Method for plausibility checking of a measured variable of a sensor in a motor vehicle
By using electronic load distribution devices and cable bundle models for credibility checks in the vehicle power grid, the problem of insufficient reliability and diagnostic coverage caused by sensor failures in the vehicle power grid is solved, enabling more advanced signal identification and autonomous driving environments. safety guarantee.
Patent Information
- Application Number
- CN201910676251.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2018-07-25
- Filing Date
- 2019-07-25
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2039-07-25
AI Technical Summary
Existing technologies are difficult to effectively improve system reliability and fault diagnosis coverage in vehicle power grids, especially when sensor failures may lead to functional failure and affect the safety of autonomous driving.
The electronic load distribution device provides independent measurement parameters for credibility check. Combined with current and voltage measurement sensors, the cable bundle model is used to back-calculate the characteristic parameters of the energy storage to ensure the integrity and availability of the signal, and automatically take action in the event of sensor failure. measures to ensure the effectiveness of system functions.
It improves the signal diagnosis coverage and availability of the system, reduces the failure rate, and ensures safety and functional integrity in the autonomous driving environment. In particular, when a sensor fails, measures can be taken quickly to prevent functional failure.
Smart Images

Figure CN110780218B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for plausibility checking of a measured variable of a sensor in a motor vehicle according to the type specified in the independent claim. Background Art
[0002] A method and a device for battery state recognition are known from EP 1 271 170 B1. Conclusions about the battery state are obtained with the aid of a first battery state recognition system, wherein in the event of a faulty operation or failure of the first battery state recognition system, conclusions about the battery state are obtained with the aid of a second battery state recognition system, wherein the first battery state recognition system determines conclusions about the battery state using a current measuring device and additionally using a temperature measuring device.
[0003] The vehicle onboard power system has the following tasks: supply energy to electrical consumers. If the energy supply in today's vehicles fails due to a fault or aging in the onboard power system or onboard power system components, important functions such as servo steering will fail. Since the steering ability of the vehicle is not impaired, but only becomes difficult to move, the failure of the onboard power system is usually accepted in today's mass-produced vehicles because the driver can provide a fallback level. In order to increase availability, a dual-channel onboard power system structure has been proposed, for example, in WO 2015 / 135729 A1. The onboard power system structure is required to allow for fault-tolerant power supply to systems for highly automated or fully automated driving operations. Summary of the invention
[0004] The present invention is based on the object of further improving the reliability of the entire system. This object is achieved by the features according to the invention.
[0005] By carrying out a plausibility check on the measured variables detected by the sensor with a further independent measured variable provided by the electronic load distribution device, the measurement signal of the sensor can be checked and the diagnostic coverage or availability of the signal can thus be increased without incurring additional costs. The electronic load distribution device contains current and voltage measuring sensors that can also be used for plausibility checks to describe other safety and diagnostic functions of the electronic load distribution device. In particular, a higher level of qualification of the provided signals can thus be achieved according to higher standards (e.g., ASIL decomposition according to ISO 26262 C - e.g.: ASIL sensor: B, ASIL load distribution device: A-> combined ASIL: C).
[0006] In a suitable development, the ascertained characteristic variable of the energy store is determined from the measured variable of the load sharing device using a cable harness model. It can therefore be inferred that in the case of a back calculation from the cable harness model, an ascertained characteristic variable approximately corresponds to the measured variable of the energy store. This makes it possible to implement a plausibility check in a simple manner to increase the integrity of the measured variable.
[0007] In a suitable development, the plausibility check device forwards the determined characteristic variable of the energy store or the measured variable, in particular to a state recognition device of the energy store and / or to an evaluation device, based on a comparison of the determined characteristic variable of the energy store with the measured variable of the energy store. As a result, only plausible variables are further processed, thereby reducing the susceptibility to failure of the entire system. Furthermore, the functional availability of the entire system can be ensured even in the event of a sensor failure.
[0008] It is particularly expedient to forward the ascertained characteristic variable in the event of a significant deviation between the ascertained characteristic variable of the energy store and a measured variable of the energy store. In the event of a significant deviation, the sensor may be defective, so that the characteristic variable ascertained by calculation can be used.
[0009] In one expedient development, the measured variable of the energy store is supplied to a state recognition device of the energy store in order to ascertain a derived characteristic variable, wherein the measured variable and / or the derived characteristic variable is supplied to an evaluation device. Thus, further conclusions about the state of the energy store, such as the charge state or the internal resistance, which are required for further functions, can also be ascertained.
[0010] In a purposeful expansion, the output signal of the plausibility check device - the measured variable or the determined characteristic variable of the energy storage - is supplied to another state recognition device of the energy storage device in order to determine the derived characteristic variable of the energy storage device. It is particularly purposeful to supply the measured variable of the energy storage device and / or the derived characteristic variable and / or the determined characteristic variable to the analysis device. Thus, even when the other state recognition device is not fed with the correct measured value, it is possible to redundantly determine the other characteristic variables of the energy storage device. Subsequently, the corresponding processing of the dispersed (ause inander fallend) sensor signals can be combined in the correct manner and method. This increases the accuracy and availability of the entire system.
[0011] In a suitable development, a fault message is generated in the event of a significant deviation between the ascertained characteristic variable and the measured variable of the energy storage device. It is particularly suitable that the automated driving function, in particular the transfer of the vehicle to a safe state or the activation of the automated driving function, is affected in the event of a fault message. Thus, in the event of a sensor fault, countermeasures can be taken quickly, thereby further increasing safety, in particular in the event of an autonomous driving operation.
[0012] In a suitable development, measured values at a separation element, in particular at a DC voltage converter, are used to determine the ascertained characteristic variable. In particular, in an onboard power supply architecture characterized by reliable power supply of safety-related loads, a plurality of onboard power supply sub-branches are provided, which in turn must be separated from one another in the event of a fault in order to prevent the fault from propagating to the still functional onboard power supply branches. Such separation elements, for example DC voltage converters, provide suitable measured variables, such as currents and voltages, which can be used particularly easily for plausibility checks.
[0013] In one expedient embodiment, the contact resistances between the energy store and the load distribution device and / or ground are used to determine the ascertained characteristic variable. These contact resistances are part of the cable harness model and are suitable for the precise determination of the ascertained characteristic variable.
[0014] In one expedient embodiment, the sum of the current at the isolating element, in particular the DC voltage converter, and the current at the load distribution device is used to determine the ascertained characteristic variable. The expected battery current can thus be determined particularly easily as the ascertained characteristic variable.
[0015] Further expedient embodiments result from the further embodiments and from the description. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 A block diagram for processing and determining desired characteristic variables is shown;
[0017] Figure 2 shows an overview of the components used; and
[0018] Figure 3 Shown is a cable harness model used for plausibility checking. DETAILED DESCRIPTION
[0019] The present invention is schematically described based on embodiments in the drawings and will be described in detail below with reference to the drawings.
[0020] In this exemplary embodiment, batteries or accumulators are described as possible energy storage devices by way of example. However, other energy storage devices suitable for this task, such as inductive or capacitive energy storage devices, fuel cells, capacitors, etc., can also be used as an alternative.
[0021] The sensor 34, in particular the battery sensor, detects the voltage Ubatt on the energy storage device 32 and / or the current Ibatt of the energy storage device 32. The measured variables (Ubatt, Ibatt) are forwarded to the state recognition device 13, in particular the battery state recognition device 13. Using the supplied measured variables (Ubatt, Ibatt) and the stored model of the energy storage device 32, important relevant determined characteristic variables of the energy storage device 32, such as the internal resistance Ri (in particular the battery internal resistance), the state of charge (SOC) and, if necessary, further variables, are determined. The output variables of the state recognition device 13 (for example, the internal resistance Ri, the battery voltage Ubatt, the battery current Ibatt and the state of charge SOC) are supplied to the analysis device 21, in particular the so-called fusion (which combines a plurality of supplied variables according to a certain criterion).
[0022] A load distribution device 52 and a current distributor are provided for controlling and / or protecting various electrical loads. The load distribution device 52 is supplied with power from the energy storage device 32. The load distribution device 52 detects typical load parameters that are also available, such as Figure 3 The corresponding load current Ilv or voltage Ulv can be further seen. The corresponding typical load parameters (especially the load current) of the electrical consumers connected to the load distribution device 52 are always available in the load distribution device 52 through corresponding measuring devices, because the load distribution device 52 usually ensures reliable protection of the electrical consumers according to the load state, so as to protect the electrical consumers, for example, from overcurrent. For this purpose, corresponding switching devices, especially electronic semiconductor switches, which are disconnected in the case of overload are provided in the load distribution device 52. Therefore, the measured parameters Ilvo, Ulvo of the load distribution device 52 are available.
[0023] The measured variables (Ulvo, Ilvo) of the load distribution device 52 are available to the plausibility check device 11. In addition, typical measured variables (e.g., current Idc, voltage Udc) of the separation element 26, such as a DC voltage converter, arrive at the plausibility check device 11. In particular, in order to reliably supply power to the onboard power supply of the motor vehicle, in particular, to supply power to the functions required for autonomous driving operation (especially steering, braking, surrounding environment sensing, trajectory planning, etc.), a plurality of partial onboard power supplies can be provided, which can be separated from each other by the separation element 26 in the event of a fault. This can be achieved, for example, by a DC voltage converter, as shown by way of example. These partial onboard power supplies are supplied to components that are redundantly designed in terms of functional technology, and the components can redundantly implement the functions mentioned by way of example. In the event of a partial onboard power supply failure, for example, the safe parking of the vehicle (driving to the nearest parking lot, immediately stopping on the shoulder of the road, etc.) can be performed by means of components of other partial onboard power supplies that are still working without fault.
[0024] The measured variables Ubatt, Ibatt determined by the sensor 34 are also supplied to the plausibility check device 11. The plausibility check device 11 comprises a comparison device 15 and a selection device 17, which only forwards the plausible measured variables of the energy storage device 32. Therefore, the plausibility check device 11 only forwards the plausible measured variables Ubatt, Ibatt, otherwise forwards the determined characteristic variable Ubatt * Ibatt * Plausible measured variables Ubatt, Ibatt or ascertained characteristic variable Ubatt of the energy storage device 32 * Ibatt * (In the event of a fault in the sensor 34) the further state recognition device 19, in particular the battery device recognition device, is reached. The further state recognition device 19 also determines so-called derived characteristic variables of the energy storage device 32, such as the internal resistance Ri or the state of charge SOC. This is again achieved using a suitable model of the energy storage device 32. The characteristic variables derived by the further state recognition device 19 or the ascertained measured variables Ubatt, Ibatt or the ascertained measured variable Ubatt of the energy storage device 32 * Ibatt * The same also reaches the evaluation device 21 .
[0025] The analysis device 21 determines (and / or forwards) credible measured variables (battery voltage Ubatt, battery current Ibatt) or credible derived characteristic variables (Ri, SOC) of the energy storage device 33 from the variables transmitted by the state recognition device 13 and the further state recognition device 19. If a significant deviation occurs between the value transmitted by the state determination device 13 and the variable determined by the further state determination device 19, a fault may exist. This possible fault situation is transferred from the analysis device 21 to a superior control device, for example, via an output signal S (safe state). The superior control device may be, for example, a control device responsible for autonomous driving operation. The superior control device is notified of the possible fault situation, and then appropriate measures are taken, such as emergency parking of the vehicle.
[0026] according to Figure 2 A part of the underlying topology of the onboard power supply system is shown. A grounded DC voltage converter 26 is connected as a possible coupling device (possibly by means of another part of the onboard power supply system not shown) to an energy storage device 32, which in turn supplies energy to a load distribution device 52. In addition, a cable harness diagnostic device 23 is provided, which can provide characteristic variables of the energy storage device 32, which are determined based on the cable harness model 25 from the input variables (voltage Udc at the DC voltage converter, current Idc at the DC voltage converter, voltage Ulv at the load distribution device 52, current Ilv at the load distribution device), namely the battery voltage Ubatt based on the cable harness model 25 * and the battery current Ibatt based on the cable bundle model 25 * The characteristic parameter Ubatt obtained * Ibatt * arrives at the comparison device 15. The comparison device 15 also receives the measured variables of the energy store 32 detected by the sensor 34, namely the battery voltage Ubatt and the battery current Ibatt.
[0027] exist Figure 32 shows a cable harness model 25 based on a typical onboard power subsystem. For example, two such onboard power subsystems can be provided in a vehicle for redundantly supplying safety-related, functionally redundant loads 36, 46. In this case, a further energy storage device 42 can be provided in the other onboard power subsystem, which has a further sensor 44 for detecting a characteristic variable of the further energy storage device 42. A partial onboard power system with relevant onboard power system components is provided, which consists of a DC voltage converter (isolating element 26, 28), an energy storage device 32, 42 with sensors 34, 44, a cable harness branch with corresponding line and contact resistances 51 (resistances on the positive side (index 1) Rx1: R11, R21, R31) and 55 (resistances on the ground side (index 2) Rx2: R12, R22, R32) and a variety of safety-related important electrical consumers 36, 46, characterized by the associated load currents Iv1, Iv2, Iv3 and terminal voltages Uv1, Uv2, Uv3 of three electrical consumers 36, 46 as an example. The electrical consumers 36, 46 are controlled by a load distribution device 52. Optionally, two or more load distribution devices 52 can also be provided. This structure forms the basis of the cable harness model 25. The cable harness resistances (line and contact resistances 51, 55) are determined or estimated in a suitable manner.
[0028] In a first step, the measured variables Ubatt and Ibatt from the sensor 36 , the voltage Udc and the current Idc from the DC / DC converter or the isolating element 26 , and the measured variables Ulvo and Ilvo from the load sharing device 52 are received.
[0029] Directly through the relationship Ibatt * =Ilv-Idc performs a credibility check on the current Ibatt. To this end, evaluate Ibatt and Ibatt * The difference between the two values is detected and a fault flag is generated if a maximum difference or a limit value is exceeded.
[0030] By RelationshipUbatt * =Ulv+Ibatt * (Rbl+Rb2) performs a plausibility check on the voltage Ubatt, wherein (Rbl+Rb2) is either assumed to be a constant in the simplest case or can be determined by a method not described in detail.
[0031] If the measured variable Ibatt / Ubatt is plausible, it is forwarded directly. In the case of a plausibility check, the value of Ubatt or Ibatt is calculated in the load distribution device 52 by the value Ubatt *and Ibatt * In addition, an error message is provided, which is used in a higher-level energy management device to initiate emergency measures. The described block is shown as a selection device 17 in the plausibility check device 11 .
[0032] Subsequent functions calculate redundant signals of battery state recognition device 13 , 19 from the measured values that have been checked for plausibility and thus certified according to a certain standard, such as ASIL C. The redundant signals are linked to the original signals from sensor 34 or battery sensor in a fusion in a higher-level energy management device or higher-level evaluation device 21 or both.
[0033] By means of a plausibility check based on independent measuring points, which are available as measured variables for the load distribution device 52, the measured variables Ubatt, Ibatt of the sensor 34 can be checked and thus the diagnostic coverage or availability of the signal can be increased without incurring additional costs. Thus, a higher level of identification of the integrity level of the signal (ASIL according to ISO 26262) is possible than would be possible by measuring without plausibility checking.
[0034] In general, further voltage values and / or current values of components additionally connected to the energy storage device 32 can be used to determine the ascertained characteristic variable Ubatt * Ibatt * As described, this may be a separation element 26 , a further load distribution device(s) 52 etc., but may also be a component which likewise detects an equally suitable characteristic variable of the onboard electrical system component in which energy storage device 32 is also arranged.
[0035] The method described is particularly suitable for increasing the reliability of an entire system, in particular for autonomous driving, for which particularly stringent safety requirements are usually imposed. However, the application of the invention is not limited thereto.
Claims
1. A method for plausibility checking of a measured variable of a sensor in a motor vehicle, wherein: At least one sensor (34) detects at least one measured variable of an energy storage device (32), wherein at least one load distribution device (52) is provided, to which energy is supplied via the energy storage device (32) for supplying energy to a plurality of electrical loads (36, 46), wherein at least one measured variable of the load distribution device (52) is determined, characterized in that at least one plausibility check device (11) is provided, which determines the determined characteristic variable of the energy storage device (32) from the measured variable of the load distribution device (52) and compares the determined characteristic variable of the energy storage device with the measured variable of the energy storage device (32).
2. The method according to claim 1, characterized in that: Using a cable harness model (25), the ascertained characteristic variable of the energy storage device (32) is determined from the measured variable of the load distribution device (52).
3. The method according to claim 1 or 2, characterized in that: In the event of a significant deviation between the ascertained characteristic variable of the energy store (32) and a measured variable of the energy store (32), the ascertained characteristic variable is forwarded.
4. The method according to claim 1 or 2, characterized in that: A measured variable of the energy storage device (32) is supplied to a state recognition device (13) of the energy storage device (32) in order to determine a derived characteristic variable, wherein the measured variable and / or the derived characteristic variable is supplied to an evaluation device (21).
5. The method according to claim 4, characterized in that An output signal of the plausibility check device (11) - a measured variable or an ascertained characteristic variable of the energy storage device (32) - is supplied to a further state recognition device (19) of the energy storage device (32) in order to ascertain a derived characteristic variable of the energy storage device (32), wherein the measured variable and / or the derived characteristic variable and / or the ascertained characteristic variable of the energy storage device (32) are supplied to an analysis device (21).
6. The method according to claim 4, characterized in that Based on a comparison of the determined characteristic variable of the energy storage device (32) with a measured variable of the energy storage device (32), the plausibility check device (11) forwards the determined characteristic variable of the energy storage device (32) or the measured variable to a further state recognition device (19) of the energy storage device (32) and / or to an analysis device (21).
7. The method according to claim 1 or 2, characterized in that: In the event of a significant deviation between the ascertained characteristic variable and a measured variable of the energy storage device (32), a fault message is generated.
8. The method according to claim 5, characterized in that In the event of a significant deviation between a characteristic variable derived by the state recognition device (13) and a characteristic variable derived by a further state recognition device (19) of the energy storage device (32), a fault message is generated.
9. The method according to claim 7, characterized in that: In the event of the fault message, the automated driving function is affected.
10. The method according to claim 8, characterized in that When the above fault information exists, the automatic driving function is affected.
11. The method according to claim 1 or 2, characterized in that: Measured values at a decoupling element (26) are used to determine an ascertained characteristic variable, wherein a plurality of onboard power supply components of the motor vehicle can be decoupled from one another by the decoupling element (26) in the event of a fault.
12. The method according to claim 1 or 2, characterized in that: Further voltage values and / or current values of components additionally connected to the energy storage device (32) are used to determine the ascertained characteristic variable.
13. The method according to claim 1 or 2, characterized in that: The contact resistance between the energy storage device (32) and the load distribution device (52) and / or ground is used to determine the ascertained characteristic variable.
14. The method according to claim 1 or 2, characterized in that: The ascertained characteristic variable is determined using a sum of a current at a decoupling element (26) and a current at the load distribution device (52), wherein a plurality of onboard power supply components of the motor vehicle can be decoupled from one another by the decoupling element (26) in the event of a fault.
15. The method according to claim 9 or 10, characterized in that In the event of the fault information being present, the automated driving function is influenced by transferring the motor vehicle into a safe state or by influencing activation of the automated driving function.
16. The method according to claim 11, characterized in that The separation element (26) is a DC voltage converter.
17. The method according to claim 14, characterized in that The separation element (26) is a DC voltage converter.