Online evaluation and early warning method and system for operation status of regional power grid control system
By constructing an online assessment and early warning model for the operating status of the power grid control system based on multi-type labels and entropy value methods, the problem of software fault location and isolation in the dispatch control system is solved, fast and accurate fault location and early warning are achieved, and system operation is improved. Efficiency of status assessment.
Patent Information
- Application Number
- CN202111057529.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-09-09
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2041-09-09
AI Technical Summary
In the process of software module upgrade and update, the existing dispatch control system lacks intuitive monitoring means and pre-control means, which makes it difficult to locate and isolate software faults, and cannot effectively assess the system operating status and risks.
By collecting and preprocessing the operation data of the regional power grid control system, a collaborative weight setting mechanism based on multi-type tags and an entropy method to determine indicator weights are constructed, and an online assessment and early warning model for the operating status of the power grid control system is established to achieve real-time evaluation and early warning.
Quickly locating and isolating software faults improves the efficiency and accuracy of locating software faults in the control system, provides timely warning information, reasonably evaluates the system operating status, and accurately locates the root cause of the fault.
Smart Images

Figure CN113807690B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of power system dispatching and control, and in particular relates to an online evaluation and early warning method and system for the operating status of a regional power grid control system. Background Art
[0002] As the functional structure of system application software becomes increasingly complex and the scale of application data expands rapidly, the operational risks borne by the dispatching control system are increasing. At the same time, the system faces continuous upgrades and updates of software modules, a single system inspection method, lack of intuitive monitoring means, insufficient pre-control means, and inability to quickly locate and effectively isolate software failures. The basis for solving these problems is to establish scientific and reasonable dispatching control system software operation status evaluation indicators. How to define the dispatching control system software operation status evaluation indicators from the aspects of system resources, availability, information security, abnormal status, etc., and establish a dispatching control system software risk assessment model are the key points and difficulties. Summary of the invention
[0003] In order to solve the deficiencies in the prior art, the purpose of the present invention is to provide a method and system for online evaluation and early warning of the operating status of a regional power grid control system, which analyzes the alarm data and log information generated by the operation of the control system software, evaluates the operating status of the software system in real time, provides early warning information of the regional power grid control system in a timely manner, and accurately locates the root cause of the system software failure.
[0004] The present invention adopts the following technical solution.
[0005] A method for online evaluation and early warning of the operation status of a regional power grid control system, the method comprising the steps of:
[0006] (1) Collect the operating data of the regional power grid control system and store the data in a standardized manner;
[0007] (2) Perform data preprocessing and perform data priority and data correctness marking;
[0008] (3) Determine the weights of the evaluation indicators and the evaluation level of the system operation status;
[0009] (4) Construct an online evaluation and early warning model for the operation status of the power grid control system;
[0010] (5) The power grid control system operation status evaluation and early warning model is trained according to the priority evaluation principle, and the trained evaluation and early warning model is used to perform online evaluation and early warning of the power grid control system operation status.
[0011] Furthermore, in step (1), the regional power grid control system operation data includes hardware equipment status data, business process status data and interaction data status data.
[0012] Furthermore, in step (2), data preprocessing includes data consistency processing and data dimensionless processing.
[0013] Furthermore, in the step (3), a collaborative weight setting mechanism based on multi-type tags is adopted, the hardware device status is a single-machine information indicator, and the weight of each indicator is set by empirical value; the business data status and interaction data status are multi-machine information indicators, and the entropy method is used to determine the weight of each indicator;
[0014] The weights of the business data status and interaction data status indicators are calculated by the following formula:
[0015]
[0016] Among them, E j It is the entropy value of each business data status and interaction data status evaluation indicator.
[0017] Furthermore, in step (3), the system operation status evaluation level includes normal, warning, abnormal, and fault.
[0018] Furthermore, in step (3), determining the system operation status evaluation level specifically includes determining a central sample, arranging the distance between the original data sample and the central sample in ascending order, and setting the system operation status evaluation level according to the distance;
[0019] The distance between two samples is calculated:
[0020]
[0021] Among them, x i and x j They represent two samples in the preprocessed system operation status real-time data set, x im and x jm For sample x i and x j The mth attribute index, w m is the weight of the mth attribute index, γ m It is the data correctness annotation based on expert advice for the mth attribute indicator.
[0022] Furthermore, in step (4), the online evaluation and early warning model of the operation status of the power grid control system is:
[0023]
[0024] Among them, H is the real-time health status assessment result of the system, H sin It is the running status of the hardware device. mul is the health status of business data and interaction data; p is the number of online evaluation indicators of hardware devices, xi is a sample of hardware device evaluation indicators, w i is x i The weight of; q is the number of online evaluation indicators of business data status and interaction data status, x j is a sample of evaluation indicators for business data status and interaction data status, w j is x j The weight of .
[0025] Furthermore, in step (5), the training of the power grid control system operation status assessment and early warning model specifically includes:
[0026] (5.1) Perform a data missing warning annotation query for the training set. If there is a warning, issue a warning; if not, continue with step (5.2);
[0027] (5.2) Perform data priority labeling query. If the priority is low, proceed to step (5.3). If the priority is high, perform health query. If the health is low, issue an early warning. If the health is high, proceed to step (5.3).
[0028] (5.3) Based on the collaborative weight setting mechanism of multiple types of tags, the weights of each evaluation indicator are obtained;
[0029] (5.4) Determine the system operation status evaluation level based on the training set data and obtain the evaluation result; if it is "warning", "abnormal" or "fault", then issue an early warning; if it is "normal", then no early warning;
[0030] (5.5) At the same time, the evaluation results are manually checked for correctness. If the evaluation results are unreasonable, the parameters are corrected; thus, the trained power grid control system operation status evaluation and early warning model is obtained.
[0031] Furthermore, in the step (5), the trained evaluation and early warning model is used to perform online evaluation and early warning of the operation status of the power grid control system to obtain early warning results and various types of information status; at the same time, the data missing early warning labels or evaluation indicators corresponding to the low health status that cause the system operation status evaluation result to be "abnormal" or "faulty" are queried to locate the fault point.
[0032] An online evaluation and early warning system for the operation status of a regional power grid control system, the system comprising a data collection module, a data storage module, a data preprocessing module, a data marking module, a system operation status evaluation level determination module, and a system operation status online evaluation and early warning module;
[0033] Data collection module, which collects real-time operation data of the regional power grid control system, including hardware equipment status data, business process status data and interaction data status data;
[0034] Data storage module, used for standardizing and storing the operation data of the regional power grid control system;
[0035] The data preprocessing module extracts the real-time operation data of the system in chronological order, and performs data consistency processing and data dimensionless processing;
[0036] Data labeling module, used for data priority labeling and data correctness labeling;
[0037] The system operation status evaluation level determination module determines the central sample, sorts the distance between the original data sample and the central sample from small to large, and sets the system operation status evaluation level according to the distance;
[0038] The system operation status online evaluation and early warning module builds an online evaluation and early warning model for the operation status of the power grid control system based on the system real-time operation data evaluation indicators and indicator weights; and pre-trains the model based on data annotation and system operation status evaluation level; and uses the trained evaluation and early warning model to perform online evaluation and early warning on the operation status of the power grid control system.
[0039] The beneficial effects of the present invention are as follows:
[0040] The present invention analyzes the key indicators that affect the operation status of the regional power grid control software system based on a large amount of alarm data and log information generated by the operation of the control system software. At the same time, combined with the type characteristics and priority level of each indicator, the present invention performs correlation analysis and cluster analysis on the actual data from multiple angles, evaluates the operation status of the software system online, quickly explores the root causes of control system software failures, and improves the efficiency and accuracy of control system software failure location.
[0041] The present invention constructs an evaluation mechanism for the operation status of a power grid control software system. Based on an operation status evaluation system of expert advice and weight relationship, the operating status of the software system is reasonably evaluated. By performing priority evaluation and rational weight setting on various types of real-time data, the root cause of control system software failure is quickly excavated, the software system operation status is evaluated online, and early warning information of the regional power grid control system is provided in a timely manner, so as to accurately locate the root cause of the system software failure. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 It is a flow chart of the online evaluation and early warning method for the operation status of the regional power grid control system of the present invention;
[0043] Figure 2 It is a framework diagram of online evaluation indicators;
[0044] Figure 3 It is a flow chart for training and testing the online evaluation model for the operation status of the regional power grid control system. DETAILED DESCRIPTION
[0045] The present application is further described below in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present application.
[0046] like Figure 1 As shown, the present invention discloses an online evaluation and early warning method for the operation status of a regional power grid control system, comprising the following steps:
[0047] (1) Collect the operation data of the regional power grid control system, including the hardware equipment status, business process status and interactive data status in the system, and store various status data in a standardized manner;
[0048] According to the factors affecting the operation status of the regional power grid control system, online evaluation indicators are designed. The specific framework is as follows: Figure 2 shown.
[0049] The hardware equipment status evaluation indicators include CPU utilization, memory utilization, hard disk utilization, network connection rate, etc.; the business process status evaluation indicators include process memory usage ratio, number of threads, working time, number of alarms, number of network connections, front-end processing, steady-state monitoring, data services, public basic applications, etc.; the interactive data status evaluation indicators include front-end channel conditions, unchanged important actual data, bit error rate, over-limit, jump, abnormal fluctuation, state estimation pass rate, CPS indicators, etc.
[0050] (2) Extract the real-time operation data of the system in chronological order and perform data preprocessing, including data consistency and dimensionless processing;
[0051] During the data consistency process, if data is missing due to missed data collection, an early warning mark will be issued.
[0052] Afterwards, the characteristics and relationships of the hardware device status, business process status, and interactive data status are fully considered, and the evaluation indicators are prioritized.
[0053] Afterwards, the data correctness is labeled γ based on the expert's advice. The correct data is labeled as 1, that is, γ=1; the incorrect data is labeled as 0, that is, γ=0.
[0054] Afterwards, according to the calculation method of the weight of the online evaluation indicator type of the regional power grid control system operation status, a collaborative weight setting mechanism based on multi-type tags is designed. The hardware equipment status is a single-machine information indicator, and the weight of each indicator is set by empirical value. The business data status and interaction data status are multi-machine information indicators. This method uses the entropy method to determine the weight of each indicator.
[0055] The weights of the business data status and interaction data status indicators are calculated by the following formula:
[0056]
[0057] Among them, E j It is the entropy value of each business data status and interaction data status evaluation indicator.
[0058] (3) Based on the weights and data annotations of various types of key data of the regional power grid control system, the K-means clustering algorithm is used to calculate the distance between each sample and the central sample. Four areas with relatively concentrated sample points are clustered according to the concentration degree of each sample point, and the system operation status evaluation level is determined. The system operation status is evaluated using four levels: "normal", "warning", "abnormal" and "fault".
[0059] Specifically, the Canopy algorithm is used for initial clustering, and then the center points of these clusters are used as the initial cluster center points of the K-means algorithm, that is, the center samples. After the center samples are determined, the distances between the original sample data and the center samples are sorted from small to large, and the system operation status evaluation level is set according to the distance.
[0060] The distance between two samples is calculated according to the following formula:
[0061]
[0062] Among them, x i and x j They represent two samples in the preprocessed system operation status real-time data set, x im and x jm For sample x i and x j The mth evaluation indicator, w m is the weight of the mth evaluation indicator, γ m is the data correctness annotation based on expert advice for the mth evaluation indicator.
[0063] (4) Design an online evaluation method for the operation status of the power grid control system and construct an online evaluation model for the operation status of the power grid control system;
[0064] The operating status of the power grid control software system is calculated by the following formula:
[0065]
[0066] Among them, H is the real-time health status assessment result of the system, H sin It is the running status of the hardware device. mul is the health status of business data and interaction data; p is the number of online evaluation indicators of hardware devices, x i is a sample of hardware device evaluation indicators, w i is x iThe weight is directly set according to the expert experience value; q is the number of online evaluation indicators of business data status and interaction data status, x j is a sample of evaluation indicators for business data status and interaction data status, w j is x j The weight is determined according to the entropy of each state.
[0067] (5) Based on the priority evaluation principle, the grid control system operation status prediction model is trained and tested, and the fault point is located according to the model parameters.
[0068] The sample set is divided into a training set and a test set; the training set is used to pre-train the model. The specific method is as follows Figure 3 shown.
[0069] (5.1) Perform a data missing warning annotation query for the training set. If there is a warning, issue a warning; if not, continue with step (5.2);
[0070] (5.2) Perform data priority labeling query. If the priority is low, proceed to step (5.3). If the priority is high, perform health query. If the health is low, issue an early warning. If the health is high, proceed to step (5.3).
[0071] Health refers to the operating status of the hardware device. sin , business data and interaction data health status H mul The hardware device status and data health status queried in the data are determined by the experience value.
[0072] (5.3) Based on the collaborative weight setting mechanism of multiple types of tags, the weights of each evaluation indicator are obtained;
[0073] (5.4) Determine the system operation status evaluation level based on the training set data and obtain the evaluation result; if it is "warning", "abnormal" or "fault", an early warning is issued; if it is "normal", no early warning is issued.
[0074] At the same time, the evaluation results are manually checked for correctness. If the evaluation results are unreasonable, the parameters are corrected. The entropy value and health compliance index of the relevant business data status and interactive data status evaluation indicators are adjusted to obtain reasonable results and record the new weight parameters.
[0075] (5.5) Conducting training on the grid control system operation status prediction model.
[0076] The power grid control system operation status test is carried out according to the test set samples to obtain the early warning results and various types of information status; at the same time, the evaluation indicators corresponding to the data missing early warning labels or low health status that cause the system operation status evaluation results to be "abnormal" or "faulty" are queried, so as to locate the fault point and realize the function of quickly discovering and locating the root cause of the control system software fault.
[0077] The present invention also provides an online evaluation and early warning system for the operation status of a regional power grid control system, comprising a data collection module, a data storage module, a data preprocessing module, a data labeling module, a system operation status evaluation level determination module, and a system operation status online evaluation and early warning module.
[0078] The data collection module collects real-time operation data of the regional power grid control system, including hardware equipment status data, business process status data and interaction data status data.
[0079] The data storage module is used to standardize and store the operating data of the regional power grid control system.
[0080] The data preprocessing module extracts the real-time operation data of the system in chronological order and performs data consistency processing and data dimensionless processing.
[0081] The data labeling module is used to label data priority and data correctness.
[0082] The system operation status evaluation level determination module determines the central sample, sorts the distance between the original data sample and the central sample from small to large, and sets the system operation status evaluation level according to the distance.
[0083] The system operation status online evaluation and early warning module builds an online evaluation and early warning model for the operation status of the power grid control system based on the system real-time operation data evaluation indicators and indicator weights; and pre-trains the model based on data annotation and system operation status evaluation level; and uses the trained evaluation and early warning model to perform online evaluation and early warning on the operation status of the power grid control system.
[0084] The following takes the operation of the regional power grid control software system in Suzhou, Jiangsu Province as an example to illustrate the specific implementation method of the present invention.
[0085] First, obtain the hardware device status information in the system, including CPU utilization, memory utilization, hard disk utilization, and network connection rate; business process status information, including process memory usage ratio, number of threads, working time, number of network connections, front-end processing alarms, steady-state monitoring alarms, data service alarms, and public basic application alarms; interactive data status information, including front-end channel conditions, important actual data unchanged, bit error rate, over-limit, jump, abnormal fluctuation, state estimation pass rate, and CPS index.
[0086] Afterwards, the acquired characteristic data is unified and dimensionless in combination with the online evaluation and early warning system architecture of the regional power grid control software operation status proposed in the present invention. If data missing due to missed sampling is found, early warning marking is performed; at the same time, data correctness marking based on expert advice is performed. At the same time, the characteristics and interrelationships of the hardware device status, business process status, and interactive data status are fully considered, and priority marking is performed on the status information evaluation indicators.
[0087] The K-means algorithm based on the weights of various types of key data and data annotations of the regional power grid control system determines the evaluation level of the system operation status. The weight is calculated according to the type of online evaluation indicators of the operation status of the regional power grid control system: the hardware equipment status is a single-machine information indicator, and the weight parameters of each indicator are set by experience. The business data status and interactive data status are multi-machine information indicators. This method uses the entropy method to determine the weight of each indicator. According to the priority evaluation principle, the operation status of the power grid control system is determined for online evaluation and an early warning signal is issued.
[0088] Finally, based on the early warning results, the fault points are analyzed and located from various types of information status, realizing the function of quickly discovering and locating the root causes of the control system software failures.
[0089] The beneficial effects of the present invention are as follows:
[0090] The present invention analyzes the key indicators that affect the operation status of the regional power grid control software system based on a large amount of alarm data and log information generated by the operation of the control system software. At the same time, combined with the type characteristics and priority level of each indicator, the present invention performs correlation analysis and cluster analysis on the actual data from multiple angles, evaluates the operation status of the software system online, quickly explores the root causes of control system software failures, and improves the efficiency and accuracy of control system software failure location.
[0091] The present invention constructs an evaluation mechanism for the operation status of a power grid control software system. Based on an operation status evaluation system of expert advice and weight relationship, the operating status of the software system is reasonably evaluated. By performing priority evaluation and rational weight setting on various types of real-time data, the root cause of control system software failure is quickly excavated, the software system operation status is evaluated online, and early warning information of the regional power grid control system is provided in a timely manner, so as to accurately locate the root cause of the system software failure.
[0092] The applicant of the present invention has made a detailed explanation and description of the implementation examples of the present invention in conjunction with the drawings in the specification. However, those skilled in the art should understand that the above implementation examples are only preferred implementation schemes of the present invention, and the detailed description is only to help readers better understand the spirit of the present invention, but not to limit the scope of protection of the present invention. On the contrary, any improvements or modifications based on the inventive spirit of the present invention should fall within the scope of protection of the present invention.
Claims
1. A method for online evaluation and early warning of the operation status of a regional power grid control system, characterized in that: The method comprises the steps of: (1) Collect the operating data of the regional power grid control system, store the data in a standardized manner, and design online evaluation indicators based on the factors affecting the operating status of the regional power grid control system; (2) Perform data preprocessing and perform data priority and data correctness labeling; (3) Determine the weights of the evaluation indicators and the evaluation level of the system operation status; In the step (3), a collaborative weight setting mechanism based on multi-type tags is adopted, the hardware device status is a single-machine information indicator, and the weight of each indicator is set by experience; the business data status and interaction data status are multi-machine information indicators, and the entropy method is used to determine the weight of each indicator; The weights of the business data status and interaction data status indicators are calculated by the following formula: in, Entropy values of evaluation indicators for each business data status and interaction data status; (4) Construct an online evaluation and early warning model for the operation status of the power grid control system; (5) Implement the training of the evaluation and early warning model for the operation status of the power grid control system according to the priority evaluation principle, and use the trained evaluation and early warning model to perform online evaluation and early warning of the operation status of the power grid control system; In step (4), the online evaluation and early warning model of the operation status of the power grid control system is: in, H It is the real-time health status assessment result of the system. H sin It is the operating status of the hardware device. H mul The health status of business data and interaction data; p is the number of online evaluation indicators of hardware devices, is a sample of hardware device evaluation indicators. yes The weight of q is the number of online evaluation indicators for business data status and interaction data status, It is a sample of evaluation indicators for business data status and interaction data status. yes The weight of In step (5), the training of the power grid control system operation status assessment and early warning model specifically includes: (5.1) Perform a warning label query for missing data in the training set. If there is a warning, issue a warning; if not, continue with step (5.2); (5.2) Perform data priority labeling query. If the priority is low, proceed to step (5.3). If the priority is high, perform health query. If the health is low, issue an early warning. If the health is high, proceed to step (5.3). (5.3) Based on the collaborative weight setting mechanism of multiple types of tags, the weights of each evaluation indicator are obtained; (5.4) Determine the system operation status evaluation level based on the training set data and obtain the evaluation result; if it is "warning", "abnormal" or "fault", then issue an early warning; if it is "normal", then no early warning; (5.5) At the same time, the evaluation results are manually checked for correctness. If the evaluation results are unreasonable, the parameters are corrected; the trained power grid control system operation status evaluation and early warning model is obtained; In the step (5), the trained evaluation and early warning model is used to perform online evaluation and early warning of the operation status of the power grid control system, and the early warning results and various types of information status are obtained; at the same time, the data missing early warning label or the evaluation index corresponding to the low health status that causes the system operation status evaluation result to be "abnormal" or "fault" is queried, so as to locate the fault point.
2. The method for online evaluation and early warning of the operation status of a regional power grid control system according to claim 1 is characterized in that: In the step (1), the regional power grid control system operation data includes hardware device status data, business process status data and interaction data status data.
3. The method for online evaluation and early warning of the operation status of a regional power grid control system according to claim 1 is characterized in that: In the step (2), data preprocessing includes data consistency processing and data dimensionless processing.
4. The method for online evaluation and early warning of the operation status of a regional power grid control system according to claim 1 is characterized in that: In step (3), the system operation status evaluation level includes normal, warning, abnormal, and fault.
5. The method for online evaluation and early warning of the operation status of a regional power grid control system according to claim 1 is characterized in that: In the step (3), the step of determining the system operation status evaluation level specifically includes determining a central sample, arranging the distance between the original data sample and the central sample in ascending order, and setting the system operation status evaluation level according to the distance; The distance between two samples is calculated: in, and They represent two samples in the preprocessed system operation status real-time data set, and For sample and No. m attribute indicators, For the m The weight of the attribute index, For the m Data correctness annotation based on expert advice for each attribute indicator.
6. A regional power grid control system operation status online evaluation and early warning system, the system is a system used by a regional power grid control system operation status online evaluation and early warning method according to any one of claims 1 to 5, characterized in that: The system includes a data collection module, a data storage module, a data preprocessing module, a data annotation module, a system operation status evaluation level determination module, and a system operation status online evaluation and early warning module; Data collection module, which collects real-time operation data of the regional power grid control system, including hardware equipment status data, business process status data and interaction data status data; Data storage module, used for standardizing and storing the operation data of the regional power grid control system; The data preprocessing module extracts the real-time operation data of the system in chronological order, and performs data consistency processing and data dimensionless processing; Data labeling module, used for data priority labeling and data correctness labeling; The system operation status evaluation level determination module determines the central sample, sorts the distance between the original data sample and the central sample from small to large, and sets the system operation status evaluation level according to the distance; The system operation status online evaluation and early warning module builds an online evaluation and early warning model for the operation status of the power grid control system based on the system real-time operation data evaluation indicators and indicator weights; and pre-trains the model based on data annotation and system operation status evaluation level; and uses the trained evaluation and early warning model to perform online evaluation and early warning on the operation status of the power grid control system.