Decoration forward design drawing method based on BIM
Through the BIM-based decoration forward design drawing method, the problem of missing construction process simulation and visualization in traditional decoration methods is solved, three-dimensional modeling design and economic estimation are realized, design efficiency and quality are improved, and the accurate budget of construction progress and cost is ensured.
Patent Information
- Application Number
- CN202411891302.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-20
- Publication Date
- 2025-03-18
AI Technical Summary
The traditional decoration methods lack simulation and visual display of construction processes, resulting in inaccurate tiles layout and component settings, making it difficult to provide timely feedback and adjustments during construction, affecting progress and cost budget.
The BIM-based decoration forward design drawing method is adopted. By obtaining decoration data parameters, a BIM model of the building structure and a basic model of decoration decoration are created, and a Revit plug-in is used for modeling and real-time updates, which realizes the mold design and data statistics of ceramic tile and ceiling panels, and supports model sharing and drawing labeling.
It realizes three-dimensional modeling design, presents design effects realistically and intuitively, integrates design information, reduces design errors and rework, improves design efficiency and quality, and provides economic estimates through BIM, accurately budgets for decoration costs, and improves tile layout design efficiency.
Smart Images

Figure CN119646948A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of building decoration and renovation construction, and more specifically to a decoration forward design drawing method based on BIM. Background Art
[0002] As the demand for interior decoration continues to increase, the technical requirements for interior decoration are also constantly increasing. Traditional decoration methods often involve direct construction, lacking simulation and visual display of the construction process, so it is impossible to layout tiles and accurately set various components. As a result, when problems arise during construction, it is impossible to provide individual and overall feedback on the construction process in a timely manner, delaying the construction progress, and at the same time, it is impossible to budget for decoration costs, affecting construction. Summary of the invention
[0003] The present invention overcomes the deficiencies in the prior art and provides a decoration forward design drawing method based on BIM.
[0004] The purpose of the present invention is achieved through the following technical solutions.
[0005] The BIM-based forward design drawing method for decoration includes the following specific steps:
[0006] S1. Obtain the data parameters required for decoration;
[0007] S2. Create a building structure BIM model based on the building construction drawings and structural construction drawings, use the Revit plug-in to model the building structure BIM model, and update the BIM model in real time according to the design process;
[0008] S3. Create a basic model for decoration and set specific data including wall, ceiling, floor, decoration material, thickness and decoration component selection;
[0009] S4. In-depth decoration design: according to the size specifications of tiles and ceiling panels, the electronic plug-in is used to make real-time statistics on the effect of the tile and ceiling panel layout design and the quantity list of components, and various data are parameterized and driven during the plan change process until the final design plan is determined;
[0010] S5. Share the building structure BIM model with the structure and electromechanical models;
[0011] S6. Mark the model drawings according to the marking requirements of the construction drawings;
[0012] S7, setting the export layer of each component;
[0013] S8. Export model drawings.
[0014] The specific steps of S6 include: using the Revit plug-in to open the model file, selecting "File" > "Export" > "Options" > "Export Settings DWG" in turn, and setting and clearly specifying the layer name after each type of component is exported.
[0015] The model drawings exported from S8 include: plan view, elevation view, section view and detail view.
[0016] The specific steps of S7 include:
[0017] S71. Select the export format, click the "File" menu, select "Export" > "CAD Format" > "DWG";
[0018] S72. Create a new export setting. In the DWG Export dialog box, click the Modify Export Settings button.
[0019] S73. Export layer settings. In the "Layer" tab, set the corresponding layer name and color after the Revit model category is exported to DWG format;
[0020] S74, export layer options, select the "Export category attributes by layer, and export replacement by primitive" option;
[0021] S75. General settings: make general settings for lines, fill patterns, text and fonts according to drawing requirements.
[0022] The specific steps of S8 include: in the "Save to Target Folder" dialog box of the "DWG Export" window, set the location and file name for saving the exported file.
[0023] The beneficial effects of the present invention are as follows: the present scheme provides a BIM-based forward design drawing method for decoration, which can perform three-dimensional modeling design according to the various related design disciplines, and can present the actual effect of the design in a real and intuitive manner. Furthermore, the present scheme adopts a three-dimensional model for design, which can realize the integration and collaborative work of design information, greatly reduce design errors and rework, and improve design efficiency and quality. At the same time, the present method uses BIM to use various tools to provide model-based economic estimates, which can more accurately budget decoration costs. The characteristics of three-dimensional visualization and parameterization can make the effect of tile layout design and components completed in real time statistics, and various data can be parameterized and driven during the scheme modification process, which greatly improves the efficiency of tile layout design on the basis of ensuring the decorative effect of the completed construction surface. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a schematic diagram of the process of the present invention. DETAILED DESCRIPTION
[0025] The technical solution of the present invention is further described below through specific embodiments.
[0026] Example
[0027] like Figure 1 As shown in the figure, the BIM-based decoration forward design drawing method includes the following specific steps:
[0028] S1. Obtain the data parameters required for decoration;
[0029] S2. Create a building structure BIM model based on the building construction drawings and structural construction drawings, use the Revit plug-in to model the building structure BIM model, and update the BIM model in real time according to the design process;
[0030] S3. Create a basic model for decoration and set specific data including wall, ceiling, floor, decoration material, thickness and decoration component selection;
[0031] S4. In-depth decoration design: according to the size specifications of tiles and ceiling panels, the electronic plug-in is used to make real-time statistics on the effect of the tile and ceiling panel layout design and the quantity list of components, and various data are parameterized and driven during the plan change process until the final design plan is determined;
[0032] S5. Share the building structure BIM model with the structure and electromechanical models;
[0033] S6. Mark the model drawings according to the marking requirements of the construction drawings;
[0034] S7, setting the export layer of each component;
[0035] S8. Export model drawings.
[0036] The specific steps of S6 include: using the Revit plug-in to open the model file, selecting "File" > "Export" > "Options" > "Export Settings DWG" in turn, and setting and clearly specifying the layer name after each type of component is exported.
[0037] The model drawings exported from S8 include: plan view, elevation view, section view and detail view.
[0038] The specific steps of S7 include:
[0039] S71. Select the export format, click the "File" menu, select "Export" > "CAD Format" > "DWG";
[0040] S72. Create a new export setting. In the DWG Export dialog box, click the Modify Export Settings button.
[0041] S73. Export layer settings. In the "Layer" tab, set the corresponding layer name and color after the Revit model category is exported to DWG format;
[0042] S74, export layer options, select the "Export category attributes by layer, and export replacement by primitive" option;
[0043] S75. General settings: make general settings for lines, fill patterns, text and fonts according to drawing requirements.
[0044] The specific steps of S8 include: in the "Save to Target Folder" dialog box of the "DWG Export" window, set the location and file name for saving the exported file.
[0045] Preferably, the electronic plug-in used in the present embodiment S4 is a red tile plug-in, and the modeling master module is used to perform real-time statistics on the effects of the completed mold design of tiles and ceiling panels and the quantity list of components.
[0046] The embodiments of the present invention are described in detail above, but the contents described are only preferred embodiments of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.
Claims
1. The forward design drawing method for decoration based on BIM is characterized by: The specific steps include: S1. Obtain the data parameters required for decoration; S2. Create a building structure BIM model based on the building construction drawings and structural construction drawings, use the Revit plug-in to model the building structure BIM model, and update the BIM model in real time according to the design process; S3. Create a basic model for decoration and set specific data including wall, ceiling, floor, decoration material, thickness and decoration component selection; S4. In-depth decoration design: according to the size specifications of tiles and ceiling panels, the electronic plug-in is used to make real-time statistics on the effect of the tile and ceiling panel layout design and the quantity list of components, and various data are parameterized and driven during the plan change process until the final design plan is determined; S5. Share the building structure BIM model with the structure and electromechanical models; S6. Mark the model drawings according to the marking requirements of the construction drawings; S7, setting the export layer of each component; S8. Export model drawings.
2. The BIM-based decoration forward design drawing method according to claim 1 is characterized in that: The specific steps of S6 include: using the Revit plug-in to open the model file, selecting "File" > "Export" > "Options" > "Export Settings DWG" in turn, and setting and clearly specifying the layer name after each type of component is exported.
3. The BIM-based decoration forward design drawing method according to claim 1 is characterized in that: The model drawings exported from S8 include: plan view, elevation view, section view and detail view.
4. The BIM-based decoration forward design drawing method according to claim 1 is characterized in that: The specific steps of S7 include: S71. Select the export format, click the "File" menu, select "Export" > "CAD Format" > "DWG"; S72. Create a new export setting. In the "DWG Export" dialog box, click the "Modify Export Settings" button; S73. Export layer settings. In the "Layer" tab, set the corresponding layer name and color after the Revit model category is exported to DWG format; S74, export layer options, select the "Export category attributes by layer, and export replacement by primitive" option; S75. General settings: make general settings for lines, fill patterns, text and fonts according to drawing requirements.
5. The BIM-based decoration forward design drawing method according to claim 4 is characterized in that: The specific steps of S8 include: in the "Save to Target Folder" dialog box of the "DWG Export" window, set the location and file name for saving the exported file.