Work plan support device and work plan support method
The work plan support device generates images to guide crane placement and transportation planning, addressing user knowledge gaps and ensuring efficient crane operations by providing detailed spatial and temporal logistics.
Patent Information
- Application Number
- JP2021086524
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-05-21
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2041-05-21
AI Technical Summary
Differences in users' knowledge and experience make it difficult to determine the appropriate crane placement and work plan for construction projects, including which crane to use and where to place it around a building.
A work plan support device that includes first and second planning support processing elements to generate primary and secondary work situation images, providing users with information on crane placement and transportation locations, while avoiding interference with buildings and materials, and considering crane specifications and external factors.
Facilitates the determination of crane work plans by reducing the influence of users' knowledge and experience, allowing for informed decisions on crane placement and transportation logistics.
Smart Images

Figure 0007589643000001 
Figure 0007589643000002 
Figure 0007589643000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a technique for supporting a work plan involving the transportation of a load by a crane. [Background technology]
[0002] In a work simulation system for plant construction, in order to realize the efficiency of the entire construction work, a technology has been proposed in which evaluation and analysis results are reflected in the instruction input by the user, and adjustments are made so that the instruction input contents fall within the input range between mutually related setting value input means (for example, see Patent Document 1). [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2009-169777 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, depending on the knowledge and / or experience of users, it may not be easy to determine a work plan, including where a crane with what performance should be placed around a building structure.
[0005] Therefore, an object of the present invention is to provide a system etc. that can reduce the influence of the degree of knowledge and experience of a user and facilitate the user's decision-making of a work plan for a crane. [Means for solving the problem]
[0006] The work plan support device of the present invention comprises: A first planning support processing element that recognizes the spatial occupation mode of the structure and the layout mode of a plurality of candidate transport locations based on a first factor specified through an input interface, generates a first work situation image representing the spatial occupation mode of the structure and the layout mode of the plurality of candidate transport locations, and outputs the image to an output interface; a second planning support processing element which recognizes an occupyable area of the crane and materials according to the arrangement of the crane based on a second factor specified through the input interface, recognizes a candidate transport location to which the crane can transport the materials while avoiding interference between the crane and the material and the structure based on the spatial occupation mode of the structure and the arrangement of the multiple candidate transport locations and the occupyable area of the crane and the material as a first transport location, generates a second work situation image in which the first transport location and a second transport location which is the other candidate transport location are expressed in a distinguishable form in the primary work situation image, and outputs the generated image to the output interface; It is equipped with:
[0007] According to the work plan support device having this configuration, a user who sees the primary work situation image output to the output interface can understand the spatial occupation mode of the structure and the layout mode of the multiple transport candidate points determined based on the first factor specified through the input interface. This allows the user to get an idea of where to place the crane in consideration of the spatial occupation mode of the structure and the layout mode of the multiple transport candidate points.
[0008] Furthermore, the system can provide a user who has come into contact with the secondary work situation image output to the output interface with a method for transporting materials by a crane while avoiding interference between the crane and materials, the crane arrangement and specifications of which are specified based on a second factor specified through the input interface, and the building structure. First transportation point The layout of the 。The first transport location may be the end location or the start location of the transport of materials. This allows the user to confirm the suitability of the second factor that determines the layout and specifications of the crane, and further the work plan including the crane specification selection defined by the second factor, in consideration of the layout of the first transport location. This reduces the influence of the user's knowledge and experience, making it easier for the user to determine the crane work plan.
[0009] In the work plan support device having the above configuration, It is preferable that the second planning support processing element recognizes the first transport location based on the first factor, the second factor, and an external factor that has an effect on a transport status of the material by the crane.
[0010] According to the work plan support of this configuration, a user who sees the secondary work situation image output to the output interface can grasp the layout of the first transport location where the crane can transport the material while avoiding interference between the crane and the material and the building structure, taking into account external factors that affect the transport situation of the material by the crane. This allows the user to confirm the suitability of the work plan defined by the second factor that takes into account the influence of external factors, in consideration of the layout of the first transport location. This reduces the influence of the user's knowledge and experience, making it easier for the user to determine the crane work plan.
[0011] In the work plan support device having the above configuration, It is preferable that the second planning support processing element recognizes the time series of the first transport location based on the time series of the external factor, generates a secondary work status image in which the first transport location and the second transport location are chronologically represented in a distinguishable form in the primary work status image, and outputs it to the output interface.
[0012] According to the work plan support of this configuration, a user who sees the secondary work situation image output to the output interface can grasp the time series of the layout of the first transport location where the crane can transport the material while avoiding interference between the crane and the material and the building in a situation where external factors change over time. This allows the user to confirm the suitability of the work plan defined by the second factor that takes into account the influence of external factors in consideration of the time series change in the layout of the first transport location. This reduces the influence of the user's knowledge and experience, making it easier for the user to determine the crane work plan.
[0013] In the work plan support device having the above configuration, It is preferable that the second planning support processing element recognizes the time series of the first transport location based on the time series of the second factor, generates a secondary work status image in which the first transport location and the second transport location are chronologically represented in a distinguishable form in the primary work status image, and outputs it to the output interface.
[0014] According to the work plan support device having the above configuration, a user who sees the secondary work situation image output to the output interface can grasp the time series of the layout of the first transport location where the crane can transport the material while avoiding interference between the crane and the material and the building structure in a situation where the layout of the crane changes over time. This allows the user to confirm the time series of the layout of the crane and / or the specifications determined by the second factor, and thus the suitability of the work plan defined by the second factor, in consideration of the time series change in the layout of the first transport location. This reduces the influence of the user's knowledge and experience, and makes it easier for the user to determine the crane work plan.
[0015] In the work plan support device having the above configuration, The first planning support processing element generates the first work situation image representing a time series of the space occupation state of the building and the arrangement state of the plurality of transportation candidate locations based on the time series of the first factor, and outputs the image to an output interface; It is preferable that the second planning support processing element recognizes the time series of the first transport location based on the time series of the first factor, generates the secondary work status image in which the first transport location and the second transport location are chronologically represented in a distinguishable form in the primary work status image, and outputs it to the output interface.
[0016] According to the work plan support device having this configuration, a user who sees the first work situation image output to the output interface can understand the time-series changes in the spatial occupation mode of the structure and the layout mode of the transport candidate location. Furthermore, a user who sees the second work situation image output to the output interface can understand the time-series changes in the layout mode of the first transport location to which the crane can transport the material while avoiding interference between the crane and the material and the structure whose spatial occupation mode changes over time. This reduces the influence of the user's knowledge and experience, and makes it easier for the user to determine the crane work plan.
[0017] In the work plan support device having the above configuration, It is preferable that the second planning support processing element outputs material attribute information representing attributes of materials that can be transported by the crane for each of the first transport locations based on the second factor to the output interface in a form that can be identified according to differences in the attributes.
[0018] According to the work plan support device having this configuration, a user who has come into contact with the material attribute information output to the output interface can grasp the attributes of materials that can be transported to each of the first transport locations. This allows the user to confirm the suitability of the second factors that determine the layout and specifications of the crane, and ultimately the work plan defined by the second factors, in consideration of the layout of the first transport locations. This reduces the influence of the user's knowledge and experience, making it easier for the user to determine the crane work plan.
[0019] In the work plan support device having the above configuration, It is preferable that the second planning support processing element partially restricts the manner in which the second factor is specified through the input interface based on the first factor that further defines an attribute of the material.
[0020] According to the work plan support device having the above configuration, the second factor that can be specified through the input interface is limited in consideration of the attributes of the material to be transported, and the arrangement and / or specifications of the crane determined according to the second factor are limited, thereby avoiding the generation of unreasonable work plan support information that exceeds the performance of the crane. This reduces the influence of the knowledge and experience of the user, making it easier for the user to determine the crane work plan. [Brief description of the drawings]
[0021] [Figure 1] 1 is a diagram illustrating the configuration of a work plan support device according to an embodiment of the present invention; [Diagram 2] 4 is a flowchart showing the function of the work plan support device. [Diagram 3] FIG. 11 is an explanatory diagram of a first work situation image (oblique image). [Figure 4] FIG. 11 is an explanatory diagram of a first work situation image (bird's-eye view image). [Diagram 5] FIG. 11 is an explanatory diagram of a secondary work situation image (oblique image). [Figure 6] FIG. 11 is an explanatory diagram regarding a secondary work situation image (bird's-eye view image). [Figure 7] FIG. 13 is an explanatory diagram relating to an output mode of material attribute information. [Figure 8] FIG. 13 is an explanatory diagram regarding a specified restriction mode for a second factor. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0022] (composition) The work plan support device according to one embodiment of the present invention shown in Fig. 1 is configured with a work plan support server 10 capable of communicating with each of a terminal device 2 and a database 102 via a network. The work plan support server 10 includes a first plan support processing element 11 and a second plan support processing element 12. Each of the first plan support processing element 11 and the second plan support processing element 12 is configured with an arithmetic processing device (CPU, processor core, etc.) and a storage device (memory such as ROM and RAM). The arithmetic processing device is designed to read necessary data and / or programs (software) from the storage device and execute arithmetic processing on the data in accordance with the programs, as described below.
[0023] The database server 102 constitutes a database that stores data necessary for work planning for the information terminal 20, such as data representing the spatial arrangement of buildings and cranes in a virtual space. The database server 102 may be a component of the work plan assistance server 10.
[0024] The terminal device 20 shown in FIG. 1 may be a smartphone, a tablet terminal, a personal computer, or the like. or As shown in FIG. 1, the terminal device 20 includes a terminal input interface 21. 、 Terminal Output Interface 22 and terminal control device 24The terminal input interface 21 is composed of capacitive touch buttons constituting a touch panel. The terminal output interface 22 is composed of an image display device constituting a touch panel, an audio output device, and further a wireless communication device. A designation signal is transmitted to the outside of the terminal device 20 by the wireless communication device. The terminal control device 20 is composed of an arithmetic processing device (CPU, processor core, etc.) and a storage device (memory such as ROM and RAM).
[0025] (function) The functions of the remote operation support system and the imaging function control system having the above configuration will be described with reference to the flowchart shown in Fig. 2. In the flowchart, a block "C●" is used for the sake of simplicity, and means transmission and / or reception of data, and means a conditional branch in which processing in a branching direction is executed on the condition that the data is transmitted and / or received.
[0026] In the information terminal 20, the first factor specified through the terminal input interface 21 is recognized by the terminal control device 24 and transmitted to the work plan assistance server 10 (FIG. 2 / STEP 212). The "first factor" is a factor for identifying a specified work situation model, which is one of a plurality of different work situation models. The work situation model is defined by the spatial occupation mode of the structure in the virtual space and the arrangement mode of the candidate transportation location. The work situation model may be defined by the topography of the location where the crane may be arranged around the structure. The work situation model may be defined by the spatial occupation mode of the vehicles and / or workers moving around the site. At this time, a terminal identifier for identifying the information terminal 20 is also transmitted to the work plan assistance server 10.
[0027] When the first factor is received by the work plan support server 10 (FIG. 2 / C 11), the first planning support processing element 11 recognizes a designated work situation model corresponding to the first factor, and further recognizes the spatial occupation mode of the structure in the virtual space that defines the designated work situation model and the layout mode of multiple transportation candidate locations (FIG. 2 / STEP 1 12).
[0028] According to the work situation model, for example, in a virtual space in which coordinate values (X, Y, Z) are defined by a three-dimensional orthogonal coordinate system shown in FIG. 3 and FIG. 4, the spatial occupation mode of a substantially rectangular building Q is defined by a three-dimensional region {X, Y, Z|X1≦X≦X2, f1(X)≦Y≦f2(Y), g1(X, Y)≦Z≦g2(X, Y)}. f1 and f2 are functions (e.g., linear functions) of the main variable X for defining the spread mode of the building Q in the Y direction. g1 and g2 are functions of the main variables X and Y for defining the spread mode of the building Q in the Z direction. Also, as shown in FIG. 3 and FIG. 4, a plurality of transportation candidate locations P in the virtual space are distributed and disposed on each of the top and sides of the building Q. The transportation candidate locations P are defined by the coordinate values (X, Y, Z) of a point or a two-dimensional or three-dimensional region spreading with respect to the reference point.
[0029] Next, the first planning support processing element 11 generates a primary work status image representing the spatial occupation pattern of the structure Q in the virtual space and the arrangement pattern of multiple candidate transportation locations P, and transmits it to the information terminal 20 (Figure 2 / STEP 114).
[0030] When the information terminal 20 receives a first work situation image (FIG. 2 / C21), the terminal control device 24 outputs the first work situation image to the terminal output interface 22 (FIG. 2 / STEP 214). As a result, an oblique image as shown in FIG. 3 and / or a bird's-eye image as shown in FIG. 4 are output to the terminal output interface 22 as a first work situation image representing the spatial occupation state of the structure Q in the virtual space and the arrangement state of multiple transport candidate locations P.
[0031] In the information terminal 20, the second factor specified through the terminal input interface 21 is recognized by the terminal control device 24 and transmitted to the work plan assistance server 10 (FIG. 2 / STEP 222). The "second factor" is a factor for specifying the arrangement and specifications of the crane M (or its base M0) in the virtual space that defines the work situation model. For example, the second factor corresponds to a unit vector indicating the coordinate value and orientation of the crane M in the virtual space around the structure Q, as well as specifications including the total rated load of the crane M and the size of the attachment M1. At this time, a terminal identifier for identifying the information terminal 20 is also transmitted to the work plan assistance server 10.
[0032] When the second factor is received by the work planning support server 10 (Figure 2 / C22), the second planning support processing element 12 recognizes the placement and specifications of the crane M in the virtual space according to the second factor (Figure 2 / STEP 122).
[0033] For example, in a virtual space in which coordinate values (X, Y, Z) are defined by the three-dimensional orthogonal coordinate system shown in Fig. 5 and Fig. 6, the position and orientation (unit vector representing the orientation) of the base body M0, which is a component of the crane M, are recognized as its arrangement mode. The respective shapes and sizes of the boom M11 and jib M12 constituting the base body M0 and the attachment M1, the permissible ranges of the swivel angle φ and elevation angle θ1 of the boom M11, the permissible range of the elevation angle θ2 of the jib M12, and the hoisting limit of the hook M22 suspended from the attachment M1 via the wire M21 are recognized as the specifications of the crane M. The hook M22 may include a main hook suspended from the tip of the boom M11 (e.g., the boom point sheave) and / or an auxiliary hook suspended from the tip of the jib M12 (e.g., the jib point sheave).
[0034] The allowable range of the height above sea level of the highest reachable part of crane M (upper limit height and lower limit height) is determined by the allowable ranges of the elevation angles θ1 and θ2, respectively, but if the structure of crane M is different, the allowable range of the height above sea level of the highest reachable part of crane M (upper limit height and lower limit height) may also be determined by the allowable range of the state variables that determine the position and / or posture of its movable parts.
[0035] In the virtual space, for example, the base body M0 is defined as a rectangular parallelepiped, the boom M11 and the jib M12 are each defined as a rectangular prism or a cylinder, and the wire M 21 is defined as a line and hook M22 is defined as a point. The shape and size of hook M22 may be defined to encompass the size of the material to be transported.
[0036] A crane M of various specifications may be selected by specifying the second factor through the terminal input interface 21. The crane M may be a mobile crane such as a crawler crane or a wheel crane (a crane that runs on tires, a rough terrain crane, a truck crane, or an all-terrain crane), or may be a fixed crane such as a jib crane, a climbing crane, or a tower crane. The crane M may be a tower crane, a luffing crane, or a fixed jib crane. The crane M may include a boom, a jib, a mast, and / or a strut as an attachment. The boom may be a telescopic boom or a lattice boom.
[0037] Next, the second planning support processing element 12 recognizes a candidate transport location P where the materials can be transported by the crane M while avoiding interference between the crane M and the materials (or hook M22) and the structure Q as the first transport location P1 (Figure 2 / STEP 123).
[0038] Specifically, the change in the position of the hook M22 and / or the material from the material transport start point P0=(X0,Y0,Z0) to the transport candidate point P=(X,Y,Z) (or from the transport candidate point P=(X,Y,Z) to the transport end point P0=(X0,Y0,Z0)) so as not to overlap with the structure Q is determined as the material position trajectory. Also, the boom M11 that realizes the material position trajectory is Turning The time series or change of the angle φ and the elevation angle θ1 of the jib M12, the elevation angle θ2 of the jib M12, and the length of the wire M21 are determined according to the inverse kinematics as the crane attitude trajectory. Turning The crane attitude trajectory is provisionally determined so that the angle φ and the elevation angle θ1, the elevation angle θ2 of the jib M12, and the length of the wire M21 do not deviate from their respective allowable ranges. For example, the allowable ranges of the elevation angle θ1 of the boom M11 and the elevation angle θ2 of the jib M12 may be determined based on the upper limit height position (upper limit value of the Z coordinate value) of the upper end of the crane M and / or the attachment M1.
[0039] Next, based on the crane attitude trajectory, the time series or change in the spatial occupation mode of the crane M and, by extension, its component, the attachment M1 (and the wire M21) is determined. Then, if the time series of the spatial occupation mode of the crane M does not overlap with the structure Q, the transport candidate location P corresponding to the time series of the spatial occupation mode of the crane M is recognized as the first transport location P1. On the other hand, if the time series of the spatial occupation mode of the crane M overlaps with the structure Q, the transport candidate location P corresponding to the time series of the spatial occupation mode of the crane M is recognized as the second transport location P2.
[0040] For example, the multiple candidate transport locations P shown in Figures 3 and 4 are divided into a first transport location P1 (see white circle) and a second transport location P2 (see black circle) as shown in Figures 5 and 6.
[0041] Then, the second planning support processing element 12 generates a secondary work status image in which the first transport location P1 and the second transport location P2 are represented in a distinguishable form in the primary work status image, and transmits it to the information terminal 20 (Figure 2 / STEP 126).
[0042] When the secondary work situation image is received by the information terminal 20 (FIG. 2 / C22), the terminal control device 24 outputs the secondary work situation image to the terminal output interface 22 (FIG. 2 / STEP224). As a result, the oblique image shown in FIG. 5 and / or the bird's-eye image shown in FIG. 6 are output to the terminal output interface 22 as a secondary work situation image in which the first transport location P1 (see white circle) and the second transport location P2 (see black circle) are identifiable in the primary work situation image representing the spatial occupation mode of the structure Q in the virtual space and the arrangement mode of the multiple transport candidate locations P.
[0043] (Action and effect) The work plan support server 10 (work plan support device) that realizes the above-mentioned functions allows a user who sees the primary work situation image output to the terminal output interface 22 of the information terminal 20 to understand the spatial occupation mode of the structure Q and the layout mode of the multiple transport candidate locations P that are determined based on the first factor specified through the terminal input interface 21 of the information terminal 20 (see FIG. 2 / STEP212→C11→STEP112→STEP114→C21→STEP214, FIG. 3 and FIG. 4). This allows the user to get an idea of where to place the crane M in consideration of the spatial occupation mode of the structure Q and the layout mode of the multiple transport candidate locations P.
[0044] Furthermore, the user who has come into contact with the secondary work situation image output to the terminal output interface 22 of the information terminal 20 can grasp the layout of the first transport location P1 where the crane M can transport the materials while avoiding interference between the crane M and the materials, the layout and specifications of which are specified based on the second factor specified through the terminal input interface 21, and the building Q (see FIG. 2 / STEP222→C12→STEP122→STEP124→STEP126→C22→STEP224, FIG. 5 and FIG. 6). This allows the user to confirm the suitability of the second factor that determines the layout and specifications of the crane M, and further the work plan including the specification selection of the crane M defined by the second factor, in consideration of the layout of the first transport location P1. This reduces the influence of the user's knowledge and experience, and facilitates the user's decision on the work plan for the crane M.
[0045] (Another embodiment of the present invention) In the above embodiment, the work plan support device is configured by the work plan support server 10, but in another embodiment, the work plan support device may be configured by the information terminal 20. That is, the first plan support processing element 11 and / or the second plan support processing element 12 may be configured by the terminal control device 24.
[0046] The second planning support processing element 12 recognizes the time series of the first transportation location P1 based on the first factor and the time series of the second factor (the time series of the arrangement state and / or the specifications of the crane M) and displays the first transportation location P1 in the first work status image. P1 and the second transportation point P2 Alternatively, a secondary work situation image in which the work status is represented in a time-series manner in a form in which the work status can be distinguished from the work status can be generated and output to the terminal output interface 22.
[0047] According to the work plan support device having the above configuration, a user who comes into contact with the secondary work situation image output to the terminal output interface 22 can grasp the time series of the arrangement of the first transport location P1 where the crane M can transport the materials while avoiding interference between the crane M and the materials and the structure Q in a situation where the arrangement of the crane M changes over time. For example, secondary work situation images (a plurality of intermittent still images or videos) in which the arrangement of the first transport location P1 and the second transport location P2 shown in Figs. 5 and 6 change are output to the terminal output interface 22. This allows the user to confirm the suitability of the second factor that determines the time series of the arrangement and specifications of the crane M, and further the work plan defined by the second factor, in consideration of the time series change in the arrangement of the first transport location P1. This reduces the influence of the user's knowledge and experience, and enables the user to confirm the suitability of the crane M. M This will facilitate the determination of work plans.
[0048] The first planning support processing element 11 may generate a primary work status image representing the time series of the spatial occupation mode of the structure Q and the layout mode of the multiple transportation candidate locations P, based on the time series of the first factor (the time series of the spatial occupation mode of the structure Q and the layout mode of the multiple transportation candidate locations P, respectively), and output it to the terminal output interface 21. In this case, the second planning support processing element 12 may recognize the time series of the first transportation location P1, based on the first factor and the second factor, generate a secondary work status image in which the first transportation location P1 and the second transportation location P2 are chronologically represented in a distinguishable form in the primary work status image, and output it to the terminal output interface 22.
[0049] The work plan support device having this configuration allows a user who sees the primary work situation image output to the terminal output interface 22 to understand the time-series changes in the spatial occupation mode of the structure Q and the layout mode of the transport candidate location P. For example, the structure Q shown in each of Figs. 3 and 4 is expanded (e.g., in the Z direction) according to the progress of the work, and a primary work situation image (a plurality of intermittent still images or video) showing the appearance of a new transport candidate location P at the expanded location (and even the disappearance of the transport candidate location P that existed until then) is output to the terminal output interface 22.
[0050] Furthermore, a user who sees the secondary work situation image output to the terminal output interface 22 can grasp the time series of the layout of the first transport location to which the crane M can transport the materials while avoiding interference between the crane M and the materials and the structure Q whose spatial occupation mode changes over time. For example, as the structure Q shown in each of Figs. 5 and 6 expands (e.g. in the Z direction) in accordance with the progress of the work, and a new transport candidate location P appears at the expanded location (and the previously existing transport candidate location P disappears), a secondary work situation image (a plurality of intermittent still images or video) showing the changing layout of the first transport location P1 and the second transport location P2 is output to the terminal output interface 22. This reduces the influence of the user's knowledge and experience, and makes it possible to easily understand the operation of the crane M by the user. M It is possible to facilitate the determination of the work plan. The secondary work situation images shown in Fig. 5 and Fig. 6 may include information representing the specifications of the crane M or a time series of the specifications.
[0051] The second planning support processing element 12 may output material attribute information representing the attributes of materials that can be transported by the crane M for each of the first transport locations P1 based on the second factor to the terminal output interface 22 in a form that can be identified according to differences in the attributes.
[0052] According to the work plan support device of this configuration, the user who comes into contact with the material attribute information output to the terminal output interface 22 can be made to understand the attributes of the materials that can be transported for each of the first transportation locations P1. For example, as shown in FIG. 7, a plurality of arc-shaped belt regions S1 and S2 as the movable regions of the hook M22 in a state where the wire M21 extends in the vertical direction or the Z direction according to the movable range of the attachment M1 based on the crane M or its base M0, and the materials that can be transported for each of the inner arc-shaped belt region S1 and the outer arc-shaped belt region S2 weight W(S1), W(S2) (and further the shape and size) are output to the terminal output interface 22. The inner diameter R0 and the outer diameter R1 of the inner arc-shaped belt region S1 are geometrically determined based on the allowable range of the elevation angle θ1 of the boom M11 and the allowable range of the elevation angle θ2 of the jib M12 determined according to the material weight W(S1). The inner diameter R1 and the outer diameter R2 of the outer arc-shaped belt region S2 are geometrically determined based on the allowable range of the elevation angle θ1 of the boom M11 and the allowable range of the elevation angle θ2 of the jib M12 determined according to the material weight W(S2) (<W(S1)).
[0053] Thereby, in view of the arrangement mode of the first transportation location P1, the crane M The second factor that determines the arrangement mode and specifications of the crane, and thus the appropriateness of the work plan defined by the second factor, can be confirmed to the user. For this reason, the influence due to the amount of the user's knowledge and experience can be reduced, and it is possible to facilitate the determination of the work plan of the crane by the user. M
[0054] The second plan support processing element 12 may partially limit the designation mode of the second factor through the terminal input interface 21 based on the first factor that further defines the attributes of the material.
[0055] According to the work plan support device with such a configuration, in view of the attributes of the materials to be transported, the second factor that can be specified through the terminal input interface 21, and thus the arrangement mode and / or specifications of the crane M determined according to the second factor are restricted. For example, when materials with a weight W(i) (W(S2) < W(i) ≤ W(S1)) are transported to the first transportation location P1(i) shown in FIG. 8, the arrangement candidate locations B1, B2,... Bm corresponding to the locations where the base M0 is arranged so that the inner arc-shaped belt region S1 shown in FIG. 7 does not overlap. Either The specification of the second factor such that the base M0 is arranged at [the above] is prohibited. On the other hand, the arrangement candidate locations A1, A2,... Am corresponding to the locations where the base M0 is arranged so that the inner arc-shaped belt region S1 shown in FIG. 7 overlaps. Either The specification of the second factor such that the base M0 is arranged at [the above] is permitted. Thereby, a situation where unreasonable work plan support information exceeding the performance of the crane M is generated is avoided. For this reason, the influence depending on the amount of the user's knowledge and experience is reduced, and it is possible to facilitate the determination of the work plan of the crane by the user. M
[0056] The second plan support processing element 12 may recognize the first transportation location P1 based on the first factor, the second factor, and external factors that affect the transportation status of the materials by the crane M.
[0057] According to the work plan support of this configuration, the user who sees the secondary work situation image output to the terminal output interface 22 can grasp the layout of the first transport location P1 where the crane M can transport the material while avoiding interference between the crane M and the material and the structure Q, in a form that takes into account external factors that affect the transport situation of the material by the crane M. The "external factors" include the allowable range of the height above sea level of the highest reach part of the crane M, the geographical area where the base body M0 of the crane M can be placed, the weather conditions that determine the geographical area (presence or absence of rainfall or snowfall, amount of rainfall or snowfall, presence or absence of freezing, etc.), and / or the direction and speed of the wind that the crane M and the material come into contact with. This allows the user to confirm the suitability of the work plan defined by the second factor that takes into account the influence of the external factors, in consideration of the layout of the first transport location P1. This reduces the influence of the user's knowledge and experience, and makes it easier for the user to determine the work plan for the crane M.
[0058] The second planning support processing element 12 may recognize the time series of the first transportation location P1 based on the time series of external factors, generate a secondary work status image in which the first transportation location P1 and the second transportation location P2 are chronologically represented in a distinguishable form in the primary work status image, and output it to the terminal output interface 22.
[0059] According to the work plan support of this configuration, a user who sees the secondary work situation image output to the terminal output interface 22 can grasp the time series of the layout of the first transport location P1 where the crane M can transport the material while avoiding interference between the crane M and the material and the structure Q in a situation where external factors change over time. This allows the user to confirm the suitability of the work plan defined by the second factor that takes into account the influence of external factors in consideration of the time series change in the layout of the first transport location P1. This reduces the influence of the user's knowledge and experience, making it easier for the user to determine the work plan for the crane M. [Explanation of symbols]
[0060] 10: Work planning support server (work planning support device), 11: First planning support processing element, 12: Second planning support processing element, 20: Information terminal, 21: Terminal input interface, 22: Terminal output interface, An: Candidate placement location, Bm: Candidate placement location, M: Crane, M0: Base, M1: Attachment, M11: Boom, M12: Jib, M21: Wire, M22: Hook, P: Candidate transport location, P1: First transport location, P2: Second transport location.
Claims
1. a first planning support processing element that generates a first work situation image representing the spatial occupation mode of the structure and the layout mode of the plurality of transportation candidate locations based on a first factor that is specified through an input interface and that defines the spatial occupation mode of the structure and the layout mode of the plurality of transportation candidate locations, and outputs the first work situation image to an output interface; a second planning support processing element which recognizes a candidate transport location to which the material can be transported by the crane as a first transport location while avoiding interference between the crane and the material and the building structure based on a second factor that defines the arrangement and specifications of the crane and is specified through the input interface in addition to the first factor, generates a second work status image in which the first transport location and a second transport location that is another candidate transport location are expressed in a distinguishable form in the primary work status image, and outputs the second work status image to the output interface; A work planning support device comprising:
2. 2. The work plan support device according to claim 1, The second planning support processing element recognizes the first transport location based on the first factor, the second factor, and an external factor that has an effect on the transport status of the material by the crane. Work planning support device.
3. 3. The work plan support device according to claim 2, The second planning support processing element recognizes a time series of the first transport location based on the time series of the external factor, generates a secondary work situation image in which the first transport location and the second transport location are chronologically represented in a distinguishable form in the primary work situation image, and outputs the secondary work situation image to the output interface. Work planning support device.
4. The work plan support device according to any one of claims 1 to 3, The second planning support processing element recognizes a time series of the first transport location based on the time series of the second factor, generates a secondary work situation image in which the first transport location and the second transport location are chronologically expressed in a distinguishable form in the primary work situation image, and outputs the secondary work situation image to the output interface. Work planning support device.
5. The work plan support device according to any one of claims 1 to 4, The first planning support processing element generates the first work situation image representing a time series of the space occupation state of the building and the arrangement state of the plurality of transportation candidate locations based on the time series of the first factor, and outputs the image to an output interface; The second planning support processing element recognizes a time series of the first transport location based on the time series of the first factor, generates the second work situation image in which the first transport location and the second transport location are chronologically expressed in a distinguishable form in the primary work situation image, and outputs the generated image to the output interface. Work planning support device.
6. The work plan support device according to any one of claims 1 to 5, The second planning support processing element outputs material attribute information representing attributes of materials that can be transported by the crane to each of the first transport locations based on the second factor in a form that can be identified according to differences in the attributes to the output interface. Work planning support device.
7. The work plan support device according to any one of claims 1 to 6, The second planning support processing element partially limits a manner in which the second factor is specified through the input interface based on the first factor that further defines an attribute of the material. Work planning support device.
8. A work plan support method including performing a first plan support process and a second plan support process by a calculation processing device, The first planning support process includes: The method includes a step of generating a primary work situation image representing the spatial occupation mode of the building and the layout mode of the plurality of transportation candidate locations based on a first factor that is specified through an input interface and that defines the spatial occupation mode of the building and the layout mode of the plurality of transportation candidate locations, and outputting the primary work situation image to an output interface; The second planning support process includes: a step of recognizing a candidate transport location to which the material can be transported by the crane as a first transport location while avoiding interference between the crane and the material and the structure, based on a second factor that defines a crane arrangement and specifications specified through the input interface in addition to the first factor; and generating a secondary work situation image in which the first transport location and a second transport location, which is another transport candidate location, are represented in a distinguishable form in the primary work situation image, and outputting the secondary work situation image to the output interface. Work planning support methods.
Citation Information
Patent Citations
Operation-simulating system for plant construction
JP2009169777A
bim-based on-site facility automation modeling system and method
JP2018522297A
Construction plan support system and construction plan support method
JP2020194426A
Crane planning support system
JP2021022020A
Simulation device
JP2021042045A