A light rain strong cold fog type artificial rainfall simulation device and its use method

Through the light rain strong cold mist artificial rainfall simulation device, the use of cold mist nozzles and water mist recovery curtain rooms, combined with hydraulic slope adjustment and runoff output devices, solves the problem that traditional devices cannot effectively simulate the intensity of light rainfall, and achieves a more accurate The rainfall produces runoff and sediment and the hydrological effects of ground cover are measured, and the occupied area is reduced.

CN110249878BInactive Publication Date: 2024-10-18SHANDONG AGRICULTURAL UNIVERSITY
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN201910598220.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-07-04
Publication Date
2024-10-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional artificial rainfall simulation devices cannot effectively simulate an environment with low rainfall intensity, resulting in inaccurate indoor quantitative results of rainfall runoff and hydrological effects on ground cover. They also occupy a large area. There is also a gap between theoretical and practical rainfall amounts and inaccuracies in spraying in nozzle design. Uniformity problem.

Method used

A light rain strong cold mist artificial rainfall simulation device is designed, which uses cold mist nozzles and water mist recovery curtain rooms to realize small water spraying and water recovery. It combines hydraulic slope adjustment and runoff output devices to simulate the natural rainfall environment. Reduce floor space, improve test efficiency, and improve the accuracy of measurement results.

Benefits of technology

It achieves simulating the natural rainfall environment in a smaller space, improves the measurement accuracy of runoff and sediment produced by rainfall and the hydrological effects of ground cover, reduces the floor space, improves test efficiency, and makes the rainfall environment closer to the real situation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110249878B_ABST
    Figure CN110249878B_ABST
Patent Text Reader

Abstract

The present application discloses a light rain and strong cold mist artificial rainfall simulation device and its use method, which relates to the field of water conservancy engineering technology, including: a water storage tank, a water mist recovery curtain room is arranged at the upper end of the water storage tank, the lower end of the water mist recovery curtain room is inserted into the upper end of the water storage tank, a cold mist type nozzle is arranged on the top of the water mist recovery curtain room, a water pump is arranged in the water storage tank, the cold mist type nozzle is connected to the water outlet of the water pump, and the water pump is electrically connected to the artificial rainfall control equipment; a test sample slot is arranged between the water mist recovery curtain room and the water storage tank, a runoff output device is arranged at the first end of the test sample slot, the first end of the test sample slot is movably connected to the water mist recovery curtain room, and the second end of the test sample slot is movably connected to the water storage tank. The cold mist type nozzle can realize the spraying of a small amount of water, and the sprayed water, in addition to entering the test sample slot, the rest of the sprayed water flows back to the water storage tank along the water mist recovery curtain room. Compared with the traditional artificial rainfall method, the indoor quantitative measurement result is more accurate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of water conservancy engineering, and in particular to a light rain strong cold fog type artificial rainfall simulation device and a method for using the same. Background Art

[0002] Since rainfall under natural conditions is often characterized by uncertainty, randomness, and instability, soil and water conservation experimental research is subject to limitations such as long research cycles and large information interference. It is urgent to accelerate the development and research of artificial rainfall simulation devices.

[0003] The artificial simulated rainfall device is an effective experimental device for soil and water conservation research. By creating a rainfall environment that includes important factors such as rainfall amount, rainfall intensity, and rainfall duration, it can quantitatively carry out mechanism research on soil erosion, runoff and sediment production, non-point source pollution, and hydrological characteristics in different underlying surface areas. Most artificial simulated rainfall devices in traditional technologies are presented in the form of artificial simulated rainfall halls, which occupy a large area, and the sprinklers are mostly spray-type or side-spray-type, resulting in a certain gap between theoretical rainfall and practical rainfall, and the minimum rainfall intensity that can be set is mostly about 30mm / h.

[0004] For natural rainfall, the rainfall intensity is mostly between 0mm / h-3mm / h. Therefore, the traditional artificial rainfall simulation hall cannot simulate the environment of small rainfall intensity commonly seen in nature to a certain extent, which makes the indoor quantitative results of rainfall runoff and sand production, ground cover hydrological effects, etc. inaccurate. Summary of the invention

[0005] In order to solve the above technical problems, this application proposes the following technical solutions:

[0006] In the first aspect, an embodiment of the present application provides a light rain intensity cold mist artificial rainfall simulation device, comprising: a water tank, a water mist recovery curtain room is arranged at the upper end of the water tank, the lower end of the water mist recovery curtain room is inserted into the upper end of the water tank, a cold mist nozzle is arranged on the top of the water mist recovery curtain room, a water pump is arranged in the water tank, the cold mist nozzle is connected with the water outlet of the water pump, and the water pump is electrically connected to the artificial rainfall control equipment; a test sample trough is arranged between the water mist recovery curtain room and the water tank, a runoff output device is arranged at the first end of the test sample trough, the first end of the test sample trough is movably connected to the water mist recovery curtain room, and the second end of the test sample trough is movably connected to the water tank.

[0007] By adopting the above implementation method, a small amount of water can be sprayed through the cold mist nozzle, and the sprayed water will not only enter the test sample tank, but also return to the water storage tank along the water mist recovery curtain room. Therefore, the above device can simulate the natural rainfall environment of light rain under artificial conditions. Compared with the traditional artificial rainfall method, it reduces the occupied area, improves the test efficiency, creates a rainfall environment closer to the real rainfall, and makes the indoor quantitative measurement results of rainfall runoff and sand production, ground cover hydrological effects, etc. more accurate.

[0008] In combination with the first aspect, in a first possible implementation of the first aspect, a water hose is arranged between the cold mist nozzle and the water outlet of the water pump, and both ends of the water hose are respectively connected to the water inlet of the cold mist nozzle and the water outlet of the water pump.

[0009] In combination with the first possible implementation of the first aspect, in a second possible implementation of the first aspect, a plurality of the cold mist nozzles are provided, and the plurality of the cold mist nozzles are evenly arranged on the top of the water mist recovery curtain room.

[0010] In combination with the second possible implementation manner of the first aspect, in a third possible implementation manner of the first aspect, the runoff output device includes a first runoff output pipe and a second runoff output pipe, one end of the first runoff output pipe is connected to the top of the first end of the test sample trough, and the other end of the first runoff output pipe is movably connected to the side wall of the water mist recovery curtain room; one end of the second runoff output pipe is connected to the bottom of the first end of the test sample trough, and the other end of the second runoff output pipe is movably connected to the side wall of the water mist recovery curtain room.

[0011] In combination with the third possible implementation of the first aspect, in a fourth possible implementation of the first aspect, a hydraulic slope adjustment rod is provided at the bottom of the second end of the test sample trough, and both ends of the hydraulic slope adjustment rod are respectively fixedly connected to the bottom of the second end of the test sample trough and the water tank.

[0012] In combination with the fourth possible implementation method of the first aspect, in a fifth possible implementation method of the first aspect, a fixed platform is provided on the side wall of the water tank corresponding to the second end of the test sample trough, and the two ends of the hydraulic slope adjustment rod are respectively fixedly connected to the bottom of the second end of the test sample trough and the fixed platform.

[0013] In combination with the first aspect or any possible implementation of the first to fifth aspects, in a sixth possible implementation of the first aspect, the outer side of the water mist recovery curtain house is fixedly connected to a movable bracket, and the movable bracket is used to fix or adjust the water mist recovery curtain house.

[0014] In combination with the sixth possible implementation of the first aspect, in the seventh possible implementation of the first aspect, the artificial rainfall control equipment includes: a control computer, a water level sensor and a frequency conversion controller, the water level sensor is arranged in the water tank, the frequency conversion controller is electrically connected to the water pump, and the control computer is electrically connected to the water level sensor and the frequency conversion controller respectively.

[0015] In combination with the first aspect, in an eighth possible implementation manner of the first aspect, the water mist recovery screen room includes a transparent acrylic water mist recovery screen room.

[0016] In the second aspect, an embodiment of the present application provides a method for using a light rain intensity cold mist artificial rainfall simulation device, using the device described in the first aspect or any possible implementation of the first aspect, and the method includes: humidifying the inner wall of the water mist recovery room before artificial rainfall until the water droplets attached to the inner wall of the water mist recovery room are in a saturated state; starting the water pump through the artificial rainfall control device to transport the water in the water tank to the cold mist nozzle, and the water sprayed by the cold mist nozzle enters the test sample trough and the inner wall of the water mist recovery room, wherein the water sprayed on the inner wall of the mist recovery room flows back into the water tank; when the control of artificial rainfall ends, the amount of water flowing out of the runoff output device and the amount of water remaining in the water tank are obtained, which are used for the study of the hydrological effects of rainfall on runoff and sand production and ground cover. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 A schematic diagram of the structure of a light rain strong cold fog artificial rainfall simulation device provided in an embodiment of the present application;

[0018] Figure 2 A schematic flow chart of a method for using a light rain strong cold fog artificial rainfall simulation device provided in an embodiment of the present application;

[0019] Figure 1-2 The symbols are represented as:

[0020] 1- water storage tank, 2- water mist recovery curtain room, 3- cold mist nozzle, 4- water pump, 5- test sample tank, 6- runoff output device, 7- water delivery hose, 8- test sample, 9- hydraulic slope adjustment rod, 10- fixed platform, 11- mobile bracket, 12- control computer, 13- water level sensor, 14- frequency conversion controller. DETAILED DESCRIPTION

[0021] The present solution is described below in conjunction with the accompanying drawings and specific implementation methods.

[0022] Figure 1 This is a structural diagram of a light rain strong cold fog artificial rainfall simulation device provided in the embodiment of the present application, see Figure 1The light rain intensity cold mist artificial rainfall simulation device provided in the embodiment of the present application comprises: a water tank 1, a water mist recovery curtain room 2 is arranged at the upper end of the water tank 1, the lower end of the water mist recovery curtain room 2 is inserted into the upper end of the water tank 1, a cold mist type nozzle 3 is arranged on the top of the water mist recovery curtain room 2, a water pump 4 is arranged in the water tank 1, the cold mist type nozzle 3 is connected to the water outlet of the water pump 4, and the water pump 4 is electrically connected to the artificial rainfall control device. A test sample slot 5 is arranged between the water mist recovery curtain room 2 and the water tank 1, a runoff output device 6 is arranged at the first end of the test sample slot 5, the first end of the test sample slot 5 is movably connected to the water mist recovery curtain room 2, and the second end of the test sample slot 5 is movably connected to the water tank 1.

[0023] In the embodiment of the present application, the water mist recovery room 2 is a transparent acrylic water mist recovery room, so that the artificial rainfall simulation inside can be observed from the outside. Moreover, the lower opening of the water mist recovery room 2 is smaller than the upper opening of the water storage tank 1, so that when the cold mist nozzle 3 sprays water, the water sprayed into the water mist recovery room 2 flows back into the water storage tank 1, avoiding the water of the simulated artificial rainfall except for the water entering the test sample tank 5, and the rest is sprayed on the ground. The water mist recovery room 2 can effectively recover the water on the side wall, making the rainfall result closer to the test setting.

[0024] The cold mist nozzle 3 used in this embodiment is different from the traditional nozzle, and the water delivery method is more gentle, which can solve the problem of dripping and poor uniformity caused by too little water output in small-intensity artificial simulated rainfall. The water pump 4 is used to provide the power required for artificial simulated rainfall, and transport the water in the water tank 1 to the cold mist nozzle 3 for spraying. Specifically, a water delivery hose 7 is arranged between the cold mist nozzle 3 and the water outlet of the water pump 4, and the two ends of the water delivery hose 7 are respectively connected to the water inlet of the cold mist nozzle 3 and the water outlet of the water pump 4.

[0025] Moreover, the cold mist type nozzle 3 is provided with a plurality of them, and the plurality of cold mist type nozzles 3 are evenly arranged on the top of the water mist recovery curtain room 2. In this way, the uniformity of rainfall during artificial rainfall simulation can be ensured, which is closer to the real rainfall environment.

[0026] In the embodiment of the present application, different environments can be set in the test sample slot 5 as needed. For example, the test sample 8 can be set in the test sample slot to be soil, a mixture of soil and gravel, or turf can be set on the surface of soil or a mixture of soil and gravel, etc. Of course, more choices can be made according to the test sample 8 to be simulated as needed, which will not be repeated here.

[0027] After the water sprayed by the cold mist nozzle 3 enters the test sample tank 5, according to the natural environment, part of the rainwater will flow through the surface, and the other part will penetrate into the bottom and flow from the bottom. Specifically, the runoff output device 6 in this embodiment includes a first runoff output pipe and a second runoff output pipe, one end of the first runoff output pipe is connected to the top of the first end of the test sample tank 5, and the other end of the first runoff output pipe is movably connected to the side wall of the water mist recovery curtain room 2 to simulate surface runoff. One end of the second runoff output pipe is connected to the bottom of the first end of the test sample tank 5, and the other end of the second runoff output pipe is movably connected to the side wall of the water mist recovery curtain room 2 to simulate underground runoff. Except for the first runoff output pipe and the second runoff output pipe, the rest of the water entering the test sample tank 5 is retained in the test sample 8.

[0028] Furthermore, in this embodiment, in order to simulate different slopes, a hydraulic slope adjustment rod 9 is provided at the bottom of the second end of the test sample slot 5, and the two ends of the hydraulic slope adjustment rod 9 are respectively fixedly connected to the bottom of the second end of the test sample slot 5 and the water storage tank 1. Specifically, a fixed platform 10 is provided on the side wall of the water tank corresponding to the second end of the test sample slot 5, and the two ends of the hydraulic slope adjustment rod 9 are respectively fixedly connected to the bottom of the second end of the test sample slot 5 and the fixed platform 10.

[0029] See also Figure 1 The outer side of the water mist recovery curtain room 2 is fixedly connected to a movable bracket 11, and the movable bracket 11 is used to fix or adjust the water mist recovery curtain room 2. For example, the height and position of the water mist recovery curtain room 2 can be adjusted.

[0030] In this embodiment, when the operator realizes artificial rainfall simulation, it is also necessary to rely on artificial rainfall control equipment, which includes: a control computer 12, a water level sensor 13 and a frequency conversion controller 14, wherein the water level sensor 13 is arranged in the water storage tank 1, the frequency conversion controller 14 is electrically connected to the water pump 4, and the control computer 12 is electrically connected to the water level sensor 13 and the frequency conversion controller 14 respectively. In this embodiment, the control computer 12 can set parameters such as the time and rainfall of artificial rainfall, the frequency conversion controller 14 controls the water pump 4, and the water level sensor 13 can transmit the water level information in the water storage tank 1 to the control computer 12 in real time, so as to manually judge whether artificial rainfall needs to be continued according to the displayed water level information.

[0031] In an illustrative embodiment, the control computer 12 sets the required artificial simulated rainfall parameters, such as rainfall duration (h), rainfall amount (mm), rainfall intensity (mm / h), etc., and starts the frequency conversion controller 14 in an analog signal transmission mode to control the water pump 4. Under the power provided by the water pump 4, the water in the water tank 1 is transported to the cold mist nozzle 3 through the water hose 7 to start the simulated rainfall. During the artificial simulated rainfall, the water that falls on the side wall of the transparent acrylic water mist recovery curtain room 2 flows back into the water tank 1.

[0032] The amount of precipitation required for artificially simulating rainfall is converted into the height of the water level drop in the water storage tank 1 according to the following formula:

[0033]

[0034] Wherein, the test area of ​​the test sample slot 5 is S1 (m 2 ), the test slope set by the hydraulic slope adjustment lever 9 is (°), and the surface area of ​​the water tank 1 is S2 (m 2 ), set the simulated rainfall intensity to (mm / h), set the simulated rainfall time to t (h), and the water level drop height in the water tank 1 to H (m).

[0035] The water level sensor 13 continuously feeds back the water level information to the control computer 12 for processing. The operator continuously adjusts the parameters of the frequency conversion controller 14 according to the processing results, and continuously adjusts the output power of the water pump 4 to make the artificial simulated rainfall result close to the required rainfall environment. The runoff output device 6 is responsible for exporting the runoff generated in the test sample tank 5 (not flowing into the water storage tank 1) for testing.

[0036] As can be seen from the above embodiments, this embodiment provides a light rain intensity cold mist artificial rainfall simulation device, comprising: a water storage tank 1, a water mist recovery curtain room 2 is arranged at the upper end of the water storage tank 1, the lower end of the water mist recovery curtain room 2 is inserted into the upper end of the water storage tank 1, a cold mist type nozzle 3 is arranged on the top of the water mist recovery curtain room 2, a water pump 4 is arranged in the water storage tank 1, the cold mist type nozzle 3 is connected to the water outlet of the water pump 4, and the water pump 4 is electrically connected to the artificial rainfall control device. A test sample slot 5 is arranged between the water mist recovery curtain room 2 and the water storage tank 1, a runoff output device 6 is arranged at the first end of the test sample slot 5, the first end of the test sample slot 5 is movably connected to the water mist recovery curtain room 2, and the second end of the test sample slot 5 is movably connected to the water storage tank 1. The cold mist nozzle 3 can spray a small amount of water, and the sprayed water not only enters the test sample tank 5, but also flows back to the water storage tank 1 along the water mist recovery curtain room 2. Therefore, the above device can simulate the natural rainfall environment of light rain under artificial conditions. Compared with the traditional artificial rainfall test, it reduces the occupied area, improves the test efficiency, creates a rainfall environment closer to the real rainfall, and makes the indoor quantitative measurement results of rainfall runoff and sand production, ground cover hydrological effects, etc. more accurate.

[0037] Corresponding to the light rain strong cold mist artificial rainfall simulation device provided in the above embodiment, the present application also provides an embodiment of a method for using the light rain strong cold mist artificial rainfall simulation device. Figure 2 , the method comprising:

[0038] S101, humidifying the inner wall of the water mist recovery room before artificial rainfall, until the water droplets attached to the inner wall of the water mist recovery room are in a saturated state.

[0039] Since the simulation device used in the above embodiment is a natural rainfall device simulating light rain, in order to further improve the simulation accuracy, the device needs to be started for a period of time before the test to moisten the side walls of the water mist recovery curtain room, thereby reducing the error caused by the side wall interception. Specifically, when the side walls of the water mist recovery curtain room are full of water and no longer fall, the saturation state is reached, and artificial rainfall can be simulated at this time.

[0040] S102, starting the water pump through the artificial rainfall control equipment to transport the water in the water tank to the cold mist nozzle, and the water sprayed from the cold mist nozzle enters the test sample tank and the inner wall of the water mist recovery curtain room, wherein the water sprayed on the inner wall of the mist recovery curtain room flows back into the water tank.

[0041] The required artificial simulated rainfall parameters, such as rainfall duration (h), rainfall amount (mm), rainfall intensity (mm / h), etc., are set by the control computer, and the frequency conversion controller is turned on to control the water pump in the form of analog signal transmission. Under the power provided by the water pump, the water in the water tank is transported to the cold mist nozzle through the water hose to start the simulated rainfall. During the artificial simulated rainfall, the water that falls on the side wall of the transparent acrylic water mist recovery curtain room flows back to the water tank 1.

[0042] The amount of precipitation required for artificially simulating rainfall is converted into the height of the water level drop in the water storage tank 1 according to the following formula:

[0043]

[0044] In the formula, the test area of ​​the test sample tank is S1 (m 2 ), the test slope set by the hydraulic slope adjustment lever is (°), and the surface area of ​​the water tank is S2 (m 2 ), set the simulated rainfall intensity to (mm / h), set the simulated rainfall time to t (h), and the height of the water level drop in the water tank to H (m).

[0045] S103, when the artificial rainfall is controlled to be finished, the amount of water flowing out of the runoff output device and the amount of water remaining in the water storage tank are obtained.

[0046] The runoff output device is responsible for exporting the runoff generated in the test sample tank (not flowing into the water tank) for testing. The amount of water output from the water tank is determined based on the amount of water obtained by the runoff output device and the height of the water level drop in the water tank after the artificial simulated rainfall. Finally, the amount of water retained in the test sample under the current simulated environment is determined. Furthermore, water, soil, sand, etc. flowing out of the runoff output device can also be obtained. This can enable later research on the hydrological effects of rainfall-generated runoff and sand and ground cover.

[0047] In this embodiment, the light rain intensity cold mist artificial rainfall simulation device can achieve light rain simulation rainfall of different intensities, and the test sample slot can also be set with different slopes. The cold mist nozzle makes the various elements of the artificial simulated rainfall closer to natural rainfall. The artificial rainfall simulation using the above simulation device makes the measurement result more accurate.

[0048] It should be noted that, in this article, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0049] Of course, the above description is not limited to the above examples. Technical features not described in the present application can be achieved by or by using existing technologies, which will not be repeated here. The above embodiments and drawings are only used to illustrate the technical solution of the present application and are not limitations of the present application. For example, the present application is only described in detail in combination with and with reference to the preferred implementation methods. Ordinary technicians in this field should understand that the changes, modifications, additions or substitutions made by ordinary technicians in this technical field within the essential scope of the present application do not depart from the purpose of the present application and should also fall within the scope of protection of the claims of the present application.

Claims

1. A method for using a light rain strong cold fog artificial rainfall simulation device, characterized in that: The following light rain strength cold mist artificial rainfall simulation device is adopted, comprising: a water storage tank, a water mist recovery curtain room is arranged at the upper end of the water storage tank, the lower end of the water mist recovery curtain room is inserted into the upper end of the water storage tank, a cold mist type nozzle is arranged on the top of the water mist recovery curtain room, a water pump is arranged in the water storage tank, the cold mist type nozzle is connected with the water outlet of the water pump, and the water pump is electrically connected with the artificial rainfall control equipment; a test sample slot is arranged between the water mist recovery curtain room and the water storage tank, a runoff output device is arranged at the first end of the test sample slot, the first end of the test sample slot is movably connected with the water mist recovery curtain room, and the second end of the test sample slot is movably connected with the water storage tank; A water delivery hose is arranged between the cold mist nozzle and the water outlet of the water pump, and the two ends of the water delivery hose are respectively connected to the water inlet of the cold mist nozzle and the water outlet of the water pump; a plurality of cold mist nozzles are arranged, and the plurality of cold mist nozzles are evenly arranged on the top of the water mist recovery curtain room; The runoff output device includes a first runoff output pipe and a second runoff output pipe, one end of the first runoff output pipe is connected to the top of the first end of the test sample tank, and the other end of the first runoff output pipe is movably connected to the side wall of the water mist recovery curtain room; one end of the second runoff output pipe is connected to the bottom of the first end of the test sample tank, and the other end of the second runoff output pipe is movably connected to the side wall of the water mist recovery curtain room; The method comprises: Before artificial rainfall, the inner wall of the water mist recovery room is humidified until the water droplets attached to the inner wall of the water mist recovery room are in a saturated state; The water pump is started by the artificial rainfall control device to transport the water in the water storage tank to the cold mist nozzle, and the water sprayed by the cold mist nozzle enters the test sample tank and the inner wall of the water mist recovery curtain room, wherein the water sprayed on the inner wall of the mist recovery curtain room flows back into the water storage tank; When the artificial rainfall is controlled to be over, the amount of water flowing out of the runoff output device and the amount of water remaining in the water storage tank are obtained for studying the hydrological effects of rainfall on runoff and sand production and ground cover.

2. The method for using the light rain strong cold fog artificial rainfall simulation device according to claim 1 is characterized in that: A hydraulic slope adjustment rod is arranged at the bottom of the second end of the test sample tank, and two ends of the hydraulic slope adjustment rod are respectively fixedly connected to the bottom of the second end of the test sample tank and the water storage tank.

3. The method for using the light rain strong cold fog artificial rainfall simulation device according to claim 2 is characterized in that: A fixed platform is arranged on the side wall of the water tank corresponding to the second end of the test sample tank, and the two ends of the hydraulic slope adjustment rod are respectively fixedly connected to the bottom of the second end of the test sample tank and the fixed platform.

4. The method for using the light rain strong cold fog artificial rainfall simulation device according to any one of claims 1 to 3, characterized in that: The outer side of the water mist recovery curtain room is fixedly connected to a movable bracket, and the movable bracket is used to fix or adjust the water mist recovery curtain room.

5. The method for using the light rain strong cold fog artificial rainfall simulation device according to claim 4 is characterized in that: The artificial rainfall control equipment includes: a control computer, a water level sensor and a frequency conversion controller. The water level sensor is arranged in the water storage tank. The frequency conversion controller is electrically connected to the water pump. The control computer is electrically connected to the water level sensor and the frequency conversion controller respectively.

6. The method for using the light rain strong cold fog artificial rainfall simulation device according to claim 1, characterized in that: The water mist recovery curtain room includes a transparent acrylic water mist recovery curtain room.

Citation Information

Patent Citations

  • Simulation experiment device for basin runoff yielding mechanisms

    CN105225600A

  • Enclosed type dismountable rainfall simulation device applied to buildings and testing method

    CN108458946A

  • Testing device for roof greening rainwater detention storage performance of sloping roof and testing method

    CN108955757A

  • Light rain strong cold fog type artificial rainfall simulation device

    CN210184071U