a second battery characteristic value (for example, voltage during discharge) to a ground server, identifying multiple parameters from these data at the ground server, and enabling the time series data of the second battery characteristic value to be restored from the parameters and the time series data of the first battery characteristic value. This makes it possible to delete the time series data of the second battery characteristic value, which is expected to reduce the data volume. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] Patent Publication No. 2021-88249 Summary of the Invention [Problem to be solved by the invention]

[0006] The technology of Patent Document 1 enables various things such as lifespan estimation, predictive diagnosis, and analysis of causes of failures by storing time-series data in a ground server. Furthermore, this technology enables some time-series data to be restored from multiple parameters, thereby reducing the amount of data to be held in the ground server. However, while the technology of Patent Document 1 can reduce the data capacity of the ground server, it cannot reduce the amount of communication from the railway vehicle to the ground server. In addition, the data size of time-series data is generally large, and a mobile phone base station line such as LTE is used as a path for transmitting this data from the railway vehicle to the ground, which requires high communication fees.

[0007] The present invention has been made in consideration of the above-mentioned problems, and an object of the present invention is to provide a battery monitoring system for railway vehicles that can reduce the amount of communication required to send data necessary for life estimation, predictive diagnosis, and cause analysis in the event of a failure from a railway vehicle to a ground server. [Means for solving the problem]

[0008] The present invention, which solves the above problems, is a battery monitoring system for railway vehicles that monitors multiple storage batteries, and generates and records at least one of the maximum, minimum, average, and integrated values ​​of the battery characteristic values ​​for all the storage batteries for one day as daily report data and transmits it to a server. Effect of the Invention

[0009] According to the present invention, a railway vehicle battery monitoring system is realized that can reduce the amount of communication required to transmit data necessary for life estimation, predictive diagnosis, and analysis of the causes of failures from a railway vehicle to a ground server. Problems, configurations, and effects other than those described above will become apparent from the description of the embodiments below. [Brief description of the drawings]

[0010] [Figure 1]FIG. 1 is a block diagram showing the overall configuration of a railway vehicle battery monitoring system (hereinafter also referred to as "this monitoring system") according to a first embodiment of the present invention, a ground server linked thereto, and the battery system that they monitor. [Diagram 2] FIG. 2 is a block diagram showing the functional configuration of the monitoring system shown in FIG. [Diagram 3] 3 is a block diagram showing the calculation process of the daily report data generating unit of FIG. 2. [Figure 4] 3 is a table showing a list of output results of the daily report data generation unit in FIG. 2. [Diagram 5] 3 is a block diagram showing the calculation process of the time-series data generating unit in FIG. 2. [Figure 6] 3 shows four types of graphs showing the output results of the time-series data generation unit in FIG. 2. [Figure 7] FIG. 3 is a block diagram showing the remote monitoring device of FIG. 2 in more detail. [Figure 8] 8 is a diagram illustrating an example of selection of transmission data in a transmission data management unit in FIG. 7; [Figure 9] This is a table comparing the daily report data and time series data stored in the ground server in Figure 1. [Figure 10] FIG. 11 is a block diagram showing a calculation process of a time-series data generating unit according to a second embodiment of the present invention. [Figure 11] 11 is a circuit diagram illustrating an example of storage batteries connected in series and parallel, from which the time-series data generating unit in FIG. 10 acquires data. [Figure 12] FIG. 11 is a block diagram showing a calculation process of a time-series data generating unit according to a third embodiment of the present invention. [Figure 13] 13 is a circuit diagram illustrating an example of storage batteries connected in series and parallel, from which the time-series data generating unit in FIG. 12 acquires data. FIG. [Figure 14] FIG. 11 is a diagram illustrating a transmission data selection in a transmission data management unit according to the fourth embodiment of the present invention. [Figure 15] FIG. 11 is a diagram showing a functional configuration of a railway vehicle battery monitoring system (also referred to as "this monitoring system") according to a fifth embodiment of the present invention. [Figure 16]FIG. 16 is a block diagram showing the remote monitoring device of FIG. 15 in more detail. [Figure 17] 17 is a diagram illustrating an example of transmission data selection in the transmission data management unit in FIG. 16. [Figure 18] FIG. 17 is a diagram illustrating data stored in the ground server of FIG. 16. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] The present monitoring system will be described below with reference to Figures 1 to 18. Example 1 will be described with reference to Figures 1 to 9, Example 2 with reference to Figures 10 to 11, Example 3 with reference to Figures 12 to 13, Example 4 with reference to Figure 14, and Example 5 with reference to Figures 15 to 18. As will be described later with reference to Figure 1, the present monitoring system 5 is an information processing function for remotely monitoring the battery state of the battery system 1 mounted on the vehicle, mainly from the ground, and is configured to be capable of linking not only with on-board equipment for railway vehicles (hereinafter also referred to as "the present on-board equipment"), but also with ground facilities for railway vehicles. EXAMPLES

[0012] Hereinafter, a first embodiment will be described with reference to Figs. 1 to 9. Fig. 1 is a block diagram showing the overall configuration of a monitoring system 5, a ground server 8 linked thereto, and a battery system 1 that is the object of monitoring by them. As shown in Fig. 1, remote monitoring of a storage battery mounted on a railway vehicle is realized by the battery system 1 as an on-board device and the ground server 8 as a railway vehicle ground facility. The monitoring system 5 for this purpose is mainly configured with a battery controller 4, a higher-level controller 6, and a remote monitoring device 7 as on-board devices, which are surrounded by a dashed line in Fig. 1, and operates in cooperation with the ground server 8. The ground server 8 may also be considered to be included in the monitoring system 5. The railway vehicle battery monitoring method executed using the monitoring system 5 is also referred to as the present method.

[0013] The battery system 1 includes a plurality of storage battery boxes 2, numbered 1 to n, a host controller 6, and a remote monitoring device 7. The storage battery box 2 is a housing that houses a battery module 3 and a battery controller 4, and is mounted on the roof or under the floor of a railway vehicle (not shown). Although the first embodiment includes a plurality of storage battery boxes 2, numbered 1 to n, a single box may house a plurality of series-connected circuits. The number of battery cells that the battery module 3 is configured from is arbitrary.

[0014] The battery module 3 is formed by combining and connecting a plurality of battery cells, which are the smallest unit of a storage battery, and is provided with a battery cell voltage monitoring board (not shown) and a temperature detection thermistor (not shown). As shown in the dotted line in Figs. 11 and 13 and described later, it is assumed that the voltage of each battery cell is monitored individually and simultaneously across the plurality of storage battery boxes 2. The battery controller 4 calculates the state of charge (SOC) of the storage battery as well as index values ​​that indicate the degree of deterioration, in other words, the lifespan, such as the capacity maintenance rate and the resistance increase rate. Note that the capacity maintenance rate = battery capacity at a certain cycle / initial battery capacity x 100, and the amount of decrease in the capacity maintenance rate and the resistance increase rate are positively correlated.

[0015] These SOC and other index values ​​are calculated based on, for example, the voltage and temperature of the battery module 3 and the current of each series group of the battery box 2. The voltage and temperature of the battery module 3 are measured by a sensor mounted on the battery module 3. The current of each series group is measured by a current sensor attached to each series group. Here, the battery controller 4 is arranged in association with the battery modules 3 in which m batteries are connected in series, and detects the voltage, current, and temperature collectively, but detects only the voltage of each battery cell individually. That is, in the battery controller 4, the current and temperature are monitored for each battery module, i.e., for each battery box 2, and the voltage is monitored for each of the battery cells. Note that the present invention is not limited to such a configuration and can be applied in other forms.

[0016] The upper controller 6 receives all of the current, voltage, temperature, SOC, and deterioration level (lifespan) output from each battery controller 4. Data processing in the upper controller 6 will be described later. The remote monitoring device 7 includes a router (not shown) and an antenna (not shown) that communicate using a mobile phone base station line such as LTE, 4G, or 5G, and transmits the data processed by the upper controller 6 to a ground server 8. The ground server 8 receives and stores the data transmitted by the remote monitoring device 7.

[0017] Fig. 2 is a block diagram showing the functional configuration of the monitoring system 5 of Fig. 1. As shown in Fig. 2, the battery controller 4 has a battery characteristic value measuring unit 4a, a SOC estimating unit 4b, an abnormality diagnosing unit 4c, and a cell information processing unit 4d. The battery characteristic value measuring unit 4a measures the battery module voltage, the battery module current, the battery module temperature, and each battery cell voltage. SOC estimation Department 4b estimates the battery module SOC based on the battery module voltage, the battery module current, and the battery module temperature among the measured battery characteristics.

[0018] The abnormality diagnosis unit 4c performs fault diagnosis for overvoltage, overcurrent, overtemperature, etc., and when a fault occurs, displays the battery module fault flag from 0 (no fault) to 1 (fault), and sets the battery module fault code from 00 (no fault) to a value assigned to each fault item. The cell information processing unit 4d outputs the maximum value of each battery cell voltage in the battery module 3 as the maximum battery cell voltage, and the minimum value as the minimum battery cell voltage.

[0019] As described above, the battery controller 4 acquires the battery module voltage, battery module current, battery module temperature, battery module SOC, battery module fault flag, battery module fault code, maximum battery cell voltage, and minimum battery cell voltage, and transmits this information to the upper controller 6 as battery module information.

[0020] The upper controller 6 receives battery module information nm from each of the battery controllers 4. The symbol nm attached to the information identifies the position of the battery module. For example, the battery module information 21 indicates that it is information on the battery module housed in the second battery box 2 (FIGS. 1, 11, and 13) in the battery system 1, that is, the first stage battery module from the high (positive) voltage side in the second series group.

[0021] This battery module information nm is input to a daily report data generating unit 6a and a time series data generating unit 6b in the upper controller 6. The daily report data generating unit 6a and the time series data generating unit 6b record the separately generated daily report data and time series data, and transmit them to the remote monitoring device 7. This monitoring system 5 can reduce the amount of communication required for data such as lifespan estimation, predictive diagnosis, and cause analysis at the time of failure from the railway vehicle to the ground server 8. The reason for this is explained below.

[0022] Time series data is a huge amount of information, and when a failure occurs, it provides data at the optimal timing in an easily analyzable state to identify the cause, but the communication places a considerable burden on the system. In contrast, daily report data can show only the most notable characteristic data from the huge amount of time series data with a small amount of information, as will be explained later using the comparison list in Figure 9.

[0023] Fig. 3 is a block diagram showing the calculation process of the daily data generating unit 6a in Fig. 2. As shown in Fig. 3, the daily data generating unit 6a receives six inputs, namely, the battery module voltage nm, the maximum battery cell voltage nm, the battery module temperature nm, the minimum battery cell voltage nm, the battery module SOC nm, and the battery module current nm, and calculates at least one of the maximum value, the minimum value, the average value, and the integrated value for each of the characteristic values. The symbol nm identifies one of the multiple battery cells connected in series and parallel.

[0024] The maximum value calculation unit 6a1 takes five inputs, namely, the battery module voltage nm, the battery module temperature nm, the battery module SOCnm, the battery module current nm, and the maximum battery cell voltage nm, and constantly outputs the maximum value during operation by comparing the input in the cycle currently being measured with the maximum output value from one cycle ago and extracting the larger value.

[0025] The minimum value calculation unit 6a2 receives the battery module voltage nm, the battery module temperature nm, the battery module SOCnm, the battery module current nm, and the minimum battery cell voltage nm as input, and always outputs the minimum value during operation by comparing the input in the cycle currently being measured with the minimum value of the output one cycle ago and extracting the smaller value.

[0026] The average calculation unit 6a3 calculates the sum of each of the battery module voltage nm, battery module temperature nm, and battery module SOCnm, and outputs the average value obtained by dividing the sum by the number of data for each. For the battery module current nm, the squared value is input to the average calculation unit 6a3, and the RMS (Root Mean Square) value is output by calculating the square root of the output. Finally, the integration value calculation unit 6a4 inputs the absolute value of the battery module current nm, calculates the sum, and outputs the sum as the integration value of the battery module current nm.

[0027] Fig. 4 is a table showing a list of the output results of the daily report data generating unit 6a in Fig. 2. As shown in Fig. 4, for all of the battery modules 3 numbered 11 to nm, the representative values ​​of the battery characteristic values, that is, at least any one of the maximum value, minimum value, average value, and integrated value, are calculated.

[0028] In addition, this daily report data may omit some characteristic values, such as the integrated voltage value not shown in the table of Fig. 4. Also, as with the RMS current value in this daily report data, calculation processing such as squaring or square root may be performed before or after the processing of calculating at least one of the maximum value, minimum value, average value, and integrated value, as a common statistical processing method.

[0029] As described above, the monitoring system 5 records and outputs at least one of the maximum, minimum, average, and integrated values ​​of the battery characteristic values ​​as daily report data, thereby reducing the amount of data compared to time-series data. In this way, the monitoring system 5 compares daily daily report data and captures changes in the state as characteristic information. In other words, in the case of an application in which only noticeable changes are to be grasped in the monitoring system 5, it is convenient to thin out and omit time-series data with no change from the daily comparison data, since this makes the characteristic information stand out.

[0030] Furthermore, because the operation of railway vehicles is managed on a daily basis, if the monitoring system 5 is used for railways, it is easier to compare differences between operation numbers and visualize the impact on the storage battery when an unsteady state such as an accident occurs by making the daily report data more concise. In other words, the monitoring system 5 makes it easier to visually recognize and grasp prominent characteristic information by graphing the daily report data.

[0031] Fig. 5 is a block diagram showing the calculation process of the time-series data generating unit 6b in Fig. 2. As shown in Fig. 5, the time-series data generating unit 6b is composed of a time-series data target extracting unit 6b1 and a battery characteristic value data extracting unit 6b2. First, the time-series data target extracting unit 6b1 extracts data to be sent to the ground server 8 by the remote monitoring device 7 from the characteristic information on all the battery modules 3.

[0032] In the first embodiment, as shown in FIG. 5, the extracted data as a monitoring target sent by the monitoring system 5 to the ground server 8 is the battery module information 11-1m of the first series group from the battery module information 11-nm of all the battery modules 3. This is only one example, and the battery module information may be changed to a different data extraction target. In addition, the monitoring system 5 may extract the data from the battery module information, that is, the monitoring target, from one battery module or from two or more series groups. Various aspects of such selection of a monitoring target will be described later with reference to FIGS. 10 and 11 of the second embodiment and FIGS. 12 and 13 of the third embodiment.

[0033] Next, the battery characteristic value data extraction unit 6b2 further extracts, from the battery module information 11~1m extracted by the time series data target extraction unit 6b1, the battery module voltage 11~1m, the battery module temperature 11~1m, the battery module SOC 11~1m, the battery module current 11~1m, the maximum battery cell voltage 11~1m, and the minimum voltage 11~1m as battery characteristic values, and records and outputs them.

[0034] FIG. 6 shows four types of graphs showing the output results of the time-series data generating unit 6b in FIG. 2. In FIG. 6, the horizontal axis indicates time, and the vertical axis plots the battery characteristic values ​​classified by the following graphs (a) to (d). Each graph plots characteristic values ​​classified into the following categories: (a) battery module voltage, maximum battery cell voltage, minimum battery cell voltage, (b) battery module current, (c) battery module SOC, and (d) battery module temperature. By obtaining such time-series data, the present monitoring system 5 is capable of estimating the life span of the storage battery (box, battery module, or battery cell) to be monitored, analyzing the cause of failure, and the like. Note that a description of the analysis method for this purpose will be omitted.

[0035] Fig. 7 is a block diagram showing the remote monitoring device 7 of Fig. 2 in more detail. As shown in Fig. 7, the remote monitoring device 7 is composed of an on-board server 7a, a router 7b, and an antenna 7c. First, the on-board server 7a will be described. As a more specific example of the on-board server 7a, a memory card provided in a part of the driver's cab of the train is used to store time-series data for a certain period of time and transmit the data to the ground server 8 as appropriate.

[0036] The on-board server 7a has the functions of a start / end determination unit 7a1 and a transmission data management unit 7a2. The start / end determination unit 7a1 determines whether the railway vehicle is starting up, in operation, or shutting down, and transmits the determination result to the transmission data management unit 7a2 as a railway vehicle status signal. Next, the transmission data management unit 7a2 determines the transmission data to be transmitted to the ground server 8 based on the daily report data, time series data, and railway vehicle status signal received from the upper controller 6.

[0037] Fig. 8 is a diagram illustrating the selection of transmission data in the transmission data management unit 7a2 in Fig. 7. As shown in Fig. 8, in a normal railway vehicle, once started up in the morning, the power supply to the railway vehicle is often not turned off until the end of the day's operation, but the power supply may be cut off during the day due to a power outage or a long downtime, etc., so a case is assumed in which the computer is started up and shut down twice each in one day.

[0038] In the first embodiment, the transmission data management unit 7a2 sets the time series data of the battery characteristic values ​​as transmission data during operation, and sets the daily report data as transmission data when the driver turns off the power. The transmission data including the daily report data of all the storage batteries and the time series data of some of the storage batteries is transmitted to the ground server 8 via the router 7b and the antenna 7c.

[0039] The ground server 8 receives the time series data during operation and the daily report data at the end, and stores this data for data display and data analysis. Here, when the ground server 8 receives daily report data multiple times in one day, it creates daily report data for that day from each daily report data and its respective operation time.

[0040] In addition, in Fig. 8, the operating hours are from 6:00 to 12:00 and from 15:00 to 21:00, but some lines operate beyond midnight. In that case, the time when operation is usually considered to have ended, such as 3:00 a.m., can be used as the dividing line for the day.

[0041] Fig. 9 is a list comparing the daily report data and time series data stored in the ground server 8 in Fig. 1. As shown in Fig. 9, for each date, (a) daily report data for all battery modules and (b) time series data for a portion (battery modules 11 to 1m) are stored.

[0042] First, as shown in Fig. 9(b), the ground server 8 accumulates, although only a part of, time-series data of, for example, three arbitrarily specified battery modules 11, 12, and 1m. Based on the accumulated time-series data, the manager of the storage battery can grasp the aging behavior of the battery characteristic values, as well as the changes in the battery characteristic values ​​due to the travel route and temperature fluctuations. Therefore, the manager of the storage battery can use the accumulated time-series data for life estimation, predictive diagnosis, and cause analysis in the event of a failure.

[0043] 9(a), the ground server 8 is provided with an analysis program, and by executing the program, in addition to the individual variations in each battery module nm in the battery system 1, if there is a battery module nm that has a significant difference from the overall average, the ground server 8 can identify which battery module nm has a significant difference from the overall average. In this manner, the ground server 8 can grasp the overall state or the state of a part of the battery modules nm identified arbitrarily for the battery system 1 to be monitored.

[0044] 9(a) and (b), the ground server 8 can infer the time series data of even battery modules not subject to (b) by correcting the time series data of (b) based on the daily report data of (a). As a result, the monitoring system 5 can grasp the overall state of the battery modules 3 in the battery system 1 in a manner similar to a sampling inspection.

[0045] To obtain the same effect as described above, the time series data of all the battery modules 3 may be transmitted from the remote monitoring device 7 to the ground server 8. However, in this case, the amount of information is enormous, imposing a burden on communication. In contrast, the daily report data can indicate only prominent characteristic data from the vast amount of time series data with a small amount of information. Therefore, in the first embodiment, if the daily report data for all the storage batteries is transmitted and the time series data is transmitted for some of the storage batteries, the amount of communication from the railway vehicle to the ground server 8 can be reduced. EXAMPLES

[0046] In the battery monitoring system 5 of the first embodiment, there is no concept of actively switching and selecting the multiple battery modules 3 to be monitored. The aspects of the second and third embodiments, which differ in this respect, will be described in order. First, the second embodiment will be described with reference to Figs. 10 and 11. In the railway vehicle battery monitoring system 5 of the second embodiment (using the reference numeral 5 in Fig. 1), the storage battery from which time series data is acquired is not fixed, but is switched on a daily basis. Fig. 10 is a block diagram showing the calculation process of a time series data generating unit 6b' of the second embodiment of the present invention.

[0047] In the first embodiment, the battery module from which time-series data is acquired is always the first series group (battery modules 11 to 1m), but in the second embodiment, a switch is turned on in the time-series data target extraction unit 6b1' to switch the target based on the extracted data target number. The extracted data target number is incremented, for example, every day, and is set to return to 1 the day after it reaches the maximum number of series groups.

[0048] Fig. 11 is a circuit diagram illustrating an example of a series-parallel connection of storage batteries from which the time-series data generating unit 6b' in Fig. 10 acquires data. As shown in Figs. 10 and 11, the time-series data generating unit 6b' in the second embodiment switches the series group of batteries from which data is acquired on a daily basis. The time-series data generating unit 6b' is configured to acquire data from battery modules 11-1m in the first battery box 2 on the first day, battery modules 22-2m in the second battery box 2 on the second day, and battery modules n1-nm in the last n-th battery box 2 on the nth day, and then acquire data from battery modules 11-1m in the first battery box 2 again on the day after the acquisition.

[0049] With the above configuration, the monitoring system 5 of the second embodiment can periodically acquire time series data of all battery modules. Therefore, it is possible to analyze the aging of battery characteristic values ​​of all battery modules in the battery system 1. Furthermore, the monitoring system 5 of the second embodiment can grasp the variation in battery cell voltage between battery cells of the same current in the same series group by acquiring data for each series group. As a result, the monitoring system 5 of the second embodiment is particularly useful for preventing failures such as battery cell overvoltage. Note that all battery cells are individually monitored for voltage.

[0050] In addition, in the present monitoring system 5 of the second embodiment, the opportunity to acquire time series data is, for example, once every 12 days in the case of a 12-parallel battery system 1. It is considered that changes such as battery deterioration and seasonal variations change in a sufficiently longer period than this cycle. Therefore, in the present monitoring system 5 of the second embodiment, the opportunity to acquire time series data may be once every several days. The other configurations of the second embodiment are the same as those of the first embodiment described above, and redundant explanations are omitted. In addition, as shown in the dashed box in FIG. 11, any of the battery cells can be monitored individually or simultaneously across multiple storage battery boxes 2. The range, information density, and frequency of the monitored object can be set arbitrarily, and the dashed box shown in FIG. 11 is merely an example. EXAMPLES

[0051] Next, a railway vehicle battery monitoring system 5 (corresponding to 5 in FIG. 1 and FIG. 2) according to a third embodiment will be described with reference to FIG. 12 and FIG. 13. In the present monitoring system 5 according to the third embodiment, the storage batteries for which time series data is acquired are not switched on a daily basis for each series group, but the same number of battery modules are selected as monitoring targets from each of the 1st to nth series groups. FIG. 12 is a block diagram showing the calculation process of a time series data generating unit 6b'' according to the third embodiment of the present invention.

[0052] A time-series data generating unit 6b'' according to Example 3 in FIG. 12 differs from a time-series data generating unit 6b' according to Example 2 in FIG. 10 in that a battery module information recombining unit 6b3 is added before the switch. The battery module information recombining unit 6b3 generates battery module information 1* to n* (*=1, 2, 3, ..., m) by decomposing and reconstructing battery module information *1 to *m (*=1, 2, 3, ..., n) transmitted respectively from each battery controller 4.

[0053] Fig. 13 is a circuit diagram illustrating an example of storage batteries connected in series and parallel, from which data is acquired by the time-series data generating unit 6b'' in Fig. 12. As shown in Fig. 13, in the third embodiment, the same number of battery modules are selected from each series group, such as the first battery module from the high voltage side of all series groups on the first day, and the second battery module from the high voltage side of all series groups on the second day.

[0054] With the above configuration, in the third embodiment, the time series data of all the battery modules can be periodically acquired. Furthermore, by selecting the data acquisition target from each of all the series groups, the current variation between the series groups can be grasped, which helps to prevent failures such as overcurrent before they occur. The other configurations of the third embodiment are the same as those of the first and second embodiments described above, and redundant explanations are omitted. Furthermore, as shown in the dashed box in FIG. 13, any of the battery modules can be individually or simultaneously monitored across multiple battery boxes 2. Note that the range, information density, and frequency of the monitored targets can be set arbitrarily, and the dashed box shown in FIG. 13 is merely an example. EXAMPLES

[0055] Next, a fourth embodiment will be described with reference to Fig. 14. Fig. 14 is a diagram illustrating an example of transmission data selection in a transmission data management unit (corresponding to 7a2 in Fig. 7) according to a fourth embodiment of the present invention. In the first embodiment shown in Fig. 8, the timing of daily report data transmission from the remote monitoring device 7 to the ground server 8 is at the end of each operation (when the computer is shut down). In contrast, in the fourth embodiment of Fig. 14, the timing is at the start of the next day.

[0056] In a railway vehicle battery monitoring system 5 (corresponding to 5 in FIG. 1 and FIG. 2) according to the fourth embodiment, a non-volatile memory is provided in an on-board server 7a. When the operation is terminated, daily report data is written to the non-volatile memory, and when the system is started up again, the daily report data is retrieved from the non-volatile memory and calculated. When the system is started up for the first time on the following day (the next operation day), the daily report data is retrieved from the non-volatile memory and transmitted to a ground server 8 via a router 7b and an antenna 7c.

[0057] With the above configuration, the monitoring system 5 of the fourth embodiment can transmit daily report data only once even if the system is started and stopped multiple times in one day, thereby reducing the amount of communication compared to the first embodiment. When multiple daily report data with different contents exist in one day, the monitoring system 5 of the fourth embodiment can combine the data into a single daily report data by extracting only the more significant maximum and minimum values, for example. Therefore, the monitoring system 5 of the fourth embodiment does not have to worry about which of multiple daily report data with different contents to transmit. EXAMPLES

[0058] Next, a fifth embodiment will be described with reference to Figures 15 to 18. In a railway vehicle battery monitoring system 5 (corresponding to 5 in Figures 1 and 2) according to the fifth embodiment, time series data of a part of the storage battery is not sent to the ground server 8 throughout the entire operation period, but rather, time series data of the storage battery is sent to the ground server 8 only for a few minutes before and after the occurrence of a fault.

[0059] Fig. 15 is a diagram showing a functional configuration of the present battery monitoring system 5. As shown in Fig. 15, in the present monitoring system 5 of the fifth embodiment, an event data generating unit 6c is added as a function of the upper controller 6'.

[0060] The event data generating unit 6c generates and outputs a failure occurrence flag that is selected by ORing the battery module failure flags of all the battery modules 3. Generate The unit 6a' records the time (fault occurrence time) when the battery module fault flag becomes 1 (fault exists) and the fault code based on the battery module fault flag of each battery module 3. Furthermore, the time-series data generating unit 6b performs the same processing as in the first embodiment, but outputs the time-series data of the battery characteristic values ​​of all the battery modules 3 only for a predetermined time before and after the occurrence of an accident.

[0061] Fig. 16 is a block diagram showing the remote monitoring device 7' of Fig. 15 in more detail. As shown in Fig. 16, in the fifth embodiment, the processing of a transmission data management unit 7a2' in the on-board server 7a' is different. The transmission data management unit 7a2' holds the time series data for the past few minutes across all the storage batteries received from the upper controller 6', and sets the time series data for the few minutes before and after the accident in which the fault occurrence flag becomes 1 (fault present) as the transmission data.

[0062] Fig. 17 is a diagram illustrating the selection of transmission data in the transmission data management unit 7a2' in Fig. 16. As shown in Fig. 17, for two faults that occur during operation, time series data of all battery modules for several minutes before and after each fault is transmitted to the ground server 8 as transmission data. Also, as with the first embodiment, daily report data is transmitted to the ground server 8 at the end of operation. Since the amount of all time series data for one day is enormous, only the main points for several minutes before and after the accident are used as time series data.

[0063] Fig. 18 is a diagram illustrating the accumulated data of the ground server 8 of Fig. 16. The daily report data of Fig. 18 accumulates the time of failure occurrence and the failure code of each battery module 3 in addition to the data of the first embodiment shown in Figs. 4 and 9. Furthermore, as time-series data, time-series data of the battery characteristic values ​​of all battery modules for several minutes before and after the failure occurrence accident is accumulated. In other words, the monitoring system 5 of the fifth embodiment continuously buffers data like a drive recorder, and uses only the main points for several minutes before and after the accident as time-series data only when a failure flag is set.

[0064] With the above configuration, the monitoring system 5 of the fifth embodiment can obtain daily report data of the battery characteristic values ​​of all the battery modules 3 and time series data for several minutes before and after the occurrence of a failure, and from these pieces of information, the cause of the failure can be analyzed in more detail. Note that, although the time series data is acquired from all the battery modules here, this is not limited to this. The monitoring system 5 of the fifth embodiment may focus on some battery modules as the monitoring targets, for example, only the battery module in which a failure has occurred. The other configurations of the monitoring system 5 of the fifth embodiment are the same as those of the first embodiment described above, and duplicated explanations are omitted.

[0065] The present invention is not limited to the above-described embodiments, and includes various modified forms. For example, the above-described embodiments have been described in detail to clearly explain the present invention, and are not necessarily limited to those including all of the configurations. In addition, it is possible to replace a part of the configuration of one embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of one embodiment. In addition, it is possible to add, delete, or replace a part of the configuration of each embodiment with another configuration.

[0066] [supplement] In recent years, against the backdrop of environmental issues such as global warming, energy conservation has become even more important in various industrial fields, and further reductions in power consumption are also required in railways. In light of this situation, railway vehicles equipped with storage batteries, such as battery-powered electric trains that run on battery power alone in non-overhead sections and hybrid diesel railcars that combine engines and storage batteries, are becoming more widespread.

[0067] The monitoring system 5 is applicable to railway vehicles equipped with a battery system 1, but there are no particular limitations on the type of vehicle. The monitoring system 5 can be applied to all railway vehicles equipped with a battery system 1, including the trains described above, hybrid diesel railcars, trains equipped with a light-load regenerative system that charges a storage battery with regenerative power for reuse, trains equipped with an emergency running system that runs on discharged power from a power storage device in an emergency, and the like.

[0068] In addition, although the above description assumes that lithium ion batteries are used as the storage batteries that make up the battery system 1, the present invention can be applied to other storage elements such as lead batteries and nickel-metal hydride batteries in the same manner. Note that the above-mentioned LTE is an abbreviation for the current third generation mobile phone, but it also refers to communication standards called 3.9G and 4G that are long-term evolutions of 3G. The communication speed and capacity of LTE are close to those of base station lines for home broadband mobile phones.

[0069] This monitoring system 5 can be summarized as follows. [1] The present monitoring system 5 shown in Fig. 1 monitors a plurality of storage batteries arranged in the nth column x mth column of Fig. 13, and generates and records at least one of the maximum, minimum, average and integrated values ​​of the battery characteristic values ​​for each storage battery as daily report data and transmits them to a server 8. The purpose of the daily report data is mainly to determine the timing of maintenance by identifying where a battery cell is arranged in the nth column x mth column, and to obtain an index showing its degree of deterioration (lifespan) as simply as possible.

[0070] Since the operation of railway vehicles is managed daily, the daily time series data and daily report data are generally repeated in the same pattern. In other words, the daily report data of the battery characteristic values ​​monitoring the storage batteries constituting the battery system 1 of the railway vehicle is operated according to the same timetable every day, excluding variable factors such as changes in transportation demand due to the calendar, season, and social situation, and environmental changes such as weather, so the battery characteristic values ​​also fluctuate in the same pattern.

[0071] For example, in the case of a battery system 1 for a railway vehicle that runs on schedule with a full load of passengers during the morning and evening rush hours on weekdays, the daily report data from Monday to Friday often repeats the same pattern. Therefore, if there is a change in the daily report data that deviates from the same pattern even though there are no fluctuation factors as described above, it is possible that the cause is a malfunction or accident. In this way, the daily report data can show only the most notable characteristic data out of the vast amount of time-series data with a small amount of information, as shown in comparison in Figure 9.

[0072] The monitoring system 5 can perform life estimation, predictive diagnosis, and cause analysis of failures from daily report data by performing calculation processing using statistical methods on various index values ​​for monitoring storage batteries. Therefore, the monitoring system 5 aims to provide appropriate information for maintaining the storage batteries mounted on the railway vehicle as well as for supporting train operation management in the long term, even if it does not have the real-time capability to give point-by-point instructions to the driver while operating the railway vehicle. Depending on this purpose, for example, for the battery module 3 shown in Fig. 1, it is possible to arbitrarily set the monitoring range to be captured in units of the battery module 3 or each battery cell individually.

[0073] To achieve this purpose, the monitoring system 5 only needs to handle daily report data that extracts the minimum necessary characteristic information from a huge amount of time-series data. In other words, if there is a change in the characteristic daily report data that deviates from the above-mentioned same pattern, it is possible that this is caused by a breakdown or accident, so it is sufficient to extract only the characteristic daily report data from the huge amount of time-series data and monitor it efficiently.

[0074] Therefore, the present monitoring system 5, which monitors multiple storage batteries, generates at least one of the maximum, minimum, average, and integrated values ​​of the battery characteristic values ​​for each day for all the storage batteries as daily report data, records and outputs the data, thereby reducing the amount of data compared with time-series data patterned by day. As a result, the present monitoring system 5 of [1] can easily obtain data that can be used for life estimation, predictive diagnosis, and cause analysis of failures, while suppressing the amount of communication from the railway vehicle to the ground server 8.

[0075] [2] In the present monitoring system 5 described in [1] above, it is preferable to generate and record time series data of the battery characteristic values ​​for one day for some of the storage batteries, and transmit the time series data for some of the storage batteries together with daily report data for all of the storage batteries to the ground server 8. The present monitoring system 5 can arbitrarily set the scope of the monitoring target, information density, and frequency, and can monitor any of the battery cells individually or simultaneously across multiple battery boxes 2. Therefore, simple daily report data and huge amounts of time series data can be used appropriately.

[0076] Time series data provides optimally timed data in an easily analyzable state for identifying the cause of a failure when it occurs, but the amount of information is huge and communication is burdensome. In contrast, daily report data, as shown in the comparison list in Figure 9, can display only prominent characteristic data from the vast amount of time series data with a small amount of information. As a result, the present monitoring system 5 in [2] can appropriately reduce communication volume, enabling efficient monitoring.

[0077] [3] In the present monitoring system 5 described in [2] above, the storage battery from which time-series data is acquired may be switched daily as shown in Figs. 11 and 13. This allows monitoring with optimal settings, since depending on the monitoring purpose, it may be desirable to set the monitoring frequency to once every few days. As a result, the present monitoring system 5 described in [3] can monitor efficiently by suppressing the current communication volume to the minimum required.

[0078] [4] In the present monitoring system 5 of [3] above, it is preferable that the storage batteries to be switched each day are each a series group. That is, as shown in Figures 10 and 11, in the present monitoring system 5 of [4], if each of the 1st to nth storage battery boxes 2 of the same specification is provided with a series group, and the 1st to nth storage battery boxes 2 are switched each day as the monitoring target, monitoring can be performed at an appropriate cycle that matches the rate at which each storage battery box 2 deteriorates. Furthermore, the present monitoring system 5 of [4] is even easier to use if the unit of storage battery boxes 2 that are switched as the monitoring target matches the unit of replacement during maintenance.

[0079] [5] In the present monitoring system 5 described in [3] above, the same number of target batteries to be switched each day may be selected from all the series groups. That is, as shown in FIG. 12 and FIG. 13, in the present monitoring system 5, each storage battery box 2 of the same specification has a series group, and each battery cell constituting the series group is also of the same specification. In that case, if the same number of battery cells are selected from each series group of all the storage battery boxes 2 to be monitored, by switching each day, current variations between the series groups can be detected. As a result, the present monitoring system 5 described in [5] can monitor the degree of deterioration in battery cell units according to the number of selections at an appropriate period. In addition, if the unit of battery cells to be switched as the monitoring target matches the unit of replacement during maintenance, the system is easy to use.

[0080] [6] In the present monitoring system 5 of [1] to [5] above, it is preferable that the battery characteristic value of the storage battery is indicated by one or more of the current, voltage, temperature, and charging rate, as shown in Fig. 4. According to the present monitoring system 5 of [6], it is possible to set an appropriate allowable charging / discharging current value according to the usage state based on the specifications according to the type of storage battery, for example, a lithium-ion battery, and also to realize good management of the maintenance cycle.

[0081] [7] In the present monitoring system 5 described in [1] to [6] above, as shown in Fig. 8, the daily report data may be transmitted to the ground server 8 when the battery monitoring system 5 is terminated (shutdown). A typical computer device includes a cache memory and a main memory for memory operations that can record data only while powered on, such as a random access memory (RAM) used during operation, and a non-volatile memory that can retain the stored contents even when the power is turned off during non-operation. According to the present monitoring system 5 described in [7], since there is no need to store data between shutdown and restart, the capacity required for the non-volatile memory in the upper controller 6 provided in the on-board device can be reduced.

[0082] [8] In the present monitoring system 5 described in [1] to [6] above, as shown in FIG. 14, the daily report data may be transmitted to the ground server 8 when the battery monitoring system 5 is started for the first time each day. When a train stops for a long period of time several times a day due to train operation schedules, the entire train including the auxiliary engines may be put into a halt state by lowering the pantograph, etc. In such a case, the computer of the on-board device is shut down even during the day. In this case, in order to prevent the data from being lost, it is convenient for the computer to intermittently store one day's worth of daily report data in its non-volatile memory and transmit it to the ground server 8 only once each day when the battery monitoring system 5 is started for the first time.

[0083] In this way, in the present monitoring system 5 of [8], one day's worth of daily report data that has been stored intermittently multiple times is consolidated into one. Therefore, in the present monitoring system 5 of [8], the maximum, minimum, average, and integrated values ​​of the battery characteristic values ​​for all the storage batteries for one day are generated and transmitted once or as a single batch of simple processing. As a result, the burden on the on-board device computer is reduced. Furthermore, since the amount of daily report data is small even for one day's worth, the present monitoring system 5 of [8] requires only a small capacity of non-volatile memory for the computer.

[0084] [9] In the present monitoring system 5 described in [1] to [8] above, as shown in Fig. 18, time series data of battery characteristic values ​​before and after a battery failure may be generated and recorded, and transmitted to a ground server together with daily report data of all the batteries. Such a present monitoring system 5 can perform the same function as a drive recorder suitable for identifying the cause of a car accident, and can analyze the cause of the failure in more detail. That is, the present monitoring system 5 described in [9] continuously stores time series data, which is huge in amount and places a burden on communication, in memory, and continues to overwrite the memory area after a predetermined time, so that even a small memory capacity can be used to identify the cause of the failure.

[0085]

[10] The on-board device for railway vehicles according to an embodiment of the present invention (the on-board device suggested in FIG. 1) has a function of monitoring multiple storage batteries, generates and records at least one of the maximum, minimum, average and integrated values ​​of the battery characteristic values ​​for all the storage batteries as daily report data, and transmits the daily report data to the ground server 8. According to the on-board device of

[10] , data that can be used for life estimation, predictive diagnosis, cause analysis at the time of failure, etc. can be easily generated while suppressing the amount of communication from the railway vehicle to the ground server 8.

[0086]

[11] A railway vehicle storage battery monitoring method (the present method) according to an embodiment of the present invention is a method for monitoring a plurality of storage batteries in a railway vehicle, and generates and records at least one of maximum, minimum, average, and integrated values ​​of battery characteristic values ​​for all the storage batteries as daily report data, and transmits the daily report data to a ground server 8. The present method is carried out by executing a program stored in a memory in a computer constituting the present monitoring system 5 in a CPU (Central Processing Unit). t) is executed to form each of the functions constituting the present monitoring system 5, which are then executed according to a prescribed procedure. A one-chip microcomputer is preferably used as the computer, but part of a computer for other purposes may also be used. According to this method

[11] , data that can be used for life estimation, predictive diagnosis, and analysis of the causes of failures can be easily obtained while minimizing the amount of communication from the railway vehicle to the ground server 8. [Explanation of symbols]

[0087] 1...Battery system, 11~1m, 21~2m, n1~nm...Battery module information, 2...Battery box StorageBattery box, 3... Battery module, 4... Battery controller, 4a... Battery characteristic value measuring part, 4b... SOC estimation part, 4c... Abnormality diagnosis part, 4d... Cell information processing part, 5... Battery monitoring system, 6, 6'... Upper controller, 6a, 6a'... Daily report data generator, 6a1... Maximum value calculator, 6a2... Minimum value calculator, 6a3... Average value calculator, 6a4... Integrated value calculator, 6b, 6b', 6b''... Time series data generator, 6b1, 6b1', 6b1''... Time series data target extraction part part), 6b2 ... Battery characteristic value data extraction part, 6b3 ... Battery module information recombination part BatteryModule information rearrangement part, 6c...Event data generator, 7,7'...Remote monitoring device, 7a...On-board server, 7a1...Start / end judgment part, 7a2,7a2'...Transmission data management part, 7b...Router, 7c...Antenna, 8...Ground server

Claims

1. A battery monitoring system for a railway vehicle that monitors a plurality of storage batteries, A battery monitoring system for railway vehicles that generates and records at least one of the maximum, minimum, average, and integrated battery characteristic values ​​for all storage batteries for one day as daily report data and transmits it to a server.

2. generating and recording time series data of battery characteristic values ​​for one day for some of the storage batteries, and transmitting the time series data of the some of the storage batteries together with daily report data of all of the storage batteries to a ground server; 2. A battery monitoring system for railway vehicles according to claim 1.

3. The storage battery for which time series data is to be acquired is switched on a daily basis.

3. A battery monitoring system for railway vehicles according to claim 2.

4. The storage batteries to be switched each day are grouped in series.

4. A battery monitoring system for railway vehicles according to claim 3.

5. An equal number of batteries to be switched each day are selected from all series groups.

4. A battery monitoring system for railway vehicles according to claim 3.

6. The battery characteristic value of the storage battery is indicated by one or more of the current, voltage, temperature, and charging rate. A battery monitoring system for railway vehicles according to any one of claims 1 to 5.

7. Send the daily report data to the ground server when the battery monitoring system is shut down.

7. A battery monitoring system for railway vehicles according to claim 1.

8. The daily report data is sent to the ground server when the battery monitoring system is first started each day.

7. A battery monitoring system for railway vehicles according to claim 1.

9. Generate and record time series data of battery characteristics before and after a battery failure occurs, and transmit this data to a ground server together with daily report data for all batteries. A battery monitoring system for railway vehicles according to any one of claims 1 to 8.

10. An on-board device for a railway vehicle that monitors a plurality of storage batteries, An on-board device for railway vehicles that generates and records at least one of the maximum, minimum, average, and integrated values ​​of battery characteristic values ​​for all storage batteries in one day as daily report data, and transmits the daily report data to a ground server.

11. A railway vehicle battery monitoring method for monitoring a plurality of storage batteries in a railway vehicle, comprising: A method for monitoring batteries for railway vehicles, which generates and records at least one of the maximum, minimum, average, and integrated values ​​of battery characteristic values ​​for all batteries in one day as daily report data, and transmits the daily report data to a ground server.

Citation Information

Patent Citations

  • Power storage system including a modularized BMS (Battery Management System) interconnected structure and its control method

    JP2014524099A

  • Secondary battery deterioration determination device

    JP2017150925A

  • Construction machine management system

    JP2020005407A

  • Railway vehicle power storage facility and railway vehicle power storage element monitoring system

    JP2021019479A

  • Storage battery data storage device, computer program and storage battery data storage method

    JP2021088249A