Battery management method and battery management device
The battery management method addresses the challenge of insufficient communication speed and space constraints by using interpolation techniques based on the battery's time constant, enabling accurate battery voltage measurement and diagnosis without dedicated circuits, thus improving the accuracy of battery state assessment.
Patent Information
- Application Number
- PCT/JP2023/017632
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-10
- Publication Date
- 2024-11-14
AI Technical Summary
The existing battery management systems face challenges in accurately diagnosing battery state due to insufficient communication speed between the Battery Management Unit (BMU) and other units, particularly when high sampling frequencies are required for impedance diagnosis, and the limited space within the BMU makes it difficult to mount dedicated circuits for feedback control.
The battery management method employs an interpolation technique based on the relationship between the sampling period of the measuring device and the time constant of the battery's negative electrode equivalent circuit, allowing for accurate acquisition of battery voltage without relying on dedicated circuits, by determining the appropriate interpolation method and using mathematical functions to supplement missing sampling points in the voltage waveform.
This approach enables accurate battery voltage measurement and diagnosis even with insufficient sampling frequencies, effectively overcoming the limitations of existing systems by interpolating the voltage waveform to capture high-frequency components necessary for battery state assessment.
Smart Images

Figure JP2023017632_14112024_PF_FP_ABST
Abstract
Description
Battery management method, battery management device
[0001] The present invention relates to a technology for managing the state of a battery.
[0002] As electric vehicles (EVs) become more widespread, there is a need to objectively assess the battery condition. Batteries installed in EVs are controlled by a battery management unit (BMU). Impedance measurement is a common method for diagnosing battery conditions using a BMU. Because impedance fluctuates depending on the battery condition, the battery condition can be estimated by analyzing the frequency characteristics obtained by impedance measurement.
[0003] To perform impedance diagnosis on a unit other than the BMU, the current and voltage values measured by the BMU must be transmitted to the other unit. The data communication interval from the BMU to the control ECU (Electronic Control Unit) is several tens of milliseconds. When an external unit references information obtained from the BMU, it must be transmitted via OBD (On-Board Diagnostics), in which case the communication interval is typically about 100 milliseconds. On the other hand, impedance diagnosis requires sampling at a higher frequency than the AC current applied to the battery. Insufficient communication speed between the BMU and the other unit hinders the transmission of measurement results sampled at a high sampling frequency to the other unit. Therefore, when acquiring data with a high sampling frequency, such as in impedance diagnosis, it is desirable to perform the diagnosis on the BMU.
[0004] The following Patent Document 1 discloses a technology in which "a battery management circuit (105) includes a reference signal generating unit (109) that generates first and second reference frequency signals having different phases, an AC superimposing unit (104) that superimposes an AC current having the frequency component of the first reference frequency signal on a secondary battery, a voltage measuring unit (115) that measures the voltage of the secondary battery by sampling at a frequency higher than the first reference frequency signal, a current measuring unit (112) that measures the current of the secondary battery by sampling at a frequency higher than the first reference frequency signal, and a converting unit (118b) that multiplies the measurement results of the voltage measuring unit (115) and the current measuring unit (112) by the first and second reference frequency signals to convert the measurement results into real and imaginary components of a complex voltage and a complex current, respectively" (see abstract).
[0005] WO2020 / 261799
[0006] Impedance measurements such as those described in Patent Document 1 require a dedicated circuit for waveform generation to apply an AC current to the target. The phase of the AC current applied to the battery lags behind the phase of the reference frequency signal due to the influence of the battery, wiring, and a driver amplifier that amplifies the reference signal. A dedicated circuit for feedback control of the AC current is also required to match the frequency of the applied AC current to the original reference frequency signal. It is difficult to incorporate a dedicated circuit within the limited structural area of a battery management device such as a BMU. Therefore, it is desirable to diagnose the battery condition using the raw voltage waveform output by the battery without using a dedicated circuit for impedance measurement.
[0007] The battery condition appears as a voltage change occurring over a period of several milliseconds to several tens of milliseconds after a current change occurs. If the sampling period for measuring battery voltage by a battery management device is long, there is no timing for measuring voltage during the period during which the battery condition can be confirmed. Therefore, it may not be possible to diagnose the battery condition from the raw voltage waveform measured by the battery management device. The period during which a voltage change occurs after a current change, allowing the battery condition to be confirmed, correlates with the eigenvalue of the battery's electrode material. This invention focuses on the fact that, in order to measure a voltage change that allows the battery condition to be confirmed, the sampling period must correspond to the eigenvalue of the battery's negative electrode. The negative electrode exhibits characteristics similar to an RC circuit, and the eigenvalue is expressed as a time constant. The reason why the battery condition cannot be diagnosed from the waveform measured by the battery management device is that the sampling period is not set taking into account the eigenvalue of the battery's electrode material.
[0008] The present invention has been made in consideration of the above-mentioned problems, and aims to provide a technology that can accurately acquire battery voltage even when it is difficult to capture the battery voltage using the sampling frequency of a measuring instrument that measures the battery voltage.
[0009] The battery management method according to the present invention selects an interpolation method for the measured waveform of the battery voltage based on the relationship between the sampling period of a measuring instrument that measures the battery voltage and the time constant of the negative electrode equivalent circuit of the battery.
[0010] According to the battery management method of the present invention, even when it is difficult to acquire the battery voltage using the sampling frequency of a measuring instrument that measures the battery voltage, the battery voltage can be acquired with high accuracy.
[0011] 1 is a diagram illustrating an example of the configuration of the battery management device 100 according to the first embodiment. FIG. 2 is a flowchart for selecting an interpolation method from the relationship between the sampling period of the measuring device 110 and the time constant. FIG. 3 is a flowchart for explaining details of S250. FIG. 4 is a flowchart for explaining details of S260. FIG. 5 is a diagram illustrating changes over time in the current and voltage output by the battery 200 during a rest period after discharge. FIG. 6 is a diagram illustrating an example of smoothing the voltage waveform acquired by the calculation unit 104. FIG. 7 is a diagram illustrating a method for calculating a time constant specific to the battery. FIG. 8 is a diagram illustrating an example of timing for determining an interpolation method for changes over time in voltage during discharge. FIG. 9 is a flowchart for explaining detailed procedures when S250 is performed during discharge. FIG. 10 is a flowchart for explaining detailed procedures when S260 is performed during discharge. FIG. 11 is a diagram illustrating another example of the configuration of the battery management device 100. FIG. 12 is a diagram illustrating another example of the configuration of S220 in the fourth embodiment. FIG. 13 is a diagram illustrating an example of the configuration of S210 in the fifth embodiment.
[0012] 1 is a diagram showing an example of the configuration of a battery management device 100 according to a first embodiment of the present invention. The battery management device 100 is connected to a measuring instrument 110. The battery management device 100 includes a detection unit 101, a detection unit 102, a comparison unit 103, and a calculation unit 104.
[0013] The detection unit 101 acquires the sampling period used when the measuring instrument 110 measures the voltage of the battery 200. The sampling period used by the measuring instrument 110 to measure the voltage may be fixed or variable, and the sampling period is acquired depending on the state. The detection unit 102 acquires a time constant τ1 specific to the battery 200. τ1 may be calculated from changes in the measured voltage over time, or the time constant τ1 corresponding to the battery being measured may be acquired from memory. The comparison unit 103 determines a method for interpolating the voltage output by the battery 200 (interpolation methods include cases where no interpolation is performed; the same applies below). The calculation unit 104 interpolates the measured voltage waveform using the determined interpolation method.
[0014] The measuring instrument 110 is connected to the battery management unit 100, the current sensor 120, and the battery 200. The measuring instrument 110 includes a MUX (multiplexer) 111, an AD converter 112, and an AD converter 113.
[0015] The MUX 111 measures the voltage of each cell that constitutes the battery 200 and transmits the analog voltage value to the AD converter 112. Since only one cell voltage can be transmitted, the MUX 111 transmits each cell voltage in turn, or transmits a selected cell voltage. The AD converter 112 converts the analog voltage value received from the MUX 111 into a digital value and transmits it to the battery management unit 100. The AD converter 113 converts the analog current value received from the current sensor 120 into a digital value and transmits it to the battery management unit 100.
[0016] The current sensor 120 is connected to the measuring instrument 110. The current sensor 120 measures the value of the current flowing through the battery 200.
[0017] The battery 200 is connected to the measuring instrument 110. The battery 200 is composed of one or more cells 201. The inside of the cell 201 is represented as an equivalent circuit, and the behavior when a current flows follows the equivalent circuit.
[0018] 2 is a flowchart for selecting an interpolation method based on the relationship between the sampling period and time constant of the measuring instrument 110. This flowchart is executed by the detection units 101 and 102, the comparison unit 103, and the calculation unit 104. Each step in FIG. 2 will be described below.
[0019] (FIG. 2: Step S210) The detection unit 101 acquires the sampling period s1 at which the measuring instrument 110 measures the voltage output from the battery 200. If the sampling period has been acquired, the process proceeds to S230. The measuring instrument 110 has its own sampling period. If the sampling period is variable, the sampling period is acquired each time. An example of calculating the sampling frequency will be described later.
[0020] (FIG. 2: Step S220) The detection unit 102 acquires the time constant τ1 when the negative electrode of the battery 200 is regarded as an RC circuit. The battery 200 has one or more inherent time constants, and the smallest time constant among them is taken as τ1, for example. A method for calculating the time constant τ1 will be described later.
[0021] (FIG. 2: Step S230) The comparison unit 103 determines a voltage interpolation method by comparing the sampling period s1 obtained in S210 with the time constant τ1 obtained in S220.
[0022] (FIG. 2: Step S240) The sampling period s1 obtained in S210 is compared with the time constant τ1 obtained in S220, and if s1 is less than half of τ1 (s1<τ1 / 2), voltage waveform interpolation is not performed. This is because multiple points of the voltage waveform in the high-frequency range above τ1, which is necessary for battery state diagnosis, have been measured.
[0023] (FIG. 2: Step S250) The sampling period s1 acquired in S210 is compared with the time constant τ1 acquired in S220, and if s1 is lower than τ1 but is equal to or greater than half of τ1, the calculation unit 104 interpolates the voltage waveform in the high frequency region above τ1 using interpolation method 1. Details of interpolation method 1 will be described later.
[0024] (FIG. 2: Step S260) The sampling period s1 acquired in S210 is compared with the time constant τ1 acquired in S220, and if s1 is greater than τ1 (s1>τ1), the calculation unit 104 interpolates the voltage waveform in the high frequency region above τ1 using interpolation method 2. Details of interpolation method 2 will be described later.
[0025] FIG. 3 is a flowchart illustrating the details of S250. This flowchart is executed by the calculation unit 104. In S250, the sampling period s1 is smaller than τ1, but is more than half of τ1, so there are two or more sampling points in the period less than τ1. Therefore, as shown in the upper left of FIG. 3, only a portion of the voltage waveform in the period less than τ1 is measured. While FIG. 3 illustrates an example of a rest period after discharging, a procedure similar to that of FIG. 3 can also be used in a rest period after charging. The same applies to FIG. 4. Each step of FIG. 3 will now be described.
[0026] (FIG. 3: Step S310) The calculation unit 104 performs a Fourier transform on the voltage waveform after the current is interrupted to calculate the real part and the imaginary part.
[0027] (FIG. 3: Step S320) The calculation unit 104 creates a Nyquist diagram from the result of the Fourier transform in S310, with the horizontal axis representing the real part and the vertical axis representing the imaginary part.
[0028] (FIG. 3: Step S330) The calculation unit 104 interpolates the Nyquist diagram in the negative electrode reaction region, which is a region higher in frequency than τ1, based on the characteristics of the negative electrode equivalent circuit of the battery 200. As shown in the upper left of FIG. 3, there are insufficient sampling points in the period below τ1, in which components originating from the negative electrode appear. Therefore, the Nyquist diagram also lacks high-frequency components corresponding to the period below τ1. In this step, the missing sampling points in the negative electrode region are interpolated on the Nyquist diagram. Techniques such as mathematical function fitting can be used as an interpolation method, but other appropriate interpolation methods may also be used. As a result of the interpolation, a Nyquist diagram with supplemented sampling points is obtained, as shown in the fourth diagram from the top in the left column of FIG. 3.
[0029] (FIG. 3: Step S340) The calculation unit 104 performs an inverse Fourier transform on the real and imaginary parts calculated from the Nyquist diagram interpolated in S330. As a result, sampling points on the time axis in a period equal to or shorter than τ1 are inversely generated from the Nyquist diagram.
[0030] (FIG. 3: Step S350) The calculation unit 104 identifies the voltage waveform in the region higher than τ1 when the voltage change is represented on a logarithmic time axis. This step makes it possible to obtain the voltage waveform in the region higher than τ1 that is necessary for diagnosing the battery state even when the sampling frequency is insufficient.
[0031] FIG. 4 is a flowchart illustrating the details of S260. This flowchart is executed by the calculation unit 104. In S260, since the sampling period s1 is greater than τ1, there are no sampling points in the period less than τ1. Therefore, as shown in the upper left of FIG. 4, the voltage waveform lacks measurement results in the period less than τ1. Each step in FIG. 4 will be explained below.
[0032] (FIG. 4: Step S410) The calculation unit 104 plots the voltage change after the current is interrupted on a logarithmic time axis.
[0033] (FIG. 4: Step S420) The calculation unit 104 calculates the voltage V1 at τ1 by mathematically interpolating the voltage waveform in the positive electrode reaction region using polynomial interpolation. As a calculation method, for example, linear interpolation, Lagrange interpolation, spline interpolation, or the like is performed on the measurement points in the positive electrode reaction region when the voltage change is expressed on a logarithmic time axis. The most appropriate method can be selected depending on the measured waveform.
[0034] (FIG. 4: Step S430) The calculation unit 104 identifies the voltage waveform in the high frequency region above τ1 when the voltage change is represented on the logarithmic time axis, using the same procedure as in S310 to S350.
[0035] (FIG. 4: Step S440) The calculation unit 104 calculates the voltage V2 at τ1 on the voltage waveform calculated in S430. Since S430 obtains the voltage waveform using a Nyquist diagram that lacks sampling points in the period equal to or shorter than τ1, V2 in this step may not necessarily be highly accurate.
[0036] (FIG. 4: Step S450) The calculation unit 104 compares V1 calculated in S420 with V2 calculated in S440. If the absolute value of the difference between V1 and V2 is equal to or less than a threshold, it is considered that V2 has been calculated with high accuracy, and the voltage waveform of the negative electrode reaction region calculated in S440 is adopted. If the absolute value of the difference between V1 and V2 is greater than the threshold, it is considered that the accuracy of V2 is insufficient, and S430 to S440 are repeated until the accuracy of V2 becomes sufficient. For example, by arbitrarily shifting any plot on the Nyquist diagram and re-executing S430 to S440, a Nyquist plot with sufficiently high accuracy for V2 can be searched for.
[0037] (FIG. 4: Step S500) The calculation unit 104 identifies, from the voltage change calculated in step S430, a voltage waveform in a higher frequency region than τ1 when the voltage change is expressed on a logarithmic time axis.
[0038] 5 is a diagram showing the time-dependent changes in the current and voltage output by the battery 200 during a rest period after discharge. The flowchart shown in FIG. 2 is implemented for the time-dependent changes in voltage immediately after discharge is completed. The flowchart shown in FIG. 2 is also implemented for the rest period after charging. During the rest period after charging or discharging, the voltage change is not affected by noise due to voltage changes or current caused by cell balance control, so interpolation can be implemented effectively.
[0039] ΔVa is the fluctuation in the battery output voltage from the end of discharge or a later first starting point to a first time after the first period ta has elapsed. For example, the fluctuation in output voltage (ΔVa) immediately after the end of discharge is strongly correlated with battery degradation. The optimal values for the start time and duration of ta can be obtained based on the interval from the end of discharge to the maximum point of the slope change rate in the voltage change curve over time. The ΔVa interval can be determined as appropriate, depending on the battery type, device, accuracy, etc., by selecting a region near or including both ends of the interval. The interpolated waveforms in Figures 2, 3, and 4 can be used to calculate ΔVa and calculate the degradation state. ΔVa can also be calculated using a similar approach during the pause period after charging. In this case, simultaneous measurement of cell voltage is not necessary; simply measuring the change in cell voltage after current interruption is sufficient.
[0040] FIG. 6 shows an example of how the calculation unit 104 smooths the acquired voltage waveform. A Fourier transform is performed on the acquired voltage waveform to calculate the relationship between frequency and phase and the relationship between frequency and amplitude. (a) The left end of the region in the amplitude-frequency characteristic where the amplitude increases as the frequency decreases, and (b) the left end of the region in the phase-frequency characteristic where the absolute value of the phase decreases as the frequency decreases, are identified as the Nyquist frequency, and the region higher than the Nyquist frequency is removed using a low-pass filter. By performing an inverse Fourier transform on the results, the voltage change can be smoothed.
[0041] FIG. 7 illustrates a method for calculating a battery's specific time constant. FIG. 7 shows the change in output voltage over time during a rest period after discharge on a logarithmic time axis. An inflection point is observed in FIG. 7. Time on the logarithmic time axis can be divided into multiple sections by the inflection point. The inventors discovered that the time at which this inflection point appears corresponds to the battery's specific time constant. The same is true for a rest period after charging; an inflection point is observed when the change in output voltage over time is plotted on a logarithmic time axis. If a similar inflection point can be observed during charging or discharging, not just during a rest period, the time at which the inflection point occurs is used as the time constant. One or more inflection points are observed, and the time constants are designated τ1, τ2, ... in ascending order. The time constant obtained in S220 is not limited to τ1; an appropriate time constant can be selected depending on the battery's characteristics. In the above description, τ1 (the first inflection point on the logarithmic time axis) was used as the negative electrode time constant.
[0042] 7 can be calculated from the waveform measured by the measuring instrument, step S220 is performed using the calculated time constant τ1. If τ1 cannot be calculated due to constraints such as the sampling period of the measuring instrument 110, a value of τ1 calculated in the past, a value of τ1 stored in memory and published by the battery manufacturer, or the like may be used.
[0043] Summary of First Embodiment The battery management device 100 according to the first embodiment determines an interpolation method for the measured waveform of the voltage after current interruption by comparing the sampling period s1 of the measuring instrument 110 with the time constant τ1 determined by the equivalent circuit of the battery 200. This makes it possible to appropriately estimate the voltage waveform in the high frequency region even when the sampling frequency of the measuring instrument 110 is insufficient. In other words, it is possible to diagnose the battery 200 using the voltage waveform in the negative electrode reaction region without relying on the sampling period of the measuring instrument 110. This method does not require a dedicated circuit such as that used in impedance measurement.
[0044] <Embodiment 2> The timing for determining the interpolation method can be the timing when a Nyquist diagram can be created for the change in voltage over time. When a change in current occurs, the voltage changes in accordance with the characteristics of the equivalent circuit. The Nyquist diagram can be created at this timing. In other words, the interpolation method can be determined at this timing. Therefore, in embodiment 2 of the present invention, the timing and procedure for determining the interpolation method will be described, other than the rest period after discharging or charging described in embodiment 1.
[0045] FIG. 8 illustrates an example of the timing for determining the interpolation method for voltage changes over time during discharge. Current changes occur at (a) the moment when discharge starts and current begins to flow, (b) the moment when the discharge current increases during discharge, and (c) the moment when the discharge current decreases during discharge. Therefore, the interpolation method can be determined for each of these periods. Similarly, during charging, the interpolation method can be determined at the moment when charge starts and current begins to flow, the moment when the discharge current increases during charge, and the moment when the discharge current decreases during charge. However, to properly create a Nyquist diagram, the voltage change must be faster than the time constant of the negative electrode.
[0046] In Figure 8, the timing for determining the interpolation method is not the rest period after charging or discharging, but since a current change occurs, it is considered possible to determine the interpolation method. Furthermore, even voltage waveforms outside of the rest period may adequately represent the battery state depending on the battery characteristics. Therefore, in this embodiment, the interpolation method is determined during the charging or discharging period, and the voltage waveform is interpolated using that interpolation method.
[0047] FIG. 9 is a flowchart illustrating the detailed procedure for performing S250 during discharging. This flowchart is performed by the calculation unit 104. The timing for performing this flowchart includes the period during which the current change described in FIG. 8 occurs. Whether or not a current change has occurred may be determined, for example, based on receipt of a current command, or by detecting a sudden change in current. The same applies to FIG. 10. While FIG. 9 describes interpolation method 1 during discharging, interpolation method 1 during charging is also performed using the same procedure.
[0048] In S910, the calculation unit 104 performs a Fourier transform on the voltage change that is faster than the time constant of the negative pole to calculate the real and imaginary parts. S920 to S950 are the same as S320 to S350. However, please note that the shapes of the voltage waveform and Nyquist diagram will differ depending on whether this flowchart is performed during the period when the current is rising or falling. The same is true for Figure 10.
[0049] Fig. 10 is a flowchart illustrating the detailed procedure for performing S260 during discharging. This flowchart is performed by the calculation unit 104. Fig. 10 explains interpolation method 2 during discharging, but interpolation method 2 during charging is also performed in a similar manner.
[0050] In S1010, the calculation unit 104 plots the voltage change that is faster than the time constant of the negative electrode on a logarithmic time axis. S1020 to S1060 are the same as S420 to S460, except that S1030 corresponds to FIG. 9.
[0051] Third Embodiment In a third embodiment of the present invention, a description will be given of another configuration example of the battery management device 100 described in the first embodiment. Matters other than the device configuration, such as the method for determining the interpolation method and the diagnostic method, are the same as those in the first and second embodiments.
[0052] FIG. 11 is a diagram showing another example configuration of the battery management device 100. The battery management device 100 does not necessarily need to be directly connected to the measuring device 110. For example, as shown in FIG. 11, the detection unit 101 may be connected between the measuring device 110 and the battery management device 100. In FIG. 11, the battery management device 100 acquires the sampling period of the measuring device 110 via a communication unit 1101. Specifically, the detection unit 102 or 1102 included in the battery management device 100 receives these detected values, for example, via a network, and the calculation unit 104 selects an interpolation method using these detected values. The configuration of the battery management device 100 is not limited to the configuration shown in FIG. 12. For example, (a) the comparison unit 103 and the calculation unit 104 may be arranged on a network, or (b) the detection unit 101 and the detection unit 102 may be arranged in a BMU (battery management unit), and the comparison unit 103 and the calculation unit 104 may be arranged in an ECU (electronic control unit).
[0053] 12 is a diagram showing another example of the configuration of S220 in a fourth embodiment of the present invention. The battery management device 100 in this embodiment stores a relationship table 1200 in a storage device, and performs S220 using the relationship table 1200. The other configurations are the same as those in the first to third embodiments.
[0054] The relationship table S1200 defines the time constant τ1 for each production lot number of the battery 200. This is because the time constant specific to a battery may differ for each production lot. In S220, the detection unit 102 obtains τ1 from the record corresponding to the production lot number of the battery.
[0055] Fifth Embodiment FIG. 13 is a diagram showing an example of the configuration of S210 in a fifth embodiment of the present invention. When sampling points are acquired according to the sampling period s1 of the measuring instrument 110, the accuracy of some of the sampling points may be low depending on the accuracy of the measuring instrument. In the example in the upper left of FIG. 13, there are two consecutive sampling points with the same value, and it is considered that at least one of these two sampling points has low accuracy. The accuracy of the measured voltage is also affected by conditions such as the SOC, the current during charging and discharging, and the battery temperature. Therefore, in this embodiment, the detection unit 101 corrects the sampling results to extract only sampling points with sufficient accuracy.
[0056] For example, the detection unit 101 extracts only some of the sampling points based on the relationship between each sampling point and the sampling points before and after it. For example, if the voltage value at a sampling point a predetermined time after a certain sampling point has not changed (or the change is minimal) from the previous sampling point, only the previous sampling point is extracted and the subsequent sampling points are discarded. This makes it possible to extract only sampling points that are assumed to have sufficiently high accuracy. As a result, the sampling period of the measuring instrument 110 is effectively u1, which is greater than s1.
[0057] 13, the issue of the voltage measurement accuracy by the measuring instrument 110 can be replaced with the issue of the sampling period. Therefore, by comparing the sampling period s1 (u1 in this embodiment) with the time constant τ1, it is possible to determine whether the voltage measurement accuracy is sufficient, and if it is insufficient, the voltage waveform can be interpolated using the method described in the above embodiment.
[0058] <Regarding Modifications of the Present Invention> The present invention is not limited to the above-described embodiments and includes various modifications. For example, the above-described embodiments have been described in detail to clearly explain the present invention, and the present invention is not necessarily limited to those including all of the described configurations. Furthermore, it is possible to replace part of the configuration of one embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of one embodiment. Furthermore, it is possible to add, delete, or replace part of the configuration of each embodiment with other configurations.
[0059] In the above-described embodiments, the functional units (e.g., detection unit 101, detection unit 102, comparison unit 103, and calculation unit 104) of the battery management device 100 can be configured by hardware such as a circuit device that implements these functions, or by software that implements these functions being executed by a calculation device such as a CPU (Central Processing Unit).
[0060] In the above embodiment, the functional units (e.g., the detection unit 101, the detection unit 102, the comparison unit 103, and the calculation unit 104) included in the battery management device 100 may be configured integrally. For example, the calculation unit 104 may perform the functions of all of these functional units.
[0061] In the above embodiment, the inflection points on the logarithmic time axis are identified to calculate the time constant determined by the equivalent circuit of the battery under test, but it is not necessary to convert the time axis to a logarithmic scale to identify the inflection points. That is, it is sufficient to be able to identify the inflection points that appear when the change in output voltage over time is plotted on a logarithmic time axis by some procedure.
[0062] In the above embodiment, it has been described that whether or not to interpolate the voltage waveform is determined based on whether or not the sampling period s1 is less than half the time constant τ1. This is because if s1 is equal to or greater than half of τ1, two or more sampling points can be obtained in the period equal to or less than τ1, making it easy to interpolate the voltage waveform in that period. However, this is not necessarily limited to this, and as long as one sampling point can be obtained in the period equal to or less than τ1, interpolation to a certain extent is possible. Therefore, it is also possible to determine whether or not to perform interpolation based on whether or not the sampling frequency is sufficient to obtain one sampling point in the period equal to or less than τ1.
[0063] 100: Battery management device 101: Detection unit 102: Detection unit 103: Comparison unit 104: Calculation unit 110: Measuring instrument 111: MUX 112: AD converter 113: AD converter 120: Current sensor 200: Battery 1101: Communication unit 1102: Detection unit
Claims
1. A battery management method comprising the steps of: acquiring a time constant of a negative electrode equivalent circuit of a battery; acquiring a sampling period of a measuring instrument that measures the voltage output by the battery; comparing the time constant with the sampling period; selecting an interpolation method to be used to interpolate a portion of the voltage that the measuring instrument was unable to capture using the sampling period according to the difference between the time constant and the sampling period; and interpolating the voltage using the selected interpolation method.
2. The battery management method according to claim 1, characterized in that, in the selecting step, if the sampling period is smaller than the time constant and the absolute value of the difference is less than a threshold value, a first method is selected as the interpolation method, and, in the selecting step, if the sampling period is larger than the time constant, a second method is selected as the interpolation method.
3. The battery management method according to claim 1, characterized in that in the selecting step, if the sampling period is smaller than the time constant by a threshold value or more, the interpolation is not performed.
4. The battery management method according to claim 1, characterized in that in said selecting step, if said sampling period is less than half of said time constant, said interpolation is not performed.
5. A battery management method as described in claim 2, characterized in that the first method comprises the steps of: generating a Nyquist diagram of the battery; interpolating a portion of the time-dependent voltage change corresponding to a time earlier than the time constant; interpolating a portion of the Nyquist diagram corresponding to the portion interpolated in the step of interpolating the time-dependent voltage change; and generating a waveform of the time-dependent voltage change by inversely transforming the Nyquist diagram interpolated in the step of interpolating the Nyquist diagram.
6. The battery management method according to claim 2, characterized in that the second method comprises the steps of: calculating, as a first voltage value, the voltage at a time corresponding to the time constant in the time change by interpolating a portion of the voltage change over time that corresponds to a time after the time constant; interpolating a portion of a Nyquist diagram of the battery that corresponds to a voltage waveform at a time before the time constant in the time change; generating a time-change waveform of the voltage by inversely converting the Nyquist diagram interpolated in the step of interpolating the Nyquist diagram; calculating, as a second voltage value, the voltage at a time corresponding to the time constant in the time-change waveform; and, if an absolute value of the difference between the first voltage value and the second voltage value is less than a threshold value, adopting the time-change waveform as a result of the second method.
7. The battery management method according to claim 6, characterized in that the second method re-performs the step of interpolating the Nyquist diagram and the step of generating the time-varying waveform when the absolute value of the difference between the first voltage value and the second voltage value is equal to or greater than the threshold value.
8. The battery management method according to claim 1, further comprising the steps of: acquiring the change in voltage over time using the measuring instrument; converting the change over time into a phase frequency characteristic and an amplitude frequency characteristic; removing, as noise components, a region higher in frequency than a region in which the absolute value of the phase decreases with a decrease in frequency in the phase frequency characteristic; removing, as noise components, a region higher in frequency than a region in which the amplitude increases with a decrease in frequency in the amplitude frequency characteristic; and reproducing the change over time by inversely converting the phase frequency characteristic from which the noise components have been removed and the amplitude frequency characteristic from which the noise components have been removed.
9. The battery management method according to claim 1, characterized in that, in the step of obtaining the time constant, the time constant is obtained based on an inflection point when the change in voltage over time is represented on a logarithmic axis.
10. The battery management method according to claim 1, further comprising a step of acquiring the change in voltage over time using the measuring device, wherein the step of acquiring the change in voltage over time includes acquiring the change in voltage over time during a rest period after the battery has finished charging or discharging.
11. The battery management method according to claim 1, further comprising a step of acquiring the change in voltage over time using the measuring device, wherein in the step of acquiring the change over time, the change over time having a frequency component smaller than the time constant of the negative electrode of the battery is acquired during a period in which the battery is being charged or discharged.
12. A battery management method as described in claim 1, characterized in that in the step of acquiring the time constant, the time constant is acquired by referring to data describing the time constant for each manufacturing lot number of the battery.
13. A battery management device comprising: a first detection unit that acquires a time constant of a negative electrode equivalent circuit of a battery; a second detection unit that acquires a sampling period of a measuring instrument that measures the voltage output by the battery; and a calculation unit that interpolates the voltage, wherein the calculation unit interpolates the voltage by carrying out the following steps: comparing the time constant with the sampling period; selecting an interpolation method to be used to interpolate a portion of the voltage that the measuring instrument was unable to capture using the sampling period according to the difference between the time constant and the sampling period; and interpolating the voltage using the selected interpolation method.
Citation Information
Patent Citations
Evaluation device of fuel cell
JP2005166601A
Higher harmonic wave component measuring device
JP2012112761A
Open-circuit voltage estimation device, power storage device and method of estimating open-circuit voltage
JP2015078918A
Secondary battery state of charge estimation device and method
JP2016508215A
Battery control device
JP2020134279A
Cited By
Vehicle energy flow analysis method and apparatus, device, and storage medium
WO2026103232A1