Cable catheter positioning device and cable catheter installation method

By designing a custody positioning device including the fetal frame, positioning skeleton, and adjustment mechanism, the problem of long adjustment and cost in the installation method of the existing cable catheter is solved, and the rapid and accurate installation of the cable catheter is realized, reducing the construction of construction cost.

CN112746562BActive Publication Date: 2025-01-28CHINA COMM 2ND NAVIGATIONAL BUREAU 2ND ENG
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202110014093.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-01-05
Publication Date
2025-01-28
Estimated Expiration
2041-01-05

AI Technical Summary

Technical Problem

In the existing cable conduit installation methods, the crane adjusts the cable conduit position for a long time and is costly, which affects the efficiency and quality of bridge construction.

Method used

Design a type of cable pipeline positioning device, including the fetal frame, positioning skeleton and adjustment mechanism. The fetal frame provides infrastructure and leveling functions. The positioning skeleton is used to fix the cable catheter. The adjustment mechanism can achieve rapid and accurate adjustment of cable catheter through walking racks, rolling wheels, and regulating gourds.

Benefits of technology

Through this device, the installation of cable catheter can be completed quickly and accurately, shorten the adjustment time, reduces construction costs, and improves installation efficiency and accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112746562B_ABST
    Figure CN112746562B_ABST
Patent Text Reader

Abstract

The present invention discloses a cable guide tube positioning device, including a tire frame, a positioning skeleton and an adjustment mechanism. The tire frame includes a basic structure, a leveling column and a horizontal beam, the leveling column is arranged on the basic structure, and the horizontal beam is arranged on the leveling column. The positioning skeleton is arranged on the horizontal beam, and the positioning skeleton is used to position and fix the cable guide tube therein. The adjustment mechanism is movably arranged on the tire frame, and the adjustment mechanism can hoist the cable guide tube to adjust the posture of the cable guide tube on the positioning skeleton. The present invention also discloses a cable guide tube installation method. The cable guide tube positioning device and the cable guide tube installation method use the adjustment mechanism to adjust the position of the cable guide tube, quickly and accurately complete the tooling of the cable guide tube outlet end and the anchoring section, and the installation position can be quickly determined by the plane limit device. The operator can quickly tool the cable guide tube in the back field, reduce the installation operation time on the tower, reduce the risk of high-altitude operations, and have high installation efficiency and precision, thereby reducing production costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a cable conduit positioning device and a cable conduit installation method. Background Art

[0002] In recent years, with the rapid development of bridge engineering construction in my country, bridge construction technology has been changing with each passing day, especially the advantages of using steel truss cable-stayed bridges to cross rivers have become more prominent. The cable guide tube of the cable anchoring system is an important component of it, and its installation and positioning efficiency and accuracy will affect the period and quality of bridge construction.

[0003] At present, the installation process of the cable duct is usually carried out by using the back-end tooling and the front-end installation. The tooling and installation method will determine the quality and efficiency of the cable duct installation. The common tooling method is to make a tooling frame and use cranes and other equipment to install the embedded column feet on the tower and weld them. However, the process of using a crane to adjust the cable duct to achieve control accuracy takes a long time and has high construction costs. Summary of the invention

[0004] Based on this, it is necessary to provide a cable duct positioning device and a cable duct installation method to address the above problems, so as to achieve efficient and accurate installation of the cable duct, thereby shortening the adjustment time and reducing the construction cost.

[0005] A cable catheter positioning device, comprising:

[0006] A tire frame, comprising a basic structure, a leveling column and a horizontal beam, wherein the leveling column is arranged on the basic structure, and the horizontal beam is arranged on the leveling column;

[0007] A positioning frame, disposed on the horizontal beam, the positioning frame being used to position and fix the cable guide tube therein; and

[0008] The adjusting mechanism is movably arranged on the tire frame, and the adjusting mechanism can suspend the cable guide tube to adjust the posture of the cable guide tube on the positioning frame.

[0009] In one of the embodiments, the foundation structure includes a steel foundation and a steel plate surface layer, the steel plate surface layer is arranged on the steel foundation, and the leveling column is arranged on the steel plate surface layer.

[0010] In one embodiment, the positioning frame includes columns, parallel links and diagonal braces, the parallel links connect two adjacent columns, and the diagonal braces are supported between two adjacent columns.

[0011] In one embodiment, the adjustment mechanism includes a traveling frame, a roller and an adjusting hoist. A track is provided on the basic structure. The roller is installed at the bottom of the traveling frame. The roller is movably arranged on the track. The adjusting hoist is arranged on the traveling frame. The adjusting hoist is used to hoist the cable guide tube.

[0012] In one embodiment, the track is provided with two groups, the two groups of the track are arranged at intervals on the basic structure, the walking frame includes a crossbeam and two legs, the two legs are respectively connected to the two ends of the crossbeam, the two legs are both equipped with the rollers, and the rollers on the two legs are respectively movably arranged on the two groups of the track.

[0013] A cable conduit installation method, using any one of the cable conduit positioning devices described above, comprises the following steps:

[0014] Installing the cable guide tube into the positioning frame, and installing the adjusting lug on the cable guide tube;

[0015] The adjusting mechanism adjusts the position of the cable guide tube outlet end, and then fixes the cable guide tube outlet end; the adjusting mechanism moves to the anchoring end of the cable guide tube, and fixes the anchoring end after adjusting it into position;

[0016] Re-test the outlet end and the anchoring end of the cable guide tube, and reinforce the cable guide tube after confirming that they are correct;

[0017] Installing a plane limiting device on the tower, and limiting the positioning frame within the plane limiting device;

[0018] The cable guide tube installed on the tower is retested, and after being confirmed to be correct, the positioning frame is fixed to complete the installation of the cable guide tube.

[0019] In one embodiment, the step of installing the cable guide tube into the positioning frame includes:

[0020] The height difference of the horizontal beam is checked, and then the positioning frame is processed on the horizontal beam.

[0021] In one embodiment, the step of checking the height difference of the horizontal beam and then machining the positioning frame on the horizontal beam further includes:

[0022] The inner diameter of the cable guide tube used in the statistical engineering is calculated, and according to the interval values ​​of various lengths and weights, the cable guide tube positioning device is designed and processed to meet the requirements of cable guide tubes of all specifications.

[0023] In one embodiment, the steps of installing a plane limiting device on the tower and limiting the positioning frame in the plane limiting device are specifically as follows:

[0024] Before installation, the column foot position is laid out on the tower, and after the elevation is adjusted, the plane limiting device is welded, and the column foot of the positioning frame is placed into the plane limiting device.

[0025] In one embodiment, the step of welding the plane limiting device is specifically:

[0026] Column feet are pre-buried on the tower according to the size of the positioning skeleton, steel plates are welded on the column feet, and limiting column feet are welded on the steel plates.

[0027] The above-mentioned cable guide tube positioning device and cable guide tube installation method use an adjustment mechanism to adjust the position of the cable guide tube, quickly and accurately complete the tooling of the cable guide tube outlet end and the anchoring section, and the installation position can be quickly determined through a plane limit device. Operators can quickly tool the cable guide tube in the back field, thereby reducing the installation operation time on the tower, reducing the risk of high-altitude operations, and having high installation efficiency and accuracy, thereby reducing production costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the specific implementation of the present invention, the following will briefly introduce the drawings required for use in the specific implementation. In all the drawings, each element or part is not necessarily drawn according to the actual scale.

[0029] Figure 1 is a schematic structural diagram of a cable catheter positioning device in one embodiment;

[0030] Figure 2 for Figure 1 A top view of the cable catheter positioning device shown;

[0031] Figure 3 for Figure 1 A side view of the cable catheter positioning device shown;

[0032] Figure 4 Flow chart of a cable catheter installation method in one embodiment.

[0033] Reference numerals:

[0034] 10-tire frame, 100-cable guide tube, 110-exit end, 120-anchor end, 12-foundation structure, 122-steel foundation, 124-steel plate surface, 14-leveling column, 16-horizontal beam, 20-positioning frame, 22-column, 24-leveling joint, 26-diagonal brace, 30-adjustment mechanism, 32-traveling frame, 34-roller, 36-adjusting hoist, 38-track. DETAILED DESCRIPTION

[0035] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present invention, so the invention is not limited by the specific implementation disclosed below.

[0036] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only and do not represent the only implementation method.

[0037] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used in the specification of the present invention herein are only for the purpose of describing specific embodiments and are not intended to limit the present invention.

[0038] See also Figure 1 The cable guide tube positioning device in one embodiment is used for quickly and accurately installing the cable guide tube 100. Specifically, the cable guide tube positioning device includes a tire frame 10, a positioning frame 20 and an adjustment mechanism 30.

[0039] The tire frame 10 is used to be placed on the ground or other planes. Specifically, the tire frame 10 includes a base structure 12, a leveling column 14 and a horizontal beam 16. The base structure 12 is set in a place that is convenient for transportation and hoisting, and the base structure 12 can be set on a concrete floor. In one embodiment, the base structure 12 includes a steel foundation 122 and a steel plate surface layer 124. The steel foundation 122 is set on the concrete floor. The number of the steel foundations 122 is multiple, and the multiple steel foundations 122 are arranged at intervals. The steel plate surface layer 124 is set on the steel foundation 122, and the surface of the steel plate surface layer 124 is relatively flat, so that the subsequent horizontal beam 16 can remain horizontal.

[0040] The leveling columns 14 are arranged on the foundation structure 12, and the horizontal beams 16 are arranged on the leveling columns 14. In one embodiment, the leveling columns 14 are arranged on the steel plate surface layer 124. Since the surface of the steel plate surface layer 124 may not be flat enough, the leveling columns 14 can adjust the height difference of the horizontal beams 16. Specifically, the heights of the leveling columns 14 are different so that the horizontal beams 16 can maintain a horizontal state. When it is necessary to adjust the height difference of the horizontal beams 16, the height difference of the horizontal beams 16 can be adjusted by setting pads on the leveling columns 14.

[0041] Please also read Figure 2 and Figure 3 The positioning skeleton 20 is arranged on the horizontal beam 16, and the positioning skeleton 20 can be directly processed on the horizontal beam 16. Of course, the positioning skeleton 20 can also be processed elsewhere and then hoisted onto the horizontal beam 16. The cable guide tube 100 can be loaded into the positioning skeleton 20, and the positioning skeleton 20 is used to position and fix the cable guide tube 100 therein. Specifically, the cable guide tube 100 is loaded into the positioning skeleton 20, and after the position of the cable guide tube 100 is adjusted in place, the position of the cable guide tube 100 can be fixed by using a limiting steel.

[0042] In one embodiment, the positioning frame 20 includes a column 22, a flat link 24, and a diagonal brace 26. The column 22 extends along the length direction of the horizontal beam 16, and the flat link 24 connects two adjacent columns 22, and four flat links 24 form a rectangle. The diagonal brace 26 is supported between two adjacent columns 22 along the length direction of the column 22 to ensure that the positioning frame 20 meets the rigidity of the cable guide 100 for operation and installation on the tower. The positioning frame 20 is trapezoidal so that the cable guide 100 can be installed and positioned at an angle.

[0043] The adjustment mechanism 30 is movably disposed on the tire frame 10, and the adjustment mechanism 30 can hoist the cable guide tube 100 to adjust the posture of the cable guide tube 100 on the positioning frame 20, so that the cable guide tube 100 is in a posture installed on the tower. In one embodiment, the adjustment mechanism 30 includes a traveling frame 32, a roller 34 and an adjustment hoist 36. A track 38 is provided on the base structure 12. Specifically, the track 38 is set on the steel plate surface layer 124. The roller 34 is installed at the bottom of the traveling frame 32, and the roller 34 is movably disposed on the track 38, and the adjustment hoist 36 is installed on the traveling frame 32.

[0044] In one embodiment, two groups of tracks 38 are provided, and the two groups of tracks 28 are arranged at intervals on the steel plate surface layer 124, and the walking frame 32 spans above the positioning frame 20. Specifically, the walking frame 32 includes a crossbeam and two legs, and the two legs are respectively connected to the two ends of the crossbeam, and the two legs are both equipped with rollers 34, and the rollers 34 on the two legs are respectively movably arranged on the two groups of tracks 38.

[0045] The adjusting hoist 36 is arranged on the traveling frame 32, and the adjusting hoist 36 is used to hoist the cable guide tube 100. Specifically, the adjusting hoist 36 is connected with a hook, and the hook can hook the adjusting lug on the cable guide tube 100 to achieve the hoisting of the cable guide tube 100. In one embodiment, the adjusting hoist 36 is arranged on the crossbeam, and the adjusting hoist 36 is a hand chain hoist.

[0046] See also Figure 4 The present invention also provides a cable conduit installation method. To implement the cable conduit 100 construction method, the cable conduit positioning device described above is used. Specifically, the installation method includes the following steps:

[0047] Step S110 : Install the cable guide tube 100 into the positioning frame 20 , and install the adjusting lug on the cable guide tube 100 .

[0048] Specifically, before the cable guide tube 100 is assembled, anchor bars are installed on the cable guide tube 100 in advance to facilitate the transportation and fixation of the cable guide tube 100. Then the cable guide tube 100 is hoisted into the positioning frame 20, and an adjustment lug is welded at the anchor bar of the cable guide tube 100, and the adjustment lug can facilitate the adjustment mechanism 30 to hoist the cable guide tube 100.

[0049] In one embodiment, before the above step S110, the above installation method further includes: statistically analyzing the inner diameters of the cable guide tubes 100 used in the project, and designing and processing a cable guide tube positioning device that meets all specifications of the cable guide tubes 100 according to the interval values ​​of various lengths and weights. Before the cable guide tube 100 is assembled, the height difference of the horizontal beam 16 is checked, and then the positioning frame 20 is processed on the horizontal beam 16.

[0050] Specifically, the horizontality of the horizontal beam 16 can be checked with a level gauge or other instrument to control the height difference error within 2 mm. The positioning frame 20 is designed to meet the rigidity of the cable guide 100 tooling and tower installation. The number of positioning frames 20 can be two, and the two positioning frames 20 are arranged side by side and spaced apart.

[0051] Step S120: the adjustment mechanism 30 adjusts the position of the outlet end 110 of the cable guide tube 100, and then fixes the outlet end 110 of the cable guide tube 100. The adjustment mechanism 30 moves to the anchor end 120 of the cable guide tube 100, adjusts the anchor end 120 to a position, and then fixes it.

[0052] Specifically, according to the measurement instruction, the adjustment hoist 36 is connected to the adjustment lug, and the adjustment mechanism is used to fine-tune the outlet end 110 of the cable guide tube 100 in various directions, and the outlet end 110 of the cable guide tube 100 is fixed after it is adjusted in place. In one embodiment, after the outlet end 110 of the cable guide tube 100 is adjusted in place, two limiting steels are made at the outlet end 110 of the cable guide tube 100, and the limiting steels are angle steels. The outlet end 110 of the cable guide tube 100 is limited between the two limiting steels, and the end face of the cable guide tube 100 abuts against one of the limiting steels.

[0053] Then, the adjustment mechanism 30 is moved to the vicinity of the anchoring end 120 of the cable guide tube 100, and the adjustment mechanism 30 adjusts the position of the anchoring end 120 of the cable guide tube 100, and fixes the anchoring end 120 after the adjustment is in place. In one embodiment, the anchoring end 120 of the cable guide tube 100 is limited by anchor bars.

[0054] Step S130: retest the outlet end 110 and the anchoring end 120 of the cable guide tube 100, and reinforce the cable guide tube 100 after confirming that they are correct.

[0055] Specifically, after the cable guide tube 100 is adjusted in place, the outlet end 110 and the anchor end 120 of the cable guide tube 100 are retested to see if the posture of the cable guide tube 100 meets the requirements. If not, the adjustment mechanism 30 is used to fine-tune the cable guide tube 100 again. After it is correct, anchor bars are used for reinforcement, and the anchor bars are welded to the positioning frame 20 to prevent damage to the outer wall of the cable guide tube 100.

[0056] Step S140: Install a plane limiting device on the tower to limit the positioning frame 20 within the plane limiting device.

[0057] Specifically, before installing the positioning frame 20, the column foot position is laid out on the tower, and after adjusting the elevation, the plane limit device is welded, and the column foot of the positioning frame 20 is placed in the plane limit device to quickly determine the installation position of the positioning frame 20. The higher the accuracy of the positioning frame 20 and the column foot laying accuracy are controlled, the higher the efficiency of installation on the tower.

[0058] In one embodiment, the process of welding the plane limiting device is as follows: pre-embed column feet on the tower according to the size of the positioning frame 20, weld steel plates on the column feet, and weld the limiting column feet on the steel plates to realize the production of the plane limiting device. The limiting column feet are angle steels, and the four corners of the positioning frame 20 are limited in the four angle steels.

[0059] Step S150: retest the cable guide tube 100 installed on the tower, and fix the positioning frame 20 after confirming that it is correct, thereby completing the installation of the cable guide tube 100.

[0060] Specifically, after the installation position of the positioning frame 20 is fixed, the cable guide tube 100 installed on the tower is retested, and after being correct, the column foot of the positioning frame 20 and the limiting column foot are welded together to complete the fixing of the positioning frame 20 and the installation of a set of cable guide tubes 100. Finally, according to the above method, the installation of the entire bridge cable guide tube 100 is completed.

[0061] The cable guide tube positioning device and the cable guide tube installation method utilize the adjustment mechanism 30 to adjust the position of the cable guide tube 100, quickly and accurately locate the tooling of the outlet end 110 of the cable guide tube 100 and the anchoring section, and the installation position can be quickly determined by the plane limit device. The operator can quickly tool the cable guide tube 100 in the back field, thereby reducing the installation operation time on the tower, reducing the risk of high-altitude operations, and having high installation efficiency and accuracy, thereby reducing production costs.

[0062] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and specification of the present invention.

Claims

1. A cable guide installation method using a cable guide positioning device, characterized in that: The cable guide tube positioning device comprises a tire frame, a positioning frame and an adjustment mechanism; The tire frame includes a basic structure, a leveling column and a horizontal beam, wherein the leveling column is arranged on the basic structure, and the horizontal beam is arranged on the leveling column; The positioning frame is arranged on the horizontal beam, and is used to position and fix the cable guide tube therein; the positioning frame comprises a column, a flat link and a diagonal brace, the column extends along the length direction of the horizontal beam, the flat link connects two adjacent columns, four flat links form a rectangle, and the diagonal brace is supported between two adjacent columns; The adjustment mechanism is movably arranged on the tire frame, and the adjustment mechanism can hoist the cable guide tube to adjust the posture of the cable guide tube on the positioning frame; the adjustment mechanism includes a walking frame, a roller and an adjustment hoist, a track is provided on the basic structure, the roller is installed at the bottom of the walking frame, the roller is movably arranged on the track, the adjustment hoist is arranged on the walking frame, and the adjustment hoist is used to hoist the cable guide tube; The installation method includes the following steps: Before the cable guide tube is installed, anchor bars are installed on the cable guide tube in advance, the cable guide tube is installed into the positioning frame, and an adjustment lug is installed on the cable guide tube; The adjusting mechanism adjusts the position of the cable guide tube outlet end, and then fixes the cable guide tube outlet end; the adjusting mechanism moves to the anchoring end of the cable guide tube, and fixes the anchoring end after adjusting it into position; The outlet end and the anchoring end of the cable guide tube are retested, and the cable guide tube is reinforced after being confirmed; specifically, anchor bars are used for reinforcement after being confirmed, and the anchor bars are welded to the positioning frame to prevent damage to the outer wall of the cable guide tube; Installing a plane limiting device on the tower, and limiting the positioning frame within the plane limiting device; Retest the cable guide tube installed on the tower, and fix the positioning frame after confirming that it is correct, thus completing the installation of the cable guide tube; The steps of installing the plane limiting device on the tower and limiting the positioning frame in the plane limiting device are specifically as follows: Before installation, the column foot position is set out on the tower, and after adjusting the elevation, the plane limiting device is welded, and the column foot of the positioning frame is placed into the plane limiting device; The steps of welding the plane limiting device are specifically as follows: Column feet are pre-buried on the tower according to the size of the positioning skeleton, steel plates are welded on the column feet, and limiting column feet are welded on the steel plates.

2. The cable conduit installation method according to claim 1, characterized in that: The foundation structure comprises a steel foundation and a steel plate surface layer, the steel plate surface layer is arranged on the steel foundation, and the leveling column is arranged on the steel plate surface layer.

3. The cable conduit installation method according to claim 1, characterized in that: There are two groups of tracks, and the two groups of tracks are arranged at intervals on the basic structure. The walking frame includes a crossbeam and two legs, and the two legs are respectively connected to the two ends of the crossbeam. The two legs are both equipped with rollers, and the rollers on the two legs are respectively movably arranged on the two groups of tracks.

4. The cable conduit installation method according to claim 1, characterized in that: The step of installing the cable guide tube into the positioning frame includes: The height difference of the horizontal beam is checked, and then the positioning frame is processed on the horizontal beam.

5. The cable conduit installation method according to claim 4, characterized in that: The step of checking the height difference of the horizontal beam and then machining the positioning frame on the horizontal beam also includes: statistically analyzing the inner diameter of the cable guide tube used in the engineering, and designing and machining the cable guide tube positioning device that can meet the requirements of all specifications of cable guide tubes according to the interval values ​​of various lengths and weights.

Citation Information

Patent Citations

  • Method for mounting and rapidly and accurately positioning main tower cable guide pipe of cable-stayed bridge

    CN105113411A

  • Space cable catheter positioning controlling means

    CN206267025U