Power line resource allocation optimization system and method

A technology of resource allocation and optimization method, applied in the direction of instruments, data processing applications, forecasting, etc., can solve the problems of investing a lot of time and resources, low utilization rate of electric power lines, waste of electric power line resources, etc., to improve utilization, improve The effect of construction speed and resource waste reduction

CN113326988APending Publication Date: 2021-08-31国网浙江省电力有限公司兰溪市供电公司 +1
0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Publication Date
2021-08-31

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention provides an electric power special line resource allocation optimization system and method, the allocation optimization system comprises a data acquisition module, a control module and a data analysis module, wherein the data acquisition module and the data analysis module are both connected with the control module. The distribution optimization method specifically comprises the steps of firstly collecting power grid data of each special power line, then establishing a special power line evaluation index system, then performing energy efficiency condition evaluation according to the special power line evaluation index system, obtaining a potential elastic coefficient of each special power line, and finally receiving an application request of a special power line user by the control module; collecting and analyzing then user power consumption data of the special power line user, and enabling the control module to formulate a power line resource planning optimization scheme according to an analysis result. According to the power special line resource allocation optimization system and method provided by the invention, the requirements of the power special line user are met by utilizing the existing power special line resources, and the utilization rate of the power special line is improved while the solving efficiency of the power special line user request is improved.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the technical field of electric power dispatching, in particular to a system and method for optimizing resource allocation of electric power dedicated lines. Background technique

[0002] With the improvement of people's living standards, the user's demand for load is also increasing year by year, and the scale of power construction and investment is also increasing. The current power users can be divided into public line users and leased line users. The demand time and quantity of private line users for power supply will continue to change with user needs. Due to its demand, leased line users will inevitably make new applications for power leased line resources. Now the common solution to the request of leased line users is to build new power leased lines for leased line users to use, but rebuilding one or more new power leased lines requires a lot of time and resources. For some leased line users with urgent needs Said that...

Examples

Embodiment

[0031] A method for optimizing power line resource allocation, such as figure 1 shown, including the following steps:

[0032] Step 1, the data acquisition module 1 collects the grid data of each power dedicated line, and the data acquisition module 1 stores the collected grid data to the real-time power grid data storage unit 4;

[0033] Step 2, the data analysis module 3 establishes the evaluation index system of the power dedicated line, and the data analysis module 3 evaluates the energy efficiency according to the power grid data of each power dedicated line through the power dedicated line evaluation index system, and obtains the potential elasticity coefficient corresponding to each power dedicated line, and the control module 2 When allocating power dedicated line resources, give priority to power dedicated lines with high potential elasticity coefficients;

[0034] Step 3, the control module 2 accepts the application request of the power line user, the control module...