Power line resource allocation optimization system and method
A technology of resource allocation and optimization method, applied in the direction of instruments, data processing applications, forecasting, etc., can solve the problems of investing a lot of time and resources, low utilization rate of electric power lines, waste of electric power line resources, etc., to improve utilization, improve The effect of construction speed and resource waste reduction
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2021-08-31
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the technical field of electric power dispatching, in particular to a system and method for optimizing resource allocation of electric power dedicated lines. Background technique
[0002] With the improvement of people's living standards, the user's demand for load is also increasing year by year, and the scale of power construction and investment is also increasing. The current power users can be divided into public line users and leased line users. The demand time and quantity of private line users for power supply will continue to change with user needs. Due to its demand, leased line users will inevitably make new applications for power leased line resources. Now the common solution to the request of leased line users is to build new power leased lines for leased line users to use, but rebuilding one or more new power leased lines requires a lot of time and resources. For some leased line users with urgent needs Said that...
Examples
Embodiment
[0031] A method for optimizing power line resource allocation, such as figure 1 shown, including the following steps:
[0032] Step 1, the data acquisition module 1 collects the grid data of each power dedicated line, and the data acquisition module 1 stores the collected grid data to the real-time power grid data storage unit 4;
[0033] Step 2, the data analysis module 3 establishes the evaluation index system of the power dedicated line, and the data analysis module 3 evaluates the energy efficiency according to the power grid data of each power dedicated line through the power dedicated line evaluation index system, and obtains the potential elasticity coefficient corresponding to each power dedicated line, and the control module 2 When allocating power dedicated line resources, give priority to power dedicated lines with high potential elasticity coefficients;
[0034] Step 3, the control module 2 accepts the application request of the power line user, the control module...