A punching cast-in-place pile construction control device and method

By using the control device of the rotation sensor and the deviation correction mechanism in the punching pile construction, the problems of low construction efficiency and shaking are solved, and efficient and safe pile hole construction is achieved, ensuring construction quality and safety.

CN112726604BActive Publication Date: 2024-11-29CHINA RAILWAY 22ND BUREAU GRP MUNICIPAL ENG CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202011619262.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-30
Publication Date
2024-11-29
Estimated Expiration
2040-12-30

AI Technical Summary

Technical Problem

The existing punching pile construction methods have high labor intensity and low efficiency, and it is difficult to effectively control the shaking of the punching hammer, resulting in construction accidents and quality problems.

Method used

The punching pile construction control device with a rotation sensor and a deviation correction mechanism is adopted to measure the rotation angle and direction of the hammer in real time through the rotation sensor, and combine it with the deviation correction mechanism to quickly stabilize the hammer in real time, and monitor the inlet measurement and speed in real time, and timely according to the changes in the formation. Adjust the stroke and set the automatic warning function.

Benefits of technology

It effectively reduces the shaking of the hammer, improves construction efficiency and quality, ensures the verticality and depth accuracy of pile holes, and promptly warning and data recording improves construction safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112726604B_ABST
    Figure CN112726604B_ABST
Patent Text Reader

Abstract

The present invention discloses a construction control device for bored piles, wherein a drum is connected to a hammer through a steel wire rope, the hammer is placed in the pile hole of the bored pile, and further comprises a rotation sensor arranged on the drum of a winch, the rotation sensor is electrically connected to a control terminal, the control terminal is also electrically connected to a timing module, the rotation sensor can measure the cumulative rotation angle α and the rotation direction of the drum in real time during the construction of the bored piles, and a correction mechanism is also sleeved on the hammer. The system can quickly stabilize the hammer through the correction mechanism, effectively reduce the shaking of the hammer in a short time, and ensure the construction quality and efficiency; it can monitor the penetration amount, penetration speed and pile hole depth of the bored pile hammer in real time, and predict the formation conditions and the formation conditions that the hammer is about to enter according to the pile hole depth.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of civil engineering, and in particular to a punching cast-in-place pile construction control device and method. Background Art

[0002] The method for measuring the depth of bored piles currently used in my country is to measure the depth of the pile hole with a lead pendant and a measuring rope. First, the pile hammer is lifted out of the hole with a wire rope, and then the measuring rope with a lead pendant is placed in the pile hole. The lead pendant slowly sinks to the bottom of the hole, and the measuring rope is repeatedly lifted and lowered by hand until the lead pendant stops sinking. Then the scale mark on the measuring rope is read and the data is recorded. The hole depth data needs to be measured multiple times during the hole forming process of a bored pile. This method has high labor intensity and low efficiency. During the construction of bored piles, the hammer needs to adjust the appropriate stroke when it punches into different soil or rock layers, and the footage and footage speed are also different. At the same time, the hammer must be kept vertical during the punching process, and there must not be a large shake, otherwise the punching position will deviate from the designed position, resulting in an inclined hole or collapsed hole, and the shaking of the hammer may damage the hole wall, leading to construction accidents. Therefore, during construction, after the hammer is lifted, it is always necessary to wait for a period of time until it basically does not swing before it can continue to punch, which leads to low construction efficiency.

[0003] Existing technologies such as: CN 105649119 A A device and method for measuring the depth of bored piles, which measures the depth of the hammer by means of photoelectric distance measurement, and improves the construction efficiency compared with the traditional manual measurement method. However, there are still many problems. For example, on the traditional bored pile driver, it is necessary to replace the steel wire rope with scale, which inevitably increases the equipment cost; the light shield is fixed on the steel wire rope between the fixed pulley and the driving wheel, and when the light shield moves to the fixed pulley with the steel wire rope, it is necessary to adjust the position of the light shield in time to avoid getting stuck at the pulley and causing the steel wire rope to fall off; the measurement device has a relatively single function, and it is impossible to calculate the time of the hammer's penetration, making it difficult to better control the construction efficiency.

[0004] Existing technologies include: CN 110485417 A, a method for punching piles in karst areas, which effectively reduces the swing amplitude of the heavy hammer in a short time by lifting the hammer out of the pile hole to a set height, and the fan-shaped plate on the casing touches the swinging hammer, thereby improving the punching efficiency. This method requires the modification of the existing punching pile driver, which is not very applicable; reducing the swing of the hammer requires lifting the hammer out of the pile hole, and for the hammer that has been constructed to a deeper position, it takes a longer time to lift the hammer out of the pile hole, and the improvement in construction efficiency is not obvious. Summary of the invention

[0005] In view of the above problems, the present invention aims to provide a bored pile construction control device and method with the features of anti-electromagnetic interference and stable measurement signal.

[0006] To achieve the technical purpose, the solution of the present invention is: a bored cast-in-place pile construction control device, comprising a winch with a drum arranged on one side of the pile hole, the drum being connected to a hammer via a wire rope, the hammer being placed in the pile hole of the bored pile, and also comprising a rotation sensor arranged on the drum of the winch, the rotation sensor being electrically connected to a control terminal, the control terminal being also electrically connected to a timing module, the rotation sensor being able to measure in real time the cumulative rotation angle α and the rotation direction of the drum during the bored cast-in-place pile construction process, and the hammer being also provided with a deviation correction mechanism.

[0007] Preferably, a control frame is provided on one side of the winch, and a deviation correction mechanism is suspended from the control frame through a suspension rope, and the steel wire rope passes through the middle of the deviation correction mechanism, and the deviation correction mechanism is located directly above the hammer;

[0008] The control frame is also provided with a remotely controlled driving motor and a pulley block, and the driving motor can drive the suspension rope through the pulley block to drive the deviation correction mechanism to rise and fall.

[0009] Preferably, the deflection correction mechanism comprises a lifting ring and a deflection correction wheel, wherein a ring-shaped electromagnet is embedded in the lifting ring, a wire hole is also provided on the lifting ring, and two or more deflection correction wheels are symmetrically arranged around the lifting ring;

[0010] The correcting wheel is connected to the lifting ring through a transmission rod and a rotating rod. The end of the rotating rod is pivotally connected to the end of the transmission rod. The other end of the transmission rod is embedded in the limiting groove of the lifting ring. An energy-absorbing spring is also arranged between the transmission rod and the lifting ring. The middle part of the rotating rod is connected to the lifting ring through a positioning spring.

[0011] Preferably, the top of the transmission rod is a ball seat structure, and the top of the rotating rod is a ball head structure. The ball head structure matches the ball seat structure. A damping rubber pad is also arranged between the ball head structure and the ball seat structure. The rotating rod can rotate universally around the ball seat structure within a limited angle.

[0012] A method of use, a punching pile construction control device, the specific steps are as follows:

[0013] S1. Installation: Install a control frame above the pile hole, connect the lifting rope on the pulley block to the deviation correction mechanism, and remotely control the lifting rope to rise or fall through the driving motor to make the deviation correction mechanism in the initial position;

[0014] S2, stabilize the hammer. When the construction starts, the winch retracts the hammer upward to the designated position of the pile hole. The construction personnel control the lowering of the correcting mechanism to the hammer position through the remote control, and energize the annular electromagnet to make the correcting mechanism generate annular suction around the hammer. At this time, the shaking of the hammer drives the correcting mechanism to collide with the steel casing at the top of the pile hole. The energy generated by the shaking and collision is dissipated by the correcting mechanism to quickly stabilize the hammer. After stabilization, the power supply of the annular electromagnet is disconnected, and then the hammer is lowered to start the construction. During the lifting and lowering process, the rotation sensor records the cumulative rotation angle α and the rotation direction at this time;

[0015] S3. Calculate, where r is the radius of the drum, Δt is the time required for the hammer to be lifted up and dropped down, and the calculation formula is as follows:

[0016] Length of wire rope moving when hammer is lifted:

[0017] Length of wire rope moving when hammer falls:

[0018] Single hammer penetration: ΔL=L x -L s

[0019] Driving speed:

[0020] Pile hole depth: H = ΔL1 + ΔL2 + ... ΔL n

[0021] S4: When the ground changes, the preset hammer stroke is used for construction. When the difference between the preset hammer stroke and the actual footage exceeds the threshold, it means that the hammer has entered a different soil or rock layer, and the appropriate stroke needs to be adjusted to match the appropriate footage and footage speed;

[0022] The geological survey information is entered into the control terminal in advance, and the control terminal is set with an automatic early warning function to monitor the hammer's footage, footage speed and pile hole depth in real time. The stratum conditions and the stratum conditions that the hammer is about to enter are predicted based on the pile hole depth. When the hammer is about to enter the next soil or rock layer, the construction personnel are promptly reminded to adjust the hammer stroke and control the footage.

[0023] As a preferred embodiment, the method further includes the following steps: S5, early warning, recording the footage and speed of each penetration through the control terminal, predicting through big data analysis whether there are unfavorable geological conditions such as inclined rocks, isolated rocks or karst caves in the next soil or rock layer that the hammer will penetrate, and if so, the control terminal promptly issues an early warning, the construction personnel control the pile driver to gradually reduce the stroke of penetration, and observe through the camera whether there is obvious deviation of the wire rope at the pile hole;

[0024] When the wire rope is obviously deviated and the control terminal finds that the hammer penetration is abnormal, stop the hammer penetration in time and formulate a treatment plan after the inspection is completed;

[0025] S6. Report: The control terminal records the penetration speed, penetration amount and penetration times of the hammer in different strata in real time, and generates a penetration data report of the hammer in different strata. The penetration data report is uploaded to the server for storage.

[0026] The beneficial effects of the present invention are as follows: the system can quickly stabilize the hammer through the deviation correction mechanism, effectively reduce the shaking of the hammer in a short time, avoid the construction problems such as inclined holes, deviated holes, hammer jams and even collapsed holes caused by the shaking of the hammer, and ensure the construction quality and efficiency; it can monitor the penetration amount, penetration speed and pile hole depth of the punching pile hammer in real time, and predict the formation conditions and the formation conditions that the hammer is about to enter according to the pile hole depth, and promptly remind the construction personnel to adjust the hammer stroke and control the penetration amount when the hammer is about to enter the next soil layer or rock layer; it can predict the formation conditions where the hammer is located according to the formation exploration report, and set an automatic early warning function for poor geology; the control terminal records the penetration speed, penetration amount and number of penetrations of the hammer in different formations in real time, and generates a penetration data report of the hammer in different formations, determines the reference index of the hammer penetration in different formations, and is used to guide the subsequent construction of punching and casting piles. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a structural schematic diagram of the present invention;

[0028] Figure 2 It is a schematic diagram of the structure of the deviation correction mechanism of the present invention;

[0029] Figure 3 It is a partial structural schematic diagram of the deviation-correcting mechanism of the present invention;

[0030] Figure 4 It is a cross-sectional view of the deviation correcting mechanism of the present invention. DETAILED DESCRIPTION

[0031] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0032] like Figure 1-4As shown, the specific embodiment of the present invention is a bored pile construction control device, including a winch 1 with a drum 2 arranged on one side of the pile hole, the drum 2 is connected to a hammer 4 through a wire rope 3, the hammer 4 is placed in the pile hole 5 of the bored pile, and also includes a rotation sensor 6 arranged on the drum 2 of the winch 1, the rotation sensor 6 is electrically connected to a control terminal 9, and the control terminal 9 is also electrically connected to a timing module. The rotation sensor 6 can measure the cumulative rotation angle α and the rotation direction of the drum 2 during the bored pile construction process in real time, and the hammer 4 is also provided with a correction mechanism 7.

[0033] A control frame 8 is provided on one side of the hoist 1, and a deviation correction mechanism 7 is suspended from the control frame 8 through a suspension rope 801. The steel wire rope 3 passes through the middle of the deviation correction mechanism 7, and the deviation correction mechanism 7 is located directly above the hammer 4.

[0034] The control frame 8 is also provided with a remotely controlled driving motor and a pulley block 802 . The driving motor can drive the suspension rope through the pulley block 802 to drive the deviation correction mechanism to rise and fall.

[0035] The deflection correction mechanism 7 includes a lifting ring 701 and a deflection correction wheel 702. A ring-shaped electromagnet 703 is embedded in the lifting ring 701. A wire hole is also provided on the lifting ring 701. Two or more deflection correction wheels 702 are symmetrically arranged around the lifting ring 701.

[0036] The deflection correction wheel 702 is connected to the hanging ring 701 through a transmission rod 705 and a rotating rod 706. The end of the rotating rod 706 is pivotally connected to the end of the transmission rod 705. The other end of the transmission rod 705 is embedded in the limiting groove of the hanging ring 701. An energy-absorbing spring 707 is also arranged between the transmission rod 705 and the hanging ring 701. The middle part of the rotating rod 706 is connected to the hanging ring 701 through a positioning spring 708.

[0037] The ring body of the correction mechanism of the present application is formed by welding a protective shell and an annular steel plate, and the annular electromagnet is placed in the ring body. The electromagnet wire is led out through the wire hole of the ring body, and the wire hole is sealed by a sealant; the power supply of the annular electromagnet is remotely controlled by the control terminal. When the hammer is lifted, the control terminal controls the annular electromagnet to be energized, and an annular suction force is generated around the shaking hammer to suck the hammer and reduce the centrifugal force generated when the hammer shakes, thereby quickly stabilizing the hammer. After the hammer is stabilized, the control terminal disconnects the power supply of the annular electromagnet, and the hammer can continue to rush in; 4 lifting rings are arranged on the ring body for lifting the correction mechanism into the pile hole, and holes are arranged on the steel plate for the transmission rod to pass through, and an energy-absorbing spring is connected between the steel plate and the transmission rod to dissipate the shaking of the hammer. The energy brought by it can quickly reduce the shaking amplitude; a rotating groove is arranged on the right side of the moving rod, which is connected with the rotating rod, and a rubber pad is bonded between the two, and the rotating rod can rotate through the rotating groove; the rotating rod and the ring body are connected by four positioning springs (one in each of the four directions), and the positioning springs are used to automatically restore the rotating rod that has been rotated; a correcting wheel is arranged on the right side of the rotating rod, which is used for sliding and collision between the correcting mechanism and the wall of the pile hole; the arrangement of the rotating groove, the energy-absorbing spring, the positioning spring and the correcting wheel provides the correcting mechanism with a flexible function, so that when the correcting mechanism hits the wall of the pile hole driven by the shaking of the hammer, it can flexibly buffer and dissipate energy, effectively stabilizing the hammer in a short time while protecting the correcting mechanism from rigid damage due to impact.

[0038] The top of the transmission rod 705 is a ball seat structure, and the top of the rotating rod 706 is a ball head structure. The ball head structure matches the ball seat structure. A damping rubber pad 704 is also provided between the ball head structure and the ball seat structure. The rotating rod 706 can rotate universally around the ball seat structure within a limited angle.

[0039] When in use, the hammer can be quickly stabilized through the correction mechanism, and the shaking of the hammer can be effectively reduced in a short time; the construction personnel can determine the position of the hammer according to the rotation sensor and the control terminal, and quickly control the remote control pulley to accurately lower the correction mechanism to the position of the hammer, thereby improving the construction efficiency; the control terminal receives the data of the rotation sensor in real time, and calculates the hammer's penetration depth, hammer stroke, and hammer penetration speed in real time through the intelligent algorithm; the control terminal monitors the hammer's penetration depth, hammer stroke, and hammer penetration speed in real time according to the formation exploration report, and reflects the formation where the hammer is located, so as to improve the construction efficiency. It can timely predict the soil / rock layer that the hammer is about to penetrate. If bad geology occurs, it can automatically issue an early warning to remind construction personnel to deal with abnormalities in time, improve construction efficiency, and better control the quality of bored cast-in-place piles. The control terminal records the penetration speed, penetration amount and number of penetrations of the hammer in different strata in real time, and generates a data report on the penetration of the hammer in different strata, determines the reference index of the penetration of the hammer in different strata, and is used to guide the subsequent construction of bored cast-in-place piles, further improve the construction efficiency of bored cast-in-place piles, control construction quality, and thus ensure construction safety.

[0040] A method of use, a punching pile construction control device, the specific steps are as follows:

[0041] S1. Installation: Install a control frame above the pile hole, connect the lifting rope on the pulley block to the deviation correction mechanism, and remotely control the lifting rope to rise or fall through the driving motor to make the deviation correction mechanism in the initial position;

[0042] S2, stabilize the hammer. When the construction starts, the winch retracts the hammer upward to the designated position of the pile hole. The construction personnel control the lowering of the correcting mechanism to the hammer position through the remote control, and energize the annular electromagnet to make the correcting mechanism generate annular suction around the hammer. At this time, the shaking of the hammer drives the correcting mechanism to collide with the steel casing at the top of the pile hole. The energy generated by the shaking and collision is dissipated by the correcting mechanism to quickly stabilize the hammer. After stabilization, the power supply of the annular electromagnet is disconnected, and then the hammer is lowered to start the construction. During the lifting and lowering process, the rotation sensor records the cumulative rotation angle α and the rotation direction at this time;

[0043] S3. Calculate, where r is the radius of the drum, Δt is the time required for the hammer to be lifted up and dropped down, and the calculation formula is as follows:

[0044] Length of wire rope moving when hammer is lifted:

[0045] Length of wire rope moving when hammer falls:

[0046] Single hammer penetration: ΔL=L x -L s

[0047] Driving speed:

[0048] Pile hole depth: H = ΔL1 + ΔL2 + ... + ΔL n

[0049] S4: When the ground changes, the preset hammer stroke is used for construction. When the difference between the preset hammer stroke and the actual footage exceeds the threshold, it means that the hammer has entered a different soil or rock layer, and the appropriate stroke needs to be adjusted to match the appropriate footage and footage speed;

[0050] The geological survey information is entered into the control terminal in advance, and the control terminal is set with an automatic early warning function to monitor the hammer's footage, footage speed and pile hole depth in real time. The stratum conditions and the stratum conditions that the hammer is about to enter are predicted based on the pile hole depth. When the hammer is about to enter the next soil or rock layer, the construction personnel are promptly reminded to adjust the hammer stroke and control the footage.

[0051] The system also includes the following steps: S5, early warning, recording the footage and speed of each penetration through the control terminal, and predicting through big data analysis whether there are unfavorable geological conditions such as inclined rocks, isolated rocks or karst caves in the next soil or rock layer that the hammer will penetrate. If there are, the control terminal will issue an early warning in time, and the construction personnel will control the pile driver to gradually reduce the stroke and penetrate, and observe through the camera whether there is obvious deviation of the wire rope at the pile hole;

[0052] When the wire rope is obviously misaligned and the control terminal finds that the hammer advances abnormally, the hammer advances are stopped in time, and a treatment plan is formulated after the inspection is completed; thereby improving construction efficiency and better controlling the quality of bored piles.

[0053] S6. Report: The control terminal records the penetration speed, penetration amount and penetration times of the hammer in different strata in real time, and generates a penetration data report of the hammer in different strata. The penetration data report is uploaded to the server for storage. The reference index of the hammer penetration in different strata is determined. This penetration data report can be used to guide the subsequent construction of bored piles, further improve the construction efficiency of bored piles, control the construction quality, and ensure construction safety.

[0054] This system can quickly stabilize the hammer through the deviation correction mechanism, effectively reduce the shaking of the hammer in a short time, and avoid construction problems such as inclined holes, deviated holes, hammer jams, and even collapsed holes caused by the hammer shaking, thus ensuring the construction quality and efficiency.

[0055] It can monitor the penetration amount, penetration speed and pile hole depth of the bored pile hammer in real time, and predict the ground conditions and the ground conditions that the hammer is about to enter according to the pile hole depth. When the hammer is about to enter the next soil or rock layer, it can promptly remind the construction personnel to adjust the hammer stroke and control the penetration amount.

[0056] It can predict the stratum conditions where the hammer is located according to the stratum survey report and set up automatic early warning function for bad geology;

[0057] The control terminal records the penetration speed, penetration amount and number of penetrations of the hammer in different strata in real time, and generates a data report on the penetration of the hammer in different strata, determines the reference index of the penetration of the hammer in different strata, and is used to guide the subsequent construction of bored cast-in-place piles.

[0058] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any slight modification, equivalent substitution and improvement made to the above embodiment based on the technical essence of the present invention should be included in the protection scope of the technical solution of the present invention.

Claims

1. A method of use, characterized in that: A punching and bored pile construction control device is used, which includes a winch with a drum arranged on one side of the pile hole, the drum is connected to a hammer through a wire rope, the hammer is placed in the pile hole of the bored pile, and also includes a rotation sensor arranged on the drum of the winch, the rotation sensor is electrically connected to a control terminal, the control terminal is also electrically connected to a timing module, the rotation sensor can measure the cumulative rotation angle α and the rotation direction of the drum during the punching and bored pile construction process in real time, and the hammer is also sleeved with a correction mechanism; the correction mechanism includes a lifting ring and a correction wheel, an annular electromagnet is embedded and installed in the lifting ring, a wire hole is also provided on the lifting ring, and more than two correction wheels are symmetrically arranged around the lifting ring; the correction wheel is connected to the lifting ring through a transmission rod and a rotating rod, the end of the rotating rod is pivotally connected to the end of the transmission rod, the other end of the transmission rod is embedded in the limit groove of the lifting ring, an energy-consuming spring is also provided between the transmission rod and the lifting ring, and the middle part of the rotating rod is connected to the lifting ring through a positioning spring; the specific steps are as follows: S1. Installation: Install a control frame above the pile hole, connect the lifting rope on the pulley block to the deviation correction mechanism, and remotely control the lifting rope to rise or fall through the driving motor to make the deviation correction mechanism in the initial position; S2, stabilize the hammer. When the construction starts, the winch retracts the hammer upward to the designated position of the pile hole. The construction personnel control the lowering of the correcting mechanism to the hammer position through the remote control, and energize the annular electromagnet to make the correcting mechanism generate annular suction around the hammer. At this time, the shaking of the hammer drives the correcting mechanism to collide with the steel casing at the top of the pile hole. The energy generated by the shaking and collision is dissipated by the correcting mechanism to quickly stabilize the hammer. After stabilization, the power supply of the annular electromagnet is disconnected, and then the hammer is lowered to start the construction. During the lifting and lowering process, the rotation sensor records the cumulative rotation angle α and the rotation direction at this time; S3. Calculate, where r is the radius of the drum, Δt is the time required for the hammer to be lifted up and dropped down, and the calculation formula is as follows: Length of wire rope moving when hammer is lifted: Length of wire rope moving when hammer falls: Single hammer penetration: ΔL=L x -L s Driving speed: Pile hole depth: H = ΔL1 + ΔL2 + ... + ΔL n S4: When the ground changes, the preset hammer stroke is used for construction. When the difference between the preset hammer stroke and the actual footage exceeds the threshold, it means that the hammer has entered a different soil or rock layer, and the appropriate stroke needs to be adjusted to match the appropriate footage and footage speed; The geological survey information is entered into the control terminal in advance, and the control terminal is set with an automatic early warning function to monitor the hammer's footage, footage speed and pile hole depth in real time. The stratum conditions and the stratum conditions that the hammer is about to enter are predicted based on the pile hole depth. When the hammer is about to enter the next soil or rock layer, the construction personnel are promptly reminded to adjust the hammer stroke and control the footage.

2. The method of use according to claim 1, characterized in that: Also includes the steps: S5, early warning, the control terminal records the footage and speed of each penetration, and uses big data analysis to predict whether there are oblique rocks, isolated rocks or poor geological conditions in the next soil or rock layer that the hammer will penetrate. If so, the control terminal will issue an early warning in time, and the construction personnel will control the pile driver to gradually reduce the stroke and observe through the camera whether the wire rope at the pile hole is obviously deviated; When the wire rope is obviously deviated and the control terminal finds that the hammer penetration is abnormal, stop the hammer penetration in time and formulate a treatment plan after the inspection is completed; S6. Report: The control terminal records the penetration speed, penetration amount and penetration times of the hammer in different strata in real time, and generates a penetration data report of the hammer in different strata. The penetration data report is uploaded to the server for storage.

3. The method of use according to claim 1, characterized in that: A control frame is provided on one side of the winch, and a deviation correction mechanism is suspended from the control frame through a suspension rope, and the steel wire rope passes through the middle of the deviation correction mechanism, and the deviation correction mechanism is located directly above the hammer; The control frame is also provided with a remotely controlled driving motor and a pulley block, and the driving motor can drive the suspension rope through the pulley block to drive the deviation correction mechanism to rise and fall.

4. The method of use according to claim 1, characterized in that: The top of the transmission rod is a ball seat structure, and the top of the rotating rod is a ball head structure. The ball head structure matches the ball seat structure. A damping rubber pad is also arranged between the ball head structure and the ball seat structure. The rotating rod can rotate universally around the ball seat structure within a limited angle.

Citation Information

Patent Citations

  • Device and method for measuring depth of punched cast-in-situ pile

    CN105649119A

  • Method for hole forming of punching pile in karst cave area

    CN110485417A

  • Automatic ramming recording system for height measurement of dynamic compactor

    CN111578878A

  • Boring cast-in-situ pile plagioclase measuring early warning system and method based on video monitoring

    CN111794295A

  • Raised pavement marker reflector impact test device

    CN203101009U