Natural gas pipeline leakage plugging device

By using auxiliary airbag assembly and auxiliary sealing monitoring structure in the natural gas pipeline leakage sealing equipment, the secondary leakage risk caused by accelerated aging of rubber pads is solved, effective sealing and long-term stability are achieved, and the safety and reliability of the device are improved.

CN222597142UActive Publication Date: 2025-03-11YINGKOU BAOMING GAS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420785136.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-16
Publication Date
2025-03-11
Estimated Expiration
2034-04-16

AI Technical Summary

Technical Problem

In existing natural gas pipeline leakage sealing equipment, rubber pads age faster without proper protection, which may cause the risk of secondary leakage and threaten the safe transportation of natural gas.

Method used

A natural gas pipeline leakage sealing device is designed, using auxiliary airbag components to wrap the leakage, and pressurize and block through auxiliary sealing and pressure sealing monitoring structure to ensure effective sealing of leakage points. At the same time, the aging of the airbag is detected by connecting the auxiliary monitoring column to ensure the safety and reliability of the device.

Benefits of technology

It effectively extends the service life of the rubber pad, ensures the long-term stability and safety of the sealing equipment, greatly reduces the risk of secondary leakage, and improves the safety and reliability of the device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222597142U_ABST
    Figure CN222597142U_ABST
Patent Text Reader

Abstract

The utility model discloses a natural gas pipeline leakage plugging device which comprises a natural gas assembling pipeline, an upper-layer device shell and a lower-layer device shell, the upper-layer device shell and the lower-layer device shell are connected with each other, and an auxiliary air bag assembly is installed on the natural gas assembling pipeline. The upper-layer device shell and the lower-layer device shell are each provided with an auxiliary plugging and press sealing monitoring structure. The utility model relates to the technical field of natural gas plugging auxiliary equipment, the device ingeniously applies a wrapping air bag through an auxiliary air bag assembly, the leakage position on a natural gas assembly pipeline is accurately wrapped, then an auxiliary plugging pressure sealing monitoring structure pressurizes the wrapping air bag, the leakage point is effectively plugged, and the safety and stability of the natural gas pipeline are ensured; in addition, it is worth mentioning that if the package air bag leaks air due to aging, the state of the package air bag can be visually detected and evaluated through the specially-arranged connection auxiliary monitoring column, the plugging effect is clear at a glance, and the safety and reliability of the device are greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of natural gas plugging auxiliary equipment, in particular to a natural gas pipeline leakage plugging device. Background Art

[0002] A natural gas pipeline is a pipeline that transports natural gas (including associated gas produced by oil fields) from the mining site or processing plant to the urban gas distribution center or industrial enterprise user. It is also called a gas transmission pipeline. It is the main way to transport natural gas in large quantities on land. Natural gas pipelines account for about half of the total length of pipelines in the world. The main reason why natural gas pipelines need leak plugging devices is safety considerations. Natural gas is a flammable and explosive gas. Once a leak occurs, it will not only cause a waste of resources, but may also cause serious accidents such as fire and explosion, posing a huge threat to people's lives and property. Therefore, installing a leak plugging device can timely and effectively plug the leak point to prevent the expansion of the accident and The current natural gas plugging equipment will add rubber pads between the equipment and the pipeline to ensure the sealing effect when implementing leak plugging. However, as time goes by, these rubber pads will age significantly faster without proper protection. This aging phenomenon may cause the risk of secondary leakage and pose a potential threat to the safe transportation of natural gas. Therefore, it is particularly urgent to solve this problem. We must take effective measures to extend the service life of the rubber pads and ensure the long-term stability and safety of the plugging equipment. For the above problems, there may already be technical means to solve them in the existing technology, but this case wants to provide an alternative or replacement technical solution. Utility Model Content

[0003] To achieve the above objectives, the utility model is implemented through the following technical solutions: a natural gas pipeline leakage plugging device, comprising: a natural gas assembly pipeline, an upper device shell and a lower device shell, the upper device shell and the lower device shell are connected to each other, an auxiliary airbag assembly is installed on the natural gas assembly pipeline, and auxiliary plugging pressure sealing monitoring structures are installed on the upper device shell and the lower device shell respectively;

[0004] The auxiliary plugging and pressure sealing monitoring structure includes: a pair of upper shell ear keys, a pair of lower shell ear keys, a pair of mounting bolts, a pair of locking screw washers, a pair of pressure arc plates, a pair of pressure push blocks, a pair of push block placement grooves, a pair of pressure boosting auxiliary springs and a pair of connection auxiliary monitoring columns;

[0005] A pair of upper shell ear keys are respectively installed on the upper device shell, a pair of lower shell ear keys are respectively installed on the lower device shell, a pair of mounting bolts are respectively inserted into the pair of upper shell ear keys and the pair of lower shell ear keys, and a pair of mounting bolts are respectively screwed and inserted into a pair of locking screw washers, a pair of push block placement grooves are respectively opened on the upper device shell and the lower device shell, a pair of pressure arc plates are respectively installed on a pair of pressure push blocks, a pair of pressure push blocks are respectively inserted in a pair of push block placement grooves, a pair of boost auxiliary springs are respectively inserted in a pair of push block placement grooves, and a pair of boost auxiliary springs are respectively connected to a pair of pressure push blocks, a monitoring column through hole is respectively opened on the upper device shell and the lower device shell, a pair of connection auxiliary monitoring columns are respectively inserted into the upper device shell and the lower device shell through a pair of monitoring column through holes, and a pair of connection auxiliary monitoring columns are respectively connected to a pair of pressure push blocks;

[0006] It should be noted that, in the above-mentioned case, when the natural gas assembly pipeline leaks during operation, the auxiliary airbag assembly is first installed on the leaking part of the natural gas assembly pipeline, and then the upper device shell and the lower device shell are combined with each other, so that a pair of pressurized arc plates fully wrap the wrapped airbag, and then the upper shell ear key and the lower shell ear key are assembled together, and then the upper shell ear key and the lower shell ear key are locked and fixed to each other by installing bolts and locking nuts, so that the upper device shell and the lower device shell are combined with each other and firmly formed into a whole, and there is a cavity in the whole formed by the upper device shell and the lower device shell, so when squeezed by the auxiliary airbag assembly, a pair of The pressurized arc plate will be pushed up, thereby pushing the pressure push block and compressing the boost auxiliary spring in the push block mounting groove, thereby causing the connection auxiliary monitoring column to expand and lift outward. In summary, after installation, the exposed part of the connection auxiliary monitoring column will be squeezed by the auxiliary airbag assembly, exposing more to the overall outside of the upper device shell and the lower device shell combination. In this way, if the auxiliary airbag assembly is aged and leaks, the exposed part of the connection auxiliary monitoring column will be shortened, thereby monitoring and evaluating the operating status of the auxiliary airbag assembly according to the auxiliary pressure detection scale line on the connection auxiliary monitoring column. The buffer auxiliary rubber pad provided on the pressurized arc plate can protect the airbag assembly when assisting in squeezing the auxiliary airbag assembly.

[0007] Preferably, the auxiliary airbag assembly comprises: a pair of airbag bearing collars, a wrapping airbag and a pair of outer auxiliary sealing rubber rings;

[0008] A pair of the airbag bearing rings are respectively sleeved on the natural gas assembly pipe, the wrapped airbags are respectively installed on the pair of the airbag bearing rings, and the wrapped airbags are connected to the outer side of the natural gas assembly pipe, and a pair of the outer auxiliary sealing rubber rings are respectively installed on the pair of the airbag bearing rings, and the pair of the outer auxiliary sealing rubber rings are respectively connected to the outer side wall of the natural gas assembly pipe;

[0009] It should be noted that, in the above, after a pair of airbag supporting rings are installed on the outside of the natural gas assembly pipe, the auxiliary reinforcement pads arranged thereon can make it better fixed and attached to the natural gas assembly pipe, and the inflation and deflation nozzles arranged on the airbag supporting rings can inflate the wrapped airbags. The inflated wrapped airbags can wrap the leaking parts and further pressurize them through the pressurized arc plates, thereby completing the sealing of the leak.

[0010] Preferably, an auxiliary pressure detection scale line is provided on the connection auxiliary monitoring column;

[0011] Preferably, a buffer auxiliary rubber pad is provided on the pressurized arc plate;

[0012] Preferably, an auxiliary reinforcement rubber pad is provided on the airbag bearing ring;

[0013] Preferably, an inflation and deflation nozzle is provided on the airbag bearing ring.

[0014] Beneficial Effects

[0015] The utility model provides a natural gas pipeline leakage plugging device. Compared with the prior art, the natural gas pipeline leakage plugging device has the following beneficial effects: the device cleverly uses the wrapped airbag through the auxiliary airbag assembly to accurately wrap the leak on the natural gas assembly pipeline, and then the auxiliary plugging pressure sealing monitoring structure pressurizes the wrapped airbag to effectively plug the leak point and ensure the safety and stability of the natural gas pipeline; it is worth mentioning that if the wrapped airbag leaks due to aging, the specially arranged connection auxiliary monitoring column of the device can intuitively detect and evaluate the state of the wrapped airbag, so that the plugging effect is clear at a glance, which greatly improves the safety and reliability of the device. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the front cross-sectional structure of a natural gas pipeline leakage plugging device described in the utility model.

[0017] Figure 2 It is a side sectional structural schematic diagram of a natural gas pipeline leakage plugging device described in the utility model.

[0018] In the figure: 1. Natural gas assembly pipeline; 2. Upper device shell; 3. Lower device shell; 4. Upper shell ear key; 5. Lower shell ear key; 6. Mounting bolt; 7. Locking nut; 8. Pressurized arc plate; 9. Pressure push block; 10. Push block placement groove; 11. Boost auxiliary spring; 12. Connection auxiliary monitoring column; 13. Airbag bearing ring; 14. Wrap airbag; 15. Outer auxiliary sealing rubber ring. DETAILED DESCRIPTION

[0019] Based on the embodiments of the present utility model, all other embodiments obtained by ordinary technicians in the field without making any creative work shall fall within the scope of protection of the present utility model.

[0020] Through the personnel in this field, all the electrical components in this case are connected to their corresponding power supplies through wires, and appropriate controllers and encoders should be selected according to actual conditions to meet the control requirements. The specific connection and control sequence should refer to the following working principle, and the electrical connection between the electrical components is completed in the order of working in sequence. The detailed connection means are well-known technologies in this field. The following mainly introduces the working principles and processes, and no longer explains the electrical control.

[0021] Example

[0022] The present invention will be described in detail below in conjunction with the accompanying drawings. Figure 1-2As shown, a natural gas pipeline leakage plugging device comprises: a natural gas assembly pipeline 1, an upper device shell 2 and a lower device shell 3, the upper device shell 2 and the lower device shell 3 are connected to each other, an auxiliary airbag assembly is installed on the natural gas assembly pipeline 1, and auxiliary plugging pressure sealing monitoring structures are installed on the upper device shell 2 and the lower device shell 3 respectively; the auxiliary plugging pressure sealing monitoring structure comprises: a pair of upper shell ear keys 4, a pair of lower shell ear keys 5, a pair of mounting bolts 6, a pair of locking screw washers 7, a pair of pressurized arc plates 8, a pair of pressure push blocks 9, a pair of push block placement A pair of upper shell ear keys 4 are respectively installed on the upper device shell 2, a pair of lower shell ear keys 5 are respectively installed on the lower device shell 3, a pair of mounting bolts 6 are respectively inserted on the pair of upper shell ear keys 4 and the pair of lower shell ear keys 5, and a pair of mounting bolts 6 are respectively screwed and inserted on a pair of locking screw washers 7, a pair of push block placement grooves 10 are respectively opened on the upper device shell 2 and the lower device shell 3, a pair of pressurized arc plates 8 are respectively installed on a pair of pressurized arc plates On the push block 9, a pair of the pressure push blocks 9 are respectively inserted into a pair of the push block placement grooves 10, a pair of the boost auxiliary springs 11 are respectively inserted into a pair of the push block placement grooves 10, and a pair of the boost auxiliary springs 11 are respectively connected to a pair of the pressure push blocks 9, and the upper device shell 2 and the lower device shell 3 are respectively provided with monitoring column through holes, a pair of the connection auxiliary monitoring columns 12 are respectively inserted into the upper device shell 2 and the lower device shell 3 through a pair of the monitoring column through holes, and a pair of the connection auxiliary monitoring columns 12 are respectively connected to a pair of the pressure push blocks 9 is connected; the auxiliary airbag assembly includes: a pair of airbag bearing rings 13, a wrapping airbag 14 and a pair of outer auxiliary sealing rubber rings 15; the pair of airbag bearing rings 13 are respectively sleeved on the natural gas assembly pipeline 1, the wrapping airbags 14 are respectively installed on the pair of airbag bearing rings 13, and the wrapping airbags 14 are connected to the outer side of the natural gas assembly pipeline 1, and the pair of outer auxiliary sealing rubber rings 15 are respectively installed on the pair of airbag bearing rings 13, and the pair of outer auxiliary sealing rubber rings 15 are respectively connected to the outer side wall of the natural gas assembly pipeline 1.

[0023] According to the attached Figure 1-2It is concluded that when the natural gas assembly pipeline 1 leaks during operation, the auxiliary airbag assembly is first installed on the leaking part of the natural gas assembly pipeline 1, and then the upper device shell 2 and the lower device shell 3 are combined together, so that a pair of pressurized arc plates 8 fully wrap the wrapped airbag 14, and then the upper shell ear key 4 and the lower shell ear key 5 are assembled together, and then the upper shell ear key 4 and the lower shell ear key 5 are locked and fixed to each other by installing bolts 6 and locking screw washers 7, so that the upper device shell 2 and the lower device shell 3 are combined with each other and firmly formed into a whole, and there is a cavity in the whole formed by the upper device shell 2 and the lower device shell 3. Therefore, when squeezed by the auxiliary airbag assembly, the pair of pressurized arc plates 8 will be pushed and lifted, thereby pushing the pressure push block 9 and compressing the booster auxiliary spring 11 in the push block placement groove 10, so that the connection auxiliary monitoring column 12 is expanded and lifted outward. In summary, the connection auxiliary monitoring column 1 2 After installation, the exposed part will be squeezed by the auxiliary airbag assembly, and more will be exposed to the overall outer side of the combination of the upper device shell 2 and the lower device shell 3. In this way, if the auxiliary airbag assembly is aged and leaks, the exposed part of the connecting auxiliary monitoring column 12 will be shortened, so that the operating status of the auxiliary airbag assembly can be monitored and evaluated according to the auxiliary pressure detection scale line on the connecting auxiliary monitoring column 12. The buffer auxiliary rubber pad set on the pressurized arc plate 8 can assist in squeezing the auxiliary airbag assembly and protect the airbag assembly; after a pair of airbag bearing rings 13 are installed on the outside of the natural gas assembly pipeline 1, the auxiliary reinforcement rubber pads set thereon can make it better fixed and attached to the natural gas assembly pipeline 1, and the inflation and deflation air nozzles set on the airbag bearing rings 13 can inflate the wrapped airbag 14. The inflated wrapped airbag 14 can wrap the leaking part and further pressurize it through the pressurized arc plate 8, so as to complete the plugging of the leak.

[0024] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A natural gas pipeline leakage plugging device, comprising: A natural gas assembly pipeline (1), an upper device shell (2) and a lower device shell (3), characterized in that the upper device shell (2) and the lower device shell (3) are connected to each other, an auxiliary airbag assembly is installed on the natural gas assembly pipeline (1), and auxiliary plugging and pressure sealing monitoring structures are installed on the upper device shell (2) and the lower device shell (3); The auxiliary plugging and pressure sealing monitoring structure comprises: a pair of upper shell ear keys (4), a pair of lower shell ear keys (5), a pair of mounting bolts (6), a pair of locking screw washers (7), a pair of pressure arc plates (8), a pair of pressure push blocks (9), a pair of push block placement grooves (10), a pair of pressure boosting auxiliary springs (11) and a pair of connection auxiliary monitoring columns (12); A pair of upper shell ear keys (4) are respectively installed on the upper device shell (2), a pair of lower shell ear keys (5) are respectively installed on the lower device shell (3), a pair of mounting bolts (6) are respectively inserted on the pair of upper shell ear keys (4) and the pair of lower shell ear keys (5), and the pair of mounting bolts (6) are respectively screwed and inserted on the pair of locking screw washers (7), a pair of push block placement grooves (10) are respectively opened on the upper device shell (2) and the lower device shell (3), a pair of pressure arc plates (8) are respectively installed on a pair of pressure push blocks (9), and a pair of pressure push blocks (9 ) are respectively inserted into a pair of the push block placement grooves (10), a pair of the boost auxiliary springs (11) are respectively inserted into a pair of the push block placement grooves (10), and the pair of the boost auxiliary springs (11) are respectively connected to a pair of the pressure push blocks (9), the upper device shell (2) and the lower device shell (3) are respectively provided with monitoring column through holes, a pair of the connection auxiliary monitoring columns (12) are respectively inserted into the upper device shell (2) and the lower device shell (3) through a pair of the monitoring column through holes, and the pair of the connection auxiliary monitoring columns (12) are respectively connected to a pair of the pressure push blocks (9).

2. A natural gas pipeline leakage plugging device according to claim 1, characterized in that: The auxiliary airbag assembly comprises: a pair of airbag bearing rings (13), a wrapping airbag (14) and a pair of outer auxiliary sealing rubber rings (15); A pair of the airbag bearing rings (13) are respectively mounted on the natural gas assembly pipe (1); the wrapping airbags (14) are respectively mounted on the pair of the airbag bearing rings (13), and the wrapping airbags (14) are connected to the outer side of the natural gas assembly pipe (1); a pair of the outer auxiliary sealing rubber rings (15) are respectively mounted on the pair of the airbag bearing rings (13), and the pair of the outer auxiliary sealing rubber rings (15) are respectively connected to the outer side wall of the natural gas assembly pipe (1).

3. A natural gas pipeline leakage plugging device according to claim 2, characterized in that: The connection auxiliary monitoring column (12) is provided with an auxiliary pressure detection scale line.

4. A natural gas pipeline leakage plugging device according to claim 3, characterized in that: A buffer auxiliary rubber pad is provided on the pressurizing arc plate (8).