A method, system and medium for active power restoration of electric energy meter
By implementing the active power restoration method in the electric energy meter and using circuit breakers and time parameters to optimize the power restoration process, the problem of low power restoration success rate in the existing technology is solved, and the electricity user experience and power restoration success rate are improved. At the same time, energy consumption and network delay impact are reduced.
Patent Information
- Application Number
- CN202210993925.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-18
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2042-08-18
AI Technical Summary
The existing power meter restoration method relies on one-way control instructions and manual processing, resulting in a low power restoration success rate and affecting user production and life. Especially when network signals or equipment fail, power restoration instructions cannot be effectively communicated.
By implementing the active power restoration method in the electric energy meter, the circuit breaker is used to open and close operations, and the power restoration query command is sent regularly based on the time parameter until the power restoration command is received from the management end, and the power restoration is completed or the timeout occurs. The method also includes clustering user categories to optimize outage time-consuming parameters and reduce the impact of network latency and hardware differences.
It improves the success rate of cost-controlled power restoration for power users, reduces the load on the main station, reduces the impact of network delays and hardware differences on power restoration events, improves the user's power experience, and extends battery life by saving energy consumption.
Smart Images

Figure CN115498625B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to electric energy metering technology, and in particular to an active power restoration method, system and medium for an electric energy meter. Background Art
[0002] At present, smart cost-controlled energy meters have been widely installed in thousands of households. The cost-control function of smart meters is mainly composed of marketing systems, electricity information collection systems, collection terminals, communication modules, energy meters and other main bodies. However, due to the current remote control method, which relies too much on one-way control instructions between various entities, when network signals or equipment fail or are abnormal, the power-off and power-restore instructions cannot be sent from the main station to the energy meter, resulting in the user's inability to power off and restore. The impact of unsuccessful power-off instructions is basically limited to the company, while unsuccessful power-on instructions will not only affect the company's related indicators, but may also affect the production and life of users, causing adverse social impacts. The current system processing flow and method for power outage and power restoration under fee control of electric energy meters are as follows: Fee control power outage method and process: The power supply company monitors the user's electricity bill balance status through the marketing system. When the balance is less than 0, a power outage work order will be generated. The work order will be transmitted to the electricity consumption information collection system (hereinafter referred to as the use and collection system) after manual review. The use and collection system transmits instructions to the collection terminal in the user's substation through the power wireless private network. After receiving the instructions, the collection terminal controls the smart fee control electric meter, thereby realizing the remote power outage function of the smart fee control electric energy meter. Fee control power restoration method and process: After the user pays the electricity bill, the marketing system monitors the user's electricity bill balance status. When the balance is greater than 0, a power restoration work order will be generated. The work order will be transmitted to the electricity consumption information collection system (hereinafter referred to as the use and collection system). The use and collection system transmits instructions to the collection terminal in the user's substation through the power wireless private network. After receiving the instructions, the collection terminal controls the smart fee control electric meter, thereby realizing the remote power restoration function of the smart fee control electric energy meter. During this control process, if the marketing system receives feedback that the power restoration is unsuccessful or does not receive feedback, it will send the work order repeatedly. When it is still unsuccessful after multiple repetitions (considering the system load, a maximum of 5 repetitions), the power restoration work order will be forwarded to the power supply company staff, who will restore the power on site. It can be seen that the existing power restoration method mainly relies on the single-phase instruction function of the marketing system and the main station of the user acquisition system. However, since the on-site acquisition terminals, communication modules, electric energy meters and other equipment involve communication methods, communication protocols and software and hardware versions between different hardware, and the on-site environment is complex, the communication situation may be interfered by various factors. Once the automatic work order processing fails, it will be transferred to the manual link, and manual processing will continue to prolong the power restoration time, which will have an adverse impact on the production and life of users. Summary of the invention
[0003] Technical problem to be solved by the present invention: In view of the above-mentioned problems in the prior art, a method, system and medium for active power restoration of an electric energy meter are provided. The present invention can realize active power restoration of the electric energy meter without increasing the hardware cost, and has the advantages of simple implementation method and high success rate of active power restoration.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0005] A method for actively restoring power to an electric energy meter, comprising:
[0006] S101, after receiving the issued power outage instruction, performing a disconnection operation on the built-in circuit breaker;
[0007] S102, based on the set time parameters, periodically sending a power restoration query instruction to the electric energy meter management end until, upon receiving the power restoration instruction returned by the electric energy meter management end, the built-in circuit breaker is closed to complete the power restoration or timeout.
[0008] Optionally, after step S101 and before step S102, the process further includes entering a low power consumption state to save energy; and after power restoration is completed in step S102, the process further includes exiting the low power consumption state.
[0009] Optionally, the power outage instruction issued in step S101 includes a set time parameter, and the step of generating the time parameter by the electric energy meter management terminal includes:
[0010] S201, respectively collecting the time difference between the time when each electric energy meter performs an opening operation and the time when each electric energy meter performs a closing operation as the cost-controlled power outage time;
[0011] S202, clustering the user category labels corresponding to each electric energy meter to obtain N cluster categories, and calculating the average cost-controlled power outage duration of users corresponding to all electric energy meters in each cluster category;
[0012] S203, according to the cluster category corresponding to the user of the electric energy meter to which the power outage instruction needs to be issued, the average fee-controlled power outage duration corresponding to the cluster category is used as the time parameter of the electric energy meter to which the power outage instruction needs to be issued and is packaged into the power outage instruction.
[0013] Optionally, the user category label in step S202 includes some or all of electricity consumption category characteristics, seasonal characteristics, electricity growth rate characteristics, weekend characteristics, user satisfaction characteristics and time period characteristics, the electricity consumption category characteristics include industrial electricity consumption, general industrial and commercial electricity consumption and residential electricity consumption, the seasonal characteristics include high temperature sensitivity, low temperature sensitivity, suitable temperature sensitivity and insensitivity, the electricity growth rate characteristics include sharp decline, decline, remain the same, rise and sharp rise, the sharp decline means that the decline in the specified period exceeds the set threshold, and the sharp rise means that the rise in the specified period exceeds the set threshold, the weekend characteristics include weekend sensitivity, weekday sensitivity and insensitivity, the user satisfaction characteristics include very dissatisfied, dissatisfied, satisfied, very satisfied and very satisfied, and the time period characteristics include daytime sensitivity, night sensitivity and insensitive.
[0014] Optionally, the electric energy meter management terminal includes an electric power marketing system, an electric power information collection system and a collection terminal; the step of issuing the power outage instruction received in step S101 includes:
[0015] S301, the power marketing system generates a fee-controlled power outage list for the electric energy meters whose electricity fee balance is less than the set value, and after the fee-controlled power outage list is reviewed and confirmed, the power outage status of the reviewed and confirmed electric energy meters is set to "power outage" locally, the time parameters corresponding to the electric energy meters are determined and packaged into a power outage instruction, and sent to the next-level electricity consumption information collection system;
[0016] S302, after receiving the power outage instruction, the power consumption information collection system sets the power outage and restoration state of the electric energy meter corresponding to the power outage instruction to "power outage" locally, and sends the power outage instruction to the collection terminal at the next level;
[0017] S303, after receiving the power outage instruction, the data collection terminal sets the local power outage and restoration state of the electric energy meter corresponding to the power outage instruction to "power outage", and sends the power outage instruction to the corresponding electric energy meters respectively.
[0018] Optionally, after the power restoration query instruction is sent in step S103, the power restoration query instruction is processed by the electric energy meter management terminal including:
[0019] S401, after receiving the power-on query instruction, the collection terminal obtains the power-off and power-on status of the electric energy meter corresponding to the power-on query instruction in the local area. If the power-off and power-on status is "power-on", the power-on instruction is sent to the electric energy meter corresponding to the power-on query instruction, and the process ends and exits; otherwise, the power-on query instruction is continued to be sent to the next-level power consumption information collection system, and the process jumps to S402;
[0020] S402, after receiving the power restoration query instruction, the power consumption information collection system obtains the local power-off and power-on status of the electric energy meter corresponding to the power restoration query instruction. If the power-off and power-on status is "power restored", the power restoration instruction is sent to the next-level collection terminal that sent the power restoration query instruction. After receiving the power restoration instruction, the next-level collection terminal that sent the power restoration query instruction sets the local power-off and power-on status of the electric energy meter corresponding to the power restoration instruction to "power restored", and sends the power restoration instruction to the electric energy meter corresponding to the power restoration instruction, and ends and exits; if the power-off and power-on status is "power off", the power restoration query instruction is continued to be sent to the next-level power marketing system, and jumps to S403;
[0021] S403, after receiving the power restoration query instruction, the power marketing system obtains the power-off and power-on status of the electric energy meter corresponding to the power restoration query instruction in the local area. If the power-off and power-on status is "power restored", the power restoration instruction is sent to the next-level power consumption information collection system that sent the power restoration query instruction. After receiving the power restoration instruction, the next-level power consumption information collection system that sent the power restoration query instruction sets the power-off and power-on status of the electric energy meter corresponding to the power restoration instruction to "power restored", and then sends the power restoration instruction to the next-level collection terminal that sent the power restoration query instruction. After receiving the power restoration instruction, the next-level collection terminal that sent the power restoration query instruction sets the power restoration status of the electric energy meter corresponding to the power restoration instruction in the local area to "power restored". The local power outage and restoration status of the electric energy meter corresponding to the instruction is "power restored", and the power restoration instruction is sent to the electric energy meter corresponding to the power restoration instruction, ending and exiting; if the power outage and restoration status is "power outage", the power outage instruction is sent to the next-level electricity consumption information collection system that sends the power restoration query instruction. After receiving the power outage instruction, the next-level electricity consumption information collection system that sends the power restoration query instruction sends the power outage instruction to the next-level collection terminal that sends the power restoration query instruction. After receiving the power outage instruction, the next-level collection terminal that sends the power restoration query instruction sends the power outage instruction to the electric energy meter corresponding to the power outage instruction, so that the electric energy meter keeps the built-in circuit breaker in the disconnected state.
[0022] Optionally, the method further includes the following processing steps of the electric energy meter management terminal for the user's electricity fee payment behavior of the target electric energy meter:
[0023] S501, the power marketing system generates a power-on instruction for the power meter with a power balance greater than 0, sets the power-off status of the power meter generating the power-on instruction to "power-on", and sends the power-on instruction to the next-level power consumption information collection system, and jumps to S502; if the power meter with a power balance greater than 0 is empty, then end and exit;
[0024] S502, after receiving the power restoration instruction, the power consumption information collection system at the next level sets the power outage and restoration state of the electric energy meter corresponding to the power restoration instruction to "power restoration", and sends the power restoration instruction to the collection terminal at the next level, and jumps to S403;
[0025] S503, after receiving the power-on instruction, the data collection terminal at the next level sets the local power-off and power-on status of the electric energy meter corresponding to the power-on instruction to "power-on", and sends the power-on instruction to the electric energy meter corresponding to the power-on instruction.
[0026] Optionally, in the network formed by the power marketing system, power consumption information collection system, collection terminal and power meter of the power meter management end, the power restoration instruction and the power outage instruction have the highest network scheduling priority among the transmitted instructions.
[0027] In addition, the present invention also provides an active power restoration system for an electric energy meter, comprising a microprocessor and a memory connected to each other, wherein the microprocessor is programmed or configured to execute the active power restoration method for the electric energy meter.
[0028] In addition, the present invention also provides a computer-readable storage medium, in which a computer program is stored. The computer program is used to be programmed or configured by a microprocessor to execute the active power restoration method of the electric energy meter.
[0029] Compared with the prior art, the present invention mainly has the following advantages:
[0030] 1. The present invention can actively query the fee-controlled power-off and power-restore status of the electric energy meter by utilizing the data communication and transmission capabilities of the electric energy meter itself, thereby improving the fee-controlled power-on success rate of the electric energy user.
[0031] 2. The present invention makes full use of the existing power collection framework and technology by cyclically executing the power restoration query instructions through the electric energy meter itself. While reducing the load on the main station, it can effectively reduce the impact of network delays, communication methods, communication protocols and software and hardware versions between different hardware on fee control power restoration events, thereby improving the electricity consumption experience of power users. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 The figure is a basic flow chart of a method according to a first embodiment of the present invention.
[0033] Figure 2 This is a multi-role interaction flow chart of the electric energy meter management terminal and the electric energy meter in the second embodiment of the present invention. DETAILED DESCRIPTION
[0034] The present invention is further described below in conjunction with the accompanying drawings and specific preferred embodiments, but the protection scope of the present invention is not limited thereby.
[0035] Embodiment 1:
[0036] like Figure 1 As shown, the active power restoration method of the electric energy meter in this embodiment includes:
[0037] S101, after receiving the issued power outage instruction, performing a disconnection operation on the built-in circuit breaker;
[0038] S102, based on the set time parameters, regularly send the power restoration query instruction to the electric energy meter management end until the built-in circuit breaker is closed to complete the power restoration or timeout when the power restoration instruction returned by the electric energy meter management end is received. If a power outage instruction is received, or no feedback is received, it is determined that the power restoration instruction returned by the electric energy meter management end has not been received, and the power restoration query instruction is continuously sent regularly (cyclically) until the built-in circuit breaker is closed to complete the power restoration or timeout when the power restoration instruction returned by the electric energy meter management end is received.
[0039] The method of this embodiment can actively query the fee-controlled power-off and power-on status of the electric energy meter by utilizing the data communication and transmission capabilities of the electric energy meter itself, thereby improving the success rate of fee-controlled power-on restoration for electric energy users; and the method of this embodiment can cyclically execute the power-on restoration query instruction through the electric energy meter itself, while reducing the load on the main station, it can effectively reduce the impact of network delays, communication methods and communication protocols between different hardware, and software and hardware versions on fee-controlled power-on events, thereby improving the power consumption experience of electric energy users.
[0040] In order to improve the success rate of power restoration for users who have been paying for a long time, this embodiment also includes entering a low power consumption state to save energy after step S101 and before step S102; and also includes exiting the low power consumption state after completing the power restoration in step S102. Through the above method, the energy consumption of the electric energy meter during the power outage can be reduced, especially for battery-powered electric energy meters, the service life of the battery can be effectively extended, thereby improving the success rate of power restoration for users who have been paying for a long time.
[0041] As an optional implementation, all electric energy meters may use the same set time parameters. The advantage of this method is that the judgment is relatively simple, and it is only necessary to write the time parameters into the electric energy meters when the electric energy meters are initialized at the factory.
[0042] However, considering that the regular sending of restoration query instructions by the power meter management end is the main way of consuming energy for the power meter during a power outage, how to accurately and independently control the time parameters of each power meter is a key factor in reducing energy consumption, improving the success rate of restoration, and improving the response time of restoration. Moreover, based on the electricity users' electricity usage habits, differentiated customization of the query interval time (time parameters) of the electricity meter itself is also conducive to realizing differentiated service concepts for electricity users. Therefore, as a more optimal implementation method, this embodiment intelligently adjusts the active restoration interval time (time parameters) according to the user's historical electricity usage habits, so as to effectively improve the electricity user's electricity usage experience. Specifically, the power outage instruction issued in step S101 includes the set time parameters, and the steps for the power meter management end to generate the time parameters include:
[0043] S201, respectively collecting the time difference between the time when each electric energy meter performs an opening operation and the time when each electric energy meter performs a closing operation as the cost-controlled power outage time;
[0044] S202, clustering the user category labels corresponding to each electric energy meter to obtain N cluster categories, and calculating the average cost-controlled power outage duration of users corresponding to all electric energy meters in each cluster category;
[0045] S203, according to the cluster category corresponding to the user of the electric energy meter to which the power outage instruction needs to be issued, the average fee-controlled power outage duration corresponding to the cluster category is used as the time parameter of the electric energy meter to which the power outage instruction needs to be issued and is packaged into the power outage instruction.
[0046] It should be noted that the timeout in step S102 means that the total power outage time exceeds time T1, and manual on-site power restoration operation is required after time T1 exceeds time T1. The time T1 is similar to the time parameter and can be a fixed value or a command set value.
[0047] In this embodiment, the user category labels in step S202 include six user category labels, namely, electricity category characteristics, seasonal characteristics, electricity growth rate characteristics, weekend characteristics, user satisfaction characteristics, and time period characteristics. Each label has multiple attributes. Under different categories and attributes, users have different tolerances for power restoration time. In addition, in the case of tolerance for degradation, part of the above user category labels can also be used. Electricity category characteristics, which are natural attributes, have different electricity demands for different types of users, and have a total of 3 attributes. Seasonal characteristics, because different users have different electricity demands in different seasons, users are divided into 4 types according to the changes in user electricity in different seasons. Electricity growth rate characteristics, according to the change trend of the user's electricity in the past month, users are divided into 5 types. Weekend characteristics, according to the average daily electricity consumption of the user on weekends and the average daily electricity consumption on weekdays in the past 3 months, users are divided into 3 types. User satisfaction characteristics, according to the user's consultation, complaint, and reply in the past year, users are divided into 5 types. Time period characteristics, according to the user's electricity consumption during the daytime and nighttime in the past month, users are divided into 2 types. In this embodiment, the user category labels of n users are standardized to generate n d-dimensional data matrices X, whose function expression is:
[0048]
[0049] Among them, dimension d is the total number of attribute data of six user category labels, x 11 ~x 1d is the d-dimensional attribute data of the first user, x n1 ~x ndis the d-dimensional attribute data of the nth user. As an optional implementation, in this embodiment, the electricity consumption category characteristics include industrial electricity consumption, general industrial and commercial electricity consumption, and residential electricity consumption. The seasonal characteristics include high temperature sensitivity, low temperature sensitivity, suitable temperature sensitivity, and insensitivity. The electricity growth rate characteristics include a sharp drop, a drop, a flat, an increase, and a sharp increase. The sharp drop means that the drop in the specified period exceeds the set threshold, and the sharp increase means that the increase in the specified period exceeds the set threshold. The weekly holiday characteristics include weekend sensitivity, weekday sensitivity, and insensitivity. The user satisfaction characteristics include very dissatisfied, dissatisfied, satisfied, very satisfied, and very satisfied. The time period characteristics include daytime sensitivity, night sensitivity, and insensitivity, as shown in Table 1.
[0050] Table 1: Electricity consumption category characteristics and their attributes.
[0051]
[0052] In this embodiment, the Kmeans clustering algorithm is specifically used for clustering. The number of clusters is initially set to C=5, and the silhouette coefficient is calculated according to the clustering result. The silhouette coefficient formula is:
[0053]
[0054] In the above formula, S(i) represents the silhouette coefficient, a(i) represents the average distance from vector i to other points in the cluster to which it belongs, and b(i) represents the average distance from vector i to all points in other clusters. By accumulating the values of C in sequence, the C value that makes the silhouette coefficient S(i) closest to 1 is finally obtained, and it is determined as the number of clusters. For N clustering categories, the average cost-controlled power outage time of users corresponding to all electricity meters under each clustering category is calculated respectively, and sorted by size, and the average cost-controlled power outage time of N groups can be obtained, which are named T1 (shortest time), T2,…,T N (longest time), and according to the category of each user, synchronously update the average cost control and power restoration time parameter T. Undoubtedly, considering that the generation of the time parameter by the above-mentioned electric energy meter management end requires a certain amount of time, in order to reduce the waiting time of power outage and power restoration for users, a timed execution method can generally be adopted. Each time the step of generating time parameters by the electric energy meter management end is executed, the average cost control and power restoration time parameter T is synchronously updated according to the category of each user, so that it can be directly used when the power outage instruction is issued, reducing the waiting time.
[0055] It should be noted that the energy meter management terminal is the management system of the energy meter, which generally has the basic functions of power consumption information collection and power outage management, and can also add related management functions such as energy meter status management and fault management as needed. As an optional implementation, the energy meter management terminal in this embodiment is a single computer device.
[0056] In addition, the present embodiment further provides an active power restoration system for an electric energy meter, comprising a microprocessor and a memory connected to each other, wherein the microprocessor is programmed or configured to execute the active power restoration method for the electric energy meter. In addition, the present embodiment further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, wherein the computer program is used to be programmed or configured by the microprocessor to execute the active power restoration method for the electric energy meter.
[0057] Embodiment 2:
[0058] This embodiment is basically the same as the first embodiment, and the main difference is that the configuration of the electric energy meter management terminal in this embodiment is different. Figure 2 As an optional implementation method, the electric energy meter management terminal in this embodiment includes a power marketing system, a power consumption information collection system and a collection terminal, and realizes the comprehensive management of the electric energy meter through multi-level nodes.
[0059] like Figure 2 As shown, the steps of issuing the power outage instruction received in step S101 include:
[0060] S301, the power marketing system generates a fee-controlled power outage list for the electric energy meters whose electricity fee balance is less than the set value, and after the fee-controlled power outage list is reviewed and confirmed, the power outage status of the reviewed and confirmed electric energy meters is set to "power outage" locally, the time parameters corresponding to the electric energy meters are determined and packaged into a power outage instruction, and sent to the next-level electricity consumption information collection system;
[0061] S302, after receiving the power outage instruction, the power consumption information collection system sets the power outage and restoration state of the electric energy meter corresponding to the power outage instruction to "power outage" locally, and sends the power outage instruction to the collection terminal at the next level;
[0062] S303, after receiving the power outage instruction, the data collection terminal sets the local power outage and restoration state of the electric energy meter corresponding to the power outage instruction to "power outage", and sends the power outage instruction to the corresponding electric energy meters respectively.
[0063] In this embodiment, the review of the fee-controlled power outage list in step S301 is performed manually. In addition, it can also be reviewed automatically by a program. The automatic review by a program generally uses different data sources such as user payment data of the electricity meter for review, which is essentially equivalent to recalculating the electricity bill balance to avoid errors in the electricity bill balance and cause accidental power outages.
[0064] In step S301, "the electric energy meter with a balance less than the set value" generally refers to the electric energy meter with a balance less than 0. However, considering the user's credit or the user's deposit, the set value can also be a value not equal to 0. Moreover, the set value can be the same for all users or can be set independently for different users.
[0065] Considering that the power marketing system, the power information collection system and the collection terminal are in a tree structure, that is, one power marketing system corresponds to multiple power information collection systems, one power information collection system corresponds to multiple collection terminals, and one collection terminal corresponds to multiple electric energy meters, therefore, as an optional implementation method, when issuing a power outage instruction in steps S301 to S303, the power information collection system and the collection terminal delete the instruction data (electricity meter, time parameter, cluster category to which the user belongs) of the electric energy meter not included in the power outage instruction according to the electric energy meter included in the next level, thereby reducing the effective load of the issued power outage instruction and improving the success rate of power restoration. It should be noted that the power outage instruction issued in steps S301 to S303 refers to the instruction that the corresponding electric energy meter needs to perform the power outage operation, which can have different titles or names, such as power outage work order, power outage message, power outage command, etc., and the required format or form can also be formulated according to needs. However, its specific title or name, format or form should not constitute a reliance on the transmission of instructions between the power marketing system, the power consumption information collection system and the collection terminal that require the corresponding electric energy meter to perform a power outage operation.
[0066] like Figure 2 As shown, after the power restoration query instruction is sent in step S103, the power restoration query instruction is processed by the electric energy meter management terminal including:
[0067] S401, after receiving the power-on query instruction, the collection terminal obtains the power-off and power-on status of the electric energy meter corresponding to the power-on query instruction in the local area. If the power-off and power-on status is "power-on", the power-on instruction is sent to the electric energy meter corresponding to the power-on query instruction, and the process ends and exits; otherwise, the power-on query instruction is continued to be sent to the next-level power consumption information collection system, and the process jumps to S402;
[0068] S402, after receiving the power restoration query instruction, the power consumption information collection system obtains the local power-off and power-on status of the electric energy meter corresponding to the power restoration query instruction. If the power-off and power-on status is "power restored", the power restoration instruction is sent to the next-level collection terminal that sent the power restoration query instruction. After receiving the power restoration instruction, the next-level collection terminal that sent the power restoration query instruction sets the local power-off and power-on status of the electric energy meter corresponding to the power restoration instruction to "power restored", and sends the power restoration instruction to the electric energy meter corresponding to the power restoration instruction, and ends and exits; if the power-off and power-on status is "power off", the power restoration query instruction is continued to be sent to the next-level power marketing system, and jumps to S403;
[0069] S403, after receiving the power restoration query instruction, the power marketing system obtains the power-off and power-on status of the electric energy meter corresponding to the power restoration query instruction in the local area. If the power-off and power-on status is "power restored", the power restoration instruction is sent to the next-level power consumption information collection system that sent the power restoration query instruction. After receiving the power restoration instruction, the next-level power consumption information collection system that sent the power restoration query instruction sets the power-off and power-on status of the electric energy meter corresponding to the power restoration instruction to "power restored", and then sends the power restoration instruction to the next-level collection terminal that sent the power restoration query instruction. After receiving the power restoration instruction, the next-level collection terminal that sent the power restoration query instruction sets the power restoration status of the electric energy meter corresponding to the power restoration instruction in the local area to "power restored". The local power outage and restoration status of the electric energy meter corresponding to the instruction is "power restored", and the power restoration instruction is sent to the electric energy meter corresponding to the power restoration instruction, ending and exiting; if the power outage and restoration status is "power outage", the power outage instruction is sent to the next-level electricity consumption information collection system that sends the power restoration query instruction. After receiving the power outage instruction, the next-level electricity consumption information collection system that sends the power restoration query instruction sends the power outage instruction to the next-level collection terminal that sends the power restoration query instruction. After receiving the power outage instruction, the next-level collection terminal that sends the power restoration query instruction sends the power outage instruction to the electric energy meter corresponding to the power outage instruction, so that the electric energy meter keeps the built-in circuit breaker in the disconnected state.
[0070] like Figure 2 As shown, this embodiment also includes the following processing steps of the electric energy meter management terminal for the user's electricity fee payment behavior of the target electric energy meter:
[0071] S501, the power marketing system generates a power-on instruction for the power meter with a power balance greater than 0, sets the power-off status of the power meter generating the power-on instruction to "power-on", and sends the power-on instruction to the next-level power consumption information collection system, and jumps to S502; if the power meter with a power balance greater than 0 is empty, then end and exit;
[0072] S502, after receiving the power restoration instruction, the power consumption information collection system at the next level sets the power outage and restoration state of the electric energy meter corresponding to the power restoration instruction to "power restoration", and sends the power restoration instruction to the collection terminal at the next level, and jumps to S403;
[0073] S503, after receiving the power-on instruction, the data collection terminal at the next level sets the local power-off and power-on status of the electric energy meter corresponding to the power-on instruction to "power-on", and sends the power-on instruction to the electric energy meter corresponding to the power-on instruction.
[0074] As an optional implementation, after step S501, the power marketing system also includes determining whether the power restoration of the electric energy meter is successful through information actively collected or actively reported by the electric energy meter. If the power restoration of the electric energy meter is unsuccessful, the number of unsuccessful power restoration attempts is increased by 1. If the number of unsuccessful power restoration attempts is less than a preset threshold value n1, step S501 is jumped again after a period of time T2. Otherwise, it is determined that the power restoration has failed, and the system is transferred to the manual processing link to manually restore the power on site.
[0075] In addition, the present embodiment further provides an active power restoration system for an electric energy meter, comprising a microprocessor and a memory connected to each other, wherein the microprocessor is programmed or configured to execute the active power restoration method for the electric energy meter. In addition, the present embodiment further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, wherein the computer program is used to be programmed or configured by the microprocessor to execute the active power restoration method for the electric energy meter.
[0076] Embodiment three:
[0077] This embodiment is a further improvement on the second embodiment.
[0078] In this embodiment, in the network composed of the power marketing system, electricity consumption information collection system, collection terminal and power meter at the power meter management end, the power restoration instruction and power outage instruction have the highest network scheduling priority among the transmitted instructions. By redefining the instruction priority, it is possible to give priority to power outage and restoration related instructions when the channel is more congested, thereby improving the success rate of power outage and restoration.
[0079] Specifically, in the network composed of the power marketing system, electricity consumption information collection system, collection terminal and electric energy meter of this embodiment, in the process of transmitting power outage and restoration information, various other information and instructions in the channel also need to be transmitted. Due to the limited channel transmission capacity, in order to transmit various information and instructions in an orderly manner as much as possible, all different types of information and instructions are arranged according to priority. The priority order is as follows. When the channel is congested, the instructions are transmitted in the order of priority from high to low (level 1 is the highest and level 6 is the lowest) shown in Table 2. When there are multiple electric energy meter restoration query instructions, they are transmitted in sequence according to the priority order shown in Table 3 (level 2.1 is the highest in level 2, and level 2.n is the lowest in level 2). If it is information or instructions with the same priority, the information is transmitted according to the FIFO principle.
[0080] Table 2: Priority table of different instructions.
[0081]
[0082]
[0083] Table 3: Priority ranking table of power recovery query instructions for different electric energy meters.
[0084] Message Type Priority Power meter 1 power query instruction A1 2.1 Power meter 2 power query instruction A2 2.2 … … The power query command An of the electric energy meter n 2.n
[0085] In addition, the present embodiment further provides an active power restoration system for an electric energy meter, comprising a microprocessor and a memory connected to each other, wherein the microprocessor is programmed or configured to execute the active power restoration method for the electric energy meter. In addition, the present embodiment further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, wherein the computer program is used to be programmed or configured by the microprocessor to execute the active power restoration method for the electric energy meter.
[0086] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present application may take the form of a computer program product implemented on one or more computer-readable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes. The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, may be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the functions in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 These computer program instructions can also be stored in a computer-readable memory that can guide a computer or other programmable data processing device to work in a specific way, so that the instructions stored in the computer-readable memory produce a product including an instruction device, which implements the functions specified in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 These computer program instructions can also be loaded onto a computer or other programmable data processing device, so that a series of operation steps are executed on the computer or other programmable device to produce a computer-implemented process, so that the instructions executed on the computer or other programmable device provide for implementing the process in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0087] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.
Claims
1. A method for actively restoring power to an electric energy meter, characterized in that: include: S101, after receiving the issued power outage instruction, performing a disconnection operation on the built-in circuit breaker; S102, sending a power restoration query instruction to the electric energy meter management terminal at a fixed time based on the set time parameters, until the built-in circuit breaker is closed to complete the power restoration or timeout when the power restoration instruction returned by the electric energy meter management terminal is received; The power outage instruction issued in step S101 includes a set time parameter, and the step of generating the time parameter by the electric energy meter management terminal includes: S201, respectively collecting the time difference between the time when each electric energy meter performs an opening operation and the time when each electric energy meter performs a closing operation as the cost-controlled power outage time; S202, clustering the user category labels corresponding to each electric energy meter to obtain N cluster categories, and calculating the average cost-controlled power outage duration of users corresponding to all electric energy meters in each cluster category; S203, according to the cluster category corresponding to the user of the electric energy meter to which the power outage instruction needs to be issued, the average fee-controlled power outage time corresponding to the cluster category is used as the time parameter of the electric energy meter to which the power outage instruction needs to be issued and is packaged into the power outage instruction; The electric energy meter management terminal includes an electric power marketing system, an electric power information collection system and a collection terminal; the steps of issuing the power outage instruction received in step S101 include: S301, the power marketing system generates a fee-controlled power outage list for the electric energy meters whose electricity fee balance is less than the set value, and after the fee-controlled power outage list is reviewed and confirmed, the power outage status of the reviewed and confirmed electric energy meters is set to "power outage" locally, the time parameters corresponding to the electric energy meters are determined and packaged into a power outage instruction, and sent to the next level of electricity consumption information collection system; S302, after receiving the power outage instruction, the power consumption information collection system sets the power outage and restoration state of the electric energy meter corresponding to the power outage instruction to "power outage" locally, and sends the power outage instruction to the collection terminal at the next level; S303, after receiving the power outage instruction, the acquisition terminal sets the local power outage and restoration state of the electric energy meter corresponding to the power outage instruction to "power outage", and sends the power outage instruction to the corresponding electric energy meter respectively.
2. The method for active power restoration of electric energy meter according to claim 1, characterized in that: After step S101 and before step S102, the process also includes entering a low power consumption state to save energy; after power restoration is completed in step S102, the process also includes exiting the low power consumption state.
3. The method for active power restoration of electric energy meter according to claim 1, characterized in that: The user category label in step S202 includes some or all of the electricity consumption category characteristics, seasonal characteristics, electricity growth rate characteristics, weekend characteristics, user satisfaction characteristics and time period characteristics. The electricity consumption category characteristics include industrial electricity, general industrial and commercial electricity and residential electricity. The seasonal characteristics include high temperature sensitivity, low temperature sensitivity, suitable temperature sensitivity and insensitivity. The electricity growth rate characteristics include sharp decline, decline, remain the same, rise and sharp rise. The sharp decline means that the decline in the specified period exceeds the set threshold, and the sharp rise means that the rise in the specified period exceeds the set threshold. The weekend characteristics include weekend sensitivity, weekday sensitivity and insensitivity. The user satisfaction characteristics include very dissatisfied, dissatisfied, satisfied, very satisfied and very satisfied. The time period characteristics include daytime sensitivity, night sensitivity and insensitive.
4. The method for active power restoration of electric energy meter according to claim 1, characterized in that: After the power restoration query instruction is sent in step S103, the power restoration query instruction is processed by the electric energy meter management terminal including: S401, after receiving the power-on query instruction, the collection terminal obtains the power-off and power-on status of the electric energy meter corresponding to the power-on query instruction in the local area. If the power-off and power-on status is "power-on", the power-on instruction is sent to the electric energy meter corresponding to the power-on query instruction, and the process ends and exits; otherwise, the power-on query instruction is continued to be sent to the next-level power consumption information collection system, and the process jumps to S402; S402, after receiving the power restoration query instruction, the power consumption information collection system obtains the local power-off and power-on status of the electric energy meter corresponding to the power restoration query instruction. If the power-off and power-on status is "power restored", the power restoration instruction is sent to the next-level collection terminal that sent the power restoration query instruction. After receiving the power restoration instruction, the next-level collection terminal that sent the power restoration query instruction sets the local power-off and power-on status of the electric energy meter corresponding to the power restoration instruction to "power restored", and sends the power restoration instruction to the electric energy meter corresponding to the power restoration instruction, and ends and exits; if the power-off and power-on status is "power off", the power restoration query instruction is continued to be sent to the next-level power marketing system, and jumps to S403; S403, after receiving the power restoration query instruction, the power marketing system obtains the local power outage and restoration status of the electric energy meter corresponding to the power restoration query instruction. If the power outage and restoration status is "power restored", the power restoration instruction is sent to the next level power consumption information collection system that sent the power restoration query instruction. After receiving the power restoration instruction, the next level power consumption information collection system that sent the power restoration query instruction sets the local power outage and restoration status of the electric energy meter corresponding to the power restoration instruction to "power restored", and then sends the power restoration instruction to the next level collection terminal that sent the power restoration query instruction. After receiving the power restoration instruction, the next level collection terminal that sent the power restoration query instruction sets the power restoration status of the electric energy meter corresponding to the power restoration instruction to "power restored". The local power outage and restoration status of the electric energy meter corresponding to the instruction is "power restored", and the power restoration instruction is sent to the electric energy meter corresponding to the power restoration instruction, ending and exiting; if the power outage and restoration status is "power outage", the power outage instruction is sent to the next-level electricity consumption information collection system that sends the power restoration query instruction. After receiving the power outage instruction, the next-level electricity consumption information collection system that sends the power restoration query instruction sends the power outage instruction to the next-level collection terminal that sends the power restoration query instruction. After receiving the power outage instruction, the next-level collection terminal that sends the power restoration query instruction sends the power outage instruction to the electric energy meter corresponding to the power outage instruction, so that the electric energy meter keeps the built-in circuit breaker in the disconnected state.
5. The method for active power restoration of electric energy meter according to claim 4, characterized in that: The electric energy meter management terminal also includes the following processing steps for the user's electricity fee payment behavior of the target electric energy meter: S501, the power marketing system generates a power-on instruction for the power meter with a balance greater than 0, sets the power-off status of the power meter generating the power-on instruction to "power-on", and sends the power-on instruction to the next-level power consumption information collection system, and jumps to S502; if the power meter with a balance greater than 0 is empty, then end and exit; S502, after receiving the power restoration instruction, the power consumption information collection system at the next level sets the power outage and restoration state of the electric energy meter corresponding to the power restoration instruction to "power restoration" in the local area, and sends the power restoration instruction to the collection terminal at the next level, and jumps to S403; S503, after receiving the power-on instruction, the acquisition terminal at the next level sets the local power-off and power-on status of the electric energy meter corresponding to the power-on instruction to "power-on", and sends the power-on instruction to the electric energy meter corresponding to the power-on instruction.
6. The method for active power restoration of electric energy meter according to claim 5, characterized in that: In the network formed by the power marketing system, power consumption information collection system, collection terminal and power meter of the power meter management end, the power restoration instruction and the power outage instruction have the highest network scheduling priority among the transmitted instructions.
7. An active power restoration system for an electric energy meter, comprising a microprocessor and a memory connected to each other, characterized in that: The microprocessor is programmed or configured to execute the active power restoration method for an electric energy meter as described in any one of claims 1 to 6.
8. A computer-readable storage medium having a computer program stored therein, characterized in that: The computer program is used to be programmed or configured by a microprocessor to execute the active power restoration method for an electric energy meter as claimed in any one of claims 1 to 6.
Citation Information
Patent Citations
Method and device for reporting power failure event of power utilization information acquisition terminal
CN110212645A
Power failure auxiliary device with remote cost control function
CN114744752A