A high pier steam maintenance equipment
By designing high-pier steam maintenance equipment, using roller mold lifting frames and steam maintenance machines to pour and maintain during the high-pier construction process, the problem of difficulty in achieving temperature regulation and control in the existing technology is solved, and the construction efficiency of high-pier and concrete hardening quality is improved.
Patent Information
- Application Number
- CN202011511037.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-12-18
- Publication Date
- 2025-03-28
- Estimated Expiration
- 2040-12-18
AI Technical Summary
The existing concrete curing methods for high-pier bridges are difficult to achieve temperature regulation and control, and it is impossible to perform steam curing in time during the construction of high-pier, which affects the effective hardening of concrete.
A high-pier steam maintenance equipment is designed, including a roller mold lifting frame, hydraulic lifting system, rolling device, lining formwork, modification frame, curing frame, steaming machine and insulation mechanism, allowing the high-pier body to be poured and maintained, and the steam maintenance machine and insulation mechanism are used to ensure the normal hardening and strength growth of concrete.
The high efficiency and rapid construction period of high piers are achieved, the normal hardening and strength growth of concrete are ensured, and the problems of waste of water resources and surface damage in the existing methods are avoided.
Smart Images

Figure CN112609587B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of high pier construction, in particular to high pier steam maintenance equipment. Background Art
[0002] With the rapid development of my country's transportation industry, highway construction has gradually extended to mountainous and hilly areas. Due to the restrictions of terrain conditions, highway construction in these areas often needs to cross deep gullies and canyons, resulting in an increasing number of high-pier bridges. In order to ensure sufficient support strength and longer service life, bridge piers are generally cast in concrete, which can effectively prevent rust, penetration and deformation, and provide protection for bridge safety; however, after the construction of the concrete structure is completed, a period of maintenance is required. Usually, maintenance needs to be started 12-18 hours after the pier concrete is cast, and the maintenance time lasts about 3-4 weeks to ensure the normal hardening and strength growth of the pier.
[0003] In addition to covering and sprinkling water on the piers after construction, the maintenance method also requires heating maintenance, constant temperature maintenance, and cooling watering in a wet state. The process is relatively cumbersome and time-consuming. Existing pier concrete maintenance methods usually use spraying or film covering to keep it moist, but due to the limited absorption rate of concrete for water, it is difficult to achieve uniform spraying by spraying, which not only wastes water resources, but also has a large impact on the surface of the pier, which can easily cause the surface mud to peel off and dissolve and lose; film covering can save water and has a good water-locking and moisturizing effect, but the film exposed to the outdoors is easily damaged, and it is difficult to ensure the integrity and effectiveness of the covering.
[0004] Both of the above two methods cannot adjust and control the curing temperature, and cannot steam-cure the poured concrete in time during the construction of the high pier, which is not conducive to the effective hardening of the high pier concrete of the bridge within the predetermined time. Summary of the invention
[0005] In order to solve the deficiencies mentioned in the above-mentioned background technology, the purpose of the present invention is to provide a high pier steam curing equipment, which can perform concrete pouring on the upper side of the roller mold lifting frame while curing the high pier body demolded on the lower side of the roller mold lifting frame, so as to achieve pouring and curing at the same time, which greatly improves the efficiency of high pier construction and shortens the construction period of high piers of bridges.
[0006] The purpose of the present invention can be achieved through the following technical solutions:
[0007] A high pier steam curing equipment comprises an operating platform, the operating platform is arranged above the high pier, a roller mould lifting frame is fixedly installed at the bottom of the operating platform, a hydraulic lifting system automatically controlled by a computer is arranged on the outer side of the roller mould lifting frame, a rolling device is fixedly installed on the inner side of the roller mould lifting frame, an inner lining template is vertically arranged between the rolling device and the high pier, the roller mould lifting frame comprises a modifying frame and a curing frame, the modifying frame is arranged on the upper side of the roller mould lifting frame, a steam curing machine is fixedly installed on the modifying frame, the curing frame is arranged on the lower side of the roller mould lifting frame, and a heat preservation mechanism is arranged on the outer side of the curing frame.
[0008] Further preferably, the roller mold lifting frame is arranged around the high pier.
[0009] Further preferably, the rolling device is a metal roller, which is horizontally arranged, and the length of the rolling device matches the length of the outer wall of the high pier, and both ends of the rolling device are fixedly mounted on the roller mold lifting frame through rolling wheel bearings.
[0010] Further preferably, the lining templates are arranged in a rectangular array, the lining templates are spliced by tongue and groove, and the lining templates are assembled upside down.
[0011] Further preferably, the modification frame and the maintenance frame are both composed of supporting truss plates and cross-connections. The cross-connections and the supporting truss plates are bolted, and the supporting truss plates are welded. A rolling device is provided on the supporting truss plates close to one side of the high pier.
[0012] Further preferably, the steaming and curing machine is arranged at the four corners of the roller mold lifting frame, and the steaming and curing machine is an electric steam generator.
[0013] Further preferably, the insulation mechanism includes a roller shutter, which is symmetrically arranged on the top of the outer wall of the curing frame, and is fixed to the outer wall of the curing frame through a flange. A tarpaulin is provided between the roller shutters, and both sides of the tarpaulin are connected to the track of the roller shutter, and the track of the roller shutter is vertically arranged on both sides of the outer wall of the curing frame.
[0014] Further preferably, the width of the tarpaulin matches the width of the outer wall of the maintenance frame, and a steel wire scissors brace is provided on the outer side of the tarpaulin.
[0015] Beneficial effects of the present invention:
[0016] The high pier steam curing equipment of the present invention lifts the roller formwork lifting frame through a hydraulic lifting system. During the lifting process, the roller formwork lifting frame rolls upward on the surface of the lining formwork, ensuring that the lining formwork and the concrete surface remain stationary, avoiding repeated removal and installation of the formwork, thereby ensuring the appearance quality of the concrete and accelerating the construction speed; a curing frame is provided on the lower side of the roller formwork lifting frame of the present invention, and after the lining formwork is removed, the high pier body at the demolding location is timely steam-cured by a steam curing machine, thereby ensuring the normal hardening and strength increase of the pier body concrete, wherein the heat preservation mechanism can play a good role in heat preservation and moisture retention during steam curing, thereby improving the effect of steam curing; the high pier steam curing equipment of the present invention can perform concrete pouring work on the upper side of the roller formwork lifting frame while curing the high pier body demolded on the lower side of the roller formwork lifting frame, thereby achieving pouring and curing at the same time, thereby greatly improving the efficiency of high pier construction and shortening the construction period of bridge high piers. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0018] Figure 1 It is a left side view of the high pier steam curing equipment of the present invention;
[0019] Figure 2 It is a front view of the high pier steam curing equipment of the present invention;
[0020] Figure 3 It is a top view of the high pier steam curing equipment of the present invention.
[0021] In the figure:
[0022] 1-operating platform, 2-high pier, 3-lifting frame, 4-rolling device, 5-lining formwork, 6-decoration frame, 7-curing frame, 8-steaming machine, 9-heat preservation mechanism, 10-roller, 11-tarpaulin. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0024] In the description of the present invention, it should be understood that the terms "opening", "upper", "lower", "thickness", "top", "middle", "length", "inside", "all around" and the like indicating orientation or positional relationship are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the components or elements referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0025] like Figure 1-3 As shown, a high pier steam curing equipment comprises an operating platform 1, an operating platform 1, and an operating platform 1 is arranged above a high pier 2. A roller mold lifting frame 3 is fixedly installed at the bottom of the operating platform 1, and a hydraulic lifting system automatically controlled by a computer is arranged on the outer side of the roller mold lifting frame 3. A rolling device 4 is fixedly installed on the inner side of the roller mold lifting frame 3, and an inner lining template 5 is vertically arranged between the rolling device 4 and the high pier 2. The roller mold lifting frame 3 comprises a modifying frame 6 and a curing frame 7. The modifying frame 6 is arranged on the upper side of the roller mold lifting frame 3, and a steam curing machine 8 is fixedly installed on the modifying frame 6. The curing frame 7 is arranged on the lower side of the roller mold lifting frame 3, and a heat preservation mechanism 9 is arranged on the outer side of the curing frame 7.
[0026] The roller mold lifting frame 3 is arranged around the high pier 2.
[0027] The rolling device 4 is a metal roller, which is horizontally arranged. The length of the rolling device 4 matches the length of the outer wall of the high pier 2 . Both ends of the rolling device 4 are fixedly mounted on the roller mold lifting frame 3 through rolling wheel bearings.
[0028] The lining templates 5 are arranged in a rectangular array, and the lining templates 5 are spliced by tongue and groove joints, and the lining templates 5 are assembled upside down.
[0029] The modification frame 6 and the maintenance frame 7 are both composed of supporting truss pieces and cross-connections. The cross-connections and the supporting truss pieces are bolted, and the supporting truss pieces are welded. A rolling device 4 is arranged on one side of the supporting truss piece close to the high pier 2.
[0030] The steaming and curing machine 8 is arranged at the four corners of the roller mold lifting frame 3, and the steaming and curing machine 8 is an electric steam generator.
[0031] The insulation mechanism 9 includes a roller shutter 10, which is symmetrically arranged on the top of the outer wall of the curing frame 7. The roller shutter 10 is fixed to the outer wall of the curing frame 7 through a flange. A tarpaulin 11 is arranged between the roller shutters 10. Both sides of the tarpaulin 11 are connected to the track of the roller shutter 10. The track of the roller shutter 10 is vertically arranged on both sides of the outer wall of the curing frame 7.
[0032] The width of the tarpaulin 11 matches the width of the outer wall of the curing frame 7 , and a steel wire scissor brace is arranged on the outer side of the tarpaulin 11 .
[0033] When using the device for high pier construction, first build the operating platform 1 and the roller formwork lifting frame 2, fix the lining formwork 5 and then pour concrete. After the pouring of one section of concrete for the high pier 2 is completed, the roller formwork lifting frame 2 is raised by the hydraulic lifting system, and the roller formwork lifting frame 2 is lifted upward along the lining formwork 5, and the lining formwork 5 in contact with the concrete surface remains stationary. After being lifted to the specified position, the lining formwork 5 of the bottom layer is removed and installed on the top layer for the next pouring of the high pier 2 body concrete. At the same time, the tarpaulin 11 is lowered by the roller shutter 10, and a steel wire scissors support is arranged on the outside of the tarpaulin 11 to prevent large shaking caused by wind. Then, the steam curing machine 8 is turned on to provide steam curing to the high pier 2 body poured under the curing frame 7. In this way, the high pier 2 body can be poured and cured simultaneously, which greatly improves the efficiency of high pier construction.
[0034] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0035] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements all fall within the scope of the present invention to be protected.
Claims
1. A steam curing equipment for high piers, characterized in that: The invention comprises an operating platform (1), wherein the operating platform (1) is arranged above a high pier (2), a roller mold lifting frame (3) is fixedly installed at the bottom of the operating platform (1), a hydraulic lifting system automatically controlled by a computer is arranged on the outer side of the roller mold lifting frame (3), a rolling device (4) is fixedly installed on the inner side of the roller mold lifting frame (3), an inner lining template (5) is vertically arranged between the rolling device (4) and the high pier (2), the roller mold lifting frame (3) comprises a trimming frame (6) and a curing frame (7), the trimming frame (6) is arranged on the upper side of the roller mold lifting frame (3), a steam curing machine (8) is fixedly installed on the trimming frame (6), the curing frame (7) is arranged on the lower side of the roller mold lifting frame (3), and a heat preservation mechanism (9) is arranged on the outer side of the curing frame (7); The steaming and curing machine (8) is arranged at the four corners of the roller mold lifting frame (3), and the steaming and curing machine (8) is an electric steam generator; The heat preservation mechanism (9) comprises a roller shutter (10), the roller shutter (10) is symmetrically arranged on the top of the outer wall of the curing frame (7), the roller shutter (10) is fixed to the outer wall of the curing frame (7) through a flange, a tarpaulin (11) is arranged between the roller shutter (10), both sides of the tarpaulin (11) are connected to the track of the roller shutter (10), and the track of the roller shutter (10) is vertically arranged on both sides of the outer wall of the curing frame (7); The width of the tarpaulin (11) matches the width of the outer wall of the curing frame (7), and a steel wire scissors brace is arranged on the outer side of the tarpaulin (11).
2. The high pier steam curing equipment according to claim 1 is characterized in that: The roller mold lifting frame (3) is arranged around the high pier (2).
3. The high pier steam curing equipment according to claim 1, characterized in that: The rolling device (4) is a metal roller. The rolling device (4) is arranged horizontally. The length of the rolling device (4) matches the length of the outer wall of the high pier (2). Both ends of the rolling device (4) are fixedly mounted on the roller mold lifting frame (3) via rolling wheel bearings.
4. The steam curing equipment for high piers according to claim 1 is characterized in that: The lining templates (5) are arranged in a rectangular array, the lining templates (5) are spliced with each other through tongue and groove joints, and the lining templates (5) are assembled upside down.
5. The high pier steam curing equipment according to claim 1, characterized in that: The modification frame (6) and the maintenance frame (7) are both composed of supporting truss pieces and cross-connections. The cross-connections and the supporting truss pieces are bolted, and the supporting truss pieces are welded. A rolling device (4) is provided on one side of the supporting truss piece close to the high pier (2).
Citation Information
Patent Citations
Hollow high-pier concrete pouring heat preservation and maintenance system
CN105625189A
Bridge high pier roller die construction device
CN203144909U
High pier slip form with maintenance function and multi-column type high pier slip form maintenance system
CN210031484U
High pier steam curing equipment
CN214459661U