A soil sampling monitoring system and method

Through the communication between the quality controller and the target sampling party of the soil sampling monitoring system, the sampling process is flexibly adjusted, the soil sampling error problem is solved, and the accuracy and reliability of soil environmental monitoring data is improved.

CN114264499BActive Publication Date: 2024-11-01CHINA NAT ENVIRONMENTAL MONITORING CENT
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111666962.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-31
Publication Date
2024-11-01
Estimated Expiration
2041-12-31

AI Technical Summary

Technical Problem

There are large errors in the soil sampling process, which affects the accuracy and reliability of soil environmental monitoring data.

Method used

A soil sampling monitoring system was designed to obtain the point information of the points to be sampled and the position information of the on-site sampling location through communication between the quality control party and the target sampling party, and determine whether the pre-retrieval plan meets the preset conditions. If it is not met, Submit an offset sampling application, and start the offset sampling procedure after the review is passed, and flexibly adjust the sampling process to reduce errors.

Benefits of technology

Effectively reduce or avoid possible errors during soil sampling, and improve the accuracy and reliability of soil environmental monitoring data.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114264499B_ABST
    Figure CN114264499B_ABST
Patent Text Reader

Abstract

The present disclosure relates to the technical field of environmental monitoring, and provides a soil sampling monitoring system and method. The system includes: a quality control party and a target sampling party; the quality control party is used to issue a soil sampling task to the target sampling party, and the soil sampling task includes the point information of the sampling point and the pre-collection plan; the target sampling party is used to submit an offset sampling application to the quality control party when it is determined that the pre-collection plan does not meet the preset on-site sampling conditions according to the point information of the sampling point and the location information of the on-site sampling location; the offset sampling application includes the offset reason and supporting materials; the quality control party is also used to review the offset sampling application and return the review result to the target sampling party; the target sampling party is also used to start the preset offset sampling program and feedback the sampling information to the quality control party when the review result is passed. The present disclosure can effectively reduce or avoid errors that may occur in the soil sampling process, and improve the accuracy and reliability of soil environmental monitoring data.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of environmental monitoring, and in particular to a soil sampling monitoring system and method. Background Art

[0002] The collection and processing of soil samples is an important prerequisite for the accuracy of soil environmental monitoring data. Collecting representative samples is a prerequisite for accurately reflecting the soil nutrient status (pollution status). The sampling error caused by the collection of soil samples is greater than any analytical error, and this error can reach 85% of the total process error in the physical and chemical analysis process.

[0003] Therefore, how to reduce the errors that may occur during soil sampling is the key to ensuring the accuracy and reliability of soil environmental monitoring data. Summary of the invention

[0004] In view of this, the embodiments of the present disclosure provide a soil sampling monitoring system and method to reduce errors that may occur during the soil sampling process, thereby improving the accuracy and reliability of soil environment monitoring data.

[0005] In a first aspect of the embodiments of the present disclosure, a soil sampling monitoring system is provided, including: a quality control party, a target sampling party in communication connection with the quality control party;

[0006] The quality control party is configured to issue soil sampling tasks to each target sampling party. The soil sampling tasks include the point information of the sampling points and the pre-sampling plan;

[0007] The target sampling party is configured to obtain the location information of the on-site sampling location when arriving at the sampling point for on-site sampling. When it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions based on the location information of the sampling point and the location information of the on-site sampling location, the target sampling party submits an application for offset sampling to the quality control party, and the application for offset sampling includes the reason for the offset and supporting information;

[0008] The quality control party is also configured to review the offset sampling application and return the review result to the target sampling party;

[0009] The target sampling party is also configured to start a preset offset sampling procedure when receiving an audit result indicating that the audit is passed, and to feed back the sampling information to the quality control party.

[0010] A second aspect of the embodiments of the present disclosure provides a soil sampling monitoring method, comprising:

[0011] Obtain the soil sampling task issued by the quality control party, which includes the location information of the sampling points and the pre-sampling plan;

[0012] When arriving at the sampling point for on-site sampling, obtaining the location information of the on-site sampling location;

[0013] When it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions based on the point information of the sampling point and the location information of the on-site sampling location, an offset sampling application is submitted to the quality control party, and the offset sampling application includes the reason for the offset and supporting information.

[0014] A second aspect of the disclosed embodiment provides another soil sampling monitoring method, comprising:

[0015] The quality control party issues soil sampling tasks to the target sampling party. The soil sampling tasks include the location information of the sampling points and the pre-sampling plan;

[0016] The target sampling party, when arriving at the sampling point for on-site sampling, obtains the location information of the on-site sampling location. When it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions based on the location information of the sampling point and the location information of the on-site sampling location, it submits an application for offset sampling to the quality control party. The application for offset sampling includes the reason for the offset and supporting information;

[0017] The quality control party shall review the application for offset sampling and return the review results to the target sampling party;

[0018] When the target sampling party receives the audit result that the audit is passed, it starts the preset offset sampling procedure and feeds back the sampling information to the quality control party.

[0019] Compared with the prior art, the beneficial effects of the disclosed embodiment include at least: providing a soil sampling monitoring system, including a quality control party and a target sampling party connected to the quality control party in communication; the quality control party is configured to issue a soil sampling task to the target sampling party, and the soil sampling task includes the point information of the sampling point to be sampled and the pre-collection plan; the target sampling party is configured to obtain the location information of the on-site sampling position when arriving at the sampling point for on-site sampling, and when it is determined that the pre-collection plan does not meet the preset on-site sampling conditions according to the point information of the sampling point to be sampled and the location information of the on-site sampling position, submit an offset sampling application to the quality control party, and the offset sampling application includes the offset reason and supporting materials; the quality control party is also configured to review the offset sampling application and return the review result to the target sampling party; the target sampling party is also configured to start the preset offset sampling program when the review result is received as approved, and feedback the sampling information to the quality control party. The disclosed method can effectively reduce or avoid errors that may occur in the soil sampling process by flexibly adjusting and monitoring the overall sampling process by the quality control party and the target sampling party, thereby improving the accuracy and reliability of soil environmental monitoring data. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the technical solutions in the embodiments of the present disclosure, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present disclosure. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0021] Figure 1 is a structural schematic diagram of a soil sampling monitoring system provided by an embodiment of the present disclosure;

[0022] Figure 2 is a structural schematic diagram of another soil sampling monitoring system provided by an embodiment of the present disclosure;

[0023] Figure 3 It is a flow chart of a soil sampling and monitoring method provided by an embodiment of the present disclosure;

[0024] Figure 4 is a timing diagram of another soil sampling monitoring method provided by an embodiment of the present disclosure;

[0025] Figure 5 It is a structural schematic diagram of an electronic device provided by an embodiment of the present disclosure. DETAILED DESCRIPTION

[0026] In the following description, specific details such as specific system structures and technologies are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present disclosure. However, it should be clear to those skilled in the art that the present disclosure may be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to avoid obstructing the description of the present disclosure with unnecessary details.

[0027] A soil sampling monitoring system and method according to an embodiment of the present disclosure will be described in detail below with reference to the accompanying drawings.

[0028] Figure 1 Schematic diagram of a soil sampling monitoring system provided by an embodiment of the present disclosure. Figure 1 As shown, the soil sampling monitoring system includes a quality control party 101 and a target sampling party 102 which is communicatively connected to the quality control party 101 .

[0029] The quality control party 101 is configured to issue a soil sampling task to the target sampling party 102 , wherein the soil sampling task includes the point information of the points to be sampled and a pre-sampling plan.

[0030] The quality control party 101 may be a server that provides various services, for example, a background server that receives an application sent by the target sampling party 102 that establishes a communication connection with the quality control party 101. The background server may receive and analyze the application sent by the target sampling party 102, and generate a processing result. The server may be a single server, a server cluster consisting of several servers, or a cloud computing service center, which is not limited in the embodiments of the present disclosure.

[0031] It should be noted that the server can be hardware or software. When the server is hardware, it can be various electronic devices that provide various services to the target sampling party 102. When the server is software, it can be multiple software or software modules that provide various services to the target sampling party 102, or it can be a single software or software module that provides various services to the target sampling party 102, and the embodiments of the present disclosure are not limited to this.

[0032] In an exemplary embodiment, the quality control party 101 may refer to a server (such as a cloud server, a backend server, etc.) set up in a provincial station.

[0033] The target sampling party 102 may be a (handheld) sampling terminal device used by sampling personnel of sampling units in prefecture-level cities and counties under the "provincial station". The sampling terminal device may be hardware or software. When the sampling terminal device is hardware, it may be various electronic devices having a display screen and supporting communication with a server, including but not limited to smart phones, tablet computers, laptop computers, and desktop computers; when the sampling terminal device is software, it may be installed in the above electronic devices. The sampling terminal device may be implemented as multiple software or software modules, or as a single software or software module, and the embodiments of the present disclosure do not limit this. Furthermore, various applications may be installed on the sampling terminal device, such as data processing applications, instant messaging tools, social platform software, search applications, and the like.

[0034] In the embodiment of the present disclosure, the target sampling party 102 can establish a communication connection with the quality control party 101 through a network (which can be a wired network connected by coaxial cable, twisted pair and optical fiber, or a wireless network that can interconnect various communication devices without wiring, such as Bluetooth, Near Field Communication (NFC), infrared, etc.).

[0035] It should be noted that the specific types, quantities and combinations of the target sampling party 102 and the quality control party 101 can be adjusted according to the actual needs of the application scenario, and the embodiments of the present disclosure do not limit this.

[0036] The sampling points include basic points, background points, and risk monitoring points (including key risk monitoring points and general risk monitoring points) in the grid of the national soil environment monitoring network. Point information includes the location information of the sampling points (such as point address information, XX village, XX town, XX district, XX city, XX province, etc., or the longitude and latitude of the point), point attributes (i.e., used to characterize whether the point belongs to basic points, background points, or risk monitoring points), point quantity, point code, etc.

[0037] The pre-collection plan includes the sampling location and sampling method of the sampling point to be sampled. Among them, the sampling location of the sampling point to be sampled can be flexibly set according to the actual situation. For example, the sampling location can be any position or multiple positions within a radius of 30 meters with the sampling point as the center. The sampling method can be determined according to the point type of the sampling point and the characteristic pollutants to be measured (such as organic pollutants (such as semi-volatile organic pollutants, etc.), inorganic pollutants (such as heavy metal ions, etc.)). The usual sampling methods include soil surface sampling and fresh soil sample collection. Among them, soil surface sampling (i.e. collecting soil surface samples) can generally be used for soil sampling at basic points and risk monitoring points. Specifically, the basic points can be sampled by a 5-point mixed sampling method; the risk monitoring points can be sampled by a separate sampling method of the soil surface. Separate sampling of the soil surface is suitable for collecting inorganic and organic samples and monitoring work for the purpose of capturing pollution conditions. Mixed sampling refers to collecting soil at multiple points within the set sampling area. The collection methods include single diagonal method, double diagonal method (i.e. plum blossom method), chessboard method and snake method, etc. Fresh soil sampling is suitable for the collection of fresh soil samples when the characteristic pollutants to be tested at the monitoring point are volatile and semi-volatile pollutants in the soil.

[0038] The target sampling party is configured to obtain the location information of the on-site sampling position when arriving at the sampling point for on-site sampling. When it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions based on the location information of the sampling point and the location information of the on-site sampling position, an offset sampling application is submitted to the quality control party. The offset sampling application includes the reason for the offset and supporting information.

[0039] As an example, the quality control party 101 can specifically determine the target sampling party (i.e., sampling unit, which can be a county-level or city-level sampling agency, etc.) that performs the soil sampling task based on the point information of the points to be sampled, such as the location information of the points to be sampled. For example, the quality control party 102 is a "provincial station" server set in Province A, and the points to be sampled are risk monitoring points in City B of Province A. Then, the "provincial station" of Province A can specifically select a subset or a full set of sampling units distributed in the counties and districts of City B to perform the soil sampling task. The subset or full set of sampling units in the counties and districts of City B here is the target sampling party. In actual applications, the sampling personnel of the sampling unit can carry a handheld sampling terminal device when performing the soil sampling task, fill in the sampling-related information through the handheld sampling terminal device and receive the audit results returned by the quality control party, so as to standardize the entire sampling process and reduce the errors that may occur in the sampling process.

[0040] As an example, when the target sampling party (sampling unit) receives the soil sampling task assigned by the "provincial station", it can first organize relevant sampling personnel to conduct pre-sampling training. The content of the training may include: the layout principles of the national soil environment monitoring network, the reasons for the layout, the geographical location of the sampling points, the water system, and the land use mode, and the collection of soil types and basic geological information in the sampling area; explaining the pollution sources around the sampling points, farmland fertilization, pesticide spraying, land freezing, paddy field irrigation period, etc.; explaining the sampling schedule, itinerary route, etc.; calibrating the global positioning system equipment (GPS), debugging the explanation of the handheld sampling terminal and portable printer, etc. Then, the sampling personnel carry the handheld sampling terminal and arrive at the address of the sampling point according to the established itinerary for on-site sampling. When the sampling personnel of the sampling unit carry the handheld sampling terminal to the address or area where the sampling point is located, the handheld sampling terminal can be used to obtain the location information of the on-site sampling location (such as GPS longitude, GPS latitude).

[0041] As an example, when it is determined based on the point information (position information) of the point to be sampled and the position information of the on-site sampling position that the offset distance between the on-site sampling position and the position of the point to be sampled exceeds the preset allowable error range (which can be flexibly set according to actual conditions, such as ≤30 meters, ≤50 meters, etc.), it is determined that the pre-sampling plan for the point to be sampled does not meet the preset on-site sampling conditions. At this time, the sampling personnel can use the handheld sampling terminal to submit an offset sampling application to the quality control party.

[0042] Among them, the application for offset sampling needs to fill in the reasons for reporting the offset and attach the corresponding supporting materials. The reasons for offset generally include: ① Inability to reach due to natural or man-made force majeure: such as natural terrain blocking and climbing difficulties; ② Inability to reach due to sudden accidents: such as road collapse or flooding, dangerous animals appearing, and temporary road closures; ③ Inability to sample due to natural or man-made force majeure: such as exposed bedrock, inability to dig, temporary flooding of land (agricultural land), quicksand, and swamp subsidence; ④ Changes in land use: such as urban expansion, construction land, road widening, residential areas, military restricted areas, unorganized landfills, tourist resorts, located in permanent water bodies (rivers, lakes, reservoirs, ponds, ditches, and cultivated land permanently turned into ponds), and adjustments to the scope of protected areas; ⑤ Inconsistency with historical point information: such as incorrect latitude and longitude, incorrect address information, and incorrect soil attribute information; ⑥ GPS signal or system deviation. Supporting information usually includes supporting photos, for example, photos taken to reflect the conditions at the on-site sampling location (such as GPS photos of the on-site sampling location).

[0043] The quality control party is also configured to review the offset sampling application and return the review result to the target sampling party.

[0044] The target sampling party is also configured to start a preset offset sampling procedure when receiving an audit result indicating that the audit is passed, and to feed back the sampling information to the quality control party.

[0045] As an example, a preset offset sampling program can be downloaded to a handheld sampling terminal device in advance to avoid going to the on-site sampling location, where the network is poor, the download time is too long or the download cannot be completed, thus affecting the sampling progress. The offset sampling program includes the sampling location of the offset sampling point and the offset sampling plan.

[0046] The technical solution provided by the embodiment of the present disclosure provides a soil sampling monitoring system, including a quality control party and a target sampling party connected to the quality control party in communication; the quality control party is configured to issue a soil sampling task to each target sampling party, and the soil sampling task includes the point information of the sampling point to be sampled and the pre-collection plan; the target sampling party is configured to obtain the location information of the on-site sampling position when arriving at the sampling point to be sampled for on-site sampling, and when it is determined that the pre-collection plan does not meet the preset on-site sampling conditions according to the point information of the sampling point to be sampled and the location information of the on-site sampling position, submit an offset sampling application to the quality control party, and the offset sampling application includes the offset reason and supporting materials; the quality control party is also configured to review the offset sampling application and return the review result to the target sampling party; the target sampling party is also configured to start the preset offset sampling program when the review result is received as approved, and feedback the sampling information to the quality control party. The present disclosure can effectively reduce or avoid errors that may occur in the soil sampling process by flexibly adjusting and monitoring the overall sampling process by the quality control party and the target sampling party, thereby improving the accuracy and reliability of soil environmental monitoring data.

[0047] Figure 2 FIG. 1 is a schematic diagram of another soil sampling monitoring system provided by an embodiment of the present disclosure. Figure 2 As shown, the soil sampling monitoring system of this embodiment is similar to the above Figure 1 The soil sampling monitoring system shown is different only in that it also includes: a general quality control party 103 that is communicatively connected to the quality control party 101 .

[0048] As an example, the general quality control party 103 is configured to issue soil sampling tasks or risk monitoring points to the quality control party, and the risk monitoring points include general risk points and key risk points. The quality control party 101 is configured to obtain soil sampling tasks and verify the point information of the points to be sampled in the soil sampling tasks. When the verification result is passed, the soil sampling task is issued to the target sampling party.

[0049] The total quality control party 103 may be a server that provides various services, for example, a background server that receives information sent by the quality control party 101 or the target sampling party 102 that establishes a communication connection with the background server. The background server may receive and analyze the application or information sent by the quality control party 101 or the target sampling party 102, and generate a processing result. The server may be a single server, a server cluster consisting of several servers, or a cloud computing service center, which is not limited in the embodiments of the present disclosure.

[0050] In one embodiment, the general quality control party 103 may specifically refer to a server that manages the quality monitoring and management of soil sampling throughout the country, which may be referred to as the "main station" for short.

[0051] In the disclosed embodiment, the hierarchical relationship among the general quality control party 103 ("general station"), the quality control party 101 ("provincial station"), and the target sampling party 102 ("sampling unit") is as follows: the "general station" manages the overall soil sampling work of the "provincial station" and the "sampling unit", the "provincial station" assigns soil sampling tasks to the "sampling unit" and reviews the point information of the sampling points, etc., and the "sampling unit" is responsible for organizing the sampling personnel to go to the site for sampling and feedback the sampling situation (including the sample information, the on-site sampling environment, etc.).

[0052] In one embodiment, the general quality control party 103 can first obtain the latest national soil environment monitoring network, and extract the point information of the basic points and background points in the monitoring network (including address information, longitude, latitude, etc.), and formulate corresponding soil sampling tasks based on the point information of the basic points and background points, and then send them to each quality control party 101 ("provincial station"). After receiving the soil sampling task issued by the general quality control party 103, the quality control party 101 can first check the point information in the soil sampling task and feedback the verification results to the general quality control party. The verification content mainly includes three categories: point information doubts, point deletion and supplement, and point replacement.

[0053] Point information in doubt means: part of the point information needs to be changed, such as: the point information (address, attributes, longitude and latitude, etc.) is inconsistent with the submitted historical point information; inconsistent with the basic information of the current area, etc. When applying for this item, you need to submit attachments that can prove the historical point information or the current status. Point deletion and addition means: a point in the point database has been identified and deleted in historical monitoring or a point needs to be added from the point database. Point replacement means: the task point issued is incorrect, and other points in the point database need to be replaced.

[0054] In one embodiment, when the general quality control party receives the above-mentioned verification results fed back by the quality control party, the information in the point database can be automatically updated according to the verification results. Then, the quality control party can check the update status of the point database and send the soil sampling task to the corresponding target sampling party after the point information of the sampling point is correct.

[0055] In another embodiment, after verifying the point information of all sampling points in the soil sampling task, the quality control party 101 can send the verification results to the general quality control party 103, and after receiving the approval message returned by the general quality control party 103, the soil sampling task is sent to the corresponding target sampling party so that the target sampling party can implement the soil sampling task.

[0056] As another example, the quality control party 101 is configured to select at least one target risk point information from the general risk point information, determine the soil sampling task based on the target risk point information and the key risk point information, and verify the point information of the points to be sampled in the soil sampling task. When the verification result is passed, the soil sampling task is issued to each target sampling party.

[0057] Among them, general risk points usually include priority protection points affected by industrial sources (points where the difference between the highest content of heavy metal elements in the point and its corresponding index value is within the preset first numerical range), soil detailed survey points (agricultural land) affected by agriculture or other sources, monitoring points retained by the national network (i.e. the above-mentioned "latest national soil environmental monitoring network"), and monitoring points of cadmium-related pollution sources that take control or restoration measures. Key risk points are usually safe utilization points that are continuously affected by industrial sources (points where the difference between the highest content of heavy metal elements in the point and its corresponding index value is within the preset second numerical range). The first numerical range and the second numerical range here can be flexibly set according to actual conditions, and can be set specifically according to relevant national standards, and no specific restrictions are made here. In practical applications, agricultural plots whose difference falls within the first numerical range can be determined as lightly polluted or unpolluted heavy metal plots (i.e. priority protection points); agricultural plots whose difference falls within the second numerical range can be determined as moderately polluted heavy metal plots (i.e. safe utilization points).

[0058] As an example, the general quality control party may first extract all risk monitoring points (including general risk points and key risk points) from the national network, and then send them to the quality control party; after obtaining the risk monitoring points, the quality control party may select at least one target risk point from the general risk points according to actual conditions, and then formulate a soil sampling task based on the selected target risk points and key risk points; then, check the point information in the soil sampling task, and feed back the verification results to the general quality control party. After receiving the approval message from the general quality control party, the soil sampling task is sent to the corresponding target sampling party so that the target sampling party can implement the soil sampling task.

[0059] As a preferred embodiment, the soil sampling task issued may also include sampling task deployment, division of labor among sampling personnel, sampling time nodes, sampling preparation, sampling volume, number of sampling portions, sampling precautions, etc.

[0060] In some embodiments, the above steps of verifying the point information of the points to be sampled in the soil sampling task, and when the verification result is passed, issuing the soil sampling task to each target sampling party, include:

[0061] Check the number of sampling points, location information, code of sampling points, and basic information of the areas where sampling points are located one by one to obtain the verification results of each item;

[0062] When the verification results of each item are qualified, obtain satellite images of the points to be sampled, and determine the pre-collection plan for the points to be sampled based on the satellite images;

[0063] A soil sampling task is issued to each target sampling party, and the soil sampling task includes the point information of the sampling points and the pre-sampling plan.

[0064] Among them, the basic information of the area where the point is located includes information such as the name of the administrative district where the point is located.

[0065] As an example, when the verification results of the number of points, point location information, point code, and basic information of the area where a certain sampling point A is located are all qualified, a satellite image of the sampling point A is further obtained, and the pre-sampling plan for the sampling point is determined by analyzing its satellite image.

[0066] In one embodiment, determining a pre-sampling plan for a point to be sampled based on a satellite image specifically includes the following steps:

[0067] Determine whether the surrounding environment of the sampling point has changed and whether it is feasible based on satellite images; if the surrounding environment of the sampling point has changed and its feasibility is in doubt, find alternative sampling points that meet the preset offset sampling conditions in the area within the preset distance value range from the sampling point, and determine the pre-sampling plan.

[0068] Specifically, the environmental information (including vegetation distribution, building distribution, etc.) around the sampling point (e.g., within a radius of 30 meters with the sampling point as the center) can be analyzed to determine whether there is any change compared with the environmental information around the sampling point recorded in the historical records. For example, some buildings have been added around the sampling point (there are no such buildings around the sampling point recorded in the historical records). Furthermore, the sampling feasibility can be determined by analyzing the environmental information around the sampling point (for example, whether a representative soil sample that can represent the soil substance to be monitored at the sampling point can be collected, or whether a soil sample can be collected).

[0069] For example, if the surrounding environment of the sampling point is determined to have changed (such as agricultural land becoming a construction site) based on the analysis and observation of satellite images, and the feasibility of the sampling point is in doubt (such as it is uncertain whether the sampling point can collect a representative soil sample), then an alternative sampling point that meets the preset offset sampling conditions is searched in an area within a preset distance value range from the sampling point, and a pre-collection plan is determined. The preset distance value range can be flexibly set according to the actual situation, for example, it can be set to ≤30 meters, 50 meters, etc.

[0070] Exemplarily, given a preset distance value range of ≤30 meters, a circle can be drawn with the point to be sampled as the center and a radius of 30 meters, and then an alternative sampling point that meets the preset offset sampling condition can be found in the circle. Among them, the alternative sampling point that meets the preset offset sampling condition refers to a point that can collect soil samples that can replace the soil samples originally sampled at the point to be sampled. For example, the closer the soil sample is to the center position of the point to be sampled (such as the center position of the point to be sampled), the more it can reflect the soil composition of the point. In practical applications, the feasibility of the point to be sampled is usually uncertain or lost due to various objective reasons (such as the above-mentioned offset reasons). At this time, a circle can be drawn with a radius of 30 meters with the point to be sampled as the center, and at least one alternative sampling point (such as any one or more positions in the circle) can be found in the circle to replace the center position (ideal sampling position) of the point to be sampled, so as to determine the corresponding pre-collection plan.

[0071] In the embodiment of the present disclosure, by verifying the point information of the sampling point, and when it is determined based on the satellite image that the surrounding environment of the sampling point has changed and the feasibility of the sampling point is uncertain, an alternative sampling point that meets the preset offset sampling conditions is searched in an area within a preset distance value range from the sampling point, and a pre-collection plan is determined, so that when the target sampling party arrives at the on-site sampling, the offset sampling work can be carried out in a targeted manner to improve the sampling efficiency.

[0072] In some embodiments, the above steps, when it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions according to the point information of the sampling point and the position information of the on-site sampling position, submitting an offset sampling application to the quality control party includes:

[0073] Determine the offset distance between the on-site sampling position and the point to be sampled according to the point information of the point to be sampled and the position information of the on-site sampling position;

[0074] If the offset distance is not within the preset allowable distance range, it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions, and an offset sampling application is submitted to the quality control party.

[0075] As an example, the offset distance between the on-site sampling position and the point to be sampled is calculated based on the position information (longitude, latitude) of the point to be sampled and the position information (longitude, latitude) of the on-site sampling position.

[0076] The preset allowable distance range can be flexibly set according to actual conditions, for example, it can be set to ≤30 meters, 50 meters, etc.

[0077] For example, assuming that the preset allowable distance range is ≤50 meters, the offset distance between the on-site sampling position a and the sampling point A is 125 meters (greater than 30 meters, that is, not within the preset allowable distance range), then it is determined that the pre-sampling plan corresponding to the sampling point A does not meet the on-site sampling conditions. At this time, the sampling personnel can submit an offset sampling application to the quality control party through a handheld sampling terminal.

[0078] In some embodiments, in the above steps, if the offset distance is not within the preset allowable distance range, it is determined that the pre-collection plan does not meet the preset on-site sampling conditions, and after submitting the offset sampling application to the quality control party, it also includes:

[0079] If the offset distance is within the preset allowable distance range, the sampling environment information of the on-site sampling location is collected;

[0080] When it is determined based on the sampling environment information that the soil at the on-site sampling location is not mineable or there is a better sampling location, it is determined that the pre-collection plan does not meet the preset on-site sampling conditions, and an offset sampling application is submitted to the quality control party.

[0081] As an example, if the offset distance between the on-site sampling position a and the sampling point A is 25 meters (within the preset distance range of ≤50 meters), the sampling environment information of the on-site sampling position is collected. The sampling environment information includes the altitude of the on-site sampling position, surrounding information (such as all land use conditions in four directions within a range of 1km), topography, soil type, land use type, crop type, and irrigation water type.

[0082] If, based on the sampling environment information of the on-site sampling location collected as above, it is determined that the soil at the on-site sampling location is not mineable or there is a better sampling location, it can be considered necessary to adjust the on-site sampling location. At this time, the sampling personnel can use the handheld sampling terminal to submit an offset sampling application to the quality control party.

[0083] In the embodiment of the present disclosure, by determining that the offset distance between the on-site sampling location and the point to be sampled is within a preset allowable distance range, further collecting sampling environment information of the on-site sampling location, and judging based on the sampling environment information that the soil at the current on-site sampling location is not sampleable or there is a better sampling location, an offset sampling application is submitted to the quality control party, and then the sampling plan is flexibly adjusted, which is conducive to improving the quality of soil sampling, thereby improving the accuracy and reliability of soil monitoring data.

[0084] In some embodiments, the above steps of reviewing the offset sampling application and returning the review result to the target sampling party include:

[0085] Review the deviation reasons and the completeness of the supporting documents, mark the unqualified items, and obtain the first review result;

[0086] Review the deviation reasons and the filling standard of supporting materials, mark and modify the unqualified items, and obtain the second review results;

[0087] The first audit result and the second audit result are returned to the target sampling party.

[0088] Among them, the reporting completeness mainly involves reviewing whether the information reported by the target sampling party contains point environmental information (information around the sampling point (within 1km) (including 4 directions), altitude, topography, soil type, land use type, crop type and irrigation water type), field work information (including sampling location, weather, sampling equipment and tools), sample information (including sampling depth (cm), soil moisture, soil texture, soil color, sample weight (g) and number of mixture samples), review information (including signatures of sampling team role members), photo information (including 9 sampling photos (before sampling, GPS photos, verification personnel, sampling personnel, east, south, west, north, after sampling), monitoring source investigation information (including 10 items: whether the enterprise is closed and relocated, current enterprise name, unified social credit code, enterprise center longitude, enterprise center latitude; enterprise establishment year (year), enterprise type, industry type, pollution impact type and emission pollutant type).

[0089] The reporting standardization mainly includes three categories: basic information, photo retention records, and sampling review management. Information reporting should comply with the relevant technical requirements of the national network soil environment monitoring. For example, the basic information reporting rules include: ① Sample weight (g): ≥2000; ② Sampling depth (cm): fill in 0~20, and the difference should be between ±5cm and the scale display in the photo after sampling; ③ Information around the sampling point (within 1km): The description is consistent with the four-direction display of the photo (4 directions); ④ Land use is consistent with the photo; ⑤ Crop type is consistent with the photo; ⑥ Sampling equipment: meet the needs of different sample collection, at least including cloth bags, polyethylene bags, brown ground mouth sample bottles, and rulers; ⑦ Sampling tools: meet the needs of different sample collection, at least including iron shovels, wooden shovels, and bamboo chips; ⑧ Altitude; ⑨ Number of mixed sampling: 5.

[0090] As an example, the quality control party ("provincial station") reviews the reasons for deviation and the completeness of supporting materials reported by the target sampling party, marks the unqualified items, modifies and marks the items that are not filled in in a standardized manner, and then feeds back the review results to the target sampling party, so that the target sampling party can make corresponding modifications based on the review results and re-report or obtain approval to carry out the deviation sampling.

[0091] The technical solution provided by the embodiment of the present disclosure can standardize the soil sampling process and reduce errors occurring during the sampling process by reviewing the offset sampling applications reported by the target sampling party, thereby ensuring the accuracy and reliability of subsequent monitoring data.

[0092] Figure 3 It is a flow chart of a soil sampling and monitoring method provided in an embodiment of the present disclosure. Figure 2 The soil sampling monitoring method can be Figure 1 The target sampling method 102 is executed. Figure 2 As shown, the soil sampling monitoring method includes:

[0093] Step S301, obtaining a soil sampling task issued by a quality control party, the soil sampling task including point information of the points to be sampled and a pre-sampling plan;

[0094] Step S302, determining the on-site sampling location according to the point information, and obtaining the location information of the on-site sampling location;

[0095] Step S303, when it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions based on the point information and the location information of the on-site sampling location, an offset sampling application is submitted to the quality control party, and the offset sampling application includes the reason for the offset and supporting information.

[0096] The technical solution provided by the embodiment of the present disclosure obtains a soil sampling task issued by a quality control party, wherein the soil sampling task includes the point information of the points to be sampled and a pre-sampling plan; determines the on-site sampling location according to the point information, and obtains the location information of the on-site sampling location; when it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions according to the point information and the location information of the on-site sampling location, submits an offset sampling application to the quality control party, wherein the offset sampling application includes the reason for the offset and supporting information, and can flexibly adjust the sampling plan according to the on-site sampling environmental conditions during on-site sampling, thereby reducing errors that may occur during the sampling process, which is beneficial to improving the accuracy and reliability of subsequent soil monitoring and analysis results.

[0097] In some embodiments, the above step S303 includes:

[0098] Determine the offset distance between the on-site sampling position and the point to be sampled according to the point information of the point to be sampled and the position information of the on-site sampling position;

[0099] If the offset distance is not within the preset allowable distance range, it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions, and an offset sampling application is submitted to the quality control party.

[0100] In some embodiments, if the offset distance is within a preset allowable distance range, the sampling environment information of the on-site sampling location is collected; when it is determined based on the sampling environment information that the soil at the on-site sampling location is not mineable or there is a better sampling location, it is determined that the pre-collection plan does not meet the preset on-site sampling conditions, and an offset sampling application is submitted to the quality control party.

[0101] Figure 4 FIG. 1 is a flow chart of another soil sampling monitoring method provided by an embodiment of the present disclosure. Figure 4 As shown, the soil sampling monitoring method comprises the following steps:

[0102] Step S401: The quality control party issues a soil sampling task to the target sampling party, where the soil sampling task includes the point information of the sampling point and the pre-sampling plan;

[0103] Step S402: The target sampling party, when arriving at the sampling point for on-site sampling, obtains the location information of the on-site sampling position, and when it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions based on the location information of the sampling point and the location information of the on-site sampling position, submits an application for offset sampling to the quality control party, and the application for offset sampling includes the reason for the offset and supporting information;

[0104] Step S403: The quality control party reviews the offset sampling application and returns the review result to the target sampling party;

[0105] Step S404: When the target sampling party receives the audit result that the audit is passed, it starts the preset offset sampling program and feeds back the sampling information to the quality control party.

[0106] In some embodiments, the above method further comprises:

[0107] The general quality control party issues soil sampling tasks or risk monitoring points to the quality control party. The risk monitoring points include general risk points and key risk points;

[0108] The quality control party obtains the soil sampling task and verifies the point information of the sampling points in the soil sampling task. When the verification result is passed, the soil sampling task is issued to the target sampling party; or,

[0109] The quality control party selects at least one target risk point from the general risk points, determines the soil sampling task based on the target risk points and key risk points, and verifies the point information of the points to be sampled in the soil sampling task. When the verification result is passed, the soil sampling task is issued to the target sampling party.

[0110] In some embodiments, the above steps of verifying the point information of the points to be sampled in the soil sampling task, and when the verification result is passed, issuing the soil sampling task to the target sampling party, include:

[0111] Check the number of sampling points, location information, code of sampling points, and basic information of the areas where sampling points are located one by one to obtain the verification results of each item;

[0112] When the verification results of each item are qualified, obtain satellite images of the points to be sampled, and determine the pre-collection plan for the points to be sampled based on the satellite images;

[0113] A soil sampling task is issued to the target sampling party, which includes the point information of the sampling points and the pre-sampling plan.

[0114] In some embodiments, the above step of determining a pre-sampling plan for the sampling point according to the satellite image includes:

[0115] Determine whether the surrounding environment of the sampling point has changed and whether it is feasible based on satellite images;

[0116] If the surrounding environment of the sampling point changes and its feasibility is in doubt, an alternative sampling point that meets the preset offset sampling conditions is searched in an area within a preset distance value range from the sampling point, and a pre-sampling plan is determined.

[0117] In some embodiments, the above steps, when it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions according to the point information of the sampling point and the position information of the on-site sampling position, submitting an offset sampling application to the quality control party includes:

[0118] Determine the offset distance between the on-site sampling position and the point to be sampled according to the point information of the point to be sampled and the position information of the on-site sampling position;

[0119] If the offset distance is not within the preset allowable distance range, it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions, and an offset sampling application is submitted to the quality control party.

[0120] In some embodiments, if the offset distance is within a preset allowable distance range, the sampling environment information of the on-site sampling location is collected; when it is determined based on the sampling environment information that the soil at the on-site sampling location is not mineable or there is a better sampling location, it is determined that the pre-collection plan does not meet the preset on-site sampling conditions, and an offset sampling application is submitted to the quality control party.

[0121] In some embodiments, the above steps of reviewing the offset sampling application and returning the review result to the target sampling party include:

[0122] Review the deviation reasons and the completeness of the supporting documents, mark the unqualified items, and obtain the first review result;

[0123] Review the deviation reasons and the filling standard of supporting materials, mark and modify the unqualified items, and obtain the second review results;

[0124] The first audit result and the second audit result are returned to the target sampling party.

[0125] All the above optional technical solutions can be arbitrarily combined to form optional embodiments of the present application, which will not be described one by one here.

[0126] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present disclosure.

[0127] Figure 5 is a schematic diagram of an electronic device 500 provided in an embodiment of the present disclosure. Figure 5 As shown, the electronic device 500 of this embodiment includes: a processor 501, a memory 502, and a computer program 503 stored in the memory 502 and executable on the processor 501. When the processor 501 executes the computer program 503, the steps in the above-mentioned method embodiments are implemented. Alternatively, when the processor 501 executes the computer program 503, the functions of the modules / units in the above-mentioned device embodiments are implemented.

[0128] Exemplarily, the computer program 503 may be divided into one or more modules / units, which are stored in the memory 502 and executed by the processor 501 to complete the present disclosure. The one or more modules / units may be a series of computer program instruction segments capable of completing specific functions, which are used to describe the execution process of the computer program 503 in the electronic device 500.

[0129] The electronic device 500 may be a desktop computer, a notebook, a PDA, a cloud server, or other electronic device. The electronic device 500 may include, but is not limited to, a processor 501 and a memory 502. Those skilled in the art will appreciate that Figure 5 It is only an example of the electronic device 500 and does not constitute a limitation of the electronic device 500. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, the electronic device may also include input and output devices, network access devices, buses, etc.

[0130] The processor 501 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or the processor may be any conventional processor, etc.

[0131] The memory 502 may be an internal storage unit of the electronic device 500, for example, a hard disk or memory of the electronic device 500. The memory 502 may also be an external storage device of the electronic device 500, for example, a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (Secure Digital, SD) card, a flash card (Flash Card), etc. equipped on the electronic device 500. Further, the memory 502 may also include both an internal storage unit of the electronic device 500 and an external storage device. The memory 502 is used to store computer programs and other programs and data required by the electronic device. The memory 502 may also be used to temporarily store data that has been output or is to be output.

[0132] The technicians in the relevant field can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example for illustration. In practical applications, the above-mentioned function allocation can be completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiment can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units and modules are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units and modules in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.

[0133] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0134] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this disclosure.

[0135] In the embodiments provided in the present disclosure, it should be understood that the disclosed devices / electronic devices and methods can be implemented in other ways. For example, the device / electronic device embodiments described above are merely schematic. For example, the division of modules or units is only a logical function division. There may be other division methods in actual implementation. Multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed may be through some interfaces, indirect coupling or communication connection of devices or units, which may be electrical, mechanical or other forms.

[0136] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0137] In addition, each functional unit in each embodiment of the present disclosure may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0138] If the integrated module / unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present disclosure implements all or part of the processes in the above-mentioned embodiment method, and can also be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. The computer program may include computer program code, and the computer program code may be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may include: any entity or device capable of carrying computer program code, recording medium, U disk, mobile hard disk, magnetic disk, optical disk, computer memory, read-only memory (ROM), random access memory (RAM), electric carrier signal, telecommunication signal and software distribution medium. It should be noted that the content contained in the computer-readable medium can be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, the computer-readable medium does not include electric carrier signals and telecommunication signals.

[0139] The above embodiments are only used to illustrate the technical solutions of the present disclosure, rather than to limit them. Although the present disclosure has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present disclosure, and should all be included in the protection scope of the present disclosure.

Claims

1. A soil sampling monitoring system, characterized in that: It includes a quality control party and a target sampling party that is in communication connection with the quality control party; The quality control party is configured to issue a soil sampling task to the target sampling party, wherein the soil sampling task includes point information of the points to be sampled and a pre-sampling plan; The target sampling party is configured to obtain the location information of the on-site sampling position when arriving at the sampling point for on-site sampling, and when it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions according to the location information of the sampling point and the location information of the on-site sampling position, submit an application for offset sampling to the quality control party, wherein the application for offset sampling includes the reason for the offset and supporting information; The quality control party is further configured to review the offset sampling application and return the review result to the target sampling party; The target sampling party is further configured to start a preset offset sampling procedure when receiving the audit result that the audit is passed, and to feed back sampling information to the quality control party; The system further comprises: a general quality control party in communication connection with the quality control party; The general quality control party is configured to issue soil sampling tasks or risk monitoring points to the quality control party, and the risk monitoring points include general risk points and key risk points; The quality control party is configured to obtain the soil sampling task and verify the point information of the points to be sampled in the soil sampling task, and when the verification result is passed, send the soil sampling task to the target sampling party; or, The quality control party is configured to select at least one target risk point from the general risk points, determine a soil sampling task according to the target risk point and the key risk point, and verify the point information of the points to be sampled in the soil sampling task, and when the verification result is passed, issue the soil sampling task to the target sampling party; The step of checking the point information of the points to be sampled in the soil sampling task and issuing the soil sampling task to the target sampling party when the checking result is passed includes: The number of points to be sampled, the point location information, the point code, and the basic information of the area where the points are located are checked item by item to obtain the verification results of each item; When the verification results of the items are all qualified, obtaining a satellite image of the point to be sampled, and determining a pre-collection plan for the point to be sampled according to the satellite image; A soil sampling task is issued to the target sampling party, wherein the soil sampling task includes the point information of the to-be-sampled points and a pre-sampling plan.

2. The system according to claim 1, characterized in that The step of determining a pre-sampling scheme for the to-be-sampled point according to the satellite image comprises: Determine whether the surrounding environment of the sampling point has changed and whether it is feasible according to the satellite image; If the surrounding environment of the sampling point changes and its feasibility is in doubt, an alternative sampling point that meets the preset offset sampling conditions is searched in an area within a preset distance value range from the sampling point, and a pre-sampling plan is determined.

3. The system according to claim 1, characterized in that When it is determined that the pre-sampling scheme does not meet the preset on-site sampling conditions according to the point information of the to-be-sampled point and the position information of the on-site sampling position, submitting an offset sampling application to the quality control party includes: Determine the offset distance between the on-site sampling position and the point to be sampled according to the point information of the point to be sampled and the position information of the on-site sampling position; If the offset distance is not within the preset allowable distance range, it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions, and an offset sampling application is submitted to the quality control party.

4. The system according to claim 3, characterized in that If the offset distance is not within the preset allowable distance range, it is determined that the pre-collection plan does not meet the preset on-site sampling conditions, and after submitting the offset sampling application to the quality control party, it also includes: If the offset distance is within a preset allowable distance range, collecting sampling environment information of the on-site sampling location; When it is determined based on the sampling environment information that the soil at the on-site sampling location is not mineable or there is a better sampling location, it is determined that the pre-collection plan does not meet the preset on-site sampling conditions, and an offset sampling application is submitted to the quality control party.

5. The system according to claim 1, characterized in that The reviewing of the offset sampling application and returning the review result to the target sampling party includes: Review the reasons for the deviation and the completeness of the supporting materials, mark the unqualified items, and obtain the first review result; Review the deviation reasons and the filling standard of supporting materials, mark and modify the unqualified items, and obtain the second review result; The first audit result and the second audit result are returned to the target sampling party.

6. A soil sampling monitoring method, characterized in that: include: Obtaining a soil sampling task issued by a quality control party, wherein the soil sampling task includes point information of a to-be-sampled point and a pre-sampling plan; Determine the on-site sampling location according to the point information, and obtain the location information of the on-site sampling location; When it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions according to the point information and the location information of the on-site sampling location, submitting an application for offset sampling to the quality control party, wherein the application for offset sampling includes the reason for the offset and supporting information; Among them, the soil sampling tasks issued by the quality control party include: The quality control party obtains the soil sampling task issued by the general quality control party, and verifies the point information of the points to be sampled in the soil sampling task. When the verification result is passed, the soil sampling task is issued to the target sampling party; or, The quality control party selects at least one target risk point from the general risk points issued by the general quality control party, determines the soil sampling task according to the target risk point and the key risk points issued by the general quality control party, and verifies the point information of the points to be sampled in the soil sampling task, and when the verification result is passed, issues the soil sampling task to the target sampling party; The step of checking the point information of the points to be sampled in the soil sampling task and issuing the soil sampling task to the target sampling party when the checking result is passed includes: The number of points to be sampled, the point location information, the point code, and the basic information of the area where the points are located are checked item by item to obtain the verification results of each item; When the verification results of the items are all qualified, obtaining a satellite image of the point to be sampled, and determining a pre-collection plan for the point to be sampled according to the satellite image; A soil sampling task is issued to the target sampling party, wherein the soil sampling task includes the point information of the to-be-sampled points and a pre-sampling plan.

7. The method according to claim 6, characterized in that When it is determined that the pre-sampling scheme does not meet the preset on-site sampling conditions according to the point information of the to-be-sampled point and the position information of the on-site sampling position, submitting an offset sampling application to the quality control party includes: Determine the offset distance between the on-site sampling position and the point to be sampled according to the point information of the point to be sampled and the position information of the on-site sampling position; If the offset distance is not within the preset allowable distance range, it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions, and an offset sampling application is submitted to the quality control party.

8. A soil sampling monitoring method, characterized in that: include: The general quality control party issues soil sampling tasks or risk monitoring points to the quality control party, and the risk monitoring points include general risk points and key risk points; The quality control party obtains the soil sampling task, and verifies the point information of the points to be sampled in the soil sampling task, and when the verification result is passed, sends the soil sampling task to the target sampling party; or, selects at least one target risk point from the general risk points, determines the soil sampling task according to the target risk point and the key risk point, and verifies the point information of the points to be sampled in the soil sampling task, and when the verification result is passed, sends the soil sampling task to the target sampling party; the soil sampling task includes the point information of the points to be sampled and the pre-collection plan; The target sampling party, when arriving at the sampling point for on-site sampling, obtains the location information of the on-site sampling position, and when it is determined that the pre-sampling plan does not meet the preset on-site sampling conditions based on the location information of the sampling point and the location information of the on-site sampling position, submits an application for offset sampling to the quality control party, wherein the application for offset sampling includes the reason for the offset and supporting information; The quality control party reviews the offset sampling application and returns the review result to the target sampling party; The target sampling party, when receiving the audit result that the audit is passed, starts the preset offset sampling program and feeds back the sampling information to the quality control party; The step of checking the point information of the points to be sampled in the soil sampling task and issuing the soil sampling task to the target sampling party when the checking result is passed includes: The number of points to be sampled, the point location information, the point code, and the basic information of the area where the points are located are checked item by item to obtain the verification results of each item; When the verification results of the items are all qualified, obtaining a satellite image of the point to be sampled, and determining a pre-collection plan for the point to be sampled according to the satellite image; A soil sampling task is issued to the target sampling party, wherein the soil sampling task includes the point information of the to-be-sampled points and a pre-sampling plan.