Energy storage device, energy storage system, and redundancy control method
By introducing redundant control mechanisms and multi-channel communication channels into the energy storage system, the problem of being unable to short-circuit or open circuit when the energy storage device fails is solved, improving the reliability and stability of the system and ensuring the normal operation of the system in the event of a fault. run.
Patent Information
- Application Number
- PCT/CN2024/088219
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-04-17
- Filing Date
- 2024-04-17
- Publication Date
- 2024-10-24
AI Technical Summary
The existing cascade energy storage system cannot effectively short-circuit or open the circuit when the energy storage device fails, resulting in low reliability and stability of system operation.
By introducing a redundant control mechanism into the energy storage device and utilizing multi-channel communication channels and dual-channel optical fiber technology, redundant control between the first controller and the second controller is achieved to ensure that the switch can still be controlled normally under fault conditions. , improve the reliability and stability of system communication.
It effectively improves the operational reliability and stability of the energy storage system, ensures that the system can still operate normally under fault conditions, and reduces the occurrence of communication failures.
Smart Images

Figure CN2024088219_24102024_PF_FP_ABST
Abstract
Description
Energy storage device, energy storage system and redundant control method
[0001] This application claims priority to the Chinese patent application filed with the China Patent Office on April 17, 2023, with application number 202310410524.7 and invention name “Energy Storage Device, Energy Storage System and Redundant Control Method”, the entire contents of which are incorporated by reference into this application. Technical Field
[0002] The present application relates to the field of energy storage, and in particular to an energy storage device, an energy storage system, and a redundant control method. Background Art
[0003] Energy storage refers to the process of storing energy through a medium or device and releasing it when needed. Existing cascade energy storage systems consist of multiple energy storage devices connected in series. When a storage device fails, the power module of that device must be short-circuited and the battery module within that device must be disconnected to ensure normal operation of the energy storage system. However, if the power module of the failed energy storage device cannot be short-circuited or the battery module cannot be disconnected, the fault will escalate, causing the energy storage system to shut down. Existing energy storage systems suffer from low reliability and stability. Technical issues
[0004] The present application provides an energy storage device, an energy storage system, and a redundant control method, which effectively improve the stability and reliability of the operation of the energy storage system. Technical Solutions
[0005] The present application provides an energy storage device, an energy storage system, and a redundant control method, which effectively improve the stability and reliability of the operation of the energy storage system.
[0006] To achieve the above objectives, this application adopts the following technical solutions:
[0007] In a first aspect, an energy storage device is provided, comprising a power module and a battery module;
[0008] The power module includes a first switch and a first controller for controlling the first switch;
[0009] The battery module includes a second switch and a second controller for controlling the second switch;
[0010] The first controller is connected to the first switch and the second controller respectively, and the second controller is connected to the second switch.
[0011] In an embodiment of the present application, the first controller is connected to the second controller, so that the first controller can obtain the status of the second switch detected by the second controller and control the second switch, and the second controller can obtain the status of the first switch detected by the first controller and control the first switch, thereby realizing redundant control of the first switch and the second switch by the first controller and the second controller, effectively improving the reliability of communication of the energy storage system, thereby improving the reliability and stability of the operation of the energy storage system.
[0012] In a possible implementation manner of the first aspect, the first controller is further connected to the second switch.
[0013] In this embodiment of the present application, the first controller can directly obtain the status of the second switch and control it without having to rely on the second controller. If the second controller fails or the connection between the second controller and the second switch is interrupted, the first controller can obtain the status of the second switch and control it. This improves the reliability of energy storage system communication.
[0014] In a possible implementation manner of the first aspect, the first controller is connected to the first switch and the second switch respectively through multiple communication channels.
[0015] Compared with the single-channel communication method, the multi-channel communication method has higher communication reliability.
[0016] In a possible implementation manner of the first aspect, the second controller is further connected to the first switch.
[0017] In this embodiment of the present application, the second controller can directly obtain the status of the first switch, without having to rely on the first controller, and can directly control the first switch. If the first controller fails or the connection between the first controller and the first switch is interrupted, the second controller can obtain the status of the first switch and control it. This improves the reliability of energy storage system communication.
[0018] In a possible implementation manner of the first aspect, the second controller is connected to the first switch and the second switch respectively through multiple communication channels.
[0019] Compared with the single-channel communication method, the multi-channel communication method has higher communication reliability.
[0020] In a possible implementation manner of the first aspect, the multi-path communication channel is a dual-path optical fiber.
[0021] Using dual optical fibers as the transmission channel between the controller and the switch can improve the reliability and stability of communication while reducing communication costs.
[0022] In a second aspect, an energy storage system is provided, comprising a third controller and at least one energy storage device according to any one of the first aspects;
[0023] The third controller is connected to the first controller in the energy storage device.
[0024] The energy storage system in the embodiment of the present application implements redundant control of the first switch and the second switch by the first controller and the second controller, effectively improving the reliability of communication of the energy storage system, thereby improving the reliability and stability of the operation of the energy storage system.
[0025] In a possible implementation manner of the second aspect, the third controller is further connected to the second controller in the energy storage device.
[0026] In the embodiment of the present application, the second controller can not only report the switch status to the third controller through the first controller, but also directly report the switch status to the third controller. In this way, when there is a communication failure between the first controller and the third controller, or a communication failure between the first controller and the second controller, the third controller can still obtain the switch information through the second controller and control the switch to be closed / opened through the second controller; in the case of a communication failure between the second controller and the third controller, or a communication failure between the first controller and the second controller, the third controller can still obtain the switch information through the first controller and control the switch to be closed / opened through the first controller. The redundant control of the first controller and the second controller by the third controller can further improve the success rate of communication, thereby further improving the reliability and stability of the energy storage system operation.
[0027] In a possible implementation manner of the second aspect, the energy storage system further includes a background management system; and the background management system is connected to the third controller.
[0028] The backend management system takes over the energy storage system, which helps to ensure the reliable operation of the energy storage system and improve management efficiency.
[0029] In a possible implementation manner of the second aspect, the background management system is connected to the first controller in the energy storage device, or is connected to the second controller in the energy storage device.
[0030] In the embodiment of the present application, redundant control of the first controller and the second controller in each energy storage device by the background management system can further improve the success rate of communication, thereby further improving the reliability and stability of the energy storage system operation.
[0031] In a possible implementation manner of the second aspect, the first controllers in any two energy storage devices in the energy storage system are connected.
[0032] Through the redundant control between the above energy storage devices, the success rate of communication can be further improved, thereby further improving the reliability and stability of the energy storage system operation.
[0033] In a third aspect, a redundancy control method is provided, applied to the energy storage system according to any one of the second aspects, the method comprising:
[0034] Acquire a first switch signal of a target switch detected by the first controller;
[0035] Acquire a second switch signal of a target switch detected by the second controller;
[0036] determining a switching state of the target switch according to the first switching signal and the second switching signal;
[0037] A control instruction for controlling the target switch is determined according to the switch state of the target switch.
[0038] In the redundant control method provided by the embodiments of the present application, a first switch signal of a target switch detected by a first controller and a second switch signal of the target switch detected by a second controller are mutually redundant information. The first switch signal and the second switch signal are then used to determine the switch state of the target switch. This method effectively improves the reliability of the detection results, thereby enhancing the reliability and stability of the energy storage system's operation, by determining the final switch state based on the redundant information in the event of a communication failure between the first or second controller.
[0039] In a possible implementation manner of the third aspect, before determining the switching state of the target switch according to the first switching signal and the second switching signal, the method further includes:
[0040] When the first switch signal and / or the second switch signal is abnormal, determining the switch state of the target switch to be a preset state;
[0041] In a case where both the first switching signal and the second switching signal are normal, a step of determining the switching state of the target switch according to the first switching signal and the second switching signal is performed.
[0042] In a possible implementation of the third aspect, determining the switch state of the target switch as a preset state includes:
[0043] When the target switch is the first switch, determining the switch state of the target switch to be an off state;
[0044] When the target switch is the second switch, the switch state of the target switch is determined to be a closed state.
[0045] In the above implementation, the first and second switch signals are first detected for abnormalities, and then the target switch state is determined based on the abnormality detection results. When both the first and second switch signals are normal, the first and second switch signals contain identical information, and either one can be determined as the target switch state. When the first and / or second switch signals are abnormal, the switch states of different switches are determined according to different pre-set conditions. This approach allows detection of the normal switch state regardless of whether the first and second switch signals are normal, improving detection efficiency and reliability.
[0046] In a possible implementation of the third aspect, determining the switching state of the target switch according to the first switching signal and the second switching signal includes:
[0047] performing a logic calculation according to the first switching signal and the second switching signal to obtain a calculation result;
[0048] The switch state of the target switch is determined according to the calculation result.
[0049] In a possible implementation of the third aspect, performing a logic calculation based on the first switching signal and the second switching signal to obtain a calculation result includes:
[0050] In a case where the multi-channel communication channel is a dual-channel optical fiber, performing an AND operation on two first signal values included in the first switch signal to obtain a first logic signal;
[0051] performing an AND operation on two second signal values included in the second switch signal to obtain a second logic signal;
[0052] An OR operation is performed on the first logic signal and the second logic signal to obtain the calculation result.
[0053] In the embodiment of the present application, the switch state of the target switch can be determined by simply performing an AND operation and an OR operation on the first switch signal and the second switch signal, which greatly improves the efficiency of determining the switch state of the target switch and facilitates timely control in the event of a system failure.
[0054] In a possible implementation of the third aspect, performing an AND operation on two first signal values included in the first switch signal to obtain the first logic signal includes:
[0055] performing an AND operation on the first first signal value and the negated value of the second first signal value to obtain a first calculated value in the first logic signal;
[0056] performing an AND operation on the inverted value of the first signal value and the second signal value to obtain a second calculated value of the first logic signal;
[0057] The performing an AND operation on two second signal values included in the second switch signal to obtain a second logic signal includes:
[0058] performing an AND operation on the first second signal value and the inverted value of the second signal value to obtain a third calculated value of the second logic signal;
[0059] performing an AND operation on the inverted value of the first second signal value and the second second signal value to obtain a fourth calculated value of the second logic signal;
[0060] The performing an OR operation on the first logic signal and the second logic signal to obtain the calculation result includes:
[0061] Performing an OR operation on the first calculated value and the third calculated value to obtain a fifth calculated value in the calculation result;
[0062] Performing an OR operation on the second calculated value and the fourth calculated value to obtain a sixth calculated value in the calculation result;
[0063] The performing an OR operation on the first logic signal and the second logic signal to obtain the calculation result includes:
[0064] The switching state of the target switch is determined according to the fifth calculated value and the sixth calculated value.
[0065] In the above manner, whether the dual optical fiber is faulty can be determined based on the first calculated value, the second calculated value, the third calculated value, and the fourth calculated value. This is equivalent to first performing an abnormality detection on the first switch signal and the second switch signal, so that the faulty communication line can be detected, thereby determining the normal switching state.
[0066] In a possible implementation of the third aspect, determining the switch state of the target switch according to the fifth calculated value and the sixth calculated value includes:
[0067] The fifth calculated value and the sixth calculated value are calculated according to a preset trigger to obtain the switch state of the target switch.
[0068] In a possible implementation of the third aspect, calculating the fifth calculated value and the sixth calculated value according to a preset trigger to obtain the switch state of the target switch includes:
[0069] performing delay processing on the fifth calculated value and the sixth calculated value respectively;
[0070] The fifth calculated value after the delay processing and the sixth calculated value after the delay processing are calculated according to the preset trigger to obtain the switch state of the target switch.
[0071] By adding delay processing, the fifth calculated value and the sixth calculated value can be ensured to be input into the RS trigger synchronously, effectively avoiding the problem of the time when the fifth calculated value is input into the RS trigger and the time when the sixth calculated value is input into the RS trigger being out of sync, thereby effectively improving the detection reliability of the third state information.
[0072] In a possible implementation manner of the third aspect, the preset trigger is an RS trigger. BRIEF DESCRIPTION OF THE DRAWINGS
[0073] FIG1 is a schematic structural diagram of an energy storage device provided in an embodiment of the present application;
[0074] FIG2 is a schematic structural diagram of an energy storage device provided in another embodiment of the present application;
[0075] FIG3 is a schematic diagram of a dual-path optical fiber provided in an embodiment of the present application;
[0076] FIG4 is a schematic diagram of an energy storage system provided in an embodiment of the present application;
[0077] FIG5 is a schematic diagram of an energy storage system provided by another embodiment of the present application;
[0078] FIG6 is a flow chart of a redundancy control method according to an embodiment of the present application;
[0079] FIG7 is a schematic diagram of a logic circuit provided in an embodiment of the present application;
[0080] FIG8 is a schematic diagram of a logic circuit provided in another embodiment of the present application;
[0081] FIG9 is a schematic diagram of an RS trigger provided in an embodiment of the present application;
[0082] FIG10 is a schematic diagram of a logic circuit provided in another embodiment of the present application;
[0083] 11-16 are schematic structural diagrams of an energy storage device provided in another embodiment of the present application. Modes for Carrying Out the Invention
[0084] In the following description, specific details such as specific system structures and techniques are provided for purposes of illustration rather than limitation to facilitate a thorough understanding of the embodiments of the present application. However, it will be apparent to those skilled in the art that the present application may be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to avoid obscuring the description of the present application with unnecessary detail.
[0085] It should be understood that when used in the present specification and the appended claims, the term "comprising" indicates the presence of described features, integers, steps, operations, elements and / or components, but does not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or collections thereof.
[0086] It will also be understood that the term "and / or" used in this specification and the appended claims refers to and includes any and all possible combinations of one or more of the associated listed items.
[0087] As used in this specification and the appended claims, the term "if" can be interpreted as "when" or "upon" or "in response to determining" or "in response to detecting," depending on the context. Similarly, the phrase "if it is determined" or "if [described condition or event] is detected" can be interpreted as meaning "upon determination" or "in response to determining" or "upon detection of [described condition or event]" or "in response to detecting [described condition or event]," depending on the context.
[0088] In addition, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.
[0089] References to "one embodiment" or "some embodiments" in this specification mean that a particular feature, structure, or characteristic described in conjunction with the embodiment is included in one or more embodiments of the present application. Thus, phrases such as "in one embodiment," "in some embodiments," "in other embodiments," and "in yet other embodiments" appearing in various places in this specification do not necessarily refer to the same embodiment, but rather mean "one or more but not all embodiments," unless otherwise specifically emphasized.
[0090] Energy storage refers to the process of storing energy through a medium or device and releasing it when needed. Existing cascade energy storage systems consist of multiple energy storage devices connected in series. When a storage device fails, the power module of that device must be short-circuited and the battery module within that device must be disconnected to ensure normal operation of the energy storage system. However, if the power module of the failed energy storage device cannot be short-circuited or the battery module cannot be disconnected, the fault will escalate, causing the energy storage system to shut down. Existing energy storage systems suffer from low reliability and stability.
[0091] To address the above issues, embodiments of the present application provide an energy storage device, an energy storage system, and a redundant control method. In these embodiments, the first and second controllers of each energy storage device are capable of redundantly controlling the first and second switches, effectively improving the reliability of energy storage system communications and thereby improving the reliability and stability of the energy storage system's operation.
[0092] First, the energy storage device provided in the embodiment of the present application is introduced. Referring to FIG1 , which is a schematic structural diagram of the energy storage device provided in the embodiment of the present application. As an example and not a limitation, as shown in FIG1 , the energy storage device includes a power module and a battery module. The power module is used to charge the battery module to provide electrical energy to the battery module, thereby converting part of the grid power into electrical energy in the battery module; and during peak hours or when the external grid is interrupted, the power module can receive the electrical energy released by the battery module and convert it into the AC grid to compensate for the grid power.
[0093] The power module includes a first switch and a first controller for controlling the first switch, and the battery module includes a second switch and a second controller for controlling the second switch. The first controller is connected to the first switch and the second controller respectively, and the second controller is connected to the second switch.
[0094] For example, the first switch is a bypass switch, and the first controller is a sub-module management controller (SMC); the second switch is a bus switch, and the second controller is a battery management controller (BMC). The SMC is connected to the bypass switch and the BMC, respectively, and the BMC is connected to the bus switch. When the bypass switch is closed, the power module is in a short-circuit state; when the bus switch is closed and the bypass switch is open, the battery module is in a charging and discharging state.
[0095] It should be noted that, for ease of description, the following embodiments of this application use an SMC as the first controller and a BMC as the second controller as an example. In actual applications, the first and second controllers may also be other controllers capable of transmitting information and issuing control instructions. The names and models of the first, second, and third controllers are not specifically limited in the embodiments of this application.
[0096] In an embodiment of the present application, the first controller is connected to the second controller, so that the first controller can obtain the status of the second switch detected by the second controller and control the second switch, and the second controller can obtain the status of the first switch detected by the first controller and control the first switch, thereby realizing redundant control of the first switch and the second switch by the first controller and the second controller, effectively improving the reliability of communication of the energy storage system, thereby improving the reliability and stability of the operation of the energy storage system.
[0097] In some embodiments, the first controller is further connected to the second switch.
[0098] In this embodiment of the present application, the first controller can directly obtain the status of the second switch and control it without having to rely on the second controller. If the second controller fails or the connection between the second controller and the second switch is interrupted, the first controller can obtain the status of the second switch and control it. This improves the reliability of energy storage system communication.
[0099] In some embodiments, a second controller is further connected to the first switch.
[0100] In this embodiment of the present application, the second controller can directly obtain the status of the first switch, without having to rely on the first controller, and can directly control the first switch. If the first controller fails or the connection between the first controller and the first switch is interrupted, the second controller can obtain the status of the first switch and control it. This improves the reliability of energy storage system communication.
[0101] For example, see Figure 2, which is a schematic structural diagram of an energy storage device provided in another embodiment of the present application. Compared with Figure 1, the energy storage device shown in Figure 2 adds a connection channel between the first controller and the second switch, and a connection channel between the second controller and the first switch. In the event of a communication failure between the first controller and the first switch, the second controller can still obtain the state of the first switch; in the event of a communication failure between the second controller and the second switch, the first controller can still obtain the state of the second switch. The energy storage device shown in the embodiment of Figure 2 can improve the success rate of communication through the cross-control of the first switch and the second switch by the first controller and the second controller, thereby improving the reliability and stability of the operation of the energy storage system.
[0102] In some embodiments, the first controller is connected to the first switch and the second switch through multiple communication channels. The second controller is connected to the first switch and the second switch through multiple communication channels.
[0103] Multi-channel communication refers to a communication method that uses a common channel to establish two or more independent transmission channels. Because multi-channel communication channels include multiple independent transmission channels, if one or more transmission channels fail, the other independent transmission channels can still transmit signals normally. Therefore, compared with single-channel communication, multi-channel communication has higher communication reliability.
[0104] Optionally, the multi-channel communication channel is a dual-channel optical fiber.
[0105] Fiber optics, short for optical fiber, are fibers made of glass or plastic that conduct light. Fiber optic transmission offers advantages such as wide bandwidth, low loss, and strong anti-interference capabilities. Therefore, using dual optical fibers as the transmission path between the controller and the switch can improve communication reliability and stability while reducing communication costs.
[0106] Refer to Figure 3, which is a schematic diagram of a dual-path optical fiber provided in an embodiment of the present application. As shown in Figure 3, the dual-path optical fiber includes an optical fiber channel 1 and an optical fiber channel 2. The left figure in Figure 3 shows the switch closed state, and the two optical fibers output 1 and 0 respectively. Among them, optical fiber channel 1 is closed, indicating that there is light, and the corresponding output signal is 1; optical fiber channel 2 is disconnected, indicating that there is no light, and the corresponding output signal is 0. The right figure in Figure 3 shows the switch open state, and the two optical fibers output 0 and 1 respectively. Among them, optical fiber channel 1 is disconnected, indicating that there is no light, and the corresponding output signal is 0; optical fiber channel 2 is closed, indicating that there is light, and the corresponding output signal is 1. When the optical fiber with light fails (output 0), the output signal is 00; when the optical fiber without light fails (output 1), the output signal is 11. That is, when the output signal is 00 or 11, it is a double dislocation, that is, the two optical fiber channels are disconnected or closed at the same time, indicating a signal abnormality.
[0107] Since the output of a single optical fiber is only 0 or 1, it is impossible to determine whether the signal is abnormal. Therefore, compared with a single optical fiber, using dual optical fibers to detect the switch state is more conducive to identifying abnormal signal states, thereby improving the reliability of switch state detection.
[0108] Based on the above-described energy storage device, an embodiment of the present application provides an energy storage system. See Figure 4, which is a schematic diagram of the energy storage system provided in an embodiment of the present application. As shown in Figure 4, by way of example and not limitation, the energy storage system includes a third controller and at least one energy storage device as described in the embodiment of Figures 1 or 2 above. The third controller is connected to the first controller of the energy storage device.
[0109] Exemplarily, the third controller is a valve base controller (VBC). In some application scenarios, the SMC in each energy storage device detects the status of the bypass switch and reports it to the VBC; the BMC detects the status of the busbar switch and reports it to the VBC via the SMC; the VBC generates a control instruction based on the received status and sends it to the SMC; the SMC controls the bypass switch to close / open according to the control instruction and transmits the control instruction to the BMC; the BMC controls the busbar switch to close / open according to the received control instruction.
[0110] The energy storage system in the embodiment of the present application implements redundant control of the first switch and the second switch by the first controller and the second controller, effectively improving the reliability of communication of the energy storage system, thereby improving the reliability and stability of the operation of the energy storage system.
[0111] In some embodiments, the third controller is further connected to the second controller in the energy storage device.
[0112] In an embodiment of the present application, redundant control of the first controller and the second controller by the third controller is implemented. Specifically, the second controller can not only report the switch status to the third controller through the first controller, but also report the switch status directly to the third controller. The third controller can send control instructions to the second controller through the first controller, or can send control instructions directly to the second controller. In this way, when there is a communication failure between the first controller and the third controller, or a communication failure between the first controller and the second controller, the third controller can still obtain the switch information through the second controller, and control the switch to be closed / disconnected through the second controller; in the case of a communication failure between the second controller and the third controller, or a communication failure between the first controller and the second controller, the third controller can still obtain the switch information through the first controller, and control the switch to be closed / disconnected through the first controller. Redundant control of the first controller and the second controller by the third controller can further improve the success rate of communication, thereby further improving the reliability and stability of the operation of the energy storage system.
[0113] In some embodiments, the energy storage system further includes a background management system connected to the third controller.
[0114] In some application scenarios, when the energy storage system includes multiple VBCs, the backend management system communicates with each VBC separately. During the control process, the SMC and BMC report switch status to the VBC, which then reports the switch status to the backend management system. The backend management system then issues control instructions to the VBC based on the switch status. The VBC then sends these instructions to the SMC and BMC. The SMC and BMC control the corresponding switches to close or open according to the control instructions.
[0115] It's understandable that the backend management system serves as the "brain" of the energy storage system. It manages and controls each energy storage device within the system through the VBC. In some application scenarios, the VBC can also manage and control the energy storage system. However, energy storage systems are typically large, and the VBC is often unable to handle such a large management task. Having the backend management system take over the energy storage system helps ensure reliable operation and improve management efficiency.
[0116] In some embodiments, the background management system is connected to the first controller in the energy storage device, or is connected to the second controller in the energy storage device.
[0117] In one implementation, the background management system is connected to the first controller but not to the second controller.
[0118] In another implementation, the background management system is connected to the second controller but not to the first controller.
[0119] In a third implementation manner, the background management system is connected to the first controller and the second controller respectively.
[0120] For example, see Figure 5, which is a schematic diagram of an energy storage system provided by another embodiment of the present application. In the energy storage system shown in Figure 5, the first controller and the second controller can not only report the switch status to the background management system through the third controller, but the first controller and the second controller can also report the switch status directly to the background management system; similarly, the background management system can not only issue control instructions to the first controller and the second controller through the third controller, but can also issue control instructions directly to the first controller and the second controller. In this way, in the event of a communication failure between the first controller and the second controller, or a communication failure between the second controller and the third controller, or a communication failure between the third controller and the background management system, the background management system and the first controller and the second controller can communicate directly, and can still obtain switch information through the first controller and the second controller, and control the switch to be closed / opened through the first controller and the second controller. The energy storage device shown in the embodiment of Figure 5 can further improve the success rate of communication through the redundant control of the first controller and the second controller in each energy storage device by the background management system, thereby further improving the reliability and stability of the operation of the energy storage system.
[0121] In some embodiments, the first controllers in any two of the energy storage devices in the energy storage system are connected.
[0122] In this way, redundant control between energy storage devices is achieved. For example, the SMC of energy storage device 1 and the SMC of energy storage device 2 are in communication connection. In the event of a communication failure between the SMC of energy storage device 1 and the VBC, the SMC of energy storage device 2 can obtain the switch status of energy storage device 1 and upload the switch status to the VBC; similarly, the VBC can send the control instructions of energy storage device 1 to the SMC of energy storage device 1 through the SMC of energy storage device 2, thereby achieving switch control of energy storage device 1. Through the above-mentioned redundant control between energy storage devices, the success rate of communication can be further improved, thereby further improving the reliability and stability of the energy storage system operation.
[0123] Optionally, in actual applications, in order to improve communication efficiency and reduce communication failure rate, the SMCs in two adjacent energy storage devices in the energy storage system can be connected in communication.
[0124] Based on the energy storage system provided in the above embodiment, the present application provides a redundant control method. Referring to FIG6 , which is a flow chart of the redundant control method provided in the present application embodiment. As an example and not a limitation, as shown in FIG6 , the redundant control method includes the following steps:
[0125] S601: Acquire a first switch signal of a target switch detected by the first controller.
[0126] S602: Acquire a second switch signal of a target switch detected by the second controller.
[0127] S603: Determine a switching state of the target switch according to the first switching signal and the second switching signal.
[0128] S604: Determine a control instruction for controlling the target switch according to the switch state of the target switch.
[0129] In one embodiment, the execution entity of the above method can be a first controller, the target switch is the first switch, and S601-S604 are specifically: the first controller detects the first switch signal of the first switch, and the second controller detects the second switch signal of the first switch; the second controller sends the second switch signal of the first switch to the first controller; the first controller determines the switching state of the first switch according to the first switching signal and the second switching signal of the first switch, and determines the control instruction of the target switch according to the switching state of the first switch.
[0130] In one embodiment, the execution entity of the above method can be the first controller, the target switch is the second switch, and S601-S604 are specifically: the first controller detects the first switch signal of the second switch, and the second controller detects the second switch signal of the second switch; the second controller sends the second switch signal of the second switch to the first controller; the first controller determines the switch state of the second switch according to the first switch signal and the second switch signal of the bypass switch, and determines the control instruction of the second switch according to the switch state of the second switch.
[0131] In one embodiment, the execution entity of the above method can be a second controller, and the target switch is the first switch. S601-S604 are specifically as follows: the first controller detects a first switch signal of the first switch and sends first state information of the first switch to the second controller; the second controller detects a second switch signal of the first switch, and determines the switch state of the first switch based on the first switch signal and the second switch signal of the first switch, and then determines a control instruction of the first switch based on the switch state of the first switch.
[0132] In one embodiment, the execution entity of the above method can be a second controller, and the target switch is the second switch. S601-S604 are specifically as follows: the first controller detects the first switch signal of the second switch and sends the first switch signal of the second switch to the second controller; the second controller detects the second switch signal of the second switch, and determines the switching state of the second switch based on the first switch signal and the second switch signal of the second switch, and then determines the control instruction of the second switch based on the switching state of the second switch.
[0133] In some embodiments, S604 may also be executed by a third controller. For example, when the first controller executes S601-S603, the first controller uploads the switch state of the target switch to the third controller, and the third controller determines a control instruction for controlling the target switch based on the switch state of the target switch.
[0134] In the redundant control method provided by the embodiments of the present application, a first switch signal of a target switch detected by a first controller and a second switch signal of the target switch detected by a second controller are mutually redundant information. The first switch signal and the second switch signal are then used to determine the switch state of the target switch. This method effectively improves the reliability of the detection results, thereby enhancing the reliability and stability of the energy storage system's operation, by determining the final switch state based on the redundant information in the event of a communication failure between the first or second controller.
[0135] Optionally, one implementation of S603 is: when the first switch signal and the second switch signal are consistent, determining the first switch signal or the second switch signal as the switch state of the target switch; and when the first switch signal and the second switch signal are inconsistent, determining the preset state as the switch state of the target switch.
[0136] The preset state may be a pre-set state value. For example, the preset state is 00. When the first switch signal and the second switch signal are inconsistent, 00 is determined as the switch state of the target switch. Since 00 is an abnormal state, when the first switch signal and the second switch signal are inconsistent, the switch state of the target switch is determined to be an abnormal state. The first switch signal or the second switch signal may also be pre-designated as the preset state. For example, if the first switch signal is pre-designated as the preset state, then when the first switch signal and the second switch signal are inconsistent, regardless of whether the first switch signal and the second switch signal are inconsistent, the first switch signal is determined as the switch state of the target switch.
[0137] The above implementation is logically simple and easy to implement, but it has the following problems: when the first and second signals match and both indicate abnormality, the target switch's state is also abnormal. Conversely, when the first and second signals disagree, the target switch's state may also be abnormal because it's unknown which state is abnormal. Therefore, this approach fails to detect the normal switch state, requiring further manual testing, which is time-consuming and labor-intensive, resulting in low detection efficiency.
[0138] To solve the above problem, in one embodiment, before determining the switching state of the target switch according to the first switching signal and the second switching signal, the redundancy control method further includes:
[0139] When the first switch signal and / or the second switch signal is abnormal, determining the switch state of the target switch to be a preset state;
[0140] In a case where both the first switching signal and the second switching signal are normal, a step of determining the switching state of the target switch according to the first switching signal and the second switching signal is performed.
[0141] Among them, the abnormality of the first switch signal and / or the second switch signal includes the following situations: in the first situation, the first switch signal is abnormal and the second switch signal is normal; in the second situation, the first switch signal is normal and the second switch signal is abnormal; in the third situation, both the first switch signal and the second switch signal are abnormal.
[0142] In one embodiment, determining the switch state of the target switch as a preset state includes:
[0143] When the target switch is the first switch, determining the switch state of the target switch to be an off state;
[0144] When the target switch is the second switch, the switch state of the target switch is determined to be a closed state.
[0145] In the above implementation, the first and second switch signals are first detected for abnormalities, and then the switch state of the target switch is determined based on the abnormality detection results. When both the first and second switch signals are normal, the first and second switch signals contain the same information, and either one can be determined as the switch state of the target switch. When the first and / or second switch signals are abnormal, the switch states of different switches are determined according to different pre-set conditions. Through the above method, the normal switch state can be detected regardless of whether the first and second switch signals are normal, thereby improving detection efficiency and reliability.
[0146] In one embodiment, determining the switching state of the target switch according to the first switching signal and the second switching signal includes:
[0147] Performing a logic calculation based on the first switch signal and the second switch signal to obtain a calculation result; and determining the switch state of the target switch based on the calculation result.
[0148] Alternatively, the logic calculation can be implemented through a software program or a hardware logic circuit. Compared with software implementation, hardware logic circuits are more reliable and stable, and are more conducive to the stability of the energy storage system.
[0149] In one embodiment, when the multi-channel communication channel is a dual-channel optical fiber, performing a logical calculation based on the first switch signal and the second switch signal to obtain a calculation result includes:
[0150] An AND operation is performed on the two first signal values included in the first switching signal to obtain a first logic signal; an AND operation is performed on the two second signal values included in the second switching signal to obtain a second logic signal; and an OR operation is performed on the first logic signal and the second logic signal to obtain the calculation result.
[0151] The first signal value is a signal value of a two-way optical fiber between the first controller and the target switch, and the second signal value is a signal value of a two-way optical fiber between the second controller and the target switch.
[0152] Taking the dual-fiber shown in Figure 4 as an example, assuming the target switch is the first switch, when the first switch is disconnected and both the first and second controllers are communicating normally (both fiber channel signals are normal), the first switch signal is 01 (fiber channel 1 is disconnected, fiber channel 2 is closed), and the second switch signal is 01. If the first switch is disconnected and the first controller is communicating normally, but the second controller has a communication failure, the first switch signal is 01, and the second switch signal is 00 (fiber channel 2 is abnormal) or 11 (fiber channel 1 is abnormal). If the first switch is disconnected, the first controller has a communication failure, and the second controller has normal communication, the first switch signal is 00 or 11, and the second switch signal is 01.
[0153] When the first switch is closed and both the first and second controllers are communicating normally, the first switch signal is 10 (fiber channel 1 is closed, fiber channel 2 is disconnected), and the second switch signal is also 10. When the first switch is closed and the first controller is communicating normally, but the second controller is communicating abnormally, the first switch signal is 10, and the second switch signal is 00 or 11. When the first switch is closed and the first controller is communicating abnormally but the second controller is communicating normally, the first switch signal is 00 or 11, and the second switch signal is 10.
[0154] The above method can be implemented by a logic circuit. See Figure 7, which is a schematic diagram of a logic circuit provided in an embodiment of the present application. As shown in Figure 7, the two first signal values are SMC_CL and SMC_OP, and the two second signal values are BMC_CL and BMC_OP.
[0155] "AND" indicates an AND gate, and "OR" indicates an OR gate. B_CL indicates the switch state of the target switch.
[0156] It should be noted that the above is only an example for dual-channel fiber optic communication. When multiple communication channels are used, the calculation logic also changes accordingly. The embodiments of this application do not specifically limit the specific calculation logic. In addition, in actual applications, an AND operation can be implemented using a single AND gate device, or a combination of several devices. Similarly, an OR operation can be implemented using a single OR gate device, or a combination of several devices.
[0157] In the embodiment of the present application, the switch state of the target switch can be determined by simply performing an AND operation and an OR operation on the first switch signal and the second switch signal, which greatly improves the efficiency of determining the switch state of the target switch and facilitates timely control in the event of a system failure.
[0158] In one embodiment, when the multi-channel communication channel is a dual-channel optical fiber, performing a logical calculation based on the first switch signal and the second switch signal to obtain a calculation result includes:
[0159] performing an AND operation on the first first signal value and the negated value of the second first signal value to obtain a first calculated value in the first logic signal;
[0160] performing an AND operation on the inverted value of the first signal value and the second signal value to obtain a second calculated value of the first logic signal;
[0161] performing an AND operation on the first second signal value and the inverted value of the second signal value to obtain a third calculated value of the second logic signal;
[0162] performing an AND operation on the inverted value of the first second signal value and the second second signal value to obtain a fourth calculated value of the second logic signal;
[0163] Performing an OR operation on the first calculated value and the third calculated value to obtain a fifth calculated value in the calculation result;
[0164] Performing an OR operation on the second calculated value and the fourth calculated value to obtain a sixth calculated value in the calculation result;
[0165] The switching state of the target switch is determined according to the fifth calculated value and the sixth calculated value.
[0166] The above method can also be implemented using a logic circuit. See Figure 8, which is a schematic diagram of a logic circuit provided in another embodiment of the present application. As shown in Figure 8, SIG1 represents the first calculated value, SIG2 represents the second calculated value, SIG3 represents the third calculated value, SIG4 represents the fourth calculated value, SIG5 represents the fifth calculated value, and SIG6 represents the sixth calculated value. "LG" represents a logical operation, and B_CL represents the switch state of the target switch.
[0167] In the embodiment of the present application, the LG is used to implement a process of determining the switch state of a target switch based on the fifth calculated value and the sixth calculated value. Specifically, the LG can determine the switch state of the target switch based on the fifth calculated value and the sixth calculated value according to different situations. For example, when the first switch signal and / or the second switch signal are abnormal, the switch state of different switches can be determined according to different pre-set conditions.
[0168] If the dual optical fibers corresponding to the first controller are double-faulted, the two first signal values are identical, resulting in both the first calculated value and the second calculated value being 0. If the dual optical fibers corresponding to the first controller are functioning normally, the two first signal values are different, resulting in both the first calculated value and the second calculated value being 1. The dual optical fibers corresponding to the second controller operate in the same manner. Therefore, the aforementioned logic circuit can determine whether the dual optical fibers are faulty based on the first, second, third, and fourth calculated values. This is equivalent to first detecting an anomaly in the first and second switching signals, thereby detecting the faulty communication line and determining a normal switching state.
[0169] In one embodiment, determining the switch state of the target switch according to the fifth calculated value and the sixth calculated value includes:
[0170] The fifth calculated value and the sixth calculated value are calculated according to a preset trigger to obtain the switch state of the target switch.
[0171] Optionally, the preset trigger is an RS trigger.
[0172] The RS trigger includes an R input terminal and an S input terminal, and includes a Q output terminal and a Q' output terminal, wherein Q is negated to obtain Q'. Referring to Figure 9, it is a schematic diagram of the RS trigger provided in an embodiment of the present application. As shown in Figure 9, the RS trigger includes two NAND gates 91. The logic of the RS trigger is: when S=1, R=0, the SR trigger will be set, Q=1, Q'=0; when S=0, R=1, the SR trigger will be reset, Q=0, Q'=1; when S=1, R=1, Q=0, Q'=1, and the state of the previous moment remains unchanged; when S=0, R=0, the SR trigger is in an uncertain state.
[0173] In practical applications, in the event of a double optical fiber misalignment, the bypass switch is determined to be open and the busbar switch is determined to be closed. This prevents misjudgments of power module short circuits or battery module disconnection due to communication failures. To achieve this, in one embodiment, when the target switch is a bypass switch, the RS trigger uses R priority (reset priority); when the target switch is a busbar switch, the RS trigger uses S priority (set priority).
[0174] It will be appreciated that the above is only one implementation of LG. In practical applications, other logic devices with similar functions, or logic circuits composed of multiple devices capable of achieving similar functions, may also be used. For example, the aforementioned RS flip-flop may also be composed of two NOR gates. As another example, LG may be implemented using a JK flip-flop. LG may also be implemented via software, that is, by using a processor with logical operation capabilities, simply by compiling the logic code within the processor. This application does not specifically limit the implementation of LG.
[0175] In actual applications, there may be communication delays, that is, the time when the fifth signal value inputs the RS trigger and the time when the sixth signal value inputs the RS trigger are not synchronized, which will cause the third state information output by the RS trigger to be wrong.
[0176] To solve the above problem, in one embodiment, calculating the fifth calculated value and the sixth calculated value according to a preset trigger to obtain the switch state of the target switch includes:
[0177] performing delay processing on the fifth calculated value and the sixth calculated value respectively;
[0178] The fifth calculated value after the delay processing and the sixth calculated value after the delay processing are calculated according to the preset trigger to obtain the switch state of the target switch.
[0179] Referring to Figure 10, which is a schematic diagram of a logic circuit provided by another embodiment of the present application, a delay module is added after each of the two OR gates.
[0180] By adding delay processing, the fifth calculated value and the sixth calculated value can be ensured to be input into the RS trigger synchronously, effectively avoiding the problem of the time when the fifth calculated value is input into the RS trigger and the time when the sixth calculated value is input into the RS trigger being out of sync, thereby effectively improving the detection reliability of the third state information.
[0181] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of this application.
[0182] An embodiment of the present application further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program. When the computer program is executed by a processor, the steps in the above-mentioned various redundant control method embodiments can be implemented.
[0183] It is understandable that the above-mentioned computer-readable storage medium may be provided in both the first controller and the second controller, so that both the first controller and the second controller may implement redundant control through the above-mentioned redundant control method.
[0184] An embodiment of the present application provides a computer program product. When the computer program product is run on a terminal device, the terminal device can implement the steps of the above-mentioned embodiments of the redundancy control method.
[0185] It can be understood that the above-mentioned computer program product can be arranged in both the first controller and the second controller, so that both the first controller and the second controller can implement redundant control through the above-mentioned redundant control method.
[0186] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, which can be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium, and when the computer program is executed by the processor, it can implement the steps of the above-mentioned various method embodiments. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may at least include: any entity or device that can carry the computer program code to the device / terminal device, a recording medium, a computer memory, a read-only memory (ROM), a random access memory (RAM), an electric carrier signal, a telecommunication signal and a software distribution medium. For example, a USB flash drive, a mobile hard disk, a magnetic disk or an optical disk. In some jurisdictions, according to legislation and patent practice, computer-readable media cannot be electric carrier signals and telecommunication signals.
[0187] 11 is a schematic diagram of the structure of an energy storage device provided in an embodiment of the present application. As an example and not a limitation, the energy storage device includes a power module and a battery module.
[0188] The power module includes a first switch and a first controller for controlling the first switch, and the battery module includes a second controller connected to the first switch.
[0189] Exemplarily, the first switch is a bypass switch, the first controller is a power sub-module management controller (SMC), and the second controller is a battery management controller (BMC). The bypass switch is connected to the SMC and the BMC respectively.
[0190] It should be noted that, for ease of description, the following embodiments of this application use an SMC as the first controller and a BMC as the second controller as an example. In actual applications, the first and second controllers may also be other controllers capable of transmitting information and issuing control instructions. The names and models of the first, second, and third controllers are not specifically limited in the embodiments of this application.
[0191] In an embodiment of the present application, the first switch is connected to the first controller and the second controller respectively, so that the first controller and the second controller can obtain the status of the first switch and control the first switch, thereby realizing redundant control of the first switch by the first controller and the second controller, effectively improving the reliability of communication of the energy storage system, thereby improving the reliability and stability of the operation of the energy storage system.
[0192] In some embodiments, as shown in FIG12 , the second controller is connected to the first switch through the first controller.
[0193] In the embodiment of the present application, the second controller obtains the state of the first switch through the first controller and controls the first switch. The data or instructions of the first controller and the second controller can be backed up, thereby improving the reliability of the energy storage system communication.
[0194] In some embodiments, as shown in FIG13 , the second controller is connected to the first switch through the first controller and is also directly connected to the first switch.
[0195] In an embodiment of the present application, the second controller is connected to the first switch in two ways. When one communication path fails, the other communication path can ensure smooth communication of data or control instructions between the second controller and the first switch, thereby improving the reliability of communication of the energy storage system.
[0196] 14 is a schematic diagram of the structure of an energy storage device provided in an embodiment of the present application. As an example and not a limitation, the energy storage device includes a power module and a battery module.
[0197] The power module includes a first controller, the battery module includes a second switch and a second controller for controlling the second switch, and the first controller is connected to the second switch.
[0198] In an exemplary embodiment, the second switch is a bus switch, the first controller is a power sub-module management controller (SMC), and the second controller is a battery management controller (BMC). The bus switch is connected to the SMC and the BMC respectively.
[0199] It should be noted that, for ease of description, the following embodiments of this application use an SMC as the first controller and a BMC as the second controller as an example. In actual applications, the first and second controllers may also be other controllers capable of transmitting information and issuing control instructions. The names and models of the first, second, and third controllers are not specifically limited in the embodiments of this application.
[0200] In an embodiment of the present application, the second switch is connected to the first controller and the second controller respectively, so that the first controller and the second controller can obtain the status of the second switch and control the second switch, thereby realizing redundant control of the second switch by the first controller and the second controller, effectively improving the reliability of communication of the energy storage system, thereby improving the reliability and stability of the operation of the energy storage system.
[0201] In some embodiments, as shown in FIG15 , the first controller is connected to the second switch through the second controller.
[0202] In the embodiment of the present application, the first controller obtains the state of the second switch through the second controller and controls the second switch. The data or instructions of the second controller and the first controller can be backed up, thereby improving the reliability of the energy storage system communication.
[0203] In some embodiments, as shown in FIG16 , the first controller is connected to the second switch through the second controller, and is also directly connected to the second switch.
[0204] In an embodiment of the present application, the first controller is connected to the second switch in two ways. When one communication path fails, the other communication path can ensure smooth communication of data or control instructions between the first controller and the second switch, thereby improving the reliability of communication of the energy storage system.
[0205] In the above embodiments, the description of each embodiment has its own focus. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant description of other embodiments.
[0206] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered beyond the scope of this application.
[0207] The above-described embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the present application, and should all be included in the scope of protection of the present application.
Claims
1. An energy storage device, It is characterized in that Including power module and battery module; The power module includes a first switch and a first controller for controlling the first switch; The battery module includes a second switch and a second controller for controlling the second switch; The first controller is connected to the first switch and the second controller respectively, and the second controller is connected to the second switch.
2. The energy storage device according to claim 1, It is characterized in that The first controller is also connected to the second switch.
3. The energy storage device according to claim 2, It is characterized in that The first controller is connected to the first switch and the second switch respectively through multiple communication channels.
4. The energy storage device according to any one of claims 1 to 3, It is characterized in that The second controller is also connected to the first switch.
5. The energy storage device according to claim 4, It is characterized in that The second controller is connected to the first switch and the second switch respectively through multiple communication channels.
6. The energy storage device according to claim 3 or 5, It is characterized in that The multi-channel communication channel is a dual-channel optical fiber.
7. An energy storage system, It is characterized in that comprising a third controller, and at least one energy storage device according to any one of claims 1 to 6; The third controller is connected to the first controller in the energy storage device.
8. The energy storage system according to claim 7, It is characterized in that The third controller is also connected to the second controller in the energy storage device.
9. The energy storage system according to claim 7 or 8, It is characterized in that The energy storage system also includes a background management system; The background management system is connected to the third controller.
10. The energy storage system according to claim 9, It is characterized in that The background management system is connected to the first controller in the energy storage device, or is connected to the second controller in the energy storage device.
11. The energy storage system according to any one of claims 7 to 10, It is characterized in that The first controllers in any two of the energy storage devices in the energy storage system are connected.
12. A redundant control method, It is characterized in that Applied to the energy storage system according to any one of claims 7 to 11, the method comprises: Acquire a first switch signal of a target switch detected by the first controller; Acquire a second switch signal of a target switch detected by the second controller; determining a switch state of the target switch according to the first switch signal and the second switch signal; A control instruction for controlling the target switch is determined according to the switch state of the target switch.
13. The redundant control method according to claim 12, It is characterized in that Before determining the switch state of the target switch according to the first switch signal and the second switch signal, the method further includes: When the first switch signal and / or the second switch signal is abnormal, determining the switch state of the target switch to be a preset state; In a case where both the first switch signal and the second switch signal are normal, a step of determining a switch state of the target switch according to the first switch signal and the second switch signal is performed.
14. The redundant control method according to claim 13, It is characterized in that The step of determining the switch state of the target switch as a preset state includes: When the target switch is the first switch, determining the switch state of the target switch to be an open state; When the target switch is the second switch, the switch state of the target switch is determined to be a closed state.
15. The redundant control method according to claim 12, It is characterized in that The determining the switch state of the target switch according to the first switch signal and the second switch signal includes: Performing a logic calculation according to the first switch signal and the second switch signal to obtain a calculation result; The switch state of the target switch is determined according to the calculation result.
16. The redundant control method according to claim 15, It is characterized in that The performing a logic calculation according to the first switch signal and the second switch signal to obtain a calculation result includes: In the case where the multi-channel communication channel is a dual-channel optical fiber, performing an AND operation according to two first signal values included in the first switch signal to obtain a first logic signal; Performing an AND operation on two second signal values included in the second switch signal to obtain a second logic signal; An OR operation is performed according to the first logic signal and the second logic signal to obtain the calculation result.
17. The redundant control method according to claim 16, It is characterized in that The step of performing an AND operation on two first signal values included in the first switch signal to obtain a first logic signal includes: Performing an AND operation on the first first signal value and the negated value of the second first signal value to obtain a first calculated value in the first logic signal; Performing an AND operation on the first negated value of the first signal value and the second first signal value to obtain a second calculated value in the first logic signal; The step of performing an AND operation on two second signal values included in the second switch signal to obtain a second logic signal includes: Performing an AND operation on the first second signal value and the inverted value of the second signal value to obtain a third calculated value in the second logic signal; Performing an AND operation on the first inverted value of the second signal value and the second signal value to obtain a fourth calculated value of the second logic signal; The performing an OR operation on the first logic signal and the second logic signal to obtain the calculation result includes: Performing an OR operation on the first calculated value and the third calculated value to obtain a fifth calculated value in the calculation result; Performing an OR operation on the second calculated value and the fourth calculated value to obtain a sixth calculated value in the calculation result; The performing an OR operation on the first logic signal and the second logic signal to obtain the calculation result includes: The switch state of the target switch is determined according to the fifth calculated value and the sixth calculated value.
18. The redundant control method according to claim 17, It is characterized in that The determining the switch state of the target switch according to the fifth calculated value and the sixth calculated value includes: The fifth calculated value and the sixth calculated value are calculated according to a preset trigger to obtain the switch state of the target switch.
19. The redundant control method according to claim 18, It is characterized in that The calculating the fifth calculated value and the sixth calculated value according to a preset trigger to obtain the switch state of the target switch includes: respectively performing delay processing on the fifth calculated value and the sixth calculated value; The fifth calculated value after the delay processing and the sixth calculated value after the delay processing are calculated according to the preset trigger to obtain the switch state of the target switch.
20. The redundant control method according to claim 18 or 19, It is characterized in that The preset trigger is an RS trigger.
21. An energy storage device, It is characterized in that Including power module and battery module; The power module includes a first switch and a first controller for controlling the first switch; The battery module includes a second controller; The second controller is connected to the first switch.
22. The energy storage device according to claim 21, It is characterized in that The second controller is connected to the first switch, including that the second controller is directly connected to the first switch, and / or the second controller is connected to the first switch through the first controller.
23. An energy storage device, It is characterized in that Including power module and battery module; The power module includes a first controller; The battery module includes a second switch and a second controller for controlling the second switch; The first controller is connected to the second switch.
24. The energy storage device according to claim 23, It is characterized in that The first controller is connected to the second switch, including that the first controller is directly connected to the second switch, and / or that the first controller is connected to the second switch through the second controller.
Citation Information
Patent Citations
Energy storage device, energy storage system and redundancy control method
CN118826076A
Battery energy storage system and power supply system
CN104253488A
Energy storage system and control method thereof
CN113131546A
Control method of energy storage device, energy storage device and storage medium
CN113410860A
Risk degradation device and risk degradation method
CN113541672A