OPERATION PLAN CREATION DEVICE AND OPERATION PLAN CREATION METHOD

JP7635795B2Active Publication Date: 2025-02-26IHI CORP
View PDF 12 Cites 0 Cited by

Patent Information

Application Number
JP2023039489
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2023-03-14
Publication Date
2025-02-26
Estimated Expiration
2043-03-14

AI Technical Summary

Benefits of technology

【0029】 本発明によれば、実行が不可能な運転計画が作成されることを抑制できる運転計画作成装置及び運転計画作成方法が提供される。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007635795000003
    Figure 0007635795000003
  • Figure 0007635795000004
    Figure 0007635795000004
  • Figure 0007635795000005
    Figure 0007635795000005
Patent Text Reader

Abstract

To suppress the creation of an operation plan which is not executable.SOLUTION: An operation plan creation device 10 comprises: a prediction section 11 obtaining a predictive value of an electric power amount which is suppliable to a process apparatus 3 and includes electric power derived from renewable energy; and a simulation calculation section 13 creating an operation plan on the basis of the predictive value and time required for an operation preparation indicating a required time required for preparation of operation.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an operation plan creating device and an operation plan creating method. [Background technology]

[0002] Reducing greenhouse gas emissions from energy use is an urgent issue for realizing a sustainable society. Efforts to decarbonize are also accelerating in the manufacturing industry. In particular, the technology of producing synthetic methane by reacting carbon dioxide with hydrogen (methanation) is attracting a great deal of attention in the gas industry. Synthetic methane is produced from carbon dioxide emitted at business premises. The produced synthetic methane can then be used within the business premises as an alternative fuel to natural gas. The produced synthetic methane can also be used at other business premises and in ordinary households by injecting it into city gas pipelines.

[0003] In this way, synthetic methane can be produced using existing city gas infrastructure. Therefore, methanation is expected to be one of the key technologies toward achieving carbon neutrality. However, for this synthetic methane to be carbon neutral, it is desirable that the electricity used to produce it comes from renewable energy sources such as wind and solar power.

[0004] Patent Documents 1 to 7 disclose operating techniques related to process equipment exemplified by a methanation reactor. In the following description, the methanation reactor will be simply referred to as a "methanation apparatus."

[0005] Patent Document 1 discloses technology relating to equipment equipped with solar power generation, a hydrogen production device, and a storage battery. The technology disclosed in Patent Document 1 charges a storage battery with surplus power generated by solar power generation. Furthermore, when the amount of power stored in the storage battery exceeds a set value, hydrogen is produced (see S110 shown in FIG. 2 of Patent Document 1).

[0006] Patent Document 2 discloses a technology applied to a system including a hydrogen production device. The technology disclosed in Patent Document 2 provides a preparation period before the demand response supply and demand adjustment period when adjusting power supply and demand using a hydrogen production device, such as demand response. Then, by starting up the hydrogen production device during the preparation period, the power consumption of the hydrogen production system is made to match a target value before the supply and demand adjustment period.

[0007] Patent Document 3 discloses a technology applied to a system including a solar power generation device and a generator. The technology disclosed in Patent Document 3 increases the load by, for example, consuming power in the load when the generated power of a generator such as a solar power generation device is surplus and the charging rate of a storage battery is equal to or higher than a predetermined value.

[0008] Patent Document 4 discloses a technology applied to a system including a renewable energy power generation device and a storage battery. The technology disclosed in Patent Document 4 first predicts the power demand and the amount of power generated by the renewable energy power generation device, and predicts the remaining amount of power stored in the storage battery. After the prediction, if it is predicted that the remaining amount of power in the storage battery will be equal to or less than a threshold value or equal to or greater than a threshold value, the power consumption of the load is reduced or increased.

[0009] Patent Document 5 discloses a technology applied to a system including a renewable energy power generation device, a hydrogen production device, a fuel cell, and a storage battery. The technology disclosed in Patent Document 5 first obtains a predicted value of the amount of power generated by the renewable energy power generation device and a predicted value of power demand. Then, the charge amount of the storage battery and the power consumption of the hydrogen production device during the day are determined, and the discharge amount of the storage battery and the power generation amount of the fuel cell during the night are determined. This system consumes and / or charges power during the day, and generates and / or discharges power at night.

[0010] Patent Document 6 discloses a technology applied to a system including a photovoltaic power generation system and an air conditioning system. The technology disclosed in Patent Document 6 first predicts the amount of surplus power based on the predicted amount of photovoltaic power generation and the predicted amount of power consumption. Next, the time during which the predicted amount of surplus power exceeds a preset value for power consumption of the air conditioning system is calculated. Then, if the time during which the set value is exceeded exceeds the set continuous operation time, the excess time is set as the operation time of the air conditioning system using the surplus power.

[0011] Patent Document 7 discloses a technology applied to a system including a hydrogen production device and a hydrogen storage device. The technology disclosed in Patent Document 7 predicts power generation by renewable energy and the load of power consumers, and estimates surplus power from the predicted values. Using the estimated surplus power, a hydrogen production plan and a hydrogen storage plan are created. Then, the time to start pre-cooling and pre-heating the hydrogen storage device (hydrogen storage alloy) is set (see FIG. 2 in Patent Document 7). [Prior art documents] [Patent documents]

[0012] [Patent Document 1] JP 2020-54085 A [Patent Document 2] International Publication No. 2020 / 121436 [Patent Document 3] Patent Publication No. 2022-020978 [Patent Document 4] JP 2021-164178 A [Patent Document 5] Patent No. 6189448 [Patent Document 6] JP 2022-25398 A [Patent Document 7] Patent No. 7008297 Summary of the Invention [Problem to be solved by the invention]

[0013] The methanation reaction using a catalyst is an exothermic reaction. If the temperature becomes too high, the amount of methane synthesis decreases, so it is necessary to remove heat after the reaction starts. On the other hand, in order to start the methanation reaction, it is necessary to raise the temperature to about 250°C to 450°C. Therefore, it is difficult to instantly start producing methane from a state in which production is not possible, which is normal temperature and pressure.

[0014] For the above reasons, the methanation device needs to be heated before starting production. The time required for the heating operation is affected by the heating method (electric heater or steam heating), the size of the methanation device, and the device temperature at the start of the heating operation. The heating operation can take, for example, 15 minutes to 5 hours.

[0015] As an example of a methanation device, the conventional technology described above does not take into consideration the allocation of renewable energy power as the power consumption of process equipment that requires time for preparation such as increasing the temperature and pressure before operation. Therefore, when planning an operation to allocate renewable energy power as the power consumption of a process device, if the technology exemplified in the conventional technology is applied, there is a possibility that an operation plan that cannot be executed will be created.

[0016] The present invention provides an operation plan creation device and an operation plan creation method that can prevent an operation plan that cannot be executed from being created. [Means for solving the problem]

[0017] One form of the present invention is an operation plan creation device that creates an operation plan for an apparatus that can be switched from a non-manufacturing state in which no end product can be obtained even if power is input, to a manufacturable state in which an end product can be obtained when power is input, by performing operation preparation, and the apparatus includes a prediction unit that obtains a predicted value of the amount of power that can be supplied to the apparatus, including power derived from renewable energy, and a processing unit that creates an operation plan based on the predicted value and an operation preparation required time that indicates the time required for operation preparation.

[0018] This operation plan creation device creates an operation plan based on a predicted value of power and a required operation preparation time indicating the time required for operation preparation. Therefore, since the resulting operation plan takes into account the required operation preparation time, it is possible to prevent the creation of an operation plan that cannot be executed.

[0019] In an operation plan creation device according to one embodiment of the present invention, the operation plan includes a plurality of possible start times that can be selected as the time when operation preparation can be started, and the processing unit has a total evaluation amount calculation unit, which calculates a total evaluation amount based on the amount of power consumption consumed by the device for manufacturing the product based on a predicted value and an operation preparation required time under a condition that the operation preparation is started at a start time candidate selected from the plurality of possible start times, for each of the plurality of start time candidates, extracts at least one total evaluation amount showing a maximum value from the plurality of total evaluation amounts obtained for each of the plurality of start time candidates as a maximum total evaluation amount, and selects the start time candidate corresponding to the at least one maximum total evaluation amount as a first candidate that is a candidate for the time when operation preparation should be started. With this configuration, the time to start operation preparation can be determined based on the total production amount.

[0020] In the operation plan creation device according to one embodiment of the present invention, the processing unit may further include a total evaluation amount determination unit, and the total evaluation amount determination unit may compare at least one maximum total evaluation amount with a threshold value to select at least one of the first candidates, the maximum total evaluation amount of which is equal to or greater than the threshold value, as a second candidate. With this configuration, the time to start preparation for operation can also be determined based on the total production amount.

[0021] In the operation plan creation device according to one embodiment of the present invention, the processing unit may further include a start time determination unit, and when the total evaluation amount determination unit selects a plurality of second candidates, the start time determination unit may adopt the latest time among the second candidates as the start time for starting the operation preparation. With this configuration, the time for starting the operation preparation can be determined based on the total production amount.

[0022] In the operation plan creation device according to an embodiment of the present invention, the prediction unit may obtain a predicted value by predicting power output from a renewable energy power generation device. With this configuration, it is possible to obtain an operation plan for a device that operates using power supplied from the renewable energy power generation device.

[0023] In the operation plan creation device according to one embodiment of the present invention, the prediction unit may obtain a predicted value by predicting the power output from the renewable energy power generation device and acquiring a schedule indicating the power output from the energy storage device and the power input to the energy storage device. With this configuration, an operation plan for a device operated by the power supplied from the renewable energy power generation device and the power input / output to / from the energy storage device can be obtained.

[0024] In the operation plan creation device according to an embodiment of the present invention, the total evaluation amount may be a total production amount of the product produced by the device, the total evaluation amount being calculated based on the power consumption amount. With this configuration, evaluation can be performed based on the total production amount of the product.

[0025] In the operation plan creation device according to an aspect of the present invention, the total evaluation amount may be an amount of power consumption. With this configuration, it is possible to perform evaluation based on the amount of power consumption required to generate the product.

[0026] In the operation plan creation device according to one embodiment of the present invention, the processing unit may have a generating unit that creates a planning problem including a term defined by including an amount of power consumed by the apparatus to obtain a product at a predetermined time and a term indicating whether the apparatus is capable of receiving power and manufacturing the product, and a computing unit that obtains candidates for the operation plan by solving the planning problem. With this configuration, it is possible to create an operation plan that takes into account the time required for operation preparation by utilizing mathematical programming.

[0027] In the operation plan creation device according to an embodiment of the present invention, the processing unit may further include an adoption / rejection determination unit that adopts the candidate operation plan as the operation plan when a total evaluation value defined by including an amount of power consumed by the device obtained based on the operation plan is equal to or greater than a threshold. With this configuration, it is possible to determine whether to adopt the operation plan using the total evaluation value.

[0028] Another aspect of the present invention is an operation plan creation method for creating an operation plan for an apparatus that can be switched from a non-manufacturable state in which no product can be obtained even if power is input to a manufacturable state in which a product can be obtained when power is input by performing operation preparation, the method comprising: obtaining a predicted value of the amount of power that can be supplied to the apparatus, including power derived from renewable energy; and creating an operation plan based on the predicted value and a required operation preparation time indicating the required time for operation preparation. This method also makes it possible to create an operation plan that takes into account the required operation preparation time. Therefore, it is possible to prevent the creation of an operation plan that cannot be executed. Effect of the Invention

[0029] According to the present invention, an operation plan creation device and an operation plan creation method are provided that can prevent an operation plan that cannot be executed from being created. [Brief description of the drawings]

[0030] [Figure 1] FIG. 1 is a diagram showing a microgrid to which an operation plan creation device of the first embodiment is applied. [Diagram 2] FIG. 2 is a diagram illustrating a functional configuration of the operation plan creation device according to the first embodiment. [Diagram 3] FIG. 3 is a diagram illustrating an example of a hardware configuration of the operation plan creation device according to the first embodiment. [Figure 4] Figure 4 is a conceptual diagram of surplus power generated in the planned section. [Diagram 5] FIG. 5 is a diagram showing the relationship between the power consumption and the production volume of the process equipment. [Figure 6]Figure 6 is a conceptual diagram of the operation preparation and production simulation. [Figure 7] FIG. 7 is a flow diagram showing main steps of an operation plan creating method executed by the operation plan creating device of the first embodiment. [Figure 8] FIG. 8 is a diagram illustrating a microgrid to which the operation plan creation device of the second embodiment is applied. [Figure 9] FIG. 9 is a diagram illustrating a functional configuration of an operation plan creation device according to the second embodiment. [Figure 10] FIG. 10 is a table showing the meanings of the symbols (sets) that make up a mixed integer programming problem. [Figure 11] FIG. 11 is a table summarizing the meanings of the symbols (parameters, dependent variables) that make up the mixed integer programming problem. [Figure 12] FIG. 12 is a table showing the meanings of the symbols (decision variables) that make up a mixed integer programming problem. [Figure 13] FIG. 13 is a diagram showing the concept of flags. [Figure 14] FIG. 14 is a flow diagram showing main steps of an operation plan creating method executed by the operation plan creating device of the second embodiment. [Figure 15] FIG. 15 is a table showing examples of numerical values ​​used in the calculation examples. [Figure 16] FIG. 16 shows predicted values ​​of the amount of power generated by photovoltaic power generation used in the calculation example. [Figure 17] FIG. 17 is a graph showing the amount of power resulting from the calculation example. [Figure 18] FIG. 18 is a graph showing the production volume as a result of the calculation example. [Figure 19] FIG. 19 is a graph showing the start time of preparation for operation as a result of a calculation example. [Figure 20] FIG. 20 is a diagram showing another example of a system to which an operation plan obtained by the operation plan creating device and the operation plan creating method is applied. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0031] First Embodiment Hereinafter, an operation plan creating device and an operation plan creating method according to a first embodiment will be described in detail with reference to the accompanying drawings. In the description of the drawings, the same elements are given the same reference numerals, and duplicated explanations will be omitted.

[0032] FIG. 1 is a diagram showing a microgrid 1 to which an operation plan creation device 10 of the first embodiment is applied. The microgrid 1 includes a photovoltaic power generation system 2, a process device 3, a connection unit 6, a transmitted power measurement unit 7, and a received power measurement unit 8. The microgrid 1 is connected to an external power grid 9. The microgrid 1 can transmit power to the power grid 9. The microgrid 1 can also receive power from the power grid 9.

[0033] The photovoltaic power generation (PV) system 2 generates power based on renewable energy. The photovoltaic power generation system 2 is composed of a solar panel and a PV-PCS (power conditioner). The PV-PCS converts direct current to alternating current. Note that the power generation system using renewable energy is not limited to the photovoltaic power generation system 2. The power generation system using renewable energy may be, for example, a wind power generation system, a geothermal power generation system, a biomass power generation system, or a waste-to-energy generation system. The amount of power generated by a photovoltaic power generation system fluctuates because it is affected by weather conditions (sun radiation, temperature, snowfall). The amount of power generated by a wind power generation system fluctuates due to the influence of wind speed. In biomass power generation systems and waste-to-energy generation systems, the properties of the biomass and waste (waste, sludge, etc.) that are the raw materials are generally not stable. Furthermore, the output of biomass power generation systems and waste-to-energy generation systems is not stable due to temporary inclusion of materials that are not suitable for incineration.

[0034] The process equipment 3 is an equipment that consumes power and takes time to start producing a product. The process equipment 3 is, for example, a methanation equipment. The product is, for example, a gas such as methane. When the product is a gas, the process equipment 3 flows the produced gas into a city gas pipeline. When the product is a gas, the process equipment 3 may compress or liquefy the produced gas, and then the compressed or liquefied gas may be filled into a container, and the container may be stored or transported. In either case, the produced product leaves the microgrid 1.

[0035] The process equipment 3 can be switched from a non-manufacturable state in which a product cannot be manufactured even if power is input to a manufacturable state in which a product can be manufactured when power is input, by making the process equipment 3 ready for operation. The process equipment 3 is a power load device.

[0036] The connection unit 6 distributes power to each unit. The power distributed by the connection unit 6 may include power received from an external power system 9. The connection unit 6 is, for example, a distribution board. The received power measuring unit 8 measures the received power received from the external system (power system 9). The transmitted power measuring unit 7 measures the transmitted power sent to the external system (power system 9).

[0037] In addition, if the process equipment 3 cannot consume the power generated by renewable energy, the surplus power is ultimately transmitted to the power grid 9. Since the unit price of power transmission is generally lower than the unit price of power reception, there is a need to consume (produce) the surplus power in the process equipment 3 rather than transmitting it. There are cases where the surplus power cannot be transmitted to the power grid 9 due to the available capacity of the power grid 9. When the surplus power cannot be transmitted to the power grid 9, the output of the solar power generation system 2 is suppressed. This also leads to an opportunity loss for power generation, which is not preferable. In the first embodiment, solar power generation power is consumed within the microgrid 1 as much as possible.

[0038] Fig. 2 is a functional diagram of the operation plan creation device 10. However, Fig. 2 illustrates only the functions (operation plan creation function) intended by the operation plan creation device 10 of the first embodiment. Fig. 2 does not illustrate other functions, such as a state monitoring function of the process equipment 3, an operation command function, a trend data storage function, and a demand monitoring function. Communication between the operation plan creation device 10 and each device may be wired communication such as analog signals or Ethernet (registered trademark), or may be wireless communication. In addition, the communication protocol may be modbus / TCP or ECHONET Lite (registered trademark).

[0039] In the operation plan creation device 10, parameters related to the creation of an operation plan are set and changed in the operation unit 105. Specifically, a user sets parameters related to the creation of an operation plan using the operation unit 105, such as a screen and a keyboard or a mouse of the computer 100 (see FIG. 3). The set parameters are held in a setting database (DB).

[0040] The hardware configuration of the operation plan creation device 10 will be described with reference to Fig. 3. Fig. 3 is a diagram showing an example of the hardware configuration of the operation plan creation device 10. The computer 100 has a processor 101 which is a CPU (Central Processing Unit), a main memory unit 102, an auxiliary memory unit 103, a communication unit 104, an operation unit 105, and an output unit 106. The operation plan creation device 10 is configured by one or more computers 100 which are configured by these hardware units and software such as programs.

[0041] When the operation plan creation device 10 is configured by a plurality of computers 100, these computers 100 may be connected locally or via a communication network such as the Internet or an intranet. By this connection, one operation plan creation device 10 is logically constructed.

[0042] The processor 101 executes an operating system, application programs, and the like. The main memory unit 102 is composed of a ROM (Read Only Memory) and a RAM (Random Access Memory). The auxiliary memory unit 103 is a storage medium composed of a hard disk, a flash memory, and the like. The auxiliary memory unit 103 generally stores a larger amount of data than the main memory unit 102. At least a part of each unit constituting the operation plan creation device 10 is realized by the auxiliary memory unit 103. For example, the process device setting DB 14 shown in FIG. 2 may be realized by the auxiliary memory unit 103. The communication unit 104 is composed of a network card or a wireless communication module. At least a part of each unit constituting the operation plan creation device 10 may be realized by the communication unit 104. The operation unit 105 is composed of a keyboard, a mouse, a touch panel, a microphone for voice input, and the like. The output unit 106 is composed of a display, a printer, and the like. For example, the operation plan creation device 10 may display the operation plan, etc. on a display, etc.

[0043] The auxiliary storage unit 103 stores in advance a program and data necessary for processing. The program causes the computer 100 to execute each functional element of the operation plan creation device 10. For example, the program is read by the processor 101 or the main storage unit 102, and causes at least one of the processor 101, the main storage unit 102, the auxiliary storage unit 103, the communication unit 104, the operation unit 105, and the output unit 106 to operate. For example, the program reads and writes data in the main storage unit 102 and the auxiliary storage unit 103.

[0044] 3 executes a method for creating an operation plan for the process equipment 3. The operation plan creation program 110 may be provided in a state recorded on a tangible recording medium such as a CD-ROM, a DVD-ROM, or a semiconductor memory. The operation plan creation program 110 may be provided as a data signal via a communication network.

[0045] <Operation plan creation device> 2 again, a specific functional configuration of the operation plan creation device 10 will be described. The operation plan creation device 10 has a communication unit 104, a prediction unit 11, and a simulation calculation unit 13. Furthermore, the operation plan creation device 10 has a process device setting DB 14. The reference numeral "101" in FIG. 2 typically indicates that the prediction unit 11 and the simulation calculation unit 13 are realized by executing a program in the processor 101.

[0046] The operation plan created by the operation plan creation device 10 includes at least the start time of the operation preparation time. Furthermore, the operation plan may include values ​​obtained by calculations up to the determination of the start time of the operation preparation time. For example, the operation plan may include the total production amount P, the element production amount in each frame, the power consumption p m may include:

[0047] The operation plan creation device 10 is connected to an external weather forecast service 201 via the Internet or a dedicated line. These connections are realized by a communication unit 104. The weather forecast service 201 periodically calculates weather data for about one to 30 days in the future in an area including the latitude and longitude of the microgrid 1, using weather simulation by a supercomputer and numerical correction technology by artificial intelligence, based on meteorological satellite data and observation data from various locations. The weather data includes, for example, temperature, humidity, wind speed, wind direction, precipitation, snowfall, snow depth, total solar radiation, cloud cover, etc. The operation plan creation device 10 periodically acquires weather forecast data from the weather forecast service by a communication protocol such as FTP (File Transfer Protocol) or HTTP (Hypertext Transfer Protocol). The acquisition timing varies, such as once a day, four times a day, or 48 times a day (every 30 minutes).

[0048] <Communications Department> The communication unit 104 acquires weather forecast data from a weather forecast service 201 via the Internet or a dedicated line.

[0049] <Prediction Section 11> The prediction unit 11 includes a power generation prediction unit 111 and a renewable energy surplus power calculation unit 112. The power generation prediction unit 111 predicts the amount of power generated (PV power generation amount) of the solar power generation system 2 based on the weather forecast data. Next, the renewable energy surplus power calculation unit 112 calculates and outputs renewable energy surplus power based on the predicted value of the PV power generation amount. Hereinafter, the renewable energy surplus power will be simply referred to as surplus power p s It is called.

[0050] <Power Generation Forecasting Division> The power generation prediction unit 111 uses the acquired weather forecast data to output a predicted value of the PV power generation amount in the planned section. The power generation prediction unit 111 calculates a predicted value of the power generation amount by using, for example, the amount of solar radiation and the temperature in the weather forecast data.

[0051] The operation of the power generation prediction unit 111 is not limited to a prediction operation using weather forecast data. For example, the power generation prediction unit 111 may predict future PV power generation from the actual value of a pyranometer in the microgrid 1 and the actual value of PV power generation by using machine learning or a statistical method. The power generation prediction unit 111 may predict the PV power generation from the prediction result of cloud movement from a celestial sphere camera in the microgrid 1. The power generation prediction unit 111 may directly receive a predicted value of the PV power generation from an external system via the Internet or the like. The predicted value of the PV power generation output by the power generation prediction unit 111 includes at least a predicted value in a plan section of an operation plan described later.

[0052] <Renewable Energy Surplus Calculation Division> The renewable energy surplus power calculation unit 112 calculates the surplus power p from the predicted value of the PV power generation amount obtained from the power generation prediction unit 111. s In the first embodiment, since there is no power load other than the process device 3, the surplus power p s is equal to the predicted value of the PV power generation. Taking into account the power consumed by the equipment in the microgrid 1, such as control equipment, communication equipment, lighting equipment, surveillance cameras, and air conditioning equipment, the surplus power p sA fixed value may be subtracted from the predicted value of the PV power generation. In this case, the surplus power p s When becomes negative, the surplus power p s is set to 0. The above fixed value is the average value of the total power consumed by the equipment in the microgrid 1.

[0053] The renewable energy surplus power calculation unit 112 calculates the predicted value of the power consumer separately and subtracts the power demand predicted value from the PV power generation predicted value to obtain the surplus power p s may be obtained.

[0054] In addition, if the scale of the power consumers is so large that it cannot be ignored and changes over time, it is necessary to predict the power demand in some way, similar to the power generated by photovoltaic power generation. However, in the first embodiment, the power demand of the power consumers is assumed to be so low that it can be ignored. In other words, the surplus power p s is equal to the predicted PV power generation.

[0055] Figure 4 shows the surplus power p s 4 is a conceptual diagram of the above. As shown in FIG. 4, the planned section is defined by a starting time t[0], an end time t[N], and a time t[i] (i=1, 2...N-1) that divides the planned section into N equal parts. The length of the time interval (h) is, for example, 30 minutes or 1 hour. When the planned section is one day, if the length of the time interval (h) is 30 minutes, N=48, and if the length of the time interval (h) is 1 hour, N=24. The planned section may be one to three days, or may be a longer period, such as one week.

[0056] In the following, the period from time t[i] to t[i+1] is referred to as frame [i]. The surplus power generated in frame [i] is referred to as surplus power p s [i] (i=0, 1, 2, ... N-1). The subscript s means surplus and p means power. In FIG. 4, surplus power p sWhere [i] is shown as negative, the bar graph is lowered to emphasize that it is 0. s The unit of [i] is the amount of electricity [kWh]. Surplus electricity p s The unit of [i] may be the average power [kW] in frame [i].

[0057] <Process equipment setting DB> The process equipment setting DB 14 includes, as a parameter, a required operation preparation time, which is the time required for preparation for operation. The required operation preparation time is the time required for the process equipment 3 to switch from a non-production state to a production possible state after preparation for operation is performed. The required operation preparation time is defined by H frames, with one frame being the unit (see FIG. 6). The planned section includes the required operation preparation time and the operation possible time.

[0058] <Simulation calculation section> The simulation calculation unit 13 will be described below. The simulation calculation unit 13 (processing unit) calculates various parameters of the process equipment setting DB 14 and the surplus power p s Based on [i], an operation plan is created by repeatedly performing simulations of preparation for operation and production of the process equipment 3 while changing the conditions. The simulation operation unit 13 has a total production amount calculation unit 131 (total evaluation amount calculation unit), a total production amount determination unit 132 (total evaluation amount determination unit), a start time determination unit 133, and an operation plan output unit 134.

[0059] <Total Production Volume Calculation Section> The total production amount calculation unit 131 calculates the total production amount P. The total production amount P is an example of a total evaluation value based on the amount of power consumption consumed by the process equipment 3 for the production of the product. Another example of the total evaluation value is the amount of power consumption p m The total production amount P is the amount of the product that the process equipment 3 can produce up to the end point t[N], assuming that the operation preparation is completed at the time t[i]. The total production amount P is the amount of the product that the process equipment 3 can produce up to the end point t[N], assuming that the operation preparation is completed at the time t[i]. sIt is calculated based on [i] and the time required to prepare for operation.

[0060] In other words, the total production amount calculation unit 131 calculates the predicted value of the surplus power p s The total production amount P, which is the amount of the product produced by the process equipment 3, is calculated for each of a plurality of start time candidates based on [i] and the operation preparation time required. The above operation of the total production amount calculation unit 131 will be described in more detail below.

[0061] FIG. 5 shows the power consumption p m The total production amount calculation unit 131 calculates the surplus power p s The power consumption p of the process device 3 determined based on [i] m and the linear equation (P=a×p m +b) to calculate the production volume P[i]. m max , minimum power consumption p m min , linear equation (P=a×p m +b) are parameters included in the process equipment setting DB 14.

[0062] The power consumption of the process device 3 is limited to the maximum power consumption p m max and the lower limit, minimum power consumption p m min The process device 3 has a maximum power consumption p m max and minimum power consumption p m min Power consumption during p m It is possible to operate at a maximum power consumption of p m max and minimum power consumption p m min The region between is called the operable region. s [i] is the minimum power consumption p m minIf the surplus power p s When [i] is below the operable region, the power consumption p m [i] is 0. And the production amount P[i] is 0.

[0063] For example, the surplus power p in frame [j] s Given [j], p s [j]≧p m max If so, the power consumption p of the process device 3 in frame [j] m [j] and production volume P[j] are as follows. Note that the relationship between variable j and variable i is defined as j=i+H. p m [j]=p m max . P[j]=a×p m max +b.

[0064] Surplus power p in frame [j] s Given [j], p s [j] <p m min If so, the power consumption p of the process device 3 in frame [j] m [j] and production volume P[j] are as follows. p m [j]=0. P[j]=0.

[0065] Surplus power p in frame [j] s Given [j], the surplus power p s If [j] is other than the above, the power consumption p of the process device 3 in frame [j] m [j] and production volume P[j] are as follows. p m [j]=p s [j]. P[j]=a×p s [j]+b.

[0066] Here, the processing of the total production amount calculation unit 131 will be specifically described with reference to FIG. 6. FIG. 6 is a conceptual diagram of operation preparation and production simulation. Here, the symbol H shown in FIG. 6 is the number of steps of the operation preparation time required for the process equipment 3. For example, if the time interval (h) is 30 minutes and the operation preparation time required is 90 minutes, H=3. The time interval required for the operation preparation time is assumed to be three frames (H=3). FIG. 6 illustrates a method of calculating the total production amount when it is assumed that operation preparation is started at each of the possible start times t[0], t[1], and t[2] as a representative example.

[0067] If the total production volume calculation unit 131 assumes that operation preparation starts at the possible start time t[0], operation preparation is performed from frame [0] to frame [2]. The possible operation time is from frame [3] to frame [N-1]. The total production volume calculation unit 131 calculates the element production volume of the deliverable for each frame from frame [3] to frame [N-1], and obtains the total production volume P, which is the sum of the calculated element production volumes.

[0068] If the total production volume calculation unit 131 assumes that operation preparation starts at the possible start time t[1], operation preparation is performed from frame [1] to frame [3], and the possible operation time is from frame [4] to frame [N-1]. The total production volume calculation unit 131 calculates the element production volume of the deliverable for each frame from frame [4] to frame [N-1], and obtains the total production volume P, which is the sum of the calculated element production volumes.

[0069] If the total production volume calculation unit 131 assumes that operation preparation starts at the possible start time t[2], operation preparation is performed from frame [2] to frame [4], and the possible operation time is from frame [5] to frame [N-1]. The total production volume calculation unit 131 calculates the element production volume of the deliverable for each frame from frame [5] to frame [N-1], and obtains the total production volume P, which is the sum of the calculated element production volumes.

[0070] The total production volume calculation unit 131 performs a similar process by calculating the available operation time assuming that operation preparation starts at each of the possible start times t[3], t[4], ..., t[N-3], calculates the production volume of the deliverables for each frame included in the available operation time, and calculates the total production volume P, which is the sum of the calculated values.

[0071] The total production amount calculation unit 131 calculates the maximum total production amount P from the multiple total production amounts P obtained for the multiple possible start times t[i]. max Then, the total production amount calculation unit 131 extracts at least one maximum total production amount P max The possible start time t corresponding to is selected as a first start time candidate, which is a candidate for the time when operation preparation should start.

[0072] <Total production quantity determination department> Maximum total production quantity P max is an estimate of the maximum value of the total production volume P when the process equipment 3 is operated. max If the total production volume P is smaller than the target production volume, it is appropriate to determine that it is better not to prepare for startup. Therefore, the total production volume P is compared with the threshold value stored in the process equipment setting DB 14. max If the threshold value is exceeded, it is determined that it is appropriate to start preparation for operation. max If is not equal to or greater than the threshold, it is determined that no preparation for operation is to be performed.

[0073] That is, the total production amount determination unit 132 determines whether it is appropriate to start preparation for operation at the first start time candidate. max By comparing with the threshold value, the maximum total production amount P max is equal to or greater than a threshold value, at least one of which is selected as a second start time candidate.

[0074] <Start time determination section> Surplus power p sDepending on the occurrence pattern, the maximum total production volume P max There may be multiple cases in which it is determined that the start time candidate is the latest. In that case, the case with the latest operation time candidate is adopted as the operation plan. In other words, the case with the shortest operation time is adopted as the operation plan. This is because the selected case is considered to be the case in which the time from completion of operation preparation to starting production is the shortest. The time from completion of operation preparation to starting production may be interpreted as the time for which the process equipment is kept on standby.

[0075] In other words, when multiple second start time candidates are selected by the total production volume determination unit 132, the start time determination unit 133 adopts the latest of the multiple second start time candidates as the start time at which operation preparation should begin.

[0076] <Operation plan output section> The operation plan output unit 134 outputs information on the operation start time t[i] at which preparation for operation is performed, the amount of power consumed by the process equipment 3 p m An operation plan is created that includes at least one of the following: the total production volume P of the product to be manufactured; and the element production volume of the product to be manufactured in each frame.

[0077] The process of creating an operation plan by the operation plan creation device 10 will be described. FIG. 7 is a flow diagram showing main steps of creating an operation plan using the operation plan creation device 10. The flow shown in FIG. 7 is periodically executed by the operation plan creation device 10 at a certain time of day (e.g., 3:00 a.m.). The flow shown in FIG. 7 may be periodically and automatically executed every hour, or may be executed manually. Manual execution means, for example, that a user of the operation plan creation device 10 operates the operation unit 105. The flow shown in FIG. 7 may be executed at the timing when weather forecast data arrives. It is assumed that the start time of the planned section is the current time, and the end time of the planned section is 24 hours later.

[0078] First, the surplus power p sThis operation is executed by the prediction unit 11. The operation of the prediction unit 11 has already been described, so the description will be omitted in this paragraph.

[0079] Next, it is determined whether or not preparation for operation has already started for the process equipment 3 (S1). This operation may be performed by obtaining operation information of the process equipment 3 from the process equipment 3, for example.

[0080] In addition, if the time t[0] of the start point of the planned section is later in time than the time when the operation plan is created, the state of the process equipment 3 at that time t[0] is generally unknown. The state of the process equipment 3 indicates, for example, whether or not the operation preparation is complete, and whether or not the process equipment 3 is operating. Therefore, if the time t[0] of the start point of the planned section is later in time than the time when the operation plan is created, and there is another operation plan for the process equipment 3, it is necessary to refer to the other operation plan.

[0081] If operation preparation has already started (S1: YES), the sum of the production amounts during the period from time t[0] to time t[N] (total production amount) is calculated (S8). This operation is executed by the total production amount calculation unit 131. Then, the element production amount of each frame from time t[0] to time t[N] and the total production amount P, which is the sum of the element production amounts, are output as an operation plan (S9). This operation is executed by the operation plan output unit 134.

[0082] If operation preparation has not been performed (S1: NO), the total production amount P is calculated (S2). This operation is executed by the total production amount calculation unit 131. The total production amount calculation unit 131 calculates the total production amount P when operation preparation is started at time t[i] to the total production amount P when operation preparation is started at time t[NH].

[0083] Next, the one with the largest total production volume P is called the maximum total production volume P max This operation may also be executed by the total production amount calculation unit 131 (S3).

[0084] Next, the maximum total production volume P max This operation is executed by the total production amount determination unit 132. In this operation, at least one maximum total production amount P max As a result, it is determined whether the maximum total production volume P max There may be one or more products that are equal to or greater than the threshold (S4: YES). On the other hand, the maximum total production volume P max It is also possible that there is no value that is equal to or greater than the threshold (S4: NO).

[0085] Total production volume P max If there is a first start time candidate whose operation preparation is equal to or greater than the threshold (S4: YES), the start time determination unit 133 determines that it is appropriate to start operation preparation from that first start time candidate. The first start time candidate is selected as a second start time candidate. Next, among the second start time candidates selected, the time at which operation preparation starts latest is adopted (S5). This operation is performed by the start time determination unit 133. Then, the total production amount P and the element production amount of each frame at the adopted operation start time are output as an operation plan. This operation is performed by the operation plan output unit 134.

[0086] Maximum total production quantity P max If there is no operation preparation that is equal to or greater than the threshold (S4: NO), the operation plan output unit 134 outputs as an operation plan (S7) that no operation preparation is being performed, that the total production amount P of the deliverables is 0, and that the element production amount of the deliverables for each frame is 0.

[0087] After the operation plan is created, the operation plan creation device 10 may instruct or advise the worker on the operation plan by displaying the monitor, turning on a lamp, sounding an alarm, notifying an e-mail, or the like. The operation plan creation device 10 may automatically operate the process equipment 3 based on the operation plan at the relevant time. In this way, when the operation plan creation device 10 has the function of creating an operation plan and executing control according to the plan, it can be said that the operation plan creation device 10 is an energy management system for the microgrid 1. The operation plan creation device 10 may only operate the process equipment 3. In addition, the use of the operation plan is not limited to operating these devices. The operation plan may be used for bidding on the electricity market or applying for self-consignment of electricity. The operation plan may be used for commands and response judgments of demand response to avoid a tight electricity situation. The operation plan may transmit a schedule of production volume to another upper system (not shown) that manages the deliverables.

[0088] <Action and effect> Hereinafter, problems associated with the conventional technology will be pointed out, and then the effects of the operation plan creation device 10 will be described.

[0089] When creating an operation plan for process equipment such as a methanation unit that is difficult to start operating instantly, two problems arise due to the constraint that it is difficult to start operation instantly. The first problem is whether or not to start preparations for operation of the process equipment. The second problem is when to start preparations for operation if preparations for operation are to be made. For the first problem, it is important to predict the production volume that can be produced if the equipment is operated. If the expected production volume is small, it can be determined that it is better not to start preparations for operation because the energy required for heating will be wasted. For the second problem, the surplus power p s New technology is needed that takes into consideration the time it takes for the device to be prepared and the time it takes for the device to be generated.

[0090] Some of the conventional techniques exemplified below have difficulty in providing solutions to such problems.

[0091] For example, Japanese Patent Application Laid-Open No. 2020-54085 (Patent Document 1) assumes that the hydrogen production device can start producing hydrogen at any time when the capacity of the storage battery reaches its upper limit. Therefore, it is difficult to directly apply the contents of Patent Document 1 to the methanation device. It is also possible to keep the process device always at a desired temperature so that it is ready to produce hydrogen at any time. However, this leads to unnecessary energy loss and is not preferable.

[0092] For example, International Publication No. 2020 / 121436 (Patent Document 2) operates the device during a preparation period before the demand response supply and demand adjustment period, which is possible because the supply and demand adjustment period is known in advance. The operation plan creation device 10 of the first embodiment is applied to production using surplus electricity from renewable energy. In other words, it is not possible to know in advance when surplus electricity will occur. Therefore, the preconditions in the technology of Patent Document 2 are different from the preconditions in the operation plan creation device 10 of the first embodiment.

[0093] For example, JP 2022-020978 A (Patent Document 3) has the same problem as JP 2020-54085 A (Patent Document 1).

[0094] For example, JP 2021-164178 A (Patent Document 4) increases and decreases the power consumption of a load device using a predicted value of the power generated by renewable energy and the remaining capacity of a storage battery. However, as described in paragraph 0130 of Patent Document 4, the assumed load is lighting and air conditioners, both of which are devices that can consume power immediately. The technology described in Patent Document 4 does not assume the control of devices that require preparation time before operating, such as the operation plan creation device 10 of the first embodiment.

[0095] For example, Japanese Patent No. 6189448 (Patent Document 5) calculates the charge / discharge power amount of a storage battery, the power amount consumed by a hydrogen production device, and the power amount generated by a fuel cell based on the predicted value of the amount of power generated by renewable energy and the predicted value of the power consumer. However, the specification of Patent Document 5 does not mention the cases where preparation time is required for the hydrogen production device. Therefore, there is room for improvement.

[0096] For example, if JP 2022-25398 A (Patent Document 6) is applied to the operation plan creation device 10 of the first embodiment as it is, it is not possible to know the expected production volume of the process equipment. It is also not possible to know the time when preparation for operation should be started.

[0097] For example, Patent No. 7008297 (Patent Document 7) determines the preheating and precooling times of a hydrogen storage facility. However, as described in the specification of Patent Document 7, after calculating the operation time of hydrogen production, the preheating and precooling times are calculated by counting backwards from the operation time of the production. When calculations are performed in this order, it may be difficult to cover the power required for preheating and precooling with surplus power. In addition, depending on the relationship between the current time, operation time, and preheating and precooling times, an unrealizable plan may be generated. For example, the operation time may be immediately after the current time, and preheating and precooling may not be completed in time.

[0098] The operation plan creation device 10 and the operation plan creation method of the first embodiment solve the problems that the conventional techniques have by using the following configuration.

[0099] The first embodiment is an operation plan creation device 10 that creates an operation plan for an apparatus that can be switched from a non-manufacturable state in which no product can be obtained even if power is input to a manufacturable state in which a product can be obtained when power is input by performing operation preparation. The operation plan creation device 10 includes a prediction unit 11 that obtains a predicted value of the amount of power that can be supplied to the process equipment 3, including power derived from renewable energy, and a simulation calculation unit 13 that creates an operation plan based on the predicted value and an operation preparation required time that indicates the time required for operation preparation.

[0100] The operation plan creation device 10 creates an operation plan based on a predicted value of the amount of power that can be supplied to the process equipment 3 and a required operation preparation time that indicates the time required for operation preparation. Therefore, the resulting operation plan takes into account the required operation preparation time, and it is possible to prevent the creation of an operation plan that cannot be executed.

[0101] In other words, the operation plan creation device 10 of the first embodiment calculates the expected production volume that can be produced when the process equipment 3, such as a methanation device, that requires preparation time before starting operation is operated, based on the predicted value of the power generation of renewable energy and the time required for operation preparation. When the expected production volume exceeds a set value, the operation plan creation device 10 determines whether or not to start preparation for operation of the process equipment 3.

[0102] The operation plan creation device 10 of the first embodiment is s Taking into consideration the trade-off between the energy required for the operation and the energy required for preparation for operation, an economical and rational operation plan for the process equipment 3 can be created. The operation plan creation device 10 creates a plan taking into consideration the time required for preparation for operation of the process equipment 3. As a result, an operation plan that can be executed can be created.

[0103] The operation plan includes a plurality of possible start times that can be selected as times when preparation for operation can be started. The simulation calculation unit 13 has a total production amount calculation unit 131. The total production amount calculation unit 131 calculates the power consumption p consumed by the process equipment 3 for the production of the product based on the predicted value and the time required for preparation for operation under a condition that preparation for operation is assumed to be started at a candidate start time selected from the plurality of possible start times. m The total production amount P based on the above is calculated for each of the multiple start time candidates, and the total production amount P having the maximum value from the multiple total production amounts P obtained for the multiple start time candidates is calculated as the maximum total production amount P max At least one maximum total production volume P maxThe start time candidate corresponding to the total production volume P is selected as a first candidate, which is a candidate for the time when operation preparation should start. According to this configuration, the time to start operation preparation can be determined based on the total production volume P.

[0104] The simulation calculation unit 13 further includes a total production amount determination unit 132. The total production amount determination unit 132 compares at least one maximum total production amount with a threshold value, and selects at least one of the at least one first candidates, whose maximum total production amount is equal to or greater than the threshold value, as a second candidate. With this configuration, the time to start preparation for operation can also be determined based on the total production amount P.

[0105] The simulation calculation unit 13 further includes a start time determination unit 133. When a plurality of second candidates are selected by the total production volume determination unit 132, the start time determination unit 133 adopts the latest time among the second candidates as the start time for starting operation preparation. With this configuration as well, the time for starting operation preparation can be determined based on the total production volume.

[0106] The simulation calculation unit 13 obtains a predicted value by predicting the power output from the solar power generation system 2. According to this configuration, an operation plan for devices that operate using power supplied from the solar power generation system 2 can be obtained.

[0107] The total evaluation amount is the power consumption p m This is the total production volume P of the deliverables produced by the process equipment 3, which is calculated based on the above. According to this configuration, evaluation can be performed based on the total production volume P of the deliverables.

[0108] The total evaluation amount is the power consumption p m In this configuration, the power consumption p required to generate the product may be calculated as m In addition, when calculating the total production volume or the total power consumption, values ​​multiplied by an appropriate coefficient may be added together. An example of the coefficient is the forgetting coefficient mentioned above.

[0109] <Second embodiment> An operation plan creation device 10A of the second embodiment shown in Fig. 8 will be described in detail. Fig. 8 is a diagram showing a microgrid 1A to which the operation plan creation device 10A of the second embodiment is applied. The microgrid 1A has an operation plan creation device 10A instead of the operation plan creation device 10. Furthermore, the microgrid 1A further has a storage battery system 5 (energy storage device).

[0110] The storage battery system 5 is a secondary battery. Examples of the secondary battery include a general type secondary battery, a liquid circulation type secondary battery, a mechanical charge type storage battery, a high temperature operation type storage battery, and an electron trap type storage battery.

[0111] For example, general-type secondary batteries include lead-acid batteries, lithium-ion secondary batteries, all-solid-state batteries, nickel-metal hydride batteries, nickel-cadmium batteries, nickel-iron batteries (Edison batteries), nickel-zinc batteries, silver oxide-zinc batteries, and cobalt-titanium lithium secondary batteries. Liquid circulation type secondary batteries include redox flow batteries, zinc-chlorine batteries, and zinc-bromine batteries. Mechanical charge type secondary batteries include aluminum-air batteries, air-zinc batteries, and air-iron batteries. High-temperature operation type secondary batteries include sodium-sulfur batteries (NAS batteries) and lithium-iron sulfide batteries. Electron trap type batteries include semiconductor secondary batteries.

[0112] In addition, a storage battery (secondary battery) is a general term for equipment that can charge and / or discharge power. The storage battery PCS that converts the direct current of the storage battery system 5 to alternating current and a device that monitors the remaining battery charge are also included in the storage battery system 5. The storage battery can also be replaced with an energy storage device that has a similar function, such as a capacitor or flywheel, a compressed air energy storage (CAES) facility, a pumped-storage power generation facility, or a heat storage power generation facility that temporarily stores electricity as heat and reconverts the heat into electricity when needed.

[0113] When creating an operation plan for the process equipment 3, the operation plan creation device 10A of the second embodiment plans the charging power and discharging power of the storage battery system 5 at the same time as the operation plan for the process equipment 3. Specifically, the operation plan creation device 10A of the second embodiment creates an operation plan by using mathematical programming. The hardware configuration of the operation plan creation device 10A is the same as the hardware configuration of the operation plan creation device 10. Therefore, a detailed description of the hardware configuration of the operation plan creation device 10A will be omitted.

[0114] Fig. 9 is a diagram showing a functional configuration of an operation plan creation device 10A. However, just as Fig. 2 shows only the functions intended by the operation plan creation device 10 of the first embodiment, only the functions (operation plan creation functions) intended by the operation plan creation device 10A of the second embodiment are shown.

[0115] <Operation plan creation device> A specific functional configuration of the operation plan creation device 10A will be described. The operation plan creation device 10A has a communication unit 104, a power generation prediction unit 111, a processing unit 15, and an operation unit 105. Furthermore, the operation plan creation device 10A has a process device setting DB 14, a storage battery setting DB 16, an external system setting DB 17, and a weight DB 18. The storage battery system 5 has a storage battery control unit 81. The storage battery control unit 81 has information on the remaining amount of storage of the storage battery in the planned section. The reference symbol "101" in FIG. 9 typically indicates that the power generation prediction unit 111 and the processing unit 15 are realized by executing a program in the processor 101. The reference symbol "103" in FIG. 9 typically indicates that the process device setting DB 14, the storage battery setting DB 16, the external system setting DB 17, and the weight DB 18 are realized in the auxiliary storage unit 103.

[0116] The processing unit 15 creates an operation plan based on the predicted value of the PV power generation amount predicted by the power generation prediction unit 111, the operation preparation required time, and information on the remaining amount of stored power acquired from the storage battery control unit 81. The processing unit 15 has an objective function / constraint condition generation unit 151 (generation unit), an optimization unit 152 (calculation unit), an adoption / rejection determination unit 153, and an operation plan output unit 154.

[0117] The power generation prediction unit 111 is the same as in the first embodiment, and therefore a detailed description thereof will be omitted.

[0118] The objective function and constraint condition generation unit 151 collects parameters required for the mathematical programming as necessary from the process equipment setting DB 14, the storage battery setting DB 16, the external system setting DB 17, and the weight DB 18. The objective function and constraint condition generation unit 151 may obtain necessary information from the storage battery control unit 81 as necessary. For example, the objective function and constraint condition generation unit 151 obtains the remaining battery capacity at the plan starting time (current time) from the storage battery control unit 81.

[0119] Then, the objective function and constraint condition generating unit 151 formulates the objective function as a mixed integer programming problem (PG). The definitions of symbols used in the minimization problem are shown in the tables of Fig. 10, 11, and 12. The tables of Fig. 11 and 12 also indicate from which component the parameters are obtained.

[0120] The mixed integer programming problem (PG) is shown below.

[0121]

number

[0122] The meanings of formulas (1) to (15) are as follows.

[0123] Equation (1) means maximizing the production volume of the end product. The first term is the production volume taking into account the forgetting factor. The first term means that near-future production volume is prioritized over distant-future production volume. If ρ=1, the value of the first term is the same as the total production volume P. The second term is a term for shortening the available operation time. The second term means that if the production volume is the same, it is better to postpone the start time of preparation for operation as much as possible. The third term means that the fluctuation in power consumption of the process equipment 3 is minimized.

[0124] The forgetting factor is used because it is desired to manufacture the product in the process equipment 3 as reliably as possible. In the second embodiment, a predicted value of the photovoltaic power generation system 2 is used. The further into the future the predicted value is, the higher the uncertainty is. For this reason, the forgetting factor is introduced in order to give a higher evaluation value to the production volume in the near future, which is more likely to be manufactured as planned, than to the production volume in the distant future. Note that, although the objective function in the second embodiment is the maximization of the production volume, this is not limiting. The objective function may be the minimization of the manufacturing cost or the maximization of the balance of income. In this case, additional information on the unit price of electricity sold, the unit price of electricity purchased, and the unit price of the product of the process equipment is required.

[0125] Equation (2) means that the demand for electricity and the supply of electricity are equal at any point during the operating period.

[0126] Equation (3) means that the amount of received power is equal to or less than the maximum amount of power.

[0127] Equation (4) means that the amount of transmitted power is less than or equal to the maximum amount of power.

[0128] Equation (5) means that the charge / discharge power amount of the storage battery is within a predetermined range.

[0129] Equation (6) means that the remaining charge of the battery lies between a predetermined upper limit and a predetermined lower limit.

[0130] Equation (7) means that the power consumption of the process equipment 3 is within a predetermined range when the process equipment 3 is in operation, and the power consumption is zero when the process equipment 3 is not in operation.

[0131] Equation (8) means that the storage battery is not charged when purchasing electricity. In other words, it means that the storage battery is charged with the power of the photovoltaic power generation system 2.

[0132] The formula (9) means that the process device 3 does not produce electricity when it is purchasing electricity. In other words, it means that electricity is produced using the power of the photovoltaic power generation system 2.

[0133] Equation (10) means that the process unit 3 is not operable during the relevant period.

[0134] Equation (11) means that the process equipment 3 becomes operable H steps after the start of preparation for operation.

[0135] Equation (12) means that the process unit 3 produces the product only when it is operable.

[0136] Equation (13) represents a constraint on the fluctuation of the power consumption of the process device 3 .

[0137] Equation (14) represents the relationship between the power consumption of the process equipment 3 and the production amount of the product.

[0138] Equation (15) represents the relationship between the charge / discharge power amount of the storage battery and the remaining storage capacity.

[0139] FIG. 13 shows a schematic diagram of the flags u[k], v[k], and z[k] shown in the table of FIG. 12. In FIG. 12, "k" indicates discrete time. For example, when H=3, if the startup preparation flag u[k] becomes 1 at k=3, the process equipment 3 is ready to operate from 3+H=6, and therefore production is possible. Even when the process equipment 3 is ready to operate (preparation completion flag v[k]=1), there may be a time when production is not performed (in-production flag z[k]=0). In FIG. 13, production is not performed at times k=8 and 9 (in-production flag z[k]=0). In the explanation of the second embodiment, for convenience, stoppage is not considered. However, it is easy to expand the above problem to include stoppage in the form of a stop preparation start flag.

[0140] The mixed integer programming problem (PG) created by the objective function and constraint condition generation unit 151 is solved by the optimization unit 152, and the decision variables (see the table in FIG. 12) are determined. Since the above mixed integer programming problem (PG) is formulated, it can be easily solved, for example, by using a commercially available optimization solver. Then, the dependent variable P[k] can be calculated from each decision variable. The total production volume P can be estimated from the sum of P[k]. The estimation of the total production volume P may be performed by the optimization unit 152.

[0141] Incidentally, the operation plan output by the optimization unit 152 does not include a judgment from the viewpoint of whether the total production amount P is more or less than the threshold value. On the other hand, as determined in the first embodiment, if the total production amount P is less than the threshold value, preparation for operation should not be started. In other words, the operation plan output by the optimization unit 152 may have a total production amount P greater than the threshold value or may have a total production amount P less than the threshold value.

[0142] Therefore, by evaluating whether the total production amount P is more or less than the threshold value, it is determined whether the operation plan output by the optimization unit 152 can be adopted. This determination is made by the adoption / rejection determination unit 153.

[0143] The operation plan output unit 154 outputs the operation plan. The operation of the operation plan output unit 154 is the same as that of the operation plan output unit 134 in the first embodiment, and therefore a detailed description thereof will be omitted.

[0144] The determination of whether to start preparation for operation may be performed in the mixed integer programming problem (PG). In that case, a constraint condition of total production amount≦threshold value is added to the mixed integer programming problem (PG). In that case, if the calculation result in the optimization unit 152 is no solution, it is interpreted that preparation for operation is not started. However, the cause of no solution may be a problem other than the total production amount P. An example of the cause of no solution is a program bug. Therefore, it is more convenient in terms of operation to perform the determination of whether to start preparation for operation using the total production amount P by a process other than the optimization calculation process, as in the second embodiment.

[0145] The process of creating an operation plan by the operation plan creation device 10A will be described. Fig. 14 is a flow diagram showing main steps of creating an operation plan using the operation plan creation device 10A. The flow shown in Fig. 14 is executed at the same timing as the operation plan creation device 10 of the first embodiment.

[0146] In the following explanation, we will assume that operation preparation has not started at the plan start time (k = 0). More generally, this can be expanded to cases where operation preparation has been performed at any time. In that case, the operation preparation completion flag variable (see formula (16)) can be extended to negative times and the initial condition can be set. For example, if operation preparation has started at time -H, the condition shown in formula (17) is set. Then, if the start time of the sum of formula (11) is set to formula (18) instead of 0, formula (19) is obtained. Formula (19) indicates that operation preparation has been completed at the plan start time. In this case, formula (11) can be calculated from k = 0, so formula (10) is deleted.

number

[0147] First, the surplus power p s This operation is the same as that in the first embodiment, so a detailed description will be omitted.

[0148] Next, an objective function and constraint conditions are generated (S11). This operation is executed by the objective function / constraint condition generating unit 151.

[0149] Next, a mixed integer programming problem (PG) represented by the objective function and the constraint conditions is solved (S12). This operation is executed by the optimization unit 152. Furthermore, a total production volume P is obtained using the solution of the mixed integer programming problem (PG).

[0150] Next, it is determined whether or not the total production volume P is equal to or greater than a threshold value (S13). This operation is executed by the adoption / rejection determination unit 153.

[0151] If the total production amount P is equal to or greater than the threshold value (S13: YES), the operation plan output by the optimization unit 152 is output (S14). This operation is executed by the operation plan output unit 134.

[0152] If the total production amount P is not equal to or greater than the threshold (S13: NO), the operation plan output by the optimization unit 152 is not adopted, and an operation plan indicating that no operation preparation is performed and that the total production amount P of the deliverables is 0 is output (S15). This operation is also executed by the operation plan output unit 134.

[0153] <Action and effect> In the operation plan creation device 10A of the second embodiment, the processing unit 15 includes an objective function / constraint condition generation unit 151 that creates a mixed integer programming problem (PG) including a term indicating the production amount of the product in the process equipment 3 at a predetermined time and a term indicating whether the process equipment 3 can receive power and produce the product, an optimization unit 152 that obtains operation plan candidates by solving the mixed integer programming problem (PG), and an adoption / rejection determination unit 153 that adopts the operation plan candidate as an operation plan when the sum of the production amounts of the product obtained based on the operation plan is equal to or greater than a threshold. With this configuration, it is possible to create an operation plan that takes into account the operation preparation time by utilizing mathematical programming.

[0154] <Calculation example> An example of optimization calculation is shown below. The parameters used are shown in the table in Figure 15. Figure 16 shows the predicted value of the amount of power generated by solar power generation used in the calculation example. The operation plan has 36 steps at one-hour intervals from April 12, 2018. In other words, a plan for one and a half days is made. The time required for operation preparation is set to 3 hours.

[0155] The optimization results are shown in Figures 17, 18 and 19. Figure 17 shows the power balance and power storage amount of the microgrid over time, with positive values ​​in the stacked bar graph representing the movement on the power consumption side and negative values ​​representing the movement on the power generation side, corresponding to the left coordinate axis. As it is symmetrical from top to bottom, it can be seen that power generation and consumption are well balanced. Also, the line graph shows the movement of SoC [%], corresponding to the right coordinate axis. Referring to Figure 17, when the photovoltaic power generation system 2 starts up, the storage battery system 5 is charged well while the process device 3 consumes power, and the final surplus power p s It can be seen that the power consumption (equivalent to the power sold in the calculation example) is kept to a minimum. In Figure 17, power selling occurs only at 2 pm on April 12th. This is because the storage capacity of the battery system 5 has reached its limit (SoC 100%) and the power consumption of the process equipment 3 has also reached its maximum (500 kWh). It can be seen that even after sunset, production is continued in the process equipment 3 using the stored power in the battery system 5, maximizing the production volume.

[0156] Fig. 18 shows the change in production volume of process equipment 3. Fig. 19 shows the operation preparation start flag for process equipment 3. We can see that operation preparation started at 3:00 AM on April 12th, and production began at 6:00 AM on the same day. This satisfies the constraint on the time required for operation preparation (see symbol H in Fig. 15: 3 hours). It also does not appear that operation preparation started unnecessarily early.

[0157] <Modification> The operation plan creation device 10, 10A and the operation plan creation method according to the first and second embodiments have been described above. The operation plan creation device 10, 10A and the operation plan creation method according to the first and second embodiments may be implemented in various forms without being limited to the above examples.

[0158] In the first and second embodiments, the process equipment 3 is a methanation equipment, but the process equipment 3 may be an equipment different from the methanation equipment. The process equipment 3 may be, for example, a hydrogen production system that produces hydrogen by water electrolysis. In general, the higher the temperature, the lower the theoretical electrolysis voltage, and therefore the more efficient the water electrolysis. Some hydrogen production systems, such as steam water electrolysis that electrolyzes high-temperature steam, also require a certain time for preparation for operation. The process equipment 3 is not limited to hydrogen or methane, and may be a production equipment for olefins (ethylene, propylene) that are raw materials for resins and plastics. The process equipment 3 may be an electric boiler. The process equipment 3 may be an electric furnace that melts scrap iron, or an electrolytic / electrical refining equipment that produces crude iron from iron ore. The process equipment 3 may be other chemical process equipment, plastic processing equipment such as rolling, food processing equipment, distillation equipment, heat treatment furnaces such as surface heat treatment, etc.

[0159] The required preparation time for operation may be for performing various tasks depending on the type of process equipment 3. Process equipment that requires thermal energy often requires preparation time for heating, pressurizing, etc. If a heating pipe is required to prevent water hammer from occurring in the steam piping, etc., the time for that may also be included in the required preparation time for operation. If purging work is required to replace toxic gas in a tank with nitrogen or air before starting operation, the time for that may also be included in the required preparation time for operation. If water supply work is required before starting up, the time for that may also be included in the required preparation time for operation. If workers are required to monitor on-site at the time of starting up for safety and legal reasons, the travel time of the workers may also be included in the required preparation time for operation. Tasks such as start-up inspection and recording performed before operation may also be included in the required preparation time for operation. Start-up inspection includes checking the residual pressure, checking the opening and closing operation of cocks, visually checking that there are no water leaks, checking the water level gauge, etc. The time for cooling and depressurization may also be included in the required preparation time for operation. The time required to prepare not only the process equipment itself but also auxiliary equipment, such as storage equipment for the product that the process equipment produces, may be included in the preparation time required for preparation.

[0160] In the first and second embodiments, the operation preparation time required is specified by the user, but may be specified in another format. For example, the operation preparation time required may be automatically calculated in the EMS by using information such as the temperature of the process equipment 3 before the start of operation preparation and the outside air temperature, and the time required to reach a desired temperature by a formula, a table function, a statistical model created in advance, or the like. In addition, the operation preparation time required may be changed by using the elapsed time since the previous stop. In the calculation of the optimization unit 152, when a stop is also planned, a constraint condition may be constructed so that the operation preparation time required varies depending on the time step interval from the stop to the start of operation preparation, and an operation plan may be created.

[0161] In the first and second embodiments, the computational resources do not need to be on-site, but may be on the cloud.

[0162] In the first and second embodiments, the system that receives and transmits energy to and from the outside is called the "microgrid 1" for convenience, but the form is not necessarily limited to a single factory or business site. For example, it may be an industrial park that bundles together multiple factories.

[0163] In the first and second embodiments, the renewable energy generator, the storage battery system 5, and the process device 3 are all present in one microgrid 1 as shown in FIG. 1. However, the configuration of the microgrid is not limited to this. For example, as shown in FIG. 20, a group of connected devices may be regarded as a virtual microgrid and the above-mentioned operation plan creation devices 10 and 10A may be applied. The microgrid 1B includes a photovoltaic power generation system 2B owned by a power generation company A, a process device 3B owned by a company B, and a storage battery system 5B owned by a company C. These photovoltaic power generation system 2B, the process device 3B, and the storage battery system 5B are connected via a power grid 9. In other words, the companies that own each system may be different. In this case, the contract between each company may be a transaction via the electricity market or a bilateral transaction.

[0164] In the first and second embodiments, for simplicity, the power required for operation preparation is set to zero. In other words, the power is assumed to be sufficiently small, and the planning is performed while ignoring the power required for operation preparation. However, the power required for operation preparation may be taken into consideration. For example, a condition that a certain amount of power consumption occurs during operation preparation may be added to the mathematical programming problem (PG). In this case, the expansion is easy. With this expansion, the power required for pre-heating and pre-cooling is calculated by subtracting the surplus power p s This will solve the problem of it being difficult to cover the costs with just one.

[0165] In the first embodiment, only power based on renewable energy is considered as the power provided to the process equipment 3. For example, when a storage battery system 5 is provided as in the microgrid 1A of the second embodiment, the power provided to the process equipment 3 may take into consideration power provided from the storage battery system 5 in addition to power based on renewable energy. In the second embodiment, the charge and discharge plan for the storage battery system 5 is also planned together with the manufacturing plan for the process equipment 3 in the mixed integer programming problem (PG). The charge and discharge plan for the storage battery system 5 may be planned separately from the manufacturing plan for the process equipment 3.

[0166] In this case, the surplus power p is calculated by using the plan of the charging power and discharging power of the storage battery system 5 and the predicted value of the power generation amount of the solar power generation system 2. s For example, the renewable energy surplus power calculation unit 112 can calculate the surplus power p s may be calculated.

[0167] That is, the prediction unit of the operation plan creation device of the modified example predicts the power output from the renewable energy power generation device, and obtains a predicted value by acquiring a schedule indicating the power output from the storage battery system 5 and the power input to the storage battery system 5. According to this configuration, an operation plan for the process equipment 3 that operates using the power supplied from the solar power generation system 2 and the power input / output to / from the storage battery system 5 can be obtained.

[0168] For example, when the battery storage system 5 is discharging, the renewable energy surplus power calculation unit 112 calculates the surplus power p s is not generated, the surplus power p s is set to 0, and when the battery storage system 5 is charging, the surplus power p s is generated, and the surplus power p s may be calculated by subtracting the charging power of the battery storage system 5 from the solar power generation amount. In this case, the surplus power p s If is negative, the surplus power p s is set to 0. Surplus power p s After calculation, the method in which the operation plan creation device 10 of the first embodiment creates an operation plan for the process equipment 3 can be used.

[0169] The microgrid 1A in the second embodiment includes one storage battery system 5. The microgrid may include a plurality of storage battery systems 5. Similarly, the microgrid may include a plurality of process devices. It is easy to extend the mixed integer programming problem (PG) to a plurality of devices.

[0170] In the second embodiment, it is assumed that the microgrid 1A includes a storage battery system 5. The operation plan creation device 10A of the second embodiment may be applied to creating an operation plan for a microgrid that does not include a storage battery system 5, that is, a microgrid that includes only a process device 3.

[0171] In the second embodiment, instead of the total production volume, the total production volume P taking into account the forgetting factor as used in the first term of formula (1) may be used to determine whether to start preparation for operation. Furthermore, the determination to start preparation for operation is not limited to the total production volume P. For example, the determination to start preparation for operation may be made based on the total power consumption of the process equipment 3. This is because there is a correlation between the production volume and the power consumption.

[0172] The coefficient used in the first term of the formula (1) in the second embodiment is not limited to the forgetting coefficient in the form of a power. The coefficient used in the first term can be a coefficient that monotonically decreases with the passage of time.

[0173] [Additional Notes] The present disclosure includes the following configurations.

[0174] The present disclosure is [1] "an operation plan creation device that creates an operation plan for a power load device that consumes some or all of the generated power of a power generation device using renewable energy, the operation plan creation device being characterized in that the operation plan is created based on a predicted value of the generated power of the renewable energy and information on an operation preparation required time required for the power load device to start operation from a production-ready state."

[0175] The present disclosure relates to [2] "the operation plan creation device according to the above

[12] , wherein the operation plan includes a start time of preparation for operation of the power load device."

[0176] The present disclosure relates to [3] "the operation plan creation device according to the above [2], wherein the operation plan includes the power consumption or production amount, or both, of the power load device."

[0177] The present disclosure is [4] "an operation plan creation device as described in [2] above, further comprising an energy storage device, and when part or all of the discharged power of the energy storage device is consumed by the power consumption device, the operation plan includes the amount of energy stored in the energy storage device, or the amount of charged and discharged power, or both."

[0178] [Others] The operation plan creation devices 10, 10A and operation plan creation methods of the first and second embodiments relate to a technology for operating a manufacturing facility by effectively utilizing surplus electricity from renewable energy. Therefore, the operation plan creation devices, operation plan creation methods, and operation plan creation programs of the first and second embodiments contribute to the following goals 7 and 9 of the Sustainable Development Goals (SDGs) led by the United Nations. Goal 7: "Ensure access to affordable, reliable, sustainable and modern energy for all". Goal 9: "Build resilient infrastructure, promote inclusive and sustainable industrialization and foster innovation." [Explanation of symbols]

[0179] 10,10A Operation plan creation device 11 Prediction Department 13 Simulation calculation unit (processing unit) 15 Processing section 131 Total production amount calculation unit (total evaluation amount calculation unit) 132 Total production amount determination unit (total evaluation amount determination unit) 133 Start time determination section 151 Objective function and constraint condition generation unit (generation unit) 152 Optimization section (calculation section) 3. Process Equipment P max Maximum total production volume

Claims

1. An operation plan creation device that creates an operation plan for an apparatus that can be switched from a non-manufacturable state in which a product cannot be obtained even if power is input to a manufacturable state in which the product can be obtained when the power is input by performing an operation preparation, the operation plan creation device comprising: A prediction unit that obtains a prediction value of the amount of power that can be supplied to the device, including power derived from renewable energy; A processing unit that creates the operation plan based on the predicted value and an operation preparation required time indicating a required time required for the operation preparation, The operation plan includes a plurality of possible start times that can be selected as times at which the operation preparation can be started, The processing unit has a total evaluation amount calculation unit, The total evaluation amount calculation unit calculating, for each of the plurality of possible start time candidates, a total evaluation amount based on the amount of power consumption consumed by the apparatus for manufacturing the deliverable, based on the predicted value and the operation preparation required time, under a condition that the operation preparation is assumed to have started at a start time candidate selected from the plurality of possible start times; extracting at least one of the total evaluation amounts showing a maximum value from the plurality of total evaluation amounts obtained for each of the plurality of start time candidates as a maximum total evaluation amount; The operation plan creation device selects the start time candidate corresponding to at least one of the maximum total evaluation amounts as a first candidate which is a candidate for the time when the operation preparation should start.

2. The processing unit further includes a total evaluation amount determination unit, The operation plan creation device according to claim 1, wherein the total evaluation amount determination unit selects, from the at least one first candidate, at least one candidate whose maximum total evaluation amount is equal to or greater than the threshold value by comparing at least one of the maximum total evaluation amounts with a threshold value as a second candidate.

3. The processing unit further includes a start time determination unit, The operation plan creation device according to claim 2, wherein when a plurality of the second candidates are selected by the total evaluation quantity determination unit, the start time determination unit adopts the latest time among the second candidates as the start time at which the operation preparation should be started.

4. The operation plan creation device according to any one of claims 1 to 3, wherein the prediction unit obtains the predicted value by predicting power output from a renewable energy power generation device.

5. The operation plan creation device according to any one of claims 1 to 3, wherein the prediction unit predicts the power output from a renewable energy power generation device and obtains the predicted value by acquiring a schedule indicating the power output from an energy storage device and the power input to the energy storage device.

6. The operation plan creation device according to any one of claims 1 to 3, wherein the total evaluation amount is a total production amount of the product produced by the device, the total evaluation amount being calculated based on the power consumption amount.

7. The operation plan creation device according to any one of claims 1 to 3, wherein the total evaluation amount is the power consumption amount.

8. The processing unit includes: a generation unit that creates a planning problem including a term defined by including an amount of power consumption consumed by the device in order to obtain the deliverable in the device at a predetermined time, and a term indicating whether the device is capable of receiving the power and producing the deliverable; The operation plan creation device according to claim 1 , further comprising: a calculation unit that obtains the operation plan candidates by solving the planning problem.

9. The processing unit includes: The operation plan creation device according to claim 8, further comprising: an adoption / rejection determination unit that adopts the candidate operation plan as the operation plan when a total evaluation value defined by including an amount of power consumption consumed by the device obtained based on the operation plan is equal to or greater than a threshold value.

10. 1. An operation plan creation method for creating an operation plan for an apparatus that can be switched from a non-manufacturable state in which a product cannot be obtained even if power is input to a manufacturable state in which the product can be obtained when power is input by performing an operation preparation, comprising: Obtaining a forecast of the amount of power available to the device, including power derived from renewable energy sources; Creating the operation plan based on the predicted value and an operation preparation required time indicating a required time required for the operation preparation, The operation plan includes a plurality of possible start times that can be selected as times at which the operation preparation can be started, Creating the operation plan includes: calculating, for each of the plurality of possible start time candidates, a total evaluation amount based on the amount of power consumption consumed by the apparatus for manufacturing the deliverable, based on the predicted value and the operation preparation required time, under a condition that the operation preparation is assumed to have started at a start time candidate selected from the plurality of possible start times; extracting at least one of the total evaluation amounts showing a maximum value from the total evaluation amounts obtained for each of the start time candidates as a maximum total evaluation amount; selecting the start time candidate corresponding to at least one of the maximum total evaluation amounts as a first candidate which is a candidate for a time when the operation preparation should start.

Citation Information

Patent Citations

  • Cold air distributor for reefer warehouse

    JP1986089448A

  • Operation management apparatus, operation management method and program

    JP2013106367A

  • Power supply system and method of controlling the same

    JP2020054085A

  • Power supply system

    JP2021164178A

  • Power control system

    JP2022020978A