Palletizing system and palletizing method

By designing side-by-side packaging conveyor lines, empty pallet conveyor lines and finished product conveyor lines, a robot palletizer is used to realize the automatic palletization of multiple conveyor lines, which solves the high cost, large area and inability to simultaneously in the existing technology. The problem of multi-line palletizing improves production efficiency.

CN110482239BActive Publication Date: 2024-11-01广州南沙珠江啤酒有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910829509.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-09-03
Publication Date
2024-11-01
Estimated Expiration
2039-09-03

AI Technical Summary

Technical Problem

The existing beer industry has high cost and large area, and it is impossible to carry out palletizing operations of more than two lines at the same time.

Method used

Design a palletizing system, including packaging conveyor lines, empty pallet conveyor lines and finished product conveyor lines arranged side by side, use a robot palletizer to perform palletizing operations on multiple conveyor lines at the same time, and pass through empty pallet conveyor lines Provide empty pallets for multiple palletizing platforms to achieve fully automated palletizing.

Benefits of technology

Fully automated palletizing operations of multiple conveying lines have been realized, which reduces equipment investment costs and production line footprints, and improves production efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110482239B_ABST
    Figure CN110482239B_ABST
Patent Text Reader

Abstract

The present application provides a palletizing system and a palletizing method, the palletizing system includes a first packaging conveyor line, a second packaging conveyor line, an empty pallet conveyor line, a finished product conveyor line, a first palletizing platform, a second palletizing platform and a robot palletizer, the first palletizing platform and the second palletizing platform are arranged between the empty pallet conveyor line and the finished product conveyor line, the empty pallet conveyor line is provided with a first pallet buffer area and a second pallet buffer area, the finished product conveyor line is provided with a first finished product buffer area and a second finished product buffer area, the first pallet buffer area is transmission-connected with the first palletizing platform and the first finished product buffer area, the second pallet buffer area is transmission-connected with the second palletizing platform and the first finished product buffer area, and the robot palletizer is erected above the first pallet buffer area and / or the second pallet buffer area. The palletizing system has the advantages of high production efficiency, low cost and small footprint.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of automated production lines, and specifically relates to a palletizing system and a palletizing method. Background Art

[0002] At present, the finished product palletizing equipment in the domestic beer industry is still dominated by mechanical palletizers. A high-speed production line is usually equipped with one or two mechanical palletizers, and each palletizer requires a dedicated employee. At the same time, there are also a few that use robots for box clamping and palletizing. However, the existing palletizing equipment, whether it is a mechanical palletizer or a robot palletizer, generally has the following disadvantages:

[0003] 1. It is only suitable for single-line palletizing. It is impossible to use one palletizer to perform palletizing operations on more than two lines at the same time;

[0004] 2. Since a production line needs to be equipped with at least one palletizer, the equipment investment cost is relatively high, and the entire palletizing production line occupies a large area. Summary of the invention

[0005] In order to overcome the above-mentioned shortcomings of the prior art, the purpose of this application is to provide a palletizing system and a palletizing method, aiming to solve the technical problems of the existing palletizing production line having high cost, large floor space, and inability to use one palletizer to perform palletizing operations on more than two lines at the same time.

[0006] The technical solution adopted by this application to solve its technical problem is:

[0007] A palletizing system comprises a first packaging conveyor line and a second packaging conveyor line arranged side by side, an empty pallet conveyor line and a finished product conveyor line arranged side by side, a first palletizing platform and a second palletizing platform arranged side by side, and a robot palletizer, wherein the first packaging conveyor line is arranged vertically to the empty pallet conveyor line, the first palletizing platform and the second palletizing platform are arranged between the empty pallet conveyor line and the finished product conveyor line, the empty pallet conveyor line is provided with a first pallet buffer area and a second pallet buffer area in sequence along the conveying direction, the finished product conveyor line is provided with a first finished product buffer area and a second finished product buffer area, the first pallet buffer area, the first pallet buffer area, the first pallet buffer area and the second palletizing platform are provided The first pallet buffer area, the second palletizing platform, and the second finished product buffer area are arranged in sequence along the conveying direction of the first packaging conveyor line, and the first pallet buffer area is isolated from the exit end of the first packaging conveyor line, the second pallet buffer area, the second stacking platform, and the second finished product buffer area are arranged in sequence along the conveying direction of the second packaging conveyor line, and the second pallet buffer area is isolated from the exit end of the second packaging conveyor line, the first pallet buffer area is transmission-connected with the first stacking platform and the first finished product buffer area, the second pallet buffer area is transmission-connected with the second stacking platform and the first finished product buffer area, and the robot palletizer is erected above the first pallet buffer area and / or the second pallet buffer area.

[0008] Preferably, the aforementioned palletizing system further comprises a first chain transmission mechanism, and in the conveying direction of the first packaging conveyor line, the first pallet buffer area is simultaneously transmission-connected to the first palletizing platform and the first finished product buffer area through the first chain transmission mechanism.

[0009] Preferably, the aforementioned palletizing system further comprises a second chain transmission mechanism, and in the conveying direction of the second packaging conveyor line, the second pallet buffer area is simultaneously transmission-connected to the second palletizing platform and the second finished product buffer area through the second chain transmission mechanism.

[0010] Preferably, the aforementioned palletizing system also includes a third packaging conveyor line, a third palletizing platform and a third chain transmission mechanism. The third packaging conveyor line is arranged side by side with the first packaging conveyor line and the second packaging conveyor line, and the third palletizing platform is arranged side by side with the first palletizing platform and the second palletizing platform. A third pallet buffer area is also provided on the empty pallet conveyor line, and a third finished product buffer area is also provided on the finished product conveyor line. The second pallet buffer area is arranged between the first pallet buffer area and the third pallet buffer area. The third pallet buffer area, the third palletizing platform and the third finished product buffer area are arranged in sequence along the conveying direction of the third packaging conveyor line, and the third pallet buffer area is isolated from the exit end of the third packaging conveyor line. The robot palletizer is erected above the second pallet buffer area. In the conveying direction of the third packaging conveyor line, the third pallet buffer area is simultaneously connected to the third palletizing platform and the third finished product buffer area through the third chain transmission mechanism.

[0011] Preferably, a film wrapping machine is also provided on the finished product conveying line, and the second finished product buffer area, the first finished product buffer area and the film wrapping machine are arranged in sequence along the conveying direction of the finished product conveying line.

[0012] Preferably, a pallet splitter is provided between the first pallet buffer area and the entrance end of the empty pallet conveyor line, and the pallet splitter is used to split the whole stack of pallets from the entrance end of the empty pallet conveyor line into single empty pallets, wherein the whole stack of pallets is formed by stacking multiple empty pallets.

[0013] Preferably, the panel disassembly machine includes a box body and a motor, a transmission mechanism, a cam, a bearing, a connecting sleeve, a pull rod, a cross bar, a support roller seat, a guide rail, a connecting rod, a swing arm, a clamping arm and a cylinder installed in the box body and arranged in pairs. The output shaft of the motor is connected to the cam through the transmission mechanism. The connecting sleeve is mounted on the bearing, and the bearing is fixedly connected to the flange portion of the cam along the axial direction. One end of the pull rod is fixedly connected to the connecting sleeve, and the other end is fixedly connected to the cross bar. The support roller seat is arranged in the vertical direction and is respectively fixedly connected to one end of the cross bar and the connecting sleeve. The first end of the rod is fixedly connected and slidably cooperates with the guide rail, the first end of the connecting rod is rotatably connected to the first end of the swing arm and slidably connected to the inner wall of the box body in the horizontal direction, the second end of the connecting rod is movably connected to the inner wall of the box body, the second end of the swing arm is fixedly connected to one end of the clamping arm, and the length direction of the clamping arm is parallel to the conveying direction of the empty pallet conveyor line, the cylinder is arranged on one side of the swing arm and the piston rod of the cylinder is movably connected to the swing arm, wherein the pull rod is arranged in the vertical direction, the guide rail is arranged in the vertical direction, and the wheel center position of the cam is higher than the position of the cross bar.

[0014] Preferably, the aforementioned palletizing system also includes a fourth chain transmission mechanism and a manual code scanning conveyor line arranged side by side with the empty pallet conveyor line. A manual code scanning area is provided at the inlet end of the manual code scanning conveyor line, and an automatic code scanning area is also provided between the first pallet buffer area and the exit of the pallet dismantling machine. The automatic code scanning area is connected to the manual code scanning area through the fourth chain transmission mechanism.

[0015] Preferably, the first packaging conveyor line is also provided with a first arranging and arranging mechanism, which includes a first cylinder, a first connecting rod, a first baffle and a first differential belt. The first piston rod of the first cylinder is rotatably connected to one end of the first connecting rod, the other end of the first connecting rod is fixedly connected to the first end of the first baffle, and the first end of the first baffle is rotatably connected to the edge of the first packaging conveyor line. The first differential belt is wound around the roller of the first packaging conveyor line and is arranged between the entrance end of the first packaging conveyor line and the first baffle.

[0016] A palletizing method, applied to the aforementioned palletizing system, comprises:

[0017] Detect whether there are empty pallets on the first palletizing platform and the second palletizing platform;

[0018] If there are empty pallets on both the first palletizing platform and the second palletizing platform, the robot palletizer is controlled to move the finished product packages on the packaging conveyor line with the highest priority to the first palletizing platform or the second palletizing platform for palletizing according to the predetermined first priority strategy, wherein the packaging conveyor line includes the first packaging conveyor line and the second packaging conveyor line;

[0019] If there are no empty pallets on either the first palletizing platform or the second palletizing platform, then according to the predetermined second priority strategy, the empty pallet conveyor line is controlled to transport the empty pallet placed thereon to the palletizing platform with a higher priority, and when the empty pallet arrives at the palletizing platform with a higher priority, the robot palletizer is controlled to transport the finished product packages on the corresponding packaging conveyor line to the first palletizing platform or the second palletizing platform for palletizing, wherein the palletizing platforms include the first palletizing platform and the second palletizing platform;

[0020] If there is an empty pallet on the first palletizing platform and there is no empty pallet on the second palletizing platform, control the robot palletizer to move the finished product packages on the first packaging conveyor line to the first palletizing platform for palletizing, and control the empty pallet conveyor line to transport the empty pallet placed thereon to the second palletizing platform;

[0021] If there is no empty pallet on the first palletizing platform and there is an empty pallet on the second palletizing platform, control the robot palletizer to move the finished product packages on the second packaging conveyor line to the second palletizing platform for palletizing, and control the empty pallet conveyor line to transport the empty pallet placed thereon to the first palletizing platform;

[0022] When the finished product packages on the first palletizing platform or the second palletizing platform are palletized to a predetermined number to form a finished product stack, the robot palletizer is controlled to switch to another palletizing platform for palletizing, and the finished product stack is transported to the finished product conveyor line for delivery.

[0023] Compared with the prior art, the beneficial effects of this application are:

[0024] The palletizing system proposed in the present application can convey two finished product packages of different specifications respectively through the first packaging conveyor line and the second packaging conveyor line, and at the same time, the empty pallets can be conveyed to the first palletizing platform corresponding to the first packaging conveyor line and the second palletizing platform corresponding to the second packaging conveyor line respectively through the empty pallet conveyor line, and then the finished product packages on different packaging conveyor lines are moved to the corresponding palletizing platforms for palletizing by the robot palletizer, and after the palletizing is completed, the palletized finished product packages can be shipped out of the warehouse through the finished product conveyor line, thereby realizing the full automation of the palletizing operation. At the same time, the overall layout of the palletizing system is compact and ingenious, and at least two packaging conveyor lines can be palletized at the same time by one robot palletizer, and at least two palletizing platforms can be provided with empty pallets by one empty pallet conveyor line, which not only improves the production efficiency, but also reduces the high investment cost of equipment and reduces the floor space of the production line. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0026] Figure 1 A top view of the overall structure of a palletizing system in one embodiment of the present application;

[0027] Figure 2 This is a top view of the overall structure of the palletizing system in one embodiment of the present application without the robot palletizer;

[0028] Figure 3 for Figure 2 The enlarged schematic diagram of point A in the middle;

[0029] Figure 4 for Figure 2 The enlarged schematic diagram of point B in the middle;

[0030] Figure 5 This is a schematic diagram of the structure of a single empty pallet in one embodiment of the present application;

[0031] Figure 6 This is a schematic diagram of the use status of the panel disassembly machine in one embodiment of the present application;

[0032] Figure 7 This is a schematic diagram of an external top view of a panel removal machine in one embodiment of the present application;

[0033] Figure 8 This is a front view of the internal structure of a panel disassembly machine in one embodiment of the present application;

[0034] Fig. 9 for Figure 8 Structural cross-sectional view along CC direction;

[0035] Fig.10 for Fig. 9 Schematic diagram of the structure along the direction of arrow D. DETAILED DESCRIPTION

[0036] In order to more clearly understand the above-mentioned objects, features and advantages of the present application, the present application is described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that, in the absence of conflict, the embodiments of the present application and the features in the embodiments can be combined with each other. In the following description, many specific details are set forth in order to fully understand the present application, and the described embodiments are only a part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the present application.

[0037] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application.

[0038] Reference Figure 1 , Figure 2 and Figure 5 The embodiment of the present application provides a palletizing system, comprising a first packaging conveyor line 1 and a second packaging conveyor line 2 arranged side by side, an empty pallet conveyor line 5 and a finished product conveyor line 8 arranged side by side, a first palletizing platform 71 and a second palletizing platform 72 arranged side by side, and a robot palletizer 6, the first packaging conveyor line 1 and the empty pallet conveyor line 5 are arranged vertically, the first palletizing platform 71 and the second palletizing platform 72 are arranged between the empty pallet conveyor line 5 and the finished product conveyor line 8, the empty pallet conveyor line 5 is sequentially provided with a first pallet buffer area 51 and a second pallet buffer area 52 along the conveying direction, the finished product conveyor line 8 is provided with a first finished product buffer area 81 and a second finished product buffer area 82, the first pallet buffer area 51, the first palletizing platform 71, and the first finished product buffer area 81 are sequentially arranged along the conveying direction of the first packaging conveyor line 1, and the first pallet buffer area 51 is isolated from the outlet end of the first packaging conveyor line 1, the second pallet buffer area 52, the second palletizing platform 72, The second finished product buffer area 82 is arranged in sequence along the conveying direction of the second packaging conveyor line 2 and the second pallet buffer area 52 is isolated from the exit end of the second packaging conveyor line 2, the first pallet buffer area 51 is transmission-connected with the first palletizing platform 71 and the first finished product buffer area 81, the second pallet buffer area 52 is transmission-connected with the second palletizing platform 72 and the first finished product buffer area 81, the robot palletizer 6 is erected above the first pallet buffer area 51 and / or the second pallet buffer area 52, illustratively, the robot palletizer 6 is erected above the second pallet buffer area 52, it should be noted here that, since the robot palletizer 6 is erected above the second pallet buffer area 52 (such as erecting the robot palletizer 6 above the second pallet buffer area 52 through a four-legged mounting bracket), there is a certain spatial range between the robot palletizer 6 and the second pallet buffer area 52, so it will not affect the empty pallet 100 entering and exiting the second pallet buffer area 52.

[0039] In this embodiment, the first packaging conveyor line 1 can be used to convey finished product packaging of one specification (such as glass bottle cartons), and the second packaging conveyor line 2 can be used to convey finished product packaging of another specification (such as can cartons). The robot palletizer 6 can use a KR180-2PA Kuka four-axis robot. Of course, other types of robots can also be used as the robot palletizer 6 in this embodiment, as long as they can meet the use requirements, and there is no specific limitation on this; specifically, the working principle of the palletizing system is as follows:

[0040] The forklift transports the empty pallet 100 to the entrance of the empty pallet conveyor line 5, and the empty pallet conveyor line 5 transports the empty pallet 100 placed thereon to the first pallet buffer area 51 and the second pallet buffer area 52 respectively, wherein, when the empty pallet 100 arrives at the first pallet buffer area 51, the empty pallet 100 is transferred from the first pallet buffer area 51 to the first palletizing platform 71, and when the empty pallet 100 arrives at the second pallet buffer area 52, the empty pallet 100 is transferred from the second pallet buffer area 52 to the second palletizing platform 72, and at the same time, the finished product packages of two different specifications from the product production line are transported to the robot clamp grasping position (i.e., one end position of the first packaging conveyor line 1 and the second packaging conveyor line 2 close to the robot palletizer 6) through the first packaging conveyor line 1 and the second packaging conveyor line 2, so as to be clamped and transported by the robot palletizer 6;When the first palletizing platform 71 and the first packaging conveyor line 1 are both ready (i.e., there is an empty pallet 100 on the first palletizing platform 71, and there are finished product packages at one end of the first packaging conveyor line 1 close to the robot palletizer 6), or when the second palletizing platform 72 and the second packaging conveyor line 2 are both ready (i.e., there is an empty pallet 100 on the second palletizing platform 72, and there are finished product packages at one end of the second packaging conveyor line 2 close to the robot palletizer 6), the robot palletizer 6 can start the palletizing operation. For example, at the beginning, the first palletizing platform 71 and the first packaging conveyor line 1 are both ready, and the second If the palletizing platform 72 and the second packaging conveyor line 2 are not ready yet, the robot palletizer 6 can be controlled to first pick up the finished product packages on the first packaging conveyor line 1 and stack them on the first palletizing platform 71. As the palletizing operation proceeds, the number of finished product packages on the first packaging conveyor line 1 will gradually decrease, while the number of finished product packages on the first palletizing platform 71 will gradually increase, and the second palletizing platform 72 and the second packaging conveyor line 2 will also be ready. When the number of finished product packages on the first palletizing platform 71 is stacked to a predetermined number to form a finished product stack, the robot palletizer 6 can be controlled to move the robot arm to the second palletizing platform 71. The finished product packages on the second packaging conveyor line 2 are then clamped onto the second palletizing platform 72 for palletizing. At the same time, the finished product pallet on the first palletizing platform 71 is transferred from the first palletizing platform 71 to the first finished product buffer area 81, and then transported out of the warehouse through the finished product conveyor line 8. At the same time, the empty pallet conveyor line 5 replenishes the empty pallets 100 placed thereon to the first pallet buffer area 51 on the first palletizing platform 71. As time goes by, a finished product pallet is formed on the second palletizing platform 72. The first palletizing platform 71 and the first packaging conveyor line 1 are ready, and the robot palletizer is controlled at this time. 6 moves the robot arm to the first packaging conveyor line 1, and then starts to clamp the finished product packages on the first packaging conveyor line 1 to the first palletizing platform 71 for palletizing. At the same time, the finished product pallets on the second palletizing platform 72 are transferred from the second palletizing platform 72 to the second finished product buffer area 82, and then transported out of the warehouse through the finished product conveyor line 8. At the same time, the empty pallet conveyor line 5 replenishes the empty pallets 100 placed thereon to the second palletizing platform 72 through the second pallet buffer area 52, waiting for the next palletizing operation, and so on. Thus, the palletizing operation of more than two lines can be automatically completed by one robot palletizer 6;In addition, it is worth mentioning that during the process of the robot palletizer 6 performing the palletizing operation on the first palletizing platform 71, when the finished product stack has not yet been formed on the first palletizing platform 71, the second palletizing platform 72 and the second packaging conveyor line 2 may be ready and the number of finished product packages on the second packaging conveyor line 2 is much larger than that on the first packaging conveyor line 1. In this case, the robot palletizer 6 can be controlled to change to the second palletizing platform 72 for palletizing operation. Similarly, during the process of the robot palletizer 6 performing the palletizing operation on the second palletizing platform 72, when the finished product stack has not yet been formed on the second palletizing platform 72, the first palletizing platform 71 and the first packaging conveyor line 1 may be ready and the number of finished product packages on the first packaging conveyor line 1 is much larger than that on the second packaging conveyor line 2. In this case, the robot palletizer 6 can be controlled to change to the first palletizing platform 71 for palletizing operation. In this way, by monitoring the number of finished product packages on different packaging conveyor lines, and then according to the monitoring results, the robot palletizer 6 is controlled to perform the palletizing operation in an alternating manner, which is conducive to further improving the production efficiency of the palletizing system. ;

[0041] In this embodiment, the palletizing system can convey two different specifications of finished product packages through the first packaging conveyor line 1 and the second packaging conveyor line 2 respectively, and at the same time, the empty pallet 100 can be conveyed to the first palletizing platform 71 corresponding to the first packaging conveyor line 1 and the second palletizing platform 72 corresponding to the second packaging conveyor line 2 respectively through the empty pallet conveyor line 5, and then the finished product packages on different packaging conveyor lines are moved to the corresponding palletizing platforms for palletizing by the robot palletizer 6. After the palletizing is completed, the palletized finished product packages can be shipped out of the warehouse through the finished product conveyor line 8, thereby realizing the full automation of the palletizing operation. At the same time, the overall layout of the palletizing system is compact and ingenious. A robot palletizer 6 can be used to palletize at least two packaging conveyor lines at the same time, and an empty pallet conveyor line 5 can be used to provide empty pallets 100 for at least two palletizing platforms respectively. Therefore, it not only improves the production efficiency, but also reduces the high investment cost of the equipment and reduces the floor space of the production line.

[0042] Reference Figure 1 , Figure 2 , Figure 3 and Figure 5In an optional embodiment, the aforementioned palletizing system further includes a first chain transmission mechanism 711 and a second chain transmission mechanism 721, wherein, in the conveying direction of the first packaging conveyor line 1, the first pallet buffer area 51 is simultaneously connected to the first palletizing platform 71 and the first finished product buffer area 81 through the first chain transmission mechanism 711; in the conveying direction of the second packaging conveyor line 2, the second pallet buffer area 52 is simultaneously connected to the second palletizing platform 72 and the second finished product buffer area 82 through the second chain transmission mechanism 721. Exemplarily, the first chain transmission mechanism 711 and the second chain transmission mechanism 721 adopt the same structural form.

[0043] In this embodiment, when the empty pallet conveyor line 5 conveys the empty pallet 100 placed thereon to the first pallet buffer area 51, the empty pallet 100 can be conveyed from the first pallet buffer area 51 to the first stacking platform 71 through the first chain transmission mechanism 711, so that during the stacking operation, the finished packages on the first packaging conveyor line 1 can be stacked on the empty pallet 100 of the first stacking platform 71. In addition, when a finished product stack is formed on the first stacking platform 71, the finished product stack can be conveyed from the first stacking platform 71 to the first finished product buffer area 81 through the first chain transmission mechanism 711 again. At the same time, if an empty pallet 100 is placed on the first pallet buffer area 51, when the finished product stack is conveyed from the first stacking platform 71 to the first finished product buffer area 81 During the process, the empty pallet 100 on the first pallet buffer area 51 will be added to the first stacking platform 71 as the first chain transmission mechanism 711 is driven, waiting for the next stacking operation; the application process of the second chain transmission mechanism 721 on the second stacking platform 72 is the same as the application process of the first chain transmission mechanism 711 on the first stacking platform 71, which can be understood by those skilled in the art and will not be described in detail here; in addition, it should be noted that since the use of chain transmission mechanisms for product transportation is a very mature technology in the field of production line technology, those skilled in the art can know the specific structural composition and specific working principle of the first chain transmission mechanism 711 and the second chain transmission mechanism 721, which will not be described in detail here.

[0044] Reference Figure 1 , Figure 2 and Figure 5In an optional embodiment, the aforementioned palletizing system further includes a third packaging conveyor line 3, a third palletizing platform 73 and a third chain transmission mechanism 731, the third packaging conveyor line 3 is arranged side by side with the first packaging conveyor line 1 and the second packaging conveyor line 2, the third palletizing platform 73 is arranged side by side with the first palletizing platform 71 and the second palletizing platform 72, the empty pallet conveyor line 5 is further provided with a third pallet buffer area 53, the finished product conveyor line 8 is further provided with a third finished product buffer area 83, and the second pallet buffer area 52 is arranged at the first pallet buffer area 5 1 and the third pallet buffer area 53, the third pallet buffer area 53, the third stacking platform 73, and the third finished product buffer area 83 are arranged in sequence along the conveying direction of the third packaging conveyor line 3, and the third pallet buffer area 53 is isolated from the exit end of the third packaging conveyor line 3, and the robot palletizer 6 is erected above the second pallet buffer area 52. In the conveying direction of the third packaging conveyor line 3, the third pallet buffer area 53 is simultaneously connected to the third stacking platform 73 and the third finished product buffer area 83 through the third chain transmission mechanism 731.

[0045] In this embodiment, the palletizing system only needs to use one robot palletizer 6 to perform palletizing operations on three production lines at the same time, further improving the production efficiency and equipment utilization rate. The specific process of using one robot palletizer 6 to perform palletizing operations on three production lines at the same time is similar to the specific process of using one robot palletizer 6 to perform palletizing operations on two production lines at the same time. Therefore, the relevant principle process can refer to the previous description of using one robot palletizer 6 to perform palletizing operations on two production lines at the same time, which will not be repeated here.

[0046] Reference Figure 1 , Figure 2 and Figure 5 In an optional embodiment, a film wrapping machine 9 is also provided on the finished product conveyor line 8, and the third finished product buffer area 83, the second finished product buffer area 82, the first finished product buffer area 81, and the film wrapping machine 9 are arranged in sequence along the conveying direction of the finished product conveyor line 8.

[0047] In this embodiment, the finished product stacks placed in the third finished product buffer area 83, the second finished product buffer area 82 and the first finished product buffer area 81 can be transported to the film wrapping machine 9 through the finished product conveyor line 8 for film wrapping and shipment. Therefore, by arranging the film wrapping machine 9 near the exit of the finished product conveyor line 8 to wrap the finished product stacks, the stability of the finished product stack packaging can be ensured.

[0048] Reference Figure 1 , Figure 2 and Figure 5In an optional embodiment, a pallet stripping machine 50 is provided between the first pallet buffer area 51 and the entrance end of the empty pallet conveyor line 5, and the pallet stripping machine 50 is used to split the whole stack of pallets 10 from the entrance end of the empty pallet conveyor line 5 into single empty pallets 100, wherein the whole stack of pallets 10 is formed by stacking multiple empty pallets 100.

[0049] In the present embodiment, the arrangement of the panel stripping machine 50 enables the forklift to provide empty pallets 100 to the empty pallet conveyor line 5 by transporting the whole stack of pallets 10, thereby avoiding the forklift from forking back and forth a single empty pallet 100, thereby not only improving the transport efficiency of the forklift, but also improving the supply efficiency of the empty pallet conveyor line 5; specifically, the forklift transports the whole stack of pallets 10 to the entrance of the empty pallet conveyor line 5, and when the whole stack of pallets 10 is transported to the workstation where the panel stripping machine 50 is located, the edge stripping machine gradually splits the whole stack of pallets 10 into pieces of empty pallets 100, so that the empty pallet conveyor line 5 can transport the empty pallets 100 piece by piece to the required workstations (such as the first pallet buffer area 51, the first stacking platform 71 and other workstations).

[0050] Reference Figures 1 to 10In an optional embodiment, the panel disassembly machine 50 includes a box body 501 and a motor 504 installed in the box body 501 and arranged in pairs, a transmission mechanism, a cam 508, a bearing (not shown in the figure), a connecting sleeve 509, a pull rod 510, a cross bar 512, a supporting roller seat 513, a guide rail 514, a connecting rod 515, a swing arm 503, a clamping arm 502 and a cylinder 518. The output shaft of the motor 504 is connected to the cam 508 through the transmission mechanism. The connecting sleeve 509 is sleeved on the bearing, and the bearing is fixedly connected to the flange portion of the cam 508 along the axial direction. One end of the pull rod 510 is fixedly connected to the connecting sleeve 509. The support roller seat 513 is arranged in the vertical direction and is respectively fixedly connected to one end of the cross bar 512, fixedly connected to the first end of the connecting rod 515, and slidably matched with the guide rail 514. The first end of the connecting rod 515 is rotatably connected to the first end of the swing arm 503 and slidably connected to the inner wall of the box body 501 in the horizontal direction. The second end of the connecting rod 515 is rotatably connected to the inner wall of the box body 501. The second end of the swing arm 503 is fixedly connected to one end of the clamping arm 502, and the length direction of the clamping arm 502 is parallel to the conveying direction of the empty pallet conveyor line 5. The cylinder 518 is arranged On one side of the swing arm 503 and the piston rod of the cylinder 518 is movably connected to the swing arm 503, wherein the pull rod 510 is arranged in the vertical direction, the guide rail 514 is arranged in the vertical direction, and the wheel center position of the cam 508 is higher than the position of the cross bar 512; illustratively, the transmission mechanism adopts a chain transmission mechanism, which specifically includes a small sprocket 505, a large sprocket 506, a chain (not shown in the figure), a bearing seat 507 and a transmission shaft, the bearing seat 507 is hung on the top of the box body 501, the large sprocket 506, the bearing seat 507 and the cam 508 are sequentially sleeved on the transmission shaft (not shown in the figure) along the axial direction of the transmission shaft, and the small sprocket 505 is sleeved on the output shaft of the motor 504 and is connected to the large sprocket 506 through a chain; illustratively, the bearing is fixedly connected to the flange of the cam 508 in the axial direction by means of a pin shaft + nut, the shape of the connecting sleeve 509 is cam-shaped, the pull rod 510 is in the form of a chain (such as a single-row roller chain), one end of the pull rod 510 can be fixedly connected to the flange of the connecting sleeve 509 by means of a pin shaft, and the other end of the pull rod 510 can be fixedly connected to the cross bar 512 by means of a flat head screw 511, and the support roller seat 513 can be slidably matched with the guide rail 514 through a roller 5131 arranged at the bottom;Exemplarily, the support roller seat 513 and the first end of the connecting rod 515 can be fixedly connected by connecting screws, and a first strip long hole 516 is provided on the inner wall of the box body 501. The first end of the connecting rod 515 and the first end of the swing arm 503 can be installed on the first strip long hole 516 by means of bolts + nuts, so that the first end of the connecting rod 515 and the first end of the swing arm 503 can be rotatably connected and can slide left and right in the horizontal direction. Similarly, a second strip long hole 517 is also provided on the inner wall of the box body 501. The second end of the connecting rod 515 can be installed on the first strip long hole 516 by means of bolts + nuts, so that the second end of the connecting rod 515 can be rotated and slide left and right in the horizontal direction; Exemplarily, a plurality of clamping parts 5021 that can be inserted into the side holes of the empty pallet 100 are provided on the clamping arm 502; In addition, in specific applications, the motor 504 and the cylinder 518 are electrically connected to the production line control system respectively. ;

[0051] In this embodiment, the panel disassembly principle of the panel disassembly machine 50 is as follows:

[0052] At the beginning, the clamping arm 502 is in an open state and at a certain height position. When the whole stack of pallets 10 from the entrance end of the empty pallet conveyor line 5 reaches the position of the clamping arm 502 of the panel dismantling machine 50, the piston rod of the control cylinder 518 is extended, pushing the swing arm 503 to swing, thereby driving the clamping arm 502 to close and clamp on the empty pallet 100 located at the second position at the bottom of the whole stack of pallets 10; when the first pallet buffer area 51, the second pallet buffer area 52, the third pallet buffer area 53, the first When any of the stacking platforms 71 and the second stacking platform 72 lacks an empty pallet 100, the motor 504 is controlled to rotate forward, and then the cam 508 is driven to rotate through the chain transmission mechanism, so that the flange portion of the cam 508 gradually rotates from the lowest point to the highest point. Since the connecting sleeve 509 is sleeved on the bearing and the bearing is fixedly connected to the flange portion of the cam 508 along the axial direction, during the rotation of the cam 508, the bearing will rotate with the rotation of the cam 508, while the connecting sleeve 509 will not rotate with the rotation of the cam 508. The connecting rod 515 is not rotated with the rotation of the cam 508, but rises from the lowest point to the highest point gradually with the rotation of the cam 508, and the flange of the connecting sleeve 509 is always facing downward, and the pull bar 510 will also rise with the rise of the connecting sleeve 509, thereby pulling the supporting roller seat 513 to move upward along the guide rail 514. When the supporting roller seat 513 moves upward, one end of the connecting rod 515 is pushed to move horizontally to the left along the first strip long hole 516, and the other end of the connecting rod 515 is pushed to move horizontally to the right along the second strip long hole 517. The connecting rod 515 moves upward (equivalent to the connecting rod 515 swinging upward, and the inclination angle with the horizontal line becomes larger), and the swing arm 503 and the clamping arm 502 rise as the connecting rod 515 swings upward, thereby gradually separating the second empty pallet 100 at the bottom from the first empty pallet 100 at the bottom, completing the board removal action, and the separated first empty pallet 100 is transported to the required station through the empty pallet conveying line 5, and when the flange portion of the cam 508 rotates from the lowest point to the highest point, the clamping arm 502 also rises to its highest critical position;

[0053] Subsequently, the control motor 504 is reversed to drive the cam 508 to rotate, so that the flange portion of the cam 508 gradually rotates from the highest point to the lowest point. Since the connecting sleeve 509 is sleeved on the bearing and the bearing is fixedly connected to the flange portion of the cam 508 along the axial direction, during the rotation of the cam 508, the bearing will rotate with the rotation of the cam 508, while the connecting sleeve 509 will not rotate with the rotation of the cam 508, but will gradually descend from the highest point to the lowest point with the rotation of the cam 508, and the flange portion of the connecting sleeve 509 is always downward, and the pull bar 510 will also fall with the descent of the connecting sleeve 509, so that the supporting roller seat 513 moves downward along the guide rail 514 under the action of its own gravity. When the supporting roller seat 513 moves downward, it pulls one end of the connecting rod 515 to move horizontally to the right along the first strip-shaped long hole 516. The other end of the connecting rod 515 moves horizontally to the left along the second strip-shaped long hole 517 (equivalent to the connecting rod 515 swinging downward, and the inclination angle with the horizontal line becomes smaller), and the swing arm 503 and the clamping arm 502 descend as the connecting rod 515 swings downward, so that the entire stack of pallets 10 also gradually descends. When the flange portion of the cam 508 rotates from the highest point to the lowest point, the clamping arm 502 also descends to its lowest critical position. At this time, the first empty pallet 100 at the bottom of the current stack of pallets 10 just contacts the roller on the empty pallet conveyor line 5. At this time, the piston rod of the control cylinder 518 is contracted, pulling the swing arm 503 to swing, thereby driving the clamping arm 502 to release the first empty pallet 100 at the bottom, thereby placing the first empty pallet 100 at the bottom of the current stack of pallets 10 on the roller, waiting for the next board removal action.

[0054] In this embodiment, the structure of the panel dismantling machine 50 is cleverly designed. By controlling the rise, fall, release and closing of the clamping arm 502, the panel dismantling machine 50 can gradually split the entire stack of pallets 10 into pieces of empty pallets 100, thereby effectively improving the panel supply efficiency of the empty pallet conveyor line 5.

[0055] Reference Figure 1 , Figure 2 and Figure 5In an optional embodiment, the aforementioned palletizing system also includes a fourth chain transmission mechanism 574 and a manual code scanning conveyor line 4 arranged side by side with the empty pallet conveyor line 5. The inlet end of the manual code scanning conveyor line 4 is provided with a manual code scanning area 41, and an automatic code scanning area 57 is also provided between the first pallet buffer area 51 and the exit of the panel remover 50. The automatic code scanning area 57 is connected to the manual code scanning area 41 through a fourth chain transmission mechanism 574. It should be pointed out here that the fourth chain transmission mechanism 574 is similar to the above-mentioned first, second and third chain transmission mechanisms 731. It is mainly driven by a driving motor to drive a sprocket and other transmission components, thereby driving the chain to rotate. Since the use of a chain transmission mechanism for product transportation is a very mature technology in the field of production line technology, the specific structural composition and specific working principle of the fourth chain transmission mechanism 574 can be known to those skilled in the art and will not be repeated here.

[0056] In this embodiment, in the beer industry, since the finished product stacks are eventually to be placed in a three-dimensional warehouse, and each finished product stack needs to be automatically transported to the corresponding storage location in the three-dimensional warehouse by a machine, a barcode 101 is generally affixed to the four sides of the empty pallet 100, front, back, left, and right, as an identification mark of the empty pallet 100. In this way, when the finished product stacks enter the three-dimensional warehouse, the machine can transport the empty pallet 100 to the corresponding storage location through the barcode 101 on the empty pallet 100. Specifically, when the empty pallet 100 is transported to the automatic code scanning area 57, the automatic code scanning area 57 can be used to scan the empty pallet 100. The automatic barcode scanner automatically scans the barcode 101 on the empty pallet 100 (for example, an automatic barcode scanner is set on the side edge of the automatic barcode scanning area 57, and the automatic barcode scanner at this position is used to scan the barcode 101 on the side of the empty pallet 100). If the automatic barcode scanning is successful, the empty pallet 100 can be transported forward to the required workstation. If the barcode scanning fails, the empty pallet 100 is transferred to the manual barcode scanning area 41 through the fourth chain transmission mechanism 574, and the employee uses a handheld barcode scanner to supplement the barcode 101 on it. After the supplementary scanning is successful, the empty pallet 100 is transported to the required workstation through the control of the fourth chain transmission mechanism 574. The driving motor in the four-chain transmission mechanism 574 is reversed, so that the empty pallet 100 after the manual code scanning is successful is automatically returned to the empty pallet conveyor line 5 to continue to be conveyed forward; in this embodiment, after the empty pallet 100 has been used for a long time, the barcode 101 set thereon may be missing, covered by debris, etc., and the automatic barcode scanner often cannot scan the barcode successfully. In the prior art, when the automatic code scanning of the empty pallet 100 fails, the employee is often required to manually remove the empty pallet 100, so the labor intensity of the employee is large. In this embodiment, by adding a manual code scanning conveyor line 4, The automatic code scanning area 57 on the empty pallet conveyor line 5 is connected to the manual code scanning area 41 on the manual code scanning conveyor line 4 through the fourth chain transmission mechanism 574, so that after the automatic code scanning of the empty pallet 100 fails, it can be automatically transferred to the manual code scanning area 41 for manual re-scanning through the fourth chain transmission mechanism 574, and after the manual re-scanning is successful, it can automatically return to the empty pallet conveyor line 5 to continue forward transportation, thereby effectively solving the problem in the prior art that when the automatic code scanning of the empty pallet 100 fails, the empty pallet 100 needs to be manually rejected, greatly reducing the labor intensity of employees.

[0057] Reference Figure 1 , Figure 2 , Figure 4 and Figure 5In an optional embodiment, the first packaging conveyor line 1 is also provided with a first arranging and sorting mechanism 11, and the first arranging and sorting mechanism 11 includes a first cylinder 110, a first connecting rod 112, a first baffle 113 and a first differential belt 115. The first piston rod 111 of the first cylinder 110 is rotatably connected to one end of the first connecting rod 112, and the other end of the first connecting rod 112 is fixedly connected to the first end of the first baffle 113, and the first end of the first baffle 113 is rotatably connected to the edge of the first packaging conveyor line 1. At the same time, a pulley 114 is also provided on the second end of the first baffle 113. The first differential belt 115 is wound around the roller of the first packaging conveyor line 1 and is arranged between the entrance end of the first packaging conveyor line 1 and the first baffle 113.

[0058] In this embodiment, specifically, finished product packages (such as glass bottle cartons) from the product production line enter from the entrance end of the first packaging conveyor line 1. When the finished product packages reach the area where the first differential belt 115 is located, since the transmission speed of the part of the first differential belt 115 close to the entrance end is slower, and the transmission speed of the part of the belt close to the first baffle 113 is faster, the first differential belt 115 can be used to open the distance between the front and rear finished product packages, and then when the finished product package "walking" in front touches the second baffle in a horizontal state, the first differential belt 115 can be used to open the distance between the front and rear finished product packages. When the first baffle 113 is blocked, the finished product package has enough space to realize a 90° turn and enter the robot clamp grasping position (for example, if the finished product package comes in horizontally, it will enter the robot clamp grasping position in a vertical posture after turning), wherein the pulley 114 on the first baffle 113 can guide the finished product package to realize better turning; and when the number of finished product packages entering from the position of the first baffle 113 reaches a predetermined number, the first piston rod 111 of the first cylinder 110 is controlled to retract, Then the first baffle plate 113 is driven to rotate and retract along the conveying direction, so that the finished product package coming in later maintains its original posture and enters the robot clamp grasping position. When the number of finished product packages entering from the position of the first baffle plate 113 reaches a predetermined number again, the first piston rod 111 of the first cylinder 110 is controlled to extend, thereby driving the first baffle plate 113 to rotate and extend in the opposite direction of the conveying direction, so that the finished product package coming in later realizes a 90° turn and enters the robot clamp grasping position, and this reciprocating process is repeated, so that the subsequent machine The human palletizer 6 clamps the finished product packages on the first packaging conveyor line 1 at different clamping angles and carries out palletizing on the first palletizing platform 71, that is, stacks the finished product packages on the empty pallet 100 in a "horizontal-vertical-horizontal" or "vertical-horizontal-vertical" manner. Compared with the palletizing method of repeatedly stacking at a single angle, by stacking the finished product packages on the empty pallet 100 in turn at staggered angles, the reliability of the palletizing operation can be improved, and the collapse of the stacked finished product packages on the empty pallet 100 can be avoided during the palletizing of the finished product packages.

[0059] Reference Figure 1 , Figure 2 and Figure 5 In an optional embodiment, a second arranging and sorting mechanism 21 is further provided on the second packaging conveyor line 2, and a third arranging and sorting mechanism 31 is further provided on the third packaging conveyor line 3, wherein the arrangement, structural composition and function of the second arranging and sorting mechanism 21 and the third arranging and sorting mechanism 31 are substantially the same as those of the first arranging and sorting mechanism 11, and therefore are not described in detail.

[0060] Reference Figures 1 to 10 The present application also provides a palletizing method, which is applied to the palletizing system in any of the above embodiments, and the method includes:

[0061] S1, detecting whether there are empty pallets 100 on the first palletizing platform 71 and the second palletizing platform 72;

[0062] S2, if there are empty pallets 100 on both the first palletizing platform 71 and the second palletizing platform 72, then according to the predetermined first priority strategy, control the robot palletizer 6 to move the finished product packages on the packaging conveyor line with the highest priority to the first palletizing platform 71 or the second palletizing platform 72 for palletizing, wherein the packaging conveyor line includes the first packaging conveyor line 1 and the second packaging conveyor line 2;

[0063] If there is no empty pallet 100 on either the first palletizing platform 71 or the second palletizing platform 72, then according to the predetermined second priority strategy, the empty pallet conveyor line 5 is controlled to transport the empty pallet 100 placed thereon to the palletizing platform with a higher priority, and when the empty pallet 100 arrives at the palletizing platform with a higher priority, the robot palletizer 6 is controlled to transport the finished product packages on the corresponding packaging conveyor line to the first palletizing platform 71 or the second palletizing platform 72 for palletizing, wherein the palletizing platforms include the first palletizing platform 71 and the second palletizing platform 72;

[0064] If there is an empty pallet 100 on the first palletizing platform 71 and there is no empty pallet 100 on the second palletizing platform 72, the robot palletizer 6 is controlled to move the finished product packages on the first packaging conveyor line 1 to the first palletizing platform 71 for palletizing, and the empty pallet conveyor line 5 is controlled to transport the empty pallet 100 placed thereon to the second palletizing platform 72;

[0065] If there is no empty pallet 100 on the first palletizing platform 71 and there is an empty pallet 100 on the second palletizing platform 72, the robot palletizer 6 is controlled to move the finished product packages on the second packaging conveyor line 2 to the second palletizing platform 72 for palletizing, and the empty pallet conveyor line 5 is controlled to transport the empty pallet 100 placed thereon to the first palletizing platform 71;

[0066] S3, when the finished product packages on the first palletizing platform 71 or the second palletizing platform 72 are palletized to a predetermined number to form a finished product stack, the robot palletizer 6 is controlled to switch to another palletizing platform for palletizing, and the finished product stack is transported to the finished product conveyor line 8 for delivery.

[0067] In the above S1, in some specific embodiments, photoelectric sensors can be set on the first stacking platform 71 and the second stacking platform 72 to detect whether there are empty pallets 100 on the first stacking platform 71 and the second stacking platform 72. Of course, other types of sensors or sensor combinations can also be used to achieve this, as long as the use requirements can be met, and there is no specific limitation on this.

[0068] In the above S2, in some specific embodiments, the predetermined first priority strategy can be pre-set by the user in the production line control system. For example, it is pre-set in the production line control system that when there are empty pallets 100 on both the first palletizing platform 71 and the second palletizing platform 72, the priority of the first packaging conveyor line 1 is higher than the priority of the second packaging conveyor line 2 (that is, the first packaging conveyor line 1 is preferentially selected for palletizing operation); in other specific embodiments, the predetermined first priority strategy can also be based on the storage quantity of finished product packages on the packaging conveyor line. For example, counting sensors can be set on the first packaging conveyor line 1 and the second packaging conveyor line 2 to The storage quantity of finished product packages on the first packaging conveyor line 1 and the second packaging conveyor line 2 is monitored, and then when there are empty pallets 100 on the first stacking platform 71 and the second stacking platform 72, the packaging conveyor line with a larger storage quantity is preferentially selected for palletizing operation. If it is monitored that the storage quantity of finished product packages on the first packaging conveyor line 1 is more than that on the second packaging conveyor line 2 (or a certain quantity value more), the first packaging conveyor line 1 can be preferentially selected for palletizing operation; and the predetermined second priority strategy can adopt the same strategy as the first priority strategy, which will not be repeated here. In actual application, these two priority strategies can be flexibly used according to actual production needs.

[0069] In the above S3, whether the finished product packages on the first palletizing platform 71 or the second palletizing platform 72 have been palletized to a predetermined number can be determined according to the number of times the robot palletizer 6 performs palletizing back and forth. When the number of times the robot palletizer 6 performs palletizing back and forth reaches a predetermined number, it can be determined that the finished product packages on the first palletizing platform 71 or the second palletizing platform 72 have been palletized to a predetermined number. For different palletizing platforms, the corresponding predetermined number can be the same or different. In actual application, it can be flexibly set according to actual production conditions.

[0070] Reference Figure 1 and Figure 2More specifically, the empty pallet conveyor line 5 is provided with an entrance area 54, a pallet removal area 55, a transition area 56, an automatic code scanning area 57, a first stack buffer plate area 51, a second pallet buffer area 52 and a third pallet buffer area 53 in sequence along the conveying direction, and the manual code scanning conveyor line 4 is provided with a manual code scanning area 41 and an actual code scanning area 42, wherein the pallet removal machine 50 is arranged on the pallet removal area 55, and the rollers on the transition area 56, the automatic code scanning area 57, the first stack buffer plate area 51, the second pallet buffer area 52 and the third pallet buffer area 53 can all be rolled along the conveying direction by one or more independent motors arranged at the bottom of the transition area 56, refer to Figures 1 to 8 In some more specific embodiments, the specific working process of the palletizing system is as follows:

[0071] On the one hand, the forklift transports the whole stack of pallets 10 to the entrance area 54 one by one. When the photoelectric sensor arranged in the panel removal area 55 detects that there is no empty pallet 100 in the panel removal area 55, one or more independent drive motors arranged at the bottom of the entrance area 54 are controlled to drive the rollers on the entrance area 54 to roll forward, thereby transporting the whole stack of pallets 10 to the panel removal area 55. When the position sensor arranged in the panel removal area 55 detects that the whole stack of pallets 10 has reached the position of the clamping arm 502 of the panel removal machine 50, the rollers on the entrance area 54 are controlled to stop rolling, and the panel removal machine 50 is controlled to move at the same time, so that the clamping arm 502 is clamped in the whole stack of pallets 10 at the bottom When the photoelectric sensor arranged on the corresponding workstation in the front detects that any of the first pallet buffer area 51, the second pallet buffer area 52, the third pallet buffer area 53, the first stacking platform 71 and the second stacking platform 72 lacks an empty pallet 100, the clamping arm 502 of the panel dismantling machine 50 is controlled to be lifted upward, so that the second empty pallet 100 at the bottom is gradually separated from the first empty pallet 100 at the bottom. When the clamping arm 502 is lifted upward to its highest critical position, one or more independent motors arranged at the bottom of the panel dismantling area 55 are controlled to drive the rollers on the panel dismantling area 55 to roll forward, thereby separating the separated empty pallets 100. The first empty pallet 100 is transported to the transition zone 56, and when the position sensor arranged on the transition zone 56 detects that the first empty pallet 100 has completely reached the transition zone 56, one or more independent drive motors arranged at the bottom of the transition zone 56 are controlled to drive the rollers thereon to roll forward, and at the same time, the rollers on the panel stripping zone 55 are controlled to stop rolling and the clamping arm 502 of the panel stripping machine 50 is controlled to move downward. When the clamping arm 502 drops to its lowest critical position (at this time, the empty pallet 100 clamped by the clamping arm 502 just contacts with the rollers on the panel stripping zone 55), the clamping arm 502 releases the empty pallet 100 currently clamped and clamps The roller 100 is held on the second empty pallet 100 at the bottom in the current stack of pallets 10, so that the first empty pallet 100 at the bottom in the current stack of pallets 10 is placed on the roller, waiting for the next unloading; and when the position sensor arranged on the automatic code scanning area 57 detects that the original first empty pallet 100 has arrived at the automatic code scanning area 57, the roller arranged thereon is controlled to stop rolling, and the automatic code scanning machine arranged on the automatic code scanning area 57 is controlled to scan the empty pallet 100. If the scanning is successful, the roller on the automatic code scanning area 57 is controlled to roll forward, so that the empty pallet 100 is transported to the required work station;If the code scanning fails, the drive motor in the fourth chain transmission mechanism 574 is controlled to rotate forward to transfer the empty pallet 100 from the automatic code scanning area 57 to the manual code scanning area 41. It should be pointed out here that for safety reasons, a barrier or other facilities are generally provided between the manual code scanning area 41 and the actual code scanning area 42 for isolation. Therefore, when the position sensor provided on the manual code scanning area 41 detects that the empty pallet 100 has arrived at the manual code scanning area 41, the fourth chain transmission mechanism 574 is controlled to stop transmission, and then the position sensor provided on the manual code scanning area 41 is controlled to stop transmission. One or more independent drive motors at the bottom of the manual code scanning conveyor line 4 rotate forward to convey the empty pallet 100 from the manual code scanning area 41 to the actual code scanning area 42. When the position sensor set on the actual code scanning area 42 detects that the empty pallet 100 arrives at the actual code scanning area 42, the employee can use a handheld barcode scanner to perform a supplementary scan on the barcode 101 on the empty pallet 100. After the supplementary scan is successful, the barcode scanner sends a signal of successful supplementary scan to the production line control system, thereby controlling the one or more independent drive motors set at the bottom of the manual code scanning conveyor line 4. The motor is reversed to return the empty pallet 100 from the actual code scanning area 42 to the manual code scanning area 41. When the empty pallet 100 after the supplementary scanning successfully reaches the manual code scanning area 41, the roller on the manual code scanning conveyor line 4 is controlled to stop rolling, and then the drive motor in the fourth chain transmission mechanism 574 is controlled to reverse to return the empty pallet 100 from the manual code scanning area 41 to the automatic code scanning area 57. When the empty pallet 100 after the supplementary scanning successfully reaches the automatic code scanning area 57, the fourth chain transmission mechanism 574 is controlled to stop transmission, and then the automatic The roller on the code scanning area 57 rolls forward, thereby conveying the empty pallet 100 to the required workstation. In this way, after the above process, each empty pallet 100 can be conveyed to the required workstation in an orderly manner through the empty pallet conveyor line 5. It should be noted here that when the empty pallet 100 after successful supplementary scanning returns to the automatic code scanning area 57, since the production line control system has received the signal of successful supplementary scanning before, the automatic code scanning machine set on the automatic code scanning area 57 will no longer scan the empty pallet 100 after successful supplementary scanning;

[0072] On the other hand, finished product packages of three different specifications from the product production line are transported to the robot clamp grasping position (i.e., one end position of the first packaging conveyor line 1, the second packaging conveyor line 2, and the third packaging conveyor line 3 close to the robot palletizer 6, at which a baffle is provided to prevent the finished product packages from continuing to be conveyed forward) through the first packaging conveyor line 1, the second packaging conveyor line 2, and the third packaging conveyor line 3, so as to be grasped and transported by the robot palletizer 6; assuming that at the beginning, the robot palletizer 6 is performing palletizing operations on the first palletizing platform 71, when analyzing the monitoring results of the counting sensors arranged on the first, second, and third packaging conveyor lines 3, it is known that the number of finished product packages on the second packaging conveyor line 2 is the largest, and is a certain number more than the number of finished product packages on the packaging conveyor line currently performing palletizing operations (this time the first packaging conveyor line 1), and the extra number reaches a predetermined number value (i.e., the current number of finished product packages When the difference in the storage volume of finished packages between the packaging conveyor line with the largest volume and the packaging conveyor line currently performing palletizing operation reaches a predetermined value), then under the premise that there is an empty pallet 100 on the current second palletizing platform 72, the robot arm of the robot palletizer 6 is controlled to rotate to the robot clamp gripping position on the second packaging conveyor line 2, and according to the telescopic state of the first piston rod 111 in the second arranging and sorting mechanism 21 (when the cylinder retracts the first piston rod 111, the corresponding state signal will be sent to the robot palletizer 6 or the production line control system), the clamp of the robot palletizer 6 is rotated to a predetermined angle adapted to the placement posture of the finished package, and then the finished package on the gripping position of the robot clamp is gripped and taken to the second palletizing platform 72 for palletizing operation. In this way, the storage quantity of the finished packages on each packaging conveyor line is monitored in real time by the counting sensor, and each monitoring result is analyzed, so that the robot palletizer 6 can be controlled to perform palletizing operations on more than one line at the same time;Assuming that during the palletizing operation of the robot palletizer 6, the first palletizing platform 71 forms a finished product pallet first, the robot palletizer 6 is controlled to switch to the production line with the highest priority among the other two production lines for palletizing, and the first chain transmission mechanism 711 is controlled to transmit, so as to transfer the finished product pallet on the first palletizing platform 71 from the first palletizing platform 71 to the first finished product buffer area 81, and then the finished product pallet is transported to the workstation of the film wrapping machine 9 through the finished product conveyor line 8 for film wrapping and out of the warehouse. In the process of transporting the finished product pallet from the first palletizing platform 71 to the first finished product buffer area 81, if there is an empty pallet 100 stored on the first pallet buffer area 51, the empty pallet 100 on the first pallet buffer area 51 will be moved along by the first chain transmission mechanism 711. The empty pallets 100 are replenished to the first palletizing platform 71 through the transmission of the transmission mechanism 711, waiting for the next palletizing operation. If there is no empty pallet 100 stored on the first pallet buffer area 51, a single empty pallet 100 is removed by the panel dismantling machine 50, and the empty pallet 100 is conveyed to the first pallet buffer area 51 through the empty pallet conveyor line 5. When the position sensor arranged on the first pallet buffer area 51 detects that the empty pallet 100 arrives at the first pallet buffer area 51, one or more independent drive motors arranged at the bottom of the transition area 56 are controlled to stop working to control the rollers on the first pallet buffer area 51 to stop rolling, and then the first chain transmission mechanism 711 is controlled to transmit, so that the empty pallet 100 is replenished to the first palletizing platform 71.

[0073] Thus, through the above process, full automation of the palletizing operation is achieved. At the same time, the palletizing system only needs one robot palletizer 6 to perform palletizing operations on more than two lines at the same time, thereby not only improving production efficiency but also reducing the investment cost of the equipment and the floor space of the production line.

[0074] The above description is only a preferred embodiment of the present application and does not constitute any form of limitation to the present application. Therefore, any modification, equivalent changes and modifications made to the above embodiments based on the technical essence of the present application without departing from the content of the technical solution of the present application are still within the scope of the technical solution of the present application.

Claims

1. A palletizing system, It is characterized in that The invention comprises a first packaging conveyor line and a second packaging conveyor line arranged side by side, an empty pallet conveyor line and a finished product conveyor line arranged side by side, a first palletizing platform and a second palletizing platform arranged side by side, and a robot palletizer, wherein the first packaging conveyor line is arranged vertically to the empty pallet conveyor line, the first palletizing platform and the second palletizing platform are arranged between the empty pallet conveyor line and the finished product conveyor line, the empty pallet conveyor line is provided with a first pallet buffer area and a second pallet buffer area in sequence along the conveying direction, the finished product conveyor line is provided with a first finished product buffer area and a second finished product buffer area, the first pallet buffer area, the first pallet stacking platform, the first finished product buffer area The first pallet buffer area is sequentially arranged along the conveying direction of the first packaging conveyor line, and the first pallet buffer area is isolated from the exit end of the first packaging conveyor line; the second pallet buffer area, the second stacking platform, and the second finished product buffer area are sequentially arranged along the conveying direction of the second packaging conveyor line, and the second pallet buffer area is isolated from the exit end of the second packaging conveyor line; the first pallet buffer area is transmission-connected with the first stacking platform and the first finished product buffer area; the second pallet buffer area is transmission-connected with the second stacking platform and the first finished product buffer area; and the robot palletizer is erected above the first pallet buffer area and / or the second pallet buffer area; A pallet splitter is provided between the first pallet buffer area and the inlet end of the empty pallet conveyor line, and the pallet splitter is used to split a whole stack of pallets from the inlet end of the empty pallet conveyor line into single empty pallets, wherein the whole stack of pallets is formed by stacking a plurality of the empty pallets; The panel disassembly machine includes a box body and a motor, a transmission mechanism, a cam, a bearing, a connecting sleeve, a pull rod, a cross bar, a support roller seat, a guide rail, a connecting rod, a swing arm, a clamping arm and a cylinder installed in the box body and arranged in pairs. The output shaft of the motor is connected to the cam through the transmission mechanism. The connecting sleeve is sleeved on the bearing, and the bearing is fixedly connected to the flange portion of the cam in the axial direction. One end of the pull rod is fixedly connected to the connecting sleeve, and the other end is fixedly connected to the cross bar; the support roller seat is arranged in the vertical direction and is respectively fixedly connected to one end of the cross bar and the first end of the connecting rod. The first end of the connecting rod is rotatably connected to the first end of the swing arm and is slidably connected to the inner wall of the box body in the horizontal direction. The second end of the connecting rod is movably connected to the inner wall of the box body. The second end of the swing arm is fixedly connected to one end of the clamping arm, and the length direction of the clamping arm is parallel to the conveying direction of the empty pallet conveyor line. The cylinder is arranged on one side of the swing arm and the piston rod of the cylinder is movably connected to the swing arm, wherein the pull bar is arranged in the vertical direction, the guide rail is arranged in the vertical direction, and the wheel center position of the cam is higher than the position of the cross bar. The palletizing system realizes palletizing by a palletizing method, and the palletizing method comprises: detecting whether there are empty pallets on the first palletizing platform and the second palletizing platform; If there are empty pallets on both the first palletizing platform and the second palletizing platform, the robot palletizer is controlled to move the finished product packages on the packaging conveyor line with the highest priority to the first palletizing platform or the second palletizing platform for palletizing according to the predetermined first priority strategy, wherein the packaging conveyor line includes the first packaging conveyor line and the second packaging conveyor line; If there are no empty pallets on either the first palletizing platform or the second palletizing platform, then according to a predetermined second priority strategy, the empty pallet conveyor line is controlled to transport the empty pallet placed thereon to a palletizing platform with a higher priority, and when the empty pallet arrives at the palletizing platform with a higher priority, the robot palletizer is controlled to transport the corresponding finished product packages on the packaging conveyor line to the first palletizing platform or the second palletizing platform for palletizing, wherein the palletizing platforms include the first palletizing platform and the second palletizing platform; If there is an empty pallet on the first palletizing platform and there is no empty pallet on the second palletizing platform, control the robot palletizer to move the finished product packages on the first packaging conveyor line to the first palletizing platform for palletizing, and control the empty pallet conveyor line to transport the empty pallet placed thereon to the second palletizing platform; If there is no empty pallet on the first palletizing platform and there is an empty pallet on the second palletizing platform, control the robot palletizer to move the finished product packages on the second packaging conveyor line to the second palletizing platform for palletizing, and control the empty pallet conveyor line to transport the empty pallet placed thereon to the first palletizing platform; When the finished product packages on the first palletizing platform or the second palletizing platform are palletized to a predetermined number to form a finished product pallet, the robot palletizer is controlled to switch to the other palletizing platform for palletizing, and the finished product pallet is transported to the finished product conveyor line for delivery.

2. The palletizing system according to claim 1, It is characterized in that It also includes a first chain transmission mechanism. In the conveying direction of the first packaging conveyor line, the first pallet buffer area is simultaneously connected to the first palletizing platform and the first finished product buffer area through the first chain transmission mechanism.

3. The palletizing system according to claim 1, It is characterized in that It also includes a second chain transmission mechanism. In the conveying direction of the second packaging conveyor line, the second pallet buffer area is simultaneously connected to the second palletizing platform and the second finished product buffer area through the second chain transmission mechanism.

4. The palletizing system according to claim 1, It is characterized in that It also includes a third packaging conveyor line, a third palletizing platform and a third chain transmission mechanism, the third packaging conveyor line is arranged side by side with the first packaging conveyor line and the second packaging conveyor line, the third palletizing platform is arranged side by side with the first palletizing platform and the second palletizing platform, the empty pallet conveyor line is also provided with a third pallet buffer area, the finished product conveyor line is also provided with a third finished product buffer area, the second pallet buffer area is arranged between the first pallet buffer area and the third pallet buffer area, the third pallet buffer area, the third pallet stacking platform and the third finished product buffer area are arranged in sequence along the conveying direction of the third packaging conveyor line, and the third pallet buffer area is isolated from the exit end of the third packaging conveyor line, the robot palletizer is erected above the second pallet buffer area, and in the conveying direction of the third packaging conveyor line, the third pallet buffer area is simultaneously connected to the third palletizing platform and the third finished product buffer area through the third chain transmission mechanism.

5. The palletizing system according to claim 1, It is characterized in that The finished product conveying line is also provided with a film wrapping machine, and the second finished product buffer area, the first finished product buffer area, and the film wrapping machine are arranged in sequence along the conveying direction of the finished product conveying line.

6. The palletizing system according to claim 1, It is characterized in that It also includes a fourth chain transmission mechanism and a manual code scanning conveyor line arranged side by side with the empty pallet conveyor line. A manual code scanning area is provided at the inlet end of the manual code scanning conveyor line. An automatic code scanning area is also provided between the first pallet buffer area and the exit of the pallet dismantling machine. The automatic code scanning area is connected to the manual code scanning area through the fourth chain transmission mechanism.

7. The palletizing system according to any one of claims 1 to 5, It is characterized in that The first packaging conveyor line is also provided with a first arranging and arranging mechanism, which includes a first cylinder, a first connecting rod, a first baffle and a first differential belt. The first piston rod of the first cylinder is rotatably connected to one end of the first connecting rod, the other end of the first connecting rod is fixedly connected to the first end of the first baffle, and the first end of the first baffle is rotatably connected to the edge of the first packaging conveyor line. The first differential belt is wound around the roller of the first packaging conveyor line and is arranged between the entrance end of the first packaging conveyor line and the first baffle.