Control device, ventilation and air conditioning system, ventilation and air conditioning control method, and program

The control device and method for ventilation air conditioning systems address the issue of frequent start-stop operations by selectively using ventilation modes and managing air conditioner compressor frequency, enhancing comfort and extending equipment life by optimizing ventilation and air conditioning operations.

WO2024224629A1PCT designated stage expired Publication Date: 2024-10-31MITSUBISHI ELECTRIC CORP
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
PCT/JP2023/016943
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-28
Publication Date
2024-10-31

AI Technical Summary

Technical Problem

Existing ventilation air conditioning systems experience frequent start-stop operations of air conditioners, leading to room temperature fluctuations and accelerated deterioration, while attempts to reduce these operations by lowering outdoor air ventilation ratios may not secure sufficient ventilation.

Method used

A control device and method that selectively operates between heat exchange and non-heat exchange ventilation modes, and adjusts air conditioner compressor frequency to suppress start-stop operations without reducing ventilation, using a server to manage ventilation devices and air conditioners to maintain optimal thermal states.

Benefits of technology

This approach effectively reduces air conditioner start-stop frequency, maintaining user comfort and extending equipment lifespan by optimizing ventilation and air conditioning operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2023016943_31102024_PF_FP_ABST
    Figure JP2023016943_31102024_PF_FP_ABST
Patent Text Reader

Abstract

A server (2) comprises: a ventilation control unit (202) that performs control such that only one of a first ventilation device (4) that ventilates the inside of a building in conjunction with heat exchange and a second ventilation device (5) that ventilates the inside of the building without heat exchange operates; and a start / stop frequency acquisition unit (201) that acquires a start / stop frequency of a compressor provided in an air conditioner (3) that performs air conditioning in the building. When the acquired start / stop frequency is equal to or greater than a predetermined threshold, the ventilation control unit (202) switches to operation of the second ventilation device (5) if the first ventilation device (4) is in operation, and switches to operation of the first ventilation device (4) if the second ventilation device (5) is in operation. This makes it possible to maintain the comfort of a user and suppress deterioration of the air conditioner (3).
Need to check novelty before this filing date? Find Prior Art

Description

Control device, ventilation and air conditioning system, ventilation and air conditioning control method and program

[0001] The present disclosure relates to a control device, a ventilation and air-conditioning system, a ventilation and air-conditioning control method, and a program.

[0002] When the room temperature approaches the set temperature, the air conditioner starts and stops repeatedly, switching between thermo-ON (compressor drive frequency > 0) and thermo-OFF (compressor drive frequency = 0), which increases the frequency of on-off operation. This causes room temperature fluctuations that can be uncomfortable for users and accelerates deterioration of the air conditioner.

[0003] In response to this, for example, Patent Document 1 discloses a technology that reduces the ventilation load by lowering the ratio of outside air to the air supplied to the room from 100%, thereby suppressing the start-stop operation of the air conditioner.

[0004] JP 2012-013375 A

[0005] However, the above methods may not ensure the necessary ventilation volume, and the reality is that there is a need to propose new technologies to reduce the start-stop operation of air conditioners.

[0006] The present disclosure has been made in consideration of the above-mentioned situation, and aims to provide a control device, a ventilation air conditioning system, a ventilation air conditioning control method, and a program that are capable of suppressing the start-stop operation of an air conditioner without reducing the ventilation volume.

[0007] In order to achieve the above object, the control device according to the present disclosure comprises: a ventilation control means for controlling operation of only one of a first ventilation means that ventilates the interior of a building with heat exchange and a second ventilation means that ventilates the interior of the building without heat exchange; and an on / off frequency acquisition means for acquiring the on / off frequency of a compressor provided in an air conditioner that conditions the interior of the building, wherein when the acquired on / off frequency is equal to or greater than a predetermined threshold, if the first ventilation means is in operation, the ventilation control means switches to operation of the second ventilation means, and if the second ventilation means is in operation, switches to operation of the first ventilation means.

[0008] According to the present disclosure, it is possible to suppress the start / stop operation of an air conditioner without reducing the ventilation volume.

[0009] FIG. 1 is a diagram showing the overall configuration of a ventilation air-conditioning system in embodiment 1. Block diagram showing the hardware configuration of a server in embodiment 1. FIG. 1 is a diagram showing the hardware configuration of an air conditioner in embodiment 1. FIG. 1 is a diagram showing the hardware configuration of a first ventilation device in embodiment 1. Block diagram showing the functional configuration of a server in embodiment 1. Flowchart showing the procedure for start / stop suppression processing in embodiment 1. FIG. 1 is a diagram showing an example of the effect of control by a server ...

[0010] The present disclosure will be described in detail below with reference to the accompanying drawings. The ventilation and air-conditioning system according to the present disclosure can be applied to a variety of buildings, such as homes, office buildings, commercial facilities, and public facilities. In the following embodiments, the ventilation and air-conditioning system will be described as being applied to homes.

[0011] (Embodiment 1) Fig. 1 is a diagram showing the overall configuration of a ventilation and air-conditioning system 1 in embodiment 1. The ventilation and air-conditioning system 1 is a system that performs ventilation and air-conditioning for a house H that is a detached house or an apartment building, and is an example of a ventilation and air-conditioning system according to the present disclosure. As shown in Fig. 1 , the ventilation and air-conditioning system 1 includes a server 2, an air conditioner 3, a first ventilation device 4, a second ventilation device 5, and a router 6.

[0012] <Server 2> The server 2 is an example of a control device according to the present disclosure. The server 2 is a so-called cloud server, and provides a customer with a ventilation and air conditioning service for appropriately performing ventilation and air conditioning in a customer's home, a house H. As shown in FIG. 2 , the server 2 includes, as its hardware configuration, a communication interface 20, a CPU (Central Processing Unit) 21, a ROM (Read-Only Memory) 22, a RAM (Random-Access Memory) 23, and an auxiliary storage device 24. These components are interconnected via a bus 25. The communication interface 20 is hardware for communicating with other devices via a network N1, which is a wide area network such as the Internet, and is, for example, an interface based on Ethernet (registered trademark).

[0013] The CPU 21 performs overall control of the server 2. The functions of the server 2 realized by the CPU 21 will be described in detail later. The ROM 22 stores multiple pieces of firmware and data used when these pieces of firmware are executed. The RAM 23 is used as a work area for the CPU 21. The auxiliary storage device 24 is composed of a readable / writable nonvolatile semiconductor memory, a hard disk drive (HDD), etc. Examples of the readable / writable nonvolatile semiconductor memory include an erasable programmable read-only memory (EPROM), an electrically erasable programmable read-only memory (EEPROM), and a flash memory. The auxiliary storage device 24 stores a ventilation / air-conditioning program, which is a program for realizing a ventilation / air-conditioning service, and data used when the ventilation / air-conditioning program is executed.

[0014] The server 2 can acquire the ventilation and air conditioning program or an update program for updating the ventilation and air conditioning program from another server via communication via the network N1. These programs can also be stored and distributed on a computer-readable recording medium such as a CD-ROM (Compact Disc Read-Only Memory), a DVD (Digital Versatile Disc), a magneto-optical disk, a USB (Universal Serial Bus) memory, a HDD, an SSD (Solid-State Drive), or a memory card. When such a recording medium is directly or indirectly attached to the server 2, the server 2 can read the ventilation and air conditioning program or update program from the recording medium and install it on itself.

[0015] <Air Conditioner 3> The air conditioner 3 is an example of an air conditioner according to the present disclosure. The air conditioner 3 is a heat pump air conditioner that uses a natural refrigerant such as an HFC (hydrofluorocarbon) such as R32 or R290 as a refrigerant, and is a so-called room air conditioner. As shown in FIG. 3 , the air conditioner 3 includes an indoor unit 30 installed indoors, an outdoor unit 31 installed outdoors, and a remote control 32. The indoor unit 30 and the outdoor unit 31 are connected via refrigerant piping 33 for circulating the refrigerant. The indoor unit 30 and the outdoor unit 31 are also electrically connected via a cable 34 including a power line and a communication line.

[0016] The indoor unit 30 includes a control board 300, an indoor heat exchanger 301, an indoor fan 302, and an air temperature sensor 303. The outdoor unit 31 includes a control board 310, a compressor 311, a four-way valve 312, an outdoor heat exchanger 313, an expansion valve 314, an outdoor fan 315, and an air temperature sensor 316. The indoor heat exchanger 301 in the indoor unit 30 and the compressor 311, four-way valve 312, outdoor heat exchanger 313, and expansion valve 314 in the outdoor unit 31 are connected in a ring shape by refrigerant piping 33. This forms a refrigerant circuit (also called a refrigeration cycle).

[0017] <<Indoor unit 30>> In the indoor unit 30, the control board 300 has a hardware configuration including a communication interface, a CPU, a ROM, a RAM, and an auxiliary storage device, all of which are not shown. The communication interface of the control board 300 includes an interface for communicating with the components of the indoor unit 30 (such as the indoor fan 302 and the air temperature sensor 303), an interface for communicating with the outdoor unit 31 via the cable 34, an interface for wireless communication with the remote control 32, and an interface for communicating with the server 2 via the router 6.

[0018] The indoor unit 30 may be configured to communicate with the remote control 32 via a wired connection. The indoor unit 30 may also be configured to include a communication interface for long-distance wireless communication to communicate directly with the server 2 without going through the router 6. Alternatively, the indoor unit 30 may be configured to communicate with the server 2 via an external communication adapter.

[0019] The CPU of the control board 300 comprehensively controls the operation of the indoor unit 30. The ROM of the control board 300 stores multiple pieces of firmware and data used when these pieces of firmware are executed. The RAM of the control board 300 is used as a work area for the CPU. The auxiliary storage device of the control board 300 is composed of readable and writable non-volatile semiconductor memory, such as an EPROM, EEPROM, or flash memory. The auxiliary storage device stores programs for controlling the operation of the indoor unit 30 and data used when the programs are executed.

[0020] The indoor heat exchanger 301 exchanges heat between indoor air drawn in by the indoor fan 302 and refrigerant from the outdoor unit 31. The indoor heat exchanger 301 functions as a condenser during heating operation and as an evaporator during cooling operation. The indoor fan 302 is, for example, a crossflow fan, which draws in indoor air and sends out the air that has undergone heat exchange by the indoor heat exchanger 301 into the room. The indoor fan 302 is communicatively connected to the control board 300 via a communication line (not shown), and changes its rotation speed according to commands from the control board 300.

[0021] The air temperature sensor 303 measures the temperature of the indoor air drawn in by the indoor fan 302. The air temperature sensor 303 is communicably connected to the control board 300 via a communication line (not shown), and outputs a signal indicating the measured indoor air temperature (hereinafter referred to as "room temperature") to the control board 300.

[0022] <<Outdoor Unit 31>> In the outdoor unit 31, the control board 310 includes a communication interface, a CPU, a ROM, a RAM, and an auxiliary storage device, all of which are not shown. The communication interface of the control board 310 includes an interface for communicating with the components of the outdoor unit 31 (such as the compressor 311, four-way valve 312, expansion valve 314, outdoor fan 315, and air temperature sensor 316), and an interface for communicating with the indoor unit 30 via the cable 34.

[0023] Note that instead of the indoor unit 30, the outdoor unit 31 may be configured to have a communication interface for communicating with the server 2 via the router 6 or a communication interface for long-distance wireless communication for communicating directly with the server 2 without going through the router 6. In this case, the outdoor unit 31 may be configured to communicate with the server 2 via an external communication adapter.

[0024] The CPU of the control board 310 comprehensively controls the operation of the outdoor unit 31. The ROM of the control board 310 stores multiple pieces of firmware and data used when these pieces of firmware are executed. The RAM of the control board 310 is used as a work area for the CPU. The auxiliary storage device of the control board 310 is composed of readable and writable nonvolatile semiconductor memory, such as an EPROM, EEPROM, or flash memory. The auxiliary storage device stores programs for controlling the operation of the outdoor unit 31 and data used when the programs are executed.

[0025] The compressor 311 compresses the refrigerant. Specifically, the compressor 311 compresses a low-temperature, low-pressure refrigerant and discharges the high-pressure, high-temperature refrigerant to the four-way valve 312. The compressor 311 includes an inverter circuit that can change the rotation speed according to the drive frequency. The compressor 311 is communicably connected to the control board 310 via a communication line (not shown), and changes the drive frequency according to commands from the control board 310.

[0026] The four-way valve 312 is a component for switching the refrigerant circulation direction. During cooling operation, the state of the four-way valve 312 is as shown by the solid line in Fig. 3 . As a result, the refrigerant circulates in the order of the compressor 311, four-way valve 312, outdoor heat exchanger 313, expansion valve 314, and indoor heat exchanger 301. During heating operation, the state of the four-way valve 312 is as shown by the dashed line in Fig. 3 . As a result, the refrigerant circulates in the order of the compressor 311, four-way valve 312, indoor heat exchanger 301, expansion valve 314, and outdoor heat exchanger 313. The four-way valve 312 is communicatively connected to the control board 310 via a communication line (not shown), and switches the refrigerant circulation direction according to commands from the control board 310.

[0027] The outdoor heat exchanger 313 exchanges heat between the refrigerant and outdoor air (i.e., outside air) drawn in by the outdoor fan 315. The outdoor heat exchanger 313 functions as an evaporator during heating operation and as a condenser during cooling operation. The expansion valve 314 reduces the pressure of the refrigerant flowing through the refrigerant piping 33 to expand it. The expansion valve 314 is, for example, an electromagnetic expansion valve whose throttle opening can be adjusted by a stepping motor (not shown). The expansion valve 314 is communicatively connected to the control board 310 via a communication line (not shown), and adjusts the refrigerant pressure by changing its opening in accordance with commands from the control board 310.

[0028] The outdoor fan 315 is, for example, a propeller fan that draws in outside air and sends the air that has undergone heat exchange by the outdoor heat exchanger 313 outdoors. The outdoor fan 315 is communicatively connected to the control board 310 via a communication line (not shown), and changes its rotation speed in accordance with commands from the control board 310. The air temperature sensor 316 measures the temperature of the outside air drawn in by the outdoor fan 315. The air temperature sensor 316 is communicatively connected to the control board 310 via a communication line (not shown), and outputs a signal indicating the measured outside air temperature (hereinafter referred to as "outside air temperature") to the control board 310.

[0029] <First Ventilation Device 4> The first ventilation device 4 is an example of a first ventilation means according to the present disclosure. The first ventilation device 4 is a ventilation device that performs ventilation operation involving heat exchange (hereinafter referred to as "heat exchange ventilation operation") and is installed, for example, by hanging it on a wall of a room. As shown in FIG. 4 , the first ventilation device 4 includes a control board 40, an exhaust fan 41, an intake fan 42, and a heat exchange element 43. Although not shown, the control board 40 includes a communication interface for communicating with the server 2 via the router 6, a CPU, ROM, RAM, and an auxiliary storage device composed of a readable and writable nonvolatile semiconductor memory. The control board 40 controls the operation of the first ventilation device 4 according to commands from a dedicated remote control (not shown) provided in the server 2 or the first ventilation device 4.

[0030] The communication interface may be hardware for long-distance wireless communication for communicating directly with the server 2 without going through the router 6. Alternatively, the first ventilator 4 may be configured to communicate with the server 2 via an external communication adapter.

[0031] The exhaust fan 41 is a fan that takes in air from inside the room and expels it to the outside through an exhaust air duct. The supply air fan 42 is a fan that takes in outside air from outside and expels it to the inside through an intake air duct. The heat exchange element 43 is a component that exchanges heat between the air taken in from inside the room and the outside air.

[0032] <Second ventilation device 5> The second ventilation device 5 is an example of a second ventilation means according to the present disclosure. The second ventilation device 5 is a ventilation device that performs ventilation operation without heat exchange (hereinafter referred to as "normal ventilation operation"), for example, a Type 3 ventilation device that only exhausts air. The second ventilation device 5 may be a Type 1 ventilation device that both supplies and exhausts air, or a Type 2 ventilation device that only supplies air. The second ventilation device 5 includes a control board and an exhaust fan, neither of which are shown. The control board includes a communication interface for communicating with the server 2 via the router 6.

[0033] The communication interface may be hardware for long-distance wireless communication for communicating directly with the server 2 without going through the router 6. Alternatively, the second ventilator 5 may be configured to communicate with the server 2 via an external communication adapter.

[0034] <Functional Configuration of Server 2> Fig. 5 is a block diagram showing the functional configuration of the server 2. As shown in Fig. 5, the server 2 includes an air conditioning data acquisition unit 200, a start / stop frequency acquisition unit 201, a ventilation control unit 202, and an air conditioning control unit 203. These functional units are realized when the CPU 21 executes the above-mentioned ventilation air conditioning program stored in the auxiliary storage device 24.

[0035] The air conditioning data acquisition unit 200 periodically acquires air conditioning data from the air conditioners 3 installed in each customer's residence H. Specifically, the air conditioning data acquisition unit 200 requests air conditioning data from the air conditioners 3, for example, every minute. Upon receiving such a request, the air conditioner 3 transmits air conditioning data including the current time and operating state to the server 2. The operating state includes the thermostat state, operating mode (heating mode, cooling mode, etc.), intake temperature, outdoor air temperature, etc. The thermostat state refers to the on / off state of the outdoor unit 31 (more specifically, the compressor 311), and indicates whether the outdoor unit 31 is operating (i.e., thermostat ON) or stopped (i.e., thermostat OFF). The air conditioner 3 may also transmit air conditioning data to the server 2 voluntarily at regular intervals.

[0036] The air conditioning data acquisition unit 200 sorts the air conditioning data acquired from each customer's air conditioner 3 in chronological order for each customer and stores the data in the data storage unit 240. In other words, the data storage unit 240 stores the history of air conditioning data for each customer. The data storage unit 240 is a memory area provided by the auxiliary storage device 24.

[0037] The on / off frequency acquisition unit 201 is an example of on / off frequency acquisition means according to the present disclosure. The on / off frequency acquisition unit 201 acquires the on / off frequency of the compressor 311 included in the air conditioner 3. Specifically, the on / off frequency acquisition unit 201 references the thermostat status history stored in the data storage unit 240 and acquires the number of times the thermostat was switched from ON to OFF within the most recent fixed period of time (e.g., 30 minutes) as the on / off frequency. The on / off frequency acquisition unit 201 may also acquire the number of times the thermostat was switched from OFF to ON within the most recent fixed period of time as the on / off frequency. The on / off frequency acquisition unit 201 sorts the acquired on / off frequencies by customer and stores them in the data storage unit 240.

[0038] The ventilation control unit 202 is an example of a ventilation control means according to the present disclosure. The ventilation control unit 202 controls so that only one of the first ventilation device 4 and the second ventilation device 5 operates in ventilation mode. When automatic selection of ventilation mode is permitted by the user, the ventilation control unit 202 operates the first ventilation device 4 when the difference between the outside air temperature and the room temperature (|outside air temperature - room temperature|) exceeds a predetermined difference threshold (°C). In other words, in this case, heat exchange ventilation mode is performed. On the other hand, when the difference between the outside air temperature and the room temperature is equal to or less than the difference threshold, the ventilation control unit 202 operates the second ventilation device 5. In other words, in this case, normal ventilation mode is performed.

[0039] Specifically, in the heating period, the ventilation control unit 202 executes heat exchange ventilation operation when the difference value (room temperature - outdoor air temperature) exceeds the difference threshold, and executes normal ventilation operation when the difference value (room temperature - outdoor air temperature) is equal to or less than the difference threshold. Also, in the cooling period, the ventilation control unit 202 executes heat exchange ventilation operation when the difference value (outdoor air temperature - room temperature) exceeds the difference threshold, and executes normal ventilation operation when the difference value (outdoor air temperature - room temperature) is equal to or less than the difference threshold.

[0040] The user can set in advance in the server 2 whether or not to permit automatic selection of ventilation operation via a user terminal such as a smartphone or tablet terminal.

[0041] Furthermore, regardless of whether automatic selection is permitted, the ventilation control unit 202 executes control to suppress the start / stop frequency when air conditioning operation is being performed by the air conditioner 3. Specifically, the ventilation control unit 202 checks the latest start / stop frequency acquired by the start / stop frequency acquisition unit 201 and the difference value between the outside air temperature and the room temperature.

[0042] Then, when the start / stop suppression condition is met, that is, the latest start / stop frequency is equal to or greater than a predetermined threshold and the difference value is equal to or greater than a predetermined ΔT (°C), the ventilation control unit 202 switches the second ventilation device 5 to ventilation operation (i.e., normal ventilation operation) immediately if the current thermostat state of the air conditioner 3 is thermo-ON when the first ventilation device 4 is in ventilation operation (i.e., during heat exchange ventilation operation), or immediately if the current thermostat state of the air conditioner 3 is thermo-OFF when the thermostat state is switched to thermo-ON when the thermostat state is switched to thermo-OFF when the thermostat state is thermo-ON when the first ventilation device 4 is in ventilation operation (i.e., during normal ventilation operation), and the start / stop suppression condition is met, the ventilation control unit 202 switches the first ventilation device 4 to ventilation operation (i.e., heat exchange ventilation operation) immediately if the current thermostat state of the air conditioner 3 is thermo-OFF when the thermostat state is thermo-ON, or immediately if the thermostat state is thermo-ON when the thermostat state is switched to thermo-OFF.

[0043] When the ventilation control unit 202 switches to ventilation operation due to the establishment of the on / off suppression condition, the ventilation control unit 202 does not automatically switch to ventilation operation until a predetermined time T1 has elapsed, even if automatic selection is permitted. The time T1 is, for example, 15 to 30 minutes. Note that if the previous ventilation operation (before switching) was initiated by a user, the ventilation control unit 202 returns to the previous ventilation operation after the time T1 has elapsed.

[0044] The air conditioning control unit 203 is an example of an air conditioning control means according to the present disclosure. When the ventilation operation is switched on due to the establishment of the on / off suppression condition, the air conditioning control unit 203 controls the air conditioner 3 so that the current heat state of the air conditioner 3 is maintained for T1 time. Specifically, when the ventilation control unit 202 performs the above-mentioned switching, the air conditioning control unit 203 commands the air conditioner 3 to maintain the heat state. Upon receiving this command, the air conditioner 3 maintains the current heat state (heat ON state or heat OFF state) regardless of fluctuations in room temperature. When T1 time has elapsed, the air conditioning control unit 203 commands the air conditioner 3 to cancel the maintenance of the heat state.

[0045] <Start / stop suppression process> Fig. 6 is a flowchart showing the procedure of the start / stop suppression process executed by the server 2. When the air conditioner 3 starts air conditioning operation, the server 2 starts executing the start / stop suppression process described below.

[0046] (Step S100) The server 2 waits for the processing for a time T1. After that, the processing of the server 2 proceeds to step S101.

[0047] (Step S101) The server 2 acquires the start / stop frequency of the air conditioner 3. After that, the process of the server 2 proceeds to step S102.

[0048] (Step S102) The server 2 determines whether the acquired start / stop frequency is equal to or greater than a threshold. If the start / stop frequency is equal to or greater than the threshold (Step S102; YES), the process of the server 2 proceeds to Step S103. On the other hand, if the start / stop frequency is not equal to or greater than the threshold (Step S102; NO), the process of the server 2 returns to Step S100.

[0049] (Step S103) The server 2 determines whether the difference between the outside air temperature and the room temperature is equal to or greater than ΔT. If the difference is equal to or greater than ΔT (step S103; YES), the process of the server 2 proceeds to step S104. On the other hand, if the difference is not equal to or greater than ΔT (step S103; NO), the process of the server 2 returns to step S100.

[0050] (Step S104) The server 2 determines whether the current ventilation operation is heat exchange ventilation operation or normal ventilation operation. If the current ventilation operation is heat exchange ventilation operation, the process of the server 2 proceeds to step S105. On the other hand, if the current operation is normal ventilation operation, the process of the server 2 proceeds to step S106.

[0051] (Step S105) If the current thermostat state of the air conditioner 3 is thermo-ON, the server 2 immediately switches the second ventilation device 5 to ventilation operation, i.e., normal ventilation operation. If the current thermostat state of the air conditioner 3 is thermo-OFF, the server 2 switches to normal ventilation operation at the timing when the thermostat state is switched to thermo-ON. Thereafter, the processing of the server 2 proceeds to step S107.

[0052] (Step S106) If the current thermostat state of the air conditioner 3 is thermo-off, the server 2 immediately switches the first ventilation device 4 to ventilation operation, i.e., heat exchange ventilation operation. Also, if the current thermostat state of the air conditioner 3 is thermo-on, the server 2 switches to heat exchange ventilation operation at the timing when the thermostat state is switched to thermo-off. Thereafter, the processing of the server 2 proceeds to step S107.

[0053] (Step S107) The server 2 commands the air conditioner 3 to maintain the heated state. After that, the process of the server 2 proceeds to step S108.

[0054] (Step S108) The server 2 waits for the processing for time T1. During this time, the server 2 does not automatically switch the ventilation operation even if automatic selection is permitted. After that, the processing of the server 2 proceeds to step S109.

[0055] (Step S109) The server 2 instructs the air conditioner 3 to cancel the heating state. Upon receiving this instruction, the air conditioner 3 returns to normal control and appropriately changes the current heating state based on fluctuations in the room temperature. After that, the process of the server 2 proceeds to step S110.

[0056] (Step S110) If the ventilation operation before the switch was initiated by a user operation, the server 2 returns to the original ventilation operation. After that, the process of the server 2 returns to step S100.

[0057] 7 to 14 show examples of the effect of control by the server 2 (more specifically, the start / stop suppression process). Figures 7 and 8 show cases where heating operation is started from normal ventilation operation. Specifically, Figure 7 shows a case where the start / stop frequency is suppressed by switching to heat exchange ventilation operation when the first start / stop suppression condition is met, and Figure 8 shows a case where the start / stop frequency is suppressed by switching to normal ventilation operation when the second start / stop suppression condition is met.

[0058] 9 and 10 show cases where the heat exchange ventilation operation was started during heating operation. In detail, Fig. 9 shows a case where the frequency of start / stop is suppressed by switching to normal ventilation operation when the first start / stop suppression condition is met, and Fig. 10 shows a case where the frequency of start / stop is suppressed by switching to heat exchange ventilation operation when the second start / stop suppression condition is met.

[0059] 11 and 12 show cases where the cooling operation was started from normal ventilation operation. In detail, Fig. 11 shows a case where the start / stop frequency was suppressed by switching to heat exchange ventilation operation when the start / stop suppression condition was met for the first time, and Fig. 12 shows a case where the start / stop frequency was suppressed by switching to normal ventilation operation when the start / stop suppression condition was met for the second time.

[0060] 13 and 14 show cases where the cooling operation was started from the heat exchange ventilation operation. In detail, Fig. 13 shows a case where the start / stop frequency was suppressed by switching to the normal ventilation operation when the first start / stop suppression condition was met, and Fig. 14 shows a case where the start / stop frequency was suppressed by switching to the heat exchange ventilation operation when the second start / stop suppression condition was met.

[0061] As explained above, in the ventilation air-conditioning system 1 of this embodiment, the server 2 switches to ventilation operation when the start / stop suppression condition is met during air conditioning operation of the air conditioner 3 (i.e., the start / stop frequency is equal to or greater than a predetermined threshold and the difference between the outside air temperature and the room temperature is equal to or greater than a predetermined ΔT). In detail, when the server 2 is in heat exchange ventilation operation, if the current thermo state of the air conditioner 3 is thermo ON, the server 2 immediately switches to normal ventilation operation, or if the thermo state is thermo OFF, the server 2 switches to normal ventilation operation when the current thermo state of the air conditioner 3 is thermo OFF, or if the thermo state is thermo ON, the server 2 switches to heat exchange ventilation operation when the server 2 is in normal ventilation operation.

[0062] In other words, the server 2 increases or decreases the ventilation load as appropriate to extend the duration of the thermo-ON state or the thermo-OFF state of the air conditioner 3. Furthermore, the server 2 causes the air conditioner 3 to maintain the thermo state for a certain period of time after switching to ventilation operation.

[0063] This makes it possible to suppress the start / stop operation of the air conditioner 3 without reducing the ventilation volume, thereby maintaining user comfort and suppressing deterioration of the air conditioner 3.

[0064] (Variation 1) When the server 2 switches to normal ventilation operation when the start / stop suppression condition is met, the server 2 may increase the ventilation airflow rate of the second ventilation device 5. In this case, the greater the difference between the outside air temperature and the room temperature, the smaller the increase in the ventilation airflow rate by the server 2.

[0065] (Variation 2) Instead of the server 2, an in-home controller (not shown) installed in the house H may have the same functions as the server 2 (see FIG. 5) and execute the start / stop suppression process shown in FIG. 6. In this case, the in-home controller is an example of a control device according to the present disclosure.

[0066] (Variation 3) Instead of the server 2, the control board 300 provided in the indoor unit 30 of the air conditioner 3 or the control board 310 provided in the outdoor unit 31 may have the same functions as the server 2 (see FIG. 5) and execute the start / stop suppression processing shown in FIG. 6. In this case, the control board 300 or the control board 310 is an example of a control device according to the present disclosure.

[0067] (Modification 4) A ventilation device (not shown) that can switch between a heat exchange ventilation operation and a normal ventilation operation may be provided instead of the first ventilation device 4 and the second ventilation device 5. In this case, the ventilation device is an example of the first ventilation means and the second ventilation means according to the present disclosure.

[0068] (Modification 5) The air conditioner 3 and the ventilation device of Modification 4 may be structurally integrated.

[0069] (Variation 6) If the start / stop frequency exceeds a threshold value while the air conditioner 3 is performing heat exchange ventilation operation during cooling operation, and the outside air temperature is lower than the room temperature, the server 2 may switch to normal ventilation operation and control the air conditioner 3 to stop cooling operation.

[0070] (Variation 7) All or part of the functional units (see FIG. 5) of the server 2 may be realized by dedicated hardware, such as a single circuit, a composite circuit, a programmed processor, an ASIC (Application-Specific Integrated Circuit), an FPGA (Field-Programmable Gate Array), or a combination thereof.

[0071] The technical ideas according to the above-described modifications may be realized independently or in appropriate combination.

[0072] Second Embodiment Next, a second embodiment of the present disclosure will be described. In the following description, components and the like common to the first embodiment will be denoted by the same reference numerals, and description thereof will be omitted.

[0073] Fig. 15 is a diagram showing the overall configuration of a ventilation and air-conditioning system 1A according to embodiment 2. The ventilation and air-conditioning system 1A is a system that provides ventilation and air-conditioning for a house H, which is a detached house or an apartment building, and is an example of a ventilation and air-conditioning system according to the present disclosure. As shown in Fig. 15 , the ventilation and air-conditioning system 1A includes a server 2A, multiple air conditioners 3, a ventilation device 7, and a router 6.

[0074] <Server 2A> The server 2A is an example of a control device according to the present disclosure. The hardware configuration of the server 2A is the same as that of the server 2 according to the first embodiment (see FIG. 2). The functions of the server 2A will be described in detail later.

[0075] <Ventilation device 7> The ventilation device 7 is an example of the first ventilation means and the second ventilation means according to the present disclosure. The ventilation device 7 is a so-called central ventilation system for ensuring the ventilation volume for the entire house H, and is a ventilation device that can switch between heat exchange ventilation operation and normal ventilation operation. As shown in Fig. 16 , the ventilation device 7 includes a ventilation unit 70, a combined air supply duct 71, a combined air exhaust duct 72, multiple air supply ducts 73, and multiple air exhaust ducts 74.

[0076] The ventilation unit 70 includes a control board, an exhaust fan, an intake fan, and a heat exchange element, all of which are not shown. The control board of the ventilation unit 70 includes a communication interface for communicating with the server 2A via the router 6, a CPU, ROM, RAM, and an auxiliary storage device consisting of a readable and writable nonvolatile semiconductor memory, all of which are not shown. The control board controls the operation of the ventilation device 7 in accordance with commands from a dedicated remote control, not shown, provided in the server 2A or the ventilation device 7.

[0077] The communication interface may be hardware for long-distance wireless communication for communicating directly with the server 2A without going through the router 6. Alternatively, the ventilator 7 may be configured to communicate with the server 2A via an external communication adapter.

[0078] The exhaust fan of the ventilation unit 70 is a fan that takes in air from each room in the house H and exhausts the taken-in air outdoors through the integrated exhaust duct 72. The rotation speed of the exhaust fan, i.e., the amount of air blown by the exhaust fan, is adjusted in accordance with commands from the control board. The supply air fan of the ventilation unit 70 is a fan that takes in outside air through the integrated supply air duct 71 and sends the taken-in outside air out to each room. The rotation speed of the supply air fan, i.e., the amount of air blown by the supply air fan, is adjusted in accordance with commands from the control board. The heat exchange element of the ventilation unit 70 is a component that exchanges heat between the air taken in from inside the room and the outside air.

[0079] Each air supply duct 73 is a duct for distributing and supplying the outside air taken in by the ventilation unit 70 to each room, and is arranged in the attic of the house H. In this embodiment, as shown in Figure 17, air supply duct 73a is arranged to supply outside air to room A, air supply duct 73b is arranged to supply outside air to room B, and air supply duct 73c is arranged to supply outside air to room C.

[0080] Each exhaust duct 74 is a duct for taking in air from each room and transporting it to the ventilation unit 70, and is arranged in the attic of the house H. The air from each room transported to the ventilation unit 70 is discharged outdoors via the integrated exhaust duct 72. In other words, each exhaust duct 74 can also be said to be a duct for exhausting air from each room. In this embodiment, as shown in FIG. 17 , exhaust duct 74a is arranged to take in air from room A, exhaust duct 74b is arranged to take in air from room B, and exhaust duct 74c is arranged to take in air from room C.

[0081] <Functional configuration of server 2A> Fig. 18 is a block diagram showing the functional configuration of server 2A. As shown in Fig. 18, server 2A includes an air conditioning data acquisition unit 200A, a start / stop frequency acquisition unit 201A, a ventilation control unit 202A, and an air conditioning control unit 203A. These functional units are realized when CPU 21 of server 2A executes a ventilation air conditioning program stored in auxiliary storage device 24.

[0082] The air conditioning data acquisition unit 200A periodically acquires air conditioning data from each air conditioner 3 installed in each customer's residence H. The method of acquiring air conditioning data in the air conditioning data acquisition unit 200A is the same as that of the air conditioning data acquisition unit 200 in embodiment 1. The air conditioning data acquisition unit 200A sorts each piece of air conditioning data acquired from each air conditioner 3 of each customer in chronological order by customer and air conditioner 3, and stores the data in the data storage unit 240.

[0083] The on / off frequency acquisition unit 201A is an example of a on / off frequency acquisition means according to the present disclosure. The on / off frequency acquisition unit 201A acquires the on / off frequency of the compressor 311 provided in the air conditioner 3 in a room (hereinafter referred to as the "target room") designated in advance by a user. The method of acquiring the on / off frequency in the on / off frequency acquisition unit 201A is the same as that of the on / off frequency acquisition unit 201 according to the first embodiment.

[0084] The ventilation control unit 202A is an example of a ventilation control means according to the present disclosure. The ventilation control unit 202A controls the ventilation device 7. When automatic selection of ventilation operation is permitted by the user, the ventilation control unit 202A causes the ventilation device 7 to perform heat exchange ventilation operation when the difference value (|outdoor air temperature - room temperature|) between the outdoor air temperature and the room temperature (e.g., the room temperature of the target room) exceeds a predetermined difference threshold (°C). On the other hand, when the difference value between the outdoor air temperature and the room temperature is equal to or less than the difference threshold, the ventilation control unit 202A causes the ventilation device 7 to perform normal ventilation operation. Note that the room temperature that is the target of the difference value is not limited to the room temperature of the target room. For example, the room temperature that is the target of the difference value may be the average room temperature of all rooms, or the lowest room temperature of all rooms during the cooling season or the highest room temperature during the heating season.

[0085] Furthermore, regardless of whether automatic selection is permitted, when air conditioning operation is being performed by the air conditioner 3 in the target room, the ventilation control unit 202A executes control to reduce the start / stop frequency of the air conditioner 3. Specifically, the ventilation control unit 202A checks the latest start / stop frequency acquired by the start / stop frequency acquisition unit 201A and the difference value between the outside air temperature and the room temperature of the target room.

[0086] Then, when the start / stop suppression condition is met, that is, the latest start / stop frequency is equal to or greater than a predetermined threshold value and the difference value is equal to or greater than a predetermined ΔT (°C), the ventilation control unit 202A switches the ventilation operation of the ventilation device 7 to normal ventilation operation immediately if the current thermo state of the air conditioner 3 is thermo ON, or at the timing when it switches to thermo ON if it is thermo OFF, when the start / stop suppression condition is met and the ventilation device 7 is in normal ventilation operation, and the ventilation control unit 202A switches the ventilation operation of the ventilation device 7 to heat exchange ventilation operation immediately if the current thermo state of the air conditioner 3 is thermo OFF, or at the timing when it switches to thermo OFF if it is thermo ON.

[0087] When the ventilation control unit 202A switches to ventilation operation due to the establishment of the on / off suppression condition, the ventilation control unit 202A does not automatically switch to ventilation operation until a predetermined time T1 has elapsed, even if automatic selection is permitted. The time T1 is, for example, 15 to 30 minutes. If the previous ventilation operation (before switching) was initiated by a user, the ventilation control unit 202A returns to the previous ventilation operation after the time T1 has elapsed.

[0088] The air conditioning control unit 203A is an example of an air conditioning control means according to the present disclosure. When the ventilation operation is switched due to the establishment of the on / off suppression condition, the air conditioning control unit 203A controls the air conditioner 3 in the target room so that the current heat state of the air conditioner 3 is maintained for T1 time. Specifically, when the ventilation control unit 202A performs the above-mentioned switching, the air conditioning control unit 203A commands the air conditioner 3 in the target room to maintain the heat state. Upon receiving this command, the air conditioner 3 maintains the current heat state (heat ON state or heat OFF state) regardless of fluctuations in room temperature. When T1 time has elapsed, the air conditioning control unit 203A commands the air conditioner 3 to cancel the maintenance of the heat state.

[0089] <Start / stop suppression process> Fig. 19 is a flowchart showing the steps of the start / stop suppression process executed by the server 2A. When the air conditioning operation is started by the air conditioner 3 in the target room, the server 2A starts executing the start / stop suppression process described below.

[0090] (Step S200) The server 2A waits for the processing for a time T1. After that, the processing of the server 2A transitions to step S201.

[0091] (Step S201) The server 2A acquires the on / off frequency of the air conditioner 3 in the target room. After that, the process of the server 2A proceeds to step S202.

[0092] (Step S202) The server 2A determines whether the acquired start / stop frequency is equal to or greater than a threshold. If the start / stop frequency is equal to or greater than the threshold (step S202; YES), the process of the server 2A proceeds to step S203. On the other hand, if the start / stop frequency is not equal to or greater than the threshold (step S202; NO), the process of the server 2A returns to step S200.

[0093] (Step S203) The server 2A determines whether the difference between the outside air temperature and the room temperature of the target room is equal to or greater than ΔT. If the difference is equal to or greater than ΔT (step S203; YES), the process of the server 2A proceeds to step S204. On the other hand, if the difference is not equal to or greater than ΔT (step S203; NO), the process of the server 2A returns to step S200.

[0094] (Step S204) The server 2A determines whether the current ventilation operation is heat exchange ventilation operation or normal ventilation operation. If the current ventilation operation is heat exchange ventilation operation, the process of the server 2A proceeds to step S205. On the other hand, if the current ventilation operation is normal ventilation operation, the process of the server 2A proceeds to step S206.

[0095] (Step S205) If the current thermostat state of the air conditioner 3 in the target room is thermo ON, the server 2A immediately switches the ventilation operation of the ventilator 7 to normal ventilation operation. Also, if the current thermostat state of the air conditioner 3 is thermo OFF, the server 2A switches the ventilation operation of the ventilator 7 to normal ventilation operation at the timing when the thermostat state is switched to thermo ON. Thereafter, the processing of the server 2A proceeds to step S207.

[0096] (Step S206) If the current thermostat state of the air conditioner 3 in the target room is thermo-off, the server 2A immediately switches the ventilation operation of the ventilator 7 to heat exchange ventilation operation. Also, if the current thermostat state of the air conditioner 3 is thermo-on, the server 2A switches the ventilation operation of the ventilator 7 to heat exchange ventilation operation at the timing when the thermostat is switched to thermo-off. Thereafter, the processing of the server 2A proceeds to step S207.

[0097] (Step S207) The server 2A commands the air conditioner 3 in the target room to maintain the heated state. After that, the process of the server 2A proceeds to step S208.

[0098] (Step S208) The server 2A waits for the processing for time T1. During this time, the server 2A does not automatically switch the ventilation operation even if automatic selection is permitted. After that, the processing of the server 2A proceeds to step S209.

[0099] (Step S209) The server 2A commands the air conditioner 3 in the target room to cancel the heat state. Upon receiving this command, the air conditioner 3 returns to normal control and appropriately changes the current heat state based on fluctuations in room temperature. After that, the processing of the server 2A proceeds to step S210.

[0100] (Step S210) If the ventilation operation before the switch was initiated by a user operation, the server 2A returns to the original ventilation operation. After that, the process of the server 2A returns to step S200.

[0101] As described above, in the ventilation air-conditioning system 1A of the present embodiment, the server 2A switches ventilation operation when the on / off suppression condition is met during air conditioning operation of the air conditioner 3 in the target room (i.e., the on / off frequency is equal to or greater than a predetermined threshold and the difference between the outside air temperature and the room temperature is equal to or greater than a predetermined ΔT). In detail, when the server 2A is in heat exchange ventilation operation, if the current thermostat state of the air conditioner 3 is thermo ON, the server 2A immediately switches to normal ventilation operation, or if the thermostat state is thermo OFF, the server 2A switches to normal ventilation operation when the current thermostat state of the air conditioner 3 is thermo OFF, or if the thermostat state is thermo ON, the server 2A immediately switches to heat exchange ventilation operation, or if the thermostat state is thermo ON, the server 2A switches to normal ventilation operation.

[0102] In other words, the server 2A increases or decreases the ventilation load as appropriate to extend the duration of the thermo-ON state or the thermo-OFF state of the air conditioner 3. Furthermore, the server 2A causes the air conditioner 3 to maintain the thermo state for a certain period of time after switching to ventilation operation.

[0103] This makes it possible to suppress the start / stop operation of the air conditioner 3 without reducing the ventilation volume, thereby maintaining user comfort and suppressing deterioration of the air conditioner 3.

[0104] (Variation 1) When the server 2A switches to normal ventilation operation when the start / stop suppression condition is met, the server 2A may increase the ventilation airflow rate of the ventilation device 7. In this case, the greater the difference between the outside air temperature and the room temperature, the smaller the increase in the ventilation airflow rate by the server 2A.

[0105] (Variation 2) Instead of the server 2A, an in-home controller (not shown) installed in the house H may have the same functions as the server 2A (see FIG. 18 ) and execute the start / stop suppression process shown in FIG. 19. In this case, the in-home controller is an example of a control device according to the present disclosure.

[0106] (Variation 3) Instead of the server 2A, the control board 300 provided in the indoor unit 30 of one of the air conditioners 3 or the control board 310 provided in the outdoor unit 31 may have the same functions as the server 2A (see FIG. 18 ) and execute the start / stop suppression processing shown in FIG. 19. In this case, the control board 300 or the control board 310 is an example of a control device according to the present disclosure.

[0107] (Variation 4) The ventilation device 7 may be a central ventilation system that exclusively performs normal ventilation operation, and may be configured to include a separate ventilation device (not shown) that performs heat exchange ventilation for the target room. In this case, the separate ventilation device is an example of the first ventilation means according to the present disclosure, and the ventilation device 7 is an example of the second ventilation means according to the present disclosure.

[0108] (Variation 5) The ventilation device 7 may be a central ventilation system that exclusively performs heat exchange ventilation operation, and may be configured to include a separate ventilation device (not shown) that performs normal ventilation of the target room. In this case, the ventilation device 7 is an example of the first ventilation means according to the present disclosure, and the separate ventilation device is an example of the second ventilation means according to the present disclosure.

[0109] (Variation 6) The air conditioner 3 may not be a room air conditioner installed in each room, but may be a so-called whole-house air conditioning system that air-conditions the entire house H. In this case, the air conditioner 3 and the ventilation device 7 may be integrated into one configuration.

[0110] (Variation 7) If the start / stop frequency exceeds a threshold value while the air conditioner 3 in the target room is in cooling mode and performing heat exchange ventilation operation, and if the outside air temperature is lower than the room temperature, the server 2A may switch to normal ventilation operation and control the air conditioner 3 to stop cooling operation.

[0111] (Variation 8) The server 2A may select a target room based on the usage status of the air conditioner 3 in each room, the number of people in the room, the time of day, and the like.

[0112] (Variation 9) All or part of the functional units of the server 2A (see FIG. 18) may be realized by dedicated hardware, such as a single circuit, a composite circuit, a programmed processor, an ASIC, an FPGA, or a combination thereof.

[0113] The technical ideas according to the above-described modifications may be realized independently or in appropriate combination.

[0114] The present disclosure allows various embodiments and modifications without departing from the broad spirit and scope. Furthermore, the above-described embodiments are intended to explain the present disclosure and do not limit the scope of the present disclosure. In other words, the scope of the present disclosure is defined by the claims, not the embodiments. Various modifications made within the scope of the claims and within the meaning of the disclosure equivalent thereto are considered to be within the scope of the present disclosure.

[0115] The present disclosure can be suitably adopted in technology for ventilation and air conditioning in buildings.

[0116] 1, 1A ventilation and air conditioning system, 2, 2A server, 3 air conditioner, 4 first ventilation device, 5 second ventilation device, 6 router, 7 ventilation device, 20 communication interface, 21 CPU, 22 ROM, 23 RAM, 24 auxiliary storage device, 25 bus, 30 indoor unit, 31 outdoor unit, 32 remote control, 33 refrigerant piping, 34 cable, 40, 300, 310 control board, 41 exhaust fan, 42 supply air fan, 43 heat exchange element, 70 ventilation unit, 71 integrated supply air duct, 72 integrated exhaust duct, 73, 73a to 73c supply air duct, 74, 74a to 74c exhaust duct, 200, 200A air conditioning data acquisition unit, 201, 201A start / stop frequency acquisition unit, 202, 202A ventilation control unit, 203, 203A Air conditioning control unit, 240 data storage unit, 301 indoor heat exchanger, 302 indoor fan, 303, 316 air temperature sensor, 311 compressor, 312 four-way valve, 313 outdoor heat exchanger, 314 expansion valve, 315 outdoor fan

Claims

1. A control device comprising: a ventilation control means for controlling the operation of only one of a first ventilation means that ventilates the interior of a building with heat exchange and a second ventilation means that ventilates the interior of the building without heat exchange; and an on / off frequency acquisition means for acquiring the on / off frequency of a compressor provided in an air conditioner that conditions the interior of the building, wherein the ventilation control means switches to operation of the second ventilation means if the first ventilation means is in operation when the acquired on / off frequency is equal to or greater than a predetermined threshold, and switches to operation of the first ventilation means if the second ventilation means is in operation.

2. The control device according to claim 1, wherein the ventilation control means switches to operation of the second ventilation means if the first ventilation means is in operation when the acquired on / off frequency is equal to or greater than a predetermined threshold and the difference between the outside air temperature and the room temperature is equal to or greater than a predetermined value, and switches to operation of the first ventilation means if the second ventilation means is in operation.

3. The control device according to claim 1 or 2, wherein the ventilation control means switches to operation of the second ventilation means when the thermo state of the air conditioner is thermo ON, and switches to operation of the first ventilation means when the thermo state of the air conditioner is thermo OFF.

4. The control device according to any one of claims 1 to 3, further comprising air conditioning control means for controlling the air conditioner so that the thermo state of the air conditioner is maintained for a predetermined period of time when the ventilation control means switches between operation of the second ventilation means or operation of the first ventilation means.

5. A ventilation and air conditioning system comprising: a first ventilation means for ventilating a building with heat exchange; a second ventilation means for ventilating the building without heat exchange; an air conditioner for conditioning the building; and a control device, wherein the control device comprises: a ventilation control means for controlling operation so that only one of the first ventilation means and the second ventilation means is operating; and an on / off frequency acquisition means for acquiring an on / off frequency of a compressor provided in the air conditioner, wherein the ventilation control means switches to operation of the second ventilation means if the first ventilation means is operating when the acquired on / off frequency is equal to or greater than a predetermined threshold value, and switches to operation of the first ventilation means if the second ventilation means is operating.

6. A ventilation and air conditioning control method, wherein an on / off frequency acquisition means acquires the on / off frequency of a compressor provided in an air conditioner that conditions the air in a building, and a ventilation control means, when the acquired on / off frequency is equal to or greater than a predetermined threshold, switches operation to a second ventilation means that ventilates the building without heat exchange if a first ventilation means that ventilates the building with heat exchange is in operation, and switches operation to the first ventilation means if the second ventilation means is in operation.

7. A program that causes a computer to function as: an on / off frequency acquisition means for acquiring the on / off frequency of a compressor equipped in an air conditioner that conditions the air in a building; and a ventilation control means for switching operation to a second ventilation means that ventilates the building without heat exchange if a first ventilation means that ventilates the building with heat exchange is in operation and switching operation to the first ventilation means if the second ventilation means is in operation, when the acquired on / off frequency is equal to or greater than a predetermined threshold.

Citation Information

Patent Citations

  • Heat-exchanging ventilator

    JP2002031384A

  • Control device, air environment adjustment system, air environment adjustment method, program, and recording medium

    WO2020240659A1

  • Ventilation device

    WO2021100098A1