Crane device for extra-large wind power generator

The crane device addresses the challenges of installing and maintaining large wind power generators by using a multi-stage tower structure and crane boom drive system for precise control and stability, enabling efficient and safe operation despite environmental challenges.

WO2024214865A1PCT designated stage expired Publication Date: 2024-10-17OSI LAB CO LTD +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
PCT/KR2023/007823
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-04-13
Filing Date
2023-06-08
Publication Date
2024-10-17

AI Technical Summary

Technical Problem

Current crane devices are inadequate for installing and maintaining very large wind power generators, as they struggle with stability, size, and maintenance costs due to the need for complex and expensive components, especially when dealing with equipment weighing over 1,500 tons at altitudes of 150m or more, and are hindered by environmental factors like wind and waves.

Method used

A crane device with a multi-stage tower structure, a crane boom driving structure, a hook position adjustment structure, and a skidding structure, which allows for precise control of the hook's x-axis, y-axis, and z-axis positions, and replaces counterweights with a crane boom drive structure, minimizing overall size and enhancing stability.

Benefits of technology

The solution enables efficient, stable, and safe installation or maintenance of very large wind power generators, reducing the impact of environmental factors and lowering maintenance costs by allowing precise control and stable operation of heavy equipment at high altitudes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure KR2023007823_17102024_PF_FP_ABST
    Figure KR2023007823_17102024_PF_FP_ABST
Patent Text Reader

Abstract

According to a technology described in the present application, provided is a crane device comprising: a first hook; a hook position adjustment structure; a crane boom one end part of which is connected to the hook position adjustment structure; and at least a first tower, a second tower, and a first tower driving part, wherein the first tower driving part comprises: a tower structure configured to drive the first tower in the vertical direction to be positioned between a first tower initial position and a first tower maximum rise position; a crane boom driving stricture which is connected to the crane boom and the first tower and drives the crane boom to be positioned between a crane boom initial position and a maximum driving position; and a skidding structure which is connected to the tower structure and is configured to move the tower structure.
Need to check novelty before this filing date? Find Prior Art

Description

Crane device for ultra-large wind turbines

[0001] The present disclosure relates to a crane device for a very large wind power generator.

[0002] Wind turbines are rapidly increasing in size for economic efficiency and efficiency. For example, wind turbines utilizing 15 MW turbines are being developed and installed. Wind turbines are installed onshore or offshore, and are typically installed using cranes. Offshore installations, in particular, utilize offshore wind installation vessels (WTIVs) equipped with cranes.

[0003] For example, in Korean Patent Publication No. 10-2022-0095402 (Patent Document 1), published on July 7, 2022, an offshore wind turbine installation vessel (WTIV) equipped with a crane device is disclosed.

[0004] However, the number of offshore wind installation vessels (WTIVs) capable of installing 15 MW wind turbines is currently very limited. Therefore, installing wind turbines offshore requires waiting until an offshore wind installation vessel becomes available.

[0005] In this context, ultra-large wind power generators, such as wind power generators using 17 MW turbines and wind power generators using 20 MW turbines, are being developed.

[0006] For the installation or maintenance of ultra-large wind turbines, cranes capable of installing or maintaining equipment weighing over 1,500 tons at altitudes exceeding 150 meters are required. Furthermore, for the installation or maintenance of ultra-large wind turbines offshore, an offshore wind installation vessel (WTIV) equipped with a crane capable of installing or maintaining equipment weighing over 1,500 tons at altitudes exceeding 150 meters is required.

[0007] However, to date, no cranes have been developed for installing these ultra-large wind turbines. To install these ultra-large wind turbines, cranes must also be enlarged. However, as cranes become larger, the impact of external factors, such as vibrations from wind (and, in the case of offshore wind and waves), increases proportionally, making it difficult to safely install ultra-large wind turbines.

[0008] Furthermore, when cranes are enlarged, their transportation and storage become more challenging. For example, during strong winds, even during the installation of equipment for a large wind turbine using a crane, installation work must be halted for safety reasons and the crane must be stored in a stable condition. However, when cranes are enlarged, maintaining stable storage also takes time.

[0009] It is also difficult to accurately move the equipment of a very large wind turbine in the x-, y-, and z-axes using a crane device. For example, when installing the equipment of a general wind turbine, the x- or y-axis position of the hook that transports the equipment can be controlled to some extent through the rotational movement of the crane device (e.g., the main body or support frame). However, as mentioned above, when installing equipment weighing 1,500 tons or more at an altitude of 150 m or higher, complex and expensive parts are required for the rotational movement of the crane device considering durability and stability, and therefore, the manufacturing cost and maintenance cost of the crane device also increase.

[0010] [Prior Art Literature]

[0011] [Patent Document]

[0012] (Patent Document 1) Korean Patent Publication No. 10-2022-0095402.

[0013] The purpose of the technology described herein is to provide a crane device for a large-scale wind power generator, which can minimize the overall size by using a tower structure having a multi-stage structure, can accurately and stably control the position of the hook in the x-axis, y-axis, and z-axis directions by moving the crane boom by using a crane boom drive structure, moving the hook by using a hook position adjustment structure, and moving the tower structure by using a skidding structure, and can replace a counterweight by using a crane boom drive structure.

[0014] In order to achieve the above technical problem, according to one form of the technology described in the present invention, there is provided a hook position adjustment structure including a first hook; a first hook adjustment unit configured to vertically raise or lower the first hook and to adjust a first horizontal position of the first hook; a crane boom having one end connected to the hook position adjustment structure; a tower structure including at least a first tower, a second tower, and a first tower drive unit, wherein the first tower drive unit is configured to vertically drive the first tower so that the first tower is positioned between a first tower initial position in which the first tower is stored inside or outside the second tower and a first tower maximum elevation position in which the first tower can vertically rise from the first tower initial position; A crane device is provided, comprising: a crane boom drive structure connected to the crane boom and the first tower, and driving the crane boom so that the crane boom is positioned between a crane boom initial position where the crane boom is stored and a maximum drive position at which the crane boom can be rotated about the other end of the crane boom from the crane boom initial position; and a skidding structure connected to the tower structure and configured to move the tower structure in a second horizontal direction different from the first horizontal direction.

[0015] According to the technology described herein, a crane device for an ultra-large wind power generator can be provided in which the overall size can be minimized by using a tower structure having a multi-stage structure, the position of the hook in the x-axis, y-axis, and z-axis directions can be accurately and stably controlled by moving the crane boom using a crane boom drive structure, moving the hook using a hook position adjustment structure, and moving the tower structure using a skidding structure, and the counterweight can be replaced by using the crane boom drive structure.

[0016] According to the technology described herein, it is possible to provide a crane device for an ultra-large wind power generator capable of efficiently, stably and safely installing or maintaining equipment of an ultra-large wind power generator weighing 1,500 tons or more at an altitude of 150 m or more, particularly on land or at sea.

[0017] FIG. 1 is a drawing showing an exemplary configuration of a crane device for a very large wind power generator according to an embodiment of the technology described herein.

[0018] FIG. 2 is a block diagram showing a control unit of a crane device for a large-scale wind power generator and components connected to the control unit according to an embodiment of the technology described herein.

[0019] FIG. 3 is a drawing exemplarily showing processing performed by a control unit of a crane device for a large-scale wind power generator according to an embodiment of the technology described herein.

[0020] Figures 4 to 9 are drawings showing the operation of a crane device for a very large wind power generator according to an embodiment of the technology described herein.

[0021] Hereinafter, an embodiment of a crane device for a large-scale wind turbine according to the technology described herein will be described in more detail with reference to the attached drawings. For convenience of explanation, the drawings illustrating the embodiments of the technology described herein may depict only a portion of the actual configuration, omit portions, modify the configuration, or draw at a different scale.

[0022] <Example>

[0023] FIG. 1 is a drawing showing an exemplary configuration of a crane device (100) for a super-large wind power generator according to an embodiment of the technology described herein, and FIG. 2 is a block diagram showing a control unit (190) of a crane device (100) for a super-large wind power generator according to an embodiment of the technology described herein and configurations related to the control unit (190).

[0024] Referring to FIGS. 1 and 2, a crane device (100) for an ultra-large wind power generator includes a first hook (110), a hook position adjustment structure (120), a crane boom (130), a tower structure (140), a crane boom drive structure (150), and a skidding structure (160). In addition, the crane device (100) for an ultra-large wind power generator may further include a second hook (115), a support structure (135), a main body (170), a leg structure (180), a control unit (190), and a wind speed measuring device (195).

[0025] The crane device (100) for a large-scale wind power generator is also referred to simply as a “crane device (100)” hereinafter.

[0026] The first hook (110) is used, for example, to transport equipment of a very large wind turbine, and can transport equipment of a very large wind turbine using a configuration such as the LT5048 full tower lifting yoke or the LT975 Blade dragon of Liftra.

[0027] If the crane device (100) further includes a second hook (115), the second hook (115) is substantially identical to the first hook (110).

[0028] The first hook (110) and the second hook (115) can transport the equipment of a very large wind turbine using a configuration such as the aforementioned LT5048 full-tower lifting yoke.

[0029] The hook position adjustment structure (120) includes a first hook adjustment unit (121) configured to raise or lower the first hook (110) in the vertical direction and adjust the first horizontal position of the first hook (110).

[0030] It is preferable that the first horizontal direction be orthogonal to the second horizontal direction described later.

[0031] Hereinafter, the first horizontal direction is also referred to as the y-axis direction, the second horizontal direction is also referred to as the x-axis direction, and the vertical direction is also referred to as the z-axis direction.

[0032] When the crane device (100) further includes a second hook (115), the hook position adjustment structure (120) includes a second hook adjustment unit (125) configured to raise or lower the second hook (115) in the vertical direction and adjust the first horizontal direction position of the second hook (115).

[0033] When the crane device (100) further includes a second hook (115), it is preferable that the first hook adjustment unit (121) and the second hook adjustment unit (125) be configured to vertically raise or lower the first hook (110) and the second hook (115) so that the heights of the first hook (110) and the second hook (115) are the same. If the heights of the first hook (110) and the second hook (115) are not the same, the posture of a configuration such as a full-tower lifting yoke connected to the first hook (110) and the second hook (115) may not be stable, and as a result, the posture of equipment of an ultra-large wind power generator connected to the full-tower lifting yoke may also not be stable. Therefore, it is preferable that the first hook (110) and the second hook (115) be vertically raised or lowered so that the heights of the first hook (110) and the second hook (115) are the same. The first hook adjustment unit (121) and the second hook adjustment unit (125) can be implemented using, for example, a configuration such as a cable connected to the first hook (110) and the second hook (115) respectively and a winder for winding the cable.

[0034] As described above, the first hook adjustment unit (121) is configured to adjust the position of the first hook (110) in the first horizontal direction (i.e., y-direction), and the second hook adjustment unit (125) is configured to adjust the position of the second hook (115) in the first horizontal direction (i.e., y-direction).

[0035] That is, according to the present embodiment, even when the x-direction position and the z-direction position of each of the first hook (110) and the second hook (115) are fixed, the position of the first horizontal direction (i.e., y-direction) of the first hook (110) can be adjusted and the position of the second hook (115) can be adjusted in the first horizontal direction (i.e., y-direction).

[0036] Additionally, the first hook adjustment unit (121) and the second hook adjustment unit (125) may be configured to adjust the gap between the first hook (110) and the second hook (115) to a predetermined gap. For example, the first hook adjustment unit (121) and the second hook adjustment unit (125) may adjust the gap between the first hook (110) and the second hook (115) according to a predetermined gap suitable for the LT5048 full tower lifting yoke or the LT975 blade dragon.

[0037] The first hook adjustment unit (121) and the second hook adjustment unit (125) can be implemented using a configuration such as a hydraulic cylinder, for example, to adjust the position of the first horizontal direction (i.e., y direction) of the first hook (110) and the position of the second hook (115) in the first horizontal direction (i.e., y direction).

[0038] Hereinafter, this embodiment will be described in more detail assuming that the crane device (100) includes a first hook (110) and a second hook (115).

[0039] One end of the crane boom (130) is fixedly connected to a hook position adjustment structure (120). The other end of the crane boom (130) is connected to a tower structure (140), more specifically, a first tower (141 in FIG. 7). The crane boom (130) is rotationally driven by a crane boom drive structure (150).

[0040] The tower structure (140) includes at least a first tower (141), a second tower (143 in FIG. 7), and a first tower drive unit (145 in FIG. 7). The first tower (141) may be configured to be telescopically extendable relative to the second tower (143). For example, the first tower drive unit (145) is configured to vertically drive the first tower (141) so that the first tower (141) is positioned between a first tower initial position (i.e., a position where the first tower (141) is maximally retracted into or out of the second tower (143) in a telescopic manner) in which the first tower (141) is stored inside or outside the second tower (143) and a first tower maximum elevation position (i.e., a position where the first tower (141) is maximally extended from the second tower (143) in a telescopic manner) in which the first tower (141) can vertically ascend from the first tower initial position. The first tower drive unit (145) can be implemented using a configuration such as a hydraulic cylinder, for example.

[0041] The tower structure (140) may be implemented by a multi-stage structure having three or more towers rather than a two-stage structure of the first tower (141) and the second tower (143).

[0042] That is, the tower structure (140) may further include a third tower (not shown) and a second tower drive unit (not shown). Similarly to the above, the second tower (143) may be configured to be telescopically extendable with respect to the third tower. In that case, the second tower drive unit is configured to vertically drive the second tower (143) so that the second tower (143) is positioned between a second tower initial position (i.e., a position where the second tower (143) is maximally retracted into or out of the third tower in a telescopic manner) where the second tower (143) is stored inside or outside the third tower and a second tower maximum elevation position (i.e., a position where the second tower (143) is maximally extended from the third tower in a telescopic manner) where the second tower (143) can vertically ascend from the second tower initial position. The second tower drive unit may be implemented using a configuration such as a hydraulic cylinder, for example.

[0043] In this way, when the tower structure (140) is configured using a multi-stage structure, the overall height of the tower structure (140) can be minimized. For example, even when the crane device (100) is configured for use at an altitude of 150 m or higher, the overall height of the tower structure (140), which is the main component of the crane device (100), can be minimized, and thus the overall height of the crane device (100) can also be minimized. Accordingly, the influence of the crane device (100) on the external environment can also be minimized.

[0044] The crane boom drive structure (150) is connected to the crane boom (130) and the tower structure (140), more specifically, to the first tower (141). The crane boom drive structure (150) is configured to drive the crane boom (130) so that the crane boom (130) is positioned between the initial position of the crane boom where the crane boom (130) is stored and the maximum drive position at which the crane boom (130) can be rotated around the other end of the crane boom (130) from the initial position of the crane boom.

[0045] To explain in more detail, as illustrated in FIG. 1, the crane boom drive structure (150) includes, for example, a cable (151) connected to the crane boom (130), a connection structure (153) connected to the crane boom (130) and the tower structure (140), and a winch (155) that drives the cable (151) through the connection structure (153).

[0046] The connection structure (153) is implemented using, for example, a wheel structure, and is configured to drive the crane boom (130) by winding or unwinding the cable (151) by the winch (155).

[0047] When driving a crane boom (130) using a winch (155), the crane device (100) can drive the crane boom (130) stably even without using a counterweight.

[0048] The crane boom drive structure (150) can drive the crane boom (130) to adjust the vertical position (and the first horizontal direction and the second horizontal direction) of the crane boom (130).

[0049] The skidding structure (160) is connected to the tower structure (140) and is configured to move the tower structure (140) in a second horizontal direction (i.e., the x-direction) different from the first horizontal direction.

[0050] Referring to FIG. 1, the crane device (100) may further include a support structure (135). The support structure (135) is connected to the other end of the crane boom (130) and the first tower (141), and is configured to support the crane boom (130) and the first tower (141) when the crane boom (130) is driven by the crane boom drive structure (150).

[0051] For example, when the crane boom (130) is between the initial position and the maximum driving position of the crane boom, the support structure (135) is configured to support the crane boom (130) and the first tower (141) at a predetermined angle. The support structure (135) can be implemented using a connecting structure such as a cable, a wheel structure, a winch, or a hydraulic cylinder, for example.

[0052] Referring to FIG. 1, the crane device (100) further includes a main body (170).

[0053] At least a skidding structure (160) is arranged on the main body (170). In addition, a winch (155) of a crane boom driving structure (150) is also arranged on the main body (170).

[0054] On the main body, a rail (173) is provided so that the skidding structure (160) can move the tower structure (140) in the second horizontal direction (i.e., x direction).

[0055] The skidding structure (160) can move the tower structure (140) in the second horizontal direction (i.e., x-direction) by moving on the rail (173).

[0056] Referring to FIG. 1, the crane device (100) may further include a leg structure (180) including a leg (181) disposed on a main body (170) and a leg drive unit (183) configured to raise or lower the leg (181).

[0057] The leg (181) can be used, for example, to secure the crane device (100) to the ground when using the crane device (100) at sea. The leg (181) can also be used to raise the crane device (100), more specifically, an offshore wind power installation vessel (WTIV) equipped with the crane device (100), by a certain height from the sea surface. By raising the offshore wind power installation vessel (WTIV) by a certain height from the sea surface using the leg (181), the impact of the offshore wind power installation vessel (WTIV) on waves can be reduced.

[0058] The leg drive unit (183) can be implemented using a configuration such as a hydraulic cylinder, for example.

[0059] Referring to Fig. 1, the main body (170) may be provided with a recess (176) positioned between rails (173). For example, the location for installing equipment of a super-large wind power generator may be a corresponding location within the recess (176). Therefore, the crane device (100) can be operated more efficiently by the recess (176).

[0060] Referring to FIG. 2, the control unit (190) is configured to control the configuration of the crane device (100), such as the hook position adjustment structure (120), the support structure (135), the tower structure (140), the crane boom drive structure (150), the skidding structure (160), the leg structure (180), and the wind speed measuring device (195), based on a control signal. The control unit (190) may include one or more processors, and may control the configuration of the aforementioned crane device (100) using a control signal generated based on a user command input from an operator of the crane device (100) using one or more input devices or generated automatically.

[0061] FIG. 3 is a drawing exemplarily showing processing performed by a control unit (190) of a crane device (100) for a very large wind power generator according to an embodiment of the technology described herein, and FIGS. 4 to 9 are drawings showing the operation of a crane device (100) for a very large wind power generator according to an embodiment of the technology described herein.

[0062] With reference to FIGS. 3 to 9 below, the processing performed by the control unit (190) will be described in detail.

[0063] Referring to FIG. 3, the control unit (190) can perform a process (P100) of moving the crane boom (130) to a crane boom working position between the crane boom initial position and the maximum driving position. The control unit (190) controls, for example, the crane boom driving structure (150), more specifically, the winch (155), to move the crane boom (130) to the crane boom working position between the crane boom initial position and the maximum driving position.

[0064] The initial position of the crane boom refers to a position where the crane boom (130) is stored in a folded state, for example, as shown in FIG. 4.

[0065] The maximum driving position of the crane boom (130) refers to the position in which the crane boom (130) is driven to rotate to the maximum extent by the crane boom driving structure (150), as illustrated in FIG. 6, for example.

[0066] The crane boom working position is between the crane boom initial position and the maximum driving position, and may be designated as the maximum driving position, for example, as shown in Fig. 6, but is not limited thereto.

[0067] In Fig. 5, a state in which a crane boom (130) is moved through processing P100 is illustrated. Referring to Fig. 5, while the crane boom (130) is moved through processing P100, a cable (151) may be supported by a support structure (135).

[0068] Preferably, processing P100 is performed in a state where the first tower (141) is positioned at the first tower initial position and the crane boom (130) is positioned at the crane boom initial position, as illustrated in FIG. 4. That is, after moving the crane boom (130) to the crane boom working position, processing P200 described below is performed.

[0069] Referring to FIG. 3, the control unit (190) can perform a process (P200) of moving the first tower (141) to a first tower working position between the first tower initial position and the first tower maximum elevation position.

[0070] Referring to FIGS. 4 to 6, the tower structure (140) is not moved from the initial position of the first tower shown in FIG. 4. However, if necessary, for example, when installing or maintaining equipment for a large-scale wind turbine at an altitude of 150 m, the height of the tower structure (140) must also be increased.

[0071] Accordingly, the control unit (190) can control, for example, the tower structure (140), more specifically, the first tower drive unit (145), to move the first tower (141) to a first tower working position between the first tower initial position and the first tower maximum elevation position.

[0072] In Fig. 7, the first tower (141) is shown in a state in which it has been vertically moved through processing P200 in the state in Fig. 6.

[0073] Fig. 8 is a drawing that enlarges the state of Fig. 7, and shows a state in which the first tower (141) rises from the second tower (143) using the first tower drive unit (145).

[0074] The first tower working position is the first tower initial position and the first tower maximum elevation position, and may be designated as the first tower maximum elevation position, for example, as shown in Fig. 7, but is not limited thereto.

[0075] When the tower structure (140) includes the third tower (not shown) described above, the control unit (190) can perform a process (not shown) for moving the second tower (143) to a second tower working position between the second tower initial position and the second tower maximum elevation position. The process for moving the second tower (143) is similar to the process P200 described above, and thus a detailed description thereof will be omitted.

[0076] Referring to FIG. 3, the control unit (190) can perform processing (P300) for adjusting the first horizontal direction position of the first hook (110).

[0077] That is, the control unit (190) can control the first hook adjustment unit (121) to adjust the first horizontal direction position of the first hook (110).

[0078] Referring to FIG. 3, the control unit (190) can perform a process (P400) of raising or lowering the first hook (110).

[0079] That is, the control unit (190) controls the first hook adjustment unit (121) to lower the first hook (100) from the hook position adjustment structure (120), as shown in FIG. 6, for example.

[0080] Through the processing P400, the first hook (100) is raised or lowered to install or maintain equipment of a large wind turbine.

[0081] Meanwhile, when the crane device (100) further includes a second hook (115), the control unit (190) can perform a process of adjusting the first horizontal position of the second hook (115) and a process of raising or lowering the second hook (115) substantially the same as the processes P300 and P400. Alternatively, the control unit (190) can control the first hook adjustment unit (121) and the second hook adjustment unit (125) to adjust the gap between the first hook (110) and the second hook (115) to a predetermined gap.

[0082] Referring to FIG. 3, the control unit (190) can perform a process (P500) of moving the tower structure (140) in the second horizontal direction.

[0083] That is, the control unit (190) can control the skidding structure (160) to move the tower structure (140) from the position shown in FIG. 7 to the position shown in FIG. 9, for example.

[0084] By moving the tower structure (140) in the second horizontal direction, the crane device (100) can be operated more smoothly.

[0085] Referring to FIG. 3, the control unit (190) can perform a process (P600) of moving the first tower (141) from the first tower working position to the first tower initial position.

[0086] For example, when the installation or maintenance of equipment of a large-scale wind power generator is completed using a crane device (100) or when a strong wind is blowing, the control unit (190) can move the first tower (141) from the first tower working position to the first tower initial position.

[0087] Referring to FIG. 3, the control unit (190) can perform a process (P700) of moving the crane boom (130) from the crane boom working position to the crane boom initial position.

[0088] That is, for example, when the installation or maintenance of equipment of a large-scale wind power generator is completed using a crane device (100) or when a strong wind is blowing, the control unit (190) can move the crane boom (130) from the crane boom working position to the crane boom initial position.

[0089] Preferably, processing P700 is performed after processing P600. That is, for stable operation of the crane device (100), processing P700 is performed after processing P600.

[0090] As described above, the crane device (100) may include a wind speed meter (195) for measuring wind speed.

[0091] In that case, referring to FIG. 3, the control unit (190) can perform processing (P800) that performs processing P100 to processing P500 described above when the wind speed measured by the wind speed measuring device (195) is lower than a predetermined threshold wind speed.

[0092] That is, for stable operation of the crane device (100), the above-described processing P100 to processing P500 can be performed only when the wind speed is below the critical wind speed.

[0093] In addition, the control unit (190) can perform processing (P900) to generate an alarm signal indicating that the aforementioned processing P600 and processing P700 are to be performed when the wind speed measured by the wind speed meter (195) exceeds a predetermined threshold wind speed, and output the alarm signal to a predetermined user terminal.

[0094] That is, when the wind speed exceeds the critical wind speed, stable operation of the crane device (100) is impossible and may be dangerous. Therefore, the control unit (190) generates an alarm signal and outputs the alarm signal to a user terminal, such as a mobile communication terminal or a computing device, of the operator of the crane device (100). Accordingly, the operator of the crane device (100) can input a user input to, for example, organize the currently performed task and perform the aforementioned processing P600 to P700 based on the alarm signal, thereby generating a control signal.

[0095] Meanwhile, as described above, the crane device (100) may include a main body (170) and a leg structure (180). That is, when the crane device (100) is used at sea, the leg structure (180) is used.

[0096] In that case, referring to FIG. 3, the control unit (190) can perform a process (P1000) of controlling the leg structure (180) to move the leg (180) to a main body fixing position before performing the processes P100 to P500. The main body fixing position is a position where the offshore wind power installation vessel (WTIV) equipped with the crane device (100) is fixed to the floor or raised to a certain height from the sea surface. By performing the process P1000, the offshore wind power installation vessel (WTIV) can be raised to a certain height from the sea surface, thereby reducing the influence of the offshore wind power installation vessel (WTIV) on waves.

[0097] <Other examples>

[0098] Although the embodiments of the technology described herein have been described in detail, this is merely an example of the technology described herein, and those skilled in the art will appreciate that various modifications may be made without departing from the essential characteristics of the technology described herein.

[0099] For example, the technology described herein may be applied to a method of controlling a crane device (100) for a very large wind power generator, the processing performed by the control unit (190) of the crane device (100) for a very large wind power generator described above.

[0100] The features of the crane device (100) for a very large wind power generator according to the technology described herein can also be applied to a method for controlling the crane device (100) for a very large wind power generator according to the technology described herein.

[0101] Therefore, the embodiments described in this specification are intended to illustrate, not limit, the technology described herein, and these embodiments do not limit the spirit or scope of the technology described herein. The scope of the technology described herein should be interpreted by the following claims, and all technologies within the scope equivalent thereto should be construed as being included within the scope of the technology described herein.

[0102] [Explanation of symbols]

[0103] 100: Crane device for ultra-large wind turbines

[0104] 110: 1st hook 115: 2nd hook

[0105] 120: Hook position adjustment structure 130: Crane boom

[0106] 135: Support structure 140: Tower structure

[0107] 141: Tower 1 143: Tower 2

[0108] 145: 1st tower drive unit 150: Crane boom drive structure

[0109] 160: Skidding structure 170: Body

[0110] 180: Leg structure 190: Control unit

[0111] 195: Wind speed meter

[0112] According to the technology described herein, a crane device for an ultra-large wind power generator can be provided in which the overall size can be minimized by using a tower structure having a multi-stage structure, the position of the hook in the x-axis, y-axis, and z-axis directions can be accurately and stably controlled by moving the crane boom using a crane boom drive structure, moving the hook using a hook position adjustment structure, and moving the tower structure using a skidding structure, and the counterweight can be replaced by using the crane boom drive structure.

[0113] According to the technology described herein, it is possible to provide a crane device for an ultra-large wind power generator capable of efficiently, stably and safely installing or maintaining equipment of an ultra-large wind power generator weighing 1,500 tons or more at an altitude of 150 m or more, particularly on land or at sea.

Claims

1. First hook; A hook position adjustment structure including a first hook adjustment unit configured to vertically raise or lower the first hook and adjust a first horizontal position of the first hook; A crane boom having one end connected to the above-mentioned hook position adjustment structure; A tower structure comprising at least a first tower, a second tower, and a first tower drive unit, wherein the first tower drive unit is configured to drive the first tower vertically so that the first tower is positioned between a first tower initial position in which the first tower is stored inside or outside the second tower and a first tower maximum elevation position in which the first tower can vertically ascend from the first tower initial position; A crane boom drive structure connected to the crane boom and the first tower, and driving the crane boom so that the crane boom is positioned between the initial position of the crane boom where the crane boom is stored and the maximum drive position at which the crane boom can be rotated around the other end of the crane boom from the initial position of the crane boom; and A skidding structure connected to the above tower structure and configured to move the tower structure in a second horizontal direction different from the first horizontal direction. Crane device including.

2. In paragraph 1, Including a second hook, A crane device wherein the hook position adjustment structure further includes a second hook adjustment unit configured to raise or lower the second hook in the vertical direction and adjust the position of the second hook in the first horizontal direction.

3. In paragraph 2, A crane device wherein the first hook adjustment unit and the second hook adjustment unit are configured to vertically raise or lower the first hook and the second hook so that the heights of the first hook and the second hook are the same.

4. In paragraph 2, A crane device wherein the first hook adjustment unit and the second hook adjustment unit are configured to adjust the gap between the first hook and the second hook.

5. In paragraph 1, A crane device wherein the first tower is configured to be telescopically extendable to the second tower.

6. In paragraph 1, The above crane boom driving structure is, Cable connected to the above crane boom; a connection structure connected to the first tower; and A winch that drives the first cable through the connection structure Crane device including 7. In paragraph 1, A support structure that is connected to the other end of the crane boom and the first tower, and supports the crane boom and the first tower when the crane boom is driven by the crane boom driving structure. Crane device including more.

8. In paragraph 1, A body having at least the skidding structure arranged thereon and having a rail configured to enable the skidding structure to move the tower structure in the second horizontal direction. Crane device including more.

9. In paragraph 8, A leg structure including a leg arranged on the main body and a leg drive unit configured to raise or lower the leg Crane device including more.

10. In paragraph 8, A crane device in which the above body has a recessed portion arranged between rails.

11. In paragraph 1, A crane device wherein the first horizontal direction and the second horizontal direction are orthogonal.

12. In paragraph 1, The above tower structure is, Further including the third tower and the second tower drive unit, A crane device wherein the second tower drive unit is configured to drive the second tower vertically so that the second tower is positioned between a second tower initial position in which the second tower is stored inside or outside the third tower and a second tower maximum elevation position in which the second tower can vertically ascend from the second tower initial position.

13. In paragraph 12, A crane device in which the second tower is configured to be telescopically extendable to the third tower.

14. In paragraph 1, A control unit configured to perform, based on a control signal, a process of controlling the hook position adjustment structure, the tower structure, the crane boom drive structure, and the skidding structure, (a) a process of moving the crane boom to a crane boom working position between the crane boom initial position and the maximum drive position, (b) a process of moving the first tower to a first tower working position between the first tower initial position and the first tower maximum elevation position, (c) a process of adjusting the position of the first horizontal rectangle of the first hook, (d) a process of raising or lowering the first hook, and (e) a process of moving the tower structure in the second horizontal direction. A crane device further comprising:

15. In paragraph 14, A crane device wherein the above processing (a) is performed while the first tower is positioned at the first tower initial position and the crane boom is positioned at the crane boom initial position.

16. In paragraph 14, The above control unit, (f) processing of moving the first tower from the first tower working position to the first tower initial position; and (g) Process of moving the crane boom from the crane boom working position to the crane boom initial position. A crane device configured to perform further.

17. In paragraph 16, A crane device wherein the above treatment (g) is performed after the above treatment (f).

18. In paragraph 14, Anemometer that measures wind speed Including more, The above control unit is configured to further perform processing of performing processing (a) to processing (e) when the wind speed measured by the wind speed measuring device is lower than a predetermined threshold wind speed.

19. In paragraph 16, Anemometer that measures wind speed Including more, The control unit is configured to further perform processing to generate an alarm signal indicating that the processing (f) and the processing (g) are to be performed when the wind speed measured by the wind speed measuring device exceeds a predetermined threshold wind speed, and output the alarm signal to a predetermined user terminal.

20. In paragraph 14, A main body having at least the skidding structure arranged thereon and having rails for allowing the skidding structure to move the tower structure in the second horizontal direction; and A leg structure including a leg arranged on the main body and a leg drive unit configured to raise or lower the leg Including more, A crane device, wherein the control unit is configured to further perform a process of controlling the leg structure to move the leg to a main body fixing position before performing the processing (a) to the processing (e) above.

Citation Information

Patent Citations

  • Loading and unloading method for large cargo

    JP1998236385A

  • Tower crane

    JP2001180887A

  • System and method for product recommendation that can provide product planning infromation based on natural language processing

    KR1020230158385A

  • Wafer prcessing method

    KR102358688B1

  • Ocean structure for installing offshore wind generator

    KR102436082B1