Plant and method of fabricating plant
The innovative plant layout with modular and non-modular facilities and load-bearing structures enables simultaneous construction phases, reducing project delays and costs by allowing non-modular work to proceed ahead of modular transport and optimizing space utilization.
Patent Information
- Application Number
- US19/515489
- Authority / Receiving Office
- US · United States
- Patent Type
- Applications(United States)
- Current Assignee / Owner
- Filing Date
- 2023-10-31
- Publication Date
- 2026-11-12
AI Technical Summary
The prolongation of the work period for a plant construction project is caused by the large volume of civil engineering work that needs to be completed after the installation of modular facilities, leading to inefficiencies in the overall construction timeline.
A plant layout is designed with modular and non-modular facilities, where non-modular facilities are placed in mixed placement sections with transportation routes free of aboveground structures, allowing construction to proceed ahead of modular facility transport, and load-bearing facilities are used to support transportation and placement, enabling simultaneous construction of underground and aboveground structures.
This layout allows for the completion of construction work in mixed placement sections without waiting for modular facility transport, reducing the overall work period and saving space, thereby suppressing project delays and costs.
Smart Images

Figure US20260357561A1-D00000_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present disclosure relates to a plant and a method of fabricating a plant.BACKGROUND ART
[0002] There has been known a method of constructing a plant by assembling a module in a remote location and carrying the module. In Patent Literature 1, there is disclosed a technology in which a carrying vehicle carries a module to an installation site, passing between a plurality of support bodies protruding upwardly from the ground. The technology described in Patent Literature 1 enables reduction in the space for carrying a module.CITATION LISTPatent Literature
[0003] PTL 1: JP 2018-168568 ASUMMARY OF INVENTIONTechnical Problem
[0004] In a work period for a plant using modules, civil engineering work is carried out in an initial period before installation of the modules. There is little overlap between the civil engineering work and another kind of construction work, and thus it is possible to proceed with the civil engineering work in high yield. However, due to reasons such as a layout plan of apparatuses or placement of a crane used for piping work or the like after installation of the modules, a part of the civil engineering work is required to be carried out after arrival of the modules. Thus, it is difficult to complete the entire civil engineering work before arrival of the modules. An increase in the volume of civil engineering work after installation of the modules is directly linked with an increase in the work period for the entire project. That is, a large volume of civil engineering work left to be carried out after installation of the modules is a cause of prolongation of the work period for construction of the plant.
[0005] The present disclosure provides a technology that can suppress prolongation of a work period for a plant.Solution to Problem
[0006] According to one aspect of the present disclosure, there is provided a plant including: a plant site partitioned off as a site for performing a predetermined process; at least one modular facility including a support part for transportation; and at least one non-modular facility to be assembled in the plant site. The plant site includes: at least one module placement section adapted to be placed with the at least one modular facility; and a mixed placement section, other than the at least one module placement section, adapted to be placed with the at least one non-modular facility. The mixed placement section includes at least one transportation route section, which is formed between a first boundary defining the at least one module placement section and a second boundary that faces the first boundary and defines the plant site, and which is used for transporting the at least one modular facility. The at least one transportation route section is free of an aboveground structure on ground thereof.
[0007] The plant according to one aspect of the present disclosure has a layout that allows the modular facility to be transported to the module placement section through the transportation route section. With this layout, it is possible to proceed with construction work for the mixed placement section ahead without waiting until transportation of the modular facility is completed. Consequently, prolongation of the work period for the plant can be suppressed.
[0008] The plant according to one aspect of the present disclosure may further include a load bearing facility configured to bear a weight applied when the at least one modular facility is transported. The load bearing facility may be placed under the ground of the at least one transportation route section. In this case, it is possible to proceed with underground construction work for the transportation route section ahead of transportation of the modular facility. This can suppress prolongation of the work period for the plant.
[0009] The plant according to one aspect of the present disclosure may further include a load bearing facility configured to bear a weight applied when the at least one modular facility is placed. The load bearing facility may be placed under ground of the at least one module placement section. In this case, a space for the plant site can be saved.
[0010] In the plant according to one aspect of the present disclosure, the at least one non-modular facility may be placed adjacent to the at least one modular facility. In this case, a space for the plant site can be saved.
[0011] The plant according to one aspect of the present disclosure may further include a connecting facility configured to connect the at least one non-modular facility and the load bearing facility to each other. The connecting facility may be placed at a position at which the connecting facility does not overlap the at least one transportation route section. In this case, it is possible to proceed with construction work for the connecting facility ahead of transportation of the modular facility. This can suppress prolongation of the work period for the plant.
[0012] The plant according to one aspect of the present disclosure may further include a side trench serving as the second boundary defining the plant site. The side trench may be a load bearing facility configured to bear a weight applied when the at least one modular facility is transported, or the side trench may allow a reinforcing material, which is configured to bear a weight applied when the at least one modular facility is transported, to be contained in the side trench. For example, the reinforcing material may be gravel that is packed to such an extent as to have a gap large enough for water to flow therethrough. When the side trench contains the reinforcing material, load bearing can be temporarily enhanced. In this case, the modular facility can pass over the side trench. It is possible to proceed with construction work for the side trench ahead of transportation of the modular facility. This can suppress prolongation of the work period for the plant.
[0013] The at least one module placement section may be rectangular. The first boundary may be a short side of the at least one module placement section. In this case, the short side of the modular facility enables a decrease in the width required for transporting the modular facility. That is, the transportation route section can be narrowed. This results in an increase in the area in which construction work for the mixed placement section can be carried out. That is, it is possible to increase an area of the mixed placement section for which construction work can be carried out ahead without waiting until transportation of the modular facility is completed. Consequently, prolongation of the work period for the plant can be suppressed.
[0014] A method of fabricating a plant according to one aspect of the present disclosure involves providing, in a plant site partitioned off as a site for performing a predetermined process, at least one modular facility including a support part for transportation and at least one non-modular facility to be assembled in the plant site. The method of fabricating a plant includes: a first step of providing the at least one non-modular facility in a mixed placement section adapted to be placed with the at least one non-modular facility; and a second step of transporting the at least one modular facility to at least one module placement section adapted to be placed with the at least one modular facility, after the first step is started. The mixed placement section is a section other than the at least one module placement section. The second step includes transporting the at least one modular facility to the at least one module placement section from outside the plant site through at least one transportation route section formed between a first boundary defining the at least one module placement section and a second boundary that faces the first boundary and defines the plant site.
[0015] In the method of fabricating a plant according to one aspect of the present disclosure, construction work for providing the non-modular facility in the mixed placement section is started before the modular facility is transported to the module placement section. This enables proceeding with construction work for the mixed placement section ahead without waiting until transportation of the modular facility is completed. Consequently, prolongation of the work period for the plant can be suppressed.
[0016] The method of fabricating a plant according to one aspect of the present disclosure may further include, before the second step, a step of placing a load bearing facility configured to bear a weight applied when the at least one modular facility is transported, along a ground surface of the at least one transportation route section or under ground of the at least one transportation route section. In this case, it is possible to proceed with underground or aboveground construction work for the transportation route section ahead of transportation of the modular facility. This can suppress prolongation of the work period for the plant.
[0017] In the method of fabricating a plant according to one aspect of the present disclosure, the load bearing facility may be a temporarily-buried part that is placed under the ground of the at least one transportation route section and is temporarily buried. The method of fabricating a plant according to one aspect of the present disclosure may further include, after the second step, a step of placing an aboveground structure that is supported by the temporarily-buried part and protrudes from the ground of the at least one transportation route section. In this case, construction work for the temporarily-buried part is proceeded before transportation of the modular facility, and subsequent construction work including construction work for the aboveground structure is proceeded after the transportation of the modular facility. A volume of construction work to be carried out after the transportation of the modular facility is reduced, thereby being capable of suppressing prolongation of the work period for the plant 1.
[0018] The method of fabricating a plant according to one aspect of the present disclosure may further include, after the second step, a step of placing an aboveground structure on ground of the at least one transportation route section. In this case, the aboveground structure is placed on the ground of the transportation route section after the modular facility is transported. This enables saving of a space for the plant site.Advantageous Effects of Invention
[0019] According to the present disclosure, a technology that can suppress prolongation of a work period for the plant can be provided.BRIEF DESCRIPTION OF DRAWINGS
[0020] FIG. 1 is a plan view for schematically illustrating an example of a plant.
[0021] FIG. 2 is a plan view for schematically illustrating an example of sections.
[0022] FIG. 3 is a schematic view for illustrating an example of a layout of the plant.
[0023] FIG. 4 is a flowchart for illustrating an example of a method of fabricating a plant.
[0024] FIG. 5 is a schematic view for illustrating an example of the plant at one fabrication stage.
[0025] FIG. 6 is a schematic view for illustrating an example of the plant at one fabrication stage.
[0026] FIG. 7 is a schematic view for illustrating an example of the plant at one fabrication stage.
[0027] FIG. 8 is a schematic view for illustrating an example of the plant at one fabrication stage.DESCRIPTION OF EMBODIMENTS
[0028] Now, an embodiment is described in detail with reference to the drawings. In the description, the same elements or elements having the same function are denoted with the same reference signs, and duplicated description is omitted.
[0029] A plant of the present disclosure is fabricated or constructed by a modular construction method. The term “modular construction method” refers to a construction method in which a facility as one unit is fabricated in a location different from a construction site of a plant, and the facility is transported (carried) to the construction site of the plant to be placed therein.
[0030] FIG. 1 is a plan view for schematically illustrating an example of a plant 1. The plant 1 includes a plant site P, at least one modular facility 2, and at least one non-modular facility 3.
[0031] The plant site P is a site partitioned off in order to perform a predetermined process. The predetermined process is performed by a plurality of apparatuses. Examples of the predetermined process include treatment of liquid, gas, or powder, a process in a generator set, and a process of obtaining end products from intermediate products, but are not limited thereto. The plant site P is a site surrounded by a side trench 4. The side trench 4 is a ditch formed, for example, in a rectangular shape in plan view. The side trench 4 defines the plant site P.
[0032] The modular facility 2 is a facility fabricated outside the plant site P. The modular facility 2 is a facility including a combination of, for example, a steel frame, a pressure vessel, rotary machine, piping, a measuring instrument, an electric apparatus, a building, and the like that are integrated into one unit. For example, the modular facility 2 has a shape close to a box or a cage. In plan view and bottom view, the modular facility 2 may be rectangular. Examples of the modular facility 2 include a process equipment module, and a pipe rack module. The process equipment module is a combination of apparatuses for performing a predetermined process. The pipe rack module is a combination of apparatuses for supporting mainly piping, a valve, an air-cooled heat exchanger, and the like.
[0033] The modular facility 2 may be transported by a self-propelled modular transporter (SPMT). The SPMT Supports the modular facility 2 from below in transportation. In another example, the modular facility 2 may be transported by a truck or a trailer. The modular facility 2 may be hung from above and installed by a crane truck.
[0034] The modular facility 2 includes a support part 2A for transportation. A shape of the support part 2A is not limited to any particular shape. In one example, the modular facility 2 includes a lower support part 20A as the support part 2A. The lower support part 20A is a beam or the like supported by the SPMT. In another example, the modular facility 2 includes an upper support part 21A as the support part 2A. The upper support part 21A is, for example, a ring-shaped hardware fitting. The ring-shaped hardware fitting is provided at each of four upper corners of the modular facility 2. The ring-shaped hardware fitting is hung on a hook of a crane truck via a hanging jig. The ring-shaped hardware fitting may be detachable. In another example, the support part 2A may be a padeye. The support part 2A may be a rectangular or circular flange that is mounted horizontally to a pillar protruding from each of the four upper corners of the modular facility 2 and includes a padeye attached so as to face the flange. The support part 2A may be a casting box for lifting up a container. The support part 2A may be a crane sling for lifting up the modular facility 2 in a container shape, and a module bottom surface in contact with the crane sling.
[0035] The non-modular facility 3 is a facility to be assembled in the plant site P. Examples of the non-modular facility 3 include a compressor building, but are not limited thereto. The compressor building includes, for example, a foundation, piping, a shelter, a crane for maintenance supported by the shelter, a compressor, lighting, and a crane cable. At least one non-modular facility 3 is placed adjacent to at least one modular facility 2.
[0036] On the ground of the plant site P, an aboveground structure G is provided. The aboveground structure G is a facility provided after transportation of the modular facility 2. The aboveground structure G includes a first aboveground structure 6 in which a temporarily-buried part 5 described later is provided underground, and a second aboveground structure 7 in which the temporarily-buried part 5 described later is not provided underground.
[0037] FIG. 2 is a schematic view for illustrating an example of sections. In FIG. 2, each facility provided on the ground is omitted. The plant site P includes at least one module placement section A and a mixed placement section M. The module placement section A is a section adapted to be placed with the modular facility 2. The mixed placement section M is a section other than the module placement section A. That is, the mixed placement section M is a section resulting from excluding the module placement section A from the plant site P.
[0038] The at least one modular facility 2 is allocated to the module placement section A in advance. A shape of the module placement section A is determined in accordance with the shape of the corresponding modular facility 2. For example, the at least one module placement section A is rectangular. A foundation is provided in the module placement section A. Construction work for the foundation is carried out before the corresponding modular facility 2 is transported.
[0039] The at least one non-modular facility 3 is placed in the mixed placement section M. The mixed placement section M includes at least one transportation route section R for transporting the at least one modular facility 2. The transportation route section R is a path for transporting the modular facility 2. The transportation route section R can be regarded as a path connecting the outside of the plant site P and the module placement section A to each other.
[0040] The transportation route section R is formed between a first boundary L1 defining the at least one module placement section A and a second boundary L2 that faces the first boundary L1 and defines the plant site P. The first boundary L1 can also be regarded as a side facing the outside of the plant site P. In plan view, the first boundary L1 is a short side of the at least one module placement section A. The second boundary L2 is, for example, the side trench 4.
[0041] The plant site P may include a vacant space V. The vacant space V is a section reserved for installation of additional facilities in future. Nothing needs to be placed on and under the ground of the vacant space V. Depending on a configuration or a layout plan of facilities in future, a facility that bears a load of the facilities may be placed under the ground of the vacant space V in advance. The vacant space V is used as the module placement section A or the mixed placement section M.
[0042] FIG. 3 is a schematic view for illustrating an example of a layout of the plant 1. In FIG. 3, an example of facilities provided on and under the ground and sections is illustrated. The plant 1 includes a load bearing facility, piping 9, a first connecting facility 11 (connecting facility), and a second connecting facility 12.
[0043] The load bearing facility C bears a weight applied when the modular facility 2 is transported or placed. Examples of the load bearing facility C include the side trench 4, a cable 8, reinforced piping 10, and the temporarily-buried part 5, but are not limited thereto. The side trench 4 itself is not always required to have a load bearing capacity for bearing a weight applied when the modular facility 2 is transported. The side trench 4 may be capable of containing a reinforcing material that bears a weight applied when the modular facility 2 is transported. The reinforcing material may be, for example, a steel plate laid on an earthwork. The reinforcing material may be gravel spread over the side trench 4. The gravel is packed to such an extent as to have a gap large enough for water to flow therethrough. The side trench 4 may be temporarily reinforced by temporarily containing a reinforcing material. The reinforced piping 10 is, for example, piping that is incorporated in reinforced concrete and is reinforced. The temporarily-buried part 5 is a facility that is placed underground and is temporarily buried. The term “temporarily buried” means filling back in a hole so that a placement operation can be performed, and performing stabilization. A stabilization method is determined in accordance with an operation performed during stabilization and removal of the temporarily-buried part 5.
[0044] Under the ground of the at least one transportation route section R, the load bearing facility C that bears a weight applied when the at least one modular facility 2 is transported is placed. For example, under the ground of the at least one transportation route section R, the temporarily-buried part 5 is placed. On the ground under which the temporarily-buried part 5 is placed, the first aboveground structure 6 may be provided. The temporarily-buried part 5 supports the first aboveground structure 6.
[0045] Under the ground of the at least one module placement section A, the load bearing facility C that bears a weight applied when the at least one modular facility 2 is placed is placed. For example, under the ground of the at least one module placement section A, the cable 8 and the reinforced piping 10 are placed. The cable 8 connects the modular facility 2 and the non-modular facility 3 to each other. The reinforced piping 10 connects the piping 9 and the piping 9 that are placed across the module placement section A, to each other via the underground of the module placement section A.
[0046] On the ground of the at least one transportation route section R, at least one aboveground structure G is placed. For example, on the ground of the at least one transportation route section R, the first aboveground structure 6 or the second aboveground structure 7 is placed. Under the ground of the first aboveground structure 6, the temporarily-buried part 5 is placed. On the ground of the at least one transportation route section R, the aboveground structure G is not always required to be placed.
[0047] The first connecting facility 11 connects the at least one non-modular facility 3 and the load bearing facility C to each other. For example, the first connecting facility 11 is a cable or piping. The first connecting facility 11 connects, for example, the non-modular facility 3 and the cable 8 to each other. The second connecting facility 12 connects the non-modular facility 3 and the piping 9 to each other. The first connecting facility 11 and the second connecting facility 12 are placed at positions at which the first connecting facility 11 and the second connecting facility 12 do not overlap the at least one transportation route section R. For example, the first connecting facility 11 and the second connecting facility 12 may be placed outside or inside the at least one non-modular facility 3. The first connecting facility 11 and the second connecting facility 12 may be placed on a lower side of the transportation route section R.Plant Fabrication Method
[0048] An example of a method of fabricating the plant 1 of the present disclosure is described with reference to FIG. 4 to FIG. 8. FIG. 4 is a flowchart for illustrating an example of the method of fabricating the plant 1. FIG. 5 to FIG. 8 are schematic views for illustrating an example of the plant 1 at respective fabrication stages. FIG. 5 to FIG. 8 are plan views for schematically illustrating some sections of the plant 1. The method of fabricating the plant 1 involves providing, in the plant site P, the at least one modular facility 2 and the at least one non-modular facility 3. In FIG. 5 to FIG. 8, description is given on the assumption that the side trench 4 has already been provided.
[0049] In Step S1, as illustrated in FIG. 5, a first step of providing the at least one non-modular facility 3 in the mixed placement section M is performed. For example, non-modular facilities 31 and 32 are provided. The non-modular facilities 31 and 32 are examples of the non-modular facility 3.
[0050] The plant site P includes module placement sections A1 to A4 and transportation route sections R1 to R4. The module placement sections A1 to A4 are examples of the module placement section A. The transportation route sections R1 to R4 are examples of the transportation route section R.
[0051] The transportation route section R1 is formed between a first boundary L11 defining the module placement section A1 and a second boundary L21 that faces the first boundary L11 and defines the plant site P. The transportation route section R2 is formed between a first boundary L12 defining the module placement section A2 and a second boundary L22 that faces the first boundary L12 and defines the plant site P. The transportation route section R3 is formed between a first boundary L13 defining the module placement section A3 and a second boundary L23 that faces the first boundary L13 and defines the plant site P. The transportation route section R4 is formed between a first boundary L14 defining the module placement section A4 and a second boundary L24 that faces the first boundary L14 and defines the plant site P.
[0052] In Step S2, as illustrated in FIG. 6, a step of placing the load bearing facility C along the ground surface of the at least one transportation route section R or under the ground of the at least one transportation route section R is performed. For example, the temporarily-buried part 5, the cable 8, the reinforced piping 10, and the reinforcing material T are provided. The temporarily-buried part 5, the cable 8, the reinforced piping 10, and the reinforcing material T are examples of the load bearing facility C.
[0053] The temporarily-buried part 5 is placed under the ground of the transportation route section R3 and is temporarily buried. The cable 8 is provided under the ground of the module placement section A4. The reinforced piping 10 is provided under the ground of the module placement section A4. The reinforcing material T may be, for example, a steel plate laid on an earthwork along the ground surface of each of the transportation route sections R1 to R4. The reinforcing material T may be gravel spread over the side trench 4. The transportation route sections R1 to R4 are adjacent to the side trench 4.
[0054] In Step S2 and the subsequent steps, first connecting facilities 111 and 112 may be provided. The first connecting facilities 111 and 112 are examples of the first connecting facility 11. The first connecting facility 111 connects the non-modular facility 31 and the cable 8 to each other. The first connecting facility 112 connects the non-modular facility 32 and the cable 8 to each other. The first connecting facilities 111 and 112 are placed at positions at which the first connecting facilities 111 and 112 do not overlap the at least one transportation route section R1, R2, R3, or R4.
[0055] In Step S2 and the subsequent steps, a non-modular facility 33 may be provided. The non-modular facility 33 is an example of the non-modular facility 3. On and under the ground of a section in which the non-modular facility 33 is provided, the piping 9 is provided. The piping 9 may have a load bearing capacity for bearing a possible load to be applied. The piping 9 is connected to, for example, the reinforced piping 10.
[0056] In Step S2 and the subsequent steps, second connecting facilities 121 and 122 may be provided. The second connecting facilities 121 and 122 are examples of the second connecting facility 12. The second connecting facility 121 connects the non-modular facility 31 and the piping 9 to each other. The second connecting facility 122 connects the non-modular facility 32 and the piping 9 to each other. The second connecting facility 121 and 122 are placed at positions at which the second connecting facilities 121 and 122 do not overlap the at least one transportation route section R1, R2, R3, or R4.
[0057] In Step S3, as illustrated in FIG. 7, a second step of transporting the at least one modular facility 2 to the at least one module placement section A is performed. For example, modular facilities 27 are transported. The modular facilities 21 to 27 are examples of the modular facility 2. The second step may be performed at any time after the first step is started, and may be performed before the first step is completed.
[0058] The modular facility 21 is allocated to the module placement section A1. In the second step, the modular facility 21 is transported to the module placement section A1 from outside the plant site P along a module transportation direction D1 through the transportation route section R1.
[0059] The modular facility 22 is allocated to the module placement section A2. In the second step, the modular facility 22 is transported to the module placement section A2 from outside the plant site P along a module transportation direction D2 through the transportation route section R2.
[0060] The modular facility 23 is allocated to the module placement section A3. In the second step, the modular facility 23 is transported to the module placement section A3 from outside the plant site P along a module transportation direction D3 through the transportation route section R3.
[0061] The modular facilities 24 to 27 are allocated to the module placement section A4. In the second step, each of the modular facilities 24 to 27 is transported to the module placement section A4 from outside the plant site P along a module transportation direction D4 through the transportation route section R4. The modular facilities 24 to 27 are transported in the stated order to be placed.
[0062] In the second step, each of the modular facilities 21 to 27 passes over the reinforcing material T. A part or all of the reinforcing material T may or may not be removed after the second step is completed. In this embodiment, description is given on the assumption that all of the reinforcing material T is removed.
[0063] In Step S4, as illustrated in FIG. 8, a step of placing the aboveground structure G on the ground of the at least one transportation route section R is performed. In the plant site P, second aboveground structures 71 and 72 and the first aboveground structure 6 are placed. The second aboveground structures 71 and 72 are examples of the second aboveground structure 7. The second aboveground structure 71 is provided on the ground of the transportation route section R1. The second aboveground structure 72 is provided on the ground of the transportation route section R2. The first aboveground structure 6 is supported by the temporarily-buried part 5 and protrudes from the ground of the transportation route section R3.
[0064] The step of placing the aboveground structure G is performed after the second step. That is, the second aboveground structure 71 is provided on the ground of the transportation route section R1 after the modular facility 21 is placed in the module placement section Al. The second aboveground structure 72 is provided on the ground of the transportation route section R2 after the modular facility 22 is placed in the module placement section A2. The first aboveground structure 6 is provided on the ground of the transportation route section R3 after the modular facility 23 is placed in the module placement section A3. The first aboveground structure 6 and the second aboveground structures 71 and 72 can be placed independently of each other.
[0065] The processing steps of Step S1 to Step S4 are not limited to any particular processing steps. In one example, in the method of fabricating the plant 1, the processing step of Step S1 and the processing step of Step S2 may be interchanged with each other. In another example, the processing step of each step may be performed independently. In Step S1, the first steps of providing the non-modular facilities 31 and 32 may be performed independently. The first step of providing the non-modular facility 32 may be started after the first step of providing the non-modular facility 31 is started and the process proceeds to Step S2 and the subsequent steps. The non-modular facilities 31 and 32 do not affect each other.
[0066] As described above, the plant 1 of the present disclosure includes: the plant site P partitioned off as a site for performing a predetermined process; the at least one modular facility 2 including the support part 2A for transportation; and the at least one non-modular facility 3 to be assembled in the plant site P. The plant site P includes the at least one module placement section A adapted to be placed with the at least one modular facility 2, and the mixed placement section M, which is adapted to be placed with the at least one non-modular facility 3, other than the at least one module placement section A. The mixed placement section M includes the at least one transportation route section R, which is formed between the first boundary L1 defining the at least one module placement section A and the second boundary L2 that faces the first boundary L1 and defines the plant site P, and which is used for transporting the at least one modular facility 2. The at least one transportation route section R is free of the aboveground structure G on the ground thereof.
[0067] The plant 1 has a layout that allows the modular facility 2 to be transported to the module placement section A through the transportation route section R. With this layout, it is possible to proceed with construction work for the mixed placement section M ahead without waiting until transportation of the modular facility 2 is completed. Consequently, prolongation of the work period for the plant 1 can be suppressed.
[0068] The plant 1 includes the load bearing facility C that bears a weight applied when the at least one modular facility 2 is transported. The load bearing facility C is placed under the ground of the at least one transportation route section R. In this case, it is possible to proceed with underground construction work for the transportation route section R ahead of transportation of the modular facility 2. This can suppress prolongation of the work period for the plant 1.
[0069] The plant 1 includes the load bearing facility C that bears a weight applied when the at least one modular facility 2 is placed. The load bearing facility C is placed under the ground of the at least one module placement section A. In this case, a space for the plant site P can be saved.
[0070] The at least one non-modular facility 3 is placed adjacent to the at least one modular facility 2. In this case, a space for the plant site P can be saved.
[0071] The plant 1 includes the first connecting facility 11 (connecting facility) that connects the at least one non-modular facility 3 and the load bearing facility C to each other. The connecting facility is placed at a position at which the connecting facility does not overlap the at least one transportation route section R. In this case, it is possible to proceed with construction work for the connecting facility ahead of transportation of the modular facility 2. This can suppress prolongation of the work period for the plant 1.
[0072] The plant 1 includes the side trench 4 serving as the second boundary L2 defining the plant site P. The side trench 4 is the load bearing facility C that bears a weight applied when the at least one modular facility 2 is transported, or is capable of containing the reinforcing material T that bears a weight applied when the at least one modular facility 2 is transported. For example, the reinforcing material T may be gravel that is packed to such an extent as to have a gap large enough for water to flow therethrough. When the side trench 4 contains the reinforcing material T, load bearing can be temporarily enhanced. In this case, the modular facility 2 can pass over the side trench 4. It is possible to proceed with construction work for the side trench 4 ahead of transportation of the modular facility 2. This can suppress prolongation of the work period for the plant 1.
[0073] The at least one module placement section A is rectangular. The first boundary L1 is a short side of the at least one module placement section A. In this case, the short side of the modular facility 2 enables a decrease in the width required for transporting the modular facility 2. That is, the transportation route section R can be narrowed. This results in an increase in the area in which construction work for the mixed placement section M can be carried out. That is, it is possible to increase an area of the mixed placement section M for which construction work can be carried out ahead without waiting until transportation of the modular facility 2 is completed. Consequently, prolongation of the work period for the plant 1 can be suppressed.
[0074] The method of fabricating the plant 1 of the present disclosure involves providing, in the plant site P partitioned off as a site for performing a predetermined process, the at least one modular facility 2 including the support part 2A for transportation and the at least one non-modular facility 3 to be assembled in the plant site P. The method of fabricating the plant 1 includes: the first step of providing the at least one non-modular facility 3 in the mixed placement section M adapted to be placed with the at least one non-modular facility 3; and the second step of transporting the at least one modular facility 2 to the at least one module placement section A adapted to be placed with the at least one modular facility 2, after the first step is started. The mixed placement section M is a section other than the at least one module placement section A. In the second step, the at least one modular facility 2 is transported to the at least one module placement section A from outside the plant site P through the at least one transportation route section R formed between the first boundary L1 defining the at least one module placement section A and the second boundary L2 that faces the first boundary L1 and defines the plant site P.
[0075] According to the method of fabricating the plant 1, construction work for providing the non-modular facility 3 in the mixed placement section M is started before the modular facility 2 is transported to the module placement section A. This enables proceeding with construction work for the mixed placement section M ahead without waiting until transportation of the modular facility 2 is completed. Consequently, prolongation of the work period for the plant 1 can be suppressed.
[0076] The method of fabricating the plant 1 further includes, before the second step, a step of placing the load bearing facility C that bears a weight applied when the at least one modular facility 2 is transported, along the ground surface of the at least one transportation route section R or under the ground of the at least one transportation route section R. In this case, it is possible to proceed with underground or aboveground construction work for the transportation route section R ahead of transportation of the modular facility 2. This can suppress prolongation of the work period for the plant 1.
[0077] The load bearing facility C is the temporarily-buried part 5 that is placed under the ground of the at least one transportation route section R and is temporarily buried. The method of fabricating the plant 1 further includes, after the second step, a step of placing an aboveground structure that is supported by the temporarily-buried part 5 and protrudes from the ground of the at least one transportation route section R. In this case, construction work for the temporarily-buried part 5 is proceeded before transportation of the modular facility 2, and construction work for the first aboveground structure 6 or the second aboveground structures 71 and 72 (aboveground structure) is proceeded after transportation of the modular facility 2. A volume of construction work to be carried out after transportation of the modular facility 2 is reduced, thereby being capable of suppressing prolongation of the work period for the plant 1.
[0078] The method of fabricating the plant 1 further includes, after the second step, a step of placing the aboveground structure G on the ground of the at least one transportation route section R. In this case, the aboveground structure G is placed on the ground of the transportation route section R after the modular facility 2 is transported. This enables saving of a space for the plant site P.
[0079] According to the plant 1 and the method of fabricating the plant 1 of the present disclosure, prolongation of the work period for the plant 1 is suppressed, and thus an increase in the cost for construction machines and personnel can also be suppressed. For example, when the work period is prolonged, a cost for securing and keeping construction machines and personnel in a work site is incurred with a low working rate. To suppress prolongation of the work period results in reduction in the cost for construction machines and personnel.Modification Examples
[0080] The present disclosure is not necessarily limited to the above-described embodiment, and various modification examples are possible within a scope not departing from the gist of the present disclosure.
[0081] In the above-described embodiment, description has been given of a case in which the second boundary L2 defining the plant site P is the side trench 4, but the present disclosure is not limited thereto. For example, the second boundary L2 may be fire piping. The fire piping is buried, for example, in a rectangular shape in plan view. A pit or the like for maintenance of the fire piping may be provided under the ground of a section near the fire piping. The fire piping and the pit may be the load bearing facility C.REFERENCE SIGNS LIST1 plant, 2 modular facility, 3 non-modular facility, 4 side trench, 5 temporarily-buried part, 6 first aboveground structure, 7 second aboveground structure, 8 cable, 9 piping, 10 reinforced piping, 11 first connecting facility, 12 second connecting facility, 2A support part, A module placement section, C load bearing facility, G aboveground structure, M mixed placement section, P plant site, R transportation route section, T reinforcing material, V vacant space, D1, D2, D3, D4 module transportation direction, L1 first boundary, L2 second boundary
Claims
1. A plant, comprising:a plant site partitioned off as a site for performing a predetermined process;at least one modular facility including a support part for transportation; andat least one non-modular facility to be assembled in the plant site,wherein the plant site includes:at least one module placement section adapted to be placed with the at least one modular facility; anda mixed placement section, other than the at least one module placement section, adapted to be placed with the at least one non-modular facility,wherein the mixed placement section includes at least one transportation route section, which is formed between a first boundary defining the at least one module placement section and a second boundary that faces the first boundary and defines the plant site, and which is used for transporting the at least one modular facility, andwherein the at least one transportation route section is free of an aboveground structure on ground thereof.
2. The plant according to claim 1, further comprising a load bearing facility configured to bear a weight applied when the at least one modular facility is transported,wherein the load bearing facility is placed under the ground of the at least one transportation route section.
3. The plant according to claim 1, further comprising a load bearing facility configured to bear a weight applied when the at least one modular facility is placed,wherein the load bearing facility is placed under the ground of the at least one module placement section.
4. The plant according to claim 1, wherein the at least one non-modular facility is placed adjacent to the at least one modular facility.
5. The plant according to claim 3, further comprising a connecting facility configured to connect the at least one non-modular facility and the load bearing facility to each other,wherein the connecting facility is placed at a position at which the connecting facility does not overlap the at least one transportation route section.
6. The plant according to claim 1, further comprising a side trench serving as the second boundary defining the plant site,wherein the side trench is a load bearing facility configured to bear a weight applied when the at least one modular facility is transported, or the side trench allows a reinforcing material, which is configured to bear a weight applied when the at least one modular facility is transported, to be contained in the side trench.
7. The plant according to claim 1,wherein the at least one module placement section is rectangular, andwherein the first boundary is a short side of the at least one module placement section.
8. A method of fabricating a plant that involves providing, in a plant site partitioned off as a site for performing a predetermined process, at least one modular facility including a support part for transportation and at least one non-modular facility to be assembled in the plant site, the method comprising:a first step of providing the at least one non-modular facility in a mixed placement section adapted to be placed with the at least one non-modular facility; anda second step of transporting the at least one modular facility to at least one module placement section adapted to be placed with the at least one modular facility, after the first step is started,wherein the mixed placement section is a section other than the at least one module placement section, andwherein the second step includes transporting the at least one modular facility to the at least one module placement section from outside the plant site through at least one transportation route section formed between a first boundary defining the at least one module placement section and a second boundary that faces the first boundary and defines the plant site.
9. The method of fabricating a plant according to claim 8, further comprising, before the second step, a step of placing a load bearing facility configured to bear a weight applied when the at least one modular facility is transported, along a ground surface of the at least one transportation route section or under ground of the at least one transportation route section.
10. The method of fabricating a plant according to claim 9,wherein the load bearing facility is a temporarily-buried part that is placed under the ground of the at least one transportation route section and is temporarily buried, andwherein the method of fabricating a plant further comprises, after the second step, a step of placing an aboveground structure that is supported by the temporarily-buried part and protrudes from the ground of the at least one transportation route section.
11. The method of fabricating a plant according to claim 8, further comprising, after the second step, a step of placing an aboveground structure on ground of the at least one transportation route section.