An intelligent design and manufacturing method for offshore drilling typhoon protection suspension single

Through intelligent design and manufacturing methods, the structure and processing technology of the single anti-typhoon suspension for offshore drilling are optimized, which solves the problems of complex and high investment in the existing design, and achieves safe navigation and economical design in harsh environments.

CN114757076BActive Publication Date: 2024-10-22CHINA UNIV OF PETROLEUM (EAST CHINA)
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210421244.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-21
Publication Date
2024-10-22
Estimated Expiration
2042-04-21

AI Technical Summary

Technical Problem

Suspension riser systems on offshore drilling platforms are prone to collisions and fractures due to vibration and load in harsh typhoon environments. The existing single-piece anti-typhoon suspensions are complex in design and difficult to manufacture, resulting in high investment and high risks.

Method used

Using intelligent design and manufacturing methods, by establishing parametric representation models, introducing machine learning algorithms, establishing finite element analysis models and multi-objective optimization models, and combining process analysis methods, the structure and processing technology of the single anti-typhoon suspension are optimized to reduce design and Manufacturing costs.

Benefits of technology

It is possible to reduce the design and manufacturing costs of a single anti-typhoon suspension, reduce the cost of trial and error, and ensure the safety of the equipment while satisfying the structural strength and functionality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114757076B_ABST
    Figure CN114757076B_ABST
Patent Text Reader

Abstract

The present invention relates to an intelligent design and manufacturing method for a single root of an offshore drilling typhoon-proof suspension. The method first establishes a structural design model based on the structural parameters of the single root of the offshore drilling typhoon-proof suspension and historical processing technology data, and carries out intelligent optimization of the structural parameters of the single root of the typhoon-proof suspension based on global finite element analysis; secondly, a process design analysis model and a strength verification model of the single root of the typhoon-proof suspension are established, virtual processing and manufacturing process analysis and local finite element analysis are carried out, and the process analysis results and local finite element analysis results are used to cyclically update the structural design model and optimize the structural parameters; finally, the optimization process is stopped when the design conditions are met, and the optimal single root structure of the offshore drilling typhoon-proof suspension is obtained and the final processing technology is determined. The present invention combines intelligent optimization theory with virtual manufacturing technology to intelligently and efficiently complete the optimization design and manufacturing process formulation of the single root of the typhoon-proof suspension, thereby improving the economy and efficiency of the design and manufacturing of the single root of the typhoon-proof suspension.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of marine oil equipment, and in particular relates to an intelligent design and manufacturing method for a marine drilling typhoon protection suspension unit. Background Art

[0002] With the depletion of oil and gas resources on land, oil and gas exploration and development have moved to the ocean, and are constantly moving towards deep waters with harsh environmental conditions and frequent typhoons. Drilling risers are key equipment for offshore oil and gas exploration and development. When encountering strong typhoons, there is a need to evacuate the risers by hanging them from the platform in order to reduce the time for recovering and lowering the risers. During the navigation and evacuation process of the platform-suspended riser system, the riser system vibrates violently under the excitation of the movement of the drilling platform and the harsh marine environmental loads, which can easily cause collisions with the moon pool and yield fracture accidents. For this reason, there is an urgent need to design and manufacture marine drilling anti-typhoon equipment for the safe navigation of the platform-suspended riser system in harsh typhoon environments.

[0003] At present, the conceptual design of the offshore drilling anti-typhoon suspension unit for dealing with typhoon environment has been completed, and the designed anti-typhoon suspension unit has the characteristics of complex structure and high manufacturing difficulty. The extremely harsh marine environment puts forward stringent requirements on the structural design strength and manufacturing quality of the anti-typhoon suspension unit, making the design and manufacture of the anti-typhoon suspension unit characterized by high investment. At the same time, the equipment connected to the lower suspension of the anti-typhoon suspension unit is of high value, and the occurrence of accidents brings extremely high trial and error costs and risks to the application of the equipment. Therefore, it is urgent to propose an intelligent design and manufacturing method to reduce the design, manufacturing and application investment of the anti-typhoon suspension unit while ensuring the essential safety of the anti-typhoon suspension unit and preventing the suspension failure of the watertight pipe system. Summary of the invention

[0004] In view of the above problems, the present invention provides an intelligent design and manufacturing method for an offshore drilling typhoon protection suspension unit, which reduces the design and manufacturing cost of the suspension unit while meeting the structural strength and functionality of the suspension unit.

[0005] The technical solution adopted by the present invention is: an intelligent design and manufacturing method for a single typhoon-proof suspension for offshore drilling, and the method is implemented in the following steps:

[0006] Step 1: Based on the actual processing operation of the workshop, a database including processing technology and processing costs is established, and the database variables are parametrically characterized to establish a parametric characterization model of the entire processing and manufacturing process; machine learning algorithms are introduced to train the parametric characterization model, a general process model between processing technology and processing costs is established, and an economic model based on the general process model is proposed.

[0007] The second step is to identify the actual structural characteristics of the single typhoon-proof suspension for offshore drilling, establish a single typhoon-proof suspension structural parameter model with the length, outer diameter and inner diameter of the pipe string structure segment as the main characteristics, and the transition arc between each pipe string segment as the transition feature, and further integrate the material parameters of the single typhoon-proof suspension to form a structural design model.

[0008] The third step: identify the key structural features of the typhoon-proof suspension single root, the connection coupling relationship between the typhoon-proof suspension single root and the watertight pipe system, and the platform motion information; establish a global finite element analysis model of the typhoon-proof suspension single root and the watertight pipe coupling system with the main characteristics of the pipe column structure as variables; take structural strength and economy as design goals, and propose a multi-objective optimization model for the typhoon-proof suspension single root combined with the economic model; establish the constraint conditions of the multi-objective optimization model based on the physical limit and strength limit criteria of the structural material, and introduce the multi-objective optimization algorithm to carry out optimization analysis to obtain multiple sets of Pareto optimal solutions for the design parameters of the typhoon-proof suspension single root structure.

[0009] The fourth step: Based on the Pareto optimal solution of the structural design parameters of the typhoon-proof suspension, determine the transition characteristic size parameters of each pipe string section, establish a structural strength verification model for the typhoon-proof suspension, carry out local finite element analysis, and determine the mechanical characteristics of the typhoon-proof suspension considering the transition characteristics and decoupling conditions; establish a process design model for the typhoon-proof suspension, introduce the processing technology analysis method, and determine the full-process processing technology of the typhoon-proof suspension; based on the analysis of the mechanical characteristics and processing technology of the typhoon-proof suspension, perform parametric characterization between the structural parameters and mechanical characteristics of the typhoon-proof suspension, and between the structural parameters and processing technology of the typhoon-proof suspension, and establish a proxy model for the mechanical characteristics of the typhoon-proof suspension and a special proxy model for the processing technology.

[0010] Step 5: Based on the proxy model of the mechanical properties of the typhoon-proof suspension and the special proxy model for the processing technology, the structural design model of the typhoon-proof suspension is updated. At the same time, as a supplementary model of the global finite element analysis model of the typhoon-proof suspension, the multi-objective optimization design of the typhoon-proof suspension with structural strength and economy as the design goals is carried out; on this basis, the strength verification model and process design model of the typhoon-proof suspension are updated to form a closed-loop iterative process, and the design of the suspension is continuously optimized based on process analysis and structural strength calculation.

[0011] Step 6: During the cyclic optimization design process, the optimization iteration process is terminated when the structural strength and economic efficiency indicators of a single typhoon-proof suspension meet the requirements that the change between the two changes is less than 2% and the comprehensive change in structural parameters is less than 5%. The last optimized structural parameters of the single typhoon-proof suspension are rounded to obtain the final detailed structural design parameters, and the processing technology analysis and correction are completed to obtain the optimal structural parameters and processing technology of the single typhoon-proof suspension.

[0012] Furthermore, in the first step, the processing technology includes the process name, tooling, process steps, process content and processing equipment; the process content includes the workpiece size and processing volume; the processing cost includes the workpiece material cost, processing equipment loss and maintenance cost, and worker wage payment cost; based on the long-term operation of the processing workshop, skilled workers and relevant technical personnel shall record and conduct technical evaluation of the processing technology and the processing cost.

[0013] Furthermore, in the second step, the main body of the typhoon-proof suspension single pipe column is composed of n sections of cylinders or frustums, the cylinder or frustum is composed of the center of the fixed end as the coordinate origin, the end face direction as the x-axis, the axial direction as the y-axis, and the cross section of the cylinder or frustum is composed of the main characteristic point C j,1 , C j,2 , C j,3 , C j,4 Determine; the section where the transition feature of the single pipe column for typhoon protection is located is determined by the arc radius R j , starting point R j,a and the arc center R j,c Determine; determine the single cylindrical cross-section of the typhoon protection suspension by the points on the cross-section, and determine the single structural parameter model of the typhoon protection suspension by rotating along the y-axis.

[0014] The main characteristic point C on the cross section of a cylinder or a truncated cone j,1 , C j,2 , C j,3 , C j,4 Determined by the segment length, outer diameter, and wall thickness of the pipe string structure, the coordinate points are expressed in a matrix as follows:

[0015]

[0016] In the formula, the first column is the horizontal axis, the second column is the vertical axis, D1 j , d1 j are the outer diameter and inner diameter of the end surface of the jth cylinder or truncated cone, both refer to the radius; D2 j , d2 j are the outer diameter and inner diameter of the lower end surface of the jth cylinder or truncated cone, both refer to the radius; L j is the height of the jth cylinder or frustum.

[0017] The coordinates of the arc points on the cross section where the transition feature is located are expressed in a matrix:

[0018]

[0019] A parametric model for the structural design of a single root of the typhoon-proof suspension is established by n groups of main feature points and n-1 groups of transition feature points, which is used to establish a finite element model and a process design model of the single root of the typhoon-proof suspension.

[0020] Furthermore, in the third step, the global finite element analysis model of the typhoon-proof suspension single-rod and watertight pipe coupling system established is expressed as:

[0021]

[0022] Where M, C, K, and F are the mass matrix, damping matrix, stiffness matrix, and load vector in the finite element analysis equation of the typhoon-proof suspension single root and the watertight pipe coupling system, respectively. δ is the displacement vector. Solving this equation and calculating the mechanical parameters, all the mechanical characteristic parameters of the typhoon-proof suspension single root and the watertight pipe coupling system under external loads are obtained.

[0023] Combined with the general process model, the parameters of the single-root structure design of the typhoon-proof suspension are used as the optimization design variables, and the established multi-objective optimization model is expressed as follows:

[0024] min[f ms (X),f ec (X)]

[0025]

[0026] In the formula, X is the design optimization variable, f ms (X), f ec (X) are the single-strand strength objective function of the typhoon protection suspension based on finite element analysis and the economic objective function based on the general process model, respectively. plpu , g plpu They are the physical limit and strength limit of the typhoon-proof single suspension pipe and the watertight pipe system, and these limit criteria constitute the constraints of the optimization model.

[0027] Furthermore, in the fourth step, the Pareto optimal solution of the structural design parameters of the typhoon-proof suspension single root is a plurality of sets of data obtained after global optimization of the structural parameters of the typhoon-proof suspension single root. Based on each set of data and the transition characteristic dimensions, a local finite element analysis model of the typhoon-proof suspension single root is established, and a database including the transition characteristic dimensions, main characteristic dimensions and stress extreme values ​​of the typhoon-proof suspension single root is obtained. Similarly, a process analysis is performed on the typhoon-proof suspension single root that has been preliminarily designed, and a database of processing technology and processing cost including process content and processing equipment is established. The processing technology includes the full process processing technology of the suspension single root from forging, turning, milling, grinding, and heat treatment. Finally, a mechanical parameter proxy model and a special proxy model of the processing technology are established according to their respective databases.

[0028] Furthermore, in the fifth step, the objective function f ms (X) becomes the weighted sum of the single root mechanical property proxy model and the global finite element analysis model for typhoon protection, and the objective function f ec(X) is transformed into a weighted sum of a dedicated proxy model of processing technology and a general process model; and the optimal single-root structural parameters of the typhoon-proof suspension are obtained by continuously performing cyclic updating and iterative optimization.

[0029] Furthermore, in the sixth step, rounding processing is performed on the basis of the obtained typhoon-proof suspension single-root optimization parameters to obtain the final typhoon-proof suspension single-root structural parameters; the tooling, work steps, process contents and processing equipment involved in the entire typhoon-proof suspension single-root processing process are repeatedly analyzed and verified to determine the final processing technology; from then on, the virtual design and processing stage of the typhoon-proof suspension single-root is transferred to the physical manufacturing stage.

[0030] Since the present invention adopts the above technical scheme, it has the following advantages: the present invention fully considers the processing technology in the actual full-process manufacturing process of mechanical equipment, combines intelligent optimization theory with virtual manufacturing technology, and constructs an intelligent design and manufacturing method for typhoon-proof suspension single roots based on finite element simulation analysis technology and data-driven model, so as to realize the intelligent and deep integration of the theoretical structural design parameters of the typhoon-proof suspension single roots and the actual processing technology data, reduce the manufacturing and processing trial and error costs in the optimization and manufacturing process of the suspension single roots, and ensure the essential safety of the typhoon-proof suspension single roots. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 The overall logic diagram of the intelligent design and manufacturing method for the typhoon protection suspension single root of offshore drilling.

[0032] Figure 2 Flowchart of the intelligent design and manufacturing method for typhoon-proof suspension single root for offshore drilling.

[0033] Figure 3 Schematic diagram of the coupling system of a single suspended and riser pipe for typhoon protection in offshore drilling.

[0034] In the figure, 1. Drilling platform, 2. Typhoon protection suspension single rod, 3. Lateral restraint, 4. Riser system. DETAILED DESCRIPTION

[0035] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the protection scope of the present invention.

[0036] like Figure 1 and Figure 2 As shown, the present invention proposes an intelligent design and manufacturing method for an offshore drilling typhoon-proof suspension single bar, comprising the following steps:

[0037] (1) Skilled workers and relevant technical personnel in the workshop record the process name, tooling, process steps, process content, processing equipment and manufacturing cost of equipment parts in actual processing and manufacturing. The process content includes the workpiece size and processing volume. The processing cost includes the workpiece material cost, processing equipment loss and maintenance cost, and worker salary payment cost. The recorded results are used to establish a historical processing technology database; the processing technology and processing cost are parametrically represented to form a parametric representation model that uses data to represent the processing process and processing cost. Machine learning is used to train the parametric representation model to form a general process model and economic model with processing technology parameters as input and manufacturing cost as output.

[0038] (2) Figure 3 As shown in the figure, a typhoon-proof suspension single-root 2-column structural parameter model is established with the segment length, outer diameter and inner diameter of the typhoon-proof suspension single-root 2-column structure as the main features and the transition arc between each column segment as the transition feature; the main body of the typhoon-proof suspension single-root 2-column is set to be composed of n sections of cylinders or frustums, and the cylinder or frustum is composed of the center of the fixed end as the coordinate origin, the end face direction as the x-axis, the axial direction as the y-axis, and the cross section of the cylinder or frustum is composed of the main feature point C j,1 , C j,2 , C j,3 , C j,4 Determine; the section where the transition feature of the single 2-column suspension for typhoon protection is located is determined by the arc radius R j , starting point R j,a and the arc center R j,c Determine; determine the 2-cylindrical section of the typhoon-proof suspension by the points on the section, and determine the 2-parameter model of the typhoon-proof suspension single-root structure along the y-axis; the main characteristic point C on the cylindrical or truncated cone section j,1 , C j,2 , C j,3 , C j,4 Determined by the segment length, outer diameter, and wall thickness of the pipe string structure, the coordinate points are expressed in a matrix as follows:

[0039]

[0040] In the formula, the first column is the horizontal axis, the second column is the vertical axis, D1 j , d1 j are the outer diameter and inner diameter of the end surface of the jth cylinder or truncated cone, both refer to the radius; D2 j , d2 j are the outer diameter and inner diameter of the lower end surface of the jth cylinder or truncated cone, both refer to the radius; L j is the height of the jth cylinder or cone.

[0041] The coordinates of the arc points on the cross section where the transition feature is located are expressed in a matrix:

[0042]

[0043] A single-root 2-structural parameter model of typhoon-proof suspension is established by n groups of main feature points and n-1 groups of transition feature points.

[0044] (3) The key structural features of the typhoon-proof suspension single root 2, the coupling relationship between the typhoon-proof suspension single root 2 and the watertight pipe system 4, and the motion information of the drilling platform 1 are identified, and the universal lateral vibration equation and axial vibration equation of the typhoon-proof suspension single root 2 and the watertight pipe system 4 are established based on the infinitesimal method. The universal lateral vibration equation is expressed as:

[0045]

[0046] The general axial vibration equation is:

[0047]

[0048] Where, E, I, A, c and m are the elastic modulus, moment of inertia, cross-sectional area, damping coefficient and mass of the typhoon protection suspension single pipe 2 and the watertight pipe system 4, respectively. x 、f y are the axial hydrodynamic load and the lateral hydrodynamic load respectively, and w is the wet weight.

[0049] The vibration equations of the typhoon-proof suspension single root 2 and the watertight pipe system 4 are discretized, and a global finite element analysis model of the typhoon-proof suspension single root 2 and the watertight pipe coupling system is established with the main characteristics of the pipe column structure as variables, which is expressed as follows:

[0050]

[0051] Where M, C, K, and F are the mass matrix, damping matrix, stiffness matrix, and load vector in the finite element analysis equation of the coupling system of the typhoon-proof suspension single root 2 and the watertight pipe, respectively, and δ is the displacement vector.

[0052] Combining the general process model with the economic model, the typhoon protection suspension single-root 2 structural parameters are taken as optimization design variables, and the established multi-objective optimization model is expressed as follows:

[0053] min[f ms (X),f ec (X)]

[0054]

[0055] In the formula, X is the design optimization variable, f ms (X), f ec (X) are the strength objective function of the single 2-wire suspension for typhoon protection based on finite element analysis and the economic objective function based on the general process model, respectively. plpu , g plpuThey are the physical limits and strength limits of the typhoon protection suspension single root 2 and the watertight pipe system 4, respectively, and constitute the constraint conditions of the optimization model based on the limit criteria; the physical limit in the constraint conditions is mainly the lateral deformation of the watertight pipe system 4, and the strength limit is the Mises stress of the watertight pipe system 4 and the minimum axial force of the watertight pipe system 4.

[0056] Based on MATLAB or Python, a global finite element analysis model of the typhoon-proof suspension single root 2 and the watertight pipe coupling system is developed to solve the Pareto optimal solution of the structural design parameters of the typhoon-proof suspension single root 2.

[0057] (4) Based on the Pareto optimal solution of the structural design parameters of the typhoon-proof suspension single root 2, the transition characteristic size parameters of each pipe string section are determined, and a structural strength verification model of the typhoon-proof suspension single root 2 based on ABAQUS, ANSYS or CATIA is established. The local finite element analysis of the typhoon-proof suspension single root 2 in the decoupled state from the watertight pipe system 4 is carried out, and the influence of the transition characteristics and main characteristics on the stress and strain of the typhoon-proof suspension single root 2 is determined and parameterized. The neural network and data fitting method are introduced to establish a proxy model of the transition characteristic size and stress-strain mechanical parameters.

[0058] At the same time, a process design model of a typhoon-proof suspension single piece 2 is established based on the DELMIA process analysis software, a database of the full process processing technology and processing cost of forging, turning, milling, grinding and heat treatment of the typhoon-proof suspension single piece 2 is established, and a special agent model for training the processing technology is introduced using neural networks and data fitting methods.

[0059] (5) Considering the influence of the actual structural characteristics of the typhoon protection suspension single root 2 on the global finite element analysis model and the economic model, the objective function f is updated in a weighted form. ms (X) and f ec (X); Continuously perform iterative optimization to obtain the best typhoon-proof suspension single-root 2 structural parameters.

[0060] (6) During the cyclic optimization design process, the optimization iteration process is terminated when the structural strength and economic efficiency indicators of the typhoon-proof suspension single root 2 meet the requirements that the change between the two changes is less than 2% and the comprehensive change of the structural parameters is less than 5%. The structural parameters of the last typhoon-proof suspension single root 2 are corrected in detail and rounded to obtain structural parameters that are more in line with the actual structural characteristics. The tooling, work steps, process contents and processing equipment involved in the entire processing of the typhoon-proof suspension single root 2 are repeatedly analyzed and verified to determine the final processing technology.

[0061] Obviously, those skilled in the art should understand that the steps in the flowcharts of the present invention and the above embodiments are displayed in sequence according to the arrows, but these steps are not necessarily executed in the order indicated by the arrows. Unless otherwise clearly stated herein, there is no strict order restriction for the execution of these steps, and they can be executed in other orders.

[0062] The above are only specific steps of the present invention and do not constitute any limitation to the protection scope of the present invention; they can be extended to the design and manufacturing process of related equipment, and any technical solutions formed by equivalent transformation or equivalent replacement shall fall within the protection scope of the present invention.

[0063] The present invention does not elaborate on some of the well-known technologies that belong to those skilled in the art.

Claims

1. An intelligent design and manufacturing method for an offshore drilling typhoon protection suspension single bar, characterized in that: The following steps are included: Step 1: Based on the actual processing operation of the workshop, a database including processing technology and processing costs is established, and the database variables are parametrically characterized to establish a parametric characterization model of the entire processing and manufacturing process; machine learning algorithms are introduced to train the parametric characterization model, a general process model between processing technology and processing costs is established, and an economic model based on the general process model is proposed; Step 2: Identify the actual structural features of the single typhoon-proof suspension for offshore drilling, establish a single typhoon-proof suspension structural parameter model with the length, outer diameter and inner diameter of the pipe string structure as the main features, and the transition arc between each pipe string segment as the transition feature, and further integrate the material parameters of the single typhoon-proof suspension to form a structural design model; Step 3: Identify the key structural features of the typhoon-proof suspension, the connection and coupling relationship between the typhoon-proof suspension and the watertight pipe system, and the platform motion information, and establish a global finite element analysis model of the typhoon-proof suspension and watertight pipe coupling system with the main features of the pipe column structure as variables; take structural strength and economy as design goals, and propose a multi-objective optimization model for the typhoon-proof suspension combined with the economy model; establish the constraint conditions of the multi-objective optimization model based on the physical limit and strength limit criteria of the structural material, and introduce the multi-objective optimization algorithm to carry out optimization analysis to obtain multiple groups of Pareto optimal solutions for the design parameters of the typhoon-proof suspension structure; Step 4: Based on the Pareto optimal solution of the structural design parameters of the typhoon-proof suspension, determine the transition characteristic size parameters of each pipe string section, establish a structural strength verification model of the typhoon-proof suspension, carry out local finite element analysis, and determine the mechanical characteristics of the typhoon-proof suspension considering the transition characteristics and decoupling conditions; establish a process design model for the typhoon-proof suspension, and introduce the processing technology analysis method to determine the full-process processing technology of the typhoon-proof suspension; based on the analysis of the mechanical characteristics and processing technology of the typhoon-proof suspension, perform parametric characterization between the structural parameters and mechanical characteristics of the typhoon-proof suspension, and between the structural parameters and processing technology of the typhoon-proof suspension, and establish a proxy model for the mechanical characteristics of the typhoon-proof suspension and a special proxy model for the processing technology; Step 5: Based on the proxy model of mechanical properties of the typhoon-proof suspension and the proxy model for processing technology, the structural design model of the typhoon-proof suspension is updated. At the same time, as a supplementary model of the global finite element analysis model of the typhoon-proof suspension, a multi-objective optimization design of the typhoon-proof suspension with structural strength and economy as the design objectives is carried out; On this basis, the single-strand strength verification model and process design model of the typhoon-proof suspension are updated to form a closed-loop iterative process, and the single-strand structural parameters of the typhoon-proof suspension are continuously optimized based on the process analysis and structural strength analysis results. Step 6: During the cyclic optimization design process, the optimization iteration process is terminated when the structural strength and economic efficiency indicators of a single typhoon-proof suspension meet the requirements that the change between the two changes is less than 2% and the comprehensive change in structural parameters is less than 5%. The last optimized structural parameters of the single typhoon-proof suspension are rounded to obtain the final detailed structural design parameters, and the processing technology analysis and correction are completed to obtain the optimal structural parameters and processing technology of the single typhoon-proof suspension.

2. The intelligent design and manufacturing method of a single typhoon-proof suspension for offshore drilling according to claim 1 is characterized by: In the first step, the processing technology includes the process name, tooling, process steps, process content and processing equipment. The process content includes the workpiece size and processing volume. The processing cost includes the workpiece material cost, processing equipment loss and maintenance cost, and worker salary payment cost. According to the long-term operation of the processing workshop, skilled workers and relevant technical personnel shall record and conduct technical evaluation of the processing technology and the processing cost.

3. The intelligent design and manufacturing method of a single typhoon-proof suspension for offshore drilling according to claim 1 is characterized by: In the second step, the main body of the single typhoon suspension column is composed of n sections of cylinders or cones. The cylinder or cone is composed of the center of the fixed end as the coordinate origin, the end face direction as the x-axis, the axial direction as the y-axis, and the cross section of the cylinder or cone is composed of the main characteristic point C j,1 , C j,2 , C j,3 , C j,4 Determine; the section where the transition feature of the single pipe column for typhoon protection is located is determined by the arc radius R j , starting point R j,a and the arc center R j,c Determine; determine the cross section of a single cylindrical typhoon-proof suspension from the points on the cross section, and determine the single structural parameter model of the typhoon-proof suspension by rotating along the y-axis; The main characteristic point C on the cross section of a cylinder or a truncated cone j,1 , C j,2 , C j,3 , C j,4 Determined by the segment length, outer diameter, and wall thickness of the pipe string structure, the coordinate points are expressed in a matrix as follows: In the formula, the first column is the horizontal axis, the second column is the vertical axis, D1 j , d1 j are the outer diameter and inner diameter of the end surface of the jth cylinder or truncated cone, both refer to the radius; D2 j , d2 j are the outer diameter and inner diameter of the lower end surface of the jth cylinder or truncated cone, both refer to the radius; L j is the height of the jth cylinder or frustum; The coordinates of the arc points on the cross section where the transition feature is located are expressed in a matrix: A parametric model for the structural design of a single root of the typhoon-proof suspension is established by n groups of main feature points and n-1 groups of transition feature points, which is used to establish a finite element model and a process design model of the single root of the typhoon-proof suspension.

4. The intelligent design and manufacturing method of a single typhoon-proof suspension for offshore drilling according to claim 1 is characterized by: In the third step, the global finite element analysis model of the typhoon-proof suspension single-rod and watertight pipe coupling system established is expressed as: In the formula, M, C, K, and F are the mass matrix, damping matrix, stiffness matrix, and load vector in the finite element analysis equation of the typhoon-proof suspension single-wire and watertight pipe coupling system, respectively. δ is the displacement vector. Solving this equation and calculating the mechanical parameters, all mechanical characteristic parameters of the typhoon-proof suspension single-wire and watertight pipe coupling system under external loads are obtained. Combined with the general process model, the parameters of the single-root structure design of the typhoon-proof suspension are used as the optimization design variables, and the established multi-objective optimization model is expressed as follows: min[f ms (X),f ec (X)] In the formula, X is the design optimization variable, f ms (X), f ec (X) are the single-strand strength objective function of the typhoon protection suspension based on finite element analysis and the economic objective function based on the general process model, respectively. plpu , g plpu They are the physical limit and strength limit of the typhoon-proof single suspension pipe and the watertight pipe system, and these limit criteria constitute the constraints of the optimization model.

5. The intelligent design and manufacturing method of a single typhoon-proof suspension for offshore drilling according to claim 1 is characterized by: In the fourth step, the Pareto optimal solution of the structural design parameters of the typhoon-proof suspension single root is a plurality of sets of data obtained after global optimization of the structural parameters of the typhoon-proof suspension single root. Based on each set of data and the transition characteristic dimensions, a local finite element analysis model of the typhoon-proof suspension single root is established to obtain a database including the transition characteristic dimensions, main characteristic dimensions and stress extreme values ​​of the typhoon-proof suspension single root. Similarly, a process analysis is performed on the preliminarily designed typhoon-proof suspension single root, and a database of processing technology and processing cost including process contents and processing equipment is established. The processing technology includes the full-process processing technology of the suspension single root from forging, turning, milling, grinding, and heat treatment. Finally, a mechanical parameter proxy model and a special proxy model of the processing technology are established according to their respective databases.

6. The intelligent design and manufacturing method of a single typhoon-proof suspension for offshore drilling according to claim 1 is characterized by: In the fifth step, the objective function f ms (X) becomes the weighted sum of the single root mechanical property proxy model and the global finite element analysis model for typhoon protection, and the objective function f ec (X) is transformed into a weighted sum of a dedicated proxy model of processing technology and a general process model; and the optimal single-root structural parameters of the typhoon-proof suspension are obtained by continuously performing cyclic updating and iterative optimization.

7. The intelligent design and manufacturing method of a single typhoon-proof suspension for offshore drilling according to claim 1 is characterized by: In the sixth step, rounding processing is performed on the basis of the obtained typhoon protection suspension single-root optimization parameters to obtain the final typhoon protection suspension single-root structural parameters; the tooling, work steps, process content and processing equipment involved in the entire typhoon protection suspension single-root processing process are repeatedly analyzed and verified to determine the final processing technology; from then on, the virtual design and processing stage of the typhoon protection suspension single-root is transferred to the physical manufacturing stage.