Single column pipe insulation prefabricated block and installation method

By using single-column pipe insulation prefabricated blocks in the water-cooled beams of the heating furnace, and using anchor insulation structures and anchor bolts to fix the prefabricated blocks, problems such as uneven thickness of castables and oxidation of anchor hooks in the existing technology are solved, and the service life of the refractory castables is extended. service life and improves the overall performance of the water-cooled beam of the heating furnace.

CN115143782BActive Publication Date: 2025-01-24JIAOZUO JINXIN HENGTUO REFRACTORIES
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210750597.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-29
Publication Date
2025-01-24
Estimated Expiration
2042-06-29

AI Technical Summary

Technical Problem

The on-site casting method of existing heating furnace water-cooled beams has problems such as thin iron sheet, oxidation and fall off of anchor hooks, high porosity after casting, deformation of the support mold, and short life of the refractory casting material, which affects the overall life of the heating furnace.

Method used

The single -column pipeline insulation prefabricated block, including prefabricated block i and prefabricated block II. It is fixed on the single -column pipe through anchoring thermal insulation structure and anchor bolts to form a hollow cylinder to ensure that the thickness of the pouring substrate is controllable and provided for protection.

Benefits of technology

Through the use of prefabricated blocks, the problem of unevenly pouring materials, oxidation of anchor hook oxidation, and extending the service life of refractory pouring materials, and improving the overall performance of heating the water and cold beams of the heating furnace.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115143782B_ABST
    Figure CN115143782B_ABST
Patent Text Reader

Abstract

The invention discloses a single-column pipeline insulation prefabricated block and an installation method, comprising a prefabricated block I, a prefabricated block II and anchor bolts. The prefabricated block I and the prefabricated block II are assembled to form a hollow cylinder. The prefabricated block I and the prefabricated block II are assembled to form an outer-wrapped rolling module of a water-cooled beam. No additional anchor hook is required on the single-column pipeline, and the anchor is directly built into the prefabricated block. The prefabricated block I and the prefabricated block II both have an insulation layer and an anchor. The anchor I of the prefabricated block I is welded to the outer wall of the single-column pipeline to play a role in installation and positioning. The anchor II of the prefabricated block II is locked with the anchor I after being matched with the anchor, and the prefabricated block I and the prefabricated block II are fastened to the single-column pipeline. The invention uses a prefabricated assembly structure, the thickness of a refractory casting matrix formed by casting is controllable, and the anchor is cast and wrapped by the refractory casting material, which protects the anchor, increases the fixed contact area with the single-column pipeline, and prolongs the overall service life.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of heating furnace water energy saving, and in particular relates to a single-column pipeline insulation prefabricated block and an installation method. Background Art

[0002] The water-cooled beam of the heating furnace is a load-bearing component for the steel billets to enter and exit the furnace and to realize heating in the furnace. It is composed of a steel pipe, an anchor hook welded on the steel pipe, a load-bearing slider and a refractory castable.

[0003] At present, the commonly used method is on-site pouring. The on-site pouring of water beams has the following main disadvantages:

[0004] 1. The iron sheet is relatively thin, and when wrapped, it directly presses against the anchor hook, which cannot ensure the casting thickness requirements;

[0005] 2. The anchor hook directly supports the thin iron sheet. After the heating furnace has been used for a period of time, the anchor hook will oxidize and fall off because there is no castable protective layer;

[0006] 3. The iron sheet is too thin, and you dare not vibrate or hit it with a rubber hammer during construction, which will cause the porosity of the castable to be too large after molding;

[0007] 4. When supporting the iron formwork, it is easy to deform when tied with iron wire, resulting in uneven thickness of the pouring layer, affecting the service life and the overall aesthetics of the poured water-cooled beam.

[0008] 5. The working conditions of refractory castables for water-cooled beams are very harsh. The thickness is relatively thin (generally 50~60mm), and it is only connected and fixed to the water-cooled beams by metal anchor hooks. It is affected by mechanical vibrations, rapid cooling and heating of the furnace when it is shut down and started, and other factors under high temperature conditions. Therefore, the life of refractory castables for water-cooled beams cast on site is generally not high, which restricts the overall life of the heating furnace. Summary of the invention

[0009] In view of the deficiencies described in the above-mentioned prior art, the present invention provides a single-column pipeline insulation prefabricated block and an installation method.

[0010] The technical solution adopted by the present invention is:

[0011] A single-column pipeline insulation prefabricated block comprises a prefabricated block I, a prefabricated block II and anchor bolts. The prefabricated block I and the prefabricated block II are assembled to form a hollow cylinder.

[0012] The prefabricated block I comprises a refractory casting base body I, which is cast by refractory castable material, and the refractory casting base body I is provided with a single pipe clearance hole I, and at least one group of anchoring insulation structures I is provided on the inner wall of the single pipe clearance hole I, and each group of the anchoring insulation structures I comprises two anchors I and an insulation layer I, and the insulation layer I is located between the two anchors I; and anchoring ends I are provided at both ends of each anchor I;

[0013] The refractory casting base body I is provided with an anchoring clearance hole I at a position corresponding to each anchoring end I; the anchoring clearance hole I is vertically connected to the single pipe clearance hole I; and a welding area is provided at a position corresponding to the anchoring end I and the outer wall of the single column pipe.

[0014] The prefabricated block II comprises a refractory casting base II, the refractory casting base II is provided with a single pipe clearance hole II, at least one group of anchoring insulation structures II is provided on the inner wall of the single pipe clearance hole II, each group of the anchoring insulation structures II comprises two anchors II and an insulation layer II, and the insulation layer II is located between the two anchors II; both ends of each anchor II are provided with anchoring ends II;

[0015] The refractory casting base II is provided with an anchoring clearance hole II at a position corresponding to each anchoring end II; the anchoring clearance hole II is vertically connected with the single pipe clearance hole II;

[0016] After the refractory casting base II and the refractory casting base I are assembled, the single pipe clearance hole II and the single pipe clearance hole I are spliced ​​into a single column pipe installation hole; the anchoring clearance hole I and the corresponding anchoring clearance hole II constitute an anchoring hole; each anchoring hole has an anchoring end I and an anchoring end II that cooperate to form an anchoring installation part; the anchoring bolt is connected to the anchoring installation part through the anchoring hole to fix the prefabricated block I and the prefabricated block II together.

[0017] As a preferred solution of the present invention, the anchoring piece I comprises an anchoring substrate I, and at least one anchoring layer I is provided on the outer circumferential wall of the anchoring substrate I in the axial direction; the provision of the anchoring layer I makes the connection between the anchoring piece I and the refractory casting substrate I stronger, and anchoring ends I are provided at both ends of the anchoring substrate I, and the anchoring ends I and the anchoring substrate I are located in the same plane. That is, the anchoring ends I are directly served by the ends of the anchoring substrate I.

[0018] As a preferred embodiment of the present invention, each of the anchoring layers I includes a plurality of anchoring sheets I, each of which is arranged circumferentially; and the anchoring sheets I are located in the refractory casting matrix I. The refractory casting material directly wraps the anchoring sheets I during casting, thereby increasing the contact area between the anchoring piece I and the refractory casting matrix I.

[0019] As a preferred solution of the present invention, in order to be able to closely match with the single-column pipeline, the end surface of the thermal insulation layer 1 facing the single-column pipeline is not lower than the end surface of the anchor substrate 1 facing the single-column pipeline. It can be flush or the thermal insulation layer 1 can exceed the anchor substrate 1 and fit closely with the single-column pipeline, because the anchor end 1 needs to be welded to the outer wall of the single-column pipeline.

[0020] As a preferred embodiment of the present invention, the anchoring member II comprises an anchoring substrate II, and at least one anchoring layer II is provided on the outer circumferential wall of the anchoring substrate II in the axial direction; the two ends of the anchoring substrate II are respectively bent outward to form an anchoring end portion II, and a receiving area for the anchoring end portion I is formed between the anchoring end portion II and the anchoring substrate II; and the anchoring end portion II is provided with an anchoring threaded hole.

[0021] As a preferred solution of the present invention, an anchor nut is provided on the end surface of the anchor end I facing the anchor end II. The anchor nut corresponds to the anchor threaded hole and is then locked with an anchor bolt.

[0022] As a preferred solution of the present invention, each of the anchoring layers II includes a plurality of anchoring sheets II, each of which is arranged circumferentially; and the anchoring sheets II are located in the refractory casting matrix II. The refractory casting material directly wraps the anchoring sheets II during casting, thereby increasing the contact area between the anchoring pieces II and the refractory casting matrix II.

[0023] As a preferred solution of the present invention, in order to be able to fit closely with the single-column pipeline, the end surface of the insulation layer II facing the single-column pipeline is not lower than the end surface of the anchor substrate II facing the single-column pipeline.

[0024] As a preferred solution of the present invention, the thermal insulation layer I and the thermal insulation layer II are thermal insulation fiber layers, which can be made of fiber felt.

[0025] The present invention also provides a method for installing a single-column pipeline insulation prefabricated block, wherein the prefabricated block I is sleeved on the outer wall of the single-column pipeline, and each anchoring end I is welded to the outer wall of the single-column pipeline;

[0026] The prefabricated block II is placed on the outer wall of the single column pipe and aligned with the prefabricated block I. The single pipe clearance hole II is aligned with the single pipe clearance hole I to form a single column pipe installation hole; the anchor clearance hole I is aligned with the anchor clearance hole II to form an anchor hole; the anchor end I is located in the accommodation area; the anchor threaded hole of the anchor end II is aligned with the anchor nut of the anchor end I;

[0027] The anchor bolts extend into the anchor holes and are threadedly connected with the anchor thread holes and anchor nuts to fix the prefabricated block I, prefabricated block II and the single column pipeline together.

[0028] The present invention uses prefabricated block I and prefabricated block II to assemble an outer rolled module of a water-cooled beam, and there is no need to additionally set an anchor hook on the single-column pipe, and the anchor is directly built into the prefabricated block, and both the prefabricated block I and the prefabricated block II have an insulation layer and an anchor, and the anchor I of the prefabricated block I is welded to the outer wall of the single-column pipe to play a role in installation and positioning, and the anchor II of the prefabricated block II is locked with the anchor I after matching with the anchor bolt, so that the prefabricated block I and the prefabricated block II are fastened to the single-column pipe. The present invention uses a prefabricated assembly structure, and the thickness of the refractory casting matrix formed by casting is controllable, and the anchor is cast and wrapped by the refractory casting material, which protects the anchor, increases the fixed contact area with the single-column pipe, and prolongs the overall service life. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0030] Figure 1 It is a schematic diagram of the structure of the present invention.

[0031] Figure 2 It is a cross-sectional view of the present invention and the single column pipeline assembly.

[0032] Figure 3 Schematic diagram of the internal structure of the prefabricated block I of the present invention.

[0033] Figure 4 This is a schematic diagram of the internal structure of the prefabricated block II of the present invention.

[0034] Figure 5 It is a schematic structural diagram of the anchor bolt of the present invention.

[0035] Figure 6 It is a schematic diagram of the assembly of the prefabricated block I and the single column pipeline of the present invention.

[0036] Figure 7 It is a schematic diagram of the assembly of the prefabricated block I, the prefabricated block II and the single column pipeline of the present invention. DETAILED DESCRIPTION

[0037] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0038] Example:

[0039] A single column pipe insulation prefabricated block, such as Figure 1 and 2 As shown, it includes a prefabricated block I1, a prefabricated block II2 and an anchor bolt 3. The prefabricated block I1 and the prefabricated block II2 are assembled into a hollow cylinder.

[0040] The prefabricated block I1, such as Figure 3 As shown, it includes a refractory casting base I100, which is cast by refractory castables. The refractory casting base I100 is provided with a single pipe clearance hole I101, and a group of anchoring insulation structures I is provided on the inner wall of the single pipe clearance hole I101. The anchoring insulation structure I includes two anchors I102 and an insulation layer I103. The insulation layer I uses an insulation fiber structure; the insulation layer I103 is located between the two anchors I102.

[0041] The anchoring piece I102 includes an anchoring substrate I1020, and at least one anchoring layer I is provided on the outer circumferential wall of the anchoring substrate I1020 in the axial direction. In this embodiment, two anchoring layers I are used; the provision of the anchoring layer I makes the connection between the anchoring piece I and the refractory casting substrate I stronger. Each of the anchoring layers I includes a plurality of anchoring sheets I1022, and each anchoring sheet I1022 is provided circumferentially; and the anchoring sheet I is located in the refractory casting substrate I100. The refractory casting material directly wraps the anchoring sheet I during casting, thereby increasing the contact area between the anchoring piece I and the refractory casting substrate I.

[0042] The end face of the insulation layer I facing the single column pipe is not lower than the end face of the anchoring substrate I1020 facing the single column pipe. It can be flush or the insulation layer I can exceed the anchoring substrate I and fit tightly with the single column pipe, because the anchoring end I needs to be welded to the outer wall of the single column pipe.

[0043] Furthermore, anchoring ends 11021 are provided at both ends of the anchoring substrate 11020, and the anchoring ends 11021 are located in the same plane as the anchoring substrate 11020. That is, the anchoring ends 11021 are directly served by the ends of the anchoring substrate 11020.

[0044] The refractory casting base body I100 is provided with an anchoring clearance hole I104 at a position corresponding to each anchoring end I; the anchoring clearance hole I104 is vertically connected to the single pipe clearance hole I101; the position corresponding to the anchoring end I and the outer wall of the single column pipe has a welding area. An anchoring nut is provided on the end face of the anchoring end I1021 facing the anchoring end II2021.

[0045] The prefabricated block II2, such as Figure 4As shown, it includes a refractory casting base II200, and the refractory casting base II200 is provided with a single pipe making way hole II201, and a group of anchoring insulation structures II is provided on the inner wall of the single pipe making way hole II201, each group of the anchoring insulation structure II includes two anchors II202 and an insulation layer II203, and the insulation layer II203 is located between the two anchors II202.

[0046] The anchoring piece II202 comprises an anchoring substrate II2020, and two anchoring layers II are arranged in the axial direction on the outer circumferential wall of the anchoring substrate II2020, and each of the anchoring layers II comprises a plurality of anchoring sheets II2022, and each anchoring sheet II2022 is arranged circumferentially; and the anchoring sheets II2022 are located in the refractory casting matrix II200. When the refractory casting material is cast, the anchoring sheets II are directly wrapped, thereby increasing the contact area between the anchoring piece II and the refractory casting matrix II.

[0047] In order to be able to fit closely with the single-column pipeline, the end surface of the insulation layer II facing the single-column pipeline is not lower than the end surface of the anchoring substrate II2020 facing the single-column pipeline.

[0048] Both ends of each anchoring substrate II2020 are bent outward to form an anchoring end II2021, and a accommodating area for the anchoring end I1021 is formed between the anchoring end II2021 and the anchoring substrate II2020; and the anchoring end II2021 is provided with an anchoring threaded hole; the anchoring threaded hole corresponds to the anchoring nut for tightening the anchoring bolt.

[0049] The refractory casting base II200 is provided with an anchoring clearance hole II204 at a position corresponding to each anchoring end II; the anchoring clearance hole II204 is vertically connected to the single pipe clearance hole II201.

[0050] After the refractory casting base II200 and the refractory casting base I100 are assembled, Figure 1 and 2 As shown, the single pipe clearance hole II201 and the single pipe clearance hole I101 are spliced ​​into a single column pipe installation hole; the anchor clearance hole I104 and the corresponding anchor clearance hole II204 constitute an anchor hole; each anchor hole has an anchor end I and an anchor end II that cooperate to form an anchor installation part; the anchor bolt 3 is connected to the anchor installation part through the anchor hole to fix the prefabricated block I1 and the prefabricated block II2 together, and the anchor bolt 3 is as shown Figure 5 shown.

[0051] For the installation method of single column pipe insulation prefabricated blocks, such as Figure 6 and 7 As shown, the prefabricated block I1 is sleeved on the outer wall of the single-column pipe, and each anchoring end I1021 is welded to the outer wall of the single-column pipe 4;

[0052] The prefabricated block II2 is placed on the outer wall of the single column pipe and aligned with the prefabricated block I1. The single pipe clearance hole II201 and the single pipe clearance hole I101 are aligned and spliced ​​into a single column pipe installation hole; the anchor clearance hole I104 and the anchor clearance hole II204 are aligned and spliced ​​into an anchor hole; the anchor end I is located in the accommodation area; the anchor threaded hole of the anchor end II is aligned with the anchor nut of the anchor end I;

[0053] The anchor bolt 3 extends into the anchor hole and is threadedly connected with the anchor thread hole and the anchor nut to fix the prefabricated block I1, the prefabricated block II2 and the single column pipeline together.

[0054] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0055] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A single-column pipeline insulation prefabricated block, characterized in that: The invention comprises a prefabricated block I (1), a prefabricated block II (2) and an anchor bolt (3), wherein the prefabricated block I (1) comprises a refractory casting base body I (100), the refractory casting base body I (100) is provided with a single pipe clearance hole I (101), at least one group of anchoring insulation structures I is provided on the inner wall of the single pipe clearance hole I (101), each group of the anchoring insulation structures I comprises two anchors I (102) and an insulation layer I (103), and the insulation layer I (103) is located between the two anchors I (102); each anchor I (102) is provided with an anchoring end portion I at both ends; The refractory casting base body I (100) is provided with an anchoring clearance hole I (104) at a position corresponding to each anchoring end I; the anchoring clearance hole I (104) is vertically connected to the single pipe clearance hole I (101); the anchoring end I has a welding area; The prefabricated block II (2) comprises a refractory casting base II (200), wherein the refractory casting base II (200) is provided with a single pipe clearance hole II (201), and at least one group of anchoring insulation structures II is provided on the inner wall of the single pipe clearance hole II (201), wherein each group of the anchoring insulation structures II comprises two anchors II (202) and an insulation layer II (203), and the insulation layer II (203) is located between the two anchors II (202); and each anchor II (202) is provided with anchoring ends II at both ends; The refractory casting base II (200) is provided with an anchoring clearance hole II (204) at a position corresponding to each anchoring end II; the anchoring clearance hole II (204) is vertically connected to the single pipe clearance hole II (201); After the refractory casting base II (200) and the refractory casting base I (100) are assembled, the single pipe clearance hole II (201) and the single pipe clearance hole I (101) are spliced ​​into a single column pipe installation hole; the anchoring clearance hole I (104) and the corresponding anchoring clearance hole II (204) form an anchoring hole; each anchoring hole has an anchoring end I and an anchoring end II that cooperate to form an anchoring installation part; the anchoring bolt (3) is connected to the anchoring installation part through the anchoring hole to fix the prefabricated block I (1) and the prefabricated block II (2) together.

2. The single-column pipeline insulation prefabricated block according to claim 1 is characterized in that: The anchoring member I (102) comprises an anchoring substrate I (1020), wherein at least one anchoring layer I is provided in the axial direction on the outer circumferential wall of the anchoring substrate I (1020); anchoring end portions I (1021) are provided at both ends of the anchoring substrate I (1020), and the anchoring end portions I (1021) and the anchoring substrate I (1020) are located in the same plane.

3. The single-column pipeline insulation prefabricated block according to claim 2 is characterized in that: Each of the anchoring layers I comprises a plurality of anchoring sheets I (1022), each of the anchoring sheets I (1022) being arranged circumferentially; and the anchoring sheets I are located within the refractory casting matrix I (100).

4. The single-column pipeline insulation prefabricated block according to claim 2 is characterized in that: The end surface of the thermal insulation layer I facing the single-column pipeline is not lower than the end surface of the anchoring substrate I (1020) facing the single-column pipeline.

5. The single-column pipeline insulation prefabricated block according to claim 2, 3 or 4, characterized in that: The anchoring member II (202) comprises an anchoring substrate II (2020), wherein at least one anchoring layer II is provided on the outer circumferential wall of the anchoring substrate II (2020) in the axial direction; the two ends of the anchoring substrate II (2020) are respectively bent outwards to form an anchoring end portion II (2021), and a receiving area for the anchoring end portion I (1021) is formed between the anchoring end portion II (2021) and the anchoring substrate II (2020); and the anchoring end portion II (2021) is provided with an anchoring threaded hole.

6. The single-column pipeline insulation prefabricated block according to claim 5 is characterized in that: An anchor nut is provided on the end surface of the anchor end portion I (1021) facing the anchor end portion II (2021).

7. The single-column pipeline insulation prefabricated block according to claim 5 is characterized in that: Each of the anchoring layers II comprises a plurality of anchoring sheets II (2022), each anchoring sheet II (2022) being arranged circumferentially; and the anchoring sheets II (2022) are located within the refractory casting matrix II (200).

8. The single-column pipeline insulation prefabricated block according to claim 7 is characterized in that: The end surface of the thermal insulation layer II facing the single-column pipeline is not lower than the end surface of the anchoring substrate II (2020) facing the single-column pipeline.

9. The single-column pipeline insulation prefabricated block according to claim 8 is characterized in that: The thermal insulation layer I and the thermal insulation layer II are thermal insulation fiber layers.

10. A method for installing a single-column pipeline insulation prefabricated block as claimed in any one of claims 1 to 9, characterized in that: The prefabricated block I (1) is placed on the outer wall of the single-column pipeline, and each anchor end I (1021) is welded to the outer wall of the single-column pipeline; The prefabricated block II (2) is placed on the outer wall of the single column pipe and aligned with the prefabricated block I (1); the single pipe clearance hole II (201) and the single pipe clearance hole I (101) are aligned and assembled into a single column pipe installation hole; the anchor clearance hole I (104) and the anchor clearance hole II (204) are aligned and assembled into an anchor hole; the anchor end I is located in the accommodation area; the anchor threaded hole of the anchor end II is aligned with the anchor nut of the anchor end I; The anchor bolt (3) extends into the anchor hole and is threadedly connected with the anchor thread hole and the anchor nut to fix the prefabricated block I (1), the prefabricated block II (2) and the single column pipeline together.

Citation Information

Patent Citations

  • Prefabricated refractory lining of top structure of high temperature equipment and construction method of prefabricated refractory lining

    CN107504816A

  • Heating furnace water beam quick installation refractory module and method

    CN110285682A