Length adjustment jig

The length adjusting jig addresses the inefficiencies and safety concerns of welding in reinforced earth wall construction by allowing for easy and precise length adjustments of residual formwork, enhancing construction efficiency and safety.

JP7669019B2Active Publication Date: 2025-04-28ENVINE CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2021003433
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-01-13
Publication Date
2025-04-28
Estimated Expiration
2041-01-13

AI Technical Summary

Technical Problem

The existing methods for constructing reinforced earth walls require complex and costly welding processes to adjust the length of residual formwork, leading to poor construction efficiency and safety concerns.

Method used

A length adjusting jig that includes a pair of bolt materials with threaded portions and a clamp mechanism, allowing for fine adjustments in length by rotating one of the bolts, and featuring a design that ensures shear resistance in both directions, preventing the bolt from being pulled out.

Benefits of technology

The length adjusting jig enables quick and precise length adjustments, improving construction efficiency and safety by eliminating the need for welding and reducing the risk of accidents, while also enhancing durability against repeated loads and vibrations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007669019000001
    Figure 0007669019000001
  • Figure 0007669019000002
    Figure 0007669019000002
  • Figure 0007669019000003
    Figure 0007669019000003
Patent Text Reader

Abstract

To provide a length adjustment tool having good workability and capable of adjusting a length easily in a short time by anyone.SOLUTION: A length adjustment tool 5' for maintaining a separation state between plate-like panel members in a length adjustable manner comprises: a pair of bolt members 50', 51' with screw parts 50a', 51a'; and a clamp mechanism 52 holding the screw parts 50a', 51a' of the pair of bolt members 50', 51' in a freely rotatable manner, wherein fine adjustment of a length is possible by rotating either of the pair of bolt members 50', 51' .SELECTED DRAWING: Figure 9
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a length adjustment jig that fastens a panel material such as a remaining formwork (remaining formwork) so that the length of the panel material can be freely adjusted. [Background technology]

[0002] Traditionally, reinforced earth walls have been constructed using the reinforced earth wall method as an alternative to block masonry and concrete retaining walls. There are many different methods for this method, depending on the type of reinforcing material and wall surface work, but for example, when constructing a geotextile reinforced earth wall, a steel frame is filled with soil (embankment) and set up in a stepped shape, and a planar geotextile made of a polymeric material is laid as a reinforcing material in the embankment to construct an earth retaining structure consisting of a wall surface that is steeper than the general stable gradient and is close to vertical.

[0003] Sloping reinforced earth walls constructed in this way are generally planted with greenery. However, due to maintenance constraints such as the high cost of weed control, there is a strong demand for not planting greenery on the surface of reinforced earth walls. Therefore, when not planting greenery on the surface, wall panels, which are residual formwork (remaining formwork), are installed by hanging them on the front of the reinforced earth wall via metal fittings for adjusting the length, such as separators.

[0004] For example, Patent Document 1 discloses a method of constructing a leaning type retaining wall (inclined wall type) in which a soil slope S is covered with a water-permeable mat 3, anchors 4 are driven into the slope S to fix the water-permeable mat 3, a foundation B is constructed, pillars 2 are installed, a remaining concrete formwork 1 is hung on this pillar material 2, and backfill concrete C is poured between the slope S and the remaining formwork 1 (see paragraphs

[0020] to

[0030] of the specification of Patent Document 1, and Figures 1 and 3 of the drawings, etc.).

[0005] However, the remaining formwork 1 used in the method for constructing a lean-type retaining wall described in Patent Document 1 was installed on the slope side of the reinforced soil wall, and the separator was welded on-site to adjust its length according to the installation position of the remaining formwork 1. This required the required length of the separator to be measured and then a separate welding operation, which resulted in poor workability and low work efficiency. Furthermore, welding joints requires workers with highly specialized welding skills, which not only increases costs but also requires strict safety management, such as the management of firearms. [Prior art documents] [Patent documents]

[0006] [Patent Document 1] JP 2014-189978 A Summary of the Invention [Problem to be solved by the invention]

[0007] The present invention has been devised in consideration of the above problems, and its object is to provide a length adjuster that is easy to install and allows anyone to easily adjust the length in a short amount of time. [Means for solving the problem]

[0008] The length adjustment jig described in claim 1 is a length adjustment jig that holds the separated state of plate-shaped panel materials so as to be freely adjustable in length, and includes a pair of bolt materials having threaded portions, and a pair of bolt materials that are threaded to each other. The direction of engagement with the thread is reversed and the shape is overlapped. and a clamp mechanism that holds the bolts rotatably, and by rotating one of the pair of bolts, fine adjustment of the length is possible.

[0009] The length adjustment jig described in claim 2 is a length adjustment jig for hanging a plate-shaped panel material so as to be freely adjustable in length, and includes a pair of hook bolts having connecting hooks and threaded portions for hanging the panel material, and the threaded portions of the pair of hook bolts are connected to each other. The direction of engagement with the thread is reversed and the shape is overlapped.and a clamp mechanism that holds the bolts rotatably, and the length can be fine-tuned by rotating either one of the pair of hook bolts.

[0010] The length adjustment jig described in claim 3 is the length adjustment jig described in claim 2, characterized in that the clamp mechanism has a pair of clamp materials which are bent from sheet material and have recesses at their ends through which the screw portions are inserted, and the pair of clamp materials are fastened together with a connecting bolt to hold the screw portions together so that they can rotate freely.

[0011] The length adjustment jig described in claim 4 is the length adjustment jig described in claim 3, characterized in that the clamp mechanism holds the threaded portions rotatably together by inserting a corner of the end face of the notch into a groove of the threaded portion.

[0012] The length adjustment jig described in claim 5 is the length adjustment jig described in claim 3 or 4, characterized in that a return piece is formed in the notch of either or both of the pair of clamp materials to hook the bolt material or hook bolt to prevent it from falling.

[0013] The length adjustment jig described in claim 6 is 2 In the length adjustment jig described in the above, one or both of the pair of hook bolts is characterized in that a part of the connecting hook or the threaded portion is crushed to expand its diameter.

[0014] The length adjustment jig described in claim 7 is the length adjustment jig described in any one of claims 1 to 6, characterized in that it maintains the spaced state of the remaining formwork covering the retaining wall in a manner that allows the length to be freely adjusted. Effect of the Invention

[0015] According to the invention of claim 1, the length can be finely adjusted by rotating one of the pair of bolt materials, so the workability is good and anyone can easily adjust the length in a short time. Also, according to the invention of claim 1, by making the direction of engagement with the left and right threads in the longitudinal direction of the bolt reversed, it is possible to ensure shear resistance to the bolt in both pushing and pulling directions, and the structure has no direction in the bolt extraction direction. Therefore, it has high durability against repeated loads and vibrations.

[0016] According to the invention of claim 2, the length can be finely adjusted by rotating one of the pair of hook bolts, so the workability is good and anyone can easily adjust the length in a short time. Also, according to the invention of claim 2, by making the direction of engagement with the left and right threads in the longitudinal direction of the bolt reversed, it is possible to ensure shear resistance to both pushing and pulling the bolt, and the structure has no direction in the bolt extraction direction. Therefore, it has high durability against repeated loads and vibrations.

[0017] In particular, according to the invention as defined in claim 3, it is possible to realize a length adjustment jig that has a simplified and simple configuration and excellent workability, and that is inexpensive and has excellent durability.

[0018] In particular, according to the invention of claim 4, the corners of the end faces of the notches are inserted into the grooves of the threaded portions, thereby holding the threaded portions together so that they can rotate freely, thereby preventing the hook bolt or the bolt material from shifting in the axial direction and enabling the hook bolt or the bolt material to withstand the pull-out force and compression force along the axial direction.

[0019] In particular, according to the invention as defined in claim 5, since the recess is formed with a return piece, it is possible to reduce the risk that the hook bolt or the bolt material will fall off the clamp mechanism 52 even during length adjustment.

[0020] In particular, according to the invention of claim 6, a part of the connecting hook or the threaded portion is crushed and expanded in diameter, so that even if a pressing force acts in the axial direction of the hook bolt or the bolt material, there is little risk of it coming loose and coming off.

[0021] In particular, according to the invention defined in claim 7, the spaced apart state of the remaining formwork covering the retaining wall is maintained so that the length can be freely adjusted, so that the above-mentioned functional effects can be exerted in the remaining formwork covering the retaining wall. [Brief description of the drawings]

[0022] [Figure 1] FIG. 1 is a vertical sectional view showing a mounting structure for a wall panel in which a wall panel is mounted using a length adjusting jig according to a first embodiment of the present invention. [Diagram 2] FIG. 2 is an enlarged view of a portion A in FIG. 1, showing an attachment structure of each wall panel. [Diagram 3] FIG. 3 is a diagram showing a wall panel of the mounting structure for a wall panel according to this embodiment, where (a) is a front view and (b) is a right side view. [Figure 4] FIG. 4 shows the wall panel of the same, (a) being a rear view and (b) being a plan view. [Diagram 5] FIG. 5 is a diagram showing a frame fixing clamp of the wall panel mounting structure according to this embodiment, where (a) is a front view and (b) is a plan view. [Figure 6] FIG. 6 is a right side view showing the frame fixing clamp. [Figure 7] FIG. 7 is a diagram showing the length adjusting jig according to the first embodiment of the present invention, where (a) is a front view and (b) is a plan view. [Figure 8] FIG. 8 is a right side view showing the length adjusting jig. [Figure 9] FIG. 9 is a partially enlarged view of FIG. 2 showing an enlarged view of the vicinity of the frame fixing clamp of the wall panel mounting structure according to this embodiment. [Figure 10] FIG. 10 is a right side view showing a length adjustment jig according to the second embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0023] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A length adjusting jig according to an embodiment of the present invention will be described in detail below with reference to the drawings.

[0024] [First embodiment] A length adjustment jig 5 according to a first embodiment of the present invention will be described with reference to Figs. 1 to 9. A case will be described in which a wall panel 3 is attached to a steel frame 2 that maintains the slope shape of soil S of a reinforced soil wall while adjusting the distance between the steel frame 2 and the wall panel 3, using the length adjustment jig 5 according to the first embodiment of the present invention. Fig. 1 is a vertical cross-sectional view showing a wall panel mounting structure 1 to which a wall panel 3 is mounted using the length adjustment jig 5 according to the first embodiment of the present invention, and Fig. 2 is an enlarged view of part A in Fig. 1 showing an enlarged view of the mounting structure of each wall panel.

[0025] As shown in Figures 1 and 2, a frame fixing clamp 4 is attached to a steel frame 2 made of expanded metal or welded wire mesh, and a length adjustment jig 5 is hung on the attached frame fixing clamp 4 to attach the wall panel 3 while adjusting the distance between the steel frame 2 and the wall panel 3, thereby constructing a wall panel mounting structure 1.

[0026] <Wall panel> Next, the wall panel 3 of the mounting structure 1 for a wall panel mounted using the length adjustment jig 5 according to this embodiment will be described with reference to Figures 3 and 4. Figure 3 shows the wall panel 3 of the mounting structure 1 for a wall panel according to this embodiment, where (a) is a front view and (b) is a right side view. Also, Figure 4 shows the wall panel 3, where (a) is a back view and (b) is a plan view. Note that the front (surface) refers to the surface seen toward the slope of the retaining wall of the reinforced earth wall (the same applies below).

[0027] As shown in Fig. 3, the wall panel 3 is a rectangular panel when viewed from the front, which is installed to cover the front of a retaining wall such as a reinforced earth wall held by a steel frame 2 for weed control and landscape improvement, and also functions as a remaining formwork when backfill concrete is poured on the rear side. However, in principle, there is no need to pour backfill concrete for the mounting structure 1 of the wall panel according to this embodiment.

[0028] The wall panel 3 according to this embodiment is a precast lightweight panel in which steel wires are embedded as tensile reinforcement in a cement-based time-hardening material such as lightweight mortar, and is formed into a rectangular shape with a width W1 of 800 mm and a height H1 of 400 mm, as shown in Fig. 3. The wall panel 3 has a surface seen from the front with an imitation rock pattern (not shown) that resembles a stone wall, and the back surface that serves as the rear surface is flat. Of course, the dimensions of the wall panel 3 are merely examples, and it goes without saying that they can be appropriately set to a width of 900 mm and a height of 300 mm, a half-split type width of 400 mm and a half-split type width of 400 mm and a half-split type width of 450 mm and a half-split type width of 300 mm, etc.

[0029] Furthermore, the material of the wall panel 3 is not limited to a cement-based time-hardening material, and may be other materials such as resin. However, it is preferable that the wall panel 3 is a lightweight panel that is light enough for a worker to carry alone. This is because lifting equipment such as a crane or a chain block is not required.

[0030] As shown in Figures 3 and 4, this wall panel 3 is composed of a panel body 30 made of a cement-based time-hardening material with a trapezoidal vertical and horizontal cross section, six guide runners 31 (three pairs on the top and bottom) protruding from the back surface of the panel body 30 toward the steel frame 2, and four panel hooks 32 (two pairs on the left and right in two rows, top and bottom) that are hooked by a length adjustment jig 5.

[0031] (Guide Runner) The guide runners 31 are U-shaped hooks made of steel wire for hooking the wall panels 3 together. When an upper wall panel 3 is placed on the lower wall panel 3 hooked by the length adjustment jig 5, the guide runners 31 are hooked to the other wall panels 3, so that the placed wall panel 3 stands on its own. In this way, the placed wall panel 3 stands on its own, making it extremely easy for even a single worker to hook the length adjustment jig 5 to the panel hook 32.

[0032] As shown in Figures 3(a), 4(a), and 4(b), the guide runners 31 provided on the upper part of the panel main body 30 and the guide runners 31 provided on the lower part of the panel main body 30 are offset to the left and right so as not to interfere with the guide runners 31 of other wall panels 3 on the adjacent upper or lower levels.

[0033] (Panel hook) The panel hook 32 is a dogleg-shaped hook made of a steel wire for hanging the wall panel 3 with the length adjustment jig 5, and as shown in Fig. 3(b) , the steel wire has a loop portion 32a formed by turning once in the middle. By hanging the connecting hook of the length adjustment jig 5 on this loop portion 32a, it is possible to reduce the risk of the connecting hook 51a (described later) coming off the loop portion 32a and becoming detached even if the steel frame 2 expands and a pressing force acts on the wall panel 3 from the back side (see also Fig. 2 ).

[0034] <Frame fixing clamp> Next, the frame fixing clamp 4 of the wall panel mounting structure 1 according to this embodiment will be described with reference to Fig. 5 and Fig. 6. Fig. 5 shows the frame fixing clamp 4 of the wall panel mounting structure 1 according to this embodiment, where (a) is a front view and (b) is a plan view. Fig. 6 is a right side view showing the frame fixing clamp 4 of the wall panel mounting structure 1.

[0035] 5 and 6, the frame fixing clamp 4 is a clamp for fixing to the steel frame 2 in order to hang the wall panel 3 on the steel frame 2 via a length adjustment jig 5. This frame fixing clamp 4 includes a clamp body 40, a hook bolt 41 screwed to this clamp body 40, and a stainless steel abutment plate 42 joined to the clamp body 40.

[0036] (Clamp body) This clamp body 40 is a member formed by cutting and bending a stainless steel plate having a thickness of about 3 mm. As shown in Figures 5 and 6, this clamp body 40 is formed with a hook piece 43 for hooking the connecting hook 50a of the length adjustment jig 5, and a recessed groove 44 for inserting the frame material constituting the expanded metal of the steel frame 2. A bolt hole (not shown) for inserting the hook bolt 41 is drilled near the center of the clamp body 40.

[0037] The hanging piece 43 is formed with a hanging hole 43a, which is a circular hole with a diameter of 8 mm, through which the connecting hook 50a of the length adjustment jig 5 can be inserted. Of course, the diameter of the hanging hole 43a may be appropriately determined according to the diameter of the connecting hook. However, as described later, in order to prevent the length adjustment jig 5 from dropping, a part of the connecting hook 50a is crushed and expanded in diameter, so it is preferable that the diameter of the hanging hole 43a is not much larger than that of the connecting hook 50a.

[0038] As shown in FIG. 6, the recessed groove 44 has a tapered side that is wider at the bottom end in the drawing, which is on the steel frame 2 side, and narrower at the top end, which is on the rear side.

[0039] (Hook bolt) The hook bolt 41 is a stainless steel bolt, and is composed of a J-hook 41a with a J-shaped bent tip, a threaded portion 41b with an M8 thread, and a stainless steel nut 41c of M8 that screws into the threaded portion 41b. Of course, M8 is merely an example of the thread diameter, and it goes without saying that it can be selected appropriately according to the size (same below).

[0040] (Abutting plate) The abutment plate 42 is a stainless steel plate with a thickness of about 3 mm, and like the clamp body 40, has a bolt hole (not shown) drilled in the center for inserting the hook bolt 41. This abutment plate 42 has a length that ensures that both ends of the abutment plate 42 come into contact with other parts of the frame material of the steel frame 2 when the abutment plate 42 is hooked to the frame material of the steel frame 2 by the hook bolt 41 inserted through the central bolt hole. In the illustrated embodiment, the length of the abutment plate 42 is 80 mm, and by ensuring a length of 40 mm to both ends of the abutment plate 42 when the center is hooked by the hook bolt 41, it is guaranteed that the abutment plate 42 will come into contact with the frame material of the expanded metal at three or more points (see also FIG. 9).

[0041] Of course, the length of this abutment plate 42 is set appropriately depending on the gap spacing and arrangement position of the frame materials of the steel frame 2, and in the case of a steel frame 2 made of welded wire mesh, it is preferable that the length be at least twice the spacing of the welded wire mesh, which is the frame material.

[0042] The abutment plate 42 is welded to the clamp body 40. However, the abutment plate 42 only needs to have a length that allows it to contact the frame material at three or more points, and may be molded integrally with the clamp body 40. In that case, the aforementioned hook piece 43 may be attached by welding or the like to the clamp body 40 integrated with the abutment plate 42.

[0043] In this way, the frame fixing clamp 4 presses the groove 44 against the frame material of the steel frame 2, and then the J-shaped hook 41a of the hook bolt 41 is hooked onto the frame material of the steel frame 2 and tightened with the nut 41c, whereby the frame material of the steel frame 2 is guided to a fixed position at the back of the groove 44 and securely latched and fixed.

[0044] <Length adjustment jig> Next, the length adjustment jig 5 according to the first embodiment of the present invention will be described with reference to Fig. 2 and Figs. 7 to 9. Fig. 7 shows the length adjustment jig 5 of the mounting structure 1 for a wall panel, with (a) being a front view and (b) being a plan view. Fig. 8 is a right side view showing the length adjustment jig 5. Fig. 9 is a partially enlarged view of Fig. 2 showing the vicinity of the frame fixing clamp 4 of the mounting structure 1 for a wall panel in an enlarged manner. As shown in Fig. 2 and other figures, the length adjustment jig 5 according to the first embodiment is a jig that connects the hanging piece 43 of the frame fixing clamp 4 and the panel hook 32 of the wall panel 3 so as to be freely length-adjustable. This length adjustment jig 5 includes a pair of hook bolts 50, 51 and a clamp mechanism 52 that rotatably holds the pair of hook bolts 50, 51, and allows fine adjustment of the length by rotating either one or both of the pair of hook bolts 50, 51.

[0045] (Hook bolt) As shown in Figures 2 and 7, the hook bolt 50 is a stainless steel hanging fitting that is hung in the hanging hole 43a of the hanging piece 43, and has a connecting hook 50a that is bent back by 180 degrees or more, and a threaded portion 50b that is continuous with this connecting hook 50a and has an M8 thread formed thereon.

[0046] After the hook bolt 50 is hooked into the hook hole 43a, the vicinity of the boundary between the connecting hook 50a and the threaded portion 50b is crimped and crushed to form a crushed portion 50c with an expanded diameter. Therefore, even if a pressing force acts in the axial direction of the hook bolt 50, the hook bolt 50 will not come off the hook hole 43a (see Figs. 2 and 9).

[0047] As shown in Figures 2 and 7, the hook bolt 51 is a stainless steel fastening fitting that is hooked onto the panel hook 32 of the wall panel 3, and has a connecting hook 51a that is bent back at approximately 170 degrees, and a threaded portion 50b that is continuous with the connecting hook 51a and has an M8 thread.

[0048] (Clamp mechanism) The clamp mechanism 52 is a mechanism that latches the threaded portions 50b, 51b of the pair of hook bolts 50, 51 described above to resist stress along the axial direction of the hook bolts 50, 51, and also overlaps these hook bolts 50, 51 to adjust their length and hold them rotatably. As shown in Figures 7 and 8, this clamp mechanism 52 is composed of a first clamp member 53 with a U-shaped cross section whose open end is open, a second clamp member 54 with a U-shaped cross section whose open end is fitted into the first clamp member 53, and a connecting bolt 55 that penetrates and holds them.

[0049] In the illustrated embodiment, the first clamp member 53 is a stainless steel plate about 3 mm thick, with both ends bent upward in the out-of-plane direction, and is formed with notches 53a through which the pair of hook bolts 50, 51 are inserted. An inner end surface 53b of this notch 53a has a predetermined inclination angle such that the cut end surface screws into the threaded portion 51b, and the corners of this inner end surface 53b fit into the thread groove of the threaded portion 51b, thereby preventing the hook bolt 51 from shifting in the axial direction against the stress along the axial direction of the hook bolt 51.

[0050] Furthermore, as shown in FIG. 7(a), a return piece 53c is formed in the recess 53a of the first clamping material 53, which reduces the risk of the hook bolt 51 falling off the clamping mechanism 52 even when fine-tuning the length.

[0051] Similarly to the first clamp material 53, the second clamp material 54 is made of a stainless steel plate about 3 mm thick, with both ends bent downward out of the plane, and has an arc-shaped notch 54a through which only the hook bolt 50 is inserted. The inner end surface 54b of this notch 54a has a predetermined inclination angle such that the cut end surface screws into the threaded portion 50b, and this inner end surface 54b fits into the thread groove of the threaded portion 51b, thereby preventing the hook bolt 51 from shifting in the axial direction against the stress along the axial direction of the hook bolt 51.

[0052] In addition, the hook bolts 50 and 51 are shaped so that the direction of engagement with the left and right threads is reversed along the length of the bolt, ensuring shear resistance in both pushing and pulling directions, and are structured so that there is no direction in the bolt extraction direction. Therefore, the clamp mechanism 52 has high durability against repeated loads and vibrations.

[0053] The connecting bolt 55 is an M8 size bolt that is inserted into a bolt hole (not shown) drilled in the center of the first clamping member 53 and the second clamping member 54. The connecting bolt 55 is screwed with a nut 55b via a washer 55a, so that the hook bolts 50, 51 are sandwiched between the first clamping member 53 and the second clamping member 54. Therefore, the clamping mechanism 52 holds the hook bolts 50, 51 in a state in which the threads of the threaded parts 50b, 51b of the hook bolts 50, 51 are engaged with each other, and can resist the pull-out force and compression force along the axial direction of the hook bolts 50, 51. In other words, the resistance to the pull-out load due to the engagement of the threads is secured by the shear force, resulting in a strong restraint structure that is different from a general simple slip resistance. In addition, it is a stable structure that is not easily affected by vibrations, etc.

[0054] [How to use the length adjustment jig] Next, a method of using the length adjustment jig 5 according to the first embodiment of the present invention will be described with reference to Figures 1, 2 and 9. The following describes an example of a case in which a sloped reinforced soil wall is constructed, and wall surface greening is not performed, but a wall panel 3 that covers the front surface of a steel frame 2 that maintains the slope shape of the soil S of the reinforced soil wall is attached to the steel frame 2 to construct the above-mentioned wall panel mounting structure 1 for the purpose of weed control and landscape improvement.

[0055] (Preliminary process) First, as shown in FIG. 1, a reinforced earth wall is constructed by laying soil S made of local soil or fill on a steel frame 2 made of expanded metal or welded wire mesh.

[0056] Specifically, as shown in Figure 1, soil S is laid to construct a slope with a trapezoidal vertical cross section and then appropriately compacted, after which geotextile G, a planar resistance material, is laid, and the aforementioned steel frame 2 is installed along the edge of the slope to connect with the laid geotextile G. In this process, these steps are repeated to interpose geotextile G within the soil S laid in layers, and the tensile resistance of geotextile G, friction and interlocking with the soil S, and promotion of consolidation of the embankment increase the strength of the soil and stabilize the entire embankment, thereby constructing a reinforced soil wall, which is a steeply sloping soil wall structure.

[0057] (Frame fixing clamp installation process) Next, in the method of using the length adjusting jig according to this embodiment, a frame fixing clamp attachment step is performed in which the frame fixing clamp 4 is fixed to the steel frame 2 installed in the preliminary step.

[0058] Specifically, as shown in Fig. 2 and Fig. 9, in this process, the groove 44 of the frame fixing clamp 4 is pressed against the frame material of the steel frame 2 made of expanded metal, and the frame material of the steel frame 2 is hooked with a J-shaped hook 41a whose tip is bent into a J-shape, and the nut 41c is turned and screwed to fix it. At this time, as shown in Fig. 6, the groove 44 has a tapered side that is wide at the bottom end shown in the figure that is the steel frame 2 side and narrow at the top end that is the back side. Therefore, by tightening the hook bolt 41, the frame fixing clamp 4 is fixed at an appropriate fixing position where the frame material of the steel frame 2 is guided by the tapered side of the groove 44 and abuts against the bottom side of the groove 44.

[0059] As described above, the frame fixing clamp 4 is provided with the abutment plate 42 having a predetermined length according to the interval between the frame members of the steel frame 2 made of expanded metal. Therefore, as shown in Figs. 2 and 9, the frame fixing clamp 4 is hooked at the center by the hook bolt 41, and both ends of the abutment plate 42 abut against other frame members of the expanded metal. Therefore, the frame fixing clamp 4 comes into contact with the steel frame 2 at three or more points, and has reaction points for each of the left and right rotation directions, so that the frame fixing clamp 4 can be prevented from rotating around the frame member hooked by the hook bolt 41. This configuration can prevent the length adjustment jig 5 from falling off the hook piece 43 of the frame fixing clamp 4 in the wall panel installation process, which is a later process. This configuration also dramatically improves the fixing force of the frame fixing clamp 4 against repeated external forces and vibrations.

[0060] (Wall panel installation process) Next, in a method of using the length adjustment jig according to this embodiment, the length adjustment jig 5 is hung on the frame fixing clamp 4 installed in the front frame fixing clamp installation process, and the wall panel installation process is performed to install the aforementioned wall panel 3.

[0061] Specifically, as shown in Fig. 2, in this step, the connecting hook 50a of the hook bolt 50 of the length adjustment jig 5 is inserted into the hanging hole 43a of the hanging piece 43 of the frame fixing clamp 4 attached in the front frame fixing clamp attachment step, and is hung. After that, the vicinity of the boundary between the connecting hook 50a and the threaded portion 50b is crimped and crushed to form the crushed portion 50c with an expanded diameter (see also Fig. 12). However, the step of forming the crushed portion 50c may be performed before the frame fixing clamp attachment step, and the frame fixing clamp attachment step may be performed in a state in which the length adjustment jig 5 is connected to the frame fixing clamp 4. This is because there is less work to be done on the back side of the wall panel 3, which is difficult for workers to see, and work efficiency is improved.

[0062] In this process, the pair of hook bolts 50, 51 are overlapped to the required length according to the deformation of the retaining frame 2 such as protrusion, clamped and held by the clamp mechanism 52, and the hook bolt 51 is hooked to the panel hook 32 of the wall panel 3. After that, the length of the connector 5 is finely adjusted by rotating one or both of the pair of hook bolts 50, 51 while clamped by the clamp mechanism 52. At this time, the length of the connector 5 can be finely adjusted by simply turning the hook bolts 50, 51 with one hand, so that the worker can support the wall panel 3 with one hand and accurately adjust the length of the connector 5 with the other hand, which makes the work extremely efficient. Moreover, the length adjustment of the connector 5 depends on the position of the hook bolts 50, 51 at which the clamp mechanism 52 clamps them, so that an extremely wide range of adjustment is possible, and it is also possible to freely set the gradient angle, such as changing the gradient of the reinforced earth wall and the gradient of the wall panel 3. In addition, the main length adjustment work involves simply overlapping a pair of hook bolts 50, 51 and clamping and holding them with the clamp mechanism 52, making it possible to make large length adjustments in a short amount of time, and also to make accurate fine adjustments by simply rotating either of the hook bolts 50, 51.

[0063] In addition, in this process, the length of the length adjustment jig 5 is adjusted again to finely adjust the protruding and retracting parts of the corners of adjacent wall panels 3, thereby ensuring the smoothness of the wall panels 3. At this time, as described above, the length of the length adjustment jig 5 can be finely adjusted by simply turning it with one hand, which improves work efficiency significantly compared to conventional wall panel installation work.

[0064] When installing the bottom wall panel 3, concrete is poured to construct a foundation F as shown in FIG. 1, and a hanging member L consisting of an L-shaped angle is fixed with an anchor A1. The guide runner 31 below the wall panel 3 is then hung on this hanging member L to install the wall panel 3.

[0065] As mentioned above, in the conventional method of directly fixing wall panels to a steel frame, the embankment and steel frame would bulge outward and deform due to compaction, and this deformation could be transmitted to the wall panel, causing it to collapse. Furthermore, there were concerns about long-term durability in an environment where rainwater could penetrate the bolts, etc.

[0066] However, in the length adjustment jig 5 according to this embodiment, not only is the connecting hook 50a of the hook bolt 50 bent back by 180 degrees or more, but a crushing portion 50c is also formed so that it will not come off due to repeated external force or vibration. In addition, the frame fixing clamp 4 and the length adjustment jig 5 are made of stainless steel, and there is no problem with long-term durability even in an environment where rainwater penetrates.

[0067] Furthermore, a return piece 53c is formed in the recess 53a of the length adjustment jig 5, which prevents the hook bolt 51 from falling out of the clamp mechanism 52 and dropping into the lower wall panel 3 or onto the foundation F even when adjusting the length of the length adjustment jig 5 in this process.

[0068] Meanwhile, the connecting hook 51a of the hook bolt 51 of the length adjustment jig 5 that is hooked onto the panel hook 32 of the wall panel 3 is bent back by about 170 degrees, making it easy to hook onto the panel hook 32 when working on the back of the wall panel 3, and also making it difficult to come off even if a pressing force is applied. Also, the panel hook 32 has a loop portion 32a formed by turning the steel wire once in the middle, so that even if the steel frame 2 is expanded and a pressing force is applied to the wall panel 3 from the back, the risk of the connecting hook 51a coming off the loop portion 32a and becoming detached can be reduced.

[0069] In this process, the wall panel 3 may be installed and its back side may be filled with a filler such as crushed stone (e.g., single-grain crushed stone). This is because constructing a crushed stone layer with drainage function not only protects the reinforced earth wall but also ensures impact resistance against collisions with driftwood and rocks.

[0070] According to the length adjustment jig 5 of the first embodiment of the present invention described above, the pair of hook bolts 50, 51 are overlapped to the required length, clamped and held by the clamp mechanism 52, and the length can be finely adjusted by rotating one of the pair of hook bolts, so that the workability is good and anyone can easily adjust the length in a short time. In addition, according to the length adjustment jig 5 of the first embodiment, the biting direction of the left and right threads is reversed in the longitudinal direction of the bolt, so that shear resistance force against the bolt in both pushing and pulling directions can be secured, and the structure has no direction in the bolt extraction direction. Therefore, it has high durability against repeated loads and vibrations.

[0071] In addition, according to the length adjustment jig 5 of the first embodiment, the wall panel 3 can be easily joined to the steel frame 2 in a short time by mechanical dry joining without welding. This solves the problem that welding to the steel frame, which is the structural material of the reinforced earth wall, is not possible due to cross-sectional loss, and the preparation process of installing the pillar material in front of the reinforced earth wall can be omitted, making it possible to shorten the construction period for installing the wall panel 3 and constructing the reinforced earth wall. Furthermore, since no welding is performed, there is no need to manage or inspect flammables and firearms, and the risk of industrial accidents can be reduced. In addition, the construction period is not affected by weather, and welding workers are not required, making it easy to secure personnel. In addition, since the wall panel 3 is installed by directly attaching the frame fixing clamp 4 to the steel frame 2, there is a high degree of freedom in arranging the wall panel 3, such as staggered arrangement or random stacking arrangement, and it is easy to plan and manage the construction, reducing the burden on the construction manager.

[0072] Furthermore, the length adjustment jig 5 of the first embodiment eliminates the need to pour backfill concrete, making it possible to omit work associated with pouring concrete, thereby also shortening the construction period.

[0073] Furthermore, with the length adjustment jig 5 according to the first embodiment, instead of the conventional installation of a weed control sheet inside a steel frame, the lightweight wall panel 3 is installed by dry joining, making it easy to dismantle, remove, replace or repair the wall panel 3, reducing running costs. Also, since the wall panel 3 is installed by attaching the frame fixing clamps 4 directly to the steel frame 2, there is a high degree of freedom in installing the wall panels, such as in a staggered or random stacking arrangement, and this makes it easy to plan and manage the construction, reducing the burden on the construction manager.

[0074] In addition, according to the length adjustment jig 5 of the first embodiment, the length of the length adjustment jig 5 can be freely adjusted, so that it is easy to install the wall panel 3 according to the deformation of the steel frame 2, such as bulging caused by the compaction of soil such as embankment. Also, the length adjustment margin of the length adjustment jig 5 is large, so not only can it easily follow the deformation of the steel frame 2, but it is also possible to freely set the gradient angle, such as by making the gradient of the reinforced soil wall and the gradient of the wall panel 3 different.

[0075] Furthermore, according to the length adjustment jig 5 of the first embodiment, the connection between the length adjustment jig 5 and the steel frame 2 via the frame fixing clamp 4, which fixes it non-rotatably with three-point contact, is a semi-fixed pin joint with moderate play, so that it can withstand compressive forces due to earthquakes, bulging, etc., and can also follow deformation over time after installation of the steel frame 2 to prevent the collapse of the wall panel 3.

[0076] [Second embodiment] Next, a length adjustment jig 5' according to a second embodiment of the present invention will be described with reference to Fig. 10. The only difference from the length adjustment jig 5 according to the first embodiment described above is that there are no connecting hooks 50a, 51a of the hook bolts 50, 51, and bolt materials 50', 51' are made of fully threaded bolts. Therefore, this point will be described, and the same components will be given the same reference numerals and descriptions thereof will be omitted.

[0077] The length adjustment jig 5' of the second embodiment of the present invention comprises a pair of bolt materials 50', 51' consisting of fully threaded bolts, and a clamp mechanism 52 that holds the threaded portions 50a', 51a' of the pair of bolt materials 50', 51' rotatably relative to each other, making it possible to fine-tune the length by rotating either one or both of the pair of bolt materials 50', 51'.

[0078] This length adjustment jig 5' is used to interpose between plate-shaped panel materials such as wooden formwork and to maintain a constant distance between them. This length adjustment jig 5' clamps the panel materials with nuts that screw into the ends of bolt materials 50', 51' made of fully threaded bolts, and maintains the distance between them. The length adjustment jig 5' can also be used to maintain the distance between plate-shaped panel materials and other structures. For example, the length adjustment jig 5' can be suitably applied to maintain a constant distance between the retaining wall and the remaining formwork that covers it. Here, the retaining wall refers to general retaining walls such as stone retaining walls, leaning retaining walls, gravity retaining walls, and L-shaped retaining walls.

[0079] The length adjustment jig 5' according to the second embodiment can be applied to adjusting the spacing of a plate-like panel material without hooks, and can achieve the above-mentioned advantageous effects.

[0080] The length adjustment jig 5 according to the first embodiment of the present invention and the length adjustment jig 5' according to the second embodiment of the present invention have been described in detail above, but the above-mentioned or illustrated embodiments are merely examples of the present invention. Therefore, the technical scope of the present invention should not be interpreted as being limited by these. In particular, the materials, dimensions, size, diameter, etc. of each component shown as an embodiment of the present invention are merely examples, and it goes without saying that they can be changed as appropriate. [Explanation of symbols]

[0081] 1: Wall panel mounting structure 2: Steel frame 3: Wall panel 30: Panel body 31: Guide Runner 32: Panel hook 32a: Loop section 4: Frame fixing clamp 40: Clamp body 41: Hook bolt 41a: J-hook 41b: Threaded part 42: Contact plate 43: Hanging piece 43a: Hanging hole 44: Groove 5,5': Length adjustment jig 50,51: Hook bolt 50',51':Bolt material 50a, 51a: Connecting hook 50b, 51b, 50a', 51a': Threaded section 50c: Collapsed part 52: Clamp mechanism 53: First clamp material (clamp material) 53a: Missing 53b: Inner end surface (end surface) 53c: Return piece 54: Second clamp material (clamp material) 54a: Missing 54b: Inner end surface (end surface) 55: Connecting bolt 55a: Washer 55b: Nut S: Soil G: Geotextile (surface resistance material) F: Basics L: Hanging material A1: Anchor

Claims

1. A length adjustment jig that holds the plate-shaped panel materials in a spaced state so that the length can be freely adjusted, A pair of bolt materials having threaded portions, and a clamping mechanism that overlaps the threaded portions of the pair of bolt materials with each other in a shape in which the engagement direction with the threads is reversed and rotatably holds them, The length can be finely adjusted by rotating one of the pair of bolt materials. A length adjustment jig characterized by:

2. A length adjustment jig for hanging and fastening a plate-shaped panel material so that the length of the panel material can be freely adjusted, a pair of hook bolts having a connecting hook and a threaded portion for hanging the panel material; and a clamp mechanism for overlapping the threaded portions of the pair of hook bolts with each other in a shape with the direction of engagement with the threads reversed so as to rotatably hold the hook bolts; The length can be finely adjusted by rotating one of the pair of hook bolts. A length adjustment jig characterized by:

3. The clamp mechanism has a pair of clamp members which are bent from a plate material and have notches at their ends through which the threaded portions are inserted, and the pair of clamp members are fastened together with a connecting bolt to rotatably hold the threaded portions together.

3. The length adjustment jig according to claim 2 .

4. The clamp mechanism holds the threaded portions rotatably relative to each other by inserting a corner of an end surface of the notch into a groove of the threaded portion. The length adjustment jig according to claim 3 .

5. A return piece is formed in the notch of either or both of the pair of clamp members to hook the bolt material or the hook bolt so that the bolt material or the hook bolt does not fall.

5. The length adjusting jig according to claim 3 or 4,

6. Either one or both of the pair of hook bolts is expanded in diameter by crushing a part of the connecting hook or the threaded portion.

3. The length adjustment jig according to claim 2 .

7. To maintain the separation state of the remaining formwork covering the retaining wall in a freely adjustable length.

7. The length adjusting jig according to claim 1, wherein

Citation Information

Patent Citations

  • Expansion separator for concrete frame construction

    JP1997144180A

  • Concrete form panel, concrete form and construction method thereof

    JP1999044025A

  • Construction method of leaning type retaining wall

    JP2014189978A