Hollow slab beam foam core mold and reinforcement cage positioning and anchoring device and method
Through modular design and intelligent dynamic correction mechanism, the problems of large positioning errors between steel cage and foam core mold and low construction efficiency have been solved, achieving high-precision and low-cost quality control of precast concrete components.
Patent Information
- Application Number
- CN202511102965.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-07
- Publication Date
- 2025-11-04
AI Technical Summary
In existing technologies, the positioning errors of steel cages and foam core molds are large, the positioning devices have poor versatility, the construction preparation time is long, the cost is high, and there is a lack of real-time monitoring and correction mechanisms, which makes it difficult to guarantee the quality consistency of precast concrete components.
The modular design of the hollow slab beam foam core mold and rebar cage positioning and anchoring device achieves precise positioning of the foam core mold and rebar cage through the combination of connecting components, anchoring components and positioning components, combined with threaded connection and bolt fixing. It also introduces a dynamic correction method based on PID control algorithm to monitor the offset in real time and generate correction instructions.
It significantly improved the positioning accuracy and construction efficiency of steel cages and foam core molds, realized digital quality management, reduced construction costs and resource waste, and improved the traceability of construction quality and the ability to optimize processes.
Smart Images

Figure CN120886361A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of building engineering, and in particular to a hollow slab beam foam core mold and a steel reinforcement cage positioning and anchoring device and method. BACKGROUND
[0002] In the field of building engineering, accurate positioning of the steel reinforcement cage and the foam core mold in the construction of prefabricated concrete components is a key link to ensure structural quality. The existing technology mainly relies on fixed positioning rings or scale rods to achieve positioning, which has the following outstanding problems: 1. The traditional method relies on manual measurement and manual adjustment, and the positioning error is large, which is difficult to meet the design requirements of high-precision prefabricated components. For example, during the pouring and vibrating process, the foam core mold is easy to float or sink due to the flow of concrete, resulting in excessive thickness deviation of the top plate and the bottom plate, and even causing the steel reinforcement cage to be offset, directly affecting the safety of the structure.
[0003] 2. The positioning device is mostly custom designed, which has poor universality, resulting in long construction preparation time and high cost; and the manual operation has strong dependence, and the quality consistency is difficult to guarantee. For example, the traditional cushion block needs to be adjusted one by one, and the reuse rate is low, which increases material waste and labor cost.
[0004] 3. There is a lack of real-time monitoring and correction mechanism, and the dynamic error in the construction process is difficult to find and correct in time; the data recording relies on manual operation, and quality tracing and process optimization cannot be achieved. For example, the traditional method cannot quantitatively record the offset data, making it difficult to locate the quality problems afterwards.
[0005] 4. The traditional positioning components (such as plastic positioning rings) are easy to wear or rust, and have low reuse rate, which increases material waste and construction cost. In addition, the structural strength is insufficient, and deformation is easy to occur during concrete pouring, affecting the positioning accuracy.
[0006] The above technical bottlenecks restrict the precision and efficiency of prefabricated concrete component construction, and an modularized and intelligent positioning and anchoring scheme is urgently needed to solve the problem. SUMMARY
[0007] This section aims to summarize some aspects of the embodiments of the present application and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the abstract and title of the specification to avoid obscuring the purpose of this section, abstract and title, and such simplifications or omissions cannot be used to limit the scope of the present application.
[0008] Therefore, in order to solve the above technical problems, the present application provides the following technical scheme: a hollow slab beam foam core mold and a steel reinforcement cage positioning and anchoring device, comprising: a connecting component connected to the foam core mold; an anchoring component anchored to the steel reinforcement cage; a positioning component positioned on the pedestal; and a bolted joint; wherein the connecting component, the anchoring component and the positioning component form an integral structure through detachable connection, and the diameter of the bolted joint matches the diameter of the steel bar fixing hole of the anchoring component.
[0009] As a preferred scheme of the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, the connecting component comprises: a core mold pressure head at the upper portion; and a core mold connecting sleeve at the lower portion; the core mold pressure head is provided with at least two core mold fixing holes perpendicular to each other, for connecting anchoring steel wires, and connecting the connecting component and the foam core mold through the anchoring steel wires.
[0010] As a preferred scheme of the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, the anchoring component comprises: a steel bar connecting head; and a steel bar fixing plate fixedly connected with the steel bar connecting head; two symmetrical steel bar fixing holes are provided on both sides of the steel bar fixing plate.
[0011] As a preferred scheme of the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, the positioning component comprises: a positioning pin connecting sleeve at the upper portion; and a positioning pin at the lower portion, inserted into a pedestal positioning hole of the pedestal; a positioning pin fixing hole is provided on the positioning pin, for connecting a steel anchor rod.
[0012] As a preferred scheme of the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, the steel anchor rod is arranged on the pedestal, one end of the steel anchor rod penetrates through the pedestal and is fixedly connected to the steel side mold through a steel fender plate; a wire is arranged in the steel anchor rod, and the wire is used for transmitting offset data of the positioning pin to a collection box.
[0013] As a preferred scheme of the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, the core mold connecting sleeve and the positioning pin connecting sleeve are respectively threadedly connected to the steel bar connecting heads of two independent anchoring components; the two anchoring components are connected to each other through a bolted joint penetrating through the steel bar fixing holes, and are anchored to the bottom plate steel bars of the steel reinforcement cage.
[0014] As a preferred scheme of the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, the positioning pin is provided with a mounting position for mounting a data acquisition sheet, the data acquisition sheet is connected to an acquisition box through a wire to form a wired monitoring loop, and stable transmission of the data signal of the offset amount of the positioning pin is ensured.
[0015] A positioning and anchoring method of a hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, which is suitable for the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device described in any one of the preceding embodiments, and comprises the following specific steps: The connecting part is anchored to the foam core mold through the anchoring steel wire passing through the core mold fixing hole; The core mold connecting sleeve of the connecting part is screwed with the steel connecting head of the anchoring part located above, the relative position of the connecting part and the anchoring part is adjusted by rotating the core mold connecting sleeve, and the distance between the foam core mold and the steel reinforcement cage is controlled to meet the requirements; The positioning pin connecting sleeve of the positioning part is screwed with the steel connecting head of the anchoring part located below, and the relative position of the positioning part and the anchoring part is adjusted by rotating the positioning pin connecting sleeve, so that the distance between the bottom plate steel reinforcement of the steel reinforcement cage and the formwork of the pedestal meets the requirement of the protective layer thickness; The upper and lower two independent anchoring parts are fixed to the bottom plate steel reinforcement of the steel reinforcement cage through bolted connections; The positioning pin of the positioning part is inserted into the pedestal positioning hole and anchored to prevent displacement of the device during pouring; After one end of the steel anchor rod passes through the positioning pin fixing hole and the pedestal in sequence, the steel anchor rod is fixed on the steel side mold through the steel backing plate.
[0016] As a preferred scheme of the positioning and anchoring method of the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, the method further comprises the step of monitoring the position of the foam core mold and the steel reinforcement cage in real time, which comprises: A maximum displacement threshold value allowed for the displacement of the foam core mold is preset in the acquisition box, such as ±5mm; When the data of the positioning pin collected by the data acquisition sheet is transmitted to the acquisition box through the wire, if the collected data exceeds the preset threshold value, an alarm signal is triggered; The alarm signal prompts the construction personnel through the sound and light device (such as a buzzer and an LED lamp) of the acquisition box, and is transmitted to the construction management terminal through the wire to trigger a warning state.
[0017] As a preferred scheme of the positioning and anchoring method of the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, the method further comprises an automatic mechanism for correcting the displacement, which specifically comprises: When the collected data exceeds the preset threshold value, the construction management terminal sends a correction instruction to the control unit through the wire; The control unit generates correction prompt information (such as correction amount value or adjustment direction) to prompt the construction personnel to manually adjust the position of the anchoring component through the display screen or voice; The construction personnel adjusts the position of the anchoring component according to the prompt information to restore the foam core mold to the designed position with the reinforcement cage.
[0018] The beneficial effects of the present application are: 1. The combination design of the connecting component, the anchoring component and the positioning component realizes the accurate positioning of the foam core mold and the reinforcement cage. The device uses threaded connection and bolt fixing technology, which significantly improves the installation efficiency and reusability, and solves the problems of poor universality and low construction efficiency of traditional positioning devices. For example, threaded connection can quickly adapt to different specifications of core mold, and bolt fixing ensures the stability of the device during pouring.
[0019] 2. The dynamic correction method based on PID control algorithm is introduced. By monitoring the offset in real time and generating correction instructions, the construction personnel can manually adjust the position of the reinforcement cage. This method effectively suppresses the dynamic error in the construction process, significantly improves the positioning accuracy and correction response speed, and makes up for the defects of traditional manual correction relying on experience and insufficient precision. For example, fine tuning can be performed through data feedback at the initial stage of concrete pouring to avoid cumulative deviation.
[0020] 3. A closed-loop system of data acquisition-analysis-optimization is constructed. By transmitting offset data in real time and generating structure quality reports, digital management of the construction process is realized. This system effectively solves the problems of difficult quality traceability and insufficient process optimization in traditional construction, and provides scientific support for engineering quality management. For example, historical data can be traced back to specific construction units, which facilitates subsequent process improvement.
[0021] 4. The modular design is compatible with various construction scenes, avoiding resource waste caused by customized processing. For example, the same set of devices can meet the design requirements of various top plate and bottom plate thicknesses and steel protection layer thicknesses of different size precast hollow slab beams, and the installation operation is flexible and convenient, with strong adaptability. BRIEF DESCRIPTION OF DRAWINGS
[0022] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the following will briefly introduce the drawings needed to be used in the embodiment description. Obviously, the drawings in the following description are only some embodiments of the present application, and those skilled in the art can obtain other drawings according to these drawings without creative labor. Among them: Figure 1 It is a schematic diagram of the overall structure of the present application.
[0023] Figure 2 It is a specific structure diagram of the connecting component of the present application.
[0024] Figure 3 Specific structure diagram of anchoring component of the present application.
[0025] Figure 4 Specific structure diagram of positioning component of the present application.
[0026] Figure 5 Specific structure diagram of mounting structure of the present application.
[0027] Figure 6 Flow chart of the present application.
[0028] In the figure: 100, connecting component; 101, core mold pressure head; 101a, core mold fixing hole; 102, core mold connecting sleeve; 200, anchoring component; 201, steel bar connecting head; 202, steel bar fixing pressing sheet; 202a, steel bar fixing hole; 300, positioning component; 301, positioning pin connecting sleeve; 302, positioning pin; 302a, positioning pin fixing hole; 400, bolt connecting pair; 500, collection box; 501, data collection sheet; 600, pedestal; 601, pedestal positioning hole; 700, bottom plate steel bar; 800, steel side mold; 801, steel cushion plate; 802, steel anchor rod; 900, foam core mold; 901, anchoring steel wire. DETAILED DESCRIPTION
[0029] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific embodiments of the present application will be described in detail below in combination with the drawings of the specification.
[0030] In the following description, a lot of specific details are set forth in order to facilitate a thorough understanding of the present application, but the present application can also be implemented in other ways different from those described herein, and those skilled in the art can make similar generalizations without departing from the connotation of the present application, therefore the present application is not limited by the specific embodiments disclosed below.
[0031] Secondly, the "one embodiment" or "embodiment" referred to herein means that the specific features, structures or characteristics can be included in at least one implementation of the present application. "In one embodiment" appearing in different places in the specification does not mean the same embodiment, nor is it an independent or alternative embodiment mutually exclusive with other embodiments.
[0032] Thirdly, the present application is described in detail in combination with the schematic diagram, in the detailed description of the embodiments of the present application, for the convenience of description, the sectional view of the device structure will be partially enlarged without the general proportion, and the schematic diagram is only an example, which should not limit the scope of protection of the present application. In addition, the three-dimensional spatial dimensions of length, width and depth should be included in actual production.
[0033] Embodiment 1 Reference Figures 1-6 For the first embodiment of the present application, a hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device and method are provided, the device comprises: 1, connecting part 100: Core mold pressure head 101: the upper part is provided with at least two mutually perpendicular core mold fixing holes 101a, which are used to connect the anchoring steel wire 901, and the connecting part 100 and the foam core mold 900 are temporarily fixed through the anchoring steel wire 901 (passing through the fixing hole 101a).
[0034] Core mold connecting sleeve 102: thread matching with the steel reinforcement connecting head 201 of the anchoring part 200 located at the upper part, and realizing detachable connection with the positioning part 300 through the bolt connecting pair 400.
[0035] 2, anchoring part 200: provided with two upper and lower, two anchoring parts 200 are arranged symmetrically up and down, specifically comprising: Steel reinforcement connecting head 201: butt joint with core mold connecting sleeve 102 and positioning pin connecting sleeve 301.
[0036] Steel reinforcement fixing pressing piece 202: a set of steel reinforcement fixing pressing pieces 202 are arranged on each group of steel reinforcement connecting heads 201, and steel reinforcement fixing holes 202a are formed on both sides of the steel reinforcement fixing pressing piece 202, which are fixed to the bottom plate steel reinforcement 700 of the steel reinforcement cage through the bolt connecting pair 400.
[0037] 3, positioning part 300: Positioning pin connecting sleeve 301: connected with the steel reinforcement connecting head 201 of the anchoring part 200 located below.
[0038] Positioning pin 302: preferably made of high-strength alloy steel, and positioning pin fixing hole 302a is used for inserting pedestal positioning hole 601 and anchoring.
[0039] The embodiment also provides a positioning and anchoring method of the hollow slab beam foam core mold and steel reinforcement cage positioning and anchoring device, comprising the following steps: S1: foam core mold 900 anchoring: The connecting part 100 is fixed with the foam core mold 900 through the anchoring steel wire 901 through the core mold fixing hole 101a.
[0040] S2: steel reinforcement cage fixing: Upper anchoring: the steel bar connector 201 of the anchoring component 200 located above is connected with the core mold connecting sleeve 102, and is fixed to the bottom plate steel bar 700 of the steel bar cage through the bolt connecting pair 400.
[0041] Lower anchoring: the steel bar connector 201 of the anchoring component 200 located below is connected with the positioning pin connecting sleeve 301, and the height of the positioning pin 302 is adjusted to the design thickness of the protective layer (such as 40 mm ± 1 mm).
[0042] S3: pedestal 600 positioning: The positioning pin 302 is inserted into the pedestal positioning hole 601 of the embedded pedestal 600 to prevent displacement of the device during pouring.
[0043] Example 2 For the second embodiment of the application, the difference between this embodiment and the first embodiment is that this embodiment provides specific steps for spacing adjustment, protective layer control and dynamic adjustment of the hollow slab beam foam core mold and steel bar cage positioning and anchoring device described in the above embodiment: S4: spacing adjustment between the foam core mold 900 and the steel bar cage; The core mold fixing hole 101a of the connecting component 100 is anchored to the foam core mold 900 through the anchoring steel wire 901 passing through the core mold fixing hole 101a, and the relative position of the core mold connecting sleeve 102 and the anchoring component 200 is adjusted to make the spacing between the foam core mold 900 and the steel bar cage meet the design specification (such as 50 mm ± 2 mm).
[0044] The verticality of the core mold connecting sleeve 102 can be calibrated with the aid of a laser projector to ensure that the axis of the foam core mold 900 coincides with the center line of the steel bar cage.
[0045] S5: protective layer thickness control of the steel bar cage; The positioning pin connecting sleeve 301 of the positioning component 300 is connected with the steel bar connector 201 of the anchoring component 200 located below, and the height of the positioning pin 302 is adjusted to make the distance between the bottom plate steel bar 700 of the steel bar cage and the formwork of the pedestal 600 meet the protective layer thickness requirement (such as 40 mm ± 1 mm).
[0046] The anchoring component 200 is fixed to the bottom plate steel bar 700 of the steel bar cage through the bolt connecting pair 400 to ensure the overall stability of the device.
[0047] S6: real-time monitoring and dynamic adjustment; A data acquisition sheet 302b is pasted at the installation position of the positioning pin 302, and the offset amount data is transmitted to the acquisition box 500 in real time through the lead wire (such as Figure 5
[0048] An alarm is triggered according to a preset threshold value (such as ±3 mm), and a construction worker adjusts the position of the positioning pin 302 or the anchoring component 200 manually to fine-tune the reinforcement cage and reduce the deviation rate during the concrete pouring process.
[0049] Embodiment 3 For a third embodiment of the present application, which is different from the first embodiment, a reinforcement cage dynamic correction method based on a PID control algorithm is used to monitor the reinforcement cage deviation in real time and calculate a correction instruction to assist a construction worker in manually adjusting the position of the reinforcement cage and reduce the deviation rate during the concrete pouring process.
[0050] PID control correction instruction formula: ; wherein, : real-time measured cover deviation (unit: mm), obtained by displacement sensor acquisition and calculation (measured value - design value); ; : proportional gain (dimensionless), value range 0.5~1.0, set according to engineering experience (such as ); : integral gain (unit: 1 / s), value range 0.01~0.1, used to eliminate steady-state error (such as =0.01); : differential gain (unit: s), value range 0.1~0.5, used to suppress system oscillation (such as ); The specific implementation steps are as follows: (1) Dynamic correction process: a. Data acquisition and transmission: A data acquisition sheet 501 is pasted at the installation position of the positioning pin 302, and the real-time monitored reinforcement cage deviation (x) is transmitted to the acquisition box 500 through a wire (such as shown in Figure 5 ). The acquisition box (500) performs filtering processing on x to eliminate environmental noise interference.
[0051] b. Correction instruction generation: The control unit (such as a PC terminal or a PLC controller) calculates the correction instruction (u) according to the above PID calculation formula, and displays it on the screen of the acquisition box 500.
[0052] Example: when x = +2.5 mm,
[0053] The final output correction is +1.3mm.
[0054] c. Manual correction operation: The construction personnel manually rotate the positioning pin connecting sleeve 301 or adjust the position of the anchoring component 200 according to the value displayed by the collection box 500, so that the reinforcement cage returns to the design position.
[0055] d. Dynamic adjustment of preset threshold: Before pouring the concrete, the initial threshold (±3mm) is set according to the design specification of the prefabricated hollow slab beam (such as GB 50666-2011).
[0056] During the pouring process, the construction personnel manually correct the threshold (±2mm) according to the vibration frequency (such as 20Hz) to ensure the correction accuracy.
[0057] (2) Data analysis and quality report: a. Data recording and statistics: After pouring is completed, the offset data stored in the collection box 500 ( ) is exported to a computer to generate a structural quality report.
[0058] The report content includes: maximum value, average value, correction times and correction time distribution.
[0059] b. Quality traceability and optimization: The report is transmitted to the project management system (such as Excel or BIM platform) through the wire, which assists in construction quality traceability and process optimization.
[0060] In summary, the present application provides a hollow slab beam foam core mold and a reinforcement cage positioning and anchoring device and method, which significantly improves the construction accuracy, efficiency and quality control level through the synergistic innovation of modular design, intelligent dynamic correction mechanism and data-driven management.
[0061] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present application and are not limited. Although the present application has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present application can be modified or replaced by equivalent, without departing from the spirit and scope of the technical solutions of the present application, which should be covered in the scope of the claims of the present application.
Claims
1. A foam core mold and rebar cage positioning and anchoring device for hollow slab beams, characterized in that: include: Connecting component (100) for connecting foam core mold (900); Anchoring component (200) anchored to the reinforcing cage; Positioning component (300) positioned on base (600); and Bolted connection pair (400); The connecting component (100), anchoring component (200) and positioning component (300) are detachably connected to form an integral structure, and the diameter of the bolt connection pair (400) matches the steel bar fixing hole (202a) of the anchoring component (200).
2. The hollow slab beam foam core mold and rebar cage positioning and anchoring device as described in claim 1, characterized in that: The connecting component (100) includes: The upper core mold bearing head (101); and The lower core mold connecting sleeve (102); The core mold bearing head (101) has at least two mutually perpendicular core mold fixing holes (101a) for connecting anchor wires (901), and the connecting component (100) and the foam core mold (900) are connected through the anchor wires (901).
3. The hollow slab beam foam core mold and rebar cage positioning and anchoring device as described in claim 2, characterized in that: The anchoring component (200) includes: Rebar connector (201); and A steel bar fixing plate (202) is fixedly connected to the steel bar connector (201); The steel bar fixing plate (202) has two symmetrical steel bar fixing holes (202a) on both sides.
4. The hollow slab beam foam core mold and rebar cage positioning and anchoring device as described in claim 3, characterized in that: The positioning component (300) includes: The upper locating pin connecting sleeve (301); and The lower positioning pin (302) is inserted into the base positioning hole (601) of the base (600); The positioning pin fixing hole (302a) is opened on the positioning pin (302) and is used to connect the steel anchor rod (802).
5. The hollow slab beam foam core mold and rebar cage positioning and anchoring device as described in claim 4, characterized in that: The steel anchor rod (802) is arranged on the platform (600). One end of the steel anchor rod (802) passes through the platform (600) and is fixed to the steel side mold (800) through the steel pad (801). A wire is arranged inside the steel anchor rod (802) and the wire is used to transmit data to the acquisition box (500).
6. The hollow slab beam foam core mold and rebar cage positioning and anchoring device as described in claim 5, characterized in that: The core mold connecting sleeve (102) and the positioning pin connecting sleeve (301) are respectively threaded to the steel bar connectors (201) of two independent anchoring components (200). The two anchoring components (200) are connected to each other by bolted pairs (400) through the reinforcing bar fixing holes (202a) and anchored to the bottom plate reinforcing bars (700) of the reinforcing bar cage.
7. The hollow slab beam foam core mold and rebar cage positioning and anchoring device as described in claim 6, characterized in that: The positioning pin (302) is provided with a mounting position for installing the data acquisition chip (501). The data acquisition chip (501) is connected to the acquisition box (500) through a wire to form a wired monitoring loop, ensuring stable transmission of the offset data signal of the positioning pin (302).
8. A positioning and anchoring method for a hollow slab beam foam core mold and reinforcing cage positioning and anchoring device, the method being applicable to the hollow slab beam foam core mold and reinforcing cage positioning and anchoring device as described in any one of claims 1-7, characterized in that: The specific steps include the following: The connecting component (100) is anchored to the foam core mold (900) by passing the anchoring wire (901) through the core mold fixing hole (101a); The core mold connecting sleeve (102) of the connecting component (100) is threadedly connected to the steel bar connector (201) of the anchoring component (200) located above. The relative position of the connecting component (100) and the anchoring component (200) is adjusted by rotating the core mold connecting sleeve (102) to control the distance between the foam core mold (900) and the steel cage so that it meets the requirements. The positioning pin connecting sleeve (301) of the positioning component (300) is threadedly connected to the steel bar connector (201) of the anchoring component (200) located below. The relative position of the positioning component (300) and the anchoring component (200) is adjusted by rotating the positioning pin connecting sleeve (301) so that the distance between the bottom plate steel bar (700) of the steel cage and the template of the platform (600) meets the requirements of the protective layer thickness. The two independent anchoring components (200) are fixed to the bottom plate reinforcement (700) of the steel cage by bolt connection pair (400); Insert the positioning pin (302) of the positioning component (300) into the positioning hole (601) of the base and anchor it to prevent the device from shifting during the pouring process; After passing one end of the steel anchor rod (802) through the positioning pin fixing hole (302a) and the base (600) in sequence, it is fixed to the steel side mold (800) through the steel pad (801).
9. The positioning and anchoring method of the foam core mold and rebar cage positioning and anchoring device for hollow slab beams as described in claim 8, characterized in that: The method also includes a step of real-time monitoring of the position of the foam core mold (900) and the rebar cage, which includes: The maximum allowable displacement threshold for the foam core mold (900) is preset in the acquisition box (500); When the data collected by the data acquisition chip (501) from the positioning pin (302) is transmitted to the acquisition box (500) through the wire, if the collected data exceeds the preset threshold, an alarm signal is triggered. The alarm signal is alerted to the construction personnel through the sound and light device of the acquisition box (500), and the alarm signal is transmitted to the construction management terminal through the wire to trigger the early warning state.
10. The positioning and anchoring method of the foam core mold and rebar cage positioning and anchoring device for hollow slab beams as described in claim 9, characterized in that: This method also includes an automated mechanism for offset correction, specifically including: When the collected data exceeds the preset threshold, the construction management terminal sends a correction command to the control unit via a wire; The control unit generates calibration prompts and prompts construction personnel to manually adjust the position of the anchoring component (200) via display screen or voice prompts; Construction workers adjusted the position of the anchoring component (200) according to the prompts, so that the foam core mold (900) and the steel cage were restored to their designed positions.