Low-carbon scheduling method and system for integrated energy system based on carbon trading model

Through the low-carbon dispatching method of the integrated energy system based on the carbon trading model, we construct a comprehensive demand response and carbon trading cost model for electricity and heat, optimize the integrated energy system, solve the problems of low carbon emission control and energy consumption efficiency in the existing technology, and realize the system low-carbon economic operation and effective consumption of renewable energy.

CN113780663BActive Publication Date: 2024-10-25RES INST OF ECONOMICS & TECH STATE GRID SHANDONG ELECTRIC POWER +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111077451.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-09-14
Publication Date
2024-10-25
Estimated Expiration
2041-09-14

AI Technical Summary

Technical Problem

In the existing technology, the low-carbon economic dispatch method of the integrated energy system fails to effectively consider the coordinated optimization of stepped carbon trading and comprehensive demand response, and fails to fully utilize the uncertainty of renewable energy power generation, resulting in carbon emission control and energy consumption efficiency. Low.

Method used

Adopt the low-carbon dispatch method of the integrated energy system based on the carbon trading model to build a comprehensive energy system with source-load coordination, including electric load, heat load, electric energy storage and power-to-gas equipment, and establish a price-based integrated demand response model for electricity and heat and carbon emissions. The interval-segmented stepped carbon transaction cost model solves user energy consumption plans and optimal dispatch plans by optimizing the objective function and constraint conditions, thereby minimizing carbon emissions and improving economic efficiency of the system.

Benefits of technology

It effectively reduces the carbon emissions of the system, improves the operating economy of the system, and promotes the consumption of renewable energy such as wind and solar. It has the advantages of being scientific, reasonable, highly applicable, and effective.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113780663B_ABST
    Figure CN113780663B_ABST
Patent Text Reader

Abstract

The present invention proposes a low-carbon dispatching method and system for an integrated energy system based on a carbon trading model. The method first constructs an integrated energy system architecture that includes multiple renewable energy power generation and multiple energy forms of electricity, heat and gas; then, based on a price-based electricity-heat integrated demand response model and a carbon trading cost model with carbon emission interval segmentation, a two-layer dispatching model for an integrated energy system is constructed with the upper layer aiming at minimizing user energy costs and the lower layer aiming at minimizing purchased energy and carbon trading costs; finally, the CPLEX solver is used to solve the model to obtain a global optimal solution. Based on this method, a low-carbon dispatching system for an integrated energy system based on a carbon trading model is also proposed. The present invention effectively solves the environmental pollution and energy shortage problems of the prior art, improves the operating economy of the system, reduces the carbon emissions of the system, and promotes the consumption of renewable energy sources such as wind and solar. It has the advantages of scientific and reasonable methods, strong applicability and good effects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of low-carbon economic operation of integrated energy systems, and in particular relates to a low-carbon scheduling method and system for integrated energy systems based on a carbon trading model. Background Art

[0002] The rapid economic development has brought tremendous pressure to environmental protection, among which global warming caused by greenhouse gas emissions is an important problem facing the world. According to surveys, carbon dioxide emissions are a key factor in climate warming, and electricity is a key industry in China's energy consumption, accounting for about 50% of the country's total emissions. Therefore, reducing carbon dioxide emissions has become an important research hotspot in power system dispatching. In this context, the integrated energy system (IES) integrates multiple energy forms such as electricity, heat, and gas at the same time. It is an integrated energy production, supply, and marketing system that coordinates all aspects of energy production, transmission, and consumption. Building IES is an important technical means to increase the proportion of renewable energy consumption and control carbon dioxide emissions. It has great practical significance for promoting energy transformation and ensuring the low-carbon economic operation of the system. The carbon trading mechanism can guide IES to transition from high-emission energy consumption to low-emission energy consumption. It is an important technical means to take into account the economic and environmental protection of electricity and low-carbon. It has significant technical advantages in application fields such as large-scale new energy access and new urban power grid construction. In addition, comprehensive demand response, as an effective means to stimulate user energy flexibility, is also of great significance to improving system economy and energy conservation and emission reduction.

[0003] In the existing technology, the carbon trading adopted for the scheduling problem of IES low-carbon economy is mostly traditional carbon trading with fixed transaction prices, and there is rarely any flexible adjustment of heat load demand response according to the changes in thermal comfort demand of users in different time periods. So far, there is no literature report or practical application of IES scheduling method that considers the coordinated optimization of step-by-step carbon trading and comprehensive demand response and takes into account the uncertainty of renewable energy generation. Summary of the invention

[0004] In order to solve the above technical problems, the present invention proposes a low-carbon scheduling method and system for an integrated energy system based on a carbon trading model. It has the advantages of being scientific and reasonable, being able to improve the operating economy of the system, effectively reducing the carbon emissions of the system, promoting the absorption capacity of renewable energy such as wind and solar, and having strong applicability and good effect. To achieve the above purpose, the present invention adopts the following technical solutions:

[0005] The low-carbon dispatch method of the integrated energy system based on the carbon trading model includes the following steps:

[0006] Constructing a source-load coordinated integrated energy system; the integrated energy system includes electric load, heat load, electric energy storage device and power-to-gas equipment; based on the integrated energy system, establishing an upper-level model of the integrated energy system, the upper-level model includes a price-based electric-heat integrated demand response model, an upper-level scheduling model of the integrated energy system and the minimum heating amount of users;

[0007] Inputting initial parameters of the upper-level scheduling model of the integrated energy system, solving the upper-level scheduling model of the integrated energy system, and obtaining the energy consumption plan of the user;

[0008] Establishing a lower-level model of an integrated energy system; the lower-level model includes a stepped carbon trading cost model for carbon emission interval segmentation and a lower-level scheduling model for an integrated energy system;

[0009] When the user energy consumption plan satisfies the first constraint, the user energy consumption plan is used as the load demand of the lower scheduling model of the integrated energy system;

[0010] The rotating reserve constraint is deterministically transformed, the initial parameters of the lower-level scheduling model of the integrated energy system are input, the lower-level scheduling model of the integrated energy system is solved to obtain the optimal cost of the integrated energy system, and the optimal scheduling plan is output when the optimal cost satisfies the second constraint.

[0011] Furthermore, the establishment of the price-based electric and thermal integrated demand response model includes making full use of the coupling and complementary relationship between electric energy and thermal energy, and establishing a mathematical model for time-shifting electric load and a mathematical model for reducing thermal load respectively;

[0012] The mathematical model of the time-shiftable electric load is: L,t =P FL,t +P SL,t ; then P L,t is the total power load of the user in period t; P SL,t is the user's time-shiftable power load in period t;

[0013] The mathematical model for reducing heat load is: H L,t =H OL,t -H CL,t ; then H L,t H is the heat load power after the user reduces it in period t; OLt H is the heat load power of the user before reduction in period t; CL,t Reduce the heat load power for users during period t.

[0014] Furthermore, the method for establishing the upper-level scheduling model of the integrated energy system includes:

[0015] The optimization objective function of the integrated energy system is constructed with the goal of minimizing the user's energy cost. The expression of the optimization objective function is:

[0016]

[0017] Among them, F1 is the energy cost of the user; μ t is the time-of-use electricity price; t is the time-sharing heating price; κ is the penalty factor that describes the user's thermal comfort requirements; κ(H CL,t ) 2 The penalty cost for users due to the decrease in thermal comfort caused by reducing heating load;

[0018] Determine the first constraint condition; the first constraint condition includes a time-shiftable electric load constraint, a reducible heat load constraint, and a thermal sensation average prediction index constraint; wherein the expression of the time-shiftable electric load constraint is:

[0019] in is the minimum value of the load that can be shifted in time period t; is the maximum value of the load that can be shifted in time period t; α is the proportion of the load that can be shifted in time;

[0020] The expression for the heat load reduction constraint is:

[0021] The expression of the thermal sensation average prediction index constraint is:

[0022]

[0023] Furthermore, the method for obtaining the minimum heat supply of the user includes:

[0024] According to the relationship between the average prediction index of thermal sensation and indoor temperature, the minimum indoor thermal comfort temperature acceptable to users can be obtained.

[0025] Where M is the energy metabolism rate of the human body; I cl is the thermal resistance of clothing; T s is the average temperature of human skin in a comfortable state; is the indoor temperature during period t;

[0026] The minimum heating supply for the user is obtained according to the minimum indoor thermal comfort temperature acceptable to the user; the heating supply is expressed as:

[0027] in, is the indoor temperature during the period t-1; T t outis the outdoor temperature at time t; K is the comprehensive heat transfer coefficient of the building; F is the surface area of ​​the building; V is the volume of the building; C air is the specific heat capacity of indoor air; ρ air is the density of indoor air; Δt is the time interval.

[0028] Furthermore, the method of inputting the initial parameters of the upper-level scheduling model of the integrated energy system, solving the upper-level scheduling model of the integrated energy system, and obtaining the energy consumption plan of the user is:

[0029] The initial parameters of the upper-level scheduling model of the integrated energy system are input, and the upper-level scheduling model of the integrated energy system is solved by using the CPLEX solver to obtain the user's energy consumption plan; the initial parameters of the upper-level scheduling model of the integrated energy system include the predicted value of electric load, outdoor temperature, time-of-use electricity price, heat price parameters, building parameters, number of scheduling periods, upper limits of each optimization variable, and lower limits of each optimization variable.

[0030] Furthermore, the method for establishing the step-by-step carbon trading cost model for carbon emission interval segmentation includes:

[0031] Constructing the actual carbon emissions expression of the system

[0032]

[0033] Among them, δ GT is the carbon emission intensity of the gas turbine; δ GB is the carbon emission intensity of the gas boiler; be is the carbon emission intensity of purchased electricity; P2G is the carbon capture intensity of the power-to-gas plant; P P2G,t is the electric power of the power-to-gas equipment in period t; β is the conversion coefficient of the power supply of the gas turbine, P GT,t is the power supply of the gas turbine in period t; H GT,t is the heat supply of the gas turbine during period t; H GB,t P is the thermal power provided by the gas boiler during period t; be,t is the purchased electric energy power in period t; T is a scheduling cycle;

[0034] Construct the total carbon emission quota expression of the system

[0035]

[0036] Where B is the total carbon emission quota of the system; λ GT is the quota coefficient of the gas turbine; GB is the quota coefficient of the gas boiler; be is the quota coefficient of purchased electricity;

[0037] Constructing a ladder-type carbon trading cost calculation model:

[0038]

[0039] Among them, F c is the carbon trading cost; σ is the basic carbon trading price; ω is the increase in the carbon trading price when the system is sold; ε is the increase in the carbon trading price when purchasing carbon emission rights; p is the step size of the carbon emission interval.

[0040] Furthermore, the method for establishing the lower-level scheduling model of the integrated energy system includes:

[0041] The optimization objective is to minimize the sum of the cost of purchasing electricity and natural gas from the integrated energy system and the cost of carbon trading. The optimization objective function is:

[0042]

[0043] Among them, F2 is the total cost of the integrated energy system; F be F is the cost of purchased electricity; bg is the natural gas cost; θ be is the price of purchased electricity; θ bg is the price of natural gas; The price of purchasing spinning reserve from the upstream power grid; P is the price of purchasing spinning reserve from the gas grid; be,t The power purchased from the upper power grid during period t; R be,t is the spinning reserve power during period t; R GT,t The reserve power provided by the gas turbine for period t; Provides gas-to-electricity efficiency for the gas turbine during period t; η P2G is the energy conversion efficiency of the power-to-gas equipment; η GB is the energy conversion efficiency of the gas boiler; Q g It is the low calorific value of natural gas;

[0044] Determine a second constraint condition; the second constraint condition includes an energy balance constraint, a gas turbine constraint, a gas boiler constraint, a power-to-gas equipment constraint, an electric energy storage constraint, a spinning reserve constraint, and an external network constraint;

[0045] Energy balance constraints include electrical power balance constraints and thermal power balance constraints.

[0046] The expression of energy balance constraint is: P REG,t is the predicted output value of renewable energy in period t; P CH,t P is the charging power of the energy storage during period t; DC,t is the discharge power of the energy storage during period t;

[0047] Gas turbine constraints include unit output constraints and ramp constraints.

[0048] The expression of gas turbine constraint is: The upper limit of gas turbine output; It is the lower limit of gas turbine output; is the maximum downward ramp rate of the gas turbine; is the maximum upward ramp rate of the gas turbine; π is the thermal-electric ratio of the gas turbine;

[0049] Gas boiler constraints include output constraints and ramp constraints of gas boilers;

[0050] The expression of gas boiler constraint is: It is the upper limit of the thermal output of the gas boiler; It is the lower limit of the thermal output of the gas boiler; is the maximum downward ramp rate of the gas boiler; is the maximum upward climbing rate of the gas boiler;

[0051] The expression of the power-to-gas equipment constraint is: is the maximum power of the power-to-gas equipment;

[0052] Electric energy storage constraints, including electric energy storage output constraints and capacity constraints;

[0053] The expression of the electric energy storage constraint is S max is the maximum capacity of electrical energy storage; S min is the minimum capacity of electrical energy storage; S (0) is the initial capacity of the energy storage device cycle; S (end) The capacity of the electrical energy storage device at the end; is the maximum charging power; γ CH For maximum charging efficiency; is the maximum discharge power; γ DC Maximum discharge efficiency;

[0054] Spinning reserve constraints, including gas turbine reserve constraints, purchased power reserve constraints, electric energy storage reserve constraints, and spinning reserve opportunity constraints;

[0055] The expression of the spinning reserve constraint is: P t W is the actual output value of the fan during period t; P t PV is the actual output value of photovoltaic power during period t; P r is the probability of the event being true; ψ is the confidence level;

[0056] External network constraints, including constraints on purchased electricity and natural gas;

[0057] The expression of the external network constraint is: The upper limit of purchased electricity; It is the lower limit of purchased electricity; The upper limit of natural gas purchase; It is the lower limit for purchasing natural gas.

[0058] Furthermore, the method of inputting the initial parameters of the lower-level scheduling model of the integrated energy system and solving the lower-level scheduling model of the integrated energy system includes: inputting the initial parameters of the lower-level scheduling model of the integrated energy system, and using the CPLEX solver to solve the lower-level scheduling model of the integrated energy system; wherein the initial parameters of the lower-level scheduling model of the integrated energy system include: gas turbine parameters, gas boiler parameters, energy storage parameters, renewable energy prediction values, the number of scheduling time periods, the upper limit value of each optimization variable, and the lower limit value of each optimization variable.

[0059] Furthermore, the output optimal scheduling plan includes the numerical values ​​corresponding to the variables to be optimized and the optimized scheduling plan of the comprehensive energy system of the optimization objective function value.

[0060] The present invention also proposes a low-carbon dispatching system for an integrated energy system based on a carbon trading model, the system comprising a first building module, a first solution model, a second building module, an input module, and a second solution module;

[0061] The first building module is used to build a source-load coordinated integrated energy system; the integrated energy system includes electric load, thermal load, electric energy storage device and power-to-gas equipment; based on the integrated energy system, an upper model of the integrated energy system is established, and the upper model includes a price-based electric-heat integrated demand response model, an upper scheduling model of the integrated energy system and the minimum heating amount of the user;

[0062] The first solving module is used to input the initial parameters of the upper-level scheduling model of the integrated energy system, solve the upper-level scheduling model of the integrated energy system, and obtain the energy consumption plan of the user;

[0063] The second construction module is used to establish a lower-level model of the integrated energy system; the lower-level model includes a stepped carbon trading cost model for carbon emission interval segmentation and a lower-level scheduling model for the integrated energy system;

[0064] The input module is used to use the user energy consumption plan as the load demand of the lower scheduling model of the integrated energy system under the condition that the user energy consumption plan meets the first constraint;

[0065] The second solving module is used to deterministically transform the rotating reserve constraint, input the initial parameters of the lower-level scheduling model of the integrated energy system, solve the lower-level scheduling model of the integrated energy system, obtain the optimal cost of the integrated energy system, and output the optimal scheduling plan when the optimal cost satisfies the second constraint condition.

[0066] The effects provided in the content of the invention are only the effects of the embodiments, not all the effects of the invention. One of the above technical solutions has the following advantages or beneficial effects:

[0067] The present invention proposes a low-carbon scheduling method and system for an integrated energy system based on a carbon trading model, comprising the following steps: the method comprises constructing an integrated energy system with coordinated sources and loads; the integrated energy system comprises electric load, heat load, electric energy storage device and electric-to-gas equipment; based on the integrated energy system, an upper model of the integrated energy system is established, the upper model comprises a price-type electric-heat integrated demand response model, an upper scheduling model of the integrated energy system and a minimum heating amount of the user to be obtained; the initial parameters of the upper scheduling model of the integrated energy system are input, the upper scheduling model of the integrated energy system is solved, and the energy consumption plan of the user is obtained; a lower model of the integrated energy system is established; the lower model comprises a stepped carbon trading cost model with segmented carbon emission intervals and a lower scheduling model of the integrated energy system; when the user's energy consumption plan meets the first constraint, the user's energy consumption plan is used as the load demand of the lower scheduling model of the integrated energy system; the rotating reserve constraint is deterministically transformed, the initial parameters of the lower scheduling model of the integrated energy system are input, the lower scheduling model of the integrated energy system is solved, and the optimal cost of the integrated energy system is obtained, and when the optimal cost meets the second constraint, the optimal scheduling plan is output. A low-carbon dispatching method for an integrated energy system based on a carbon trading model is also proposed, and a low-carbon dispatching system for an integrated energy system based on a carbon trading model is also proposed. The present invention first constructs an integrated energy system architecture that contains multiple renewable energy power generation and multiple energy forms of electricity, heat and gas; then, based on a price-based electricity-heat integrated demand response model and a carbon trading cost model with carbon emission interval segmentation, a two-layer dispatching model for an integrated energy system is constructed with the upper layer aiming at minimizing the user's energy cost and the lower layer aiming at minimizing the purchased energy and carbon trading costs; finally, the CPLEX solver is used to solve the model to obtain a global optimal solution, which effectively solves the environmental pollution and energy shortage problems of the prior art, improves the operating economy of the system, reduces the carbon emissions of the system, and promotes the consumption of renewable energy such as wind and solar power, and has the advantages of scientific and reasonable methods, strong applicability and good effects. BRIEF DESCRIPTION OF THE DRAWINGS

[0068] like Figure 1 This is a flow chart of a low-carbon scheduling method for an integrated energy system based on a carbon trading model proposed in Example 1 of the present invention;

[0069] Figure 2 is a schematic diagram of the IES structure in Example 1 of the present invention;

[0070] Figure 3 This is a schematic diagram of the time-sharing limitation of the PMV indicator in Example 1 of the present invention;

[0071] Figure 4 It is a schematic diagram of the comparison between the unit output and the total output of purchased electric energy in Example 1 of the present invention;

[0072] Figure 5 Schematic diagram of the total amount of heat load reduction and carbon emissions changing with the penalty factor in Example 1 of the present invention;

[0073] Figure 6 This is a schematic diagram of the carbon emissions and system costs changing with the carbon trading price in Example 1 of the present invention;

[0074] Figure 7 This is a schematic diagram of a low-carbon scheduling system for an integrated energy system based on a carbon trading model proposed in Example 1 of the present invention. DETAILED DESCRIPTION

[0075] In order to clearly illustrate the technical features of the present solution, the present invention is described in detail below through specific implementation methods and in conjunction with the accompanying drawings. The disclosure below provides many different embodiments or examples for realizing different structures of the present invention. In order to simplify the disclosure of the present invention, the components and settings of specific examples are described below. In addition, the present invention may repeat reference numbers and / or letters in different examples. This repetition is for the purpose of simplification and clarity, and does not itself indicate the relationship between the various embodiments and / or settings discussed. It should be noted that the components illustrated in the accompanying drawings are not necessarily drawn to scale. The present invention omits the description of known components and processing techniques and processes to avoid unnecessary limitations on the present invention.

[0076] Example 1

[0077] The low-carbon scheduling method for an integrated energy system based on a carbon trading model proposed in Example 1 of the present invention can effectively solve the problems of environmental pollution and energy shortage. Figure 1 A flow chart of a low-carbon scheduling method for an integrated energy system based on a carbon trading model according to Embodiment 1 of the present invention is given.

[0078] Start working on the process;

[0079] A source-load coordinated IES architecture is constructed, wherein IES is an integrated energy system, and the constructed IES architecture includes electric load, thermal load, electric energy storage device and P2G equipment, wherein the P2G equipment is power-to-gas (P2G) equipment. Figure 2It is a schematic diagram of the IES structure in Example 1 of the present invention; the IES architecture includes electric load, thermal load, electric energy storage device and P2G equipment, wherein the electric load is borne by wind turbines, photovoltaics, gas turbines and purchased electricity, the thermal load is borne by gas turbines and gas boilers, the electric energy storage device improves the flexibility of system operation by storing and releasing electric energy, and the P2G device converts electric energy into natural gas to provide natural gas energy for gas turbines and gas boilers.

[0080] A price-based electricity-heat integrated demand response model is established. The integrated demand response in the established electricity-heat integrated demand response model makes full use of the coupling and complementary relationship between electricity and thermal energy, and establishes mathematical models for time-shiftable electricity loads and heat loads that can be reduced, including:

[0081] A mathematical model of time-shiftable load is established. In addition to fixed load, there is also a part of time-shiftable load that can autonomously adjust power and time according to electricity price information to reduce energy costs of users. Assume P L,t is the total electricity load of the user in period t, then the mathematical model of the user's time-shiftable electricity load is shown in formula (1):

[0082] P L,t =P FL,t +P SL,t ; (1)

[0083] Then P L,t is the total power load of the user in period t; P SL,t is the user's time-shiftable electricity load in period t.

[0084] A mathematical model for reducing heat load is established. The heat demand of users is fuzzy. Users can reduce a certain amount of heating load within an acceptable range according to their own requirements for thermal comfort, thereby reducing the user's energy cost and the system's carbon emissions. Assume H L,t is the heat load power after the user reduces it in period t, then the mathematical model for reducing the heat load is shown in formula (2):

[0085] H L,t =H OL,t -H CL,t ; (2)

[0086] Then H L,t H is the heat load power after the user reduces it in period t; OL,t H is the heat load power of the user before reduction in period t; CL,t Reduce the heat load power for users during period t.

[0087] The IES upper-level scheduling model is constructed with the goal of minimizing the user's energy cost. The construction process of the IES upper-level scheduling model includes the following steps: constructing the expression of the optimization objective function, selecting the optimization target, and in order to fully mobilize users to actively participate in the comprehensive demand response, the objective function of the IES upper-level scheduling model is set to minimize the user's energy cost. Let F1 be the user's energy cost, then the expression of the optimization objective function is shown in formula (3):

[0088]

[0089] Among them, F1 is the energy cost of the user; μ t is the time-of-use electricity price; t is the time-sharing heating price; κ is the penalty factor that describes the user's thermal comfort requirements; κ(H CL,t ) 2 The penalty cost for users due to the decrease in thermal comfort caused by reducing heating load;

[0090] Determine the constraints. The constraints of the IES upper-level scheduling model include time-shiftable load constraints, reducible heat load constraints, and PMV index constraints. Determine the time-shiftable load constraints, which include total load proportion constraints and power constraints for each time period.

[0091]

[0092] in is the minimum value of the load that can be shifted in time period t; is the maximum value of the load that can be shifted in time period t; α is the proportion of the load that can be shifted in time;

[0093] Determine the heat load constraints that can be reduced, set is the minimum value of the heating load in period t, then the heat load constraint can be reduced as shown in formula (5):

[0094] Determine the PMV index constraint. Since users are in a sleeping state at night and are less sensitive to thermal sensation than during the day, this paper sets a time-sharing limit on the PMV value within a scheduling cycle. The PMV index constraint is shown in formula (6):

[0095] Among them, PMV is the mean prediction of thermal sensation.

[0096] The minimum heating demand of users is obtained according to the PMV index, and obtaining the minimum heating demand of users includes obtaining the minimum indoor thermal comfort temperature acceptable to users and obtaining the heat load expression, specifically including obtaining the minimum indoor thermal comfort temperature acceptable to users. The minimum indoor thermal comfort temperature acceptable to users can be obtained according to the relationship between the PMV index and the indoor temperature. The relationship is shown in formula (7):

[0097]

[0098] Where M is the energy metabolism rate of the human body; I cl is the thermal resistance of clothing; T s is the average temperature of human skin in a comfortable state; T t in is the indoor temperature during period t;

[0099] The heat load expression is obtained. The transient heat balance equation of the building can describe the effect of the change of heat supply on the indoor temperature. By linking heat and temperature, the required heat supply can be obtained according to the indoor temperature. Let H L,t is the heat load power after the user reduces heat load in period t. Then, the transient heat balance equation can be transformed and solved to obtain the heat load expression as shown in formula (8):

[0100]

[0101] in, is the indoor temperature during the period t-1; T t out is the outdoor temperature at time t; K is the comprehensive heat transfer coefficient of the building; F is the surface area of ​​the building; V is the volume of the building; C air is the specific heat capacity of indoor air; ρ air is the density of indoor air; Δt is the time interval.

[0102] The initial parameters of the IES upper-level scheduling model are input, and the CPLEX solver is used to solve the IES upper-level scheduling model to obtain the user energy consumption plan data and generate an upper-level solution. The initial parameters input into the IES upper-level scheduling model include the predicted value of electric load, outdoor temperature, time-of-use electricity price and heat price parameters, building parameters, number of scheduling periods, and the upper and lower limits of each optimization variable.

[0103] Check whether the upper solution satisfies the first constraint. If the first constraint is satisfied, the user energy consumption plan is used as the load demand of the lower scheduling model of the integrated energy system; wherein the first constraint is:

[0104] and

[0105]

[0106] Construct a step-by-step carbon trading cost model for carbon emission interval segmentation, where step-by-step carbon trading refers to dividing carbon emissions into multiple intervals for carbon trading. When the actual carbon emissions are greater than the carbon emission quota, the carbon emission source needs to purchase carbon emission quotas from the carbon trading market. The more CO2 emissions there are in the interval, the higher the carbon trading price. Conversely, when the actual carbon emissions are less than the carbon emission quota, the carbon emission source sells carbon emission quotas to the carbon trading market. The smaller the CO2 emissions are, the higher the carbon trading price is. Constructing a step-by-step carbon trading cost model for carbon emission interval segmentation includes constructing an expression for the actual carbon emissions of the system, constructing an expression for the total carbon emission quota of the system, and constructing a step-by-step carbon trading cost calculation model. The specific steps include:

[0107] Construct the expression of the actual carbon emissions of the system. There are three sources of carbon emissions in the system, namely gas turbines, gas boilers and purchased electricity. At the same time, the P2G equipment absorbs CO2 as raw material during the power-to-gas process to offset part of the CO2 emitted by the carbon emission source. Let D be the actual carbon emissions of the system, then the expression of the actual carbon emissions of the system is as follows:

[0108]

[0109] Among them, δ GT is the carbon emission intensity of the gas turbine; δ GB is the carbon emission intensity of the gas boiler; be is the carbon emission intensity of purchased electricity; P2G is the carbon capture intensity of the power-to-gas plant; P P2G,t is the electric power of the power-to-gas equipment in period t; β is the conversion coefficient of the power supply of the gas turbine, P GT,t is the power supply of the gas turbine in period t; H GT,t is the heat supply of the gas turbine during period t; H GB,t P is the thermal power provided by the gas boiler during period t; be,t is the purchased electric energy power in period t; T is a scheduling cycle;

[0110] Construct the total carbon emission quota expression of the system, which corresponds to the system carbon emission source. The total carbon emission quota of the system is composed of the carbon emission quotas of gas turbines, gas boilers and purchased electricity. Let B be the total carbon emission quota of the system. The total carbon emission quota expression of the system is shown in formula (10):

[0111]

[0112] Where B is the total carbon emission quota of the system; λ GT is the quota coefficient of the gas turbine; GB is the quota coefficient of the gas boiler; beis the quota coefficient of purchased electricity;

[0113] A step-by-step carbon trading cost calculation model is constructed. When B>D, it is negative, and when B<D, it is positive. The step-by-step carbon trading cost calculation model is shown in formula (11):

[0114]

[0115] Among them, F c is the carbon trading cost; σ is the basic carbon trading price; ω is the increase in the carbon trading price when the system is sold; ε is the increase in the carbon trading price when purchasing carbon emission rights; p is the step size of the carbon emission interval.

[0116] The IES lower-level dispatch model is constructed with the goal of minimizing the cost of purchased energy and carbon trading. The construction process of the IES lower-level dispatch model includes selecting optimization objectives and determining constraints. The specific steps are as follows:

[0117] Select the optimization target, and choose the minimum sum of IES purchased electricity and natural gas energy costs and carbon trading costs as the optimization target. Considering the randomness of renewable energy generation, use electric energy storage, gas turbines and purchased electricity to provide spinning reserve for the system. Let F2 be the total cost of IES, then the expression of the optimization objective function is shown in formula (12):

[0118]

[0119] Among them, F2 is the total cost of the integrated energy system; F be F is the cost of purchased electricity; bg is the natural gas cost; θ be is the price of purchased electricity; θ bg is the price of natural gas; The price of purchasing spinning reserve from the upstream power grid; P is the price of purchasing spinning reserve from the gas grid; be,t The power purchased from the upper power grid during period t; R be,t is the spinning reserve power during period t; R GT,t The reserve power provided by the gas turbine for period t; Provides gas-to-electricity efficiency for the gas turbine during period t; η P2G is the energy conversion efficiency of the power-to-gas equipment; η GB is the energy conversion efficiency of the gas boiler; Q g It is the low calorific value of natural gas;

[0120] Determine a second constraint condition; the second constraint condition includes an energy balance constraint, a gas turbine constraint, a gas boiler constraint, a power-to-gas equipment constraint, an electric energy storage constraint, a spinning reserve constraint, and an external network constraint;

[0121] Energy balance constraints include electrical power balance constraints and thermal power balance constraints.

[0122] The expression of energy balance constraint is:

[0123] P REG,t is the predicted output value of renewable energy in period t; P CH,t P is the charging power of the energy storage during period t; DC,t is the discharge power of the energy storage during period t;

[0124] Gas turbine constraints include unit output constraints and ramp constraints.

[0125] The expression of gas turbine constraint is:

[0126] The upper limit of gas turbine output; It is the lower limit of gas turbine output; is the maximum downward ramp rate of the gas turbine; is the maximum upward ramp rate of the gas turbine; π is the thermal-electric ratio of the gas turbine;

[0127] Gas boiler constraints include output constraints and ramp constraints of gas boilers;

[0128] The expression of gas boiler constraint is:

[0129] It is the upper limit of the thermal output of the gas boiler; It is the lower limit of the thermal output of the gas boiler; is the maximum downward ramp rate of the gas boiler; is the maximum upward climbing rate of the gas boiler;

[0130] The expression of the power-to-gas equipment constraint is:

[0131] is the maximum power of the power-to-gas equipment;

[0132] Electric energy storage constraints, including electric energy storage output constraints and capacity constraints;

[0133] The expression of the electric energy storage constraint is

[0134] S max is the maximum capacity of electrical energy storage; S min is the minimum capacity of electrical energy storage; S (0) is the initial capacity of the energy storage device cycle; S (end) The capacity of the electrical energy storage device at the end; is the maximum charging power; γ CH For maximum charging efficiency; is the maximum discharge power; γ DC Maximum discharge efficiency;

[0135] Spinning reserve constraints, including gas turbine reserve constraints, purchased power reserve constraints, electric energy storage reserve constraints, and spinning reserve opportunity constraints;

[0136] The expression of the spinning reserve constraint is:

[0137]

[0138] P t W is the actual output value of the fan during period t; P t PV is the actual output value of photovoltaic power during period t; P r is the probability of the event being true; ψ is the confidence level;

[0139] External network constraints, including constraints on purchased electricity and natural gas;

[0140] The expression of the external network constraint is:

[0141] The upper limit of purchased electricity; It is the lower limit of purchased electricity; The upper limit of natural gas purchase; It is the lower limit for purchasing natural gas.

[0142] The user energy consumption plan obtained by solving the IES upper-level scheduling model is used as the load demand of the IES lower-level scheduling model, where the user energy consumption plan obtained by solving the IES upper-level scheduling model is the user's electric load and heat load demand in each time period after comprehensive demand response.

[0143] The spinning reserve constraint is transformed into a deterministic one, wherein the opportunity constraint of the spinning reserve is transformed into a deterministic constraint, and the processed model has a mixed integer linear programming structure.

[0144] The initial parameters of the IES lower-level scheduling model are input, and the CPLEX solver is used to solve the lower-level scheduling model to obtain the lower-level solution. The input initial parameters include gas turbine parameters, gas boiler parameters, energy storage parameters, renewable energy forecast values, number of scheduling periods, and upper and lower limits of each optimization variable.

[0145] Check whether the lower layer solution satisfies the second constraint condition. If so, output the optimal scheduling solution, where the second constraint condition includes formulas (13)-(19).

[0146] The output optimal scheduling plan includes the numerical values ​​of the variables to be optimized and the optimized objective function value of the comprehensive energy system optimization scheduling plan.

[0147] The following describes the use effect of the low-carbon scheduling method of the integrated energy system based on the carbon trading model of the present invention. This embodiment is based on the actual power load, outdoor temperature and wind and solar output of a certain IES, and sets four operating modes for example comparison and analysis to verify the effectiveness of the model constructed by this method. The four modes set are:

[0148] Mode 1: Traditional carbon trading without comprehensive demand response;

[0149] Model 2: Traditional carbon trading, taking into account comprehensive demand response;

[0150] Model 3: Tiered carbon trading without comprehensive demand response;

[0151] Model 4: Tiered carbon trading, taking into account comprehensive demand response;

[0152] In the above mode, the optimization scheduling results of the method of the present invention are as follows: Figure 4 This is a comparison chart of the total output of each device and purchased electricity under different modes. Figure 5 This is the heat load reduction and system carbon emission change diagram under different penalty factors in Mode 4. Figure 6 This is a graph showing the changes in energy purchase cost, total cost and carbon emissions in Model 4 as the carbon trading price increases.

[0153] Depend on Figure 4 It can be seen that after considering the step-by-step carbon trading, the output of purchased electricity and gas boilers decreases, and the output of gas turbines increases. This is because after considering the step-by-step carbon trading, in order to suppress the high carbon emissions of purchased electricity, the purchased electricity is reduced, the electric output of the gas turbine increases, and the thermal output of the gas turbine also increases due to the thermal power constraint. In order to maintain the balance of thermal load, the output of the gas boiler decreases. This shows that considering the step-by-step carbon trading can effectively constrain high-carbon units, increase the output of low-carbon units, and thus reduce the overall carbon emission level of the system.

[0154] Depend on Figure 5 It can be seen that as the penalty factor increases, the heat load reduction decreases, but the carbon emissions increase. The penalty factor reflects the user's requirements for thermal comfort. The larger the value, the higher the user's requirements for thermal comfort. Therefore, the penalty factor should be set reasonably to meet the user's thermal comfort requirements while reducing the system's carbon emissions.

[0155] Depend on Figure 6It can be seen that carbon emissions decrease as the carbon trading price increases, and the carbon trading cost, that is, the difference between the total cost and the energy purchase cost, continues to increase. This is because the step-by-step carbon trading reduces the purchase of electricity and increases the power output of the gas turbine, thereby reducing carbon emissions. When the carbon trading price is 1,000 yuan / t, the carbon emissions and the system's energy purchase cost remain unchanged. This is because the gas turbine has reached its output limit at this time, the unit output no longer changes, and the capacity of the gas turbine is smaller than the purchased electricity. The actual carbon emissions of the system will not be less than the quota, so the total cost increases in direct proportion to the increase in the carbon trading price.

[0156] Table 1 shows the system carbon emissions, carbon trading costs, energy purchase costs and total costs under different modes.

[0157] model Carbon emissions (t) Carbon trading cost (yuan) Energy purchase cost (yuan) Total cost (yuan) Mode 1 14.26 89.57 11147.33 11236.89 Mode 2 14.13 102.74 10768.60 10871.34 Mode 3 12.80 121.88 11328.60 11450.47 Mode 4 12.43 144.38 10979.82 11124.20

[0158] It can be seen from Table 1 that the carbon emissions from Mode 1 to Mode 4 gradually decrease, indicating that considering step-by-step carbon trading and comprehensive demand response is beneficial to suppress the carbon emissions of the system; among them, Mode 4 considers comprehensive demand response compared with Mode 3. Although the carbon trading cost increases, the energy purchase cost decreases, and the total cost of the system decreases; compared with Mode 2, after considering step-by-step carbon trading, Mode 4 reduces carbon emissions by 12.03%, while the total cost only increases by 2.33%, indicating that the model proposed in this paper can effectively reduce carbon emissions while taking into account the operating economy of the system.

[0159] In summary, the low-carbon scheduling method of the integrated energy system based on the carbon trading model of the present invention first constructs an IES architecture that contains multiple renewable energy power generation and multiple energy forms of electricity, heat and gas; then, according to the price-type electricity-heat comprehensive demand response model and the carbon trading cost model with carbon emission interval segmentation, an IES two-layer scheduling model is constructed with the upper layer aiming at minimizing the user energy cost and the lower layer aiming at minimizing the purchased energy and carbon trading costs; finally, the CPLEX solver is used to solve the model to obtain the global optimal solution, which effectively solves the environmental pollution and energy shortage problems of the prior art, improves the operating economy of the system, reduces the carbon emissions of the system, and promotes the consumption of renewable energy such as wind and solar power, and has the advantages of scientific and reasonable methods, strong applicability and good effects.

[0160] Example 2

[0161] Based on the low-carbon scheduling method of the integrated energy system based on the carbon trading model in the first embodiment of the present invention, the second embodiment of the present invention further proposes a low-carbon scheduling system of the integrated energy system based on the carbon trading model. Figure 7 A schematic diagram of a low-carbon dispatching system for an integrated energy system based on a carbon trading model proposed in Example 1 of the present invention, the system comprising a first building module, a first solving model, a second building module, an input module, and a second solving module;

[0162] The first building module is used to build a source-load coordinated integrated energy system; the integrated energy system includes electric load, heat load, electric energy storage device and power-to-gas equipment; based on the integrated energy system, an upper-level model of the integrated energy system is established, and the upper-level model includes a price-based electric-heat integrated demand response model, an upper-level scheduling model of the integrated energy system and the minimum heating capacity of users;

[0163] The first solving module is used to input the initial parameters of the upper-level scheduling model of the integrated energy system, solve the upper-level scheduling model of the integrated energy system, and obtain the energy consumption plan of the user;

[0164] The second building module is used to establish a lower-level model of the integrated energy system; the lower-level model includes a stepped carbon trading cost model for carbon emission interval segmentation and a lower-level scheduling model for the integrated energy system;

[0165] The input module is used for taking the user energy consumption plan as the load demand of the lower scheduling model of the integrated energy system when the user energy consumption plan satisfies the first constraint condition;

[0166] The second solving module is used to deterministically transform the rotating reserve constraint, input the initial parameters of the lower-level scheduling model of the integrated energy system, solve the lower-level scheduling model of the integrated energy system, obtain the optimal cost of the integrated energy system, and output the optimal scheduling plan when the optimal cost satisfies the second constraint.

[0167] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that there is any such actual relationship or order between these entities or operations. Moreover, the term "include", "comprise" or any other variant thereof is intended to cover non-exclusive inclusion, so that the process, method, article or equipment that includes a series of elements are inherent to the elements. In the absence of more restrictions, the elements limited by the sentence "comprise one..." do not exclude the presence of other identical elements in the process, method, article or equipment that includes the elements. In addition, the above-mentioned technical solution provided in the embodiment of the present application is consistent with the corresponding technical solution in the prior art in principle, and the part is not described in detail, so as not to repeat too much.

[0168] Although the above describes the specific implementation of the present invention in conjunction with the accompanying drawings, it is not intended to limit the scope of protection of the present invention. For those skilled in the art, other different forms of modifications or deformations can be made on the basis of the above description. It is not necessary and impossible to list all the implementation methods here. On the basis of the technical solution of the present invention, various modifications or deformations that can be made by those skilled in the art without creative work are still within the scope of protection of the present invention.

Claims

1. A low-carbon scheduling method for an integrated energy system based on a carbon trading model, characterized in that: The following steps are involved: Constructing a source-load coordinated integrated energy system; the integrated energy system includes electrical load, thermal load, electrical energy storage device and power-to-gas equipment; Based on the integrated energy system, an upper model of the integrated energy system is established, wherein the upper model includes a price-based electric-heat integrated demand response model, an upper-level scheduling model of the integrated energy system, and a minimum heating amount for users; the establishment of the price-based electric-heat integrated demand response model includes making full use of the coupling and complementary relationship between electric energy and thermal energy, and respectively establishing a mathematical model for time-shifting electric loads and a mathematical model for reducing thermal loads; The method for obtaining the minimum heat supply of the user comprises: According to the relationship between the average prediction index of thermal sensation and indoor temperature, the minimum indoor thermal comfort temperature acceptable to users can be obtained. Where M is the energy metabolism rate of the human body; I cl is the thermal resistance of clothing; T s is the average temperature of human skin in a comfortable state; T t in is the indoor temperature during period t; The minimum heating supply for the user is obtained according to the minimum indoor thermal comfort temperature acceptable to the user; the heating supply is expressed as: in, is the indoor temperature during the period t-1; T t out is the outdoor temperature at time t; K is the comprehensive heat transfer coefficient of the building; F is the surface area of ​​the building; V is the volume of the building; C air is the specific heat capacity of indoor air; ρ air is the density of indoor air; Δt is the time interval; The mathematical model of the time-shiftable electric load is: L,t =P FL,t +P SL,t ; then P L,t is the total power load of the user in period t; P SL,t is the user's time-shiftable power load in period t; The mathematical model for reducing heat load is: H L,t =H OL,t -H CL,t ; then H L,t H is the heat load power after the user reduces it in period t; OL,t H is the heat load power of the user before reduction in period t; CL,t Reducing heat load power for users during period t; The method for establishing the upper-level scheduling model of the integrated energy system includes: The optimization objective function of the integrated energy system is constructed with the goal of minimizing the user's energy cost. The expression of the optimization objective function is: Among them, F1 is the energy cost of the user; μ t is the time-of-use electricity price; t is the time-sharing heating price; κ is the penalty factor that describes the user's thermal comfort requirements; κ(H CL,t ) 2 The penalty cost for users caused by the decrease in thermal comfort due to the reduction of heating load; Determine the first constraint condition; the first constraint condition includes a time-shiftable electric load constraint, a reducible heat load constraint, and a thermal sensation average prediction index constraint; wherein the expression of the time-shiftable electric load constraint is: in is the minimum value of the load that can be shifted in time period t; is the maximum value of the load that can be shifted in time period t; α is the proportion of the load that can be shifted in time; The expression for the heat load reduction constraint is: The expression of the thermal sensation average prediction index constraint is: Inputting initial parameters of the upper-level scheduling model of the integrated energy system, solving the upper-level scheduling model of the integrated energy system, and obtaining the energy consumption plan of the user; Establishing a lower-level model of an integrated energy system; the lower-level model includes a stepped carbon trading cost model for carbon emission interval segmentation and a lower-level scheduling model for an integrated energy system; the method for establishing the stepped carbon trading cost model for carbon emission interval segmentation includes: Constructing the actual carbon emissions expression of the system Among them, δ GT is the carbon emission intensity of the gas turbine; δ GB is the carbon emission intensity of the gas boiler; be is the carbon emission intensity of purchased electricity; P2G is the carbon capture intensity of the power-to-gas plant; P P2G,t is the electric power of the power-to-gas equipment in period t; β is the conversion coefficient of the power supply of the gas turbine, P GT,t is the power supply of the gas turbine in period t; H GT,t is the heat supply of the gas turbine during period t; H GB,t P is the thermal power provided by the gas boiler during period t; be,t is the purchased electric energy power in period t; T is a scheduling cycle; Construct the total carbon emission quota expression of the system Among them, B is the total carbon emission quota of the system; λ GT is the quota coefficient of the gas turbine; GB is the quota coefficient of the gas boiler; be is the quota coefficient of purchased electricity; Constructing a ladder-type carbon trading cost calculation model: Among them, F c is the carbon trading cost; σ is the basic carbon trading price; ω is the increase in the carbon trading price when the system is sold; ε is the increase in the carbon trading price when purchasing carbon emission rights; p is the step size of the carbon emission interval; The method for establishing the lower-level scheduling model of the integrated energy system includes: The optimization objective is to minimize the sum of the cost of purchasing electricity and natural gas from the integrated energy system and the cost of carbon trading. The optimization objective function is: Among them, F2 is the total cost of the integrated energy system; F be F is the cost of purchased electricity; bg is the natural gas cost; θ be is the price of purchased electricity; θ bg is the price of natural gas; The price of purchasing spinning reserve from the upstream power grid; P is the price of purchasing spinning reserve from the gas grid; be,t The power purchased from the upper power grid during period t; R be,t is the spinning reserve power during period t; R GT,t The reserve power provided by the gas turbine for period t; Provides gas-to-electricity efficiency for the gas turbine during period t; η P2G is the energy conversion efficiency of the power-to-gas equipment; η GB is the energy conversion efficiency of the gas boiler; Q g It is the low calorific value of natural gas; Determine a second constraint condition; the second constraint condition includes an energy balance constraint, a gas turbine constraint, a gas boiler constraint, a power-to-gas equipment constraint, an electric energy storage constraint, a spinning reserve constraint, and an external network constraint; Energy balance constraints include electrical power balance constraints and thermal power balance constraints. The expression of energy balance constraint is: P REG,t is the predicted output value of renewable energy in period t; P CH,t P is the charging power of the energy storage during period t; DC,t is the discharge power of the energy storage during period t; Gas turbine constraints include unit output constraints and ramp constraints. The expression of gas turbine constraint is: The upper limit of gas turbine output; It is the lower limit of gas turbine output; is the maximum downward ramp rate of the gas turbine; is the maximum upward ramp rate of the gas turbine; π is the thermal-electric ratio of the gas turbine; Gas boiler constraints include output constraints and ramp constraints of gas boilers; The expression of gas boiler constraint is: It is the upper limit of the thermal output of the gas boiler; It is the lower limit of the thermal output of the gas boiler; is the maximum downward ramp rate of the gas boiler; is the maximum upward climbing rate of the gas boiler; The expression of the power-to-gas equipment constraint is: is the maximum power of the power-to-gas equipment; Electric energy storage constraints, including electric energy storage output constraints and capacity constraints; The expression of the electric energy storage constraint is S max is the maximum capacity of electrical energy storage; S min is the minimum capacity of electrical energy storage; S (0) is the initial capacity of the electric energy storage device cycle; S (end) The capacity of the electrical energy storage device at the end; is the maximum charging power; γ CH For maximum charging efficiency; is the maximum discharge power; γ DC Maximum discharge efficiency; Spinning reserve constraints, including gas turbine reserve constraints, purchased power reserve constraints, electric energy storage reserve constraints, and spinning reserve opportunity constraints; The expression of the spinning reserve constraint is: P t W is the actual output value of the fan during period t; P t PV is the actual output value of photovoltaic power during period t; P r is the probability of the event being true; ψ is the confidence level; External network constraints, including constraints on purchased electricity and purchased natural gas; The expression of the external network constraint is: The upper limit of purchased electricity; It is the lower limit of purchased electricity; The upper limit of natural gas purchase; It is the lower limit of natural gas purchased from outside; When the user energy consumption plan satisfies the first constraint, the user energy consumption plan is used as the load demand of the lower scheduling model of the integrated energy system; The rotating reserve constraint is deterministically transformed, the initial parameters of the lower-level scheduling model of the integrated energy system are input, the lower-level scheduling model of the integrated energy system is solved to obtain the optimal cost of the integrated energy system, and the optimal scheduling plan is output when the optimal cost satisfies the second constraint.

2. The low-carbon scheduling method for an integrated energy system based on a carbon trading model according to claim 1 is characterized in that: The method of inputting the initial parameters of the upper-level scheduling model of the integrated energy system, solving the upper-level scheduling model of the integrated energy system, and obtaining the energy consumption plan of the user is: The initial parameters of the upper-level scheduling model of the integrated energy system are input, and the upper-level scheduling model of the integrated energy system is solved by using the CPLEX solver to obtain the user's energy consumption plan; the initial parameters of the upper-level scheduling model of the integrated energy system include the predicted value of electric load, outdoor temperature, time-of-use electricity price, heat price parameters, building parameters, number of scheduling periods, upper limits of each optimization variable, and lower limits of each optimization variable.

3. The low-carbon scheduling method for an integrated energy system based on a carbon trading model according to claim 1 is characterized in that: The method of inputting the initial parameters of the lower-level scheduling model of the integrated energy system and solving the lower-level scheduling model of the integrated energy system includes: inputting the initial parameters of the lower-level scheduling model of the integrated energy system, and using the CPLEX solver to solve the lower-level scheduling model of the integrated energy system; wherein the initial parameters of the lower-level scheduling model of the integrated energy system include: gas turbine parameters, gas boiler parameters, energy storage parameters, renewable energy prediction values, the number of scheduling time periods, the upper limit value of each optimization variable, and the lower limit value of each optimization variable.

4. The low-carbon scheduling method for an integrated energy system based on a carbon trading model according to claim 3 is characterized in that: The output optimal scheduling plan includes the numerical values ​​corresponding to the variables to be optimized and the comprehensive energy system optimization scheduling plan of the optimization objective function value.

5. A low-carbon dispatching system for an integrated energy system based on a carbon trading model, used to execute the low-carbon dispatching method for an integrated energy system based on a carbon trading model according to any one of claims 1 to 4, characterized in that the system comprises a first building module, a first solving module, a second building module, an input module, and a second solving module; The first building module is used to build a source-load coordinated integrated energy system; the integrated energy system includes electric load, thermal load, electric energy storage device and power-to-gas equipment; based on the integrated energy system, an upper model of the integrated energy system is established, and the upper model includes a price-based electric-heat integrated demand response model, an upper scheduling model of the integrated energy system and the minimum heating amount of the user; The first solving module is used to input the initial parameters of the upper-level scheduling model of the integrated energy system, solve the upper-level scheduling model of the integrated energy system, and obtain the energy consumption plan of the user; The second construction module is used to establish a lower-level model of the integrated energy system; the lower-level model includes a stepped carbon trading cost model for carbon emission interval segmentation and a lower-level scheduling model for the integrated energy system; The input module is used to use the user energy consumption plan as the load demand of the lower scheduling model of the integrated energy system under the condition that the user energy consumption plan meets the first constraint; The second solving module is used to deterministically transform the rotating reserve constraint, input the initial parameters of the lower-level scheduling model of the integrated energy system, solve the lower-level scheduling model of the integrated energy system, obtain the optimal cost of the integrated energy system, and output the optimal scheduling plan when the optimal cost satisfies the second constraint condition.