A drilling and anchoring trolley grouting system and control method thereof

By using the mixing and boosting unit driven by a variable frequency motor in the drilling and anchoring trolley grouting system, combined with the circulation pipeline and valve control, the problems of slurry solidification, waste, motor life and cleaning are solved, and the slurry is not hardened. , adjustable slurry output and quick cleaning effect, improving construction efficiency and safety.

CN114352328BActive Publication Date: 2024-10-18XUZHOU XUGONG FOUNDATION CONSTRUCTION MACHINERY CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202210012785.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-06
Publication Date
2024-10-18
Estimated Expiration
2042-01-06

AI Technical Summary

Technical Problem

The existing drilling and anchoring trolley grouting system has problems such as irreversible solidification of slurry, waste of slurry, reduced motor life, water consumption for cleaning and stuck spiral boosting unit. It is especially difficult to effectively solve the problems of small grouting volume and troubleshooting. .

Method used

A grouting system including a control module and an execution module is adopted, and a variable frequency motor is used to drive the mixing and boosting unit to realize slurry mixing, flow control and circulation cleaning, ensuring that the slurry does not harden, the slurry output is adjustable, and the slurry output is quickly cleaned and unblocked. lag function.

Benefits of technology

It effectively prevents slurry from hardening, saves slurry and water resources, extends the life of the motor, enables rapid cleaning and clearing of jams, and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114352328B_ABST
    Figure CN114352328B_ABST
Patent Text Reader

Abstract

The present invention discloses a drilling and grouting anchor trolley grouting system and a control method thereof. The grouting system includes a control module and an execution module; the control module is connected to the execution module; the execution module includes a stirring unit, a slurry storage unit, and a spiral booster unit, and the stirring unit is connected to the slurry storage unit through a slurry delivery pipe; one end of the spiral booster unit is connected to the lower part of the slurry storage unit, and the other end is connected to the stirring unit through a main pipe cavity and a circulation pipeline in sequence; the main pipe cavity is connected to a water pipe through a water valve, and the main pipe cavity is also connected to a slurry outlet pipe through a slurry outlet valve. This system can prevent the hardening of the mixed slurry during the processing of a drilling and grouting anchor trolley failure; can achieve the purpose of the motor speed being at an appropriate level and the slurry outlet being adjustable during the construction of anchor rods with a small grouting volume; can realize the rapid cleaning of the entire grouting system after the grouting construction is completed; can achieve effective dredging when the spiral booster unit is stuck.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of mine tunnel construction, in particular to a drilling and anchoring trolley grouting system for mine tunnel support construction and a control method thereof. Background Art

[0002] In the construction process of geotechnical engineering such as tunnel engineering, mining engineering, slope and foundation pit, anchor rods are often used to reinforce and support the stratum to prevent the deformation, collapse or instability of the foundation from endangering safety. The high strength of the anchor rods themselves set in the anchor holes of the stratum and the grouting consolidation body formed around the anchor rods are used to reinforce the stratum to improve the integrity of the stratum, thereby controlling the deformation of the stratum and keeping the stratum in a stable and safe state.

[0003] At present, in order to quickly support weak rock formations and broken rock formations, the most advanced equipment used in the industry is the drilling and grouting anchor trolley, which can complete the processes of drilling, grouting, and installing anchor rods. The grouting system generally uses a mixing and grouting integrated machine. The grouting system is Figure 1 As shown, it generally includes a mixing unit, a slurry storage unit, and a spiral supercharging unit. The mixing unit and the spiral supercharging unit are driven by a mixing motor and a supercharging motor respectively. There is a valve with manually controlled opening between the mixing unit and the slurry storage unit. After cement, river sand, water and other materials are manually poured into the mixing unit in proportion, the mixing motor is turned on to finally mix the materials into a uniform slurry; the valve is manually opened to allow all or part of the slurry to flow into the slurry storage unit, and the supercharging motor is turned on. The slurry in the slurry storage unit is pressurized and output through the spiral supercharging unit. During the output process, the spiral supercharging unit will generate a lot of heat. The problems existing in the above grouting system are:

[0004] 1. The cement-containing slurry is irreversible after solidification, and the slurry storage unit has no stirring function. When the slurry flows into the slurry storage unit, it must be discharged through the spiral booster unit in a short time for grouting; the spiral booster unit generates a lot of heat during the transportation process. During the transportation, part of the heat generated will be taken away by the slurry to form a dynamic balance. Once the transportation is stopped, the slurry in the spiral booster unit will harden within a certain period of time, and its hardening speed is faster than the hardening speed of the slurry in the slurry storage unit; once the slurry in the spiral booster unit and the slurry storage unit hardens, it will cause serious accidents. Sometimes unexpected situations occur in the drilling and anchor installation process of the trolley front, and grouting needs to be stopped or delayed. During the process of stopping or delaying grouting, a part of the slurry can be actively discharged at intervals to ensure that the slurry in the increasing mechanism does not harden, and the slurry in the slurry storage unit will not harden due to flow; and once the amount of slurry in the slurry storage unit is not enough to build pressure for the spiral booster unit, the entire grouting system needs to be thoroughly cleaned. This requires that even if grouting is not needed, the slurry must be pressurized and discharged before it hardens, which results in a large amount of waste of slurry.

[0005] 2. The demand for slurry in a single hole of anchor bolt construction is relatively small. If a fixed-frequency motor is used to drive the spiral booster unit, the slurry flow rate is large and the anchor bolt hole will be filled in a short time, which will inevitably cause a large amount of slurry to overflow from the anchor bolt hole, resulting in waste. If a variable-frequency motor is used to drive the spiral booster unit, it needs to be started at high speed to overcome the resistance of the initial slurry delivery. After the actual grouting, the speed needs to be adjusted to a very low level, and the spiral booster unit is prone to jamming at low speeds, and long-term low speeds will reduce the life of the motor.

[0006] 3. After the trolley construction is completed, the grouting system needs to be thoroughly cleaned. At present, the industry generally uses an external water pipe to manually introduce water into the mixing unit, open the valve between the mixing unit and the slurry storage unit, and start the mixing motor and the booster motor. Use water to flush the slurry in the mixing unit and the slurry storage unit. The mixture of water and slurry is finally discharged to the outside through the spiral booster unit. Since the slurry has a certain adhesion, the cleaning process requires a large amount of water, resulting in a certain amount of waste.

[0007] 4. During the slurry transportation process, the spiral booster unit generates a lot of heat. If the interval between two groutings during the construction process exceeds a certain time, the slurry in the spiral booster unit may become hardened to a certain extent, causing the spiral booster unit to get stuck. In addition, if the grouting system is not used for a long time, it may also cause the spiral booster unit to get stuck when it is used again. Summary of the invention

[0008] The technical problem to be solved by the present invention is to overcome the defects of the prior art and provide a drilling and grouting anchor trolley grouting system and a control method thereof, which can prevent the mixed slurry from hardening during the process of handling a malfunction of the drilling and grouting anchor trolley; can achieve the purpose of keeping the motor speed at an appropriate level and adjusting the slurry output during anchor construction with a small grouting volume; can achieve rapid cleaning of the entire grouting system after the grouting construction is completed; and can achieve effective unblocking when the spiral booster unit is stuck.

[0009] In order to solve the above technical problems, the present invention provides a drilling and grouting anchor trolley grouting system, including a control module and an execution module; the control module is connected to the execution module to enable the execution module to perform corresponding actions; the execution module includes a stirring unit, a slurry storage unit, a spiral booster unit, a main pipe cavity, a circulation pipeline, a water valve, a slurry discharge valve, a slurry delivery valve and a circulation valve, and the stirring unit is connected to the slurry storage unit through a slurry delivery pipe; one end of the spiral booster unit is connected to the lower part of the slurry storage unit, and the other end is connected to the stirring unit through the main pipe cavity and the circulation pipeline in sequence; the main pipe cavity is connected to the water pipe through the water valve, and the main pipe cavity is also connected to the slurry discharge pipe through the slurry discharge valve; the slurry delivery pipe is provided with a slurry delivery valve; the circulation pipeline is provided with a circulation valve.

[0010] Furthermore, the control module is connected to the slurry discharge valve and the circulation valve respectively, and controls the opening of the slurry discharge valve and the circulation valve at the same time.

[0011] Furthermore, pressurized water is provided in the water pipe; the control module is connected to the water valve to control the opening of the water valve to enable the pressurized water to enter the main pipe cavity.

[0012] Furthermore, the stirring unit is driven by a variable frequency motor to stir various raw materials put into the stirring unit, and the control module is connected to the variable frequency motor to control the start, stop, direction and speed of the variable frequency motor.

[0013] Furthermore, the spiral boosting unit is driven by a variable frequency motor, and the control module is connected to the variable frequency motor to control the start, stop, direction, and speed of the variable frequency motor to pressurize the slurry in the slurry storage unit and transport it to the main pipe cavity, or to reversely transport the pressure slurry in the main pipe cavity to the slurry storage unit.

[0014] Furthermore, the control module is connected to the slurry delivery valve to control the opening of the slurry delivery valve, thereby controlling the flow rate of the slurry flowing from the stirring unit into the slurry storage unit.

[0015] The present invention also provides a control method for the above-mentioned drilling and anchoring trolley grouting system, comprising:

[0016] Manually put various materials into the mixing unit according to the set proportion, and operate the control module to achieve: the mixing unit works; the slurry delivery valve is closed, the slurry discharge valve is closed, the circulation valve is opened, the water valve is opened, and water enters the mixing unit; when the amount of water entering the mixing unit reaches the requirement, the water valve is closed; when the slurry in the mixing unit is stirred to the right place, the stirring is stopped;

[0017] When grouting is required, the control module is operated to realize: the slurry delivery valve is opened, the water valve is closed, the slurry discharge valve is opened, and the circulation valve is closed; after the slurry completely enters the slurry storage unit, the spiral booster unit starts to work, and the slurry is output at full flow through the slurry discharge pipe;

[0018] When it is necessary to reduce the amount of grouting, the control module is operated to achieve: the slurry delivery valve is opened, the water valve is closed, the slurry discharge valve is opened, the circulation valve is opened to 10% to 50% of the total opening, the mixing unit starts working, the spiral booster unit starts working, and a part of the slurry is output to the front through the slurry discharge pipe for grouting, and the other part of the slurry enters the mixing unit through the circulation pipeline, and then enters the slurry storage unit through the slurry delivery pipe to form a circulation.

[0019] Further, including:

[0020] After the grouting is completed, when the grouting system needs to be cleaned, the control module is operated to implement the following steps:

[0021] The water valve is open, the slurry discharge valve is closed, the circulation valve is open, the slurry delivery valve is closed, and the mixing unit is working;

[0022] After the water volume in the mixing unit reaches the specified requirement, the water valve is closed, the slurry delivery valve is opened, the spiral booster unit is working, and the circulation valve is opened. The diluted turbid slurry circulates among the mixing unit, slurry delivery pipe, slurry delivery valve, slurry storage unit, spiral booster unit, main pipe cavity, circulation valve, and circulation pipeline, continuously washing away the slurry attached to the components;

[0023] After the diluted slurry circulates for 3-5 minutes, its scouring effect is greatly reduced. The water valve can be closed, the slurry delivery valve can be opened, the spiral booster unit can be operated, and the circulation valve can be closed. The diluted turbid slurry can be discharged from the slurry discharge pipe.

[0024] Repeat the above steps until the grouting system is cleaned.

[0025] Further, including:

[0026] When the grouting system is not used for a long time or the spiral booster unit is stuck due to the large particles of the mixed material, the control module is operated to achieve: closing the slurry outlet valve, closing the circulation valve, opening the slurry delivery valve, opening the water valve, and rotating the booster unit in reverse to eliminate the jam of the spiral booster unit.

[0027] The beneficial effects achieved by the present invention are:

[0028] 1. After the slurry enters the slurry storage unit, if there is a problem such as a failure of the front actuator, during the process of stopping or delaying the grouting, the water valve and the slurry outlet valve can be closed, and the circulation valve and the slurry delivery valve can be opened, so that the slurry in the slurry storage unit can circulate between the slurry storage unit, the spiral booster unit, the main pipe cavity, the circulation pipeline, the mixing unit, and the slurry delivery pipe without hardening.

[0029] 2. When grouting anchor holes of different types or sizes, different grout injection volumes are required. The present invention can control the opening of each valve through a control module to achieve the purpose of keeping the motor speed at an appropriate level and adjusting the grout output volume.

[0030] 3. The present invention can save a lot of water when cleaning the grouting system while ensuring the cleaning effect.

[0031] 4. When the grouting system is not used for a long time or the spiral booster unit is stuck due to the excessive size of the mixed material particles, the present invention can achieve rapid unblocking. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 It is a schematic diagram of a grouting system of a drilling and anchoring trolley known at present;

[0033] Figure 2 It is a schematic diagram of the positions of the control module and the execution module of the grouting system of the present invention in the whole machine;

[0034] Figure 3 It is a schematic diagram of the composition and mutual relationship of the execution modules of the grouting system of the present invention.

[0035] In the figure: 1-control module, 2-execution module, 3-mixing unit, 4-slurry delivery pipe, 5-slurry storage unit, 6-slurry delivery valve, 7-spiral booster unit, 8-main pipe cavity, 9-water valve, 10-water pipe, 11-circulation valve, 12-circulation pipeline, 13-slurry discharge valve, 14-slurry discharge pipe. DETAILED DESCRIPTION

[0036] The present invention will be further described below in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present invention.

[0037] Example 1

[0038] like Figure 2 and Figure 3 As shown, a drilling and grouting anchor trolley grouting system includes a control module 1 and an execution module 2; the control module 1 is connected to the execution module 2, and the control module 1 is a part of the drilling and grouting anchor trolley control system. Under the operation of the operator, the control module 1 will make the execution module 2 perform corresponding actions. The execution module 2 includes a stirring unit 3, a slurry storage unit 5, a spiral booster unit 7, a main pipe cavity 8, a circulation pipeline 12, a water valve 9, a slurry discharge valve 13, a slurry delivery valve 6 and a circulation valve 11. The stirring unit 3 is connected to the slurry storage unit 5 through a slurry delivery pipe 4; one end of the spiral booster unit 7 is connected to the lower part of the slurry storage unit 5, and the other end is connected to the stirring unit 3 through the main pipe cavity 8 and the circulation pipeline 12 in turn; the main pipe cavity 8 is connected to the water pipe 10 through the water valve 9, and the main pipe cavity 8 is also connected to the slurry discharge pipe 14 through the slurry discharge valve 13. The slurry delivery pipe 4 is provided with a slurry delivery valve 6. The circulation pipeline 12 is provided with a circulation valve 11.

[0039] Specifically, the control module 1 is connected to the slurry outlet valve 13 and the circulation valve 11 respectively, and controls the opening of the slurry outlet valve 13 and the circulation valve 11 at the same time, so as to control the conveying direction and conveying amount of the pressure slurry in the main lumen 8.

[0040] Specifically, pressurized water is provided in the water pipe 10 ; the control module 1 is connected to the water valve 9 to control the opening of the water valve 9 so as to allow the pressurized water to enter the main pipe cavity 8 .

[0041] Specifically, the stirring unit 3 is driven by a variable frequency motor to stir various raw materials put into the stirring unit 3. The control module 1 is connected to the variable frequency motor to control the start, stop, direction and speed of the variable frequency motor.

[0042] Specifically, the spiral boosting unit 7 is driven by a variable frequency motor, and the control module 1 is connected to the variable frequency motor to control the start, stop, direction, and speed of the variable frequency motor, so as to pressurize the slurry in the slurry storage unit 5 and transport it to the main lumen 8, or reversely transport the pressurized slurry in the main lumen 8 to the slurry storage unit 5.

[0043] Specifically, the control module 1 is connected to the slurry delivery valve 6 to control the opening of the slurry delivery valve 6 , thereby controlling the flow rate of the slurry flowing from the stirring unit 3 into the slurry storage unit 5 .

[0044] Example 2

[0045] This embodiment provides a control method for a drilling and anchoring trolley grouting system, comprising:

[0046] 1. Slurry preparation

[0047] Cement and other materials are manually put into the mixing unit 3 in proportion, and the control module 1 is operated to achieve: the mixing unit 3 works; the slurry delivery valve 6 is closed, the slurry discharge valve 13 is closed, the circulation valve 11 is opened, and the water valve 9 is opened, and water enters the mixing unit 3; when the amount of water entering the mixing unit 3 reaches the requirement, the water valve 9 is closed; when the slurry in the mixing unit 3 is stirred to the right place, the stirring is stopped.

[0048] 2. Grouting

[0049] When grouting is required, the control module 1 is operated to achieve: the slurry delivery valve 6 is opened, the water valve 9 is closed, the slurry discharge valve 13 is opened, and the circulation valve 11 is closed; after the slurry completely enters the slurry storage unit 5, the spiral booster unit 7 starts to work, and the slurry is output at full flow through the slurry discharge pipe 14; if it is necessary to reduce the slurry discharge volume to a certain level, the speed of the variable frequency motor can be controlled to reduce the delivery speed of the spiral booster unit.

[0050] 3. Reduced grouting

[0051] When it is necessary to reduce the amount of grouting, the control module 1 is operated to achieve: the slurry delivery valve 6 is opened, the water valve 9 is closed, the slurry discharge valve 13 is opened, the circulation valve 11 is opened to 10% of the total opening, the stirring unit 3 starts to work, the spiral booster unit 7 starts to work, a part of the slurry is output to the front through the slurry discharge pipe 14 for grouting, and a part of the slurry enters the stirring unit 3 through the circulation pipeline 12, and then enters the slurry storage unit 5 through the slurry delivery pipe 4 to form a circulation.

[0052] 4. Grouting system cleaning

[0053] After the grouting is completed, when the grouting system needs to be cleaned, the control module 1 is operated to implement the following steps.

[0054] (1) Step 1: the water valve 9 is opened, the slurry discharge valve 13 is closed, the circulation valve 11 is opened, the slurry delivery valve 6 is closed, and the stirring unit 3 is working.

[0055] (2) Step 2: After the water volume in the stirring unit 3 reaches the specified requirement, the water valve 9 is closed, the slurry delivery valve 6 is opened, the spiral booster unit 7 is operated, and the circulation valve 11 is opened. The diluted turbid slurry circulates among the stirring unit 3, the slurry delivery pipe 4, the slurry delivery valve 6, the slurry storage unit 5, the spiral booster unit 7, the main pipe cavity 8, the circulation valve 11, and the circulation pipeline 12, continuously flushing the slurry attached to the components.

[0056] (3) Step 3: After the diluted slurry circulates for 3-5 minutes, its flushing effect is greatly reduced. The water valve 9 can be closed, the slurry delivery valve 6 can be opened, the spiral booster unit 7 can be operated, and the circulation valve 11 can be closed. The diluted turbid slurry can be discharged from the slurry outlet pipe 14.

[0057] (4) Step 4: Repeat steps 1, 2, and 3 until the grouting system is cleaned.

[0058] 5. Rinse the spiral booster unit

[0059] When the grouting system is not used for a long time or the spiral booster unit 7 is stuck due to the large particles of the mixed material, the control module 1 is operated to achieve: closing the slurry outlet valve 13, closing the circulation valve 11, opening the slurry delivery valve 6, opening the water valve 9, and the rotary booster unit 7 is reversed to eliminate the jam of the spiral booster unit 7.

[0060] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A drilling and anchoring trolley grouting system, characterized in that: The invention comprises a control module (1) and an execution module (2); the control module (1) is connected to the execution module (2) so that the execution module (2) performs corresponding actions; the execution module (2) comprises a stirring unit (3), a slurry storage unit (5), a spiral supercharging unit (7), a main pipe cavity (8), a circulation pipeline (12), a water valve (9), a slurry discharge valve (13), a slurry delivery valve (6) and a circulation valve (11); the stirring unit (3) is connected to the slurry storage unit (5) via a slurry delivery pipe (4); one end of the spiral supercharging unit (7) is connected to the slurry storage unit (5); The main pipe cavity (8) is connected to the water pipe (10) through a water valve (9), and the main pipe cavity (8) is also connected to the slurry discharge pipe (14) through a slurry discharge valve (13); the slurry delivery pipe (4) is provided with a slurry delivery valve (6); the circulation pipeline (12) is provided with a circulation valve (11); the control module (1) is respectively connected to the slurry discharge valve (13) and the circulation valve (11), and simultaneously controls the opening of the slurry discharge valve (13) and the circulation valve (11).

2. The drilling and anchoring trolley grouting system according to claim 1 is characterized in that: The water pipe (10) is provided with pressurized water; the control module (1) is connected to the water valve (9) to control the opening of the water valve (9) so as to allow the pressurized water to enter the main pipe cavity (8).

3. The drilling and anchoring trolley grouting system according to claim 1 is characterized in that: The stirring unit (3) is driven by a variable frequency motor to stir various raw materials placed in the stirring unit (3); the control module (1) is connected to the variable frequency motor to control the start, stop, direction and speed of the variable frequency motor.

4. The drilling and anchoring trolley grouting system according to claim 1 is characterized in that: The spiral boosting unit (7) is driven by a variable frequency motor, and the control module (1) is connected to the variable frequency motor to control the start, stop, direction, and speed of the variable frequency motor, thereby pressurizing the slurry in the slurry storage unit (5) and transporting it to the main pipe cavity (8), or reversely transporting the pressurized slurry in the main pipe cavity (8) to the slurry storage unit (5).

5. The drilling and anchoring trolley grouting system according to claim 1, characterized in that: The control module (1) is connected to the slurry delivery valve (6) to control the opening of the slurry delivery valve (6), thereby controlling the flow rate of slurry flowing from the stirring unit (3) into the slurry storage unit (5).

6. The control method of the drilling and anchoring trolley grouting system according to any one of claims 1 to 5, characterized in that: include: A plurality of materials are manually placed into the stirring unit (3) according to a set ratio, and the control module (1) is operated to achieve: the stirring unit (3) is operated; the slurry delivery valve (6) is closed, the slurry discharge valve (13) is closed, the circulation valve (11) is opened, and the water valve (9) is opened, and water enters the stirring unit (3); after the amount of water entering the stirring unit (3) reaches the required amount, the water valve (9) is closed; after the slurry in the stirring unit (3) is stirred to the desired level, the stirring is stopped; When grouting is required, the control module (1) is operated to realize: the slurry delivery valve (6) is opened, the water valve (9) is closed, the slurry discharge valve (13) is opened, and the circulation valve (11) is closed; after the slurry completely enters the slurry storage unit (5), the spiral booster unit (7) starts to work, and the slurry is discharged at full flow through the slurry discharge pipe (14); When reduced-volume grouting is required, the control module (1) is operated to achieve: the slurry delivery valve (6) is opened, the water valve (9) is closed, the slurry discharge valve (13) is opened, the circulation valve (11) is opened to 10% to 50% of the total opening, the stirring unit (3) starts to work, the spiral booster unit (7) starts to work, a part of the slurry is output to the front through the slurry discharge pipe (14) for grouting, and the other part of the slurry enters the stirring unit (3) through the circulation pipeline (12), and then enters the slurry storage unit (5) through the slurry delivery pipe (4) to form a circulation.

7. The control method of the drilling and anchoring trolley grouting system according to claim 6 is characterized in that: include: After the grouting is completed, when the grouting system needs to be cleaned, the control module (1) is operated to implement the following steps: The water valve (9) is opened, the slurry discharge valve (13) is closed, the circulation valve (11) is opened, the slurry delivery valve (6) is closed, and the stirring unit (3) is working; After the water volume in the stirring unit (3) reaches the specified requirement, the water valve (9) is closed, the slurry delivery valve (6) is opened, the spiral booster unit (7) is operated, and the circulation valve (11) is opened, and the diluted turbid slurry circulates among the stirring unit (3), the slurry delivery pipe (4), the slurry delivery valve (6), the slurry storage unit (5), the spiral booster unit (7), the main pipe cavity (8), the circulation valve (11), and the circulation pipeline (12), and the slurry attached to the components is continuously washed off; After the diluted slurry circulates for 3-5 minutes, its flushing effect is greatly reduced, the water valve (9) can be closed, the slurry delivery valve (6) can be opened, the spiral booster unit (7) can be operated, and the circulation valve (11) can be closed, and the diluted turbid slurry can be discharged from the slurry discharge pipe (14); Repeat the above steps until the grouting system is cleaned.

8. The control method of the drilling and anchoring trolley grouting system according to claim 6, characterized in that: include: When the grouting system is not used for a long time or the spiral booster unit (7) is stuck due to excessively large particles of the mixed material, the control module (1) is operated to: close the slurry outlet valve (13), close the circulation valve (11), open the slurry delivery valve (6), open the water valve (9), and the rotary booster unit (7) is reversely transported, thereby eliminating the stuck spiral booster unit (7).