Intelligent path optimization control method and system for sweeper

By constructing a tree structure diagram of the sweeper's driving path, calculating edge weights and coordination loss values, and optimizing the path combination of multiple sweepers, it solves the problems of insufficient utilization of traditional sweeper resources and large path planning calculations, and achieves Efficient and timely garbage removal and real-time path planning.

CN114839999BActive Publication Date: 2024-10-18JINING JINGZE INFORMATION TECH CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210595872.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-30
Publication Date
2024-10-18
Estimated Expiration
2042-05-30

AI Technical Summary

Technical Problem

When traditional sweepers clean up garbage through cyclic movement, they cannot effectively utilize vehicle resources, leading to the accumulation or waste of garbage in some neighborhoods. Moreover, path planning requires a large amount of calculations and cannot guarantee real-time performance.

Method used

The intelligent path optimization control method is used to construct a tree structure diagram of the sweeper's driving path. The reliability is calculated through edge weights and coordination loss values, and the path combination of multiple sweepers is optimized to quickly determine the optimal path plan.

Benefits of technology

It improves the efficiency of sweeper vehicles and the timeliness of garbage cleaning, reduces the calculation amount of path planning, and meets the needs of real-time path planning with the cooperation of multiple vehicles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114839999B_ABST
    Figure CN114839999B_ABST
Patent Text Reader

Abstract

The present invention discloses an intelligent path optimization control method and system for a sweeper, belonging to the field of vehicle path control technology; comprising the following steps: obtaining the cleaning time of multiple sweepers to complete street cleaning in a service block, constructing multiple driving path scheme combinations; calculating the edge weight of a single sweeper from a street node to any adjacent street node through all driving path scheme combinations from a street node to any adjacent street node in the service block; adding the coordination loss values ​​of the first sweeper and all sweepers as the comprehensive coordination loss value; selecting the connection line from the s node to the i-th node with the largest reliability as the best new path plan for the first sweeper; combining the new path plans of each sweeper to obtain the optimal path plan combination. The present invention obtains the reliability of the direction according to the coordination loss value and the edge weight, and obtains the optimal path plan combination according to the direction reliability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of vehicle path control, and in particular to an intelligent path optimization control method and system for a sweeper. Background Art

[0002] With the development of social economy and the improvement of urbanization level, the amount of garbage generated has also increased. If the garbage is not cleaned up in time, the accumulation of garbage will affect people's lives. Therefore, it is necessary to use a sweeper to clean up the garbage in time. Traditionally, the sweeper cleans up the garbage by moving back and forth in a cycle to collect the garbage. However, the different garbage generation efficiency in various places causes the sweeper to be unable to be fully utilized, that is, there may be some blocks where the sweepers are particularly busy and cannot clean up the garbage in time, while some blocks are particularly idle and there is no garbage to collect. At the same time, the different congestion conditions in each block will also cause different garbage cleaning time costs. When cleaning other blocks in a cycle, the blocks that have been cleaned in the early stage will generate new garbage. At the same time, the speed of garbage generation in each block is different. For example, the garbage generation efficiency of block A is relatively high, and the garbage generation efficiency of block E is relatively high, but the two blocks are far apart. If the garbage is cleaned by a circular movement of a car, when the sweeper moves to block E for garbage cleaning, a large amount of garbage will accumulate in block A. Therefore, this method cannot achieve timely cleaning of garbage in each block.

[0003] In order to improve the utilization rate of each sweeper and ensure the timeliness of garbage cleaning in each block, it is considered to complete the garbage cleaning through the cooperation of multiple sweepers. The key point in the cooperation of multiple sweepers is how to achieve close cooperation among multiple sweepers. For example, when sweeper a completes the road cleaning of block A at 10 minutes and 50 seconds, sweeper b comes to clean the block at 10 minutes and 55 seconds. Due to the short time interval, the amount of garbage generated may be small, which will cause the sweepers to be not closely coordinated and waste the sweepers. At the same time, the garbage generation efficiency of each block is different. Some blocks have a higher garbage generation efficiency. When using sweepers for cleaning, the cleaning frequency of the block needs to be increased. For example, the garbage generation efficiency of block A is 10kg / h, and the garbage generation efficiency of block B is 5kg / h. Therefore, with the same small time interval, the garbage generation of block A is twice that of block B.

[0004] In order to achieve the above purpose, the technicians in this field provide a cleaning solution based on the above problem, which can not only meet the timeliness of garbage cleaning but also meet the high efficiency of each vehicle. Under normal circumstances, all feasible cleaning solutions need to be listed, and the evaluation index of each solution is calculated by evaluating the cleaning situation of each solution, and then the solution with the best cleaning effect is selected. However, in this case, all possible paths need to be traversed to find the optimal path. Therefore, this method has too much calculation and cannot guarantee the real-time performance of path planning. Summary of the invention

[0005] The present invention provides an intelligent path optimization control method and system for a road sweeper, which uses all feasible solutions for each vehicle to construct a tree structure diagram of the vehicle driving path. A part of the path solution data is traversed to obtain a solution evaluation value, and the edge weight of each edge of the vehicle driving path tree diagram is calculated according to the characteristics of the traversed solution data. The vehicle coordination loss when each edge is used as a path direction edge is analyzed, and the reliability of the direction is obtained according to the coordination loss value and the edge weight, and the optimal path solution combination is obtained according to the direction reliability.

[0006] The first object of the present invention is to provide an intelligent path optimization control method for a sweeper, comprising the following steps:

[0007] Obtain the cleaning time of multiple street sweepers in the service block to complete street sweeping, and construct a driving path tree diagram of each sweeper, wherein each driving path tree diagram has multiple driving path plans; select any driving path plan from different driving path plans of each sweeper to combine, and construct multiple driving path plan combinations;

[0008] The edge weight of a single street sweeper from a street node to any adjacent street node is obtained by calculating the combination of all driving path solutions from a street node to any adjacent street node in the service block;

[0009] Selecting a first sweeper and a second sweeper from a plurality of sweepers, presetting the first sweeper to pass through a street node s to the i-th node adjacent to the street, and the second sweeper to pass through the i-th node, where i is the number of street nodes adjacent to the s node;

[0010] The coordination loss value of the first sweeper from the s node to the i node relative to the second sweeper arriving at the i node is calculated by the time when the first sweeper arrives at the i node and the time when the second sweeper arrives at the i node from the initial node; the coordination loss value of the first sweeper and other sweepers is obtained by analogy with this method, and the coordination loss value of the first sweeper and all sweepers is added as the comprehensive coordination loss value;

[0011] Then, the reliability of the first sweeper from node s to the i-th adjacent node is obtained by subtracting the comprehensive coordination loss value from the edge weight of the first sweeper from node s to the i-th adjacent node. In this way, the reliability of different nodes adjacent to node s is calculated, and the connection from node s to the i-th node with the largest reliability is selected as the best new path plan for the first sweeper.

[0012] By analogy, this method calculates the best new path plan for each sweeper in turn;

[0013] And the new path plans of each sweeper are combined to obtain the optimal path plan combination.

[0014] Preferably, the edge weight of a single street sweeper from a street node to any adjacent street node is obtained according to the following steps:

[0015] Obtain the waste generation efficiency of each street in the service block;

[0016] Analyze the path scheme combination to obtain the start cleaning time sequence of each sweeper on the same street, and obtain the garbage cleaning amount of each sweeper on the street through the start cleaning time sequence of each sweeper on the same street and the garbage generation efficiency of the street;

[0017] The evaluation value of the path scheme combination on the cleaning situation of the street block is calculated by including the amount of garbage cleaned by each street sweeper on a street, the total number of streets cleaned in the service block, and the total number of vehicles passing on each street; the evaluation values ​​of multiple different driving path scheme combinations are calculated in sequence;

[0018] An average is calculated based on the evaluation values ​​of all driving path scheme combinations from a street node to any adjacent street node, and an edge weight of a single street sweeper from a street node to any adjacent street node is calculated based on the average.

[0019] More preferably, the calculation formula of the edge weight from the s node to the i-th node is as follows:

[0020]

[0021] In the formula, Represents the average evaluation value from the sth node to the i-th adjacent node;

[0022] Represents the number of street nodes adjacent to node s;

[0023] Represents the edge weight from the sth node to the i-th adjacent node.

[0024] More preferably, the garbage generation efficiency of each street is obtained by collecting garbage samples from the garbage areas of the street, and then subtracting the garbage volumes at certain intervals and dividing by the interval time.

[0025] More preferably, the fit loss value is obtained according to the following steps:

[0026] Selecting the best route plan combination from multiple driving route plan combinations;

[0027] The minimum time coordination deviation ratio of the second sweeper's arrival at the i-th node relative to the first sweeper's arrival at the i-th node from the s node to the i-th node is calculated by using the first time interval between the first sweeper and the second sweeper's arrival at the i-th node in the optimal path solution combination and the second time interval between the first sweeper's arrival at the i-th node and the second sweeper's arrival at the i-th node in any driving path solution;

[0028] For the driving path plan corresponding to the minimum time coordination deviation ratio in which the second sweeper can reach the i-th node, the edge weight loss of the second sweeper starting from the initial point to reach the i-th node in the driving path plan is calculated;

[0029] Therefore, the coordination loss value of the first sweeper from the s node of a street to the i-th node adjacent to the next level street relative to the second sweeper reaching the i-th node is calculated through the minimum time coordination deviation ratio and the edge weight loss.

[0030] More preferably, if the driving path plan of the second road sweeper is different, multiple second time intervals are obtained; and the minimum time coordination deviation ratio is obtained by respectively calculating the first time interval with multiple second time intervals.

[0031] More preferably, the calculation formula of the minimum time matching deviation ratio is as follows:

[0032]

[0033] In the formula, represents the second time interval for the second sweeper to reach the i-th node in any driving path plan;

[0034] represents the first time interval between the first sweeper and the second sweeper arriving at the i-th node in the optimal path solution combination;

[0035] It represents the minimum time coordination deviation ratio of the second sweeper to reach the i-th node relative to the first sweeper from the s node to the i-th node.

[0036] More preferably, the path solutions with the largest evaluation values ​​are combined into the optimal path solution combination.

[0037] Preferably, the edge weight loss is obtained according to the following steps:

[0038] Assume that the second sweeper starts from the initial point and reaches the i-th node through multiple nodes, analyze the maximum value of the edge weight in the node level where each node is located, and calculate the difference between each node and the maximum value of the node in the level as the loss value of the edge weight of the node;

[0039] The loss values ​​of the edge weights from the initial point to the i-th node through multiple nodes are added together to obtain the edge weight loss of the second sweeper from the initial point to the i-th node.

[0040] The second object of the present invention is to provide an intelligent path optimization control system for a sweeper, comprising:

[0041] The collection and construction module is used to obtain the cleaning time of multiple street sweepers in the service block to complete street cleaning, and to construct a driving path tree diagram of each street sweeper, wherein each driving path tree diagram of the street sweeper has multiple driving path plans; and to select any driving path plan from the different driving path plans of each street sweeper to combine and construct multiple driving path plan combinations;

[0042] An edge weight calculation module, used for calculating the edge weight of a single street sweeper from a street node to any adjacent street node by combining all driving path schemes from a street node to any adjacent street node in a service block;

[0043] A preset module is selected for selecting a first sweeper and a second sweeper from among multiple sweepers, and the first sweeper is preset to pass through a street node s to the i-th node adjacent to the street, and the second sweeper passes through the i-th node, where i is the number of street nodes adjacent to the s node;

[0044] A comprehensive coordination loss value calculation module is used to calculate the coordination loss value of the first sweeper from the s node to the i-th node relative to the second sweeper arriving at the i-th node by using the time when the first sweeper arrives at the i-th node and the time when the second sweeper arrives at the i-th node from the initial node; the coordination loss value of the first sweeper and other sweepers is obtained by analogy with the method, and the coordination loss value of the first sweeper and all sweepers is added as the comprehensive coordination loss value;

[0045] The best path determination module for the sweeper is used to obtain the reliability of the first sweeper from the s node to the i-th adjacent node by removing the comprehensive coordination loss value from the edge weight of the first sweeper from the s node to the i-th node, and to adjust and calculate the reliability of different adjacent nodes, and select the connection from the s node to the i-th node with the largest reliability as the best new path plan for the first sweeper; and the best new path plan for each sweeper is calculated in turn by analogy with this method;

[0046] The optimal path plan combination determination module is used to combine the new path plans of each sweeper to obtain the optimal path plan combination;

[0047] The controller is used to coordinate the work of the collection and construction module, the edge weight calculation module, the preset selection module, the comprehensive coordination loss value calculation module, the sweeper optimal path determination module and the optimal path plan combination determination module.

[0048] The beneficial effects of the present invention are:

[0049] The present invention obtains the cleaning time of multiple street sweepers in the service block to complete street sweeping, constructs a dendrogram of the driving path of each sweeper, selects any driving path plan from the different driving path plans of each sweeper to combine, constructs multiple driving path plan combinations, traverses a part of the path plan data to obtain the plan evaluation value, calculates the edge weight of each edge of the tree diagram of the driving path of the sweeper according to the characteristics of the traversed plan data, analyzes the vehicle coordination loss when each edge is used as a path direction edge, obtains the reliability of the direction according to the coordination loss value and the edge weight, and obtains the optimal path plan combination according to the direction reliability. In this way, a more optimal path plan can be found quickly.

[0050] The present invention takes into account the problem that vehicle cleaning path planning under multi-vehicle cooperation cannot meet real-time requirements, uses the previously traversed solutions to guide the search direction of the next solution, reduces the number of path traversals, and efficiently determines the optimal solution. BRIEF DESCRIPTION OF THE DRAWINGS

[0051] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0052] Figure 1 A schematic flow chart of the overall steps of an embodiment of an intelligent path optimization control method for a road sweeper of the present invention;

[0053] Figure 2 The present invention is a control principle block diagram of an intelligent path optimization control system for a road sweeper. DETAILED DESCRIPTION

[0054] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0055] The present invention provides an intelligent path optimization control method for a sweeper, see Figure 1 As shown, the following steps are included:

[0056] S1. Determine that multiple sweepers are performing cleaning work in the service block.

[0057] The street image is collected by multiple cameras arranged on a street, and the multiple images collected by multiple cameras on the street are transmitted to the computer central processing unit. The image stitching algorithm is used to perform image stitching processing to obtain the complete street image of the block, and the YOLOv3 target detection algorithm is used to identify garbage in each complete street image and identify the garbage area. The area of ​​the garbage area is used to reflect the amount of garbage, and then the amount of garbage on each street is obtained; the amount of garbage on each street is obtained by analogy. Among them, the image stitching algorithm adopts the APAP algorithm. It should be noted that the YOLOv3 target detection algorithm and the APAP algorithm used in this embodiment are both existing technologies and will not be described here. Then, the garbage generation efficiency of the street is obtained by subtracting the amount of garbage at a certain interval and dividing it by the interval time.

[0058] The road camera collects images of each street, obtains the cleaning time of multiple street sweepers in the service block, and constructs a tree diagram of the driving path of each street sweeper. In the process of constructing each street sweeper, for each street in the block, each street is regarded as a tree node. The connection between two nodes indicates that the two streets are adjacent streets, that is, the two streets can be directly reached. At the same time, the streets of the next level adjacent to each street are regarded as adjacent nodes on the tree diagram;

[0059] At the same time, in order to increase the utilization rate of the sweeper and the timeliness of garbage cleaning, it is considered to use multiple sweepers to cooperate. Therefore, if there are several vehicles, several vehicle driving tree diagrams need to be constructed.

[0060] Because under normal circumstances, the sweeper generally starts from a fixed point, then arrives at a designated location, and dumps the garbage. Therefore, the starting point of all sweepers set by the present invention is the same designated location, and the end point is also the same designated location.

[0061] In order to achieve close coordination between vehicles, the cleaning interval of each street should be as similar as possible, that is, to avoid the situation where no one cleans the same street for a long time, resulting in continuous accumulation of garbage, and sometimes multiple cleanings in a short period of time, resulting in empty running of vehicles. For example, when vehicle A goes to street A for cleaning at 10 minutes and 30 seconds, and vehicle B goes to street A for control at 10 minutes and 31 seconds, the interval between the two is very short, and the amount of new garbage generated during the interval is very small, so vehicle B cleans very little garbage. Therefore, the evaluation indicators of each scheme are constructed based on this feature, as follows:

[0062] In the driving path tree diagram of each sweeper, multiple driving path plans are provided; by selecting any driving path plan from the different driving path plans in each sweeper to combine, multiple driving path plan combinations are constructed; that is, randomly selecting one of the multiple path plans of each sweeper, combining the selected plans to obtain a driving path plan combination, and in this way, several driving path plan combinations are obtained.

[0063] S2. The edge weight of a single street sweeper from a street node to any adjacent street node is calculated by combining all driving path plans from a street node to any adjacent street node in the service block. The specific method is as follows:

[0064] First, based on the combination of driving route plans, we analyze the start time sequence of each street sweeper on the same street, and then obtain the garbage removal amount of each street sweeper on the same street through the start time sequence of each street sweeper on the same street and the garbage generation efficiency of the street; the details are as follows:

[0065] Assume that garbage collection starts at , the start time of sweeper A cleaning street A is , the start time of sweeper B cleaning street A is , the start time of sweeper C cleaning street A is At the same time, assuming that sweeper A is the first vehicle to start cleaning Street A, the amount of garbage at the start time is obtained through image recognition , the amount of garbage cleaned by sweeper A this time is The amount of garbage that sweeper B sweeps on Street A is the amount of garbage generated between the time sweeper A finishes sweeping and the time sweeper B arrives at Street A for cleaning. , the amount of garbage ,in, represents the garbage generation rate of Street A;

[0066] In this way, the amount of garbage removed by each street sweeper on Street A can be obtained.

[0067] Secondly, in order to make the time intervals of each sweeping vehicle as even as possible, to prevent the problem of some time intervals being too long causing untimely garbage cleaning and some time intervals being too long causing vehicle waste, the number of vehicles passing through the street should also match the garbage generation rate, that is, the amount of garbage cleaned by each vehicle passing through each block should be as equal as possible. Therefore, the evaluation value of the path plan combination for the block cleaning situation is calculated by including the amount of garbage cleaned by each sweeper on a street, the total number of streets cleaned in the service block, and the total number of vehicles passing through each street; the evaluation values ​​of multiple different driving path plan combinations are calculated in turn; the calculation formula of the evaluation value of the cleaning plan is shown as follows:

[0068]

[0069] In the formula, It represents the variance of the time intervals of all the sweepers passing through the i-th street in the j-th scheme combination. This value is used to reflect the reasonable time allocation characteristics of garbage cleaning. The larger the value, the greater the deviation of the time intervals of the vehicles passing through the i-th street.

[0070] M represents the total number of streets that need to be cleaned;

[0071] represents the cleaning volume of each street sweeper on the i-th street in the j-th scheme combination;

[0072] It represents the mean amount of garbage cleaned by all the sweepers in the j-th solution combination each time they pass the i-th street;

[0073] represents the total number of vehicles passing through all streets in the jth solution combination;

[0074] It represents the deviation value of the garbage volume cleaned up each time on the i-th street in the j-th scheme combination. The larger the value is, the more unreasonable the vehicle path arrangement of the scheme combination is.

[0075] represents the evaluation value of the jth driving path solution combination;

[0076] In this way, the evaluation value of each solution combination is obtained.

[0077] Finally, the mean is calculated based on the evaluation values ​​of all driving path scheme combinations from a street node to any adjacent street node, and the edge weight of a single street sweeper from a street node to any adjacent street node is calculated by the mean. The edge weights of each driving path dendrogram are calculated by analyzing the traversed scheme information, as follows:

[0078] The edge weight of each street sweeper driving tree diagram is related to the path evaluation value caused by the vehicle driving from a street node to an adjacent street node in a certain direction. Assuming that starting from node s, there will be three adjacent node directions s1, s2, and s3, among which the path direction to s3 has a relatively high corresponding evaluation value. Therefore, the edge weight from s to s3 is larger. The specific calculation method is as follows:

[0079] Based on the analysis of a single node of the dendrogram of the driving path of a single sweeper, the connection weight between the node and the adjacent node of the next level is calculated.

[0080] Analyze the tree diagram of street sweeper A, obtain all the path plans of street sweeper A through street node s, obtain the evaluation value corresponding to each path plan, and average the evaluation values ​​of all path plans from node s to node s1. , in this way we get s to s1, s to s2, ..., s to s q The mean of the evaluation values. q represents the number of street nodes adjacent to the sth node. Therefore, the calculation formula for the edge weight from the sth node to the i-th node is as follows:

[0081]

[0082] In the formula, Represents the average evaluation value from the sth node to the i-th adjacent node;

[0083] Represents the number of street nodes adjacent to node s;

[0084] Represents the edge weight from the sth node to the i-th adjacent node.

[0085] Thus, the edge weights between nodes are obtained in this way; at the same time, the edge weights of any path plan traveled by each sweeper are also obtained.

[0086] S3, calculating the coordination loss value of each cleaning vehicle in the connecting edge between each node;

[0087] Although the edge weight obtained for a single sweeper is very high, it cannot reflect the coordination between the sweepers. Although the cleaning effect is relatively good for a single sweeper, it cannot guarantee that the cleaning direction is also relatively good when multiple sweepers cooperate. For example, the nodes adjacent to the sth node are s1, s2, ..., s q , according to the analysis of a single vehicle, this direction is most likely to be the optimal path. However, considering the coordination of multiple vehicles, there may be a time interval when the vehicle arrives at the node that is not the optimal time interval. Therefore, it is necessary to combine the coordination of each vehicle.

[0088] First, a first sweeper and a second sweeper are selected from multiple sweepers, and it is preset that the first sweeper passes through a street node s to the i-th node adjacent to the street, and the second sweeper passes through the i-th node, where i is the number of street nodes adjacent to the s node; wherein, the preset driving path plan of the first sweeper from the initial position to the s-th node selects the driving path plan with the largest edge weight;

[0089] There are two main aspects that affect the coordination loss. One is the edge weight loss value of the second sweeper's driving route segment corresponding to the driving direction of the first sweeper compared to the optimal path solution segment. The other is the time interval deviation ratio of the second sweeper's driving route segment corresponding to the driving direction of the first sweeper.

[0090] The coordination loss value of the first sweeper from the s node to the i-th node relative to the second sweeper arriving at the i-th node is calculated by the time the first sweeper arrives at the i-th node and the time the second sweeper arrives at the i-th node from the initial node, as follows:

[0091] The best route plan combination is selected from multiple driving route plan combinations; the route plan combination with the largest evaluation value is combined into the best route plan combination.

[0092] The minimum time coordination deviation ratio of the second sweeper to the i-th node relative to the first sweeper from the s node to the i-th node is calculated by using the first time interval between the first sweeper and the second sweeper in the optimal path solution combination and the second time interval between the first sweeper arriving at the i-th node and the second sweeper arriving at the i-th node in any driving path solution; the details are as follows:

[0093] If the driving path plan of the second road sweeper is different, multiple second time intervals are obtained; the minimum time matching deviation ratio is obtained by calculating the first time interval with the multiple second time intervals respectively.

[0094] The calculation formula of the minimum time matching deviation ratio is as follows:

[0095]

[0096] In the formula, represents the second time interval for the second sweeper to reach the i-th node in any driving path plan;

[0097] represents the first time interval between the first and second sweepers arriving at the i-th node in the optimal path solution combination;

[0098] It represents the minimum time coordination deviation ratio of the second sweeper to reach the i-th node relative to the first sweeper from node s to the i-th node.

[0099] Secondly, for the driving path plan corresponding to the minimum time coordination deviation ratio for the second sweeper to reach the i-th node, the edge weight loss of the second sweeper from the initial point to the i-th node in the driving path plan is calculated; wherein the weight loss is obtained according to the following steps:

[0100] Assume that the second street sweeper starts from the initial point and passes through multiple nodes to reach the i-th node. Analyze the maximum value of the edge weight in the node level where each node is located, and calculate the difference between each node and the maximum value of the node in this level as the loss value of the edge weight of the node; add up the loss values ​​of the edge weights from the initial point to the i-th node through multiple nodes, and obtain the edge weight loss of the second street sweeper from the initial point to the i-th node.

[0101] Thus, the coordination loss value of the first sweeper from the s node of a street to the i-th node adjacent to the next level street relative to the second sweeper reaching the i-th node is calculated through the minimum time coordination deviation ratio and the edge weight loss. The calculation formula of the coordination loss value is as follows:

[0102]

[0103] In the formula, It represents the minimum time coordination deviation ratio of the second sweeper to reach the i-th node relative to the first sweeper from node s to the i-th node.

[0104] It represents the edge weight loss of the second sweeper from the initial point to the i-th node in the driving path plan

[0105] It represents the coordination loss value of the first street sweeper from the s node of a street to the i-th node adjacent to the next level of street relative to the second street sweeper reaching the i-th node.

[0106] Finally, analogously to the above method, the coordination loss value between the first sweeper and other sweepers is obtained, and the comprehensive coordination loss value is obtained by adding the coordination loss values ​​of the first sweeper and all sweepers. ;

[0107] S4, calculating the reliability of each sweeper and determining the best new path plan for each sweeper;

[0108] The reliability of the first sweeper from node s to the i-th adjacent node is obtained by subtracting the comprehensive coordination loss value from the edge weight of the first sweeper from node s to the i-th node. The reliability calculation formula is as follows:

[0109]

[0110] In the formula, The sum of the coordination loss values ​​of the first sweeper and all sweepers is taken as the comprehensive coordination loss value;

[0111] represents the edge weight of the first sweeper from the sth node to each i-th node;

[0112] Represents the reliability of the first sweeper from node s to the i-th adjacent node.

[0113] By adjusting the first sweeper from the s node to different i-th nodes, the reliability of different adjacent nodes is calculated, and the connection from the s node to the i-th node with the largest reliability is selected as the best new path plan for the first sweeper;

[0114] By analogy with the above method, the best new path plan for each sweeper is calculated in turn;

[0115] S5. Combining the new path plans of each cleaning vehicle to obtain an optimal path plan combination, using the optimal plan combination as the cleaning path of the cleaning vehicle, and completing the cleaning work of each vehicle according to the path.

[0116] In addition, each sweeper can also drive along the driving route of the optimal solution combination for 10 minutes. After driving for 10 minutes, the route is recalculated using the above method according to the position of each sweeper, and the newly calculated route is updated. In the next stage, the sweeper drives and cleans according to the newly updated route. In this way, the route is updated every 10 minutes, and the road cleaning is completed according to the latest updated route.

[0117] The intelligent path optimization control system of the sweeper provided by the present invention is shown in Figure 2 As shown, including:

[0118] The collection and construction module is used to obtain the cleaning time of multiple street sweepers in the service block to complete street cleaning, and to construct a driving path tree diagram of each street sweeper, wherein each driving path tree diagram of the street sweeper has multiple driving path plans; and to select any driving path plan from the different driving path plans of each street sweeper to combine and construct multiple driving path plan combinations;

[0119] An edge weight calculation module, used for calculating the edge weight of a single street sweeper from a street node to any adjacent street node by combining all driving path schemes from a street node to any adjacent street node in a service block;

[0120] A preset module is selected for selecting a first sweeper and a second sweeper from among multiple sweepers, and the first sweeper is preset to pass through a street node s to the i-th node adjacent to the street, and the second sweeper passes through the i-th node, where i is the number of street nodes adjacent to the s node;

[0121] The comprehensive coordination loss value calculation module is used to calculate the coordination loss value of the first sweeper from the s node to the i node relative to the second sweeper arriving at the i node by using the time when the first sweeper arrives at the i node and the time when the second sweeper arrives at the i node from the initial node; the coordination loss value of the first sweeper and other sweepers is obtained by analogy with this method, and the coordination loss value of the first sweeper and all sweepers is added as the comprehensive coordination loss value;

[0122] The best path determination module for the sweeper is used to obtain the reliability of the first sweeper from the s node to the i-th adjacent node by removing the comprehensive coordination loss value from the edge weight of the first sweeper from the s node to the i-th node, and to adjust and calculate the reliability of different adjacent nodes, and select the connection from the s node to the i-th node with the largest reliability as the best new path plan for the first sweeper; and the best new path plan for each sweeper is calculated in turn by analogy with this method;

[0123] The optimal path plan combination determination module is used to combine the new path plans of each sweeper to obtain the optimal path plan combination;

[0124] The controller is used to coordinate the work of the collection and construction module, the edge weight calculation module, the preset selection module, the comprehensive coordination loss value calculation module, the sweeper optimal path determination module and the optimal path plan combination determination module.

[0125] Among them, the controller includes a coordination collection construction module, an edge weight calculation module, a preset selection module, a comprehensive coordination loss value calculation module, a sweeper optimal path determination module and an optimal path solution combination determination module;

[0126] In this embodiment, the controller controls the acquisition building module to perform the following operations:

[0127] Obtain the cleaning time of multiple street sweepers in the service block to complete street sweeping, and construct a driving path tree diagram of each sweeper, wherein each driving path tree diagram has multiple driving path plans; and construct multiple driving path plan combinations by selecting any driving path plan from different driving path plans of each sweeper;

[0128] The controller calls the multiple driving path schemes constructed by the acquisition construction module to combine the control edge weight calculation module and perform the following operations:

[0129] The edge weight of a single street sweeper from a street node to any adjacent street node is obtained by calculating the combination of all driving path solutions from a street node to any adjacent street node in the service block;

[0130] The controller calls the acquisition construction module to build multiple driving path solutions and selects the preset module by combining the control. The following operations are performed:

[0131] A first sweeper and a second sweeper are selected from a plurality of sweepers, and it is preset that the first sweeper passes through a street node s to the i-th node adjacent to the street, and the second sweeper passes through the i-th node, where i is the number of street nodes adjacent to the s node;

[0132] The controller retrieves the edge weight of a single street sweeper from a street node to any adjacent street node obtained by the edge weight calculation module, retrieves the acquisition construction module to construct multiple driving path scheme combinations, and retrieves the preset information of the selection preset module to control the comprehensive coordination loss value calculation module, and performs the following operations:

[0133] The coordination loss value of the first sweeper from the s node to the i node relative to the second sweeper arriving at the i node is calculated by the time when the first sweeper arrives at the i node and the time when the second sweeper arrives at the i node from the initial node; the coordination loss value of the first sweeper and other sweepers is obtained by analogy with this method, and the comprehensive coordination loss value is obtained by adding the coordination loss values ​​of the first sweeper and all sweepers;

[0134] The controller retrieves the comprehensive coordination loss value obtained by the comprehensive coordination loss value calculation module and retrieves the preset information of the preset module to control the optimal path determination module of the sweeper, and performs the following operations:

[0135] The reliability of the first sweeper from node s to the i-th adjacent node is obtained by removing the comprehensive coordination loss value from the edge weight of the first sweeper from node s to the i-th adjacent node. The reliability of different adjacent nodes is calculated by adjustment, and the connection from node s to the i-th node with the largest reliability is selected as the best new path plan for the first sweeper. The best new path plan for each sweeper is calculated in turn by analogy with this method.

[0136] The controller calls the best new path plan of each sweeper obtained by the best path determination module of the sweeper to control the optimal path plan combination determination module, and performs the following operations:

[0137] The new path plans of each sweeper are combined to obtain the optimal path plan combination.

[0138] In summary, the present invention uses the cleaning time of multiple street sweepers to complete street sweeping in the service block to construct a dendrogram of the driving path of each street sweeper, selects any driving path plan from the different driving path plans of each street sweeper to combine, constructs multiple driving path plan combinations, traverses a part of the path plan data to obtain the plan evaluation value, calculates the edge weight of each edge of the street sweeper driving path dendrogram according to the characteristics of the traversed plan data, analyzes the vehicle coordination loss when each edge is used as a path direction edge, obtains the reliability of the direction according to the coordination loss value and the edge weight, and obtains the optimal path plan combination according to the direction reliability. In this way, a more optimal path plan can be found faster.

[0139] The present invention takes into account the problem that vehicle cleaning path planning under multi-vehicle cooperation cannot meet real-time requirements, uses the previously traversed solutions to guide the search direction of the next solution, reduces the number of path traversals, and efficiently determines the optimal solution.

[0140] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. An intelligent path optimization control method for a sweeper, It is characterized in that The following steps are involved: Obtain the cleaning time of multiple street sweepers in the service block to complete street sweeping, and construct a driving path tree diagram of each sweeper, wherein each driving path tree diagram has multiple driving path plans; select any driving path plan from different driving path plans of each sweeper to combine, and construct multiple driving path plan combinations; The edge weight of a single street sweeper from a street node to any adjacent street node is obtained by calculating the combination of all driving path solutions from a street node to any adjacent street node in the service block; Selecting a first sweeper and a second sweeper from a plurality of sweepers, presetting the first sweeper to pass through a street node s to the i-th node adjacent to the street, and the second sweeper to pass through the i-th node, where i is the number of street nodes adjacent to the s node; The coordination loss value of the first sweeper from the s node to the i node relative to the second sweeper arriving at the i node is calculated by the time when the first sweeper arrives at the i node and the time when the second sweeper arrives at the i node from the initial node; the coordination loss value of the first sweeper and other sweepers is obtained by analogy with this method, and the coordination loss value of the first sweeper and all sweepers is added as the comprehensive coordination loss value; Then, the reliability of the first sweeper from node s to the i-th adjacent node is obtained by subtracting the comprehensive coordination loss value from the edge weight of the first sweeper from node s to the i-th adjacent node. In this way, the reliability of different nodes adjacent to node s is calculated, and the connection from node s to the i-th node with the largest reliability is selected as the best new path plan for the first sweeper. By analogy, this method calculates the best new path plan for each sweeper in turn; The new path plans of each sweeper are combined to obtain the optimal path plan combination; The edge weight of a single street sweeper from a street node to any adjacent street node is obtained by following the steps below: Obtain the waste generation efficiency of each street in the service block; Analyze the path scheme combination to obtain the start cleaning time sequence of each sweeper on the same street, and obtain the garbage cleaning amount of each sweeper on the street through the start cleaning time sequence of each sweeper on the same street and the garbage generation efficiency of the street; The evaluation value of the path scheme combination on the cleaning situation of the street block is calculated by including the amount of garbage cleaned by each street sweeper on a street, the total number of streets cleaned in the service block, and the total number of vehicles passing on each street; the evaluation values ​​of multiple different driving path scheme combinations are calculated in sequence; Calculate a mean value based on the evaluation values ​​of all driving path scheme combinations from a street node to any adjacent street node, and calculate the edge weight of a single street sweeper from a street node to any adjacent street node based on the mean value; The calculation formula for the edge weight from node s to node i is as follows: In the formula, Represents the average evaluation value from the sth node to the i-th adjacent node; Represents the number of street nodes adjacent to node s; Represents the edge weight from the sth node to the i-th adjacent node; The fit loss value is obtained by following the steps below: Selecting the best route plan combination from multiple driving route plan combinations; The minimum time coordination deviation ratio of the second sweeper's arrival at the i-th node relative to the first sweeper's arrival at the i-th node from the s node to the i-th node is calculated by using the first time interval between the first sweeper and the second sweeper's arrival at the i-th node in the optimal path solution combination and the second time interval between the first sweeper's arrival at the i-th node and the second sweeper's arrival at the i-th node in any driving path solution; For the driving path plan corresponding to the minimum time coordination deviation ratio in which the second sweeper can reach the i-th node, the edge weight loss of the second sweeper starting from the initial point to reach the i-th node in the driving path plan is calculated; Thus, the coordination loss value of the first sweeper from the s node of a street to the i-th node adjacent to the next level street relative to the second sweeper reaching the i-th node is calculated through the minimum time coordination deviation ratio and the edge weight loss amount; The edge weight loss is obtained by following the steps below: Assume that the second sweeper starts from the initial point and reaches the i-th node through multiple nodes, analyze the maximum value of the edge weight in the node level where each node is located, and calculate the difference between each node and the maximum value of the node in the level as the loss value of the edge weight of the node; The loss values ​​of the edge weights from the initial point to the i-th node through multiple nodes are added together to obtain the edge weight loss of the second sweeper from the initial point to the i-th node.

2. The intelligent path optimization control method for a sweeper according to claim 1, It is characterized in that The garbage generation efficiency of each street is obtained by collecting garbage in the street garbage area, and then subtracting the garbage amount at a certain interval and dividing it by the interval time.

3. The intelligent path optimization control method for a sweeper according to claim 1, It is characterized in that If the driving path plan of the second road sweeper is different, multiple second time intervals are obtained; the minimum time matching deviation ratio is obtained by calculating the first time interval with multiple second time intervals respectively.

4. The intelligent path optimization control method for a sweeper according to claim 3, It is characterized in that The calculation formula of the minimum time matching deviation ratio is as follows: In the formula, represents the second time interval for the second sweeper to reach the i-th node in any driving path plan; represents the first time interval between the first sweeper and the second sweeper arriving at the i-th node in the optimal path solution combination; It represents the minimum time coordination deviation ratio of the second sweeper to reach the i-th node relative to the first sweeper from the s node to the i-th node.

5. The intelligent path optimization control method for a sweeper according to claim 4, It is characterized in that The path solutions with the largest evaluation values ​​are combined into the optimal path solution combination.

Citation Information

Patent Citations

  • Automatic distribution method for municipal solid waste cleaning routes

    CN112611387A

  • Evaluation method combining multi-dimensional analysis and critical path method and related device

    CN114461390A