Method and system for synthesizing ammonia by producing hydrogen from electricity

By using the control center to adjust the operating modes of the electrolytic water hydrogen production station and the ammonia synthesis station in the electric hydrogen production and ammonia synthesis system, it adapts to the fluctuations of wind power and photovoltaic power, solves the problem of high production costs caused by power fluctuations, and achieves a more stable and stable Economical ammonia production.

CN115117936BActive Publication Date: 2024-10-22SICHUAN ENERGY INTERNET RES INST TSINGHUA UNIV +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210897476.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-07-28
Publication Date
2024-10-22
Estimated Expiration
2042-07-28

AI Technical Summary

Technical Problem

In the existing wind power and photovoltaic coupling ammonia synthesis process, due to the volatility of wind power or photovoltaic power, the power grid needs to provide additional power to ensure the stability of the production process, resulting in high production costs.

Method used

Design an electric hydrogen production and ammonia synthesis system that communicates with the power grid dispatching center, electrolysis water hydrogen production station and synthetic ammonia station through the control center, determines the power control target value and adjustment time according to the power grid dispatching instructions, and adjusts the electrolysis water hydrogen production station and synthetic ammonia station. operating mode to adapt to fluctuations in wind power and photovoltaic power.

Benefits of technology

It effectively overcomes the impact of wind power and photovoltaic power fluctuations on the production process, reduces dependence on grid power, and reduces production costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115117936B_ABST
    Figure CN115117936B_ABST
Patent Text Reader

Abstract

The electric hydrogen production and ammonia synthesis method and system provided in the embodiment of the present invention relate to the field of clean energy smelting technology. First, the control center receives the dispatch instruction sent by the power grid dispatch center; then, the control center determines the power control target value and power adjustment time of the electric hydrogen production and ammonia synthesis system based on the dispatch instruction; then, the control center determines the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and sends the target power consumption to the water electrolysis hydrogen production station, so that the water electrolysis hydrogen production station produces hydrogen based on the target power consumption; at the same time, the control center determines the target adjustment mode of the working condition of the ammonia synthesis station according to the power adjustment time, and sends the target adjustment mode to the ammonia synthesis station, so that the ammonia synthesis station synthesizes liquid ammonia based on the target adjustment mode, so as to overcome the influence of the fluctuating power provided by new energy sources such as wind power and photovoltaic power on the stability of the production process, reduce the use of power from the power grid, and reduce production costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of clean energy smelting, and in particular to a method and system for synthesizing ammonia by producing hydrogen from electricity. Background Art

[0002] The traditional ammonia synthesis process mainly obtains raw materials by using fossil energy to produce hydrogen and air separation to produce nitrogen, and synthesizes ammonia under the action of catalysts in the synthesis tower. However, chemical plants that use fossil energy such as coal and natural gas as raw materials will emit a large amount of carbon dioxide during the hydrogen production process, exacerbating the greenhouse effect. In order to reduce carbon dioxide emissions and alleviate global warming and other negative impacts, renewable energy such as wind power and photovoltaics can be used to electrolyze water to produce hydrogen to reduce the use of fossil energy.

[0003] In the existing wind power and photovoltaic coupled ammonia synthesis process technology, wind power or photovoltaics are only mechanically introduced into the production process. Due to the volatility of the electricity provided by wind power or photovoltaics, in order to ensure the stability of the production process, the power grid must provide electricity for balance, or large-scale energy storage equipment must be configured for power balance, resulting in high production costs. Summary of the invention

[0004] In order to overcome the shortcomings of the prior art, the embodiments of the present invention provide a method and system for synthesizing ammonia by producing hydrogen from electricity, which can overcome the impact of fluctuating electricity provided by new energy sources such as wind power and photovoltaics on the stability of the production process, reduce the use of grid electricity, and reduce production costs.

[0005] The technical solution of the embodiment of the present invention can be implemented as follows:

[0006] In a first aspect, an embodiment of the present invention provides a method for synthesizing ammonia from hydrogen by electricity, which is applied to a system for synthesizing ammonia from hydrogen by electricity. The system for synthesizing ammonia from hydrogen by electricity includes a control center, a water electrolysis hydrogen production station, and a synthetic ammonia station. The control center communicates with the water electrolysis hydrogen production station and the synthetic ammonia station, respectively. The hydrogen produced by the water electrolysis hydrogen production station is transmitted to the synthetic ammonia station through a pipeline. The control center also communicates with a power grid dispatching center. The method includes:

[0007] The control center receives the dispatching instruction sent by the power grid dispatching center;

[0008] The control center determines the power control target value and power adjustment time of the electric hydrogen production and ammonia synthesis system based on the dispatch instruction, wherein the electric hydrogen production and ammonia synthesis system satisfies the preset operating conditions when operating according to the power control target value, and the power adjustment time represents the time taken for the electric hydrogen production and ammonia synthesis system to adjust from the current power consumption to the power control target value;

[0009] The control center determines the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and sends the target power consumption to the water electrolysis hydrogen production station, so that the water electrolysis hydrogen production station produces hydrogen based on the target power consumption;

[0010] The control center determines a target adjustment mode of the operating conditions of the synthetic ammonia station according to the power adjustment time, and sends the target adjustment mode to the synthetic ammonia station, so that the synthetic ammonia station synthesizes liquid ammonia based on the target adjustment mode.

[0011] Optionally, the electric hydrogen production and ammonia synthesis system further includes a wind power station and a photovoltaic power station, and the wind power station and the photovoltaic power station both provide electricity to the water electrolysis hydrogen production station and the ammonia synthesis station through transmission lines, and the control center also communicates with the wind power station and the photovoltaic power station respectively;

[0012] The step of determining, by the control center based on the dispatch instruction, a power control target value and a power adjustment time of the electric hydrogen production and ammonia synthesis system comprises:

[0013] The control center obtains wind speed data of the area where the wind power station is located and solar irradiance data of the area where the photovoltaic power station is located;

[0014] The control center inputs the wind speed data and the solar irradiance data into a pre-established system simulation model, and determines the power control target value and the power adjustment time according to the model output result.

[0015] Optionally, the electric hydrogen production and ammonia synthesis system further includes a wind power station and a photovoltaic power station, and the wind power station and the photovoltaic power station both provide electricity to the water electrolysis hydrogen production station and the ammonia synthesis station through a transmission line, and the control center communicates with both the wind power station and the photovoltaic power station;

[0016] The step of the control center determining the target power consumption of the water electrolysis hydrogen production station according to the power control target value comprises:

[0017] The control center obtains the current power generation of the wind power station, the current power generation of the photovoltaic power station, the current power consumption of the synthetic ammonia station, the current power abandonment of the wind power station and the current power abandonment of the photovoltaic power station;

[0018] The control center determines the target power consumption of the water electrolysis hydrogen production station based on the current power generation power of the wind power station, the current power generation power of the photovoltaic power station, the current power consumption of the synthetic ammonia station, the current abandoned power of the wind power station, the current abandoned power of the photovoltaic power station and the power control target value.

[0019] Optionally, the water electrolysis hydrogen production station includes an in-station controller and a plurality of rectifiers, the in-station controller controls the operation of the plurality of rectifiers, and the in-station controller communicates with the control center;

[0020] After the control center sends the target power to the water electrolysis hydrogen production station, the method further includes:

[0021] The station controller compares the target power consumption with a preset maximum power and a preset minimum power;

[0022] If the station controller determines that the target power consumption is greater than the preset minimum power and the target power consumption is less than the preset maximum power, the operating power of each rectifier is determined according to the target power consumption;

[0023] If the station controller determines that the target power consumption is not greater than the preset minimum power, the operating power of each rectifier is determined according to the preset minimum power;

[0024] If the station controller determines that the target power consumption is not less than the preset maximum power, the operating power of each rectifier is determined according to the preset maximum power.

[0025] Optionally, the water electrolysis hydrogen production station further includes a gas-liquid separator and a plurality of electrolyzers, one of the electrolyzers is electrically connected to one of the rectifiers, the gas-liquid mixture produced by each electrolyzer is transmitted to the gas-liquid separator through a pipeline, and the cooling water device in the gas-liquid separator cools down the alkali liquid in the gas-liquid mixture. The method further includes:

[0026] The station controller obtains the alkali solution temperature at the inlet and outlet of the plurality of electrolytic cells;

[0027] If the station controller determines that the alkali solution temperature at the inlet of the multiple electrolytic cells and / or the alkali solution temperature at the outlet of the multiple electrolytic cells deviates from the preset temperature range, then the operating parameters of the multiple electrolytic cells and the cooling water temperature at the inlet and outlet of the cooling water device are obtained;

[0028] The station controller determines the cooling water demand of the cooling water device according to the alkali solution temperature at the inlet and outlet of the multiple electrolytic cells, the operating parameters of the multiple electrolytic cells and the cooling water temperature at the inlet and outlet of the cooling water device;

[0029] The station controller adjusts the valve at the inlet of the cooling water device according to the cooling water demand so that the alkali solution temperature at the inlet of the multiple electrolytic cells and / or the alkali solution temperature at the outlet of the multiple electrolytic cells is within a preset temperature range.

[0030] Optionally, the method further comprises:

[0031] The station controller obtains the concentration of the alkali solution in the multiple electrolytic cells and the liquid level of the alkali solution in the gas-liquid separator;

[0032] If the station controller determines that the concentration of the alkali solution is higher than the preset concentration, and / or the liquid level of the alkali solution is lower than the preset liquid level, the demand for raw water in the electrolysis water hydrogen production station is determined according to the target power consumption of the electrolysis water hydrogen production station;

[0033] The station controller adjusts the valves at the inlets of the multiple electrolytic cells according to the demand for the raw water to reduce the concentration of the alkali solution and / or increase the liquid level of the alkali solution.

[0034] Optionally, the synthetic ammonia station includes a gas storage tank and a synthesis tower, the hydrogen produced by the water electrolysis hydrogen production station is transmitted to the gas storage tank through a pipeline, and the hydrogen in the gas storage tank is transmitted to the synthesis tower through a pipeline, and the control center determines the target adjustment mode of the operating condition of the synthetic ammonia station according to the power adjustment time. The step includes:

[0035] The control center obtains the hydrogen intake, hydrogen release and hydrogen storage of the gas storage tank;

[0036] The control center determines the buffer time of the gas storage tank according to the hydrogen intake, hydrogen release and hydrogen storage, wherein the buffer time represents the time required for the gas storage tank to be fully filled with hydrogen;

[0037] If the control center determines that the power adjustment time is not greater than the buffer time, the target adjustment mode is determined to be a first adjustment mode, and the first adjustment mode is used to adjust the operation of the gas storage tank;

[0038] If the control center determines that the power adjustment time is greater than the buffer time, the target adjustment mode is determined to be the second adjustment mode, and the second adjustment mode is used to adjust the operation of the synthesis tower.

[0039] Optionally, the target adjustment mode includes a first adjustment mode and a second adjustment mode, the synthetic ammonia station includes a gas storage tank, a synthesis tower and an in-station controller, the in-station controller communicates with the control center, and the in-station controller controls the operation of the gas storage tank and the synthesis tower;

[0040] After the step of the control center sending the target adjustment mode to the synthetic ammonia plant, the method further includes:

[0041] If the target regulation mode received by the station controller is the first regulation mode, the pressure control valve on the inlet pipe of the gas storage tank and / or the pressure control valve on the outlet pipe of the gas storage tank are adjusted according to the hydrogen consumption in the synthesis tower and the hydrogen intake of the gas storage tank;

[0042] If the target regulation mode received by the in-station controller is the second regulation mode, the gas pressure in the synthesis tower is regulated according to the change in the amount of hydrogen entering the gas storage tank.

[0043] Optionally, the step of adjusting the gas pressure in the synthesis tower by the station controller according to the amount of hydrogen entering the gas storage tank comprises:

[0044] If the station controller determines that the change value of the hydrogen inlet amount is positive, the gas pressure in the synthesis tower is increased;

[0045] If the station controller determines that the change value of the hydrogen inlet amount is negative, the gas pressure in the synthesis tower is reduced;

[0046] In a second aspect, an embodiment of the present invention provides an electric hydrogen production and ammonia synthesis system, comprising a control center, a water electrolysis hydrogen production station and an ammonia synthesis station, wherein the control center communicates with the water electrolysis hydrogen production station and the ammonia synthesis station respectively, the hydrogen produced by the water electrolysis hydrogen production station is transmitted to the ammonia synthesis station through a pipeline, and the control center also communicates with a power grid dispatching center;

[0047] The control center is used to:

[0048] Receiving a dispatching instruction sent by the power grid dispatching center;

[0049] Based on the scheduling instruction, determining a power control target value and a power adjustment time of the electric hydrogen production and ammonia synthesis system, wherein the electric hydrogen production and ammonia synthesis system meets a preset operating condition when operating according to the power control target value;

[0050] Determining the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and sending the target power consumption to the water electrolysis hydrogen production station;

[0051] determining a target adjustment mode of the operating conditions of the synthetic ammonia station according to the power adjustment time, and sending the target adjustment mode to the synthetic ammonia station;

[0052] The water electrolysis hydrogen production station is used to receive the target power consumption sent by the control center and produce hydrogen based on the target power consumption;

[0053] The synthetic ammonia station is used to receive the target regulation mode sent by the control center and synthesize liquid ammonia based on the target regulation mode.

[0054] Compared with the prior art, the electric hydrogen production and ammonia synthesis method and system provided in the embodiment of the present invention firstly comprises the following steps: the control center receives a dispatch instruction sent by a power grid dispatch center; then, the control center determines a power control target value and a power adjustment time of the electric hydrogen production and ammonia synthesis system based on the dispatch instruction, wherein the electric hydrogen production and ammonia synthesis system satisfies preset operating conditions when operating according to the power control target value, and the power adjustment time represents the time taken for the electric hydrogen production and ammonia synthesis system to adjust from the current power consumption to the power control target value; then, the control center determines the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and sends the target power consumption to the water electrolysis hydrogen production station, so that the water electrolysis hydrogen production station produces hydrogen based on the target power consumption; at the same time, the control center determines the target adjustment mode of the operating condition of the ammonia synthesis station according to the power adjustment time, and sends the target adjustment mode to the ammonia synthesis station, so that the ammonia synthesis station synthesizes liquid ammonia based on the target adjustment mode. In the embodiment of the present invention, the control center determines the power control target value and power adjustment time of the electric hydrogen production and ammonia synthesis system based on the dispatch instruction issued by the power grid dispatch center, determines the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and determines the target adjustment mode of the operating conditions of the ammonia synthesis station according to the power adjustment time, thereby adjusting the operation of the water electrolysis hydrogen production station and the ammonia synthesis station to overcome the impact of fluctuating electricity provided by new energy sources such as wind power and photovoltaics on the stability of the production process, reduce the use of grid electricity, and reduce production costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0055] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0056] Figure 1 A schematic block diagram of the structure of a system for synthesizing ammonia from hydrogen produced by electricity provided in an embodiment of the present invention;

[0057] Figure 2 A process flow chart of a system for synthesizing ammonia from hydrogen by electricity provided in an embodiment of the present invention;

[0058] Figure 3 A schematic diagram of a process for synthesizing ammonia by producing hydrogen from electricity provided in an embodiment of the present invention Figure 1 ;

[0059] Figure 4 A flowchart of an implementation method of step S102 provided in an embodiment of the present invention;

[0060] Figure 5A flowchart of an implementation method of step S103 provided in an embodiment of the present invention;

[0061] Figure 6 A schematic diagram of a process for synthesizing ammonia by producing hydrogen from electricity provided in an embodiment of the present invention Figure 2 ;

[0062] Figure 7 A flowchart of an implementation method of step S104 provided in an embodiment of the present invention;

[0063] Figure 8 A schematic diagram of a process for synthesizing ammonia by producing hydrogen from electricity provided in an embodiment of the present invention Figure 3 .

[0064] Icons: 100-electric hydrogen production and ammonia synthesis system; 110-control center; 120-wind power station; 130-photovoltaic power station; 140-water electrolysis hydrogen production station; 150-air separation station; 160-synthetic ammonia station; 170-auxiliary equipment; DETAILED DESCRIPTION

[0065] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0066] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0067] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0068] In addition, the terms “first”, “second”, etc., if used, are merely used to distinguish between the descriptions and should not be understood as indicating or implying relative importance.

[0069] It should be noted that, in the absence of conflict, the features in the embodiments of the present invention may be combined with each other.

[0070] The traditional ammonia synthesis process mainly obtains raw materials through hydrogen production from fossil energy and nitrogen production from air separation, and then synthesizes ammonia under the action of catalysts in the synthesis tower. However, chemical plants that use petrochemical media such as coal and natural gas as raw materials emit a large amount of carbon dioxide during production operations, exacerbating the greenhouse effect.

[0071] In order to reduce carbon dioxide emissions during the production process and alleviate global warming and other negative impacts, renewable and clean energy such as wind energy, solar energy, hydropower and geothermal energy can be introduced into the process of synthetic ammonia.

[0072] The existing wind power and photovoltaic coupled ammonia synthesis process technology usually only uses wind power or photovoltaic to provide electricity, which has limited power supply time and high hydrogen production cost. In addition, wind power or photovoltaic is only mechanically introduced in the process of electric hydrogen production and ammonia synthesis. There are fluctuations in wind power or photovoltaic power supply. In order to ensure the safety and stability of the production process, it is necessary to access the power grid to provide electricity, or configure large-scale lithium battery energy storage, compressed air energy storage and pumped water energy storage and other energy storage equipment for power balance, resulting in high equipment costs;

[0073] In view of this, an embodiment of the present invention provides a method for synthesizing ammonia by producing hydrogen from electricity, so as to overcome the influence of fluctuating electricity provided by new energy sources such as wind power and photovoltaic power on the stability of the production process, reduce the use of grid electricity, and reduce production costs, which will be introduced in detail below.

[0074] The embodiment of the present invention first introduces a system 100 for synthesizing ammonia through hydrogen production from electricity, which is the execution body of the method for synthesizing ammonia through hydrogen production from electricity provided by the embodiment of the present invention.

[0075] Please refer to Figure 1 The electric hydrogen production and ammonia synthesis system 100 includes a control center 110, a wind power station 120, a photovoltaic power station 130, a water electrolysis hydrogen production station 140, an air separation station 150, a synthetic ammonia station 160 and auxiliary equipment 170, wherein the control center 110 can communicate with the wind power station 120, the photovoltaic power station 130, the water electrolysis hydrogen production station 140, the air separation station 150, the synthetic ammonia station 160 and the auxiliary equipment 170, and can monitor the system operation status and issue control instructions. In addition, the control center can also communicate with the power grid dispatching center, receive the dispatching instructions issued by the power grid center, and participate in the safe and economic operation service of the power grid.

[0076] The electric hydrogen production and ammonia synthesis system 100 also includes a power booster station, a transmission line and a user-side substation. If the wind power station 120 and the photovoltaic power station 130 are co-located, they can be connected to the same power booster station. If the wind power station 120 and the photovoltaic power station 130 are not co-located, each is connected to a power booster station. The power booster station is connected to the user-side substation through a transmission line. After the user-side substation reduces the pressure, it is connected to the water electrolysis hydrogen production station 140, the air separation station 150, the ammonia synthesis station 160 and the auxiliary equipment 170. The user-side substation can also be connected to the power grid.

[0077] like Figure 2 As shown, the wind power station 120 includes wind turbines, wind power converters (AC / DC / AC), combiner boxes and other equipment.

[0078] The photovoltaic power station 130 includes equipment such as a photovoltaic array, a combiner box, and a photovoltaic inverter (DC / AC).

[0079] The water electrolysis hydrogen production station 140 includes a rectifier (AC / DC), an electrolyzer, a gas-liquid separation device, a gas purification device and a gas storage tank, wherein the gas-liquid separation device includes a hydrogen / alkaline liquid separator and an oxygen / alkaline liquid separator, the gas purification equipment includes a hydrogen purification device and an oxygen purification device, and the gas storage tank includes a hydrogen storage tank and an oxygen storage tank.

[0080] The air separation station includes equipment such as air separation devices and gas storage tanks.

[0081] The synthetic ammonia station 160 includes hydrogen and nitrogen compressors, hydrogen and nitrogen storage tanks, circulating gas compressors, inlet and outlet tower heat exchangers, a synthetic tower, waste heat recovery devices, water coolers, cold exchangers, ammonia cooling compressors, ammonia cooling devices, ammonia separators, liquid ammonia discharge tanks and liquid ammonia storage tanks and other equipment.

[0082] The process flow of the electric hydrogen production and ammonia synthesis system 100 is as follows:

[0083] The wind power station 120 and the photovoltaic power station 130 generate electricity, which is transmitted to the user-side substation of the industrial park through the transmission line. The user-side substation then supplies power to the water electrolysis hydrogen production station 140, the air separation station 150, the synthetic ammonia station 160 and the auxiliary equipment 170.

[0084] When the sum of the power generated by the wind power station 120 and the photovoltaic power station 130 is greater than the total power load of the production process, the excess power generation will be connected to the power grid through the user-side substation and absorbed by the power grid; when the sum of the power generated by the wind power station 120 and the photovoltaic power station 130 is less than the total power load of the production process, electricity is purchased from the power grid to meet the gap between the power generation of the wind power station 120 and the photovoltaic power station 130 and the total power load of the production process, thereby ensuring the reliability of electricity consumption in the production process; when the sum of the power generated by the wind power station 120 and the photovoltaic power station 130 is equal to the total power load of the production process, no electricity is exchanged between the electric hydrogen production and ammonia synthesis system 100 and the power grid.

[0085] The water electrolysis hydrogen production station 140 uses an electrolyzer to decompose water to produce hydrogen and oxygen, wherein the hydrogen / alkaline solution mixture passes through a hydrogen / alkaline solution separator, the separated hydrogen enters a hydrogen purification device, and the purified hydrogen enters a hydrogen storage tank; the oxygen / alkaline solution mixture passes through an oxygen / alkaline solution separator, the separated oxygen enters an oxygen purification device, and the purified oxygen enters an oxygen storage tank.

[0086] The alkali separated from the hydrogen / alkali separator and the oxygen / alkali separator flows back into the electrolyzer. The raw water is connected to the pipeline in front of the alkali inlet of the electrolyzer. There are heat exchangers in the hydrogen / alkali separator and the oxygen / alkali separator, and the cooling water cools the alkali through the heat exchangers.

[0087] The air separation station 150 produces liquid nitrogen and liquid oxygen by controlling the separation device. The liquid oxygen enters the oxygen pipeline after being vaporized, and the liquid nitrogen enters the nitrogen storage tank after being vaporized.

[0088] The hydrogen produced by the water electrolysis hydrogen production station 140 is mixed with the nitrogen produced by the air separation station 150 in the hydrogen and nitrogen storage tank, and the obtained fresh hydrogen and nitrogen (also known as supplementary gas) enters the hydrogen and nitrogen compressor, and the gas pressure is compressed to 13.1MPa (A), and then enters the filter to filter out the oil that may be carried in the compressor; then, it is mixed with the incoming circulating gas and enters the circulating gas combined compressor, and the gas pressure is compressed to 13.827MPa (A), and then sent to the inlet and outlet tower heat exchanger for preheating; the preheated gas enters the synthesis tower through the gas main line, and passes through the heat exchanger between the upper and middle catalyst layers of the synthesis tower to heat the gas to about 330°C, and is mixed at the entrance of the upper catalyst layer at the top of the synthesis tower, and then enters the upper radial catalyst layer, and under the action of the catalyst, it reacts violently to generate ammonia and releases a large amount of reaction heat.

[0089] In order to make the components in the gas tend to equilibrium quickly, the reaction heat released by the synthesis reaction is taken out by the reaction gas. The reaction gas leaves the upper radial layer, enters the upper heat exchanger and the cold exchanger in the tube, and enters the middle radial catalyst layer to react after being cooled to about 355°C; after leaving the middle radial catalyst layer, the reaction gas enters the interlayer heat exchanger and the cold exchanger in the tube, and enters the lower radial catalyst layer after being cooled to about 355°C. The obtained reaction gas has an ammonia concentration of about 19.4%.

[0090] The reaction gas leaves the synthesis tower at about 400°C, becomes synthesis gas, and enters the steam superheater and synthesis waste heat boiler in the waste heat recovery device. When it is cooled to 210°C, it enters the inlet gas heat exchanger to heat the inlet cold air.

[0091] The syngas enters the water cooler at about 80°C, where the cold brought by the air and evaporated desalted water cools the syngas to 38°C. The cooled syngas enters the cold exchanger to exchange heat with the cold circulating gas from the liquid ammonia separator to recover cold energy.

[0092] After being cooled to 28°C, the syngas enters the 1# ammonia cooler, where the liquid ammonia evaporates outside the tube and cools the syngas to 8°C. The gas then enters the 2# ammonia cooler, where the liquid ammonia evaporates outside the tube and cools the syngas to 0°C. During these cooling processes, a large amount of gaseous ammonia in the syngas is condensed into liquid ammonia. The syngas containing a large amount of liquid ammonia enters the liquid ammonia separator to separate the liquid ammonia.

[0093] The gas coming out of the cold side of the cold exchanger enters the circulating gas compressor for recycling. The liquid ammonia separated by the liquid ammonia separator is decompressed and sent to the liquid ammonia discharge tank to discharge the gas dissolved in the liquid ammonia. The liquid ammonia at the outlet of the discharge tank is heat-exchanged with the liquid ammonia from the refrigeration process to 30°C and then sent to the liquid ammonia storage tank. The gas discharged from the discharge tank is sent to the inlet of the hydrogen and nitrogen compressor for comprehensive utilization.

[0094] Please refer to Figure 3 A method for synthesizing ammonia by producing hydrogen from electricity provided in an embodiment of the present invention includes steps S101 to S104.

[0095] S101, the control center 110 receives a dispatching instruction sent by a power grid dispatching center.

[0096] The power grid not only provides additional power when the sum of the power generated by the wind power station 120 and the photovoltaic power station 130 is less than the total power load of the production process, but also absorbs the excess power generation when the sum of the power generated by the wind power station 120 and the photovoltaic power station 130 is greater than the total power load of the production process. The power grid dispatching center sends a dispatching instruction to the control center 110, so that the control center 110 determines whether the power grid needs to absorb the excess power generation.

[0097] S102, the control center 110 determines the power control target value and power adjustment time of the electric hydrogen production and ammonia synthesis system 100 based on the scheduling instruction.

[0098] The electric hydrogen production and ammonia synthesis system 100 meets the preset operating conditions when operating according to the power control target value, and the power adjustment time represents the time taken for the electric hydrogen production and ammonia synthesis system 100 to adjust the current power consumption to the power control target value.

[0099] The preset operating conditions refer to the optimal economic performance of the hydrogen-to-ammonia synthesis system 100. It can be understood that the power control target value is the optimal power consumption of the hydrogen-to-ammonia synthesis system 100 at the current moment obtained by the control center 110 through a simulation experiment aimed at optimizing the economic performance of the hydrogen-to-ammonia synthesis system 100.

[0100] S103, the control center determines the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and sends the target power consumption to the water electrolysis hydrogen production station, so that the water electrolysis hydrogen production station produces hydrogen based on the target power consumption.

[0101] Among them, in the electric hydrogen production and ammonia synthesis system 100, the power consumption of the water electrolysis hydrogen production station 140 can be quickly adjusted, while the ammonia synthesis station 160 is subject to the safety and economy of the chemical process and does not have the ability to quickly adjust the power consumption. Therefore, the power consumption adjustment of the electric hydrogen production and ammonia synthesis system 100 is mainly achieved by adjusting the power consumption of the water electrolysis hydrogen production station 140.

[0102] The control center 110 determines the target power consumption of the water electrolysis hydrogen production station 140 based on the power control target value and the power consumption of other equipment in the system. The water electrolysis hydrogen production station 140 operates according to the target power consumption. When producing hydrogen, the economy of the entire electric hydrogen production and ammonia synthesis system 100 reaches the optimal level.

[0103] S104, the control center determines the target adjustment mode of the operating conditions of the synthetic ammonia station according to the power adjustment time, and sends the target adjustment mode to the synthetic ammonia station, so that the synthetic ammonia station synthesizes liquid ammonia based on the target adjustment mode.

[0104] Among them, since the hydrogen production of the electrolytic water hydrogen production station 140 changes during the process of adjusting the current power consumption to the target power consumption, the synthetic ammonia station 160 needs to change its own working conditions in order to adapt to the change in hydrogen production. The chemical process of the synthetic ammonia station 160 is subject to the safety and economic constraints of the pressure, temperature, flow, refrigeration and other processes, so the change of its working conditions requires a series of equipment to be operated synchronously.

[0105] The target adjustment mode may indicate the equipment and adjustment method to be adjusted for the operation status in the synthetic ammonia plant 160. The control center 110 may determine the target adjustment mode for the operation status of the synthetic ammonia plant according to the power adjustment time.

[0106] The following is a detailed description of step S102.

[0107] Please refer to Figure 4 , step S102 includes sub-steps S102-1 and S102-2.

[0108] S102 - 1 , the control center 110 obtains wind speed data of the area where the wind power station 120 is located and solar irradiance data of the area where the photovoltaic power station 130 is located.

[0109] S102-2, the control center 110 inputs the wind speed data and the solar irradiance data into a pre-established system simulation model, and determines the power control target value and the power adjustment time according to the model output results.

[0110] The system simulation model includes the system equipment model and the system economic analysis model. The system equipment model is based on Figure 2 The process flow shown in the figure is established, including: wind power station and photovoltaic power station models, power exchange model between the electric hydrogen production and ammonia synthesis system and the power grid, water electrolysis hydrogen production station model, raw gas storage tank model, air separation station and ammonia synthesis station model.

[0111] (1) Wind power station and photovoltaic power station model

[0112] For the wind power station 120 and the photovoltaic power station 130 that have been put into operation, their historical hourly power generation data are used. As the power generation data, The power generated by the wind power station for 8760 hours a year, in kW; The power generated by the photovoltaic power station for 8760 hours a year, in kW; For a period of one year.

[0113] For the planned wind power station 120 and photovoltaic power station 130, the wind speed data of the area where the wind power station 120 is located is used to calculate the power generation of the wind power station 120, and the solar irradiance data of the area where the photovoltaic power station 130 is located is used to calculate the power generation of the photovoltaic power station 130.

[0114] The formula for calculating the power generation of the wind power station 120 based on the wind speed data is as follows:

[0115]

[0116]

[0117]

[0118] Among them, η w To consider the efficiency such as wake effect, fan loss, etc.; N w is the number of wind turbines; P w (v) is the power generation capacity of a single wind turbine, in kW; v, v ci 、v r 、v co They are regional wind speed, wind turbine cut-in wind speed, wind turbine rated design wind speed, and wind turbine cut-out wind speed, all in m / s; P wr is the rated power of the wind turbine, in kW; ρ is the air density, in kg / m 3 ; A w is the swept area, unit: m 2 ; C p is the wind energy conversion efficiency value.

[0119] The formula for calculating the power generation of the photovoltaic power station 130 based on the solar irradiance data is as follows:

[0120]

[0121] Where t0 is the temperature of the photovoltaic panel at time t, in °C; I t0 is the solar radiation intensity in the area where the photovoltaic array is located, in W / m 2 ; η s (t0,I to ) is the temperature of the photovoltaic array at t0 and I t0 Power generation efficiency under solar radiation intensity conditions; A s is the area of ​​the photovoltaic array, in m 2 .

[0122] (2) Power exchange model between the hydrogen production and ammonia synthesis system and the power grid

[0123] When the sum of the power generated by the wind power station 120 and the photovoltaic power station 130 in the electric hydrogen production and ammonia synthesis system 100 is greater than the total power load of the production process, the excess power generation will be connected to the power grid through the user-side substation and consumed by the power grid. This state can be called online; when the sum of the power generated by the wind power station 120 and the photovoltaic power station 130 in the electric hydrogen production and ammonia synthesis system 100 is less than the total power load of the production process, electricity is purchased from the power grid to meet the gap between the power generation of the wind power station 120 and the photovoltaic power station 130 and the total power load of the production process. This state can be called offline. The above two states cannot coexist at the same time.

[0124]

[0125]

[0126] in, For Internet access power, is the off-grid electricity, is a binary variable, and when its value is 0, it represents that the power is from the power grid to the electric hydrogen production and ammonia synthesis system 100, and when its value is 1, it represents that the power is from the electric hydrogen production and ammonia synthesis system 100 to the power grid. M1 is a sufficiently large positive number.

[0127] The power exchange between the electric hydrogen production and ammonia synthesis system 100 and the power grid is divided into two forms: one is the sales of power from the wind power station 120 and the photovoltaic power station 130 to the grid, and the other is the purchase of power from the power grid by the electric hydrogen production and ammonia synthesis system 100. Considering the limited ability of the power grid to absorb the power generated by the electric hydrogen production and ammonia synthesis system 100, the net power grid is proposed to constrain it.

[0128] The net on-grid electricity represents the difference between the on-grid electricity and the off-grid electricity of the hydrogen production and ammonia synthesis system 100 in a certain period of time. The proportion limit of the on-grid electricity of the hydrogen production and ammonia synthesis system 100 to the annual power generation, the proportion limit of the electricity purchased from the grid by the hydrogen production and ammonia synthesis system 100 to the annual total power generation, and the proportion limit of the net on-grid electricity of the hydrogen production and ammonia synthesis system 100 to the annual power generation are determined according to the grid absorption capacity.

[0129]

[0130]

[0131]

[0132]

[0133] Among them, r1, r2, and r3 are respectively the proportion limit of the on-grid electricity of the electric hydrogen production and ammonia synthesis system 100 to the annual power generation, the proportion limit of the electricity purchased from the power grid by the electric hydrogen production and ammonia synthesis system 100 to the annual total power generation, and the proportion limit of the net on-grid electricity of the electric hydrogen production and ammonia synthesis system 100 to the annual power generation; E RG It is the sum of the annual total power generation of the wind power station 120 and the photovoltaic power station 130 in the electric hydrogen production and ammonia synthesis system 100, in kWh.

[0134] (3) Water electrolysis hydrogen production station model

[0135] The electrolysis water hydrogen production station 140 is used to convert electricity into hydrogen and oxygen. The electrolysis water hydrogen production station 140 uses a porous diaphragm to allow the gas on the hydrogen side electrode and the oxygen side electrode in the electrolyzer to diffuse. Under normal operating conditions, the electrolysis water hydrogen production station 140 has a fast lye flow rate, and the proportion of gas passing through the diaphragm is small. However, when the electrolysis water hydrogen production station 140 is running at low load, the proportion of gas passing through the diaphragm increases, resulting in a high content of oxygen impurities in hydrogen and a high content of hydrogen impurities in oxygen, which affects the operating safety and gas purity of the electrolysis water hydrogen production station 140.

[0136] Therefore, there is a minimum operating power and a maximum operating power when the water electrolysis hydrogen production station 140 is operating normally. The power speed of the water electrolysis hydrogen production station 140 is relatively fast when in operation, and its power conversion rate is greater than 20% of the rated load / s.

[0137] The water electrolysis hydrogen production station 140 adjusts the power consumption to adapt to the power generation changes of the wind power station 120 and the photovoltaic power station 130, thereby optimizing the power exchange between the electric hydrogen production and ammonia synthesis system 100 and the power grid.

[0138]

[0139]

[0140]

[0141]

[0142] in, is the power of the water electrolysis hydrogen production station 140, in kW; κ H2 is the energy efficiency constant of the water electrolysis hydrogen production station 140, which depends on the energy conversion efficiency η H2 and low heating value LHV of hydrogen H2 , energy conversion efficiency η H2 Typically 5kWh / Nm3; C AE is the capacity of the electric hydrogen production equipment, in kW; η AE,min , η AE,max N is the minimum operating power ratio and the maximum operating power ratio of the electric hydrogen production equipment; AE is the number of electrolytic cells; is the capacity of a single electrolytic cell in kW.

[0143] (4) Raw gas storage tank model

[0144] In the electric hydrogen production and ammonia synthesis system 100, hydrogen and nitrogen are buffered by gas storage tanks. When the power generation of the wind power station 120 and the photovoltaic power station 130d is large and the power consumption of the power grid is limited, the operating power of the water electrolysis hydrogen production station 140 is increased, the hydrogen production load is increased, and the excess hydrogen is stored in the gas storage tank. At the same time, the operating power of the air separation station 150 is increased, nitrogen is produced under the condition of nitrogen: hydrogen of 3:1, and the excess nitrogen is stored in the gas storage tank. A gas storage tank is also configured in the ammonia synthesis station 160 for storing synthesis gas. Since the scale of the air separation station 150 is large, the output of nitrogen can be quickly adjusted by configuring a gasification device. Therefore, the buffering effect of the gas storage tank in the water electrolysis hydrogen production station 140 on synthesis gas is mainly considered in the embodiment of the present invention.

[0145]

[0146]

[0147]

[0148] Among them, C HS is the hydrogen storage capacity in the gas tank, in Nm 3 ; is the hydrogen storage capacity in the gas tank at time t, in Nm 3 ; Respectively, they are the storage of oxygen and nitrogen in the gas tank, in Nm 3 ; The amount of hydrogen produced by the water electrolysis hydrogen production station 140 entering the gas storage tank, in Nm 3 ; The amount of hydrogen released from the gas tank and entering the ammonia synthesis station 160, in Nm 3 ; η HS,min , η HS,max It is the minimum and maximum ratio of hydrogen stored in the gas tank.

[0149] It should be noted that all products such as hydrogen, nitrogen, and oxygen in the electric hydrogen production and ammonia synthesis system 100 must be consumed.

[0150] (5) Air separation station and ammonia synthesis station model

[0151] The synthetic ammonia station 160 mainly uses hydrogen and nitrogen to synthesize liquid ammonia, and the technology adopts Haber-Bosch synthesis technology. Hydrogen comes from the electrolysis water hydrogen production station 140, and nitrogen comes from the air separation station 150. The main power-consuming equipment in the process flow of the synthetic ammonia station 160 is power equipment such as compressors and pumps. The operating conditions of the synthetic ammonia station 160 are constrained by chemical safety and economy. The synthetic ammonia station 160 adjusts its operating conditions to adapt to the fluctuations of hydrogen produced by the electrolysis water hydrogen production station 140 and oxygen produced by the air separation station 150.

[0152]

[0153]

[0154]

[0155] Among them, κ N2 , κ NH3 The power consumption for producing unit volume of nitrogen and liquid ammonia, in kW / Nm 3 ; They are respectively the nitrogen consumption and liquid ammonia production at time t, in Nm 3 ; They are the power consumption for producing nitrogen and the power consumption for producing liquid ammonia at time t respectively.

[0156]

[0157] in, is the total power consumption of the air separation station 150 and the synthetic ammonia station 160 at time t, in kW; κ AS,NH3 The power consumption per unit volume of hydrogen, in kW / Nm 3 ; It is the hydrogen consumption at time t, in Nm3.

[0158] At rated power, the rated production rate of hydrogen is defined as the rated production rate of liquid ammonia of the synthetic ammonia station 160

[0159] The operating adjustment mode of the synthetic ammonia station 160 is as follows:

[0160]

[0161]

[0162]

[0163] in, is the operating condition of the k-th synthetic ammonia station 160; ΔT AS is the operating condition adjustment cycle, in h; the operating condition of the synthetic ammonia station 160 is affected by the catalyst performance (pressure and temperature range), and there are minimum safe operating conditions and maximum safe operating conditions. η AS,min , η AS,max are the minimum safe operating condition ratio and the maximum safe operating condition ratio of the synthetic ammonia station 160. The operating condition switching rate of the synthetic ammonia station is limited by the process flow, and the ratio of the maximum adjustment rate to the rated production rate is 20% / h.

[0164] The relationship for adjusting the operating conditions of the synthetic ammonia station 160 is as follows:

[0165]

[0166] Among them, T tran It is the switching period of the operating conditions of the synthetic ammonia station, and its value is 4h.

[0167] The constraints of the system equipment model are as follows:

[0168]

[0169]

[0170] Among them, C H2mA is the conversion rate of hydrogen to synthetic ammonia, and its value is 5.060*10 -4 ton / Nm 3 .

[0171] On the basis of the above system equipment model, a system economic analysis model is established with the goal of maximizing system economic efficiency.

[0172] The yield of the electric hydrogen production and ammonia synthesis system 100 is divided into two types: one is selling electricity to the power grid, and the other is selling synthetic ammonia. All hydrogen in the system is converted into synthetic ammonia and none of it is sold to the outside.

[0173] It can be understood that the income of the electric hydrogen production and ammonia synthesis system 100 is divided into the income from electricity sales and the income from synthetic ammonia sales. The system economic analysis model is established with the goal of maximizing the system economic efficiency as follows:

[0174] J PtA =J PtA,Profit -J PtA,Invest

[0175]

[0176]

[0177]

[0178]

[0179]

[0180]

[0181] Among them, J PtA is the profit of the electric hydrogen production and ammonia synthesis system 100, unit: RMB; J PtA,Profit is the income of the electric hydrogen production and ammonia synthesis system 100, in Yuan; J PtA,Investis the cost of the electric hydrogen production and ammonia synthesis system 100, in Yuan; is the on-grid electricity price, in RMB / kWh; is the liquid ammonia selling price, in yuan / ton; CRF(r,Y) is the capital recovery factor, r is the loan interest rate, and Y is the facility operation cycle; They are respectively the initial investment, operation and maintenance costs, staff wages and welfare costs, consumables costs, and land rent of the electric hydrogen production and ammonia synthesis system 100, in Yuan; They are the initial investments of wind power station 120, photovoltaic power station 130, transmission line, water electrolysis hydrogen production station 140, raw gas storage tank, air separation station 150 and synthetic ammonia station 160, in Yuan; They are the operation and maintenance costs of the wind power station 120, photovoltaic power station 130, transmission lines, water electrolysis hydrogen production station 140, raw gas storage tanks, air separation station 150 and synthetic ammonia station 160, in Yuan; They are respectively the cost of purchasing electricity from the power grid, the cost of purchasing industrial water, the cost of purchasing chemical catalysts, and the cost of purchasing equipment parts, all in RMB.

[0182] Optionally, the cost of purchasing electricity from the grid The calculation formula is as follows:

[0183]

[0184] in, It is the electricity purchase price from the power grid, in Yuan / kWh.

[0185] Electricity-generated hydrogen-to-ammonia system 100 engineering profit J PtA With maximization as the goal, the operations of the wind power station 120, the photovoltaic power station 130, the transmission lines, the water electrolysis hydrogen production station 140, the raw gas storage tanks, the air separation station 150 and the synthetic ammonia station 160 are optimized to improve the overall economy and system operation flexibility of the electric hydrogen production and synthetic ammonia system 100.

[0186] The following is a detailed description of step S103.

[0187] Please refer to Figure 5 , step S103 includes sub-steps S103-1 and S103-2.

[0188] S103 - 1 , the control center 110 obtains the current power generation of the wind power station 120 , the current power generation of the photovoltaic power station 130 , the current power consumption of the synthetic ammonia station 160 , the current power abandonment of the wind power station 120 , and the current power abandonment of the photovoltaic power station 130 .

[0189] S103-2, the control center 110 determines the target power consumption of the water electrolysis hydrogen production station 140 based on the current power generation power of the wind power station 120, the current power generation power of the photovoltaic power station 130, the current power consumption of the synthetic ammonia station 160, the current abandoned power of the wind power station 120, the current abandoned power of the photovoltaic power station 130 and the power control target value.

[0190] Among them, the current power generation power of the wind power station 120, the current power generation power of the photovoltaic power station 130, the current power consumption of the synthetic ammonia station 160, the current abandoned power of the wind power station 120, the current abandoned power of the photovoltaic power station 130 and the target power consumption of the water electrolysis hydrogen production station 140, and the power control target value satisfy the following formula:

[0191]

[0192] Among them, C W , C S are the complete machine capacities of the wind power station 120 and the photovoltaic power station 130, in kW; is the power generation of the wind power station 120 and the photovoltaic power station 130 at time t; is the target power consumption of the water electrolysis hydrogen production station 140 at time t, in kW; is the power consumption of the synthetic ammonia station 160 at time t, in kW; It is the sum of the abandoned power of the wind power station 120 and the photovoltaic power station 130, in kW.

[0193] The following will introduce the process of adjusting the electric power of the water electrolysis hydrogen production station 140 based on the power control target value.

[0194] exist Figure 3 Based on Figure 6 After the control center sends the target power to the water electrolysis hydrogen production station, the method for synthesizing ammonia by hydrogen production provided by the embodiment of the present invention further includes steps S201 to S204.

[0195] S201: The station controller compares the target power consumption with a preset maximum power and a preset minimum power.

[0196] Among them, the water electrolysis hydrogen production station 140 also includes Figure 2 The station controller in the station controller can be understood that the communication between the water electrolysis hydrogen production station 140 and the control center 110 is essentially the communication between the station controller and the control center 110. The station controller can control and adjust the operation of other equipment in the water electrolysis hydrogen production station 140.

[0197] Since the power consumption of the water electrolysis hydrogen production station 140 can only be within [ηAE,min *C AE , η AE,max *C AE ] within the power range (η AE,min *C AE is the preset maximum power, η AE,max *C AE Therefore, the station controller needs to compare the target power consumption with the preset maximum power and the preset minimum power.

[0198] S202: If the station controller determines that the target power consumption is greater than the preset minimum power and the target power consumption is less than the preset maximum power, the operating power of each rectifier is determined according to the target power consumption.

[0199] Among them, at time t The value of [η AE,min *C AE , η AE,max *C AE ] range, the station controller will The value is evenly distributed to n AC / DC rectifiers, and the power value of each rectifier is

[0200] S203: If the station controller determines that the target power consumption is not greater than the preset minimum power, the operating power of each rectifier is determined according to the preset minimum power.

[0201] Among them, at time t The value is less than or equal to η AE,min *C AE When AE,min *C AE Evenly distributed to n AC / DC rectifiers, the power value of each rectifier is

[0202] S204: If the station controller determines that the target power consumption is not less than the preset maximum power, the operating power of each rectifier is determined according to the preset maximum power.

[0203] Among them, at time t The value is greater than or equal to η AE,max *C AE When AE,max *C AE The value is evenly distributed to n AC / DC rectifiers, and the power value of each rectifier is

[0204] Since each AC / DC rectifier is connected to an electrolyzer, when the operating power of each AC / DC rectifier changes, the operating status of each electrolyzer also changes. The station controller needs to monitor the operating status of all electrolyzers.

[0205] Therefore, please refer again to Figure 6 After step S202, S203 or S204, the method for synthesizing ammonia by producing hydrogen from electricity provided in an embodiment of the present invention further includes steps S205 to S208.

[0206] S205, the station controller obtains the alkali solution temperature at the inlet and outlet of the multiple electrolytic cells.

[0207] S206, if the station controller determines that the alkali solution temperature at the inlet of the multiple electrolytic cells and / or the alkali solution temperature at the outlet of the multiple electrolytic cells deviates from the preset temperature range, the operating parameters of the multiple electrolytic cells and the cooling water temperature at the inlet and outlet of the cooling water device are obtained.

[0208] S207, the station controller determines the cooling water demand of the cooling water device according to the alkali solution temperature at the inlet and outlet of the multiple electrolytic cells, the operating parameters of the multiple electrolytic cells and the cooling water temperature at the inlet and outlet of the cooling water device.

[0209] S208, the station controller adjusts the valve at the inlet of the cooling water device according to the cooling water demand, so that the alkali solution temperature at the inlet of the multiple electrolytic cells and / or the alkali solution temperature at the outlet of the multiple electrolytic cells is within a preset temperature range.

[0210] Among them, the preset temperature range corresponding to the alkali solution temperature at the inlet of multiple electrolytic cells can be 60℃~70℃, the preset temperature range corresponding to the alkali solution temperature at the outlet of multiple electrolytic cells can be 80℃~90℃, and the operating parameters of multiple electrolytic cells include electrolytic cell voltage, electrolytic cell current and alkali solution concentration.

[0211] The station controller uses the following formula to calculate the cooling water demand of the cooling water device.

[0212]

[0213]

[0214]

[0215] ΔT lye =T lye,out -T lye,in

[0216] ΔT water,cool =T water,cool out -T water,cool in

[0217] Among them, P water,cool is the cooling water demand, in m 3 / s;Q g is the heat output of the electrolytic cell, in kJ; Q s,loss is the heat dissipation of the electrolytic cell and pipeline, in kJ; C lye , C water are the heat capacity of alkali solution and cooling water, respectively, in J / K; P flow is the mass flow rate of alkali solution, in kg / s; U stack (t) ,I stack (t) are the DC voltage of the electrolytic cell at time t and the current passing through the electrolytic cell, in V and A respectively; U th For an electrolytic cell at a temperature of T stack The thermal neutral voltage at the time, unit V; T stac,k , T amb is the temperature of the electrolytic cell and pipeline and the ambient temperature, in K; R stack is the thermal resistance from the electrolytic cell and pipeline to the air, in K / W; T lye,out , T lye,in , T water,cool out , T water,cool in They are respectively the alkali solution temperature at the outlet of the electrolytic cell, the alkali solution temperature at the inlet of the electrolytic cell, the cooling water temperature at the outlet of the cooling water device in the gas-liquid separator, and the cooling water temperature at the inlet, and the unit is K.

[0218] Since changes in the concentration and amount of the alkali solution in the water electrolysis hydrogen production station 140 will affect the normal operation of the water electrolysis hydrogen production station 140, the station controller also needs to monitor the concentration and amount of the alkali solution.

[0219] Therefore, please refer again to Figure 6 After step S208, the method for synthesizing ammonia by producing hydrogen from electricity provided in the embodiment of the present invention further includes steps S209 to S211.

[0220] S209, the station controller obtains the concentration of the alkali solution in the multiple electrolytic cells and the liquid level of the alkali solution in the gas-liquid separator.

[0221] S210, if the station controller determines that the concentration of the alkali solution is higher than the preset concentration and / or the liquid level of the alkali solution is lower than the preset liquid level, the demand for raw water in the electrolysis water hydrogen production station is determined according to the target power consumption of the electrolysis water hydrogen production station.

[0222] S211, the station controller adjusts the valves at the inlets of the multiple electrolytic cells according to the demand for raw water to reduce the concentration of the alkali solution and / or increase the liquid level of the alkali solution.

[0223] The station controller uses the following formula to calculate the demand for raw water in the water electrolysis hydrogen production station 140.

[0224]

[0225]

[0226] in, qwater,raw is the raw water consumption in the water electrolysis hydrogen production station 140, in kg; q water,loss is the loss of hydrogen carried out in the gas-liquid separator, in kg; θ water The water content in each standard cubic meter of hydrogen, in kg / Nm 3 .

[0227] It should be noted that the station controller also needs to monitor the gas impurity content at the outlet of the gas-liquid separator and the gas impurity content at the outlet of the gas purification equipment, so that the hydrogen produced by the water electrolysis hydrogen production station 140 meets the requirements.

[0228] When the gas impurity content at the outlet of the gas-liquid separator is higher than the set value, the operating conditions of the gas-liquid separator are optimized to improve the gas-liquid separation capacity. At the same time, the alkali solution flow rate at the inlet of the electrolyzer is reduced to prevent the gas that has not been completely separated in the alkali solution from being brought into the electrolyzer, resulting in a decrease in the efficiency of hydrogen production and an increase in the impurity content at the outlet of the gas-liquid separator.

[0229] Optionally, for a cyclone-type gas-liquid separator, the rotation speed of the rotating parts inside the equipment can be increased to thereby improve its gas-liquid separation capability; for a gravity-type sedimentation gas-liquid separator, the alkali solution flow rate at the inlet of the electrolytic cell is reduced to increase the residence time of the alkali solution in the gas-liquid separator and reduce the presence of gas in the alkali solution.

[0230] At the same time, when the station controller detects that the impurity content of the gas at the outlet of the gas purification equipment exceeds the set value, the operating power of the gas purification equipment is increased to ensure that the purified gas meets the purity requirements of downstream chemical production.

[0231] The station controller of the water electrolysis hydrogen production station 140 also needs to monitor the outlet pressure of the hydrogen side and the outlet pressure of the oxygen side of the gas-liquid separator in real time, and control the outlet valves or valve groups on both sides to avoid pressure difference between the hydrogen side and the oxygen side, thereby ensuring pressure balance in the gas-liquid separator.

[0232]

[0233] in, They are respectively the hydrogen side outlet pressure and the oxygen side outlet pressure of the gas-liquid separator in the water electrolysis hydrogen production station 140, in Pa.

[0234] The following is a detailed description of step S104.

[0235] Please refer to Figure 7 , step S104 includes steps S104-1 to S104-4.

[0236] S104-1, the control center 110 obtains the amount of hydrogen entering, the amount of hydrogen released, and the amount of hydrogen stored in the gas storage tank.

[0237] The synthetic ammonia station 150 also includes Figure 2 As for the in-station controller, it can be understood that the communication between the synthetic ammonia station 150 and the control center 110 is essentially the communication between the in-station controller and the control center 110. The in-station controller can control and adjust the operation of other equipment in the synthetic ammonia station 150.

[0238] The control center 110 communicates with the in-station controller of the synthetic ammonia station 150 to obtain the amount of hydrogen entering, the amount of hydrogen released, and the amount of hydrogen stored in the gas tank in the synthetic ammonia station 150 .

[0239] S104-2 The control center 110 determines the buffer time of the gas storage tank according to the amount of hydrogen entering, the amount of hydrogen released and the amount of hydrogen stored.

[0240] The buffer time represents the time required for the gas storage tank to be fully filled with hydrogen. The control center 110 uses the following formula to determine the buffer time.

[0241]

[0242]

[0243] Among them, T buffer C is the buffer time; HS is the hydrogen storage capacity in the gas tank, in Nm 3 ; is the amount of hydrogen stored in the gas tank at time t, in Nm 3 ; The amount of hydrogen produced by the water electrolysis hydrogen production station 140 entering the gas storage tank, that is, the amount of hydrogen entering, in Nm 3 ; The amount of hydrogen released from the gas tank into the synthetic ammonia station 160, i.e., the amount of hydrogen released, in Nm 3 ; η HS,min , η HS,max It is the minimum and maximum ratio of hydrogen stored in the gas tank.

[0244] S104-3: If the control center determines that the power adjustment time is not greater than the buffer time, the target adjustment mode is determined to be the first adjustment mode.

[0245] The first adjustment mode is used to adjust the operation of the gas tank. When the power adjustment time is less than or equal to T buffer This means that the storage and release of the gas storage tank can be used to buffer the fluctuation of the hydrogen production of the electrolytic water hydrogen production station 140. At this time, the rate of the chemical reaction in the synthesis tower in the synthetic ammonia station 160 remains unchanged.

[0246] S104-4: If the control center determines that the power adjustment time is greater than the buffer time, the target adjustment mode is determined to be the second adjustment mode.

[0247] The second adjustment mode is used to adjust the operation of the synthesis tower. buffer When the storage and release of the gas storage tank is insufficient to buffer the fluctuation of the hydrogen production of the electrolytic water hydrogen production station 140, the rate of the chemical reaction in the synthesis tower of the synthetic ammonia station 160 needs to be changed.

[0248] The following will introduce the process of adjusting the operating conditions of the synthetic ammonia station 160 based on the target adjustment mode.

[0249] exist Figure 3 Based on Figure 8 After the control center sends the target adjustment mode to the synthetic ammonia station, the method for synthesizing ammonia by hydrogen production provided by the embodiment of the present invention further includes steps S301 to S302.

[0250] S301, if the target regulation mode received by the station controller is the first regulation mode, the pressure control valve on the inlet pipe of the gas storage tank and / or the pressure control valve on the outlet pipe of the gas storage tank are adjusted according to the hydrogen consumption in the synthesis tower and the hydrogen intake of the gas storage tank.

[0251] When the amount of hydrogen entering the gas tank is greater than the amount of hydrogen consumed in the synthesis tower, it means that the hydrogen production of the water electrolysis hydrogen production station 140 increases, and it can be concluded that the current power consumption of the water electrolysis hydrogen production station 140 is less than the target power consumption. At this time, the pressure control valve on the inlet pipe of the gas tank is opened, and the excess hydrogen and nitrogen are stored in the gas tank through the pressure control valve according to the composition requirement of 3:1.

[0252] When the amount of hydrogen entering the gas tank is less than the amount of hydrogen consumed in the synthesis tower, it means that the hydrogen production of the water electrolysis hydrogen production station 140 is reduced, and it can be concluded that the current power consumption of the water electrolysis hydrogen production station 140 is greater than the target power consumption. At this time, the pressure control valve on the outlet pipe of the gas tank is opened to add hydrogen and nitrogen in the gas tank to the synthesis tower for chemical reaction, so as to keep the rate of the chemical reaction in the synthesis tower unchanged.

[0253] It is understandable that when the above two situations occur, the total power generation of the wind power station 120 and the photovoltaic power station 130 may be greater than the power control target value of the hydrogen-to-ammonia synthesis system, or may be less than the power control target value of the hydrogen-to-ammonia synthesis system.

[0254] S302: If the target regulation mode received by the station controller is the second regulation mode, the gas pressure in the synthesis tower is regulated according to the change in the amount of hydrogen entering the gas storage tank.

[0255] In the case where the storage and release of the gas tank is not sufficient to buffer the fluctuation of the hydrogen production of the electrolytic water hydrogen production station 140, the embodiment of the present invention also introduces a safety time that characterizes the duration of continuous operation of the synthetic ammonia station 160 under the minimum safe operating condition and the maximum safe operating condition. The size of the safety time is affected by factors such as the catalyst type in the synthesis tower, the control accuracy of the synthetic ammonia pressure, and the control accuracy of the synthesis temperature.

[0256] When the power adjustment time is greater than the buffer time and less than the safety time, the fluctuation of the hydrogen production of the water electrolysis hydrogen production station 140 can be dealt with by adjusting the reaction rate in the synthesis tower.

[0257] Optionally, the implementation process of step S302 is as follows:

[0258] In case one, if the station controller determines that the change in the amount of hydrogen entering is positive, the gas pressure in the synthesis tower is increased.

[0259] Among them, since the performance of the catalyst in the synthesis tower is affected by the gas pressure in the synthesis tower, the greater the gas pressure, the more active the catalyst is, thereby increasing the rate of the chemical reaction.

[0260] When the change value of the hydrogen intake is positive, it means that the hydrogen production of the water electrolysis hydrogen production station 140 is constantly increasing. Since the storage and release of the gas tank are not sufficient to buffer the fluctuation of the hydrogen production of the water electrolysis hydrogen production station 140, at this time, the station controller can increase the gas pressure of the hydrogen and nitrogen entering the synthesis tower by controlling the circulating compressor to speed up the rate of the chemical reaction in the synthesis tower.

[0261] In the second case, if the station controller determines that the change in the amount of hydrogen entering is negative, the gas pressure in the synthesis tower is reduced.

[0262] Among them, when the change value of the hydrogen intake is negative, it means that the hydrogen production of the water electrolysis hydrogen production station 140 is constantly decreasing. Since the storage and release of the gas tank are not sufficient to buffer the fluctuation of the hydrogen production of the water electrolysis hydrogen production station 140, at this time, the station controller can reduce the gas pressure of the hydrogen and nitrogen entering the synthesis tower by controlling the circulating compressor to slow down the rate of the chemical reaction in the synthesis tower.

[0263] It should be noted that the performance of the catalyst in the synthesis tower is also affected by the gas temperature in the synthesis tower. The higher the gas temperature, the more active the catalyst is, thereby increasing the rate of the chemical reaction.

[0264] The station controller can monitor the gas pressure and temperature in the synthesis tower and adjust the operating conditions of the waste heat recovery device and the heat exchangers in and out of the tower according to the following formula to avoid drastic changes in the gas pressure and temperature in the synthesis tower.

[0265]

[0266] Among them, K Θ The reaction in the synthesis tower is T AS The reaction equilibrium constant is related to the reaction temperature T AS Related functions; They are respectively the ammonia pressure, nitrogen pressure and hydrogen pressure in the synthesis tower at time t, in Pa.

[0267]

[0268] The intrinsic reaction kinetic equation of the ammonia synthesis reaction according to the ammonia synthesis reaction process is as follows:

[0269]

[0270] Among them, r NH3 is the production rate of ammonia; k1 and k2 are the reaction rate constants of the forward and reverse reactions respectively; α and β are constants measured in the laboratory respectively.

[0271] When the power adjustment time is greater than the safety time, it means that the power control target value analyzed by the control center 110 has exceeded the adjustment range of the electric hydrogen production and ammonia synthesis system 100. Under the condition of normal, safe and economical operation of the power grid, the probability of this situation occurring is small. For such a small probability event, the solution provided by the embodiment of the present invention is as follows:

[0272] When a power grid failure occurs, making it difficult to connect to the grid or the grid-connected power is severely limited, and the power generated by the wind power station 120 and the photovoltaic power station 130 is greater than the maximum safe operating load of the hydrogen-to-ammonia synthesis system 100, the hydrogen-to-ammonia synthesis system 100 operates at the maximum allowable load. At the same time, the operating power of the wind power station 120 and the photovoltaic power station 130 is determined based on the loads of the wind power station 120, the photovoltaic power station 130, the water electrolysis hydrogen production station 140 and the ammonia synthesis station 160, as well as the power constraints of the grid connection point, so as to discard excess generated power.

[0273] When a power grid failure occurs, it is difficult to connect to the grid or the grid power is severely limited, and the power generation of the wind power station 120 and the photovoltaic power station 130 is less than the minimum safe operating load of the hydrogen-to-ammonia synthesis system 100, the hydrogen-to-ammonia synthesis system 100 enters a safe shutdown operation process. Accordingly, the wind power station 120 and the photovoltaic power station 130 determine the power generation and abandoned power according to the grid connection point constraints, and in extreme cases, they can completely stop power generation.

[0274] When the power grid resumes normal operation and the wind power station 120 and the photovoltaic power station 130 resume normal operation, and the control center 110 of the hydrogen production and ammonia synthesis system 100 analyzes relevant data to determine that the hydrogen production and ammonia synthesis system 100 meets the startup requirements, the hydrogen production and ammonia synthesis system 100 starts according to the instructions of the control center 110 and enters the cold start mode.

[0275] Furthermore, when the electric hydrogen production and ammonia synthesis system 100 executes the above method provided by the embodiment of the present invention, the control center 110 is used to receive a dispatch instruction sent by the power grid dispatch center; based on the dispatch instruction, determine the power control target value and power adjustment time of the electric hydrogen production and ammonia synthesis system, wherein the electric hydrogen production and ammonia synthesis system meets the preset operating conditions when operating according to the power control target value; determine the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and send the target power consumption to the water electrolysis hydrogen production station; determine the target adjustment mode of the operating condition of the ammonia synthesis station according to the power adjustment time, and send the target adjustment mode to the ammonia synthesis station.

[0276] The water electrolysis hydrogen production station 140 is used to receive the target power consumption sent by the control center and produce hydrogen based on the target power consumption.

[0277] The synthetic ammonia station 140 is used to receive the target regulation mode sent by the control center and synthesize liquid ammonia based on the target regulation mode.

[0278] In one possible implementation, the control center 110 can be used to obtain wind speed data in the area where the wind power station is located and solar irradiance data in the area where the photovoltaic power station is located; input the wind speed data and solar irradiance data into a pre-established system simulation model, and determine the power control target value and power adjustment time according to the model output results.

[0279] In one possible implementation, the control center 110 can also be used to obtain the current power generation of the wind power station, the current power generation of the photovoltaic power station, the current power consumption of the synthetic ammonia station, the current power abandonment of the wind power station, and the current power abandonment of the photovoltaic power station; determine the target power consumption of the water electrolysis hydrogen production station based on the current power generation of the wind power station, the current power generation of the photovoltaic power station, the current power consumption of the synthetic ammonia station, the current power abandonment of the wind power station, the current power abandonment of the photovoltaic power station, and the power control target value.

[0280] In one possible implementation, the in-station controller in the water electrolysis hydrogen production station 140 is used to compare the target power consumption with the preset maximum power and the preset minimum power; if it is determined that the target power consumption is greater than the preset minimum power and the target power consumption is less than the preset maximum power, the operating power of each rectifier is determined according to the target power consumption; if it is determined that the target power consumption is not greater than the preset minimum power, the operating power of each rectifier is determined according to the preset minimum power; if it is determined that the target power consumption is not less than the preset maximum power, the operating power of each rectifier is determined according to the preset maximum power.

[0281] In one possible implementation, the station controller in the water electrolysis hydrogen production station 140 is also used to obtain the alkali solution temperature at the inlet and outlet of multiple electrolytic cells; if it is determined that the alkali solution temperature at the inlet of multiple electrolytic cells and / or the alkali solution temperature at the outlet of multiple electrolytic cells deviates from the preset temperature range, the operating parameters of the multiple electrolytic cells and the cooling water temperature at the inlet and outlet of the cooling water device are obtained; the cooling water demand of the cooling water device is determined according to the alkali solution temperature at the inlet and outlet of the multiple electrolytic cells, the operating parameters of the multiple electrolytic cells and the cooling water temperature at the inlet and outlet of the cooling water device; according to the cooling water demand, the valve at the inlet of the cooling water device is adjusted to ensure that the alkali solution temperature at the inlet of the multiple electrolytic cells and / or the alkali solution temperature at the outlet of the multiple electrolytic cells are within the preset temperature range.

[0282] In one possible implementation, the station controller in the water electrolysis hydrogen production station 140 is also used to obtain the concentration of alkali solution in multiple electrolytic cells and the liquid level of alkali solution in the gas-liquid separator; if it is determined that the concentration of the alkali solution is higher than the preset concentration, and / or the liquid level of the alkali solution is lower than the preset liquid level, the demand for raw water in the water electrolysis hydrogen production station is determined according to the target power consumption of the water electrolysis hydrogen production station; according to the demand for raw water, the valves at the inlets of multiple electrolytic cells are adjusted to reduce the concentration of the alkali solution and / or increase the liquid level of the alkali solution.

[0283] In a possible implementation, the control center 110 can also be used to obtain the amount of hydrogen entering, the amount of hydrogen released, and the amount of hydrogen stored in the gas tank; determine the buffer time of the gas tank based on the amount of hydrogen entering, the amount of hydrogen released, and the amount of hydrogen stored, and the buffer time represents the time required for the gas tank to be fully stored with hydrogen; if it is determined that the power adjustment time is not greater than the buffer time, then the target adjustment mode is determined to be the first adjustment mode, and the first adjustment mode is used to adjust the operation of the gas tank; if it is determined that the power adjustment time is greater than the buffer time, then the target adjustment mode is determined to be the second adjustment mode, and the second adjustment mode is used to adjust the operation of the synthesis tower.

[0284] In a possible implementation, the station controller in the synthetic ammonia station 160 is further configured to adjust the pressure control valve on the inlet pipe of the gas storage tank and / or the pressure control valve on the outlet pipe of the gas storage tank according to the hydrogen consumption in the synthesis tower and the hydrogen inlet amount of the gas storage tank if the received target adjustment mode is the first adjustment mode. If the received target adjustment mode is the second adjustment mode, the gas pressure in the synthesis tower is adjusted according to the change value of the hydrogen inlet amount of the gas storage tank.

[0285] In one possible implementation, the station controller in the synthetic ammonia station 160 is used to adjust the gas pressure in the synthesis tower according to the change value of the hydrogen intake amount of the gas storage tank if the received target adjustment mode is the second adjustment mode. It is also specifically used to increase the gas pressure in the synthesis tower if the change value of the hydrogen intake amount is determined to be positive; and reduce the gas pressure in the synthesis tower if the change value of the hydrogen intake amount is determined to be negative.

[0286] In summary, the electric hydrogen production and ammonia synthesis method and system provided by the embodiment of the present invention firstly receives the dispatch instruction sent by the power grid dispatch center at the control center; then, the control center determines the power control target value and power adjustment time of the electric hydrogen production and ammonia synthesis system based on the dispatch instruction, wherein the electric hydrogen production and ammonia synthesis system satisfies the preset operating conditions when operating according to the power control target value, and the power adjustment time represents the time consumed by the electric hydrogen production and ammonia synthesis system to adjust from the current power consumption to the power control target value; then, the control center determines the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and sends the target power consumption to the water electrolysis hydrogen production station, so that the water electrolysis hydrogen production station produces hydrogen based on the target power consumption; at the same time, the control center determines the target adjustment mode of the operating condition of the ammonia synthesis station according to the power adjustment time, and sends the target adjustment mode to the ammonia synthesis station, so that the ammonia synthesis station synthesizes liquid ammonia based on the target adjustment mode. In the embodiment of the present invention, the control center determines the power control target value and power adjustment time of the electric hydrogen production and ammonia synthesis system based on the dispatch instruction issued by the power grid dispatch center, determines the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and determines the target adjustment mode of the operating conditions of the ammonia synthesis station according to the power adjustment time, thereby adjusting the operation of the water electrolysis hydrogen production station and the ammonia synthesis station to overcome the impact of fluctuating electricity provided by new energy sources such as wind power and photovoltaics on the stability of the production process, reduce the use of grid electricity, and reduce production costs.

[0287] The above are only specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims

1. A method for synthesizing ammonia by producing hydrogen from electricity, characterized in that: Applied to an electric hydrogen production and ammonia synthesis system, the electric hydrogen production and ammonia synthesis system comprises a control center, a water electrolysis hydrogen production station and a synthetic ammonia station, the control center communicates with the water electrolysis hydrogen production station and the synthetic ammonia station respectively, the hydrogen produced by the water electrolysis hydrogen production station is transmitted to the synthetic ammonia station through a pipeline, and the control center also communicates with a power grid dispatching center, the method comprises: The control center receives the dispatching instruction sent by the power grid dispatching center; The control center determines the power control target value and power adjustment time of the electric hydrogen production and ammonia synthesis system based on the dispatch instruction, wherein the electric hydrogen production and ammonia synthesis system satisfies the preset operating conditions when operating according to the power control target value, and the power adjustment time represents the time taken for the electric hydrogen production and ammonia synthesis system to adjust from the current power consumption to the power control target value; The control center determines the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and sends the target power consumption to the water electrolysis hydrogen production station, so that the water electrolysis hydrogen production station produces hydrogen based on the target power consumption; The control center determines a target adjustment mode of the operating conditions of the synthetic ammonia station according to the power adjustment time, and sends the target adjustment mode to the synthetic ammonia station, so that the synthetic ammonia station synthesizes liquid ammonia based on the target adjustment mode.

2. The method according to claim 1, characterized in that The electric hydrogen production and ammonia synthesis system also includes a wind power station and a photovoltaic power station, and the wind power station and the photovoltaic power station both provide electricity to the water electrolysis hydrogen production station and the ammonia synthesis station through transmission lines, and the control center also communicates with the wind power station and the photovoltaic power station respectively; The step of determining, by the control center based on the dispatch instruction, a power control target value and a power adjustment time of the electric hydrogen production and ammonia synthesis system comprises: The control center obtains wind speed data of the area where the wind power station is located and solar irradiance data of the area where the photovoltaic power station is located; The control center inputs the wind speed data and the solar irradiance data into a pre-established system simulation model, and determines the power control target value and the power adjustment time according to the model output result.

3. The method according to claim 1, characterized in that The electric hydrogen production and ammonia synthesis system also includes a wind power station and a photovoltaic power station, and the wind power station and the photovoltaic power station both provide electricity to the water electrolysis hydrogen production station and the ammonia synthesis station through transmission lines, and the control center communicates with the wind power station and the photovoltaic power station; The step of the control center determining the target power consumption of the water electrolysis hydrogen production station according to the power control target value comprises: The control center obtains the current power generation of the wind power station, the current power generation of the photovoltaic power station, the current power consumption of the synthetic ammonia station, the current power abandonment of the wind power station and the current power abandonment of the photovoltaic power station; The control center determines the target power consumption of the water electrolysis hydrogen production station based on the current power generation power of the wind power station, the current power generation power of the photovoltaic power station, the current power consumption of the synthetic ammonia station, the current abandoned power of the wind power station, the current abandoned power of the photovoltaic power station and the power control target value.

4. The method according to claim 1, characterized in that The water electrolysis hydrogen production station comprises an in-station controller and a plurality of rectifiers, wherein the in-station controller controls the operation of the plurality of rectifiers, and the in-station controller communicates with the control center; After the control center sends the target power to the water electrolysis hydrogen production station, the method further includes: The station controller compares the target power consumption with a preset maximum power and a preset minimum power; If the station controller determines that the target power consumption is greater than the preset minimum power and the target power consumption is less than the preset maximum power, the operating power of each rectifier is determined according to the target power consumption; If the station controller determines that the target power consumption is not greater than the preset minimum power, the operating power of each rectifier is determined according to the preset minimum power; If the station controller determines that the target power consumption is not less than the preset maximum power, the operating power of each rectifier is determined according to the preset maximum power.

5. The method according to claim 4, characterized in that The water electrolysis hydrogen production station also includes a gas-liquid separator and a plurality of electrolyzers, one of the electrolyzers is electrically connected to one of the rectifiers, the gas-liquid mixture produced by each electrolyzer is transmitted to the gas-liquid separator through a pipeline, and the cooling water device in the gas-liquid separator cools down the alkali liquid in the gas-liquid mixture. The method also includes: The station controller obtains the alkali solution temperature at the inlet and outlet of the plurality of electrolytic cells; If the station controller determines that the alkali solution temperature at the inlet of the multiple electrolytic cells and / or the alkali solution temperature at the outlet of the multiple electrolytic cells deviates from the preset temperature range, then the operating parameters of the multiple electrolytic cells and the cooling water temperature at the inlet and outlet of the cooling water device are obtained; The station controller determines the cooling water demand of the cooling water device according to the alkali solution temperature at the inlet and outlet of the multiple electrolytic cells, the operating parameters of the multiple electrolytic cells and the cooling water temperature at the inlet and outlet of the cooling water device; The station controller adjusts the valve at the inlet of the cooling water device according to the cooling water demand so that the alkali solution temperature at the inlet of the multiple electrolytic cells and / or the alkali solution temperature at the outlet of the multiple electrolytic cells is within a preset temperature range.

6. The method according to claim 5, characterized in that The method further comprises: The station controller obtains the concentration of the alkali solution in the multiple electrolytic cells and the liquid level of the alkali solution in the gas-liquid separator; If the station controller determines that the concentration of the alkali solution is higher than the preset concentration, and / or the liquid level of the alkali solution is lower than the preset liquid level, the demand for raw water in the electrolysis water hydrogen production station is determined according to the target power consumption of the electrolysis water hydrogen production station; The station controller adjusts the valves at the inlets of the multiple electrolytic cells according to the demand for the raw water to reduce the concentration of the alkali solution and / or increase the liquid level of the alkali solution.

7. The method according to claim 1, characterized in that The synthetic ammonia station includes a gas storage tank and a synthesis tower. The hydrogen produced by the water electrolysis hydrogen production station is transmitted to the gas storage tank through a pipeline, and the hydrogen in the gas storage tank is transmitted to the synthesis tower through a pipeline. The control center determines the target adjustment mode of the working condition of the synthetic ammonia station according to the power adjustment time, including the following steps: The control center obtains the hydrogen intake, hydrogen release and hydrogen storage of the gas storage tank; The control center determines the buffer time of the gas storage tank according to the hydrogen intake, hydrogen release and hydrogen storage, wherein the buffer time represents the time required for the gas storage tank to be fully filled with hydrogen; If the control center determines that the power adjustment time is not greater than the buffer time, the target adjustment mode is determined to be a first adjustment mode, and the first adjustment mode is used to adjust the operation of the gas storage tank; If the control center determines that the power adjustment time is greater than the buffer time, the target adjustment mode is determined to be the second adjustment mode, and the second adjustment mode is used to adjust the operation of the synthesis tower.

8. The method according to claim 1, characterized in that The target adjustment mode includes a first adjustment mode and a second adjustment mode, the synthetic ammonia station includes a gas storage tank, a synthesis tower and an in-station controller, the in-station controller communicates with the control center, and the in-station controller controls the operation of the gas storage tank and the synthesis tower; After the step of the control center sending the target adjustment mode to the synthetic ammonia plant, the method further includes: If the target regulation mode received by the station controller is the first regulation mode, the pressure control valve on the inlet pipe of the gas storage tank and / or the pressure control valve on the outlet pipe of the gas storage tank are adjusted according to the hydrogen consumption in the synthesis tower and the hydrogen intake of the gas storage tank; If the target regulation mode received by the in-station controller is the second regulation mode, the gas pressure in the synthesis tower is regulated according to the change in the amount of hydrogen entering the gas storage tank.

9. The method according to claim 8, characterized in that The step of adjusting the gas pressure in the synthesis tower according to the amount of hydrogen entering the gas storage tank by the station controller comprises: If the station controller determines that the change value of the hydrogen inlet amount is positive, the gas pressure in the synthesis tower is increased; If the station controller determines that the change in the amount of hydrogen entering is negative, the gas pressure in the synthesis tower is reduced.

10. A system for synthesizing ammonia by producing hydrogen from electricity, characterized in that: It includes a control center, a water electrolysis hydrogen production station and a synthetic ammonia station. The control center communicates with the water electrolysis hydrogen production station and the synthetic ammonia station respectively. The hydrogen produced by the water electrolysis hydrogen production station is transmitted to the synthetic ammonia station through a pipeline. The control center also communicates with a power grid dispatching center; The control center is used to: Receiving a dispatching instruction sent by the power grid dispatching center; Based on the scheduling instruction, determining a power control target value and a power adjustment time of the electric hydrogen production and ammonia synthesis system, wherein the electric hydrogen production and ammonia synthesis system meets a preset operating condition when operating according to the power control target value; Determining the target power consumption of the water electrolysis hydrogen production station according to the power control target value, and sending the target power consumption to the water electrolysis hydrogen production station; determining a target adjustment mode of the operating conditions of the synthetic ammonia station according to the power adjustment time, and sending the target adjustment mode to the synthetic ammonia station; The water electrolysis hydrogen production station is used to receive the target power consumption sent by the control center and produce hydrogen based on the target power consumption; The synthetic ammonia station is used to receive the target regulation mode sent by the control center and synthesize liquid ammonia based on the target regulation mode.