Method and device for optimizing engineering project schedule in response to uncertainty

By inserting time buffers into engineering projects and building robust optimization models, the problem of cost increase and construction delay caused by uncertainty in repetitive engineering projects is solved, and the robustness and efficiency of schedule optimization are improved, which is suitable for repetitive projects. Buffer time and work force number management.

CN114418219BActive Publication Date: 2024-10-15NORTH CHINA ELECTRIC POWER UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210065904.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-20
Publication Date
2024-10-15
Estimated Expiration
2042-01-20

AI Technical Summary

Technical Problem

The existing technology in repetitive engineering projects causes increased project costs and delays in construction schedules due to uncertain factors. It also lacks a unified robustness index model and has complex calculation steps, making it difficult to effectively optimize schedules.

Method used

By obtaining the preset starting time of all processes in the project, an initial progress plan with the shortest construction period as the goal is formulated, a time buffer is inserted, a robust optimization index based on the time difference utility function is constructed, the model constraints are determined, and a robust optimization model is constructed Optimize the initial schedule with the optimal solution that optimizes the time buffer.

Benefits of technology

It improves the robustness and efficiency of engineering project schedule optimization, ensures that the project is completed on time, provides a unified robust optimization model and a theoretical basis for uncertain factors, and is suitable for buffer time allocation and work team quantity management for repetitive projects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114418219B_ABST
    Figure CN114418219B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and device for optimizing the progress of an engineering project in response to uncertainty. The method comprises: obtaining preset starting times of all processes included in the engineering project; wherein each of the processes includes a plurality of construction units with the same preset unit duration; formulating an initial progress plan for the engineering project with the shortest duration as the goal, and obtaining an optimal value for the number of work teams; fixing the optimal value for the number of work teams, and inserting a time buffer after the processes of the engineering project; constructing a robust optimization index based on a time difference utility function; determining model constraints according to the preset starting time, the preset unit duration, the number of work teams, the deadline, and the time buffer; constructing a robust optimization model according to the robust optimization index and the model constraints, and determining an optimal solution for the time buffer according to the maximum value of the robust optimization index; and optimizing the progress of the engineering project based on the optimal solution.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of engineering progress management, and in particular to an engineering project progress optimization method, device, computer equipment and storage medium to cope with uncertainty. Background Art

[0002] Repetitive projects refer to projects in which each sub-process is repeated in each process unit of the construction project, including roads, bridges, high-rise buildings, oil and gas pipelines, wind power, photovoltaic power stations, etc. Existing studies have proposed some scheduling methods suitable for repetitive projects, such as LOB (line of balance) balance line diagram. However, due to the characteristics of repetitive projects such as large scale, long cycle, multiple participants, and complex engineering environment, the existing technology has many uncertain factors in the project execution process, which is easy to cause problems such as increased project costs and construction delays.

[0003] CN102609820A discloses a critical chain buffer adjustment method based on project characteristics, including the following steps: step 1, generating an initial feasible scheduling scheme; step 2, calculating the free time difference of the task and identifying the critical chain; step 3, using two classical quantitative methods to calculate the buffer size, selecting the better one to adjust the buffer size through the adjustment strategy; step 4, generating a buffer scheduling scheme and outputting the result. On the one hand, the comparative document measures the priority relationship by calculating the total number of successor nodes of the task, and on the other hand, measures the resource tightness according to the available resources and the ratio of the task to the resource demand, so as to cope with the uncertainty in the project. The above method has complex calculation steps, and does not establish a unified robustness index model for different engineering projects, and the reliability is not high.

[0004] Therefore, there is a need to provide an improved method for scheduling engineering projects. Summary of the invention

[0005] The exemplary embodiments disclosed herein are directed to overcoming the above-mentioned and / or other problems in the prior art.

[0006] Therefore, according to one aspect of the present invention, a method for optimizing the progress of an engineering project in response to uncertainty is provided, comprising:

[0007] Obtaining preset start times of all processes included in the project; wherein each process includes a plurality of construction units with the same preset unit duration; the process has a corresponding production efficiency, and the production efficiency is related to the preset unit duration and the number of work teams working simultaneously;

[0008] Based on the preset starting time, an initial schedule of the engineering project is formulated with the shortest construction period as the goal, and an optimal value of the number of work teams is obtained;

[0009] Fixing the optimal value of the number of work teams, and inserting a time buffer after the process of the engineering project;

[0010] Constructing a robust optimization index based on a time difference utility function; the robust optimization index is used to evaluate the robustness of the inserted time buffer to the deadline of the engineering project;

[0011] Determine the model constraint condition according to the preset starting time, the preset unit duration, the number of work teams, the deadline and the time buffer;

[0012] Constructing a robust optimization model according to the robust optimization index and the model constraint condition, and determining an optimal solution of the time buffer according to a maximum value of the robust optimization index;

[0013] The initial schedule of the engineering project is optimized based on the optimal solution of the time buffer.

[0014] According to the method for optimizing the progress of a construction project provided by the present invention, preferably, the step of inserting a time buffer after the process of the construction project comprises:

[0015] Insert the first time buffer s between any two adjacent processes i :

[0016] s i =min{S j1 -(S i1 +d i ),S jm -(S im +d i )};

[0017] In the above formula, i represents the immediately preceding process among two adjacent processes, j represents the immediately following process among two adjacent processes, and S i1 represents the start time of the first construction unit of process i, S im represents the start time of the last construction unit of work i, S j1 represents the start time of the first construction unit of process j, S jm is the start time of the last construction unit of process j, d i represents the preset unit duration of the construction unit in process i;

[0018] Insert a second time buffer S after the last process n :

[0019] S n =δ-(S nm +d n );

[0020] In the above formula, n represents the last process of the project, m represents the last construction unit of process n, δ is the deadline of the project, S nm is the start time of construction unit m in process n, d n is the preset unit duration of process n.

[0021] According to the project schedule optimization method provided by the present invention, preferably, the step of constructing a robust optimization index based on the time difference utility function is calculated by the following formula:

[0022]

[0023] Among them, Robu represents the robust optimization index, CIW i represents the preset delay risk of process i, and |P(i)| represents the number of all processes before process i.

[0024] According to the project schedule optimization method provided by the present invention, preferably, the step of determining the model constraint conditions according to the preset start time, the preset unit duration, the number of work teams, the deadline and the time buffer comprises:

[0025] Determine the recursive relationship between repeated construction units in each process; where:

[0026]

[0027]

[0028] In the above formula, S im represents the start time of the last construction unit m of process i, k i represents the number of work teams working simultaneously in process i, r i represents the productivity of process i;

[0029] Based on the above recursive relationship, the start time constraint condition is determined so that the end time of the first construction unit of the immediately preceding process after the time buffer is inserted is less than the start time of the first construction unit of the immediately succeeding process; and the time after the last construction unit of the immediately preceding process after the time buffer is inserted is less than the time of the last construction unit of the immediately succeeding process;

[0030] S i1 +d i +S i ≤S j1 ;

[0031] S im +d i +s i ≤S jm .

[0032] According to the project schedule optimization method provided by the present invention, preferably, the step of determining the model constraint conditions according to the preset starting time, the preset unit duration, the number of work teams, the deadline and the time buffer further comprises:

[0033] Determine the deadline constraint so that the project can be inserted into the second time buffer s n After the end time is less than the end date:

[0034] S nm +d n +S n ≤δ;

[0035] In the above formula, δ represents the deadline.

[0036] According to the project schedule optimization method provided by the present invention, preferably, the step of determining the model constraint conditions according to the preset starting time, the preset unit duration, the number of work teams, the deadline and the time buffer further comprises:

[0037] Determine the constraints on the number of work teams so that the number of work teams working simultaneously in process i is k i Less than the preset maximum number of available work teams

[0038]

[0039] According to the project schedule optimization method provided by the present invention, preferably, the step of constructing a robust optimization model according to the robust optimization index and the model constraint condition, and determining the optimal solution of the time buffer according to the maximum value of the robust optimization index comprises:

[0040] Define a 0-1 variable x ik , when process i uses k work teams x ik =1, otherwise x ik =0,0-1 variable x ik Satisfy the following formula:

[0041]

[0042] Use 0-1 variable x ik Replace the variable k in the recurrence relation between repeated construction units i ,get:

[0043]

[0044] Among them, k iIndicates the number of work teams working simultaneously in process i; defines a 0-1 integer variable y il , when process i inserts l days of buffer y il =1, otherwise y il =0, then:

[0045]

[0046] Where a is the upper limit number of days for inserting time buffer for process i;

[0047] make Transform the robust optimization index into:

[0048]

[0049] According to the converted robust optimization index, an optimal solution of the time buffer is searched by using an enumeration method.

[0050] According to another aspect of the present disclosure, there is provided a device for optimizing the progress of an engineering project in response to uncertainty, comprising:

[0051] A process acquisition unit is used to acquire the preset start time of all processes included in the engineering project; wherein each of the processes includes a plurality of construction units with the same preset unit duration; the processes have corresponding production efficiency, and the production efficiency is related to the preset unit duration and the number of work teams working simultaneously;

[0052] The optimal work team module is adapted to formulate the initial schedule of the engineering project based on the preset starting time and taking the shortest construction period as the goal, and obtain the optimal value of the number of work teams;

[0053] A time buffer unit, adapted to fix the optimal value of the number of work teams and insert a time buffer after the process of the engineering project;

[0054] A robust optimization unit, adapted to construct a robust optimization index based on a time difference utility function; the robust optimization index is used to evaluate the robustness of the inserted time buffer to the deadline of the engineering project;

[0055] A model constraint condition unit, adapted to determine a model constraint condition according to the preset start time, the preset unit duration, the number of work teams, the deadline and the time buffer;

[0056] An optimal solution unit, adapted to construct a robust optimization model according to the robust optimization index and the model constraint condition, and determine an optimal solution of the time buffer according to a maximum value of the robust optimization index;

[0057] The schedule optimization unit is adapted to optimize the initial schedule plan of the engineering project based on the optimal solution of the time buffer.

[0058] According to another aspect of the present invention, a computing device is provided, including a memory, a processor, and computer instructions stored in the memory and executable on the processor, wherein the processor implements the steps of the project scheduling method as described above when executing the instructions.

[0059] According to another aspect of the present disclosure, a computer-readable storage medium is provided, which stores computer instructions, and when the instructions are executed by a processor, the steps of the method for scheduling a project as described above are implemented.

[0060] The method based on the LOB balance line diagram of the present invention expresses the unit duration of each process in the engineering project and the rotation of each work team, and determines the corresponding relationship between the starting time of each process in the engineering project based on the LOB balance line diagram, which is conducive to establishing a unified robust optimization model for different engineering projects, and provides the necessary theoretical basis for quantitatively analyzing uncertain factors such as buffer time allocation in project engineering and the number of construction work teams. Furthermore, the present invention constructs a robust optimization index suitable for the characteristics of repetitive projects, which can reasonably allocate decentralized buffers for each process and project buffers for the entire engineering project on the basis of ensuring the continuity of repetitive project work. According to the preferred technical solution of the present invention, by seeking the optimal solution, the best choice of uncertain items in the engineering project can be obtained in a relatively short time, which can effectively improve the efficiency of schedule optimization. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] The present invention may be better understood by describing exemplary embodiments of the present invention in conjunction with the accompanying drawings.

[0062] Figure 1 What is shown is a schematic structural block diagram of a computing device according to an embodiment disclosed in the present invention;

[0063] Figure 2 What is shown is a schematic flow chart of a method for optimizing a construction project schedule in response to uncertainty according to an embodiment disclosed in the present invention;

[0064] Figure 3 This is a schematic diagram of a project based on a LOB representation method according to the first embodiment of the present invention;

[0065] Figure 4A and Figure 4B The time buffer schematic diagrams of the convergent process and the divergent process are shown respectively;

[0066] Figure 5 A schematic diagram of a method for calculating productivity according to a first embodiment of the present invention;

[0067] Figure 6 Shown is a schematic diagram of a device for optimizing a construction project schedule in response to uncertainty according to an embodiment disclosed in the present invention. DETAILED DESCRIPTION

[0068] The specific embodiments of the present invention will be described below. It should be noted that in the specific description of these embodiments, in order to be concise and clear, this specification cannot provide a detailed description of all the features of the actual embodiments. It should be understood that in the actual implementation of any embodiment, just as in the process of any engineering project or design project, in order to achieve the specific goals of the developer and to meet system-related or business-related restrictions, various specific decisions are often made, and this will also change from one embodiment to another. In addition, it can also be understood that although the efforts made in this development process may be complex and lengthy, for ordinary technicians in the field related to the content disclosed by the present invention, some changes such as design, manufacturing or production based on the technical content disclosed by the present invention are just conventional technical means, and should not be understood as the content of the present invention is insufficient.

[0069] Unless otherwise defined, the technical or scientific terms used in the claims and the specification shall have the usual meaning understood by persons with ordinary skills in the technical field to which the invention belongs. The words "first", "second" and similar words used in the patent application specification and the claims of the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. "One" or "one" and other similar words do not indicate a quantitative limitation, but indicate the existence of at least one. "Include" or "comprises" and other similar words mean that the elements or objects appearing before "include" or "comprises" include the elements or objects listed after "include" or "comprises" and their equivalent elements, and do not exclude other elements or objects. "Connected" or "connected" and other similar words are not limited to physical or mechanical connections, nor are they limited to direct or indirect connections.

[0070] Figure 1 The structure block diagram of a computing device 100 according to an embodiment of the present specification is shown. The components of the computing device 100 include but are not limited to a memory 110 and a processor 120. The processor 120 is connected to the memory 110 via a bus 130, and the database 150 is used to store data.

[0071] The computing device 100 also includes an access device 140 that enables the computing device 100 to communicate via one or more networks 160. Examples of these networks include a public switched telephone network (PSTN), a local area network (LAN), a wide area network (WAN), a personal area network (PAN), or a combination of communication networks such as the Internet. The access device 140 may include one or more of any type of network interface (e.g., a network interface card (NIC)) whether wired or wireless, such as an IEEE 802.11 wireless local area network (WLAN) wireless interface, a World Wide Interoperability for Microwave Access (Wi-MAX) interface, an Ethernet interface, a universal serial bus (USB) interface, a cellular network interface, a Bluetooth interface, a near field communication (NFC) interface, and the like.

[0072] In one embodiment of the present specification, the above components of the computing device 100 and Figure 1 Other components not shown in the figure may also be connected to each other, for example, via a bus. It should be understood that Figure 1 The computing device structure block diagram shown is only for the purpose of illustration, and is not intended to limit the scope of this specification. Those skilled in the art can add or replace other components as needed.

[0073] The computing device 100 may be any type of stationary or mobile computing device, including a mobile computer or mobile computing device (e.g., a tablet computer, a personal digital assistant, a laptop computer, a notebook computer, a netbook, etc.), a mobile phone (e.g., a smart phone), a wearable computing device (e.g., a smart watch, smart glasses, etc.), or other types of mobile devices, or a stationary computing device such as a desktop computer or PC. The computing device 100 may also be a mobile or stationary server.

[0074] The processor 120 may execute Figure 2 Steps in the method shown.

[0075] Figure 2 A schematic flow chart of a method for optimizing a construction project schedule in response to uncertainty according to an embodiment of the present application is shown, including steps 201 to 207 .

[0076] In order to make the objectives, technical solutions and advantages of the present invention more clear, the embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.

[0077] Step 201: Obtain the preset start time of all processes included in the engineering project; wherein each of the processes includes multiple construction units with the same preset unit duration; the processes have corresponding production efficiency, and the production efficiency is related to the preset unit duration and the number of work teams working simultaneously.

[0078] In this embodiment, it is assumed that a repetitive project has n processes, each process consists of m repetitive units, A = {1, ..., n} is the process set, U = {1, ..., m} is the unit set; the preset unit duration of process i (i = 1, ..., n) is defined as d i ; The number of available work teams for process i is And k i ∈z + The priority constraints between activities are represented by the set E∈A×A, process j is the immediate successor of process i, (i,j)∈E. Repetitive project scheduling also needs to meet the following requirements: ① Maintain work continuity, that is, there must be no shutdowns or interruptions; ② To avoid additional cost increases caused by changing the execution mode of the process, the execution mode of the sub-units of the same process must be consistent; ③ To ensure that the team used in the process does not suffer efficiency losses during work, the rotation of the team must meet the "natural rhythm".

[0079] Figure 3 This is a schematic diagram of a project based on the LOB representation method in the first embodiment of the present invention, which can clearly reflect the unit duration of each process and the rotation of each work team. Figure 3 As shown, the horizontal axis represents time; the vertical axis represents the sub-unit of the process; each process is represented by an inclined column, and each small rectangle represents a sub-unit in the process. For example, in a high-rise building project, the construction of building decoration and renovation can be regarded as a process, and the construction of building decoration and renovation on each floor can be regarded as a sub-unit of a certain process. The intersection of the left boundary of the inclined column and the sub-unit represents the start time of the sub-unit, and the intersection of the right boundary and the sub-unit represents the end time of the sub-unit; the width of each inclined column represents the unit duration of the process; the slope of the inclined column represents the work efficiency of the process. The work efficiency of each process is determined by the number of work teams in each process. The more work teams there are, the higher the work efficiency of the process, and the fewer work teams there are, the lower the work efficiency of the process. The total duration of the entire repetitive project is represented by the end time of the last unit of the last process.

[0080] Step 202: Generate an initial scheduling plan with the shortest construction period as the goal, and obtain the optimal number of work teams.

[0081] It is understandable that the construction period of a project is related to the number of work teams working at the same time. The more work teams working at the same time, the longer the construction period. However, in actual situations, the number of work teams working at the same time cannot be increased arbitrarily, but needs to take into account various factors such as funds, hired personnel, and team rotation status. Therefore, in this step, after comprehensively considering the above factors, the optimal number of work teams that can work simultaneously in each process is first determined with the shortest construction period as the goal, so as to obtain the initial scheduling plan. It should be noted that the time buffer between processes is not considered in the initial scheduling plan.

[0082] Step 203: Fix the optimal number of work teams and insert a time buffer after the process of the engineering project.

[0083] The purpose of inserting a time buffer is to leave a margin for the construction time of each process and the entire project, so as to ensure that the project can be completed on time. In this embodiment, the inserted time buffer includes two types, one of which is the first time buffer S i , which is used to insert between any two adjacent processes, also called distributed buffering; the other is the second time buffer S n , which is used to be inserted after the last process of the engineering project, also called project buffer. Figure 3 As shown, the project includes three processes, namely process 1, process 2 and process 3, and the number of work teams working simultaneously in each process is 9. Among them, a dispersed buffer is inserted between process 1 and process 2, and between process 2 and process 3, and a project buffer is inserted between process 3 and the deadline.

[0084] In this embodiment, the first time buffer S to be inserted i and the second time buffer S n They can be expressed by the following formulas:

[0085] S i =min{S j1 -(S i1 +d i ), S jm -(S im +d i )};

[0086] In the above formula, i represents the earlier process among two adjacent processes, j represents the later process among two adjacent processes, and S i1 represents the start time of the first construction unit of process i, S im represents the start time of the last construction unit of work i, S j1 represents the start time of the first construction unit of process j, S jm is the start time of the last construction unit of process j, d i Represents the preset unit duration of the construction unit in process i.

[0087] S n =δ-(S nm +d n );

[0088] In the above formula, n represents the last process of the project, m represents the last construction unit of process n, δ is the deadline of the project, S nm is the start time of construction unit m in process n, dn is the preset unit duration of process n.

[0089] It should be noted that in the LOB schedule, the relationship between two processes can be divided into convergent and divergent types. If the slope of the next process is greater than the slope of the previous process, that is, R i <R i+! , then the relationship between them is called convergent (such as Figure 3 On the contrary, if R i >R i+1 , then it is called divergent (such as Figure 3 of process 1 and process 2).

[0090] Figure 4A and Figure 4B The time buffer diagrams of the convergent process and the divergent process are shown respectively. As shown in FIG4, when the two processes are in a convergent relationship ( Figure 4A ), in the last unit, the start time of the next process is controlled by the end time of the previous process. Due to the requirement of work continuity, the previous process A i If any unit of the process is delayed, it will cause the delay of the last unit of this process, thus causing the delay of the next process A. i+1 All units start time is delayed. In this case, inserting a time buffer after the last unit of the preceding process can help absorb the delay. Similarly, when the relationship between two processes is divergent ( Figure 4B ), inserting a time buffer after the first unit of the preceding process can help absorb delays.

[0091] Step 204: construct a robust optimization index based on the time difference utility function; the robust optimization index is used to evaluate the robustness of the inserted time buffer to the deadline of the engineering project.

[0092] The number of time buffers a process has and the robustness of the project schedule has a nonlinear relationship. The contribution of an increase in the number of time buffers to the enhancement of robustness is decreasing at the margin. This relationship can be represented by a robustness metric based on a time difference effect function. Generally speaking, the more processes have time buffers, the more robust the scheduling scheme is. Using a time difference utility function can make the distribution of time buffers more dispersed among the processes to avoid allocating time buffers to only a few processes, thereby enhancing the robustness of the scheduling scheme. Assume that process 1 has 2 units of time buffer, process 2 has 0 units of time buffer, and the process instability weights are both 1. If an additional 1 unit of time buffer is chosen to be allocated to process 1 or process 2, then there are two options:

[0093] ① Assigned to process 1. At this time, process 1 has 3 units of time buffer, process 2 has 0 units of time buffer, and the time difference utility is:

[0094]

[0095] ② Assigned to process 2. At this time, process 1 has 2 units of time buffer, process 2 has 1 unit of time buffer, and the time difference utility is:

[0096]

[0097] At this time, in order to maximize the time difference utility of the scheduling plan, plan ② should be selected.

[0098] Therefore, the present invention constructs a robust optimization index based on the time difference utility function, and the specific formula is as follows:

[0099]

[0100] Among them, CIW i is the delay risk weight of process i. The project manager can set it based on experience. In order to improve the robustness of the schedule, a larger risk weight can be set for the last process. |P(i)| represents the number of all processes before process i, that is, the number of processes that precede the process i. i Indicates inserting the first time buffer between any two adjacent processes. When the process is the last process, s i =s n By calculating the maximum value max(Robu) of the robust optimization index according to the above formula, we can get the maximum schedule robustness.

[0101] Step 205: Determine model constraints based on the preset start time, the preset unit duration, the number of work teams, the deadline and the time buffer.

[0102] The model constraints in this embodiment mainly include a start time constraint, a deadline constraint, and a work team quantity constraint, which are introduced below respectively.

[0103] (1) Start time constraints

[0104] First, in repetitive projects, the productivity r of process i i It can be expressed as:

[0105]

[0106] For the specific process, see Figure 5 As shown. Figure 5 It can be seen that the productivity r of process i iThat is the slope of the inclined column corresponding to process i.

[0107] In this embodiment, it is assumed that the most common "end-start (FS)" relationship exists between processes. After the insertion time buffer is considered, it should be satisfied that the time when the first construction unit of the front process is inserted into the time buffer is less than the time when the first construction unit of the back process is inserted; and the time when the last construction unit of the front process is inserted into the time buffer is less than the time when the last construction unit of the back process is inserted. The specific formula is as follows:

[0108] S i1 +d i +S i ≤S j1 , (i, j)∈E;

[0109] S im +d i +S i ≤S jm , (i, j)∈E

[0110] Among them, S i1 represents the start time of the first construction unit of process i, S im represents the start time of the last construction unit of work i, S j1 represents the start time of the first construction unit of process j, S jm is the start time of the last construction unit of process j.

[0111] (2) Deadline Constraints

[0112] Usually, a project will be given a deadline constraint, that is, the last unit of the last process of the project must be completed before the deadline. If a project buffer is added to the last unit of the last process, then the last unit of the last process plus the second time buffer S n , which needs to be completed within the deadline. The constraint is as follows:

[0113] S nm +d n +S n ≤δ;

[0114] Where n is the last process of the project, m is the last construction unit of process n, δ is the deadline of the project, S nm is the start time of construction unit m in process n, d n is the preset unit duration of process n.

[0115] (3) Constraints on the number of work teams

[0116] In the construction of repetitive projects, there is a constraint on the number of work teams, that is, there is an upper limit on the number of work teams to be employed in each process. is the maximum number of available teams in process i, and the number of teams working simultaneously in process i is team k i The constraints are as follows:

[0117]

[0118] Through the above constraints, the hard limits that the robust optimization indicators in the engineering project need to meet can be determined, which is conducive to accurately calculating the maximum robustness of the insertion time buffer.

[0119] Step 206: construct a robust optimization model according to the robust optimization index and the model constraints, and determine the optimal solution of the time buffer according to the maximum value of the robust optimization index.

[0120] The robust optimization model in this embodiment is a generalized representation of the robust optimization index, so the general mathematical expressions of the robust optimization model and the robust optimization index are actually consistent. It should be noted that the robust optimization model in the above text is a nonlinear integer programming model, and it is difficult to obtain the optimal solution in a short time. Therefore, this embodiment can use linear regularization techniques to convert the robust optimization model into a mixed integer linear programming model (MILP) for solution.

[0121] Define a 0-1 variable x ik , when process i uses k work teams x ik =1, otherwise x ik = 0. Since there can be only one allocation plan for the work team in a process, the variable x ik The following formula should be satisfied:

[0122]

[0123] Replace the variable k in the nonlinear constraint i , we can get:

[0124]

[0125] Similarly, define a 0-1 integer variable y il , when process i inserts l days of buffer y il =1, otherwise y il = 0, let a be the upper limit of the number of days for inserting a time buffer for process i. Since there are only two situations after a process, there can be a time buffer or no time buffer, then the variable y il The following formula should be satisfied:

[0126]

[0127] Further, let Then the robust optimization index can be transformed into the following formula:

[0128]

[0129] Through the above normalization process, the robust optimization index is transformed from the nonlinear integer programming model to the mixed integer linear programming model, which is conducive to determining the optimal solution more quickly and accurately.

[0130] In an example, the Matlab YALMIP toolbox can be used to call CPLEX to solve the model. Since the MILP problem is an NP-hard problem, the program may not terminate in a reasonable time. Therefore, the maximum running time of the program is limited. If the program can stop by itself, then the optimal solution of the problem is obtained; otherwise, an approximate optimal solution will be obtained.

[0131] The specific steps may include:

[0132] (1) Under the premise of satisfying the precedence constraints and resource constraints, an initial scheduling plan is formulated with the shortest construction period as the goal. b , get the optimal number of hired teams k * and the shortest duration σ, the total number of time buffers that can be inserted is δ-σ.

[0133] (2) Calculate the distributed buffer and project buffer s owned by all processes according to the initial scheduling plan i , and set an upper limit on the number of days to insert a buffer for each process

[0134] (3) The optimal value k for the number of fixed work teams * , calling the robust optimization model proposed by the present invention, inserting Days of time buffer, each process generates (a+1) buffer insertion schemes, and a total of (a+1)×n buffer insertion schedules Π a .

[0135] (4) Select the ∏ that satisfies the maximum value of the robust optimization index, max(Robu), among all the schedules a As a robust schedule.

[0136] Step 207: Optimizing the initial schedule of the engineering project based on the optimal solution of the time buffer.

[0137] After determining the optimal solution for inserting the time buffer, the construction progress of the project is optimized based on the optimal solution, that is, the optimal solution for inserting the determined time buffer is inserted after each process, thereby ensuring that the project can be completed on schedule on the basis of maximum robustness.

[0138] Corresponding to the above method, this specification also provides an embodiment of a project schedule optimization device for coping with uncertainty, Figure 6 The figure shows a schematic diagram of a device for optimizing the progress of an engineering project according to an embodiment disclosed in the present invention. Figure 6 As shown, the construction project schedule optimization device 600 includes:

[0139] The process acquisition unit 610 is adapted to acquire the preset start time of all processes included in the engineering project; wherein each of the processes includes a plurality of construction units with the same preset unit duration; the processes have corresponding production efficiency, and the production efficiency is related to the preset unit duration and the number of work teams working simultaneously;

[0140] The optimal work team unit 620 is adapted to formulate an initial schedule of the engineering project based on the preset starting time and taking the shortest construction period as a target, and obtain an optimal value of the number of work teams;

[0141] A time buffer unit 630, adapted to fix the optimal value of the number of work teams and insert a time buffer after the process of the engineering project;

[0142] A robust optimization unit 640 is adapted to construct a robust optimization index based on a time difference utility function; the robust optimization index is used to evaluate the robustness of the inserted time buffer to the deadline of the engineering project;

[0143] A model constraint condition unit 650, adapted to determine a model constraint condition according to the preset start time, the preset unit duration, the number of work teams, the deadline and the time buffer;

[0144] An optimal solution unit 660, adapted to construct a robust optimization model according to the robust optimization index and the model constraint condition, and determine an optimal solution of the time buffer according to a maximum value of the robust optimization index;

[0145] The schedule optimization unit 670 is adapted to optimize the initial schedule plan of the engineering project based on the optimal solution of the time buffer.

[0146] An embodiment of the present application further provides a computer-readable storage medium storing computer instructions, which, when executed by a processor, implement the steps of the method for optimizing the progress of an engineering project as described above.

[0147] The above is a schematic scheme of a computer-readable storage medium of this embodiment. It should be noted that the technical scheme of the storage medium and the technical scheme of the above-mentioned engineering project schedule optimization method belong to the same concept, and the details not described in detail in the technical scheme of the storage medium can be referred to the description of the technical scheme of the above-mentioned engineering project schedule optimization method.

[0148] The above is a description of a specific embodiment of the specification. Other embodiments are within the scope of the appended claims. In some cases, the actions or steps recorded in the claims can be performed in an order different from that in the embodiments and still achieve the desired results. In addition, the processes depicted in the drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.

[0149] The computer instructions include computer program codes, which may be in source code form, object code form, executable files or some intermediate forms, etc. The computer-readable medium may include: any entity or device capable of carrying the computer program code, recording medium, USB flash drive, mobile hard disk, magnetic disk, optical disk, computer memory, read-only memory (ROM), random access memory (RAM), electric carrier signal, telecommunication signal and software distribution medium, etc. It should be noted that the content contained in the computer-readable medium may be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, computer-readable media do not include electric carrier signals and telecommunication signals.

[0150] It should be noted that, in the apparatus and method disclosed in the present invention, it is obvious that each component or each step can be decomposed and / or recombined. These decompositions and / or recombinations should be regarded as equivalent schemes disclosed in the present invention. In addition, the steps of performing the above series of processes can naturally be performed in chronological order according to the order of description, but do not necessarily need to be performed in chronological order. Some steps can be performed in parallel or independently of each other.

[0151] The above specific implementations do not constitute a limitation on the scope of protection disclosed by the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions may occur depending on design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle disclosed by the present invention shall be included in the scope of protection disclosed by the present invention.

Claims

1. A method for optimizing the progress of an engineering project in response to uncertainty, characterized in that: include: Obtaining preset start times of all processes included in the project; wherein each process includes a plurality of construction units with the same preset unit duration; the process has a corresponding production efficiency, and the production efficiency is related to the preset unit duration and the number of work teams working simultaneously; Based on the preset starting time, an initial schedule of the engineering project is formulated with the shortest construction period as the goal, and an optimal value of the number of work teams is obtained; Fixing the optimal value of the number of work teams, and inserting a time buffer after the process of the engineering project; Constructing a robust optimization index based on a time difference utility function; the robust optimization index is used to evaluate the robustness of the inserted time buffer to the deadline of the engineering project; Determine the model constraint condition according to the preset starting time, the preset unit duration, the number of work teams, the deadline and the time buffer; Constructing a robust optimization model according to the robust optimization index and the model constraint condition, and determining an optimal solution for the time buffer according to a maximum value of the robust optimization index; Optimizing the initial schedule of the engineering project based on the optimal solution of the time buffer; The step of inserting a time buffer after the process of the engineering project comprises: Insert the first time buffer S between any two adjacent processes i : s i =min{S j1 -(S i1 +d i ),S jm -(S im +d i )}; In the above formula, i represents the immediately preceding process among two adjacent processes, j represents the immediately following process among two adjacent processes, and S i1 represents the start time of the first construction unit of process i, S im represents the start time of the last construction unit of work i, S j1 represents the start time of the first construction unit of process j, S jm is the start time of the last construction unit of process j, d i represents the preset unit duration of the construction unit in process i; Insert a second time buffer S after the last process n : s n =δ-(S nm +d n ); In the above formula, n represents the last process of the project, m represents the last construction unit of process n, δ is the deadline of the project, S nm is the start time of construction unit m in process n, d n is the preset unit duration of process n; The steps to construct a robust optimization indicator based on the time-difference utility function are calculated by the following formula: Among them, Robu represents the robust optimization index, CIW i represents the preset delay risk of process i, |P(i)| represents the number of all processes before process i; The steps of constructing a robust optimization model according to the robust optimization index and the model constraint condition, and determining the optimal solution of the time buffer according to the maximum value of the robust optimization index include: Define a 0-1 variable x ik , when process i uses k work teams x ik =1, otherwise x ik =0,0-1 variable x ik Satisfy the following formula: Use 0-1 variable x ik Replace the variable k in the recurrence relation between repeated construction units i ,get: Among them, k i Indicates the number of work teams working simultaneously in process i; defines a 0-1 integer variable y il , when process i inserts l days of buffer y il =1, otherwise y il =0, then: Where a is the upper limit number of days for inserting time buffer for process i; make Transform the robust optimization index into: According to the converted robust optimization index, an optimal solution of the time buffer is searched by using an enumeration method.

2. The method for optimizing the progress of a construction project according to claim 1, characterized in that: The step of determining the model constraint conditions according to the preset starting time, the preset unit duration, the number of work teams, the deadline and the time buffer comprises: Determine the recursive relationship between repeated construction units in each process; where: In the above formula, S im represents the start time of the last construction unit m of process i, k i represents the number of work teams working simultaneously in process i, r i represents the productivity of process i; Based on the above recursive relationship, the start time model constraint condition is determined so that the end time of the first construction unit of the immediately preceding process after the time buffer is inserted is less than the start time of the first construction unit of the immediately succeeding process; and the end time of the last construction unit of the immediately preceding process after the time buffer is inserted is less than the start time of the last construction unit of the immediately succeeding process; S i1 +d i +s i ≤S j1 ; S im +d i +s i ≤S jm 。 3. The method for optimizing the progress of a construction project according to claim 2, characterized in that: The step of determining the model constraint conditions according to the preset starting time, the preset unit duration, the number of work teams, the deadline and the time buffer also includes: Determine the deadline constraint so that the project can be inserted into the second time buffer s n The end time after is less than the end date: S nm +d n +s n ≤δ; In the above formula, δ represents the deadline.

4. The method for optimizing the progress of a construction project according to claim 3, characterized in that: The step of determining the model constraint conditions according to the preset starting time, the preset unit duration, the number of work teams, the deadline and the time buffer also includes: Determine the constraints on the number of work teams so that the number of work teams working simultaneously in process i is k i Less than the preset maximum number of available work teams 5. A device for optimizing the progress of an engineering project in response to uncertainty for implementing the method of claim 1, characterized in that: include: A process acquisition unit is used to acquire the preset start time of all processes included in the engineering project; wherein each of the processes includes a plurality of construction units with the same preset unit duration; the processes have corresponding production efficiency, and the production efficiency is related to the preset unit duration and the number of work teams working simultaneously; The optimal work team module is adapted to formulate the initial schedule of the engineering project based on the preset starting time and taking the shortest construction period as the goal, and obtain the optimal value of the number of work teams; A time buffer unit, adapted to fix the optimal value of the number of work teams and insert a time buffer after the process of the engineering project; A robust optimization unit, adapted to construct a robust optimization index based on a time difference utility function; the robust optimization index is used to evaluate the robustness of the inserted time buffer to the deadline of the engineering project; A model constraint condition unit, adapted to determine a model constraint condition according to the preset start time, the preset unit duration, the number of work teams, the deadline and the time buffer; An optimal solution unit, adapted to construct a robust optimization model according to the robust optimization index and the model constraint condition, and determine an optimal solution of the time buffer according to a maximum value of the robust optimization index; The schedule optimization unit is adapted to optimize the initial schedule plan of the engineering project based on the optimal solution of the time buffer.

6. A computing device comprising a memory, a processor, and computer instructions stored in the memory and executable on the processor, characterized in that: When the processor executes the instructions, the steps of the method according to any one of claims 1 to 4 are implemented.

7. A computer-readable storage medium storing computer instructions, characterized in that: When the instruction is executed by a processor, the steps of the method described in any one of claims 1 to 4 are implemented.