Steel anchor box installation mechanism and installation method
By designing a steel anchor box installation mechanism with a hollow frame and positioning part, combined with BIM technology and precise positioning of a total station, the problems of complexity and low precision of traditional installation devices are solved, and efficient and accurate steel anchor box installation is achieved. Reduced production costs.
Patent Information
- Application Number
- CN202210615866.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-01
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2042-06-01
AI Technical Summary
The traditional steel anchor box installation device has a complex structure, low precision, and poor stability, resulting in low installation efficiency and high production costs.
A steel anchor box installation mechanism including a hollow frame and a positioning part is designed. BIM technology is used to establish a three-dimensional solid model, and a total station is used for precise positioning and adjustment. The hollow frame and splints are used for support and positioning, simplifying the installation process. .
The installation accuracy and efficiency of the steel anchor box are improved, ensuring that the spatial accuracy is within 5mm, simplifying the installation process and reducing production costs.
Smart Images

Figure CN115045190B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge steel structure installation, and in particular relates to a steel anchor box installation mechanism and an installation method. Background Art
[0002] Most bridges currently use arch bridges. Hangers are necessary devices to connect the arch ribs to the bridge deck. Generally, a steel-concrete bridge is used to reduce the deadweight of the structure. The bridge deck is a concrete structure, and the arch ribs are generally steel structures. The anchor box becomes an important part of the connection, which forms a steel-concrete structure between the bridge deck and the bridge deck. As an important component connected to the hanger, its installation accuracy has an important influence on the tensioning force of the hanger. However, the traditional installation device has a complex structure and outdated technology. It still uses the method of arranging a measurement network for layout, supplemented by a powder line and a plumb line. As a result, the number of machines and tools required for on-site installation of the steel anchor box is large and the accuracy is low. The installation is complex, the reinforcement stability is poor, and the overall installation efficiency is very low, which seriously affects the work progress and production costs. Summary of the invention
[0003] The present invention provides a steel anchor box installation mechanism and an installation method, which solve the technical problems that the existing steel anchor box installation mechanism is complex, has poor stability and low arrangement accuracy, resulting in high overall production cost.
[0004] In order to solve at least one of the above technical problems, the technical solution adopted by the present invention is:
[0005] A steel anchor box installation mechanism, comprising:
[0006] The support part is constructed with a hollow frame body, which can support the height of the steel anchor box based on the installation position of the steel anchor box;
[0007] The positioning part is constructed at the center of gravity of the steel anchor box;
[0008] The positioning portion can enable the steel anchor box to be suspended on the support portion and placed upright with an inclination during installation.
[0009] Furthermore, the frame structure is a hollowed-out square frame, equipped with a plurality of parallel frame rings and vertical poles connecting the corner points of the frame rings;
[0010] A support plate is also arranged in a corresponding position on the upper end of the vertical rod, and the support plate is arranged on a shorter side surface of the frame.
[0011] Furthermore, all the frame rings are arranged horizontally and adjacent frame rings are arranged at intervals.
[0012] Furthermore, the spacing height between the two frame rings placed on the uppermost layer is smaller than the spacing height between the two adjacent frame rings therebelow;
[0013] The other frame circles of the two frame circles on the uppermost layer are evenly distributed at the same height.
[0014] Furthermore, the height of the vertical pole is higher than the height of the support plate;
[0015] The number of the vertical poles is not less than the number of the corner points of the frame.
[0016] Furthermore, the support plates are all extended outwards along their length directions.
[0017] Furthermore, gaskets are provided on the lower end surfaces of all the vertical poles.
[0018] Furthermore, the positioning portion is constructed as clamping plates arranged opposite to each other, and the clamping plates are arranged along the longer width direction of the cross section of the frame body;
[0019] The clamping plates are fixedly arranged on both sides of the width of the steel frame plate of the steel anchor box and are cross-arranged with the length of the supporting plate.
[0020] Furthermore, it also includes an adjustment part arranged on the support plate near the inclined end of the steel anchor box head, and the upper end surface of the adjustment part is used to resist the ear platform in the steel anchor box, so that the contact point between the steel anchor box and the adjustment part, the center of gravity of the steel anchor box, and the contact point between the steel anchor box and the frame ring are all located on the same straight line.
[0021] A method for installing a steel anchor box, using the installation mechanism as described in any one of the above, the steps comprising:
[0022] S1. Establish a three-dimensional solid model;
[0023] Model the steel anchor box based on BIM technology to form a three-dimensional solid model;
[0024] Set the installation position of the steel anchor box based on the drawing requirements and transform the global control coordinates of all steel anchor boxes into the solid model to form local control coordinates;
[0025] Based on the data of the mileage coordinate values in the drawings, the coordinate data of the corresponding steel anchor box section is input into the physical model, and the coordinate values in the on-site surveying and mapping network are also input into the physical model to form model data under the global coordinate system;
[0026] S2, installation and positioning;
[0027] Determine the position control points of the installation mechanism and the relative position control points of the steel anchor box on the installation mechanism in the physical model;
[0028] Then, the local coordinate information of the position control points of the installation mechanism and the relative position control points of the steel anchor box on the installation mechanism is extracted and formed into a data table. The position control points of the installation mechanism and the relative position control points of the steel anchor box on the installation mechanism are lofted on the concrete bridge bottom membrane plate using a total station.
[0029] The installation mechanism is aligned and installed in place according to the released position control point, and the clamping plate in the positioning part is fixed at the height of the center of gravity of the steel anchor box and arranged along the length direction of the steel anchor box; at the same time, the position of the support plate is determined on the installation mechanism, and the clamping plate in the positioning part is perpendicular to the support plate in the support part and is arranged vertically, and the intersection point is the relative position control point of the steel anchor box and the installation mechanism;
[0030] S3. Adjust the position of the steel anchor box;
[0031] After the positioning part is adjusted into position, the steel anchor box is hoisted into the positioning part and positioned according to the relative position control points between the steel anchor box and the installation mechanism. After positioning, the center of the upper pipe mouth of the steel anchor box is selected as the fine-tuning control point, and precise adjustments are made with the aid of a total station to complete the installation of the steel anchor box.
[0032] The steel anchor box installation mechanism and installation method designed by the present invention have a simple structure and are easy to adjust. Local control and full-node placement and positioning installation can accurately adjust the positioning of the steel anchor box and fix it. At the same time, during the installation process, a batch of steel anchor boxes can be roughly installed in place, and then assisted by the overall precise adjustment of the whole station, so as to improve the installation efficiency and adjustment accuracy, and the spatial accuracy can be controlled within 5mm. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 is a three-dimensional diagram of a steel anchor box according to an embodiment of the present invention;
[0034] Figure 2 This is a diagram showing the coordination of a steel anchor box and an installation mechanism according to an embodiment of the present invention;
[0035] Figure 3 is a top view of a mounting mechanism according to an embodiment of the present invention;
[0036] Figure 4 is a side view of a support portion according to an embodiment of the present invention;
[0037] Figure 5 is a diagram showing the coordination of a positioning portion and a steel anchor box according to an embodiment of the present invention;
[0038] Figure 6 It is a schematic diagram of a three-dimensional solid model formed by modeling a steel anchor box based on BIM technology according to an embodiment of the present invention;
[0039] Figure 7It is a schematic diagram of establishing local coordinates in a three-dimensional solid model of a steel anchor box based on BIM technology according to an embodiment of the present invention;
[0040] Figure 8 It is a schematic diagram of global coordinate transformation in a three-dimensional solid model of a steel anchor box based on BIM technology according to an embodiment of the present invention.
[0041] In the figure:
[0042] 100, installation mechanism 200, steel anchor box 10, support part
[0043] 11. Frame 12. Frame 13. Vertical pole
[0044] 14. Support plate 15. Auxiliary rod 16. Gasket
[0045] 20, positioning part 21, clamping plate 30, adjustment part
[0046] 40. Center of nozzle DETAILED DESCRIPTION
[0047] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.
[0048] This embodiment provides an installation mechanism 100 for a steel anchor box 200, wherein the structure of the steel anchor box 200 is as follows: Figure 1 The structure of the steel anchor box 200 and the installation mechanism 100 is shown as Figure 2 The mounting structure 100 includes a supporting portion 10 and a positioning portion 20, wherein the supporting portion 10 is configured with a hollow frame 11, which can support the height of the steel anchor box 200 based on the installation position of the steel anchor box 200; the positioning portion 20 is configured at the center of gravity of the steel anchor box 200; the positioning portion 20 can make the steel anchor box 200 be suspended on the supporting portion 10 and placed upright in an inclined manner during installation.
[0049] Specifically, Figure 3-4 As shown, the frame 11 is constructed as a hollowed-out square frame, equipped with several layers of frame rings 12 arranged in parallel and poles 13 connecting the corners of several frame rings 12; a support plate 14 is also constructed at the upper end of the pole 13, and the support plate 14 is arranged on the shorter side of the frame 11. In order to further improve the strength of the frame 11 and simplify the structure of the support part 10, preferably, the structure of the frame 11 is a rectangular frame, that is, the frame ring 12 is also a rectangular structure, and all the poles 13 are sequentially connected to the corners of the frame ring 12. This structure is not only simple to process, but also has enough space for the steel anchor box 200 to be vertically suspended. All the frame rings 12 are arranged horizontally and adjacent frame rings 12 are arranged at intervals. The multiple layers of frame rings 12 arranged at intervals are more conducive to the oblique insertion of the steel anchor box 200.
[0050] Furthermore, the spacing height of the two frame rings 12 placed on the uppermost layer is smaller than the spacing height of the two adjacent frame rings 12 below it; that is, along the height direction of the vertical poles 13, from top to bottom, the distance between the frame rings 12 of the first layer and the frame rings 12 of the second layer is smaller than the spacing height distance between the frame rings 12 of the third layer and the fourth layer. The strength between the vertical poles 13 is weaker as one goes up, and in order to improve the strength of the surrounding of the adjacent vertical poles 13, the spacing between the frame rings 12 of the first layer and the second layer is required to be smaller, so as to improve the stability strength of the overall frame 11 to prevent its deformation, and at the same time, further improve its vertical support force.
[0051] At the same time, in order to further improve the deformation resistance of the middle and lower parts of the frame 11, it is required that the other frame rings 12 except the two frame rings 12 placed on the top layer are evenly distributed, that is, all the frame rings 12 on the third layer and below from the top are evenly distributed. In addition, along the height direction of the vertical pole 13, there is also an auxiliary rod 15 for intermediate reinforcement on the length section of the frame ring 12, and the number of the vertical pole 13 and the auxiliary rod 15 can be set based on actual working conditions.
[0052] Preferably, the height of the vertical rod 13 is higher than the position height of the support plate 14, and the number of the vertical rods 13 is not less than the number of corner points of the frame ring 12. That is, in this embodiment, the frame ring 12 is a rectangular structure with four corner points, and the number of the vertical rods 13 is greater than or equal to the number of four corner points of the frame ring 12. Of course, the frame ring 12 can also be a regular polygon structure, and accordingly, the number of the vertical rods 13 is also not less than the number of corner points of the frame ring 12.
[0053] At the same time, in order to improve the support strength of the support plate 14 in the support part 10 to the steel anchor box 200 and ensure the stability of the placement of the steel anchor box 200, the height of the support plate 14 is required to be higher than the position height of the first layer of the frame ring 12 from top to bottom along the height of the vertical pole 13, that is, the support plate 14 is located at the uppermost end of the frame body 11, which can reduce the interference when the steel anchor box 200 is installed and placed, and improve the stability and safety of the installation of the steel anchor box 200. And all the support plates 14 are extended outward along their length direction. In this embodiment, the support plate 14 is an angle steel, and its vertical surface is welded to the outer wall surface of the vertical pole 13, and its horizontal surface is set outward. The horizontally placed and relatively arranged support plates 14 are conducive to the installation of the steel anchor box 200.
[0054] Furthermore, in order to improve the stability of the frame 11 when placed upright, it is required that a horizontally arranged square-shaped gasket 16 is provided on the lower end surface of all the vertical poles, and the four gaskets 16 are provided independently of each other. Of course, in order to further improve the stability of the placement of the gasket 16, the gaskets 16 under the four vertical poles 13 can be connected to each other.
[0055] Further, such as Figure 5As shown, the positioning portion 20 is constructed as clamping plates 21 arranged opposite to each other, and the clamping plates 21 are arranged along the longer width direction of the cross section of the frame body 11, that is, arranged along the longer width direction of the frame ring 12. Preferably, the clamping plates 21 are also angle steels, and their length is greater than the width distance between the oppositely arranged support plates 14, in order to allow the steel anchor box 200 to be suspended on the frame body 11. The clamping plates 21 are fixed on both sides of the width of the steel frame plate of the steel anchor box 200 and are arranged crosswise with the length of the support plate 14. Before fixed installation, the two clamping plates 21 are first fixed oppositely in the length direction of the steel anchor box 200, and the position of the clamping plates 21 is located at the center of gravity of the steel anchor box 200 and is arranged horizontally and transversely, so that the steel frame plate of the steel anchor box 200 and the clamping plates 21 have a certain angle.
[0056] like Figure 2 As shown, the adjusting part 30 is also provided on the supporting plate 14 near the inclined end of the head of the steel anchor box 200. In this embodiment, the adjusting part 30 is a jack commonly used in engineering construction. The model or structure of the jack is not limited, as long as its height can be extended to abut against the lower end surface of the ear in the steel anchor box 200. The upper end surface of the adjusting part 30 is used to abut against the ear in the steel anchor box 200, so that the contact point where the steel anchor box 200 is connected to the upper end surface of the adjusting part 30, the center of gravity of the steel anchor box, and the contact point where the steel anchor box 200 straddles the frame ring 12 and contacts the frame ring 12 are all located on the same straight line, thereby ensuring that the steel anchor box 200 is stably and obliquely placed upright on the installation mechanism 100, thereby improving the safety and reliability of its installation.
[0057] During operation, after the steel anchor box 200 is suspended into the hollow frame surrounded by the frame body 11, the steel frame plate in the steel anchor box 200 is placed vertically after crossing one of the frame rings 12 in the middle layer, and the clamping plate 21 is placed on the support plate 14 and perpendicularly intersected with the support plate 14, that is, the center of gravity of the steel anchor box 200 is suspended at the height of the support plate 14. At the same time, in order to prevent the head of the steel anchor box 200 from tilting, an adjustment part 30 is set on the heavier side of the head of the steel anchor box 200 as a support, and the adjustment part 30 is placed on the support plate 14 to push the ear platform in the steel anchor box 200, so as to ensure that the steel anchor box 200 is stably inserted obliquely on the installation mechanism 100.
[0058] The present invention proposes a steel anchor box installation mechanism, which has a simple structure and is easy to adjust, and can accurately adjust the positioning of the steel anchor box and fix it; at the same time, during the installation process, a batch of steel anchor boxes can be roughly installed in place, and then assisted by precise adjustment, so as to improve the installation efficiency and adjustment accuracy, and the spatial accuracy can be controlled within 5mm.
[0059] A method for installing a steel anchor box, using the installation mechanism 100 as described in any one of the above, comprises the following steps:
[0060] S1. Establish a three-dimensional solid model.
[0061] First, the steel anchor box 200 is modeled according to the engineering design drawings and based on BIM technology to form a three-dimensional solid model. The final solid model is as follows: Figure 6 In the modeling process, it is required that the installation positions of all steel anchor boxes 200 are relatively and spaced according to the requirements of the design drawings. Accordingly, each installation mechanism 100 is matched with a steel anchor box 200, and the installation position of the steel anchor box 200 is also the position where the installation structure 100 is placed.
[0062] Then, the installation position of the steel anchor box 200 is set based on the requirements of the engineering design drawings and the global control coordinates of all the steel anchor boxes 200 are converted into the solid model to form local control coordinates. Figure 7 shown.
[0063] Based on the data of the mileage coordinate values in the engineering design drawings, the coordinate data of each section of the corresponding steel anchor box 200 is input into the physical model, and the coordinate values in the on-site surveying and mapping network are also input into the physical model to form the model data under the global coordinate system, such as Figure 8 shown.
[0064] Based on the above data, the local coordinates are transformed in the solid model, that is, the origin of the local coordinates is moved to the center line of the beam and the center of the bridge section, so that the control points are completely symmetrical and the layout direction is consistent with the direction of the bridge, which is convenient for quickly releasing the control points.
[0065] S2. Installation and positioning.
[0066] The position control points of the installation mechanism 100 and the relative position control points of the steel anchor box 200 on the installation mechanism 100 are determined in the physical model.
[0067] The local coordinate information of the position control points of the installation mechanism 100 and the relative position control points of the steel anchor box 200 on the installation mechanism 100 is then extracted and formed into a data table. The position control points of the installation mechanism 100 and the relative position control points of the steel anchor box 200 on the installation mechanism 100 are laid out on the concrete bridge bottom membrane plate using a total station.
[0068] The installation mechanism 100 is aligned and installed in place according to the released position control point, and the clamping plate 21 in the positioning part 20 is fixed at the height of the center of gravity of the steel anchor box 200 and arranged along the length direction of the steel anchor box 200; at the same time, the position of the support plate 14 is determined on the installation mechanism 100, and the clamping plate 21 in the positioning part 20 is perpendicular to the support plate 14 in the support part 10 and is arranged vertically, and the intersection point is the relative position control point of the steel anchor box 200 and the installation mechanism 100. The structure is as follows: Figure 2As shown, to ensure that the position of the steel anchor box 200 in the horizontal plane is accurately controlled.
[0069] S3. Adjust the position of the steel anchor box 200.
[0070] After the positioning part 20 is adjusted into position, the steel anchor box is hoisted into the positioning part 20 and positioned according to the relative position control points of the steel anchor box 200 and the installation mechanism 100. After positioning, the upper pipe mouth center 40 of the steel anchor box 200 is selected as the fine adjustment control point, and the adjustment part 30 is set at the inclined end close to the pipe mouth center 40 to top the head of the steel anchor box 200, and the adjustment part 30 is placed on the support plate 14, and then accurately adjusted with the aid of a total station to complete the installation of the steel anchor box 200.
[0071] The present invention proposes an installation method for a steel anchor box 200 using the above-mentioned installation mechanism 100, which is to establish a physical model of the steel anchor box 200 through BIM technology, accurately simulate the installation position, convert the global control coordinates into the model through BIM technology, form local control coordinates, use a total station to lay out the control points, and use the installation positioning measures tooling, and after the installation is completed, use the total station to make precise adjustments. Finally, the steel anchor box is accurately positioned and reinforced. At the same time, the layout control points can also be accurately arranged. During the installation process, a batch of steel anchor boxes 200 can be roughly installed in place, and then the total station can be used to make precise adjustments as a whole, which improves the efficiency and accuracy of the installation, and the spatial accuracy can be controlled within 5mm.
[0072] The steel anchor box installation mechanism and installation method designed by the present invention have a simple structure and are easy to adjust. Local control and full-node placement and positioning installation can accurately adjust the positioning of the steel anchor box and fix it. At the same time, during the installation process, a batch of steel anchor boxes can be roughly installed in place, and then assisted by the overall precise adjustment of the whole station, so as to improve the installation efficiency and adjustment accuracy, and the spatial accuracy can be controlled within 5mm.
[0073] The above embodiments of the present invention are described in detail, and the contents are only preferred embodiments of the present invention, and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made according to the scope of application of the present invention should still fall within the scope of the patent coverage of the present invention.
Claims
1. A steel anchor box installation mechanism, It is characterized in that Contains: The support part is constructed with a hollow frame body, which can support the height of the steel anchor box based on the installation position of the steel anchor box; The positioning part is constructed at the center of gravity of the steel anchor box; The positioning part can make the steel anchor box be suspended on the support part and placed upright in an inclined manner during installation; The frame structure is a hollowed-out square frame, equipped with a plurality of parallel frame rings and vertical poles connecting the corner points of the frame rings; A support plate is also arranged at the upper end of the vertical rod, and the support plate is arranged on a shorter side of the frame; The positioning portion is constructed as clamping plates arranged opposite to each other, and the clamping plates are arranged along the longer width direction of the cross section of the frame body; The clamping plates are fixed on both sides of the width of the steel frame plate of the steel anchor box and are arranged crosswise with the length of the support plate; It also includes an adjustment part arranged on the support plate near the inclined end of the steel anchor box head, and the upper end surface of the adjustment part is used to resist the ear platform in the steel anchor box, so that the contact point between the steel anchor box and the adjustment part, the center of gravity of the steel anchor box, and the contact point between the steel anchor box and the frame ring are all located on the same straight line.
2. A steel anchor box installation mechanism according to claim 1, It is characterized in that All the frame rings are arranged horizontally and adjacent frame rings are arranged at intervals.
3. A steel anchor box installation mechanism according to claim 1 or 2, It is characterized in that The spacing height between the two frame rings placed on the uppermost layer is smaller than the spacing height between the two adjacent frame rings below the two frame rings; The other frame circles of the two frame circles on the uppermost layer are evenly distributed at the same height.
4. A steel anchor box installation mechanism according to claim 3, It is characterized in that The height of the vertical pole is higher than the height of the support plate; The number of the vertical poles is not less than the number of the corner points of the frame.
5. A steel anchor box installation mechanism according to any one of claims 1-2 and 4, It is characterized in that The support plates are all extended outwards along their length directions.
6. A steel anchor box installation mechanism according to claim 3, It is characterized in that Gaskets are arranged on the lower end surfaces of all the vertical poles.
7. A method for installing a steel anchor box. It is characterized in that Using the installation mechanism according to any one of claims 1 to 6, the steps include: S1. Establish a three-dimensional solid model; Model the steel anchor box based on BIM technology to form a three-dimensional solid model; Set the installation position of the steel anchor box based on the drawing requirements and transform the global control coordinates of all steel anchor boxes into the solid model to form local control coordinates; Based on the data of the mileage coordinate values in the drawings, the coordinate data of the corresponding steel anchor box section is input into the physical model, and the coordinate values in the on-site surveying and mapping network are also input into the physical model to form model data under the global coordinate system; S2, installation and positioning; Determine the position control points of the installation mechanism and the relative position control points of the steel anchor box on the installation mechanism in the physical model; Then, the local coordinate information of the position control points of the installation mechanism and the relative position control points of the steel anchor box on the installation mechanism is extracted and formed into a data table. The position control points of the installation mechanism and the relative position control points of the steel anchor box on the installation mechanism are lofted on the concrete bridge bottom membrane plate using a total station. The installation mechanism is aligned and installed in place according to the released position control point, and the clamping plate in the positioning part is fixed at the height of the center of gravity of the steel anchor box and arranged along the length direction of the steel anchor box; at the same time, the position of the support plate is determined on the installation mechanism, and the clamping plate in the positioning part is perpendicular to the support plate in the support part and is arranged vertically, and the intersection point is the relative position control point of the steel anchor box and the installation mechanism; S3. Adjust the position of the steel anchor box; After the positioning part is adjusted into position, the steel anchor box is hoisted into the positioning part and positioned according to the relative position control points between the steel anchor box and the installation mechanism. After positioning, the center of the upper pipe mouth of the steel anchor box is selected as the fine-tuning control point, and precise adjustments are made with the aid of a total station to complete the installation of the steel anchor box.