A board test platform and test method for subway operation system
By designing a board test platform containing multiple modules and using the sliding window principle to process test signals, the problem of resource waste and high cost of traditional test platforms is solved, and efficient testing for quickly locating fault points is achieved.
Patent Information
- Application Number
- CN202210352699.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-31
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2042-03-31
AI Technical Summary
The board test platform of the traditional subway operation system wastes resources and is costly, and cannot locate fault points efficiently and quickly.
Design a test platform that includes a digital acquisition module, a digital output module, an analog input and output module, and a pulse signal acquisition module. The test signal is sent through the input socket, and the RIOM chassis, gateway board, RPT board, and CCU unit are used. Perform signal processing and data exchange with the ERM unit, and use the sliding window principle to calculate the empirical likelihood value to determine whether the equipment is faulty.
It achieves rapid location of subway operation system fault points, reduces resource waste and costs, and improves testing efficiency.
Smart Images

Figure CN114814533B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of subway operation system testing, and in particular to a board card testing platform and a testing method for a subway operation system. Background Art
[0002] At present, the board test bench used for subway operation system is usually composed of train network operation products. When the digital quantity acquisition module, digital quantity output module, analog quantity input and output module, and pulse signal acquisition module in the subway operation system fail, the train operation status is simulated to reproduce the faulty equipment and quickly find the cause and point of the fault. The traditional test bench is basically composed of equipment according to the original vehicle plan, that is, each component of the test bench is a component actually used in the subway operation system. Therefore, although the entire test bench is basically fully functional, there will be a waste of resources and high cost. Summary of the invention
[0003] The present invention provides a board test platform and a test method for a subway operation system to overcome the above technical problems.
[0004] In order to achieve the above object, the technical solution of the present invention is:
[0005] A board test platform for a subway operation system, comprising a device to be tested, wherein the device to be tested comprises a digital quantity acquisition module, a digital quantity output module, an analog quantity input and output module, a pulse signal acquisition module, and further comprises: a chassis, a display unit, a main control chassis, an RIOM chassis, an input plug-in box, an output plug-in box, and a power supply;
[0006] The input plug-in box is connected to the device under test so as to send a test signal to the device under test through the input plug-in box; the test signal includes: a digital input signal, an analog input and output signal, and a pulse signal;
[0007] The RIOM chassis includes a RIOM backplane, an RPT board, and a gateway board; the RIOM backplane is provided with a numerical quantity acquisition module interface, a digital quantity output interface, an analog quantity input and output interface, and a pulse signal acquisition interface;
[0008] The digital quantity acquisition module is connected to the numerical quantity acquisition module interface to transmit the digital quantity input signal to the RIOM backplane;
[0009] The analog input and output module is connected to the analog input and output interface to transmit the analog input and output signals to the RIOM backplane;
[0010] The pulse signal acquisition module is connected to the pulse signal acquisition interface to transmit the pulse signal to the RIOM backplane;
[0011] The gateway board is connected to the RIOM backplane; so that the digital input signal, analog input and output signal and pulse signal can be exchanged with the gateway board through the RIOM backplane;
[0012] The gateway board is connected to the RPT board to amplify the digital input signal / analog input / output signal / pulse signal through the RPT board to obtain the amplified digital input signal / amplified analog input / output signal / amplified pulse signal;
[0013] The main control chassis includes a main control backplane, a CCU unit and an ERM unit; the CCU unit and the ERM unit are both connected to the main control backplane;
[0014] The RPT board is connected to the input end of the ERM unit to achieve data exchange between the RPT board and the ERM unit;
[0015] The output end of the ERM unit is connected to the input end of the CCU unit respectively to realize data exchange between the ERM unit and the CCU unit;
[0016] The output end of the CCU unit is connected to the input end of the display unit to realize data exchange between the CCU unit and the display unit;
[0017] The output plug-in box is connected to the digital output interface; so as to feedback the working status of the device under test through the output plug-in box;
[0018] The display unit, the main control backplane, the RIOM backplane, the input plug-in box, and the output plug-in box are all connected to the power supply;
[0019] The display unit, the main control chassis, the RIOM chassis, the input plug-in box, and the output plug-in box are all arranged inside the chassis.
[0020] Furthermore, it also includes a computer; the computer is connected to the ERM unit to achieve data exchange between the computer and the ERM unit.
[0021] Furthermore, it also includes a first terminal resistor; the output end of the display unit is connected to the first terminal resistor.
[0022] Furthermore, it also includes a second terminal resistor and a third terminal resistor;
[0023] The RPT board includes an MVB-L1 interface, an MVB-L2 interface, an MVB-R1 interface, and an MVB-R2 interface;
[0024] The MVB-R1 interface of the RPT board is connected to the input end of the ERM unit;
[0025] The MVB-R2 interface of the RPT board is connected to the third terminal resistor;
[0026] The MVB-L1 interface of the RPT board is connected to the gateway board;
[0027] The MVB-L2 interface of the RPT board is connected to the second terminal resistor.
[0028] Furthermore, it also includes a fourth terminal resistor;
[0029] The gateway board includes an MVB1 interface and an MVB2 interface;
[0030] The MVB1 interface of the gateway board is connected to the MVB-L1 interface of the RPT board;
[0031] The MVB2 interface of the gateway board is connected to the fourth terminal resistor.
[0032] The present invention also discloses a board card testing method for a board card testing platform of a subway operation system, comprising the following steps:
[0033] S1: The input plug-in box sends a test signal to the device under test to obtain the test signal data;
[0034] S2: The signal data to be tested is transmitted to the gateway board through the numerical quantity acquisition module interface, the analog quantity input and output interface and the pulse signal acquisition interface to obtain the network signal data to be tested;
[0035] S3: The network signal data to be tested is transmitted to the RPT board, and the amplified signal data to be tested is obtained;
[0036] S4: The amplified test signal data is transmitted to the CCU unit, and the CCU unit processes the amplified test signal data to obtain the processed test signal data, and then determines whether the test device fails;
[0037] S5: The processed test signal data is transmitted to the output plug-in box through the digital output interface, so as to judge and display whether a fault state occurs according to the state of the output plug-in box.
[0038] Furthermore, in S4, the CCU unit processes the amplified signal data to determine whether the device under test fails by:
[0039] S41: Assume that the length of the normal sample data set is 2m,
[0040] S42: Divide the normal sample data set into a reference sample data set: and validation sample dataset
[0041] Right now:
[0042] S43: Using the sliding window principle, the validation sample data set is divided into m-a+1 validation sample data set subsets of length a (a<m):
[0043]
[0044] S44: Calculate the empirical likelihood value in each group of windows to obtain the likelihood value set {L1, L2, ..., L m-a+1};
[0045] S45: Obtaining a confidence limit L0 according to the likelihood value of the validation sample data set subset;
[0046] S46: Selecting a sample data set to be tested with a length of 2 m from the amplified signal data to be tested;
[0047] S47: According to S42 to S45, a likelihood value set {L′1, L′2, L′3 . . .} of the sample data set to be tested is obtained;
[0048] S48: If any likelihood value of a sample to be tested in the likelihood value set of the sample data set to be tested is greater than the confidence limit L0, it is determined that the device to be tested has a fault;
[0049] Otherwise, it is determined that the device under test has no fault.
[0050] Furthermore, the formula for calculating the empirical likelihood value in each group of windows in S44 is as follows:
[0051]
[0052] Where: L is the likelihood value of the data set in the sliding window; p i is the probability mass of the data set in the sliding window.
[0053] Furthermore, the method for obtaining the confidence limit L0 is as follows:
[0054]
[0055] in,
[0056] Where: Z is the reference coefficient under different values of confidence.
[0057] Furthermore, before step S5, the method further includes: if the device under test fails, the ERM unit records the processed data of the signal under test.
[0058] Beneficial effect: The board card testing platform and testing method for the subway operation system of the present invention designs a set of circuit board fault testing test benches, which simulate the operating state of the subway operation system when working by inputting the signal sent by the plug-in box, thereby reproducing the working state of the subway operation vehicle, and can quickly locate the fault point to obtain the cause of the failure of the subway operation system. BRIEF DESCRIPTION OF THE DRAWINGS
[0059] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0060] Figure 1 It is a topological diagram of the board test platform for subway operation of the present invention;
[0061] Figure 2 This is a schematic diagram of the appearance of a test platform for the subway operation method of the present invention;
[0062] Figure 3 This is a power supply principle diagram of the digital quantity acquisition module of the present invention;
[0063] Figure 4 This is a power supply principle diagram of the input plug box of the present invention;
[0064] Figure 5 This is a power supply principle diagram of the analog input and output module of the present invention;
[0065] Figure 6 This is a power supply principle diagram of the output plug box of the present invention;
[0066] Figure 7 This is a schematic diagram of the input interface of the power board of the present invention;
[0067] Figure 8 This is a schematic diagram of the output interface of the power board of the present invention;
[0068] Fig. 9Schematic diagram of the X5 pin in an embodiment of the present invention;
[0069] Fig.10 Schematic diagram of the X6 pin in an embodiment of the present invention;
[0070] Fig.11 is a fault detection flow chart in an embodiment of the present invention.
[0071] Among them: 1. Main control chassis; 2. RIOM chassis; 3. Input plug-in box; 4. Display unit; 5. Output plug-in box; 9. Chassis. DETAILED DESCRIPTION
[0072] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0073] This embodiment provides a board test platform and a test method for a subway operation system. Figure 1-11 As shown, the device under test includes a digital quantity acquisition module, a digital quantity output module, an analog quantity input and output module, and a pulse signal acquisition module, and is characterized in that it includes: a chassis 9, a display unit 4, a main control chassis 1, a RIOM chassis 2, an input plug-in box 3, an output plug-in box 5, a power supply, and a computer; the chassis in this embodiment adopts a 19-inch cabinet with a size of 600x600x1830 (mm).
[0074] The input plug-in box 3 (ITM) is connected to the device under test to send a test signal to the device under test through the input plug-in box 3; the test signal includes: a digital input signal, an analog input and output signal, and a pulse signal;
[0075] The RIOM chassis 2 includes a RIOM backplane, an RPT board (repeater), and a gateway board; the RIOM backplane is provided with a numerical quantity acquisition module interface, a digital quantity output interface, an analog quantity input and output interface, and a pulse signal acquisition interface;
[0076] The digital quantity acquisition module is connected to the numerical quantity acquisition module interface to transmit the digital quantity input signal to the RIOM backplane;
[0077] The analog input and output module is connected to the analog input and output interface to transmit the analog input and output signals to the RIOM backplane;
[0078] The pulse signal acquisition module is connected to the pulse signal acquisition interface to transmit the pulse signal to the RIOM backplane;
[0079] The gateway board (GW) is connected to the RIOM backplane; so that the digital input signal, analog input and output signal and pulse signal can be exchanged with the gateway board through the RIOM backplane;
[0080] Preferably, the gateway board includes an MVB1 interface and an MVB2 interface; the MVB1 interface of the gateway board is connected to the MVB-L1 interface of the RPT board; and the MVB2 interface of the gateway board is connected to the fourth terminal resistor.
[0081] The gateway board is connected to the RPT board to amplify the digital input signal / analog input / output signal / pulse signal through the RPT board to obtain the amplified digital input signal / amplified analog input / output signal / amplified pulse signal;
[0082] The main control chassis 1 includes a main control backplane, a CCU unit and an ERM unit; the CCU unit and the ERM unit are both connected to the main control backplane; the CCU unit (main control unit) and the ERM unit (data recording unit) are powered by the main control backplane; the CCU and ERM in this embodiment have the same hardware structure, and only realize their respective functions through different internal software. They all have MVB interface, RS232 serial communication interface, M12 and RJ45 Ethernet interface, USB interface, and the main control chassis as a whole is a standard 3U structure.
[0083] The RPT board is connected to the input end of the ERM unit to achieve data exchange between the RPT board and the ERM unit;
[0084] Preferably, the RPT board includes an MVB-L1 interface, an MVB-L2 interface, an MVB-R1 interface, and an MVB-R2 interface;
[0085] The MVB-R1 interface of the RPT board is connected to the input end of the ERM unit;
[0086] The MVB-R2 interface of the RPT board and the 19-inch cabinet are used as carriers, and the size is 600x600x1830 (mm). The third terminal resistor is connected;
[0087] The MVB-L1 interface of the RPT board is connected to the gateway board;
[0088] The MVB-L2 interface of the RPT board is connected to the second terminal resistor.
[0089] The output end of the ERM unit is connected to the input end of the CCU unit respectively to realize data exchange between the ERM unit and the CCU unit;
[0090] The output end of the CCU unit is connected to the input end of the display unit 4 to realize data exchange between the CCU unit and the display unit 4; the output end of the display unit 4 is connected to the first terminal resistor;
[0091] The output plug-in box 5 is connected to the digital output interface; so as to feedback the working status of the device under test through the output plug-in box 5;
[0092] The display unit 4, the main control backplane, the RIOM backplane, the input plug-in box 3, and the output plug-in box 5 are all connected to the power supply;
[0093] The display unit 4, the main control chassis 1, the RIOM chassis 2, the input plug-in box 3, and the output plug-in box 5 are all arranged inside the chassis.
[0094] The computer is connected to the ERM unit to realize data exchange between the computer and the ERM unit, so as to maintain the CCU unit, the ERM unit and the gateway board, and ensure that the entire test platform can work normally.
[0095] Specifically, the CCU unit (main control unit) in this embodiment includes X5: a first MVB2 interface and X6: a first MVB1 interface; the ERM includes X5: a second MVB2 interface and X6, a second MVB1 interface and X4: an RJ45 interface;
[0096] The first MVB2 interface is connected to the second MVB1 interface;
[0097] The first MVB1 interface is connected to the display unit 4;
[0098] The RJ45 interface is connected to the computer;
[0099] The display unit 4HMI in this embodiment is INC-90.49, which is the display screen used by Beijing Subway Line 6, and can monitor the operation and communication status of the test bench CCU unit, ERM unit, and RIOM unit under test; the CCU unit (main control unit) adopts the PQ-171 chassis, which is the vehicle main control program of Beijing Subway Line 6, and can connect any network control system device that complies with Beijing Subway Line 6 as the device to be tested, and record the operation data of the device to be tested. The ERM unit (data recording unit) adopts the PQ-204 chassis, which also uses the program of the train monitoring system of Beijing Subway Line 6, and can also connect any network control system device that complies with Beijing Subway Line 6 as the device to be tested to record its fault data.
[0100] Specifically, the chassis in this embodiment is equipped with a power supply module, which can use the load energy of multiple devices and has the conversion function of converting 220V AC into 110V DC. It can provide suitable conversion voltage for the display unit 4, main control unit, RIOM unit, input plug-in box 3 (ITM), and output plug-in box 5 (OTM).
[0101] Specifically, after the ERM is connected to the PTU computer, the PTU computer can be used to force related variables online, so that the ERM unit can simulate the data of each port of the test bench and determine whether the test equipment has a fault. Specifically, the input plug-in box 3 in this embodiment adopts the BX10-P02-004 chassis, which is a standard 6U chassis size and can be placed in a 19-inch cabinet. The parameters of the DI connector include 160 signal switch quantities, DC110V / 50mA, of which the first 140 signals share the same input terminal (DC110V), and the last 20 signals need to be connected to a separate input terminal; and 7 signal switch quantities, AC220V / 2A. The parameters in the AX connector include 12 channels, 0~10V, and a maximum current of 0.5A.
[0102] The output plug-in box (0TM) in this embodiment adopts the BX10-P02-005 chassis, which is used to check whether the hard-wired connections of the digital quantity acquisition module DI, the digital quantity output module DO, the analog quantity input and output module AX, and the pulse signal acquisition module PWM are online. Figure 5 The electrical schematic diagram of the output plug-in box has 48 signals in total. The RPT board, i.e. the relay output, requires the voltage / current limit to be AC220V / 8A. If the device under test does not fail, the output indicator light will be green. If the device under test fails, the indicator light on the output plug-in box 5 will be red.
[0103] The RIOM backplane in this embodiment is a power conversion board with a rated voltage of 110V input and 24V output, and its external interface is as shown in the attached Figure 7 and attached Figure 8 .
[0104] Specifically, the first terminal resistor, the second terminal resistor, the third terminal resistor and the fourth terminal resistor in this embodiment are all used to prevent the reflection of the MVB signal. Since the signal is amplified by the RPT board, in order to reduce the interference generated after the signal is amplified, the terminal is added to ensure that the board test platform in this embodiment can work smoothly. The gateway board in this embodiment can be used for communication protocol conversion between MVB and RS485, MVB and CAN, and its interface definition is shown in the table:
[0105]
[0106]
[0107] Specifically, in this embodiment, when the device to be tested is a CCU unit and an ERM unit of a subway operation system, the CCU unit and the ERM unit in the main control chassis of the present invention can be replaced. It is convenient to test each module of the subway system. When the device to be tested is a CCU unit and an ERM unit, the ERM unit can be connected to the RPT board.
[0108] The present invention also discloses a board card testing method for a subway operation system, comprising the following steps:
[0109] S1: The input plug-in box 3 sends a test signal to the device under test to obtain the test signal data;
[0110] S2: The signal data to be tested is transmitted to the gateway board through the numerical quantity acquisition module interface, the analog quantity input and output interface and the pulse signal acquisition interface to obtain the network signal data to be tested;
[0111] S3: The network signal data to be tested is transmitted to the RPT board, and the amplified signal data to be tested is obtained;
[0112] S4: The amplified test signal data is transmitted to the CCU unit, and the CCU unit processes the amplified test signal data to obtain the processed test signal data, and then determines whether the test device fails;
[0113] The method in which the CCU unit processes the amplified signal data to determine whether the device under test fails is as follows:
[0114] S41: Assume that the length of the normal sample data set is 2m,
[0115] S42: Divide the normal sample data set into a reference sample data set: and validation sample dataset
[0116] Right now:
[0117] S43: Using the sliding window principle, the validation sample data set is divided into m-a+1 validation sample data set subsets of length a (a<m):
[0118]
[0119] S44: Calculate the empirical likelihood value in each group of windows to obtain the likelihood value set {L1, L2, ..., L m-a+1};
[0120] The formula for calculating the empirical likelihood value within each group of windows is as follows:
[0121]
[0122] Where: L is the likelihood value of the data set in the sliding window; p i is the probability mass of the data set in the sliding window.
[0123] S45: Obtaining a confidence limit L0 according to the likelihood value of the validation sample data set subset;
[0124] The method for obtaining the confidence limit L0 is as follows:
[0125] in, Represents the mean of the empirical likelihood function values corresponding to each sliding window data set;
[0126] Where: Z is the reference coefficient of confidence at different values. The selection of confidence can be found in the normal distribution Z value table.
[0127] S46: Selecting a sample data set to be tested with a length of 2 m from the amplified signal data to be tested;
[0128] S47: According to S42 to S45, a likelihood value set {L′1, L′2, L′3 . . .} of the sample data set to be tested is obtained;
[0129] S48: If any likelihood value of a sample to be tested in the likelihood value set of the sample data set to be tested is greater than the confidence limit L0, it is determined that the device to be tested has a fault;
[0130] Otherwise, it is determined that the device under test has no fault.
[0131] If the device under test fails, the ERM unit records the processed signal data under test.
[0132] S5: The processed test signal data is transmitted to the output plug-in box 5 through the digital output interface, so as to determine whether a fault occurs through the status of the output plug-in box 5 .
[0133] Specifically, in this embodiment, the normal sample data (already stored in the storage card) when the CCU unit built-in device under test is normal, according to 600 data per minute, a 4-minute normal sample data set is selected, including 2400 data, the first 1200 data are reference samples, and the last 1200 are verification samples. In the verification sample data set, 1001 verification sample data set subsets with a length of 200 are selected by the sliding window principle, and the corresponding empirical likelihood function value is obtained for each verification sample data set subset. In order to improve the accuracy, the confidence level is selected as 99%, and the confidence limit is obtained as 0.68.
[0134] Insert the device under test into the test bench. At this time, the CCU unit obtains the amplified signal data under test, selects the same amount of data as the normal sample data set as the sample data set under test, selects 2201 subsets of the sample data set under test with a length of 200, and calculates the corresponding empirical likelihood function value for each subset of the sample data set under test. If the empirical likelihood function values corresponding to the 2201 subsets of the sample data set under test are all ≤0.68, the device under test has no fault. If there is a certain subset (assuming it is 1080) where the calculated likelihood function value is greater than 0.68, the device under test has a fault.
[0135] Specifically, in this embodiment, it is assumed that the number of data in the selected normal sample data set is an even number, and the data in the reference sample data set verification sample data set is the same. If the number of data in the selected normal sample data set is an even number, that is, 2m+1, then the number of data in the reference sample data set verification sample data set is m and m+1 respectively, so that the amount of data in the reference sample data set verification sample data set is almost the same, which can ensure that the error of the verification result is minimized.
[0136] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A board test method for a board test platform of a subway operation system, It is characterized in that The steps include: S1: The input plug-in box sends a test signal to the device under test to obtain the test signal data; S2: The measured signal data is transmitted to the gateway board through the numerical quantity acquisition module interface, the analog quantity input and output interface and the pulse signal acquisition interface to obtain the network measured signal data; S3: The network signal data to be tested is transmitted to the RPT board, and the amplified signal data to be tested is obtained; S4: The amplified test signal data is transmitted to the CCU unit, and the CCU unit processes the amplified test signal data to obtain processed test signal data, and then determines whether the test device fails; In S4, the CCU unit processes the amplified signal data to determine whether the device under test fails. The method is: S41: Assume that the length of the normal sample data set is 2m, S42: Divide the normal sample data set into a reference sample data set: and validation sample dataset Right now: S43: Use the sliding window principle to divide the validation sample data set into m-a+1 validation sample data set subsets of length a, where a <m: S44: Calculate the empirical likelihood value in each group of windows to obtain the likelihood value set of the validation sample data set subset {L 1 , L 2 , …, L m-a+1 }; S45: Obtain the confidence limit L according to the likelihood value of the validation sample data set subset 0 ; S46: Selecting a sample data set to be tested with a length of 2 m from the amplified signal data to be tested; S47: According to S42 to S45, obtain the likelihood value set {L' 1 , L' 2 , L' 3 …}; S48: If any of the likelihood values of the sample data set to be tested exists and is greater than the confidence limit L 0 , it is determined that the device under test fails; Otherwise, it is determined that the device under test has no fault; S5: The processed test signal data is transmitted to the output plug-in box through the digital output interface, so as to judge and display whether a fault state occurs according to the state of the output plug-in box.
2. A board test method for a board test platform for a subway operation system according to claim 1, It is characterized in that The formula for calculating the empirical likelihood value in each group of windows in S44 is as follows: Where: L is the likelihood value of the data set in the sliding window; p i is the probability mass of the data set in the sliding window.
3. The board test method of the board test platform for a subway operation system according to claim 1, It is characterized in that The confidence limit L is obtained 0 The method is as follows: in, Where: Z is the reference coefficient under different values of confidence.
4. The board test method of the board test platform for a subway operation system according to claim 1, It is characterized in that Before step S5, the method further includes: if the device under test fails, the ERM unit records the processed signal data under test.
Citation Information
Patent Citations
Universal device, system and method for RIOM performance test
CN112015608A
Remote input and output module of train control and monitoring system
CN202372844U