A power grid dispatching method and system based on graph database

Using graph database technology to process power panoramic data, build graphs and push decision support information, it solves the problem of traditional databases being difficult to manage massive data and improves the decision-making efficiency and accuracy of power grid dispatching.

CN112418736BActive Publication Date: 2024-10-22SHENZHEN POWER SUPPLY BUREAU
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202011469089.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-15
Publication Date
2024-10-22
Estimated Expiration
2040-12-15

AI Technical Summary

Technical Problem

Traditional relational databases cannot meet the management and analysis needs of massive data in the power industry, and cannot effectively support power grid dispatching decisions.

Method used

Graph database technology is used to obtain power panoramic data from multiple power grid management systems. Through the data extraction rules of new word discovery, semantic association and event relationship, the dispatch specification map, dispatch plan map and abnormal event map are constructed, and the LSTM model is used to process the data. , and push multi-level and multi-stage decision support information.

Benefits of technology

It improves the efficiency of data query and retrieval, meets the management and analysis needs of massive data in the power industry, and provides more accurate and timely decision support.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112418736B_ABST
    Figure CN112418736B_ABST
Patent Text Reader

Abstract

The present invention discloses a power grid dispatching method based on a graph database, including: obtaining power panoramic data from multiple power grid management systems; extracting and processing the power panoramic data based on preset data extraction rules to obtain key data; the data extraction rules include new word discovery, semantic association and event relationship; obtaining constructed data according to the key data; constructing a graph database according to the constructed data and storing it; and pushing multi-level and multi-stage decision support information to power grid dispatchers based on the graph database. The present invention also discloses a corresponding system. By implementing the present invention and using a graph database to push decision support information to power grid dispatchers, the efficiency of data query and retrieval can be improved to meet the development needs of the power industry with massive data.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power grid dispatching, and in particular to a power grid dispatching method and system based on a graph database. Background Art

[0002] Power equipment and grid operation services are the core assets of the State Grid. The healthy operation and maintenance level of power equipment is closely related to the safe operation level of the grid. Research on the comprehensive management of power equipment quality is of great significance to the safe and stable operation of the grid and the operation and maintenance of equipment.

[0003] With the development of Internet of Things technology, the various business departments related to power equipment management of State Grid Corporation of China have established corresponding information management systems, realizing all-round management of procurement, dispatching, operation, inspection and maintenance of power equipment from different aspects. However, the traditional power grid information management system uses traditional relational databases, which are difficult to meet the development needs of the power industry. Summary of the invention

[0004] In order to solve the above technical problems, the present invention provides a power grid dispatching method and system based on a graph database to meet the development needs of the power industry.

[0005] As one aspect of the present invention, a power grid dispatching method based on a graph database is provided, which includes:

[0006] Step S101, acquiring power panoramic data from multiple power grid management systems;

[0007] Step S102, extracting and processing the power panoramic data based on preset data extraction rules to obtain key data; the data extraction rules include new word discovery, semantic association and event relationship;

[0008] Step S103, obtaining construction data according to the key data;

[0009] Step S104, constructing a graph database according to the construction data and storing it;

[0010] Step S105, pushing multi-level and multi-stage decision support information to power grid dispatchers based on the graph database.

[0011] Preferably, the power panoramic data includes historical SCADA measurement data, power grid topology data, power generation data, load forecast data, maintenance plans, dispatching procedures, dispatching plans, operation tickets, historical fault alarms, geographic information and meteorological information.

[0012] Preferably, after acquiring the power panoramic data, the method further includes:

[0013] Process unstructured power landscape data into structured data.

[0014] Preferably, obtaining construction data according to the key data specifically includes:

[0015] Dividing the key data into a training set and a test set;

[0016] Selecting an LSTM network model, and using the training set to perform parameter training on the LSTM to obtain a target model;

[0017] The test set is input into the target model to obtain the construction data.

[0018] Preferably, the graph database includes a dispatch specification graph, a dispatch plan graph, a power grid event graph, and an abnormal event graph;

[0019] According to the graph database, multi-level and multi-stage decision support information is pushed to the grid dispatcher, including:

[0020] In the dispatching specification map, the dispatching operation details and precautions of the current power grid situation are obtained, and standard handling guidance is provided;

[0021] Perform intelligent query in the dispatch plan map, extract and push key information in the accident plan applicable to the current power grid risk situation;

[0022] Reasoning is performed based on the similarity between the power grid event graph and the abnormal event graph, and effective key features and corresponding operation information in historical handling cases are extracted and pushed.

[0023] Accordingly, another aspect of the present invention further provides a power grid dispatching system based on a graph database, comprising:

[0024] An acquisition unit, used for acquiring power panoramic data from multiple power grid management systems;

[0025] An extraction unit, configured to extract and process the power panoramic data based on preset data extraction rules to obtain key data; the data extraction rules include new word discovery, semantic association and event relationship;

[0026] A processing unit, configured to obtain construction data according to the key data;

[0027] A construction unit, used to construct a graph database according to the construction data and store it;

[0028] A push unit is used to push multi-level and multi-stage decision support information to power grid dispatchers based on the graph database.

[0029] Preferably, the power panoramic data includes historical SCADA measurement data, power grid topology data, power generation data, load forecast data, maintenance plans, dispatching procedures, dispatching plans, operation tickets, historical fault alarms, geographic information and meteorological information;

[0030] The processing unit is further used for processing unstructured power panorama data into structured data.

[0031] Preferably, the construction unit further comprises:

[0032] A division unit, used for dividing the key data into a training set and a test set;

[0033] A target model obtaining unit is used to select an LSTM network model, perform parameter training on the LSTM using the training set, and obtain a target model;

[0034] The construction data obtaining unit is used to input the test set into the target model to obtain the construction data.

[0035] Preferably, the graph database includes a dispatch specification graph, a dispatch plan graph, a power grid event graph, and an abnormal event graph;

[0036] The pushing unit further comprises:

[0037] A guidance information acquisition unit, used to obtain the dispatching operation details and precautions of the current power grid situation in the dispatching specification map, and provide standard handling guidance;

[0038] A query unit, used to perform intelligent query in the dispatch plan map, extract and push key information in the accident plan applicable to the current power grid risk situation;

[0039] The inference processing unit is used to perform inference based on the similarity between the power grid event map and the abnormal event map, and to extract and push effective key features and corresponding operation information in historical handling cases.

[0040] Correspondingly, another aspect of the present invention also provides a power grid dispatching system based on a graph database, which includes a processor, an input device, an output device and a memory, wherein the processor, input device, output device and memory are interconnected, wherein the memory is used to store a computer program, and the computer program includes program instructions, and the processor is configured to call the program instructions to execute the aforementioned method.

[0041] The implementation of the present invention has the following beneficial effects:

[0042] The present invention provides a power grid dispatching method and system based on a graph database. When the embodiments of the present invention are implemented, power panoramic data are obtained from multiple power grid management systems; based on preset data extraction rules, the power panoramic data are extracted and processed to obtain key data; construction data is obtained according to the key data; a graph database is constructed according to the construction data and stored; multi-level and multi-stage decision support information is pushed to power grid dispatchers based on the graph database; the embodiments of the present invention use the graph database to push decision support information to power grid dispatchers, which can improve data query and retrieval efficiency and meet the development needs of the power industry with massive data. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, without paying creative labor, other drawings obtained based on these drawings still belong to the scope of the present invention.

[0044] Figure 1 It is a main flow chart of an embodiment of a power grid dispatching method based on a graph database provided by the present invention;

[0045] Figure 2 It is a structural diagram of a first embodiment of a power grid dispatching system based on a graph database provided by the present invention;

[0046] Figure 3 yes Figure 2 Schematic diagram of the structure of the building block;

[0047] Figure 4 yes Figure 2 A schematic diagram of the structure of the push unit in FIG.

[0048] Figure 5 It is a structural diagram of a second embodiment of a power grid dispatching system based on a graph database provided by the present invention. DETAILED DESCRIPTION

[0049] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0050] In order to better understand the embodiments of the present invention, the related knowledge involved is first described as follows:

[0051] Different from the index-based relational data structure, the graph database uses "nodes" and "edges" as the basic storage units to store data. It takes advantage of the physical "pointing" between nodes to provide "index-free" association operations for adjacent nodes. It has the characteristics of real-time dynamic status updates, supports big data distributed storage and parallel computing, and effectively improves the efficiency of data storage and processing. It is particularly suitable for managing, processing and analyzing application problems with interdependencies between a large number of objects. It is a database specifically designed to handle "massive relationships".

[0052] Please refer to Figure 1 , an embodiment of the present invention provides a power grid dispatching method based on a graph database, comprising:

[0053] Step S101, obtaining power panoramic data from multiple power grid management systems.

[0054] Among them, the power panoramic data includes but is not limited to historical SCADA measurement data, power grid topology data, power generation data, load forecast data, maintenance plans, dispatching procedures, dispatching plans, operation tickets, historical fault alarms, geographic information and meteorological information, etc.

[0055] Step S102: Process the unstructured power panoramic data into structured data.

[0056] Step S103: extracting and processing the power panoramic data based on preset data extraction rules to obtain key data.

[0057] The data extraction rules include but are not limited to new word discovery, semantic association and event relationship.

[0058] Step S104, obtaining construction data according to the key data.

[0059] With the rapid development of big data and machine learning technology, algorithms such as recurrent neural network (RNN), long-term memory (LSTM) and hybrid model clustering have gradually been applied to the power industry. In this embodiment, the LSTM model is also used for data construction. The specific process is as follows:

[0060] Dividing the key data into a training set and a test set;

[0061] Selecting an LSTM network model, and using the training set to perform parameter training on the LSTM to obtain a target model;

[0062] The test set is input into the target model to obtain the construction data.

[0063] It should be noted that, in specific applications, the above-mentioned target model can be continuously iterated and updated so that more prepared construction data can be obtained through the above-mentioned target model, thereby providing a better foundation for the subsequent construction of the graph database.

[0064] Step S105: construct a graph database according to the construction data and store it.

[0065] Among them, the constructed graph database includes but is not limited to dispatch specification graphs, dispatch plan graphs, power grid event graphs and abnormal event graphs.

[0066] Step S106, pushing multi-level and multi-stage decision support information to power grid dispatchers based on the graph database.

[0067] Specifically, step S106 includes:

[0068] In the dispatching specification map, the dispatching operation details and precautions of the current power grid situation are obtained, and standard handling guidance is provided;

[0069] Perform intelligent query in the dispatch plan map, extract and push key information in the accident plan applicable to the current power grid risk situation;

[0070] Reasoning is performed based on the similarity between the power grid event graph and the abnormal event graph, and effective key features and corresponding operation information in historical handling cases are extracted and pushed.

[0071] The power grid dispatching method of the embodiment of the present invention is implemented to obtain power panoramic data from multiple power grid management systems; based on preset data extraction rules, the power panoramic data is extracted and processed to obtain key data; construction data is obtained according to the key data; a graph database is constructed according to the construction data and stored; multi-level and multi-stage decision support information is pushed to power grid dispatchers based on the graph database; that is, the embodiment of the present invention uses the graph database to push decision support information to power grid dispatchers, which can improve data query and retrieval efficiency and meet the development needs of the power industry with massive data.

[0072] Based on the same inventive concept, Figure 2 FIG. 1 is a schematic diagram showing a structure of a first embodiment of a power grid dispatching system based on a graph database provided by the present invention. Figure 3 and Figure 4 As shown, in this embodiment, the system includes:

[0073] The acquisition unit 10 is used to acquire power panoramic data from multiple power grid management systems; wherein the power panoramic data includes but is not limited to historical SCADA measurement data, power grid topology data, power generation data, load forecast data, maintenance plans, dispatching procedures, dispatching plans, operation tickets, historical fault alarms, geographic information and meteorological information, etc.;

[0074] An extraction unit 11 is used to extract and process the power panoramic data based on preset data extraction rules to obtain key data; the data extraction rules include but are not limited to new word discovery, semantic association and event relationship, etc.;

[0075] A processing unit 12, configured to process the unstructured power panoramic data into structured data, and obtain constructed data according to the key data;

[0076] The construction unit 13 is used to construct a graph database according to the construction data and store it; wherein the graph database includes but is not limited to a dispatch specification graph, a dispatch plan graph, a power grid event graph, and an abnormal event graph, etc.

[0077] The push unit 14 is used to push multi-level and multi-stage decision support information to power grid dispatchers based on the graph database.

[0078] Furthermore, the construction unit 13 further includes:

[0079] A division unit 130, configured to divide the key data into a training set and a test set;

[0080] A target model obtaining unit 131 is used to select an LSTM network model, perform parameter training on the LSTM using the training set, and obtain a target model;

[0081] The construction data obtaining unit 132 is used to input the test set into the target model to obtain the construction data.

[0082] Furthermore, the push unit 14 further includes:

[0083] The guidance information acquisition unit 140 is used to obtain the dispatching operation details and precautions of the current power grid situation in the dispatching specification map, and provide standard handling guidance;

[0084] A query unit 141 is used to perform intelligent query in the dispatch plan map, extract and push key information in the accident plan applicable to the current power grid risk situation;

[0085] The reasoning processing unit 142 is used to perform reasoning based on the similarity between the power grid event map and the abnormal event map, and extract and push effective key features and corresponding operation information in historical handling cases.

[0086] Alternatively, in another preferred embodiment of the present invention, as Figure 5 As shown, a schematic diagram of the main structure of a power grid dispatching system based on a graph database is shown. In this embodiment, the system may include: one or more processors 101, one or more input devices 102, one or more output devices 103 and a memory 104. The processors 101, input devices 102, output devices 103 and memory 104 are interconnected via a bus 105. The memory 104 is used to store a computer program, and the computer program includes program instructions. The processor 101 is configured to call the program instructions to execute Figure 1 The method shown.

[0087] It should be understood that in the embodiment of the present invention, the processor 101 may be a central processing unit (CPU), and the processor may also be other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc.

[0088] The input device 102 may include a keyboard, etc., and the output device 103 may include a display (LCD, etc.), a speaker, etc.

[0089] The memory 104 may include a read-only memory and a random access memory, and provides instructions and data to the processor 101. A portion of the memory 104 may also include a non-volatile random access memory. For example, the memory 104 may also store information on the device type.

[0090] In a specific implementation, the processor 101, input device 102, and output device 103 described in the embodiment of the present invention can execute the implementation method described in the embodiment of the power grid scheduling method based on the graph database provided in the embodiment of the present invention, which will not be repeated here.

[0091] Implementing the power grid dispatching system provided by the embodiment of the present invention and using the graph database to push decision support information to power grid dispatching personnel can improve data query and retrieval efficiency and meet the development needs of the power industry with massive data.

[0092] Accordingly, an embodiment of the present invention provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, wherein the computer program includes program instructions, and when the program instructions are executed by a processor, the above-mentioned power grid scheduling method based on the graph database is implemented.

[0093] The computer-readable storage medium may be an internal storage unit of the system described in any of the foregoing embodiments, such as a hard disk or memory of the system. The computer-readable storage medium may also be an external storage device of the system, such as a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (Secure Digital, SD) card, a flash card (Flash Card), etc. equipped on the system. Furthermore, the computer-readable storage medium may also include both an internal storage unit of the system and an external storage device. The computer-readable storage medium is used to store the computer program and other programs and data required by the system. The computer-readable storage medium may also be used to temporarily store data that has been output or is to be output.

[0094] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in terms of function in the above description. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.

[0095] In the several embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. In addition, the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces, devices or units, or it can be an electrical, mechanical or other form of connection.

[0096] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the embodiments of the present invention.

[0097] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0098] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention is essentially or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk and other media that can store program codes.

[0099] The implementation of the embodiments of the present invention has the following beneficial effects:

[0100] The present invention provides a power grid dispatching method and system based on a graph database, which obtains power panoramic data from multiple power grid management systems; extracts and processes the power panoramic data based on preset data extraction rules to obtain key data; obtains constructed data based on the key data; constructs a graph database based on the constructed data and stores it; and pushes multi-level and multi-stage decision support information to power grid dispatchers based on the graph database. The embodiment of the present invention uses a graph database to push decision support information to power grid dispatchers, which can improve data query and retrieval efficiency and meet the development needs of the power industry with massive data.

[0101] The above disclosure is only a preferred embodiment of the present invention, which certainly cannot be used to limit the scope of the present invention. Therefore, equivalent changes made according to the claims of the present invention are still within the scope of the present invention.

Claims

1. A power grid dispatching method based on a graph database, characterized in that: include: Step S101, acquiring power panoramic data from multiple power grid management systems; Step S102, extracting and processing the power panoramic data based on preset data extraction rules to obtain key data; the data extraction rules include new word discovery, semantic association and event relationship; Step S103, obtaining construction data according to the key data; Step S104, constructing a graph database according to the construction data and storing it; Step S105, pushing multi-level and multi-stage decision support information to power grid dispatchers according to the graph database; The construction data is obtained according to the key data, specifically including: Dividing the key data into a training set and a test set; Selecting an LSTM network model, and using the training set to perform parameter training on the LSTM to obtain a target model; Inputting the test set into the target model to obtain the construction data; The graph database includes a dispatch specification graph, a dispatch plan graph, a power grid event graph, and an abnormal event graph; According to the graph database, multi-level and multi-stage decision support information is pushed to the grid dispatcher, including: In the dispatching specification map, the dispatching operation details and precautions of the current power grid situation are obtained, and standard handling guidance is provided; Perform intelligent query in the dispatch plan map, extract and push key information in the accident plan applicable to the current power grid risk situation; Reasoning based on the similarity between the power grid event graph and the abnormal event graph, extracting and pushing effective key features and corresponding operation information in historical disposal cases; The power panoramic data includes historical SCADA measurement data, power grid topology data, power generation data, load forecast data, maintenance plans, dispatching procedures, dispatching plans, operation tickets, historical fault alarms, geographic information and meteorological information; After obtaining the power panoramic data, the method further includes: Process unstructured power landscape data into structured data.

2. A power grid dispatching system based on a graph database, characterized in that: include: An acquisition unit, used for acquiring power panoramic data from multiple power grid management systems; An extraction unit, configured to extract and process the power panoramic data based on preset data extraction rules to obtain key data; the data extraction rules include new word discovery, semantic association and event relationship; A processing unit, configured to obtain construction data according to the key data; A construction unit, used to construct a graph database according to the construction data and store it; A push unit, used to push multi-level and multi-stage decision support information to power grid dispatchers according to the graph database; Wherein, the construction unit further comprises: A division unit, used for dividing the key data into a training set and a test set; A target model obtaining unit is used to select an LSTM network model, perform parameter training on the LSTM using the training set, and obtain a target model; A construction data obtaining unit, used for inputting the test set into the target model to obtain the construction data; The graph database includes a dispatch specification graph, a dispatch plan graph, a power grid event graph, and an abnormal event graph; The push unit further comprises: A guidance information acquisition unit, used to obtain the dispatching operation details and precautions of the current power grid situation in the dispatching specification map, and provide standard handling guidance; A query unit, used to perform intelligent query in the dispatch plan map, extract and push key information in the accident plan applicable to the current power grid risk situation; An inference processing unit, used to perform inference based on the similarity between the power grid event map and the abnormal event map, extract and push effective key features and corresponding operation information in historical disposal cases; The power panoramic data includes historical SCADA measurement data, power grid topology data, power generation data, load forecast data, maintenance plans, dispatching procedures, dispatching plans, operation tickets, historical fault alarms, geographic information and meteorological information; The processing unit is further used for processing unstructured power panorama data into structured data.

3. A power grid dispatching system based on a graph database, characterized in that: The method comprises a processor, an input device, an output device and a memory, wherein the processor, the input device, the output device and the memory are interconnected, wherein the memory is used to store a computer program, the computer program comprises program instructions, and the processor is configured to call the program instructions to execute the method as claimed in claim 1.

Citation Information

Patent Citations

  • Knowledge graph construction method and system of power system

    CN110727741A

  • Scheduling decision generation method and device, electronic equipment and storage medium

    CN111861250A

  • Power grid knowledge graph construction method and system

    CN111930784A

  • Power grid fault knowledge recommendation and knowledge management system and method based on knowledge graph

    CN111985653A