Rock mining method

Through the combination of carbon dioxide phase transition fracture and crushing technology and protective devices, the problems of low efficiency and poor safety of rock mining are solved, and efficient, safe and environmentally friendly rock mining is achieved.

CN120465930APending Publication Date: 2025-08-12CHINA RAILWAY 19 BUREAU GRP CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202510558269.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-04-29
Publication Date
2025-08-12

AI Technical Summary

Technical Problem

The existing rock mining methods are inefficient and poor in safety, and there are problems such as blasting safety hazards, low mechanical crushing efficiency, and serious resource waste.

Method used

Carbon dioxide phase transformation cracking and crushing technology is adopted, and protective devices are set up by cleaning the soil layer to form phase transformation cracking steps according to the rules, and precise crushing is used to use carbon dioxide phase transformation cracking devices, and cutting grooves are formed in combination with mechanical crushing to control the range and degree of crushing.

Benefits of technology

It improves mining efficiency, reduces resource waste, reduces safety risks and environmental pollution, ensures the safety of personnel and facilities, and meets environmental protection requirements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120465930A_ABST
    Figure CN120465930A_ABST
Patent Text Reader

Abstract

The invention provides a rock mining method, and belongs to the field of rock mining. Comprising the following steps that S100, a soil layer is cleared and transported, the soil layer covered by a rock stratum is cleared and transported, and a protection device is arranged; step S200, performing carbon dioxide phase change fracturing crushing: performing carbon dioxide phase change fracturing crushing on the rock according to a first rule to form a plurality of phase change fracturing steps, and performing carbon dioxide phase change fracturing crushing on the plurality of phase change fracturing steps according to a second rule; s300, rock clearing and transporting, wherein the crushed rock is cleared and transported; and S400, rock mining is completed. The rock mining method aims at solving the problems that in the prior art, a rock mining method is low in mining efficiency and poor in safety. The device has the technical effects that the safety is guaranteed while the mining efficiency is improved while excessive mining and waste of rocks are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of rock mining, and in particular to a rock mining method. Background Art

[0002] In the field of rock mining, traditional mining methods face many challenges and difficulties, which has also prompted the exploration and development of new rock mining methods.

[0003] In the past, common rock extraction methods included explosive blasting and mechanical crushing. While explosive blasting is highly efficient, it carries significant safety risks. The intense vibrations and shock waves generated during blasting can not only cause severe damage to surrounding buildings and infrastructure, but also pose a direct threat to the lives of on-site construction workers. Furthermore, the dust generated by blasting can cause severe atmospheric pollution, and the noise generated by blasting can disrupt the lives of nearby residents.

[0004] Mechanical crushing and mining are inefficient. Small-scale mechanical crushing equipment often struggles with hard, large-scale rock, resulting in extremely slow mining progress. While large-scale machinery offers greater crushing power, it is expensive and complex to operate, requiring specialized technicians for operation and maintenance. This undoubtedly increases the labor cost and technical difficulty of mining.

[0005] In addition, whether it is blasting mining or mechanical crushing mining, it is difficult to accurately control the mining range and crushing degree during the mining process, which easily leads to waste of resources. Summary of the Invention

[0006] The present invention provides a rock mining method to solve the defects of low mining efficiency and poor safety of rock mining methods in the prior art, thereby avoiding excessive mining and waste of rocks while increasing mining efficiency and ensuring safety.

[0007] The present invention provides a rock mining method, comprising the following steps: Step S100: clearing the soil layer, clearing the soil layer covered by the rock layer and setting up protective devices; Step S200: Carbon dioxide phase change cracking and crushing, performing carbon dioxide phase change cracking and crushing on the rock according to a first rule to form a plurality of phase change cracking steps, and performing carbon dioxide phase change cracking and crushing on the plurality of phase change cracking steps according to a second rule; Step S300: rock removal, which involves removing the crushed rocks; Step S400: rock mining is completed.

[0008] In addition, the rock mining method according to the present invention may also have the following additional technical features: In some embodiments of the present invention, in step S200, the first rule is: carbon dioxide phase change fracture and crushing are performed on each layer of rock from top to bottom to form a plurality of phase change fracture steps.

[0009] In some embodiments of the present invention, in the first rule: before fracturing and crushing each layer of rock, at least one cutting groove is mined in the layer of rock using mechanical crushing.

[0010] In some embodiments of the present invention, the second rule is: performing carbon dioxide phase change cracking and crushing on multiple phase change cracking steps from bottom to top or from top to bottom in sequence until carbon dioxide phase change cracking and crushing on all phase change cracking steps is completed.

[0011] In some embodiments of the present invention, in step S200, the method for carbon dioxide phase change cracking and fracturing of each rock layer in the first rule and the method for carbon dioxide phase change cracking and fracturing of each phase change cracking step in the second rule both include the following steps: Step S210: drilling phase change crack holes; Step S220: Filling the phase change cracking hole with a carbon dioxide phase change cracking device; Step S230: connecting the conductive network and igniting the explosion; Step S240: Inspection and recycling.

[0012] In some embodiments of the present invention, in step S200, in the first rule, before each rock layer is fractured by carbon dioxide phase transition, the rock blocks formed by the rock layer that has been fractured by carbon dioxide phase transition are transported out; In the second rule, before each phase change fracture step is broken, the broken rock blocks formed after the carbon dioxide phase change fracture are transported out.

[0013] In some embodiments of the present invention, in step S100, the method for setting a protective device includes the following steps: Step S110: Connect multiple bamboo frame steel pipes and lay them on the foundation pit beams; Step S120: Covering the connected bamboo frame with a carpet; Step S130: laying sandbags on top of the carpet; Step S140: Cover the sandbag with a cannon quilt; Step S150: Cover the quilt with a wire mesh and secure it with anchoring steel bars; Step S160: The protection device is set up.

[0014] In some embodiments of the present invention, in step 210 , the phase change induced fracturing excavation area is measured and calibrated and the hole position is calibrated before drilling the phase change induced fracturing hole.

[0015] In some embodiments of the present invention, in step 230 , the phase change crack holes are filled before connecting the conductive network.

[0016] In some embodiments of the present invention, in step S220, before the carbon dioxide phase change fracturing device is filled into the phase change fracturing hole, the parameters of the carbon dioxide phase change fracturing device are set according to the parameters of the phase change fracturing hole.

[0017] In summary, this application includes the following beneficial technical effects: by setting up a soil clearing layer, the soil layer covering the rock layer can be effectively removed, providing a safe operating space for subsequent operations; by setting up a protective device, the accidental risks such as stone splashing and collapse that may occur during the mining process can be greatly reduced, thereby ensuring the safety of personnel and surrounding facilities.

[0018] The impact force generated by carbon dioxide phase-change fracturing of rock is relatively mild and controllable. Phase-change fracturing steps are formed according to the first principle, and secondary crushing is carried out according to the second principle. This precisely controls the scope and extent of rock fragmentation, minimizing disturbance to surrounding rocks, ensuring safety, improving resource utilization, and increasing mining efficiency while avoiding over-exploitation and waste. Furthermore, the carbon dioxide phase-change process does not produce harmful gases or large amounts of dust, significantly reducing environmental pollution and meeting environmental protection requirements. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Various other advantages and benefits will become apparent to those skilled in the art upon reading the detailed description of the preferred embodiment below. The accompanying drawings are for illustration purposes only and are not to be considered as limiting the present invention. The same reference numerals are used throughout the accompanying drawings to denote the same components. In the accompanying drawings: Figure 1 A flow chart of a rock mining method according to some embodiments of the present invention is schematically shown.

[0020] Figure 2 The structure diagram of the continuous phase change fracture steps in the foundation pit of the rock mining method according to some embodiments of the present invention is schematically shown.

[0021] Figure 3 The structure diagram of the cutting groove in the foundation pit of the rock mining method according to some embodiments of the present invention is schematically shown.

[0022] Figure 4 The structure diagram of the carbon dioxide phase change fracturing device disposed in the phase change fracturing hole of the rock mining method according to some embodiments of the present invention is schematically shown.

[0023] Figure 5 A schematic diagram of the arrangement of phase change-induced fracturing holes in a rock mining method according to some embodiments of the present invention is schematically shown.

[0024] Figure 6 The structure diagram of the conductive network of the rock mining method according to some embodiments of the present invention is schematically shown.

[0025] Reference numerals: 1. First fracturing zone, 2. Second fracturing zone, 3. Excavator, 4. Phase change fracturing step, 41. Phase change fracturing hole, 5. Cutting groove, 51. Free surface, 6. Carbon dioxide phase change fracturing device, 7. Pulling tube, 81. Initiator, 82. Main line, 83. Branch line, 84. Ignition head. DETAILED DESCRIPTION

[0026] Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments described herein. Rather, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art.

[0027] It should be understood that the terms used herein are for the purpose of describing specific example embodiments only and are not intended to be limiting. Unless the context clearly indicates otherwise, the singular forms "one", "an", and "" as used herein may also be meant to include plural forms. The terms "comprise", "include", "contain", and "have" are inclusive and therefore specify the presence of the stated features, steps, operations, elements, and / or parts, but do not exclude the presence or addition of one or more other features, steps, operations, elements, parts, and / or combinations thereof. The method steps, processes, and operations described herein are not to be construed as necessarily requiring them to be performed in the specific order described or illustrated, unless the order of execution is clearly indicated. It should also be understood that additional or alternative steps may be used.

[0028] Although the terms first, second, third, etc. can be used in the text to describe multiple elements, components, regions, layers and / or sections, these elements, components, regions, layers and / or sections should not be limited by these terms. These terms can only be used to distinguish an element, component, region, layer or section from another region, layer or section. Unless the context clearly indicates otherwise, terms such as "first", "second" and other numerical terms do not imply order or sequence when used in the text. Therefore, the first element, component, region, layer or section discussed below can be referred to as the second element, component, region, layer or section without departing from the teaching of the example embodiments.

[0029] For ease of description, spatially relative terms may be used herein to describe the relationship of one element or feature relative to another element or feature as shown in the figures, such as "inside," "outside," "inside," "outside," "below," "beneath," "above," and the like. Such spatially relative terms are intended to include different orientations of the device in use or operation in addition to the orientation depicted in the figures. For example, if the device in the figures is flipped, an element described as "below" or "below" another element or feature would then be oriented as "above" or "above" another element or feature. Thus, the example term "below" may include both above and below orientations. The device may be otherwise oriented rotated 90 degrees or in other orientations and the spatially relative descriptors used herein are interpreted accordingly.

[0030] like Figure 1 As shown, according to an embodiment of the first aspect of the present invention, a rock mining method is proposed, comprising the following steps: Step S100: clearing the soil layer, clearing the soil layer covered by the rock layer and setting up protective devices; Step S200: Carbon dioxide phase change cracking and crushing: performing carbon dioxide phase change cracking and crushing on the rock according to a first rule to form a plurality of phase change cracking steps 4; and performing carbon dioxide phase change cracking and crushing on the plurality of phase change cracking steps 4 according to a second rule; Step S300: rock removal, which involves removing the crushed rocks; Step S400: rock mining is completed.

[0031] In the above embodiment, it should be noted that the method for clearing and transporting the rocks is to use a plurality of excavators to carry out three-step relay transport to clean up the fractured and crushed rocks.

[0032] The technical effects achieved by the above embodiments are as follows: by setting up the soil layer for clearing, the soil layer covering the rock layer can be effectively removed, providing a safe operating space for subsequent operations; by setting up the protective device, the accidental risks such as stone splashing and collapse that may occur during the mining process can be greatly reduced, thereby ensuring the safety of personnel and surrounding facilities.

[0033] The impact force generated by rock fragmentation through carbon dioxide phase-change fracturing is relatively mild and controllable. The phase-change fracturing step (four steps) is formed according to the first principle, and secondary crushing is performed according to the second principle. This precisely controls the scope and extent of rock fragmentation, minimizing disturbance to surrounding rocks, improving resource utilization, avoiding over-mining and waste, and increasing mining efficiency. Furthermore, the carbon dioxide phase-change process produces no harmful gases or significant amounts of dust, significantly reducing environmental pollution and meeting environmental protection requirements.

[0034] Optional, such as Figure 1and Figure 2 As shown, in step S200, the first rule is: carbon dioxide phase change fracture is performed on each layer of rock from top to bottom to form a plurality of phase change fracture steps 4.

[0035] The beneficial effects of the above-mentioned optional embodiment are as follows: the formation of the phase-change fracture steps 4 by sequentially fracturing the rock from top to bottom ensures a safe and orderly mining process; the method of first fracturing the upper layer of rock from top to bottom avoids the risk of the upper rock accidentally falling on the lower layer. Furthermore, the layered fracturing of the rock facilitates precise control of the crushing process, creates favorable conditions for subsequent operations, and improves rock mining efficiency.

[0036] Optional, such as Figures 1 to 3 As shown, in step S200, in the first rule: before fracturing and crushing each layer of rock, at least one cutting groove 5 is mined in the layer of rock using mechanical crushing.

[0037] In the above optional embodiment, it should be noted that each cutting groove 5 can form at least one free surface 51 after being formed.

[0038] In addition, the rocks in the foundation pit are divided into a first fracturing zone 1 and a second fracturing zone 2 by the center line of the foundation pit, and then the carbon dioxide phase change fracturing device 6 is used to perform phase change fracturing on each layer of rock in the first fracturing zone 1 and each layer of rock in the second fracturing zone 2 in an alternating manner.

[0039] Specifically, first, a protective layer is reserved at a position of 1 to 2 meters away from the continuous wall of the foundation pit in the first fracturing zone 1, and then a cutting groove 5 is mined next to the protective layer by mechanical breaking. Then, a carbon dioxide phase change fracturing device 6 is used to fracture and crush the top layer of rock in the first fracturing zone 1 from the position of the cutting groove 5 to the middle of the foundation pit. After the top layer of rock is fractured and crushed to a preset position, a first layer of phase change fracturing steps 4 in the first fracturing zone 1 is formed. Then, the top layer of rock in the second fracturing zone 2 is mined in the same manner to form the first layer of phase change fracturing steps 4 in the second fracturing zone 2. Then, the second layer of rock in the first fracturing zone 1 is mined from top to bottom in the same manner to form the second layer of phase change fracturing steps 4 in the first fracturing zone 1. Then, the second layer of rock in the second fracturing zone is mined from top to bottom in the same manner to form the second layer of phase change fracturing steps 4 in the second fracturing zone 2. This process is repeated until a plurality of phase change fracturing steps 4 continuous from top to bottom are formed in both the first fracturing zone 1 and the second fracturing zone 2.

[0040] It should be noted here that every 6 to 8 meters of rock layer is defined as a layer of rock, that is, the top layer of rock is the rock layer 6 to 8 meters below the top of the foundation pit rock, and the bottom of the second layer of rock is 12 to 16 meters below the top of the foundation pit rock, and so on.

[0041] After each layer of rock is fractured by carbon dioxide phase change to form a rock step, the rock blocks are transported to the outside by using an excavator 3 in conjunction with a vehicle, and then the next layer of rock is fractured by carbon dioxide phase change.

[0042] The beneficial effect of the above-described optional embodiment is that, before each layer of rock is fractured, mechanical crushing is used to create cutting grooves 5, effectively forming free surfaces 51. The presence of free surfaces 51 alters the stress distribution within the rock, allowing subsequent carbon dioxide phase change fractures to more concentratedly direct energy in the desired direction, enhancing the fracture effect and significantly improving rock fracture efficiency. Furthermore, the cutting grooves 5 formed by mechanical crushing are precisely positioned, guiding the fracture direction, making the fracture range and degree easier to control, reducing disturbance to rocks in non-mining areas, improving resource utilization, and reducing mining costs.

[0043] Optional, such as Figure 1 and Figure 2 As shown, in step S200, the second rule is: performing carbon dioxide phase change cracking and crushing on multiple phase change cracking steps 4 from bottom to top or from top to bottom in sequence until carbon dioxide phase change cracking and crushing on all phase change cracking steps 4 are completed.

[0044] In the above optional embodiment, it should be noted that the method of performing carbon dioxide phase change fracturing and crushing on multiple phase change fracturing steps 4 from bottom to top is to use the carbon dioxide phase change fracturing device 6 to fracture and crush the bottommost phase change fracturing step 4 of the first fracturing zone 1, and then use the excavator 3 to cooperate with the vehicle to transport the crushed rock blocks while using the carbon dioxide phase change fracturing device 6 to fracture and crush the bottommost phase change fracturing step 4 of the second fracturing zone 2, and then use the excavator 3 to cooperate with the vehicle to transport the crushed rock blocks while using the carbon dioxide phase change fracturing device 6 to fracture and crush the second phase change fracturing step 4 from bottom to top in the first fracturing zone 1, and then use the excavator 3 to cooperate with the vehicle to transport the crushed rock blocks while using the carbon dioxide phase change fracturing device 6 to fracture and crush the second phase change fracturing step 4 from bottom to top in the second fracturing zone 2, and so on and so forth until all phase change fracturing steps 4 are completely fractured and crushed.

[0045] The method of performing carbon dioxide phase change fracturing and crushing from top to bottom is as follows: the method of performing carbon dioxide phase change fracturing and crushing on multiple phase change fracturing steps 4 from top to bottom is: using the carbon dioxide phase change fracturing device 6 to fracture and crush the topmost phase change fracturing step 4 of the first fracturing zone 1, and then using the excavator 3 to cooperate with the vehicle to transport the crushed rock blocks while using the carbon dioxide phase change fracturing device 6 to fracture and crush the topmost phase change fracturing step 4 of the second fracturing zone 2, and then using the excavator 3 to cooperate with the vehicle to transport the crushed rock blocks while using the carbon dioxide phase change fracturing device 6 to fracture and crush the second phase change fracturing step 4 from top to bottom of the first fracturing zone 1, and then using the excavator 3 to cooperate with the vehicle to transport the crushed rock blocks while using the carbon dioxide phase change fracturing device 6 to fracture and crush the second phase change fracturing step 4 from top to bottom of the second fracturing zone 2, and so on and so forth until all phase change fracturing steps 4 are completely fractured and crushed.

[0046] The beneficial effect of the above optional embodiment is that by sequentially crushing the multiple phase change fracture steps 4 from bottom to top or from top to bottom, the crushing process can be made safer. If the phase change fracture steps 4 are crushed from bottom to top, the bottom steps can be crushed first to provide more support and cushioning for the upper steps, thereby reducing the risk of collapse; if the phase change fracture steps 4 are crushed from top to bottom, it is easier to clean up the crushed objects and reduce the accumulation of obstacles.

[0047] Optional, such as Figures 1 to 6 As shown, in step S200, the carbon dioxide phase change cracking and crushing method for each rock layer in the first rule and the carbon dioxide phase change cracking and crushing method for each phase change cracking step 4 in the second rule both include the following steps: Step S210 : drilling the phase change crack hole 41 .

[0048] Step S220: Fill the phase change cracking hole 41 with the carbon dioxide phase change cracking device 6; Step S230: connecting the conductive network and igniting the explosion; Step S240: Inspection and recycling.

[0049] In the above optional embodiment, it should be noted that the method for drilling the phase-change fracture hole 41 is as follows: when using a drilling rig to drill the phase-change fracture hole 41, if the rock surface is relatively intact, a small amount of air is applied without pressure to first blow away the scum, then the rock surface is slowly impacted. After the hole is drilled, the drill tool is rotated to drill down and open the hole. After the drill bit enters the hole, the air volume is gradually increased to a full air and full pressure state for rapid rock drilling. For hard rock, a high-quality, high-hardness drill bit should be selected, and full air and full pressure should be applied. However, the rotation speed should not be too high to prevent damage to the drill bit. For soft rock, full air and half pressure should be applied, and the drill should be lifted and the hole blown every 1.0-1.5 m of drilling to prevent excessive slag accumulation at the bottom of the hole and hole jamming.

[0050] When the rock at the orifice of the phase change crack hole 41 is unstable, mud wall protection should be used during the drilling process.

[0051] The operation method of mud wall protection is: drill a crack hole 2m to 3m deep, pile a certain amount of water-containing sticky yellow mud at the hole mouth, move the drill rod up and down, replace the yellow mud into the hole and soak it into the broken rock cracks.

[0052] After the drilling is completed, the depth of the crack hole and the hole network parameters need to be checked and the resistance line needs to be verified; if there is water in the phase change crack hole 41, construction cannot be carried out.

[0053] If the crack hole 41 caused by phase change is blocked or not deep enough, it should be re-drilled in time.

[0054] After the fracture hole is drilled, the hole opening is immediately blocked with materials such as plastic or woven bags to prevent rainwater or other debris from entering the fracture hole. Then, the rock at the hole opening of the phase change fracture hole 41 is cleaned to prevent it from falling into the hole.

[0055] The conductive network includes an initiator 81, a main line 82, branch lines 83, and a ignition head 84. Branch lines 83 are electrically connected to the initiator 81 via the main line 82. Branch lines 83 are electrically connected to the ignition head 84. During operation, the ignition head 84 is electrically connected to the heating tube of the carbon dioxide cracking device. Specifically, multiple branch lines 83 are connected in parallel to the main line 82, each of which is electrically connected to a ignition head 84. Each ignition head 84 is electrically connected to a heating tube of the carbon dioxide phase change cracking device 6.

[0056] The beneficial effects of this optional embodiment are as follows: by filling the phase-change fracturing holes 41 with a carbon dioxide phase-change fracturing device 6, the fracturing energy is concentrated within the rock, enhancing the fragmentation effect. Connecting the conductive network and igniting the blasting operation is convenient, and carbon dioxide phase-change fracturing significantly improves safety compared to traditional explosive blasting, reducing the risk of explosion accidents. Finally, the inspection and recovery steps facilitate timely assessment of the fracturing effect, allowing for rapid adjustments and secondary operations for areas that are insufficiently fragmented. Furthermore, the recovery of equipment such as the fracturing device effectively reduces costs and avoids resource waste.

[0057] By arranging the main line 82, the branch line 83 and the ignition head 84, a plurality of carbon dioxide fracturing devices can simultaneously perform rock fracturing and crushing work, thereby increasing the efficiency of rock mining.

[0058] Optional, such as Figure 2 and Figure 3 As shown, in step S200, in the first rule, before each layer of rock is fractured by carbon dioxide phase change, the rock blocks formed by the rock layer that has been fractured by carbon dioxide phase change are transported out; In the second rule, before each phase change fracture step 4 is broken, the broken rock blocks formed by the phase change fracture step 4 that has been broken by the carbon dioxide phase change fracture are transported out.

[0059] The beneficial effects of the above optional embodiments are: by transporting the crushed rocks in advance, the working surface can be cleaned in time, providing open space for the phase change cracking and crushing of subsequent layers of rocks, avoiding the accumulation of broken stones that hinder drilling, filling and other operations, and improving the efficiency of rock cracking and crushing.

[0060] Optionally, in step S100, the method for setting a protective device includes the following steps: Step S110: Connect multiple bamboo frame steel pipes and lay them on the foundation pit beams; Step S120: Covering the connected bamboo frame with a carpet; Step S130: laying sandbags on top of the carpet; Step S140: Cover the sandbag with a cannon quilt; Step S150: Cover the quilt with a wire mesh and secure it with anchoring steel bars; Step S160: The protection device is set up.

[0061] In the above optional embodiment, it should be noted that the protective device is arranged on the foundation pit beam.

[0062] The protective device includes multiple bamboo panels, steel pipes, carpet, wire mesh, a quilt, and multiple sandbags. The bamboo panels are connected by steel pipes and cover the phase change crack holes 41. The carpet covers the bamboo panels. Sandbags are placed sequentially on the bamboo panels, and the quilt covers the sandbags. The wire mesh covers the quilt and is secured to the continuous wall or foundation pit beams via anchor bars.

[0063] The beneficial effects of the above-mentioned optional embodiments are as follows: the bamboo frame panels connected to the steel pipes and then laid on the foundation pit beams can stabilize the structure. The carpet covering reduces friction and vibration transmission. The sandbags increase weight, enhance the stability of the protection, and block the flying of small stones. The blasting blanket further cushions the impact force and reduces the energy of the flying stones. The wire mesh can intercept larger stones and is fixed with anchor steel bars to prevent the displacement of the protective device. The overall multi-level protection system is formed to comprehensively reduce the safety risks caused by flying stones and vibration during the mining process, protecting the safety of on-site personnel and surrounding facilities.

[0064] Optional, such as Figures 1 to 6 As shown, in step 210 , before drilling the phase change induced fracturing hole 41 , the phase change induced fracturing excavation area is measured and calibrated, and the hole position is calibrated.

[0065] In the above optional embodiments, it should be noted that the number of the multiple phase change fracture holes 41 of each phase change fracture step 4 is four, five or six; when the number of the multiple phase change fracture holes 41 of the phase change fracture step 4 is four, the shape of their arrangement combination is a parallelogram, and the four phase change fracture holes 41 are respectively located at the four corners of the parallelogram; when the number of the multiple phase change fracture holes 41 of the phase change fracture step 4 is five or six, the multiple phase change fracture holes 41 are arranged in a straight line; the distance between two adjacent phase change fracture holes 41 is between 1.7 meters and 2 meters and as the depth of the rock layer increases and the rock strength increases, the distance between the phase change fracture holes 41 can be appropriately reduced and can be set to a=1.5 meters to 1.8 meters.

[0066] When rock is crushed on one of the phase change fracturing steps 4, at least one carbon dioxide phase change fracturing device 6 and a pulling tube 7 are provided in each of the multiple phase change fracturing holes 41 on the corresponding phase change fracturing step 4, and the pulling tube 7 is located above the corresponding carbon dioxide phase change fracturing device 6.

[0067] The length of the minimum resistance line W of the carbon dioxide phase change cracking device 6 in each phase change cracking hole 41 is between 1.5m and 2.3m.

[0068] Each time the cracking holes are arranged for the corresponding phase change cracking step 4, the minimum resistance line of the phase change cracking hole 41 closest to the continuous wall should be equal to 1.5m to ensure that the cracking energy is released from the free surface as much as possible, reducing the proportion of energy transmitted from the corresponding protective layer into the continuous wall, so as to weaken the impact of the cracking vibration on the continuous wall.

[0069] The distance between each two adjacent phase change crack holes 41 is between 1.7 meters and 2.0 meters.

[0070] When the corresponding phase change cracking step 4 is subjected to phase change cracking and crushing, a carbon dioxide phase change cracking device 6 is provided in each phase change cracking hole 41 on the corresponding phase change cracking step 4 .

[0071] The beneficial effects of the above optional embodiment are: by measuring and calibrating the excavation area, the rock extraction range can be clearly defined, over-excavation or under-excavation can be avoided, resource utilization can be improved, and the impact on surrounding areas can be reduced. The calibration of the hole positions ensures accurate drilling positions and a scientific and reasonable distribution of the fracturers within the rock. This allows subsequent fracture energy to be evenly applied to the target rock, enhancing the crushing effect and ensuring uniform and holistic rock crushing.

[0072] Optional, such as Figures 1 to 6 As shown, in step 230 , before connecting the conductive network, the phase change crack holes 41 are filled.

[0073] In the above optional embodiment, it should be noted that the packing method when using a pipe installation method with a lifting rod is as follows: after packing, the exposed length of the lifting rod, A: 0.3 ≤ A ≤ 0.5 m. The packing material is angular gravel, which is piled around the crack-inducing hole. The packing material is slowly placed into the crack-inducing hole, while simultaneously tapping the exposed lifting rod to facilitate the sinking and compaction of the packing material. A handheld vibrator can also be used to improve packing efficiency.

[0074] When using a deep-buried carbon dioxide phase change fracturing device without connecting a lifting rod, the filling method should be used. At this time, the filling length should not be less than 2.5m. The filling particles should be angular gravel particles, and they should be piled around the fracturing hole. After installing the fracturing device, slowly put the filling material into the fracturing hole, and let the filling material fill the gap between the fracturing tube and the fracturing hole. Finally, fill it all the way to the mouth of the fracturing hole and vibrate it with a vibrating rod.

[0075] The beneficial effects of this optional embodiment are as follows: Packing effectively prevents the ineffective dissipation of energy during carbon dioxide phase-change fracturing, allowing more energy to act on the rock, significantly enhancing the fracturing effect and improving the degree and efficiency of rock fragmentation. Furthermore, packing reduces the transmission of blasting noise, minimizing disturbances to the surrounding environment and personnel.

[0076] Optional, such as Figure 4 and Figure 5 As shown, in step S220 , before the carbon dioxide phase change cracking device 6 is filled into the phase change cracking hole 41 , the parameters of the carbon dioxide phase change cracking device 6 are set according to the parameters of the phase change cracking hole 41 .

[0077] The beneficial effect of the above-mentioned optional embodiment is that, by setting the parameters of the fracturing device according to the parameters of the phase change fracturing hole 41 before filling, precise adaptation can be achieved. This ensures that the energy released by the fracturing device is consistent with the rock characteristics and drilling conditions, enhancing the crushing effect. This avoids energy waste or insufficiency, improves mining efficiency, and reduces costs.

[0078] The above are merely preferred embodiments of the present invention, but the scope of protection of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by a person skilled in the art within the technical scope disclosed in the present invention should be included in the scope of protection of the present invention. Therefore, the scope of protection of the present invention should be based on the scope of protection of the claims.

Claims

1. A rock mining method, characterized in that: The following steps are involved: Step S100: clearing the soil layer, clearing the soil layer covered by the rock layer and setting up protective devices; Step S200: Carbon dioxide phase change cracking and crushing, performing carbon dioxide phase change cracking and crushing on the rock according to a first rule to form a plurality of phase change cracking steps (4), and performing carbon dioxide phase change cracking and crushing on the plurality of phase change cracking steps (4) according to a second rule; Step S300: rock removal, which involves removing the crushed rocks; Step S400: rock mining is completed.

2. The rock mining method according to claim 1, characterized in that: In step S200, the first rule is: performing carbon dioxide phase change fracture and crushing on each layer of rock from top to bottom to form a plurality of phase change fracture steps (4).

3. The rock mining method according to claim 2, characterized in that: In the first rule, at least one cutting groove (5) is mined by mechanical crushing before fracturing each layer of rock.

4. The rock mining method according to claim 3, characterized in that: The second rule is: the carbon dioxide phase change cracking and crushing are performed on the multiple phase change cracking steps (4) from bottom to top or from top to bottom in sequence until the carbon dioxide phase change cracking and crushing of all the phase change cracking steps (4) are completed.

5. The rock mining method according to claim 4, characterized in that: In step S200, the carbon dioxide phase change cracking and crushing method for each layer of rock in the first rule and the carbon dioxide phase change cracking and crushing method for each phase change cracking step (4) in the second rule both include the following steps: Step S210: drilling a phase change crack hole (41); Step S220: filling the phase change cracking hole (41) with a carbon dioxide phase change cracking device (6); Step S230: connecting the conductive network and igniting the explosion; Step S240: Inspection and recycling.

6. The rock mining method according to claim 4, characterized in that: In step S200, in the first rule, before each layer of rock is fractured by carbon dioxide phase transition, the rock blocks formed by the rock layer that has been fractured by carbon dioxide phase transition are transported out; In the second rule, before each layer of the phase change fracture step (4) is broken, the broken rock blocks formed after the carbon dioxide phase change fracture are transported out.

7. The rock mining method according to any one of claims 1 to 6, characterized in that: In step S100, the method for setting a protective device includes the following steps: Step S110: Connect multiple bamboo frame steel pipes and lay them on the foundation pit beams; Step S120: Covering the connected bamboo frame panels with a carpet; Step S130: laying sandbags on the carpet; Step S140: Covering the sandbag with a cannon quilt; Step S150: Cover the quilt with a wire mesh and fix it with anchoring steel bars; Step S160: The protection device is set up.

8. The rock mining method according to claim 5, characterized in that: In step 210, before drilling the phase change cracking hole (41), the phase change cracking excavation area is measured and calibrated and the hole position is calibrated.

9. The rock mining method according to claim 5, characterized in that: In step 230, before connecting the conductive network, the phase change crack hole (41) is filled.

10. The rock mining method according to claim 5, characterized in that: In step S220, before the carbon dioxide phase change cracking device (6) is filled into the phase change cracking hole (41), the parameters of the carbon dioxide phase change cracking device (6) are set according to the parameters of the phase change cracking hole (41).

Citation Information

Cited By

  • Rock mining device

    CN120465931A