A method for protecting tunnels along goaf with narrow coal pillars in shallow coal seams
Through laboratory mechanics experiments and geological sampling analysis, the limit balance theory and data simulation system were used to determine the width and support parameters of the narrow coal column, which solved the problem of roof stress concentration caused by the unreasonable retaining size of the narrow coal column, and realized the coal resources Efficiently adopt and stable maintenance of tunnels.
Patent Information
- Application Number
- CN202210004132.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-01-05
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2042-01-05
AI Technical Summary
In the prior art, the unreasonable size of narrow coal columns leads to concentrated stress on the roof, affecting the safety of coal resources and tunnel maintenance.
Through laboratory mechanics experiments and geological sampling analysis, the width and support parameters of the narrow coal column are determined using the ultimate balance theory and data simulation system to ensure that the coal column can support the top plate pressure and prevent stress concentration, and then a reasonable support plan is designed.
Effectively prevent waste of coal resources, reduce workers' labor intensity and tunnel maintenance costs, and ensure the safety and stability of mining work.
Smart Images

Figure CN114526072B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of mine tunneling, and in particular to a method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars. Background Art
[0002] China, as the country with the largest coal production and consumption in the world, has always been known as "rich in coal, poor in oil and little gas". It is undeniable that coal, as China's main energy and fuel, has a very high production structure and its basic status will not change in the short term. In my country, most coal mines are mined underground, which requires a large number of tunnels, of which more than 80% are recovery tunnels.
[0003] The existing mining tunnel layout methods can be divided into three types: leaving wide coal pillars to protect the tunnel, leaving tunnels along the goaf, and driving tunnels along the goaf. The width of the coal pillars used to protect the tunnels with wide coal pillars is 15 to 30 meters. The mining area recovery rate is low, and the coal resources are seriously wasted. In addition, with the increase of mining depth, the original rock stress continues to increase, and the width of the coal pillars protecting the tunnels is getting larger and larger. This not only reduces the coal recovery rate and makes tunnel maintenance difficult, but also forms stress concentration in the wider section of the coal pillars after the working face is mined, which is not conducive to preventing and controlling coal spontaneous combustion and coal and gas outbursts. Driving tunnels along the goaf is to leave narrow coal pillars along the edge of the goaf after the adjacent working face is mined, the overlying rock activity in the goaf is basically terminated, and the stress redistribution caused by mining has tended to be stable. Generally, the coal pillars are less than 10 meters, and tunnels are driven. The tunnels along the goaf are in the area of reduced lateral support pressure, which puts the tunnels in a more favorable stress environment, which is beneficial to the stability of the tunnel surrounding rock. The tunnels along the goaf are only affected by mining once during service, and the dynamic pressure impact time is It is short and easy to maintain. The stress environment and maintenance conditions of goaf-side roadway driving are better than those of goaf-side roadway retention. By setting up reasonable section coal pillars and adopting reasonable support technology, the surrounding rock deformation of the roadway can be kept small during excavation and mining of the working face in this section. In addition, compared with goaf-side roadway retention, goaf-side roadway driving has a simple process, does not require filling bodies, has low roadway support costs, and is more conducive to promotion. In recent years, goaf-side roadway driving with small coal pillars has become one of the important technical ways to improve coal recovery rates in mines in my country. However, in the existing goaf-side roadway protection methods, if the size of the small coal pillars is unreasonable, it will not only fail to support the pressure from the roof, but may also cause fracturing and damage of the coal pillars due to excessive stress concentration in the mining stage, causing gas and water in the goaf to enter the working face being mined, affecting safe production. Therefore, reasonably determining the size of coal pillars and roadway support parameters is an important measure to prevent waste of coal resources, reduce the labor intensity of workers and roadway maintenance costs, and ensure mining safety. Summary of the invention
[0004] To this end, the present invention provides a method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars, so as to overcome the problem in the prior art that the unreasonable size of the narrow coal pillars makes it easy for stress concentration to occur on the roof.
[0005] To achieve the above-mentioned purpose, the present invention provides a method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars, comprising:
[0006] Step S1, extracting coal and rock samples from the roof and floor of the auxiliary transport chute of the working face to be mined adjacent to the goaf, conducting laboratory mechanical experiments, obtaining the physical and mechanical parameters of the surrounding rock of the auxiliary transport chute of the working face to be mined, calculating the physical and mechanical parameters of the surrounding rock using the limit equilibrium theory, obtaining the width of the limit narrow coal pillar, and using a data simulation system to determine the lateral support stress distribution data of the goaf of the working face to be mined under the condition of the width of the limit narrow coal pillar based on the physical and mechanical parameters of the surrounding rock of the auxiliary transport chute of the working face to be mined;
[0007] Step S2, performing geological sampling and analysis on the working face to be mined to obtain geological parameters of the working face to be mined, simulating the stress distribution and deformation of the tunnel surrounding rock under different coal pillar widths through the data simulation system according to the geological parameters of the working face to be mined and the lateral support stress distribution data of the goaf, and determining the final coal pillar width between the working face to be mined and the goaf;
[0008] Step S3, according to the determined coal pillar width, carry out tunneling along the goaf for the mining face to be mined, detect the displacement of the surrounding rock under the coal pillar width after tunneling, calculate the damage depth of the coal wall and the roof of the mining roadway in combination with the geological parameters of the mining face to be mined and the lateral support stress distribution data of the goaf, calculate the length of the support anchor at the corresponding position according to the damage depth of the coal seam in each part of the mining roadway, then calculate the surrounding rock pressure and the roof pressure according to the damage depth of the coal wall, calculate the anchoring force of the anchor by the rock strength of the coal wall and the roof, determine the spacing, preload and row spacing parameters of the support anchor according to the anchoring force of the anchor, the surrounding rock pressure and the roof pressure, and support the mining roadway according to the support parameters.
[0009] Furthermore, in the step S3, the confining stress concentration coefficient K of the mining roadway, the bulk density γ of the overburden, the dimensionless parameter B of the mining influence level, the coal seam hardness coefficient fy, and the internal friction angle θ of the coal rock mass are obtained in the data simulation system, and then the mining roadway depth H and the mining roadway height h in the mining roadway are measured, and the coal wall destruction depth C of the mining roadway is calculated. The calculation formula of the coal wall destruction depth C of the mining roadway is,
[0010] C=[(KγHB / 10 4 fy)-1]×h×tan(45°-θ / 2).
[0011] Furthermore, after the calculation of the coal wall destruction depth C of the mining roadway is completed, the stability coefficient ky of the anchored rock layer of the mining roadway in the data simulation system and the hardness coefficient fn of the anchored rock layer are obtained, the inclination angle of the coal rock body in the mining roadway is measured, the inclination angle of the coal rock body is α, and the width W of the mining roadway is measured. According to the coal wall destruction depth C of the mining roadway, the destruction depth b of the surrounding rock body of the roof of the mining roadway is calculated, and the calculation formula is,
[0012] b = (a + C) cos α / (ky × fn), where a is half the width of the mining tunnel, and a = W / 2.
[0013] Further, according to the set anchor rod force length ratio Sr and anchor rod fixed connection length ratio Se, the length Lr of the top plate anchor rod of the mining roadway at the destruction depth b of the top plate surrounding rock mass is calculated, Lr = b + (b × Sr) + (b × Se);
[0014] Then, according to the coal wall damage depth C, the length Ls of the coal wall support anchor rod at the coal wall damage depth C in the mining tunnel is calculated, Ls = C + (C × Sr) + (C × Se).
[0015] Further, after the theoretical length Lo of the supporting anchor at each position in the mining tunnel is determined, where o=r, s, the supporting anchor is selected according to the actual length L1, L2 of the supporting anchor and the anchor length ratio A affected by the force, where A≤0.1, L1 is the standard anchor length lower than the theoretical length Lo of the supporting anchor, L2 is the standard anchor length higher than the theoretical length Lo of the supporting anchor, and there is no standard length supporting anchor between the L1 length supporting anchor and the L2 length supporting anchor, calculate the standard grade length difference ΔL, ΔL=L2-L1, then calculate the anchor excess length difference ΔLo, ΔLo=Lo-L1, calculate the anchor excess length ratio Ao according to the anchor excess length difference ΔLo and the standard grade length difference ΔL, Ao=ΔLo / ΔL, compare the anchor excess length ratio Ao with the anchor length ratio A affected by the force,
[0016] When Ao>A, the anchor rod with length L2 is selected as the supporting anchor rod to support the position;
[0017] When Ao≤A, select the anchor rod with length L1 as the supporting anchor rod to support the position.
[0018] Furthermore, the gravity density γy of the coal seam and the gravity density γn of the rock layer in the mining roadway are obtained in the data simulation system, and the surrounding rock pressure Q acting on the support on the side of the damaged coal wall is calculated according to the coal wall damage depth C of the mining roadway, wherein:
[0019] Q=C×[(γyh×s inα)+γnb×tan(45°-θ)]
[0020] After the calculation of the surrounding rock pressure acting on the support on the side of the damaged coal seam is completed, the roof pressure QH of the mining roadway is calculated again according to the damaged depth b of the surrounding rock mass of the roof of the mining roadway, and it is determined according to the normal relative to the rock stratum bedding, where QH = 2γnabB.
[0021] Furthermore, the spacing s between anchor bolts is calculated based on the damage depth b of the surrounding rock mass of the mining roadway roof and half of the mining roadway width a. p The calculation formula is:
[0022]
[0023] Wherein, Z is the length of the anchor rod exceeding the destruction depth of the surrounding rock mass of the top plate, Z = (b × Sr) + (b × Se).
[0024] Furthermore, according to the diameter d of the selected standard anchor and the tensile strength limit value σt of the anchor, the hardness coefficient f of the surrounding rock mass of the anchoring section of the mining roadway roof is obtained, and the anchoring force P of the top plate anchor at the location where the hardness coefficient of the surrounding rock mass of the anchoring section is f is calculated. The calculation formula is:
[0025] Then obtain the hardness coefficient f1 of the surrounding rock mass of the anchoring section on both sides of the mining tunnel, and calculate the anchoring force P1 of the two sides of the anchor rod at the location where the hardness coefficient of the surrounding rock mass of the anchoring section is f1. The calculation formula is:
[0026]
[0027] Complete the determination of the anchoring force P of the top plate anchor and the anchoring force P1 of the two side anchors.
[0028] Furthermore, according to the calculated length Lr of the roof bolt of the mining roadway, the roof pressure QH of the mining roadway and the anchoring force P of the roof bolt, the number Nk of the anchor bolts in each row of the roof of the mining roadway is determined, and the result is calculated according to the following formula based on the balance condition of the acting force:
[0029]
[0030] Among them, K3 is the safety factor, which can be adjusted according to the safety requirement level in the mining tunnel.
[0031] Furthermore, after determining the number of anchors Nk in each row of the roof of the mining roadway, the row spacing ay of the supporting anchors on both sides of the coal wall in the mining roadway is calculated according to the calculated anchoring force P1 of the anchors on both sides and the surrounding rock pressure Q acting on the support on the side of the damaged coal wall. The calculation formula is:
[0032] Compared with the prior art, the beneficial effect of the present invention lies in that, by analyzing the uniaxial compressive strength, elastic modulus, Poisson's ratio and Proctor's coefficient of the rock on the roof and floor coal rock samples of the auxiliary transport chute of the working face to be mined, a uniaxial compression test can be used to determine the compressive strength classification of the roof and floor rocks, and the width of the theoretical narrow coal pillar is calculated by the limit equilibrium theory through numerical simulation according to the physical and mechanical parameters of the surrounding rock of the auxiliary transport chute of the working face to be mined, and then the stability of the surrounding rock under different coal pillar widths is calculated using the calculated theoretical narrow coal pillar width and the geological parameters of the working face to be mined and the lateral support stress distribution of the goaf, and the final width of the mining coal pillar is selected from the simulated data to ensure the stability of the surrounding rock of the mining roadway when the narrow coal pillar mining is realized. Qualitatively achieve the best effect, then mine the mining face with the determined coal pillar width, and detect the displacement of surrounding rock under the coal pillar width of the mining roadway during the mining process. Determine the damage range in the mining roadway by measuring the displacement of surrounding rock under the coal pillar width of the mining roadway during the mining process. Combined with the stress distribution in the mining roadway and the geological parameters of the coal pillar mining face, design and calculate the length, spacing, preload and row spacing parameters of the support anchor. Support the mining roadway with the calculated support parameters, so that in the case of narrow coal pillar mining, there will be no stress concentration in the mining roadway. Reasonable determination of coal pillar size and roadway support parameters is to prevent waste of coal resources and reduce the labor intensity of workers' maintenance. At the same time, support is carried out by accurately calculating support parameters to ensure the safe implementation of mining work.
[0033] Furthermore, by utilizing the dimensionless parameters of the confining pressure stress concentration coefficient and mining influence level of the mining roadway obtained by numerical simulation, and the actual geological parameters and mining roadway parameters of the mining roadway, the coal wall failure depth of the mining roadway is calculated. The support parameters of the mining roadway are calculated based on the parameters based on the actual coal wall failure depth of the mining roadway. This can make the support setting in the mining roadway more in line with the stress distribution in the mining roadway, and avoid stress concentration on both sides of the mining roadway due to insufficient calculation of the coal wall failure depth of the mining roadway, which brings safety hazards to the mining roadway.
[0034] Furthermore, after completing the calculation of the damage depth of the coal wall of the mining roadway, the damage depth of the rock mass surrounding the roof of the mining roadway is calculated again. Combined with parameters such as the width of the mining roadway, the inclination of the coal rock mass, the stability coefficient of the anchored rock layer and the hardness coefficient of the anchored rock layer, the damage depth of the rock mass surrounding the roof of the mining roadway is determined according to the damage depth of the coal wall of the mining roadway. Similarly, the damage depth of the rock mass surrounding the roof of the mining roadway is used as the basic parameter to calculate the mining roadway support parameters, which can make the support setting in the mining roadway more in line with the stress distribution in the mining roadway, greatly reduce the stress concentration in the roof of the mining roadway, and further reduce the safety hazards in the mining work.
[0035] Furthermore, when determining the length of the anchor rod, the length of the anchor rod is divided into three parts, namely, the depth of the anchor rod anchored in the damaged range of the surrounding rock, the depth of the anchor rod anchored in the undamaged surrounding rock and the exposed length of the anchor rod for connection and fixation as the total length of the anchor rod, so that the anchor rod can penetrate the damaged part of the surrounding rock mass of the roof of the mining roadway, so that the anchor rod can completely support the damaged part of the surrounding rock mass of the roof of the mining roadway, further disperse the stress distribution of the roof and the two sides of the mining roadway, so that when using narrow coal pillars to mine along the goaf, the stress distribution of the mining roadway along the goaf is uniform, thereby improving the safety of the roadway.
[0036] In particular, the surrounding rock pressure acting on the support on the side of the destroyed coal wall is calculated by calculating the coal wall destruction depth of the mining roadway, the gravity density of the coal seam and the gravity density of the rock stratum. The overall pressure on the upper and lateral sides of the coal wall support and the inclination pressure of the rock mass on the upper roof can be taken into account. At the same time, the roof pressure of the mining roadway is calculated, and the pressure of each part in the mining roadway is accurately calculated. The support parameters of the mining roadway are determined according to the pressure of each part, so that the support setting in the mining roadway is more in line with the pressure distribution in the mining roadway, the support setting effect is increased, and the safety hazards in the mining work are further reduced.
[0037] Furthermore, the spacing between anchor rods is calculated based on basic parameters such as the damage depth of the surrounding rock mass of the mining tunnel roof and the width of the mining tunnel. At the same time, combined with the length of the anchor rod that is not in the surrounding rock damage range, the setting of the spacing between anchor rods can meet the changes in parameters at different positions in the mining tunnel, so that the anchor support of the mining tunnel can achieve the greatest protection effect, and the stress of the top and coal wall of the mining tunnel can be dispersed between the anchor rods, thereby improving the support quality of the mining tunnel and reducing the labor intensity of the later support and maintenance personnel.
[0038] In particular, in order to calculate the support effect of mining more accurately, the anchoring force of each anchor bolt on the roof of the mining tunnel is calculated. In the process of calculating the anchoring force of the anchor bolt, the strength of the surrounding rock mass, the diameter of the anchor bolt, the hardness coefficient of the surrounding rock mass in the anchoring section and the tensile strength limit value of the anchor bolt are combined to accurately determine the anchoring force of each anchor bolt. The anchoring force of the anchor bolt can be used to determine whether the support can be set up for this part of the tunnel to protect it, further avoiding the safety hazard caused by the detachment of the support due to insufficient anchoring force of the anchor bolt.
[0039] Furthermore, similarly, the anchoring force of the anchor rods on both sides of the mining tunnel is calculated through the basic parameters of the anchor rods and the basic parameters of the rock wall, ensuring that the lateral stress on both sides of the mining tunnel caused by top extrusion is within the range of the anchoring force of the anchor rods, further reducing the safety hazards in the mining work.
[0040] Furthermore, the number of anchor rods in each row of the mining tunnel roof is determined according to the roof pressure of the mining tunnel, the length of the roof anchor rods of the mining tunnel and the anchoring force of the roof anchor rods. The anchor rods of the mining tunnel roof are used to disperse the pressure from the mining tunnel roof, thereby improving the quality of mining tunnel support and improving the safety and reliability of mining tunnel support.
[0041] Furthermore, the anchor spacing of the coal wall is calculated based on the number of anchors in each row, so that the anchors between the top of the mining tunnel and the coal walls on both sides are set on the basis of the same parameters. In the actual support process, there will be no stress deviation between the top support of the mining tunnel and the coal walls on both sides of the mining tunnel, which will affect the actual support effect. In the case of mining along the goaf with narrow coal pillars, the support setting of the mining tunnel is used to make the stress distribution of the mining tunnel along the goaf uniform, thereby further improving the safety of the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 The present invention is a flow chart of the method for goaf-side tunnel protection in shallow coal seams with narrow coal pillars. DETAILED DESCRIPTION
[0043] In order to make the objects and advantages of the present invention more clearly understood, the present invention is further described below in conjunction with embodiments; it should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0044] The preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the protection scope of the present invention.
[0045] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.
[0046] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0047] See also Figure 1As shown, it is a flow chart of the shallow coal seam narrow coal pillar goaf-side tunnel protection method of the present invention. The present invention provides a shallow coal seam narrow coal pillar goaf-side tunnel protection method, comprising:
[0048] Step S1, extracting coal and rock samples from the roof and floor of the auxiliary transport chute of the working face to be mined adjacent to the goaf, conducting laboratory mechanical experiments, obtaining the physical and mechanical parameters of the surrounding rock of the auxiliary transport chute of the working face to be mined, calculating the physical and mechanical parameters of the surrounding rock using the limit equilibrium theory, obtaining the width of the limit narrow coal pillar, and using a data simulation system to determine the lateral support stress distribution data of the goaf of the working face to be mined under the condition of the width of the limit narrow coal pillar based on the physical and mechanical parameters of the surrounding rock of the auxiliary transport chute of the working face to be mined;
[0049] Step S2, performing geological sampling and analysis on the working face to be mined to obtain geological parameters of the working face to be mined, simulating the stress distribution and deformation of the tunnel surrounding rock under different coal pillar widths through the data simulation system according to the geological parameters of the working face to be mined and the lateral support stress distribution data of the goaf, and determining the final coal pillar width between the working face to be mined and the goaf;
[0050] Step S3, according to the determined coal pillar width, carry out tunneling along the goaf for the mining face to be mined, detect the displacement of the surrounding rock under the coal pillar width after tunneling, calculate the damage depth of the coal wall and the roof of the mining roadway in combination with the geological parameters of the mining face to be mined and the lateral support stress distribution data of the goaf, calculate the length of the support anchor at the corresponding position according to the damage depth of the coal seam in each part of the mining roadway, then calculate the surrounding rock pressure and the roof pressure according to the damage depth of the coal wall, calculate the anchoring force of the anchor by the rock strength of the coal wall and the roof, determine the spacing, preload and row spacing parameters of the support anchor according to the anchoring force of the anchor, the surrounding rock pressure and the roof pressure, and support the mining roadway according to the support parameters.
[0051] By analyzing the uniaxial compressive strength, elastic modulus, Poisson's ratio and Proctor's coefficient of the rock by taking coal and rock samples from the roof and floor of the auxiliary transport chute of the working face to be mined, the uniaxial compression test can be used to determine the compressive strength classification of the roof and floor rocks. According to the physical and mechanical parameters of the surrounding rock of the auxiliary transport chute of the working face to be mined, the width of the theoretical narrow coal pillar is calculated using the limit equilibrium theory through numerical simulation. The calculated width of the theoretical narrow coal pillar, the geological parameters of the working face to be mined, and the lateral support stress distribution of the goaf are used to calculate the surrounding rock stability under different coal pillar widths. The final width of the mining coal pillar is selected from the simulated data to ensure that the stability of the surrounding rock of the mining roadway reaches the optimal effect when the narrow coal pillar mining is realized. The mining face to be mined is mined with the determined coal pillar width, and the displacement of surrounding rock under the coal pillar width of the mining roadway during the mining process is detected. The damage range in the mining roadway is determined by the displacement of surrounding rock under the coal pillar width of the mining roadway during the mining process. The length, spacing, preload and row spacing parameters of the support anchors are designed and calculated in combination with the stress distribution in the mining roadway and the geological parameters of the coal pillar mining face. The mining roadway is supported by the calculated support parameters, so that in the case of narrow coal pillar mining, stress concentration will not occur in the mining roadway. Reasonable determination of coal pillar size and roadway support parameters is to prevent waste of coal resources and reduce the labor intensity of workers' maintenance. At the same time, support is carried out by accurately calculating support parameters to ensure the safe implementation of mining work.
[0052] Specifically, in step S3, the confining pressure stress concentration coefficient K of the mining roadway, the bulk density γ of the overburden, the dimensionless parameter B of the mining impact level, the coal seam hardness coefficient fy, and the internal friction angle θ of the coal rock mass in the data simulation system are obtained, and then the mining roadway depth H and the mining roadway height h in the mining roadway are measured, and the coal wall damage depth C of the mining roadway is calculated. The calculation formula of the coal wall damage depth C of the mining roadway is:
[0053] C=[(KγHB / 10 4 fy)-1]×h×tan(45°-θ / 2).
[0054] By using the dimensionless parameters of the confining pressure stress concentration coefficient and mining influence level of the mining roadway obtained by numerical simulation, and the actual geological parameters and mining roadway parameters of the mining roadway, the coal wall failure depth of the mining roadway is calculated. The support parameters of the mining roadway are calculated based on the parameters based on the actual coal wall failure depth of the mining roadway. This can make the support setting in the mining roadway more in line with the stress distribution in the mining roadway, and avoid stress concentration on both sides of the mining roadway due to insufficient calculation of the coal wall failure depth of the mining roadway, which brings safety hazards to the mining roadway.
[0055] Specifically, after the calculation of the coal wall destruction depth C of the mining roadway is completed, the stability coefficient ky of the anchored rock layer of the mining roadway in the data simulation system and the hardness coefficient fn of the anchored rock layer are obtained, the inclination angle of the coal rock body in the mining roadway is measured, the inclination angle of the coal rock body is α, and the width W of the mining roadway is measured. According to the coal wall destruction depth C of the mining roadway, the destruction depth b of the surrounding rock body of the roof of the mining roadway is calculated, and the calculation formula is:
[0056] b = (a + C) cos α / (ky × fn), where a is half the width of the mining tunnel, and a = W / 2.
[0057] After completing the calculation of the coal wall damage depth of the mining roadway, the damage depth of the mining roadway roof surrounding rock mass is calculated again. Combined with parameters such as the mining roadway width, the inclination of the coal rock mass, the stability coefficient of the anchored rock layer and the hardness coefficient of the anchored rock layer, the damage depth of the mining roadway roof surrounding rock mass is determined according to the coal wall damage depth of the mining roadway. Similarly, the damage depth of the mining roadway roof surrounding rock mass is used as the basic parameter to calculate the mining roadway support parameters, which can make the support setting in the mining roadway more in line with the stress distribution in the mining roadway, greatly reduce the stress concentration in the roof of the mining roadway, and further reduce the safety hazards in the mining work.
[0058] Specifically, according to the set anchor rod force length ratio Sr and anchor rod fixed connection length ratio Se, the length Lr of the top plate anchor rod of the mining roadway at the destruction depth b of the top plate surrounding rock mass is calculated, Lr = b + (b × Sr) + (b × Se);
[0059] Then, according to the coal wall damage depth C, the length Ls of the coal wall support anchor rod at the coal wall damage depth C in the mining tunnel is calculated, Ls = C + (C × Sr) + (C × Se).
[0060] After determining the theoretical length Lo of the support anchor at each position in the mining tunnel, where o=r, s, select the support anchor according to the actual length L1, L2 of the support anchor and the anchor length ratio A affected by the force, where A≤0.1, L1 is the standard anchor length lower than the theoretical length Lo of the support anchor, L2 is the standard anchor length higher than the theoretical length Lo of the support anchor, and there is no standard length support anchor between the L1 length support anchor and the L2 length support anchor. Calculate the standard grade length difference ΔL, ΔL=L2-L1, and then calculate the anchor excess length difference ΔLo, ΔLo=Lo-L1. Calculate the anchor excess length ratio Ao according to the anchor excess length difference ΔLo and the standard grade length difference ΔL, Ao=ΔLo / ΔL, and compare the anchor excess length ratio Ao with the anchor length ratio A affected by the force.
[0061] When Ao>A, the anchor rod with length L2 is selected as the supporting anchor rod to support the position;
[0062] When Ao≤A, select the anchor rod with length L1 as the supporting anchor rod to support the position.
[0063] When determining the length of the anchor rod, the length of the anchor rod is divided into three parts, namely the depth of the anchor rod anchored in the damaged range of the surrounding rock, the depth of the anchor rod anchored in the undamaged surrounding rock and the exposed length of the anchor rod for connection and fixation as the total length of the anchor rod, so that the anchor rod can penetrate the damaged part of the surrounding rock mass of the roof of the mining roadway, so that the anchor rod can completely support the damaged part of the surrounding rock mass of the roof of the mining roadway, further disperse the stress distribution of the roof and the two sides of the mining roadway, so that when using narrow coal pillars to mine along the goaf, the stress distribution of the mining roadway along the goaf is uniform, thereby improving the safety of the roadway.
[0064] Specifically, the gravity density γy of the coal seam and the gravity density γn of the rock layer in the mining roadway are obtained in the data simulation system, and the surrounding rock pressure Q acting on the support on the side of the damaged coal wall is calculated according to the coal wall damage depth C of the mining roadway, wherein:
[0065] Q=C×[(γyh×s inα)+γnb×tan(45°-θ)]
[0066] After the calculation of the surrounding rock pressure acting on the support on the side of the damaged coal seam is completed, the roof pressure QH of the mining roadway is calculated again according to the damaged depth b of the surrounding rock mass of the roof of the mining roadway, and it is determined according to the normal relative to the rock stratum bedding, where QH = 2γnabB.
[0067] The surrounding rock pressure acting on the support on the side of the damaged coal wall is calculated by calculating the coal wall destruction depth of the mining roadway, the gravity density of the coal seam and the gravity density of the rock layer. The overall pressure on the upper and lateral sides of the coal wall support and the inclination pressure of the rock mass on the upper roof can be taken into account. At the same time, the roof pressure of the mining roadway is calculated, and the pressure of each part in the mining roadway is accurately calculated. The support parameters of the mining roadway are determined according to the pressure of each part, so that the support setting in the mining roadway is more in line with the pressure distribution in the mining roadway, the support setting effect is increased, and the safety hazards in the mining work are further reduced.
[0068] Specifically, the spacing s between anchor bolts is determined based on the damage depth b of the surrounding rock mass of the mining roadway roof and half of the mining roadway width a. p The calculation formula is:
[0069]
[0070] Among them, Z is the length of the anchor beyond the damage depth of the roof surrounding rock mass, Z = (b × Sr) + (b × Se). The spacing between anchors is calculated based on the basic parameters such as the damage depth of the roof surrounding rock mass of the mining roadway and the width of the mining roadway. At the same time, combined with the length of the anchor that is not in the surrounding rock damage range, the setting of the spacing between anchors can meet the changes in parameters of different positions in the mining roadway, so that the anchor support of the mining roadway can achieve the greatest protection effect, and the stress of the top and coal ridge of the mining roadway can be dispersed between the anchors, which improves the support quality of the mining roadway and reduces the labor intensity of the support and maintenance staff in the later stage.
[0071] Specifically, according to the diameter d of the selected standard anchor and the tensile strength limit value σt of the anchor, the hardness coefficient f of the surrounding rock mass of the anchoring section of the mining roadway roof is obtained, and the anchoring force P of the top plate anchor at the hardness coefficient f of the surrounding rock mass of the anchoring section is calculated. The calculation formula is:
[0072] Then obtain the hardness coefficient f1 of the surrounding rock mass of the anchoring section on both sides of the mining tunnel, and calculate the anchoring force P1 of the two sides of the anchor rod at the location where the hardness coefficient of the surrounding rock mass of the anchoring section is f1. The calculation formula is:
[0073]
[0074] Complete the determination of the anchoring force P of the top plate anchor and the anchoring force P1 of the two side anchors.
[0075] In order to calculate the support effect of mining more accurately, the anchoring force of each anchor bolt on the roof of the mining tunnel is calculated. In the process of calculating the anchoring force of the anchor bolt, the strength of the surrounding rock mass, the diameter of the anchor bolt, the hardness coefficient of the surrounding rock mass in the anchoring section and the tensile strength limit value of the anchor bolt are combined to accurately determine the anchoring force of each anchor bolt. The anchoring force of the anchor bolt can be used to determine whether the support can be set up for this part of the tunnel to protect it, further avoiding the safety hazard caused by the detachment of the support due to insufficient anchoring force of the anchor bolt.
[0076] Similarly, the anchoring force of the anchor rods on both sides of the mining tunnel is calculated through the basic parameters of the anchor rods and the basic parameters of the rock wall, ensuring that the lateral stress on both sides of the mining tunnel caused by top extrusion is within the range of the anchoring force of the anchor rods, further reducing the safety hazards in the mining work.
[0077] Specifically, according to the calculated length Lr of the roof bolt of the mining roadway, the roof pressure QH of the mining roadway and the anchoring force P of the roof bolt, the number Nk of the anchor bolts in each row of the roof of the mining roadway is determined, and the result is calculated according to the balance condition of the acting force as follows:
[0078]
[0079] Among them, K3 is the safety factor, which can be adjusted according to the safety requirement level in the mining tunnel.
[0080] The number of anchors in each row of the mining roadway roof is determined according to the roof pressure of the mining roadway, the length of the roof anchors and the anchoring force of the roof anchors. The anchors on the roof of the mining roadway are used to disperse the pressure from the roof of the mining roadway, thereby improving the quality of mining roadway support and improving the safety and reliability of mining roadway support.
[0081] Specifically, after determining the number of anchors Nk in each row of the roof of the mining roadway, the row spacing ay of the supporting anchors on both sides of the coal wall in the mining roadway is calculated according to the calculated anchoring force P1 of the anchors on both sides and the surrounding rock pressure Q acting on the support on the side of the damaged coal wall. The calculation formula is:
[0082] The anchor spacing of the coal wall is calculated based on the number of anchors in each row, so that the anchors between the top of the mining roadway and the coal walls on both sides are set on the basis of the same parameters. In the actual support process, there will be no stress deviation between the top support of the mining roadway and the coal walls on both sides of the mining roadway, which will affect the actual support effect. In the case of mining along the goaf with narrow coal pillars, the support setting of the mining roadway is used to make the stress distribution of the mining roadway along the goaf uniform, further improving the safety of the roadway.
[0083] So far, the technical solutions of the present invention have been described in conjunction with the preferred embodiments shown in the accompanying drawings. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present invention.
[0084] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars, characterized in that: include, Step S1, extracting coal and rock samples from the roof and floor of the auxiliary transport chute of the working face to be mined adjacent to the goaf, conducting laboratory mechanical experiments, obtaining the physical and mechanical parameters of the surrounding rock of the auxiliary transport chute of the working face to be mined, calculating the physical and mechanical parameters of the surrounding rock using the limit equilibrium theory, obtaining the width of the limit narrow coal pillar, and using a data simulation system to determine the lateral support stress distribution data of the goaf of the working face to be mined under the condition of the width of the limit narrow coal pillar based on the physical and mechanical parameters of the surrounding rock of the auxiliary transport chute of the working face to be mined; Step S2, performing geological sampling and analysis on the working face to be mined to obtain geological parameters of the working face to be mined, simulating the stress distribution and deformation of the tunnel surrounding rock under different coal pillar widths through the data simulation system according to the geological parameters of the working face to be mined and the lateral support stress distribution data of the goaf, and determining the final coal pillar width between the working face to be mined and the goaf; Step S3, according to the determined coal pillar width, carry out goaf-side tunneling for the mining face to be mined, detect the displacement of the surrounding rock under the coal pillar width after tunneling, calculate the damage depth of the coal wall and the roof of the mining roadway in combination with the geological parameters of the mining face to be mined and the lateral support stress distribution data of the goaf, calculate the length of the support anchor at the corresponding position according to the coal seam damage depth of each part in the mining roadway, calculate the surrounding rock pressure and the roof pressure according to the coal wall damage depth, calculate the anchor force of the anchor by the rock strength of the coal wall and the roof, determine the spacing, preload and row spacing parameters of the support anchor according to the anchor force of the anchor, the surrounding rock pressure and the roof pressure, and support the mining roadway according to the various support parameters; In the step S3, the confining pressure stress concentration coefficient K of the mining roadway, the bulk density γ of the overburden stratum, the dimensionless parameter B of the mining influence level, the coal seam hardness coefficient fy, and the internal friction angle θ of the coal rock mass in the data simulation system are obtained, and then the mining roadway depth H and the mining roadway height h in the mining roadway are measured, and the coal wall destruction depth C of the mining roadway is calculated. The calculation formula of the coal wall destruction depth C of the mining roadway is, C=[(KγHB / 10 4 fy)-1]×h×tan(45°-θ / 2); After the calculation of the coal wall destruction depth C of the mining roadway is completed, the stability coefficient ky of the anchored rock layer of the mining roadway in the data simulation system and the hardness coefficient fn of the anchored rock layer are obtained, the inclination angle of the coal rock body in the mining roadway is measured, the inclination angle of the coal rock body is α, and the width W of the mining roadway is measured. According to the coal wall destruction depth C of the mining roadway, the destruction depth b of the surrounding rock body of the roof of the mining roadway is calculated, and the calculation formula is: b = (a + C) cos α / (ky × fn), where a is half the width of the mining tunnel, a = W / 2; According to the set anchor rod force length ratio Sr and anchor rod fixed connection length ratio Se, calculate the length Lr of the top plate anchor rod of the mining roadway at the damage depth b of the top plate surrounding rock mass, Lr = b + (b × Sr) + (b × Se); Then, according to the coal wall damage depth C, the length Ls of the coal wall support anchor rod at the coal wall damage depth C in the mining tunnel is calculated, Ls = C + (C × Sr) + (C × Se).
2. The method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars according to claim 1 is characterized in that: After determining the theoretical length Lo of the support anchor at each position in the mining tunnel, where o=r, s, select the support anchor according to the actual length L1, L2 of the support anchor and the anchor length ratio A affected by the force, where A≤0.1, L1 is the standard anchor length lower than the theoretical length Lo of the support anchor, L2 is the standard anchor length higher than the theoretical length Lo of the support anchor, and there is no standard length support anchor between the L1 length support anchor and the L2 length support anchor, calculate the standard grade length difference ΔL, ΔL=L2-L1, then calculate the anchor excess length difference ΔLo, ΔLo=Lo-L1, calculate the anchor excess length ratio Ao according to the anchor excess length difference ΔLo and the standard grade length difference ΔL, Ao=ΔLo / ΔL, compare the anchor excess length ratio Ao with the anchor length ratio A affected by the force, When Ao>A, select anchor rod with length L2 as the support of the position. Support anchor rod; when Ao≤A, select anchor rod with length L1 as support Protect the support anchor at this location.
3. The method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars according to claim 2 is characterized in that: The gravity density γy of the coal seam and the gravity density γn of the rock layer in the mining roadway are obtained in the data simulation system, and the surrounding rock pressure Q acting on the support on the side of the damaged coal wall is calculated according to the coal wall damage depth C of the mining roadway, wherein: Q=C×[(γyh×sinα)+γnb×tan(45°-θ)] After the calculation of the surrounding rock pressure acting on the support on the side of the damaged coal seam is completed, the roof pressure QH of the mining roadway is calculated again according to the damaged depth b of the surrounding rock mass of the roof of the mining roadway, and it is determined according to the normal relative to the rock stratum bedding, where QH = 2γnabB.
4. The method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars according to claim 3 is characterized in that: According to the destruction depth b of the surrounding rock mass of the mining roadway roof and half of the mining roadway width a, the spacing s between anchor bolts is p The calculation formula is: Wherein, Z is the length of the anchor rod exceeding the destruction depth of the surrounding rock mass of the top plate, Z = (b × Sr) + (b × Se).
5. The method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars according to claim 4 is characterized in that: According to the diameter d of the selected standard anchor rod and the tensile strength limit value σt of the anchor rod, the hardness coefficient f of the surrounding rock mass of the anchor section of the mining roadway roof is obtained, and the anchoring force P of the top plate anchor rod at the point where the hardness coefficient of the surrounding rock mass of the anchor section is f is calculated. The calculation formula is for, Then obtain the hardness coefficient f1 of the surrounding rock mass of the anchoring section on both sides of the mining tunnel, and calculate the anchoring force P1 of the two sides of the anchor rod at the location where the hardness coefficient of the surrounding rock mass of the anchoring section is f1. The calculation formula is: Complete the determination of the anchoring force P of the top plate anchor and the anchoring force P1 of the two side anchors.
6. The method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars according to claim 5 is characterized in that: According to the calculated length Lr of the roof bolt of the mining roadway, the roof pressure QH of the mining roadway and the anchoring force P of the roof bolt, the number Nk of the anchor bolts in each row of the roof of the mining roadway is determined, and the result is calculated according to the balance condition of the acting force: Among them, K3 is the safety factor, which can be adjusted according to the safety requirement level in the mining tunnel.
7. The method for protecting tunnels along goafs in shallow coal seams with narrow coal pillars according to claim 6 is characterized in that: After determining the number of anchor rods Nk in each row of the top plate of the mining roadway, the row spacing ay of the supporting anchor rods on both sides of the coal wall in the mining roadway is calculated according to the calculated anchoring force P1 of the two-wall anchor rods and the surrounding rock pressure Q acting on the support on the side of the damaged coal wall. The calculation formula is: