Installation method for thermal insulation and decoration integrated facade panels
An installation method and a technology of exterior wall panels, which are applied in covering/lining, construction, building construction, etc., can solve problems affecting construction progress and project quality, shortening the service life of buildings, and cracking of wall finish coatings, etc. Achieve excellent thermal insulation properties, enhanced availability, time-saving and labor-saving handling and installation
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2015-05-27
- Estimated Expiration
- Not applicable · inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to the field of construction methods in the construction industry, in particular to an installation method for an integrated exterior wall panel with thermal insulation and decoration. Background technique
[0002] my country is a country with large energy consumption, and per capita resources are short. Energy shortage is the main contradiction restricting my country's economic development. Therefore, the issue of building energy conservation must be highly valued, and building energy conservation has become a key link in alleviating my country's energy shortage, improving the quality of people's living environment, reducing environmental pollution, and implementing the strategic goal of sustainable development. The external thermal insulation technology of external walls is an important technology in building energy conservation, and it plays a key role in the technical control of the construction design and construction pro...
Examples
Embodiment Construction
[0051] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0052] In this embodiment, refer to Figure 1 to Figure 7 , the specific implementation of the installation method includes the following steps (such as Figure 7 shown):
[0053] The first step is to deal with the main wall surface, check the condition of the original external wall brick, chisel out the hollow part, clean the wall surface with oxalic acid or detergent to ensure that the surface of the brick surface is clean and free of stains, and then use the paste interface Brush the wall surface with the agent to make it completely cover the brick wall surface, and ensure that the flatness reaches the intermediate plastering standard, and finally determine the beam position of the main steel structure of the main wall. In this embodiment, the beam of the main steel structure of the main wall I-beam 1 for transverse setting, ...