Comprehensive flexible scheduling method considering dual-equipment collaborative processes
Through collaborative process drive and equipment cross-selection strategies, the scheduling of dual-equipment collaborative processes is optimized, solving the problems of consistency in start and end time and time usage of dual-equipment collaborative processes, improving production efficiency and shortening processing time.
Patent Information
- Application Number
- CN202110571449.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-05-25
- Publication Date
- 2024-10-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing technology has low efficiency when dealing with flexible comprehensive scheduling of dual-equipment collaborative processes. Especially when the equipment cannot complete processing independently, it is difficult to ensure that the start and end time of the process on different equipment are consistent and the processing time is the same.
A comprehensive flexible scheduling method is proposed. Through the collaborative process driving strategy and the equipment cross-selection strategy, collaborative processes are prioritized to ensure that the collaborative processes are processed on the most suitable equipment group, and the earliest completed scheduling plan is selected without conflict, shortening the time Completion time.
It effectively ensures that collaborative processes are processed on the most suitable equipment group as early as possible, shortens the total processing time, improves production efficiency, and achieves the simultaneous completion of dual-equipment collaborative processes.
Smart Images

Figure 210525153612 
Figure 210525153621 
Figure 210525153626
Abstract
Description
Technical Field
[0001] The invention relates to a comprehensive flexible scheduling method considering dual-equipment collaborative processes. Background Art
[0002] There have been studies on comprehensive scheduling methods for processes with multiple equipment, but there are fewer research results on the flexible comprehensive scheduling problem with dual equipment collaboration, and further research is needed. In actual production, there may be processes that a single device cannot complete independently and require two devices to work together. These two devices are called a collaborative equipment group for the process, and the process is allowed to be processed with different processing times on different collaborative equipment groups. The process is required to have the same start processing time, end time, and processing time on the two devices. Summary of the invention
[0003] The purpose of the present invention is to provide a comprehensive flexible scheduling method considering the collaborative process of two equipments; the method sorts the processes in the schedulable process set at the equipment driving moment, and the idle equipment selects the process for scheduling in sequence; the collaborative process in the schedulable process set is scheduled first, and when there is no idle collaborative equipment group at the current equipment driving moment, the idle equipment does not schedule any process, and directly starts the next equipment driving moment, thereby ensuring that the collaborative process has priority in selecting equipment; for equipment with conflicting planned scheduling processes, equipment selection process sets are established respectively, and the processes in the process set cross-select equipment to form a pre-scheduling plan, and the plan that makes the equipment end time early is selected for scheduling, thereby shortening the completion time;
[0004] The above purpose is achieved through the following technical solutions:
[0005] Its feature is that the scheduling method includes the following steps: first, the processes in the schedulable process set at the equipment driving moment are sorted according to the priority order of the collaborative process. If the collaborative process is not unique, the collaborative process with more total processes on the path is scheduled first; secondly, the general processes with collaborative processes on the subsequent paths are sorted according to the number of collaborative processes. If the number of subsequent collaborative processes is the same, they are sorted according to the distance to the collaborative process; finally, the general processes without special processes on the path are sorted according to the total number of processes on the path; when there is a collaborative process in the schedulable process set, the collaborative process driving strategy is adopted to determine the start processing time and processing equipment of the collaborative process; finally, when there is no collaborative process in the schedulable process set or the collaborative process has been scheduled, the idle equipment schedules the general flexible process. When there are two devices with the same planned scheduling process, the equipment cross selection strategy is adopted to determine the processing process for the idle equipment; according to the order of the processes in the schedulable process set, the idle equipment selects the process for scheduling in turn until all processes are scheduled;
[0006] The comprehensive flexible scheduling method considering the dual-equipment collaborative process, the specific implementation steps of the scheduling method are as follows:
[0007] Step 1: Input product process and equipment information to build a flexible processing tree with dual-equipment collaborative processes;
[0008] Step 2: At the initial time T0, all leaf node processes are added to the schedulable process set, and the processes in the schedulable process set are sorted, with collaborative processes being prioritized. Then, general processes with collaborative processes on the subsequent paths are sorted by the number of collaborative processes. If the number of subsequent collaborative processes is the same, they are sorted by the distance to the collaborative processes. Finally, general processes without special processes on the path are sorted by the total number of processes on the path.
[0009] Step 3: In T k At the equipment driving moment, if there is no collaborative process in the schedulable process set or the collaborative process has been scheduled, go to step 5; if not, determine whether there is an idle collaborative equipment group in the first collaborative process. If not, directly start the next equipment driving moment; if yes, go to step 4;
[0010] Step 4: Determine whether the collaborative process can be processed in the collaborative equipment group with the shortest time. If so, schedule the process directly at the driving time of this equipment; if not, calculate and compare T i+1 -T i With t max -t min , if T i+1 -T i <=t max -t min Then schedule the process at this device driving time, otherwise directly start the next device driving time;
[0011] Step 5: Create a set of pending processes for each idle device, sort them in the order of the schedulable process set, and select the first process in the set of pending processes as the scheduled process for the device;
[0012] Step 6: Determine whether the currently idle equipment has a conflicting scheduled process. If not, directly process the scheduled process. If yes, establish equipment selection process sets respectively, cross-select the processes in the process set to form a scheduling plan. If the plan has a conflict between the equipment scheduled process and other equipment, establish the equipment selection process set again to cross-select the equipment, and select the plan that makes the equipment end time earlier among all the scheduling plans.
[0013] Step 7: Take the earliest end time of the processing process as the next equipment driving time, update the schedulable process set, and go to step 3;
[0014] Step 8: Determine whether all the processes in the schedulable process set have been processed. If so, go to step 9; if not, go to step 7;
[0015] Step 9: Output the scheduling Gantt chart and end;
[0016] The dual-device collaborative flexible process is a process that can be processed on different collaborative equipment groups with different processing times. The processes in the collaborative equipment group are required to start and end processing at the same time and have the same processing time.
[0017] The collaborative process driving strategy described above determines the first collaborative process at the equipment driving moment if there is a collaborative process in the schedulable process set: if the collaborative process has no idle collaborative equipment group to process at this equipment driving moment, no process will be scheduled at this equipment driving moment, and the next equipment driving moment will be started directly; if the collaborative process can be processed by the collaborative equipment group with the shortest time, the process will be directly scheduled at this equipment driving moment; if the collaborative process can only be processed by the collaborative equipment group with a longer time, the comparison T will be calculated. i+1 -T i With t max -t min , if T i+1 -T i <=t max -t min Then schedule the process at this device driving time, otherwise directly start the next device driving time;
[0018] The equipment cross selection strategy is that at the equipment driving moment, when there are two equipments whose scheduled scheduling processes are the same process, equipment selection process sets are established respectively, and the processes in the process set cross-select equipment to form a pre-scheduling plan. When there is a plan in which the equipment's scheduled scheduling process is the same as other equipment, an equipment selection process set is established again to cross-select equipment, and finally all scheduling plans are formed, and the plan that makes the equipment end time earlier is selected for scheduling;
[0019] Beneficial effects:
[0020] 1. Aiming at the characteristics of the dual-device collaborative process, the present invention proposes a collaborative process driving strategy. If there is no idle collaborative device group to process in the collaborative process at the current device driving moment, no process will be scheduled at this device driving moment, and the next device driving moment will be started directly; if the collaborative process can be processed by the collaborative device group with the shortest time, the process will be directly scheduled at this device driving moment; if the collaborative process can only be processed by the collaborative device group with a longer time, the T will be calculated and compared. i+1 -T i With t max -t min , if T i+1 -T i <=t max -t min The process is scheduled at this equipment driving time, otherwise the next equipment driving time is started directly, which not only ensures that the collaborative process with higher equipment requirements is processed as soon as possible, but also enables the collaborative process to be scheduled preferentially in the most suitable equipment group;
[0021] 2. The present invention designs a method of cross-selecting idle equipment for processing general flexible processes. When the planned scheduling processes of two devices are the same process, equipment selection process sets are established respectively. The processes in the process set cross-select equipment to form two scheduling schemes. When the planned scheduling process of the equipment is the same as that of other equipment in the scheme, the equipment selection process set is established again to cross-select equipment. Among all the scheduling schemes finally formed, the scheme that makes the equipment end time earlier is selected to shorten the completion time. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Attached Figure 1 It is a flow chart of the comprehensive flexible scheduling method considering the collaborative process of dual equipments of the present invention;
[0023] Attached Figure 2 The flexible processing technology tree of the present invention has dual-equipment collaborative processes;
[0024] Attached Figure 3 The present invention is directed to Figure 2 The Gantt chart of the scheduling results of the process tree shown;
[0025] Attached Figure 4 It is the existing technology for the Figure 2 The Gantt chart of the scheduling results of the process tree shown; DETAILED DESCRIPTION
[0026] Embodiment 1:
[0027] A comprehensive flexible scheduling method considering the collaborative processes of close pairs of equipment is characterized in that: the scheduling method includes the following steps: first, the processes in the schedulable process set at the time of equipment driving are sorted according to the priority order of the collaborative processes. If the collaborative process is not unique, the collaborative process with more total processes on the path is scheduled first; secondly, the general processes with collaborative processes on the subsequent paths are sorted according to the number of collaborative processes. If the number of subsequent collaborative processes is the same, they are sorted according to the distance to the collaborative process; finally, the general processes without special processes on the path are sorted according to the total number of processes on the path; when there is a collaborative process in the schedulable process set, the collaborative process driving strategy is used to determine the start processing time and processing equipment of the collaborative process; finally, when there is no collaborative process in the schedulable process set or the collaborative process has been scheduled, the idle equipment schedules the general flexible process. When there is a planned scheduling process of two devices that is the same process, the equipment cross selection strategy is used to determine the processing process for the idle equipment; according to the order of the processes in the schedulable process set, the idle equipment selects the process for scheduling in turn until all processes are scheduled;
[0028] Embodiment 2:
[0029] Step 1: Input product process and equipment information to build a flexible processing tree with dual-equipment collaborative processes;
[0030] Step 2: At the initial time T0, all leaf node processes are added to the schedulable process set, and the processes in the schedulable process set are sorted, with collaborative processes being prioritized. Then, general processes with collaborative processes on the subsequent paths are sorted by the number of collaborative processes. If the number of subsequent collaborative processes is the same, they are sorted by the distance to the collaborative processes. Finally, general processes without special processes on the path are sorted by the total number of processes on the path.
[0031] Step 3: In T k At the equipment driving moment, if there is no collaborative process in the schedulable process set or the collaborative process has been scheduled, go to step 5; if not, determine whether there is an idle collaborative equipment group in the first collaborative process. If not, directly start the next equipment driving moment; if yes, go to step 4;
[0032] Step 4: Determine whether the collaborative process can be processed in the collaborative equipment group with the shortest time. If so, schedule the process directly at the driving time of this equipment; if not, calculate and compare T i+1 -T i With t max -t min , if T i+1 -T i <=t max -t min Then schedule the process at this device driving time, otherwise directly start the next device driving time;
[0033] Step 5: Create a set of pending processes for each idle device, sort them in the order of the schedulable process set, and select the first process in the set of pending processes as the scheduled process for the device;
[0034] Step 6: Determine whether the currently idle equipment has a conflicting scheduled process. If not, directly process the scheduled process. If yes, establish equipment selection process sets respectively, cross-select the processes in the process set to form a scheduling plan. If the plan has a conflict between the equipment scheduled process and other equipment, establish the equipment selection process set again to cross-select the equipment, and select the plan that makes the equipment end time earlier among all the scheduling plans.
[0035] Step 7: Take the earliest end time of the processing process as the next equipment driving time, update the schedulable process set, and go to step 3;
[0036] Step 8: Determine whether all the processes in the schedulable process set have been processed. If so, go to step 9; if not, go to step 7;
[0037] Step 9: Output the scheduling Gantt chart and end;
[0038] Embodiment 3:
[0039] The dual-device collaborative flexible process is a process that can be processed on different collaborative equipment groups with different processing times. The two devices that can jointly complete a dual-device collaborative process are a collaborative equipment group of the process. The process is required to start and end processing at the same time on the collaborative equipment group, and the processing time is the same;
[0040] The collaborative process driving strategy described above determines the first collaborative process at the equipment driving moment if there is a collaborative process in the schedulable process set: if the collaborative process has no idle collaborative equipment group to process at this equipment driving moment, no process will be scheduled at this equipment driving moment, and the next equipment driving moment will be started directly; if the collaborative process can be processed by the collaborative equipment group with the shortest time, the process will be directly scheduled at this equipment driving moment; if the collaborative process can only be processed by the collaborative equipment group with a longer time, the comparison T will be calculated. i+1 -T i With t max -t min , if T i+1 -T i <=t max -t min Then schedule the process at this device driving time, otherwise directly start the next device driving time;
[0041] The equipment cross selection strategy is to establish a to-be-processed process set consisting of schedulable processes that can be processed on the current equipment for each idle equipment at the equipment driving moment, and sort them in the order of the schedulable process set, select the first process in the to-be-processed process set as the planned scheduling process of the equipment, and when the planned scheduling processes of two equipments are the same process, establish equipment selection process sets for the two equipments, add the process and the next process in the to-be-processed process sets of the two equipments to the set, and cross-select equipment in the equipment selection process set to form a pre-scheduling plan. When the plan scheduling process of the equipment is the same as that of other equipment, establish the equipment selection process set again to cross-select equipment, and finally form all scheduling plans, and select the plan that makes the equipment end time earlier.
[0042] Embodiment 4:
[0043] The above-mentioned comprehensive flexible scheduling method considering the dual-equipment collaborative process is as follows: Figure 1 As shown, it is a product processing flow chart of the present invention, which introduces the product processing process and the method used:
[0044] The following will be combined with the attached Figure 1The product processing flow chart in is used to illustrate the specific execution process of this technology. Processes A1, A10, A13, A18, and A20 are dual-equipment collaborative flexible processes, and processes A2, A3, A4, A5, A6, A7, A8, A9, A11, A12, A14, A15, A16, A17, A19, and A21 are general flexible processes;
[0045] Embodiment 5:
[0046] The above comprehensive flexible scheduling method considering the dual-equipment collaborative process will be used below to target the attached Figure 2 The product processing technology tree diagram shown executes scheduling;
[0047] At the initial time T0=0, the processes in the schedulable process set are A7, A1, A3, A4, A11, A5, and A6. The sorted order is A1, A4, A6, A7, A3, A5, and A11. The collaborative process driving strategy is adopted to prioritize the scheduling of collaborative process A1. The equipment group (M1, M3) with the shortest processing time for A1 is idle. A1 is selected to be scheduled at (M1, M3). Equipment M2 is idle. A set of processes to be processed is established for M2 and sorted: M2: {A4, A7, A5, A11}. Equipment M2 selects the planned scheduling process A4 for scheduling; when T1=5, the processes in the schedulable process set are sorted as follows: A10, A6, A7, A3, A5, and A11. The collaborative process driving strategy is adopted to prioritize the scheduling of collaborative process A10. Equipment M2 is idle. A10 has no idle processing equipment group. Equipment M2 is not scheduled and the next equipment driving time is started directly; when T2=8, the collaborative process A is scheduled first. 10Schedule on the idle equipment group (A1, A3) with the shortest processing time. Equipment M2 is idle, so the planned scheduling process A7 is selected for scheduling; when T3=15, there is no coordinated process in the schedulable process set, and equipment M1 and M3 are idle. The process sets to be processed are established and sorted for the idle equipment M1 and M3 respectively: M1: {A6, A3, A5}, M3: {A6, A2, A3, A11}. The planned scheduling of equipment M1 and M3 both conflict with A6. The equipment cross selection strategy is adopted to establish the equipment selection process sets respectively: M1: {A6, A3}, M3: {A6, A2}, two scheduling plans are formed: M1:A6,M3:A2 and M1:A3,M3:A6; the plan that makes the equipment end time earlier is selected: A6 is processed on M1, and A2 is processed on M3; the scheduling order determined by this method is: A1, A4, A10, A7, A6, A2, A13, A14, A3, A8, A5, A11, A9, A15, A12, A16, A18, A19, A17, A20, A21, and finally the Gantt chart of all process scheduling results is output, as shown in the attached figure. Figure 3 As shown;
[0048] According to the attached Figure 1As shown in the process, this scheduling method is used to Figure 2 The product process tree shown is scheduled until all processes are completed. The scheduling result Gantt chart is as shown in the attached Figure 3 As shown;
[0049] Embodiment 6:
[0050] The above comprehensive flexible scheduling method considering the dual-equipment collaborative process is compared with the following examples:
[0051] The scheduling method of the present invention is compared with an existing method for solving the comprehensive scheduling problem of multiple equipment processes by example.
[0052] Attached Figure 4 In order to use the existing method to solve the comprehensive scheduling problem of multiple equipment processes, Figure 2 The product processing technology tree diagram shown in the figure shows the scheduling Gantt chart; by comparing the attached Figure 3 and attached Figure 4 It can be seen that not only the processing equipment selected for the process is different, but also the scheduling order of the process is different. The scheduling method of the present invention has a good effect on solving the comprehensive flexible scheduling problem of the process with dual equipment collaboration. Figure 4 The completion time of the product scheduled by the method in is 88, while the completion time of the product scheduled by the method of the present invention is 71, which shows that the scheduling method effectively shortens the total processing time;
[0053] Therefore, the scheduling method proposed in the present invention is an optimization of the comprehensive flexible scheduling problem with dual-equipment collaborative processes.
Claims
1. A comprehensive flexible scheduling method considering dual-equipment collaborative processes, characterized by : For flexible dual-equipment collaborative processes, a collaborative process driving strategy is designed to ensure that collaborative processes are scheduled first; for general flexible processes, an equipment cross-selection strategy is designed to complete the process at the current equipment driving moment as early as possible, thereby shortening the product completion time; The specific implementation steps of the scheduling method are as follows: Step 1: Input product process and equipment information to build a flexible processing tree with dual-equipment collaborative processes; Step 2: At the initial time T0, all leaf node processes are added to the schedulable process set, and the processes in the schedulable process set are sorted, with collaborative processes being prioritized. Then, general processes with collaborative processes on the subsequent paths are sorted by the number of collaborative processes. If the number of subsequent collaborative processes is the same, they are sorted by the distance to the collaborative processes. Finally, general processes without special processes on the path are sorted by the total number of processes on the path. Step 3: In T k At the equipment driving moment, if there is no collaborative process in the schedulable process set or the collaborative process has been scheduled, go to step 5; if not, determine whether there is an idle collaborative equipment group in the first collaborative process. If not, directly start the next equipment driving moment; if yes, go to step 4; Step 4: Determine whether the collaborative process can be processed in the collaborative equipment group with the shortest time. If so, schedule the process directly at the driving time of this equipment; if not, calculate and compare T i+1 -T i With t max -t min , if T i+1 -T i <=t max -t min Then schedule the process at this device driving time, otherwise directly start the next device driving time, T i Indicates the current device driving time; T i+1 Indicates the next device driving time; t max Indicates the maximum processing time of the process; t min Indicates the shortest processing time of the process; Step 5: Create a set of pending processes for each idle device, sort them in the order of the schedulable process set, and select the first process in the set of pending processes as the scheduled process for the device; Step 6: Determine whether the currently idle equipment has a conflicting scheduled process. If not, directly process the scheduled process. If yes, establish equipment selection process sets respectively, cross-select the processes in the process set to form a scheduling plan. If the plan has a conflict between the equipment scheduled process and other equipment, establish the equipment selection process set again to cross-select the equipment, and select the plan that makes the equipment end time earlier among all the scheduling plans. Step 7: Take the earliest end time of the processing process as the next equipment driving time, update the schedulable process set, and go to step 3; Step 8: Determine whether all the processes in the schedulable process set have been processed. If so, go to step 9; if not, go to step 7; Step 9: Output the scheduling Gantt chart and end; The dual-device collaborative flexible process is a process that can be processed on different collaborative equipment groups with different processing times. The processes in the collaborative equipment group are required to start and end processing at the same time and have the same processing time. The collaborative process driving strategy is as follows: at the equipment driving moment, if there is a collaborative process in the schedulable process set, the collaborative process is scheduled first; if there is no idle collaborative equipment group for processing the collaborative process at this equipment driving moment, no process is scheduled at this equipment driving moment, and the next equipment driving moment is started directly; if the collaborative process can be processed by the collaborative equipment group with the shortest time, the process is directly scheduled at this equipment driving moment; If the collaborative process can only be processed in a collaborative equipment group with a longer time, calculate the comparison T i+1 -T i With t max -t min , if T i+1 -T i <=t max -t min Then schedule the process at this device driving time, otherwise directly start the next device driving time; The equipment cross-selection strategy is as follows: at the equipment driving moment, when the planned scheduling processes of two devices are the same process, equipment selection process sets are established respectively, and the processes in the process set cross-select equipment to form a pre-scheduling plan. When the planned scheduling process of a device in the plan is the same as that of other devices, an equipment selection process set is established again to cross-select equipment, and finally all scheduling plans are formed, and the plan that makes the equipment end time earlier is selected.
Citation Information
Patent Citations
Multi-factory cooperative scheduling optimization method during equipment manufacturing
CN101916404A
Two-workshop flexible integration scheduling method of buffer process migration in advance
CN106485347A