Drill rod for construction of integrated stirring forming type cemented soil stiff anchor rod and construction method of integrated stirring forming type cemented soil stiff anchor rod

Through the integrated stirring of the drill rod for the construction of cement soil stiff anchor rods, and the spiral blades are used for stirring, the integrated molding of hole formation, anchoring and grouting processes is achieved, which solves the problems of soil residues, structural molding defects and process complexity in the existing technology, and improves the bearing capacity and safety of the anchor rods.

CN120119900APending Publication Date: 2025-06-10JIANGSU DONGHENAN GEOTECHNICAL TECH CO LTD
View PDF 0 Cites 5 Cited by

Patent Information

Application Number
CN202510256348.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-05
Publication Date
2025-06-10

AI Technical Summary

Technical Problem

The existing high-pressure jet enlarged head anchor technology has soil residues, structural molding defects and process complexity during construction, resulting in significant deviations from the actual bearing capacity of the anchor and the design value, especially under soft soil geological conditions, bearing capacity reduction often occurs.

Method used

The drill rod for construction using integrated stirred cement soil stiff anchor rods, including drill heads and hollow drill rods, is stirred with spiral blades to achieve integrated molding of hole formation, anchoring and grouting processes, simplify the construction process, and improve the construction speed and quality.

Benefits of technology

Through the integrated molding process, the internal structure of the cement soil pile body is uniform, the pile body strength is reliable, and the tension distribution of the anchor rod is more uniform, which reduces the stress concentration phenomenon, improves the safety of the anchor system, and reduces the deviation between the actual bearing capacity and the design value.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120119900A_ABST
    Figure CN120119900A_ABST
Patent Text Reader

Abstract

The invention discloses a drill rod for construction of an integrated stirring forming type cemented soil stiff anchor rod, the drill rod comprises a drill bit part and a hollow drill rod, the drill bit part comprises a shell, an anchor disc fixed in the shell and a spiral blade welded on the shell, and the hollow drill rod is inserted into the shell; the sheath steel pipe is inserted into the hollow drill rod and fixed to the shell, the grouting pipe is inserted into the sheath steel pipe, one end of the rod body is fixed to the anchor disc, and the other end of the rod body extends out of the sheath steel pipe. A first grouting hole is formed in the shell, and a second grouting hole is formed in the sheath steel pipe. The invention further discloses a construction method of the integrated stirring forming type cemented soil stiff anchor rod. When the method is used, the processes of hole forming, anchoring, grouting and the like are integrally formed, the process is simple, the speed is high, and the quality is easy to control; the formed cement-soil pile body is uniform in internal structure and reliable in strength; tension of the anchor rod is uniformly distributed, so that stress concentration can be reduced; and the formed cement soil pile body is high in end strength and good in safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technology of rock bolts with enlarged heads, and particularly to a drill pipe and a construction method for the construction of integrally mixed and formed cement-soil stiffened rock bolts. Background Art

[0002] The high-pressure jet grouting enlarged-head rock bolt is a new type of rock bolt structure with a large-diameter anchor body formed by cutting the soil at the bottom of the anchor hole with high-pressure fluid and then grouting cement slurry. There are already detailed construction specifications. Although this technology has significant bearing capacity advantages over traditional rock bolts, there are still the following technical bottlenecks in actual construction:

[0003] (1) Problem of soil residue: The existing process is difficult to completely remove the cut soil in the enlarged-head cavity. Especially when constructing in soft soil strata, the phenomenon of hole collapse in the enlarged-head cavity occurs frequently, resulting in a large amount of soil residue. The residual soil and the grouting body form a mixed structure, seriously weakening the strength of the anchor body.

[0004] (2) Defects in structure forming: After the hole enlargement operation, the shape of the cavity is irregular, resulting in difficult insertion of the anchor plate and insufficient positioning accuracy, directly affecting the mechanical properties of the rock bolt structure.

[0005] (3) Problem of process complexity: The current process includes multiple independent processes such as drilling the ordinary section, hole enlargement, hole cleaning, installing the anchor, and grouting. The requirements for process connection are high, and the quality control nodes are scattered, which is easy to cause the accumulation of construction errors.

[0006] The superposition effect of the above problems results in a significant deviation between the actual bearing capacity of the rock bolt and the design value. Especially in soft soil geological conditions, the phenomenon of bearing capacity reduction often occurs, seriously restricting the engineering applicability of this technology. Therefore, it is urgent to develop a new construction process to solve the defects of the existing technology. Summary of the Invention

[0007] To reduce the problem of a significant deviation between the actual bearing capacity of the rock bolt and the design value, the present application first proposes a drill pipe for the construction of integrally mixed and formed cement-soil stiffened rock bolts, which includes a drill head and a hollow drill pipe extending along the first axis direction. The drill head includes a housing, an anchor plate fixed in the housing, and a spiral blade welded to the housing. The hollow drill pipe is inserted into the housing. The hollow drill pipe can drive the drill head to rotate, and when the hollow drill pipe moves away from the drill head, the hollow drill pipe can be disengaged from the drill head;

[0008] The sheathed steel pipe is inserted into the hollow drill pipe, and the sheathed steel pipe is fixed to the outer shell. The grouting pipe is inserted into the sheathed steel pipe. One end of the rod body passes through the inner cavity of the sheathed steel pipe and is fixed to the anchor plate, and the other end of the rod body extends away from the drill head direction and extends out of the sheathed steel pipe. The sheathed steel pipe is coaxially arranged with the hollow drill pipe. A first grouting hole communicating the inside and outside of the outer shell is opened on the outer shell, and a second grouting hole communicating the inside and outside of the sheathed steel pipe is opened on the pipe wall of the sheathed steel pipe.

[0009] The present application has the following advantages:

[0010] 1. When using this drill pipe to construct the cement-soil rigid anchor rod, while drilling the anchor hole, the installation of the rod body and the injection of cement slurry are completed at the same time, so that processes such as hole forming, anchor setting, and grouting are integrally formed. The construction process is simple, the construction speed is fast, and the construction quality is easy to control.

[0011] 2. Since the spiral blade is used for stirring, the internal structure of the formed cement-soil pile body is uniform and the pile body strength is reliable.

[0012] 3. The cement-soil rigid anchor rod formed by using the drill pipe in the present application is fully length anchored and stressed, and the tension distribution of the anchor rod is more uniform, which can reduce the stress concentration phenomenon and improve the safety of the anchoring system. While the traditional underreamed anchor rod is stressed at the end of the anchor rod, and the tension of the anchor rod is mainly concentrated on the end anchor, which is easy to cause local stress concentration.

[0013] 4. After the construction of the cement-soil is completed, the hollow drill pipe is lifted upward and separated from the drill head, so that the drill head remains underground. Since the spiral blade is made of steel structure and the end of the anchor rod is a blade-cement-soil rigid composite structure, it has the advantage of good integrity. By using the spiral blade, the strength of the cement-soil pile body can be adjusted by increasing the stirring times and the cement content, so that the strength of the whole end is high and the safety is good.

[0014] 5. Vertical or inclined anti-pull anchor rods can be constructed, and the applicable scenarios are numerous. Specifically, it can be applied to projects such as basement anti-floating, inclined anchor pulling in foundation pit engineering, and inclined anchor pulling of flexible photovoltaic brackets. Therefore, by using this drill pipe, the deviation between the actual bearing capacity of the anchor rod and the design value can be effectively reduced.

[0015] Furthermore, an end plate is fixedly arranged in the outer shell, and the end plate is located on the side of the anchor plate facing the hollow drill pipe. A slurry cavity is formed between the end plate and the anchor plate, and the grouting pipe communicates with the slurry cavity; in the first axis direction, the first grouting hole is located between the end plate and the anchor plate, and the first grouting hole is within the height range of the spiral blade; the sheathed steel pipe is welded to the end plate. The slurry cavity can effectively maintain the pressure during grouting and prevent the slurry from overflowing upward along the protective sleeve.

[0016] Furthermore, to enable the cement slurry to smoothly enter the slurry cavity and, after grouting is completed, to be able to recover the grouting pipe, the drill head further includes a grouting connection pipe, which is hermetically welded to the end plate and communicates with the slurry cavity. The grouting pipe is inserted into the grouting connection pipe, and by pulling the grouting pipe, the grouting pipe can be disengaged from the grouting connection pipe. By using the grouting connection pipe, the cement slurry can be smoothly injected into the slurry cavity. Since the grouting pipe is inserted into the grouting connection pipe, when the grouting pipe is pulled out, the grouting pipe can be disengaged from the grouting connection pipe to recover the grouting pipe.

[0017] Specifically, a passive member is fixed on the pipe wall of the outer shell, and a driving member is fixed on the pipe wall of the hollow drill pipe. When the hollow drill pipe is inserted into the outer shell, the driving member can press against the passive member circumferentially, enabling the hollow drill pipe to drive the drill head to rotate synchronously. This design not only ensures that the hollow drill pipe can drive the drill head to rotate, but also enables the hollow drill pipe to be smoothly separated axially when the hollow drill pipe is pulled, so as to recover the hollow drill pipe.

[0018] Specifically, to facilitate fixing the rod body, the outer shell includes a drill pipe steel pipe extending along the first axis direction and a guide cap fixed on the drill pipe steel pipe. The guide cap is installed on the drill pipe steel pipe after the rod body is fixed on the anchor plate. When assembling the drill pipe, first fix the rod body on the anchor plate, then weld the anchor plate to one end of the drill pipe steel pipe and make the rod body extend out from the other end of the drill pipe steel pipe, and then weld the guide cap to the drill pipe steel pipe. Or first weld the anchor plate inside the drill pipe steel pipe, and then weld the guide cap to the drill pipe steel pipe after fixing the rod body on the anchor plate.

[0019] Furthermore, slurry passing holes penetrating the anchor plate are provided on the anchor plate, and end spraying holes are provided at one end of the guide cap away from the hollow drill pipe. During the construction process, when the drill pipe is drilled underground, the cement slurry is sprayed downward from the end spraying holes to the drill head. The cement slurry can not only moisten the underground soil body, reduce the hardness of the underground soil body, but also pre-stir the cement slurry and the underground soil body to improve the mixing uniformity of the cement slurry and the underground soil body.

[0020] Specifically, the rod body includes at least one cable or threaded steel. When the rod body includes at least two cables or threaded steels, the at least two cables or threaded steels are evenly spaced around the central axis of the steel sleeve. The cable can specifically be a steel strand or a glass fiber composite cable, and the threaded steel can specifically be a precision rolled threaded steel or a common threaded steel. In specific construction, appropriate materials can be selected to make the rod body according to actual needs.

[0021] The anchor cable can specifically be a steel strand or a glass fiber composite anchor cable. When the rod body is made of an anchor cable, to prevent the drill head from separating from the hollow drill pipe, after the drill pipe is assembled, the anchor cable needs to be tightened and fixed at one end of the sheath steel pipe away from the drill head. When the anchor cable needs to be tensioned, it is then disassembled from the sheath steel pipe. When the rod body is made of deformed steel bars, there is no need to fix it.

[0022] Secondly, the present application also discloses a construction method of an integrally mixed and formed soil-cement stiff anchor rod, which is carried out by using the drill pipe described in any one of the above. The construction method includes the following steps:

[0023] (1.1) Rotate the drill pipe underground along the set direction, and at the same time spray the first cement slurry outward through the first grouting hole, so that the first cement slurry is mixed with the underground soil to form a soil-cement pile body until the drill pipe reaches the set depth;

[0024] (1.2) Pull out the hollow drill pipe, tension the rod body, and then inject the second cement slurry into the sheath steel pipe through the grouting pipe. While injecting the second cement slurry, lift the grouting pipe upward. The second cement slurry diffuses outward through the second grouting hole and merges with the first cement slurry. After the injection of the second cement slurry is completed, recover the grouting pipe; the drill head remains underground.

[0025] Alternatively, the construction method of the integrally mixed and formed soil-cement stiff anchor rod includes the following steps:

[0026] (2.1) Rotate the drill pipe underground along the set direction, and at the same time spray the first cement slurry outward through the first grouting hole, so that the first cement slurry is mixed with the underground soil to form a soil-cement pile body until the drill pipe reaches the set depth;

[0027] (2.2) Pull out the hollow drill pipe, and then inject the second cement slurry into the sheath steel pipe. The second cement slurry diffuses outward through the second grouting hole and merges with the first cement slurry; the drill head remains underground.

[0028] Specifically, in the above two construction methods, the angle between the drill pipe and the vertical direction is 0 - 60°.

[0029] In the above two construction methods, when drilling the anchor holes, the installation of the rod body and the injection of cement slurry are completed simultaneously, enabling the integration of processes such as hole formation, anchor placement, and grouting. The construction process is simple, the construction speed is fast, and the construction quality is easy to control. The spiral blades are used for stirring, making the internal structure of the formed soil-cement pile body uniform and the pile body strength reliable. The completed soil-cement stiffened anchor is fully anchored and stressed, and the tensile force distribution of the anchor is more uniform, which can reduce the stress concentration phenomenon and improve the safety of the anchoring system. In contrast, the traditional underreamed anchor is stressed at the end of the anchor, and the tensile force of the anchor is mainly concentrated on the end anchor, which is prone to local stress concentration. Since the end of the anchor is a steel pipe spiral blade soil-cement stiffened composite structure with the advantage of good integrity, the spiral blades can be used to adjust the strength of the soil-cement pile body by increasing the stirring times and the cement content, making the strength of the entire end high and the safety good. The above construction methods are applicable to many scenarios and can be specifically applied to projects such as basement anti-floating, inclined anchor pulling in foundation pit engineering, and inclined anchor pulling of flexible photovoltaic brackets.

[0030] In specific construction, different construction methods can be adopted according to needs. Brief Description of the Drawings

[0031] Figure 1 is a schematic structural diagram of the drill pipe in this application.

[0032] Figure 2 is Figure 1 an enlarged view of part A in

[0033] Figure 3 is Figure 2 a schematic diagram after removing part of the structure.

[0034] Figure 4 is Figure 3 a view in the B-B direction in

[0035] Figure 5 is a schematic structural diagram of the connection between the hollow drill pipe and the drill head.

[0036] Figure 6 is a construction flow chart of the integrally mixed and formed soil-cement stiffened anchor in this application. Detailed Description of the Preferred Embodiments

[0037] Example 1

[0038] First, the structure of the drill pipe for the construction of the integrally mixed and formed soil-cement stiffened anchor will be described in detail below. Please refer to Figures 1-5 , in the drawings, the direction indicated by the arrow Y represents the first axis direction.

[0039] The drill pipe includes a drill head 10 and a hollow drill pipe 41 extending along a first axis direction. The drill head 10 includes a housing 101, an anchor plate 17 fixed within the housing 101, and a steel spiral blade 13 welded to the housing. Specifically, in this embodiment, the housing 101 includes a drill pipe 12 extending along the first axis direction and a guide cap 11 fixed to the drill pipe. The guide cap 11 has a conical drill tip 111 that protrudes away from the drill pipe. The guide cap is installed on the drill pipe after fixing the following rod body to the anchor plate 17.

[0040] The hollow drill pipe 41 is inserted into the drill pipe 12 of the housing. The hollow drill pipe can drive the drill head to rotate, and when the hollow drill pipe moves away from the drill head, the hollow drill pipe can be disengaged from the drill head. A passive member is fixed to the pipe wall of the housing 101, and a pushing member is fixed to the pipe wall of the hollow drill pipe 41. When the hollow drill pipe is inserted into the housing, the pushing member can press against the passive member circumferentially, enabling the hollow drill pipe to drive the drill head to rotate synchronously. Specifically, in this embodiment, the passive member is a first half pipe 16 welded to the inner wall of the drill pipe 12, and the pushing member is a second half pipe 44 welded to the inner wall of the hollow drill pipe. The first half pipe extends out of the drill pipe, and the second half pipe extends out of the hollow drill pipe. The hollow drill pipe and the drill pipe are made of steel pipes of the same model, and the first half pipe and the second half pipe are cut from the same steel pipe along the central axis. When the hollow drill pipe is inserted into the housing, the first half pipe is inserted into the hollow drill pipe, and the second half pipe is inserted into the drill pipe, and the side surface of the second half pipe can press against the side surface of the first half pipe, that is, the pushing member can press against the passive member circumferentially. When the hollow drill pipe is rotated, the drill head can be driven to rotate through the first half pipe and the second half pipe.

[0041] It can be understood that in other embodiments, the first half pipe and the second half pipe can also be welded to the outer walls of the drill pipe and the hollow drill pipe respectively, or the pushing member and the passive member can be designed as a spline structure that can be inserted into each other. For example, a first strip-shaped protrusion extending along the first axis direction is provided on the inner wall of the drill pipe, and a second strip-shaped protrusion extending along the first axis direction is provided on the outer wall of the hollow drill pipe, and the outer diameter of the hollow drill pipe is smaller than the inner diameter of the drill pipe. When the hollow drill pipe is inserted into the drill pipe, the first strip-shaped protrusion and the second strip-shaped protrusion can be arranged at intervals; of course, the first strip-shaped protrusion can also be provided on the outer wall of the drill pipe, and the second strip-shaped protrusion can be provided on the inner wall of the hollow drill pipe, and the outer diameter of the drill pipe is smaller than the inner diameter of the hollow drill pipe, so that the drill pipe can be inserted into the interior of the hollow drill pipe, and the first strip-shaped protrusion and the second strip-shaped protrusion are arranged at intervals, or a notch can be used to replace the first strip-shaped protrusion or the second strip-shaped protrusion.

[0042] The anchor plate 17 is welded to one end of the drill pipe 12 facing away from the hollow drill rod. An end plate 14 is also welded inside the drill pipe 12, and the end plate 14 is located on the side of the anchor plate 17 facing the hollow drill rod. A slurry cavity 123 is formed between the end plate and the anchor plate. The sheath steel pipe 21 is inserted into the hollow drill rod 41, and the sheath steel pipe 21 is welded to the end plate 14, so that the sheath steel pipe is fixed to the housing through the end plate 14, and the sheath steel pipe and the hollow drill rod are coaxially arranged.

[0043] The drill head 10 further includes a grouting connection pipe 43. There is a grouting hole 15 in the center of the end plate 14. The grouting connection pipe is hermetically welded to the end plate and communicates with the grouting hole 15. The grouting connection pipe extends away from the anchor plate. One end of the grouting pipe 42 is inserted into the grouting connection pipe, so that the grouting pipe communicates with the slurry cavity 123 through the grouting connection pipe. Pulling the grouting pipe can disconnect the grouting pipe from the grouting connection pipe. In this embodiment, the grouting pipe is specifically a plastic pipe, which is sleeved on the grouting connection pipe and tied with a clamp. When the grouting pipe is pulled, the grouting pipe can be pulled off from the grouting connection pipe for recycling. It can be understood that in another embodiment, the grouting connection pipe can also be cancelled, the grouting pipe can be tied to the following rod body, and the grouting pipe can be inserted into the grouting hole so that the cement slurry can smoothly enter the slurry cavity. Of course, the grouting pipe can also be made of a metal pipe, and the grouting pipe is movably inserted into the sheath steel pipe and abuts against the edge of the grouting hole or the grouting pipe is inserted into the grouting hole. If the grouting pipe does not need to be recycled, the grouting pipe can be welded to the end plate and the grouting pipe is hermetically connected to the grouting hole.

[0044] A first grouting hole 121 communicating inside and outside the housing is opened on the drill pipe of the housing. In this embodiment, several first grouting holes 121 are arranged along the circumferential direction of the drill pipe. There is no specific limit on the number of the first grouting holes, as long as the cement slurry can be evenly sprayed into the surrounding soil. The number of the first grouting holes is controlled between 2 and 20.

[0045] In the first axis direction, the first grouting hole is located between the end plate and the anchor plate, and the first grouting hole is within the height range of the spiral blade. An end grouting hole 112 is provided on the drill tip of the guide cap, that is, an end grouting hole is provided at one end of the guide cap away from the hollow drill rod. A second grouting hole 211 communicating inside and outside the sheath steel pipe is opened on the pipe wall of the sheath steel pipe.

[0046] In this embodiment, the rod body is composed of three steel strands 22, and the steel strands are specifically fixed by wedge-type anchors. Corresponding to each steel strand 22, a through-plate hole 141 is formed in the end plate 14, and an anchoring hole 18 is formed in the anchor plate. After each steel strand 22 passes through the corresponding through-plate hole 141 and anchoring hole 18 in sequence, a set of wedges 31 is installed. The anchoring hole is a conical hole with the small end facing the end plate. The set of wedges 31 is arranged in the anchoring hole 18. On the side of the anchor plate facing away from the end plate, a pressing plate 33 is provided. After the locking bolt 34 passes through the bolt hole 172 in the anchor plate and the pressing plate, the pressing plate is connected to the anchor plate, and a sleeve 32 sleeved on the steel strand is provided between the anchor plate and the pressing plate. The two ends of the sleeve respectively abut against the end faces of the pressing plate and the wedges in the set of wedges, so that one end of the rod body passes through the inner cavity of the sheath steel pipe and is fixed on the anchor plate, and the other end of the rod body extends in the direction away from the drill head and extends out of the sheath steel pipe. To facilitate the entry of cement slurry into the guide cap, a slurry passing hole 171 communicating the slurry cavity with the inner cavity of the guide cap is formed in the anchor plate.

[0047] When assembling the drill pipe, first pass each steel strand through the anchor plate and the end plate, and fix each steel strand on the anchor plate, then weld the anchor plate and the end plate inside the drill pipe, and extend each steel strand out of the drill pipe, and then weld the guide cap on the drill pipe. Or, first weld the anchor plate and the end plate inside the drill pipe, then fix each steel strand on the anchor plate, and finally weld the guide cap on the drill pipe.

[0048] The three steel strands 22 are evenly spaced around the central axis of the steel sleeve, and the three steel strands 22 are evenly spaced around the grouting connection pipe. It can be understood that the steel strand can also be replaced by a glass fiber composite anchor cable, and both the steel strand and the glass fiber composite anchor cable are anchor cables. In other embodiments, the rod body can also be made of threaded steel. When the rod body is made of threaded steel, the rod body can be fixed with corresponding nuts, and there is no need to use a set of wedges and corresponding components. The threaded steel can specifically be precision rolled threaded steel or ordinary threaded steel.

[0049] To prevent the drill head from separating from the hollow drill pipe, after the drill pipe is assembled, the steel strands are tightened and fixed at one end of the sheath steel pipe away from the drill head. When the steel strands need to be tensioned, the steel strands are disassembled from the sheath steel pipe. When the rod body is made of a glass fiber composite anchor cable, a similar method is also needed to fix the glass fiber composite anchor cable on the sheath steel pipe. When the rod body is made of threaded steel, there is no need to fix it.

[0050] Embodiment 2

[0051] The construction method of the integrally mixed and formed cement-soil stiffening anchor rod is described below. Please refer to Figure 6 , and this construction method uses the drill pipe in Embodiment 1. This construction method includes the following steps:

[0052] (1.1) Refer to Figure 6 Steps (a) and (b) in to position the drill pipe at the set position, and then drill the drill pipe underground along the set direction. At the same time, inject the first cement slurry into the slurry cavity 123 through the grouting pipe. The first cement slurry in the slurry cavity is sprayed out through the first grouting holes 121, so that the first cement slurry is mixed with the underground soil to form a cement-soil pile body 51. The cement slurry in the slurry cavity also enters the drill tip of the guide cap and is sprayed out through the end grouting holes 112 to facilitate disturbing the lower soil body and increasing the humidity, which is beneficial to accelerating the drilling speed. Refer to Figure 6 Step (c) in to continuously drill downward and spray the first cement slurry until the drill pipe reaches the set depth.

[0053] In this embodiment, the drill pipe extends in the vertical direction, that is, the included angle between the drill pipe and the vertical direction is 0°. It can be understood that in other embodiments, the included angle between the drill pipe and the vertical direction is 10°, 20°, 30°, 45°, 50° or 60°, and of course it can also be other angles between 0 - 60°.

[0054] (1.2) Refer to Figure 6 Step (d) in to pull out the hollow drill pipe and tension the steel strand 22 serving as the rod body to generate prestress on the steel strand.

[0055] Refer to Figure 6 Step (e) in to then inject the second cement slurry into the sheath steel pipe through the grouting pipe. While injecting the second cement slurry, lift the grouting pipe upward to separate the grouting pipe from the grouting connection pipe. The second cement slurry diffuses outward through the second grouting holes and merges with the first cement slurry. After the injection of the second cement slurry is completed, recover the grouting pipe; the drill head remains underground.

[0056] Embodiment 3

[0057] This embodiment is another construction method of an integrally mixed and formed cement-soil stiffened anchor rod. In this embodiment, this construction method is carried out using the drill pipe in Embodiment 1, and the specific steps are as follows:

[0058] (2.1) Drill the drill pipe underground along the set direction. At the same time, inject the first cement slurry into the slurry cavity 123 through the grouting pipe. The first cement slurry in the slurry cavity is sprayed out through the first grouting holes 121, so that the first cement slurry is mixed with the underground soil to form a cement-soil pile body 51. The cement slurry in the slurry cavity also enters the drill tip of the guide cap and is sprayed out through the end grouting holes 112 to facilitate disturbing the lower soil body and increasing the humidity, which is beneficial to accelerating the drilling speed. Continuously drill downward and spray the first cement slurry until the drill pipe reaches the set depth.

[0059] In this embodiment, the drill pipe extends in the vertical direction, that is, the angle between the drill pipe and the vertical direction is 45°. It can be understood that in other embodiments, the angle between the drill pipe and the vertical direction is 0°, 10°, 20°, 30°, 40°, 50° or 60°, and of course it can also be other angles between 0 and 60°.

[0060] (2.2) Remove the hollow drill pipe and the grouting pipe, and then inject the second cement slurry into the steel sheath pipe. The second cement slurry diffuses outward through the second grouting holes and merges with the first cement slurry; the drill head remains underground.

[0061] It can be understood that in other embodiments, the grouting pipe can also be directly left underground.

Claims

1. A drill rod for construction of an integrally mixed cement soil rigid anchor, characterized in that: The drill head comprises a drill head and a hollow drill rod extending along a first axis direction, the drill head comprises a shell, an anchor plate fixed in the shell, and a spiral blade welded to the shell, the hollow drill rod is plugged into the shell, the hollow drill rod can drive the drill head to rotate, and when the hollow drill rod moves in a direction away from the drill head, the hollow drill rod can be separated from the drill head; The sheath steel pipe is inserted into the hollow drill rod and fixed on the outer shell. The grouting pipe is inserted into the sheath steel pipe. One end of the rod body passes through the inner cavity of the sheath steel pipe and is fixed on the anchor plate, and the other end of the rod body extends in a direction away from the drill head and extends out of the sheath steel pipe. The sheath steel pipe is coaxially arranged with the hollow drill rod. A first grouting hole connecting the inside and outside of the outer shell is opened on the outer shell, and a second grouting hole connecting the inside and outside of the sheath steel pipe is opened on the pipe wall of the sheath steel pipe.

2. The drill pipe according to claim 1, characterized in that: An end plate is also fixedly arranged in the outer shell, and the end plate is located on the side of the anchor plate facing the hollow drill rod. A slurry cavity is formed between the end plate and the anchor plate, and the grouting pipe is connected to the slurry cavity. In the first axial direction, the first grouting hole is located between the end plate and the anchor plate, and the first grouting hole is located within the height range of the spiral blade. The sheath steel pipe is welded to the end plate.

3. The drill pipe according to claim 2, characterized in that: The drill head also includes a grouting pipe, which is sealed and welded to the end plate and connected to the slurry cavity. The grouting pipe is plugged into the grouting pipe, and the grouting pipe can be pulled away from the grouting pipe.

4. The drill pipe according to claim 1, characterized in that: A passive component is fixed on the tube wall of the shell, and a pushing component is fixed on the tube wall of the hollow drill rod. When the hollow drill rod is plugged into the shell, the pushing component can press against the passive component along the circumferential direction, so that the hollow drill rod can drive the drill head to rotate synchronously.

5. The drill pipe according to claim 1, characterized in that: The housing comprises a drill bit steel pipe extending along the first axial direction and a guide cap fixed on the drill bit steel pipe. The guide cap is installed on the drill bit steel pipe after the rod body is fixed on the anchor plate.

6. The drill pipe according to claim 5, characterized in that A grouting hole penetrating the anchor plate is provided on the anchor plate, and an end grouting hole is provided on the end of the guide cap away from the hollow drill rod.

7. The drill pipe according to claim 1, characterized in that The rod body comprises at least one anchor cable or threaded steel bar. When the rod body comprises at least two anchor cables or threaded steel bars, the at least two anchor cables or threaded steel bars are evenly spaced around the central axis of the steel sleeve.

8. A construction method for an integrated mixing and forming cement soil rigid anchor bolt, characterized in that: The construction method is carried out using the drill rod according to any one of claims 1 to 7, and comprises the following steps: (1.1) Rotate the drill rod underground along a set direction, and simultaneously spray the first cement slurry outward through the first grouting hole, so that the first cement slurry mixes with the underground soil to form a cement soil pile body, until the drill rod reaches the set depth; (1.2) Remove the hollow drill rod, tension the rod body, and then inject the second cement slurry into the sheathed steel pipe through the grouting pipe. While injecting the second cement slurry, lift the grouting pipe upward. The second cement slurry diffuses outward through the second grouting hole and merges with the first cement slurry. After the injection of the second cement slurry is completed, recover the grouting pipe; the drill head remains underground.

9. A construction method for an integrated mixing and forming cement soil rigid anchor bolt, characterized in that: The construction method is carried out using the drill rod according to any one of claims 1 to 7, and comprises the following steps: (2.1) Rotate the drill rod underground along the set direction, and simultaneously spray the first cement slurry outward through the first grouting hole, so that the first cement slurry mixes with the underground soil to form a cement soil pile body, until the drill rod reaches the set depth; (2.2) The hollow drill rod is removed, and then the second cement slurry is injected into the sheath steel pipe. The second cement slurry diffuses outward through the second grouting hole and merges with the first cement slurry. The drill head is retained underground.

10. The construction method according to claim 8 or 9, characterized in that: The angle between the drill pipe and the vertical direction is 0-60°.

Citation Information

Cited By

  • Water injection and grouting type spiral anchor foundation and construction method

    CN120700922A

  • One-time drilling anchor rod and construction method thereof

    CN120719661A

  • Disposable drill hole anchor rod and construction method thereof

    CN120719661B

  • Underwater rock wall drilling anchor and construction method

    CN120819098A

  • An underwater rock wall drilling anchor and its construction method

    CN120819098B