An intelligent control method for a multi-energy complementary heating system

Through big data and artificial intelligence in multi-energy complementary heating systems, intelligent regulation methods are used to optimize the operation of gas boilers and heat pumps, solving the problem that traditional manual regulation is difficult to achieve efficient operation, and realizing on-demand heating and reducing carbon emissions Effect.

CN115342419BActive Publication Date: 2024-11-12中核坤华能源发展有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210951889.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-09
Publication Date
2024-11-12
Estimated Expiration
2042-08-09

AI Technical Summary

Technical Problem

In a multi-energy complementary heating system, how to determine the order of commissioning, commissioning time and load distribution, traditional manual experience regulation is difficult to achieve economical and efficient operation, and cannot achieve the purpose of on-demand heating and precise heating.

Method used

Using intelligent regulation methods based on big data mining and artificial intelligence, we can periodically collect outdoor temperature data, calculate the daily average outdoor temperature, determine the start and stop of gas boilers and heat pumps, and establish a heating cost model, and use optimization algorithms (such as ants) Group search, simulated annealing or genetic algorithm) optimize the load of gas boilers, heat pumps and circulation pumps, and generate regulatory solutions to achieve the lowest heating cost.

Benefits of technology

It realizes efficient operation of multi-energy complementary heating systems, reduces operating costs and carbon emissions, ensures heating on demand on the user side, and improves the overall efficiency and operating safety of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115342419B_ABST
    Figure CN115342419B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of heating technology, and specifically to an intelligent control method for a multi-energy complementary heating system. In the first N days of heating, the average daily outdoor comprehensive temperature is calculated; the start and stop of the gas boiler and the heat pump are determined; after N days of heating, the operation data of the gas boiler, heat pump, circulating pump and blower in the first N days are collected, and the efficiency of the gas boiler, heat pump, circulating pump and blower is calculated; a control scheme is generated periodically; including: predicting the heating demand in the next cycle; establishing a heating cost model for a multi-energy complementary heating system; setting the heating amount of the multi-energy complementary heating system to be equal to the heating demand in the next cycle, the optimization target is to obtain the lowest heating cost from the heating cost model, establish an optimization algorithm; execute the optimization algorithm; and use the loads of the gas boiler, heat pump and circulating pump obtained as the control result of the next cycle. The beneficial technical effects of the present invention include: realizing the optimal scheduling of multi-energy complementarity and improving the comprehensive efficiency of the multi-energy complementary heating system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of heating, and in particular to an intelligent control method for a multi-energy complementary heating system. Background Art

[0002] In the Nanyang Recycled Water Source Heat Pump Heating and Cooling Demonstration Project, water source heat pump technology and gas clean heating technology are used together to achieve a multi-energy complementary heating method. However, in the operation of the multi-energy complementary heating system, the operating efficiency of different types of energy systems is different. How to determine the order of commissioning, commissioning duration and load distribution requires full consideration of factors such as the comprehensive energy cost and carbon emissions. If we rely on traditional manual experience control, we will not be able to achieve economical and efficient operation of the multi-energy complementary heating system, and we will not be able to achieve the purpose of on-demand heating and precise heating.

[0003] Based on the above problems, it is necessary to study the use of advanced technologies such as big data mining and artificial intelligence to establish an intelligent control model for a multi-energy complementary heating system, and to ensure the operation effect while achieving multi-objective optimization. Summary of the invention

[0004] The technical problem to be solved by the present invention is that there is currently a lack of solutions to improve the operating efficiency of a multi-energy heating system. An intelligent control method for a multi-energy complementary heating system is proposed, which can intelligently control the heating operating state and improve the efficiency of the heating system.

[0005] To solve the above technical problems, the present invention adopts the following technical solution: an intelligent control method for a multi-energy complementary heating system, comprising:

[0006] In the first N days of heating, outdoor temperature data is collected periodically to calculate the outdoor daily average comprehensive temperature t _WZ ;

[0007] According to the outdoor daily average comprehensive temperature t _WZ Determine the start and stop of gas boilers and heat pumps;

[0008] After N days of heating, collect the operating data of the gas boiler, heat pump, circulation pump and blower in the previous N days, and calculate the efficiency of the gas boiler, heat pump, circulation pump and blower;

[0009] Periodically generate a control plan, the control plan including the start and stop of the gas boiler and the heat pump and the operating load;

[0010] Methods for periodically generating control plans include:

[0011] Collect outdoor temperature data and calculate the outdoor daily average comprehensive temperature t _WZ , predict the heating demand in the next cycle;

[0012] Establish a heating cost model for a multi-energy complementary heating system, and substitute the efficiency of gas boilers, heat pumps, circulation pumps and blowers into the heating cost model;

[0013] The heating supply of the multi-energy complementary heating system is set to be equal to the heating demand of the next cycle. The optimization goal is to obtain the lowest heating cost from the heating cost model and establish an optimization algorithm.

[0014] Execute the optimization algorithm to obtain the load of gas boiler, heat pump and circulation pump when the heating cost is the lowest;

[0015] The obtained loads of the gas boiler, heat pump and circulating pump are used as the control results of the next cycle.

[0016] As a preferred method, calculate the outdoor daily average comprehensive temperature t _WZ The methods include:

[0017] Collect the temperatures of multiple outdoor temperature sensors and calculate the average temperature;

[0018] Collect the detection values ​​of multiple outdoor light intensity sensors and calculate the average light intensity;

[0019] Generate temperature correction value according to light intensity;

[0020] The average temperature and the temperature correction value are superimposed as the outdoor daily average comprehensive temperature t _WZ .

[0021] Preferably, the method for generating a temperature correction value according to light intensity includes:

[0022] When the average light intensity is less than or equal to 10 Lux, the temperature correction value is 0. When the average light intensity is greater than 10 and not greater than 20 Lux, the temperature correction value is +0.5°C; when the average light intensity is greater than 20 and not greater than 30 Lux, the temperature correction value is +1.0°C; when the average light intensity is greater than 30 and not greater than 45 Lux, the temperature correction value is +1.5°C; when the average light intensity is greater than 45 Lux, the temperature correction value is +2°C.

[0023] As a preferred method, the indoor target comfort temperature is set. In the first N days of heating, the indoor target comfort temperature and the outdoor daily average comprehensive temperature t _WZ Calculate the average daily load Q _D , according to the daily average load Q _D and the installed capacity of the heat pump, calculate the heat pump load rate when only the heat pump is started, if the heat pump load rate exceeds the preset threshold, start the gas boiler and the heat pump, if the heat pump load rate does not exceed the preset threshold, only start the heat pump.

[0024] Preferably, when the control scheme is generated periodically, the operation data of the gas boiler and the heat pump in the previous cycle are read, and the efficiency of the gas boiler and the heat pump is calculated based on the operation data of the gas boiler and the heat pump in the previous cycle.

[0025] Preferably, according to the operation data of the gas boiler, the heat pump and the circulating pump in the previous cycle, the method for calculating the efficiency of the gas boiler, the heat pump, the circulating pump and the blower includes:

[0026] Calculating the COP of a heat pump _HP ,

[0027]

[0028] Calculation of the efficiency η of a gas boiler _GAS ,

[0029]

[0030] In the formula, Q _HP is the total heat output of the heating system, E _HE The electricity consumption of the circulating pump, E _HP The electricity consumption for heat pump operation, Q _GAS is the heat output of the gas boiler per unit time, q _GAS is the calorific value of natural gas, G _GAS is the gas consumption of the gas boiler per unit time;

[0031] According to the operating data of the circulation pump in the previous N days, calculate the efficiency η of the water pump _pump ,

[0032]

[0033] Among them, G _pump is the instantaneous flow rate of the circulating pump, and a, b, c are fitting coefficients, which are obtained by fitting the operating data of the circulating pump in the previous N days.

[0034] As a preferred embodiment, after N days of heating, a decision is made in each cycle based on the heat pump operation data whether to exit the operation of the heat pump, specifically including:

[0035] Calculate the cost M of the heat pump providing 1GJ of heat _HP ,

[0036]

[0037] According to the efficiency η of the gas boiler in the previous cycle _GAS , calculate the cost M when the gas boiler provides 1GJ of unit heat _GAS ,

[0038]

[0039] Among them, the electricity price is A yuan / kWh, the gas price is B yuan / cubic meter, let M _HP Equal to M _GAS , solve the obtained COP value, determine whether there is a heat pump unit with an efficiency lower than the calculated COP value in the previous cycle, and shut down the heat pump unit with an efficiency lower than the calculated COP.

[0040] As a preferred method, the heating cost model of the multi-energy complementary heating system is established as follows:

[0041]

[0042] Among them, M _Tatal The total cost required to provide the heating demand for the next cycle for the multi-energy complementary heating system, cop i is the efficiency of the ith heat pump, A i The electricity price set for the i-th heat pump, is the efficiency of the jth gas boiler, The calorific value of natural gas set for the jth gas boiler, B j The gas price set for the jth gas boiler, G ε_pump is the instantaneous flow rate of the εth circulating pump, H ε_pump is the head of the εth circulating pump, is the efficiency of the εth circulating pump, G ω_Fan is the air volume of the ωth fan, H ω_Fan is the head of the first fan, is the efficiency of the ωth fan, and the efficiency of the fan is provided by the fan manufacturer. The operating data of all heat pumps, gas boilers, circulating pumps and fans are substituted into the heating cost model to obtain the total cost required for the multi-energy complementary heating system to provide the heating demand for the next cycle under the current state.

[0043] Preferably, the established optimization algorithm is an ant colony search algorithm, a simulated annealing algorithm or a genetic algorithm.

[0044] Preferably, after N days of heating, the cycle for generating the control plan is 1 hour.

[0045] The beneficial technical effects of the present invention include: based on the intelligent prediction data of the expert system of the heat production center platform, combined with a comprehensive analysis of factors such as the heat source operating cost and storage margin, to achieve optimal scheduling of multi-energy complementarity and improve the comprehensive efficiency of the multi-energy complementary heating system; through load forecasting, ensure on-demand heating at the user end and ensure the safety of user heating; based on the optimization algorithm, provide the best control plan to maximize the efficiency of the multi-energy complementary heating system; combine the carbon emissions and operating costs of the energy to perform optimal scheduling, which not only reduces the operating cost, but also reduces carbon emissions, and achieves regional optimization scheduling of multiple energy sources.

[0046] Other features and advantages of the present invention will be disclosed in detail in the following specific embodiments and drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] The present invention will be further described below in conjunction with the accompanying drawings:

[0048] Figure 1 It is a schematic flow chart of the intelligent control method of the heating system according to an embodiment of the present invention.

[0049] Figure 2 It is a schematic diagram of the structure of a heating system according to an embodiment of the present invention.

[0050] Figure 3 Schematic diagram of heat load time continuation according to an embodiment of the present invention.

[0051] Figure 4 The present invention is a flowchart of periodically generating a control scheme according to an embodiment of the present invention.

[0052] Figure 5 The figure is a flow chart of a method for calculating the average outdoor daily comprehensive temperature according to an embodiment of the present invention.

[0053] Among them: 10. Recycled water heat exchange unit, 20. Heat pump, 30. Gas boiler. DETAILED DESCRIPTION

[0054] The technical solutions of the embodiments of the present invention are explained and described below in conjunction with the drawings of the embodiments of the present invention, but the following embodiments are only preferred embodiments of the present invention, not all. Based on the embodiments in the implementation mode, other embodiments obtained by those skilled in the art without creative work are all within the protection scope of the present invention.

[0055] In the following description, terms such as "inside", "outside", "up", "down", "left", "right", etc. that indicate directions or positional relationships are only used to facilitate the description of the embodiments and simplify the description, and do not indicate or imply that the referred device or element must have a specific direction, be constructed and operate in a specific direction. Therefore, it should not be understood as a limitation of the present invention.

[0056] A method for intelligent control of a multi-energy complementary heating system, please refer to the attached Figure 1 ,include:

[0057] Step A01) During the first N days of heating, periodically collect outdoor temperature data and calculate the outdoor daily average comprehensive temperature t _WZ ;

[0058] Step A02) Based on the outdoor daily average comprehensive temperature t _WZ Determine the start and stop of the gas boiler 30 and the heat pump 20;

[0059] Step A03) After N days of heating, collect the operating data of the gas boiler 30, the heat pump 20, the circulating pump and the blower in the previous N days, and calculate the efficiency of the gas boiler 30, the heat pump 20, the circulating pump and the blower;

[0060] Step A04) Periodically generate a control plan, which includes the start and stop and operating load of the gas boiler 30 and the heat pump 20. After N days of heating, the cycle of generating the control plan is 1 hour.

[0061] Please see attached Figure 2 , the equipment providing heat in the heating system includes a regenerative water heat exchanger unit 10, a heat pump 20 and a gas boiler 30, wherein the regenerative water heat exchanger unit 10 only considers the power consumption of the circulating pump used by it. The combined output of the basic heat source and the peak-shaving heat source is adjusted on a daily basis. The basic heat source is the regenerative water heat exchanger unit 10 and the heat pump 20, and the peak-shaving heat source is the gas boiler 30. The energy consumption of the regenerative water heat exchanger unit 10 and the heat pump 20 is low, so it is preferred to consider using the regenerative water heat exchanger unit 10 and the heat pump 20 to provide heat energy. First, ensure that the basic heat source is at the high efficiency point and works within the rated load. In general, the load rate corresponding to the highest efficiency point of the heat pump 20 is 70%-95%, so when the load rate of the basic heat source reaches 95%, the peak-shaving heat source, that is, the gas boiler 30, is started. The gas boiler 30 will not have a great impact on the boiler efficiency within a large range of load rate changes, but in order to ensure the burner efficiency, the heat load rate when starting the gas boiler 30 must be greater than 30%. Therefore, the load rate and operating efficiency of the basic heat source and the peak-shaving heat source are comprehensively considered, and the output of each system is dynamically adjusted to ensure that the coupled system is always in an efficient operating condition. That is, when the load rate of the basic heat source reaches 95%, the peak-shaving heat source is started, and once the peak-shaving heat source is started, it is ensured that the thermal load rate of the peak-shaving heat source is always greater than 30%. When the heat load needs to reach 21,000 kW, the peak-shaving heat source needs to be started, and the outdoor temperature is -3°C at this time. The local outdoor temperature of -3°C will last for 43 days. Figure 3 As shown in the figure, it is a schematic diagram of the heat load time duration in the heating plan. According to the heat load time duration and the installed capacity of the basic heat source, it is possible to preliminarily determine the length of time it takes to start the peak load heat source so as to make early planning preparations. The on-site heating area of ​​this embodiment is 600,000 m2, and the heat load time duration diagram is as follows Figure 3 As shown, during the planned heating period, the operation strategy of the heating system coupled with the heat pump 20 and the gas boiler 30 is shown in Table 1.

[0062] Table 1 Operation strategy of heat pump 20 and gas boiler 30

[0063]

[0064] Please see attached Figure 4 , the method of periodically generating a control scheme includes:

[0065] Step B01) Collect outdoor temperature data and calculate the outdoor daily average comprehensive temperature t _WZ , predict the heating demand in the next cycle;

[0066] Step B02) Establishing a heating cost model for a multi-energy complementary heating system, substituting the efficiencies of the gas boiler 30, the heat pump 20, the circulating pump and the blower into the heating cost model;

[0067] Step B03) setting the heating capacity of the multi-energy complementary heating system equal to the heating demand of the next cycle, the optimization target is to obtain the lowest heating cost from the heating cost model, and establishing an optimization algorithm;

[0068] Step B04) executing the optimization algorithm to obtain the loads of the gas boiler 30, the heat pump 20 and the circulation pump when the heating cost is the lowest;

[0069] Step B05) The obtained loads of the gas boiler 30, the heat pump 20 and the circulation pump are used as the control results of the next cycle.

[0070] Please see attached Figure 5 , calculate the average daily outdoor temperature t _WZ The methods include:

[0071] Step C01) collecting the temperatures of multiple outdoor temperature sensors and calculating the temperature average;

[0072] Step C02) collecting detection values ​​of multiple outdoor light intensity sensors and calculating the average light intensity;

[0073] Step C03) generating a temperature correction value according to the light intensity;

[0074] Step C04) The temperature average value and the temperature correction value are superimposed as the outdoor daily average comprehensive temperature t _WZ .

[0075] Among them, the method of generating a temperature correction value according to the light intensity in step C03) includes: when the average light intensity is less than or equal to 10 Lux, the temperature correction value is 0; when the average light intensity is greater than 10 and not greater than 20 Lux, the temperature correction value is +0.5°C; when the average light intensity is greater than 20 and not greater than 30 Lux, the temperature correction value is +1.0°C; when the average light intensity is greater than 30 and not greater than 45 Lux, the temperature correction value is +1.5°C; when the average light intensity is greater than 45 Lux, the temperature correction value is +2°C.

[0076] Set the indoor target comfort temperature. In the first N days of heating, according to the indoor target comfort temperature and the outdoor daily average comprehensive temperature t _WZ Calculate the average daily load Q _D , according to the daily average load Q_D and the installed capacity of the heat pump 20, calculate the load rate of the heat pump 20 when only the heat pump 20 is started, if the load rate of the heat pump 20 exceeds the preset threshold, start the gas boiler 30 and the heat pump 20, if the load rate of the heat pump 20 does not exceed the preset threshold, only start the heat pump 20.

[0077] When the control scheme is generated periodically, the operation data of the gas boiler 30 and the heat pump 20 in the previous cycle are read, and the efficiency of the gas boiler 30 and the heat pump 20 is calculated based on the operation data of the gas boiler 30 and the heat pump 20 in the previous cycle.

[0078] According to the operation data of the gas boiler 30, the heat pump 20 and the circulation pump in the previous cycle, the method for calculating the efficiency of the gas boiler 30, the heat pump 20, the circulation pump and the blower includes:

[0079] Calculate the COP of the heat pump 20 _HP ,

[0080]

[0081] Calculation of the efficiency η of the gas boiler 30 _GAS ,

[0082]

[0083] In the formula, Q _HP is the total heat output of the heating system, E _HE The electricity consumption of the circulating pump, E _HP The electricity consumption for heat pump operation, Q _GAS is the heat output of the gas boiler per unit time, q _GAS is the calorific value of natural gas, G _GAS is the gas consumption of the gas boiler per unit time;

[0084] According to the operating data of the circulation pump in the previous N days, calculate the efficiency η of the water pump _pump ,

[0085]

[0086] Among them, G _pump is the instantaneous flow rate of the circulating pump, and a, b, c are fitting coefficients, which are obtained by fitting the operating data of the circulating pump in the previous N days.

[0087] After N days of heating, in each cycle, according to the operation data of the heat pump 20, it is decided whether to exit the operation of the heat pump 20, specifically including:

[0088] Calculate the cost M when the heat pump 20 provides 1GJ of unit heat _HP ,

[0089]

[0090] According to the efficiency η of the gas boiler 30 in the previous cycle _GAS , calculate the cost M when the gas boiler 30 provides 1GJ of unit heat _GAS ,

[0091]

[0092] Among them, the electricity price is A yuan / kWh, the gas price is B yuan / cubic meter, let M _HP Equal to M _GAS , solve and obtain the COP value, determine whether there is a heat pump 20 unit with an efficiency lower than the calculated COP value in the previous cycle, and shut down the heat pump 20 unit with an efficiency lower than the calculated COP.

[0093] The heating cost model of a multi-energy complementary heating system is established as follows:

[0094]

[0095] Among them, M _Tatal The total cost required to provide the heating demand for the next cycle for the multi-energy complementary heating system, cop i is the efficiency of the i-th heat pump 20, A i The electricity price set for the i-th heat pump 20, is the efficiency of the j-th gas boiler 30, The calorific value of natural gas set for the jth gas boiler 30, B j The gas price set for the jth gas boiler 30, G ε_pump is the instantaneous flow rate of the εth circulating pump, H ε_pump is the head of the εth circulating pump, is the efficiency of the εth circulating pump, G ω_Fan is the air volume of the ωth fan, H ω_Fan is the head of the first fan, is the efficiency of the ωth fan, which is provided by the fan manufacturer. The operation data of all heat pumps 20, gas boilers 30, circulating pumps and fans are substituted into the heating cost model to obtain the total cost required for the multi-energy complementary heating system to provide the heating demand for the next cycle under the current state. The established optimization algorithm is an ant colony search algorithm, a simulated annealing algorithm or a genetic algorithm.

[0096] The beneficial technical effects of this embodiment include: based on the intelligent prediction data of the expert system of the heat production center platform, combined with a comprehensive analysis of factors such as the heat source operating cost and storage margin, to achieve optimal scheduling of multi-energy complementarity and improve the overall efficiency of the multi-energy complementary heating system; through load forecasting, ensure on-demand heating at the user end and ensure the safety of users' heating; based on the optimization algorithm, provide the best control plan to maximize the efficiency of the multi-energy complementary heating system; combine the carbon emissions and operating costs of the energy to perform optimized scheduling, which not only reduces operating costs, but also reduces carbon emissions, and achieves regional optimized scheduling of multiple energy sources.

[0097] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Those skilled in the art should understand that the present invention includes but is not limited to the contents described in the drawings and the above specific embodiments. Any modification that does not deviate from the functional and structural principles of the present invention will be included in the scope of the claims.

Claims

1. An intelligent control method for a multi-energy complementary heating system, characterized in that: include: In the first N days of heating, outdoor temperature data is collected periodically to calculate the outdoor daily average comprehensive temperature t _WZ ; According to the outdoor daily average temperature t _WZ Determine the start and stop of gas boilers and heat pumps; After N days of heating, collect the operating data of the gas boiler, heat pump, circulation pump and blower in the previous N days, and calculate the efficiency of the gas boiler, heat pump, circulation pump and blower; Periodically generate a control plan, the control plan including the start and stop of the gas boiler and the heat pump and the operating load; Methods for periodically generating control plans include: Collect outdoor temperature data and calculate the outdoor daily average comprehensive temperature t _WZ , predict the heating demand in the next cycle; Establish a heating cost model for a multi-energy complementary heating system, and substitute the efficiency of gas boilers, heat pumps, circulation pumps and blowers into the heating cost model; The heating supply of the multi-energy complementary heating system is set to be equal to the heating demand of the next cycle. The optimization goal is to obtain the lowest heating cost from the heating cost model and establish an optimization algorithm. Execute the optimization algorithm to obtain the load of gas boiler, heat pump and circulation pump when the heating cost is the lowest; The obtained loads of the gas boiler, heat pump and circulating pump are used as the control results of the next cycle; Calculate the average daily outdoor temperature t _WZ The methods include: Collect the temperatures of multiple outdoor temperature sensors and calculate the average temperature; Collect the detection values ​​of multiple outdoor light intensity sensors and calculate the average light intensity; Generate temperature correction value according to light intensity; The average temperature and the temperature correction value are superimposed as the outdoor daily average comprehensive temperature t _WZ ; Set the indoor target comfort temperature. In the first N days of heating, according to the indoor target comfort temperature and the outdoor daily average comprehensive temperature t _WZ Calculate the average daily load Q _D , according to the daily average load Q _D and the installed capacity of the heat pump, calculate the heat pump load rate when only the heat pump is started, if the heat pump load rate exceeds the preset threshold, start the gas boiler and the heat pump, if the heat pump load rate does not exceed the preset threshold, only start the heat pump; When periodically generating a control plan, the operation data of the gas boiler and the heat pump in the previous cycle are read, and the efficiency of the gas boiler and the heat pump is calculated based on the operation data of the gas boiler and the heat pump in the previous cycle; Based on the operating data of the gas boiler, heat pump and circulating pump in the previous cycle, the methods for calculating the efficiency of the gas boiler, heat pump, circulating pump and blower include: Calculating the COP of a heat pump _HP , Calculation of the efficiency η of a gas boiler _GAS , In the formula, Q _HP is the total heat output of the heating system, E _HE The electricity consumption of the circulating pump, E _HP The electricity consumption for heat pump operation, Q _GAS is the heat output of the gas boiler per unit time, q _GAS is the calorific value of natural gas, G _GAS is the gas consumption of the gas boiler per unit time; According to the operating data of the circulation pump in the previous N days, calculate the efficiency η of the water pump _pump , Among them, G _pump is the instantaneous flow rate of the circulating pump, a, b, c are fitting coefficients, obtained by fitting the operating data of the circulating pump in the previous N days; After N days of heating, the heat pump operation data is used to determine whether to exit the heat pump operation in each cycle, including: Calculate the cost M of the heat pump providing 1GJ of heat _HP , According to the efficiency η of the gas boiler in the previous cycle _GAS , calculate the cost M when the gas boiler provides 1GJ of unit heat _GAS , Among them, the electricity price is A yuan / kWh, the gas price is B yuan / cubic meter, let M _HP Equal to M _GAS , solve the obtained COP value, determine whether there is a heat pump unit with an efficiency lower than the calculated COP value in the previous cycle, and shut down the heat pump unit with an efficiency lower than the calculated COP; The heating cost model of a multi-energy complementary heating system is established as follows: Among them, M _Tatal The total cost required to provide the heating demand for the next cycle for the multi-energy complementary heating system, cop i is the efficiency of the ith heat pump, A i The electricity price set for the i-th heat pump, is the efficiency of the jth gas boiler, The calorific value of natural gas set for the jth gas boiler, B j The gas price set for the jth gas boiler, G ε_pump is the instantaneous flow rate of the εth circulating pump, H ε_pump is the head of the εth circulating pump, is the efficiency of the εth circulating pump, G ω_Fan is the air volume of the ωth fan, H ω_Fan is the head of the first fan, is the efficiency of the ωth fan, and the efficiency of the fan is provided by the fan manufacturer. The operating data of all heat pumps, gas boilers, circulating pumps and fans are substituted into the heating cost model to obtain the total cost required for the multi-energy complementary heating system to provide the heating demand for the next cycle under the current state.

2. According to claim 1, a multi-energy complementary heating system intelligent control method is characterized in that: Methods for generating temperature correction values ​​based on light intensity include: When the average light intensity is less than or equal to 10 Lux, the temperature correction value is 0. When the average light intensity is greater than 10 and not greater than 20 Lux, the temperature correction value is +0.5°C; when the average light intensity is greater than 20 and not greater than 30 Lux, the temperature correction value is +1.0°C; when the average light intensity is greater than 30 and not greater than 45 Lux, the temperature correction value is +1.5°C; when the average light intensity is greater than 45 Lux, the temperature correction value is +2°C.

3. The intelligent control method for a multi-energy complementary heating system according to any one of claims 1 to 2, characterized in that: The optimization algorithms established are ant colony search algorithm, simulated annealing algorithm or genetic algorithm.

4. The intelligent control method for a multi-energy complementary heating system according to any one of claims 1 to 2, characterized in that: After N days of heating, the cycle for generating the control plan is 1 hour.