A fully assembled shear wall beam, slab and column high-strength bolt connection system and construction method
Through the fully-assembled shear wall beam slab column high-strength bolt connection system, the existing prefabricated concrete structure system is solved, and the problems of incomplete assembly and cast-in-place connection of nodes are realized, fully-assembled connection of the structure is simplified, process improvement, quality saving and construction period.
Patent Information
- Application Number
- CN202211184826.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-27
- Publication Date
- 2025-04-22
- Estimated Expiration
- 2042-09-27
AI Technical Summary
The existing prefabricated concrete structures have problems such as incomplete assembly of the system, cast-in-place connection of nodes, complex processes, many node quality problems and long cycles.
A fully-assembled shear wall beam, slab column high-strength bolt connection system is adopted. By pre-production of assembled components in the factory and high-strength bolts are used to connect assembled shear wall, beam, slab and column on site, the fully-assembled connection of the structure is achieved.
The factory pre-production and on-site lifting and installation of structural components have been realized, the process has been simplified, the node quality has been improved, a large amount of construction period has been saved, and cracked and insufficient strength in on-site concrete pouring has been avoided, and a true full-prefabricated connection of concrete structures has been realized.
Smart Images

Figure CN115559412B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of structural engineering, and in particular to a fully assembled shear wall beam, slab and column high-strength bolt connection system and a construction method. Background Art
[0002] As a pillar industry in my country, the construction industry has made important contributions to my country's economic development. However, traditional wet construction has always had problems such as long construction period, low efficiency and high pollution. In recent years, with the country's proposal of the concept of green development, the traditional construction industry has considered the combination of economic development and environmental protection. Prefabricated buildings refer to buildings that are prefabricated in part or in their entirety in a factory and then transported to the construction site and assembled into a whole using effective connection methods. Because prefabricated buildings can be prefabricated in factories, they have the advantages of high industrialization, high construction efficiency and low pollution, meeting the development needs of "Green China" at this stage.
[0003] However, the existing prefabricated concrete structures have the following shortcomings: 1. The system is not fully assembled, with some structural components assembled and some cast-in-place; 2. The nodes are partially cast-in-place, and the traditional prefabricated system node connection is connected by steel sleeves, and the formwork is set up and concrete is poured on site for node connection; 3. The process is complicated, and traditional cast-in-place components such as beams and floor slabs also need to use traditional steel bars, formworks, concrete, maintenance, and demolding methods, which are complicated; 4. There are many node quality problems, and the components are connected by cast-in-place concrete, which is prone to concrete quality problems; 5. The cycle is long, and it takes a lot of time to set up scaffolding, support formwork, tie steel bars to support formwork, increase concrete strength, and remove scaffolding and formwork. These shortcomings need to be solved urgently to meet the current demand for the rapid development of prefabrication. Summary of the invention
[0004] The purpose of the present invention is to solve the following shortcomings in the prior art: 1. Incomplete system assembly, with some structural members assembled and some members cast in place; 2. Part of the nodes are cast in place, and the nodes of the traditional assembled system are connected by steel sleeves, and the formwork is set up and concrete is poured on site for node connection; 3. The process is complicated, and traditional cast-in-place components such as beams, floor slabs and other components also need to use traditional steel bars, formworks, concrete, maintenance, and demolding, and the process is complicated; 4. There are many node quality problems, and the components are connected by cast-in-place concrete, and concrete quality problems are prone to occur; 5. The cycle is long, and it takes a lot of time to set up scaffolding, support formwork, tie steel bars to support formwork, increase concrete strength, and dismantle scaffolding and formwork. A fully assembled shear wall beam, slab and column high-strength bolt connection system and construction method are proposed.
[0005] In order to achieve the above object, the present invention adopts the following technical solutions:
[0006] A fully assembled shear wall beam-slab-column high-strength bolt connection system comprises a bottom plate, an assembled shear wall and an assembled concrete column, wherein an assembled column embedded T-shaped connector is installed on one side of the assembled concrete column, and a shear wall embedded T-shaped column connector is installed on one side of the assembled shear wall, wherein the shear wall embedded T-shaped column connector is connected to the assembled column embedded T-shaped connector by high-strength bolts;
[0007] The bottom plate is provided with a bottom plate embedded T-shaped connector, and the bottom plate embedded T-shaped connector is connected to the assembled shear wall through high-strength bolts. The upper surface of the assembled shear wall is provided with a shear wall embedded beam T-shaped connector, and an assembled T-shaped beam is provided above the assembled shear wall, and the assembled T-shaped beam is installed with an assembled beam and shear wall embedded T-shaped connector.
[0008] Preferably, the upper surface of the prefabricated T-beam is installed with a prefabricated beam and shear wall T-shaped connector, both sides of the prefabricated T-beam are provided with prefabricated floor slabs, the two prefabricated floor slabs are symmetrically arranged, and one side of the prefabricated T-beam is installed with a prefabricated beam and column embedded T-shaped connector.
[0009] Preferably, a pre-buried T-shaped connector of the pre-assembled floor slab is installed on one side of each of the pre-assembled floor slabs, and each of the pre-buried T-shaped connector of the pre-assembled floor slab is connected to the pre-assembled T-shaped beam via high-strength bolts.
[0010] Preferably, an assembled upper column is arranged above the assembled concrete column, and upper and lower column pre-embedded H-shaped connecting pieces are arranged on the upper surface of the assembled concrete column, and the upper and lower column pre-embedded H-shaped connecting pieces are connected to the assembled upper column by high-strength bolts.
[0011] Preferably, a beam pre-embedded T-shaped connector is provided on one side of the prefabricated concrete column, and the beam pre-embedded T-shaped connector is connected to the prefabricated T-shaped beam through high-strength bolts.
[0012] Preferably, a fixing plate is installed on the assembled concrete column, a plurality of round rods are slidably connected to the fixing plate, the round rods are clamped with the pre-buried T-shaped connectors of the assembly column, and the plurality of round rods are connected by a rectangular plate.
[0013] Preferably, a rectangular rod is fixedly connected to the rectangular plate, the rectangular rod and the fixed plate are slidably connected, and one end of the rectangular rod is fixedly connected to a limiting block.
[0014] Preferably, the fixed plate is slidably connected to a moving rod, the moving rod is clamped with the rectangular rod, one end of the moving rod is fixedly connected to a moving block, and the moving block is connected to the fixed plate via a screw.
[0015] A fully assembled shear wall beam-slab-column high-strength bolt connection system, and a construction method thereof, comprising the following steps:
[0016] S1: Connect the prefabricated column with the pre-buried anchor bolts of the foundation and fix the column after correction;
[0017] S2: Connect the pre-buried connectors of the assembled shear wall with the pre-buried connectors of the base plate and column through high-strength bolts;
[0018] S3: Connect the prefabricated beam embedded parts with the columns and shear wall embedded parts through high-strength bolts;
[0019] S4: Connect the prefabricated T-shaped floor slab embedded parts and the beam embedded parts with high-strength bolts;
[0020] S5: Strip panels, strip panels and T-shaped floor panels are spliced by embedded parts;
[0021] S6: Connect the upper assembly column and the lower assembly column with high-strength bolts;
[0022] S7: Install shear walls, beams and slabs to carry out prefabricated installation of the new floor slab;
[0023] S8: The installation is completed until the top layer is assembled.
[0024] Compared with the prior art, the present invention has the following beneficial effects:
[0025] 1. The fully assembled shear wall beam, slab and column high-strength bolt connection system realizes the pre-production of all structural components in the factory, and on-site hoisting and installation, which improves the traditional system of partial assembly and partial cast-in-place components;
[0026] 2. High-strength bolt connection replaces the traditional prefabricated system, the node connection is connected by steel sleeve, and the formwork is supported and concrete is poured;
[0027] 3. High-strength bolt connection is fast, efficient and high-strength. Compared with traditional methods, it saves a lot of construction time, realizes full assembly of components on-site, avoids common problems such as cracking and insufficient strength of on-site concrete pouring, and improves quality;
[0028] 4. It realizes the fully assembled connection of concrete structure in the true sense. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 A schematic diagram of the arrangement of the bottom plate embedded parts of a fully assembled shear wall beam, plate and column high-strength bolt connection system proposed by the present invention;
[0030] Figure 2 This is a schematic diagram of the installation of an assembly column of a fully assembled shear wall beam-slab-column high-strength bolt connection system proposed by the present invention;
[0031] Figure 3A schematic diagram of the installation of an assembled shear wall of a fully assembled shear wall beam, slab and column high-strength bolt connection system proposed by the present invention;
[0032] Figure 4 A schematic diagram of the installation of an assembled beam of a fully assembled shear wall beam-slab-column high-strength bolt connection system proposed by the present invention;
[0033] Figure 5 A schematic diagram of the installation of an assembled floor slab of a fully assembled shear wall beam-slab-column high-strength bolt connection system proposed by the present invention;
[0034] Figure 6 This is a schematic diagram of the installation of the upper assembly column of a fully assembled shear wall beam-slab-column high-strength bolt connection system proposed by the present invention;
[0035] Figure 7 A schematic diagram of the side structure of an assembled concrete column of a fully assembled shear wall beam-slab-column high-strength bolt connection system proposed by the present invention;
[0036] Figure 8 It is a schematic diagram of the partial structure of the rectangular rod and the limit block;
[0037] Fig. 9 The present invention provides a flow chart of a connection method for a fully assembled shear wall beam, slab and column high-strength bolt connection system.
[0038] In the figure: 1 bottom plate, 2 bottom plate embedded T-type connector, 3 assembled concrete column, 4 assembled column embedded T-type connector, 5 beam embedded T-type connector, 6 upper and lower column embedded H-type connector, 7 high-strength bolts, 8 assembled shear wall, 9 shear wall embedded T-type column connector, 10 shear wall embedded beam T-type connector, 11 assembled beam and shear wall embedded T-type connector, 12 assembled beam and column embedded T-type connector, 13 assembled T-type beam, 14 assembled beam and shear wall T-type connector, 15 assembled floor slab embedded T-type connector, 16 assembled floor slab, 17 assembled upper column, 18 rectangular plate, 19 fixed plate, 20 round rod, 21 moving block, 22 screw, 23 moving rod, 24 rectangular rod, 25 limit block. DETAILED DESCRIPTION
[0039] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0040] Reference Figure 1-9A fully assembled shear wall beam-slab-column high-strength bolt connection system comprises a base plate 1, an assembled shear wall 8 and an assembled concrete column 3, wherein an assembled column embedded T-type connector 4 is installed on one side of the assembled concrete column 3, a shear wall embedded T-type column connector 9 is installed on one side of the assembled shear wall 8, the shear wall embedded T-type column connector 9 is connected to the assembled column embedded T-type connector 4 through high-strength bolts 7, a base plate embedded T-type connector 2 is arranged on the base plate 1, the base plate embedded T-type connector 2 is connected to the assembled shear wall 8 through high-strength bolts 7, a shear wall embedded beam T-type connector 10 is arranged on the upper surface of the assembled shear wall 8, an assembled T-type beam 13 is arranged above the assembled shear wall 8, and an assembled beam and shear wall embedded T-type connector 11 is installed on the assembled T-type beam 13.
[0041] An assembled beam and shear wall T-shaped connector 14 is installed on the upper surface of the assembled T-shaped beam 13, and assembled floor slabs 16 are arranged on both sides of the assembled T-shaped beam 13. The two assembled floor slabs 16 are symmetrically arranged. An assembled beam and column embedded T-shaped connector 12 is installed on one side of the assembled T-shaped beam 13, and an assembled floor slab embedded T-shaped connector 15 is installed on one side of each assembled floor slab 16. Each assembled floor slab embedded T-shaped connector 15 is connected to the assembled T-shaped beam 13 through a high-strength bolt 7. An assembled upper column 17 is arranged above the assembled concrete column 3, and upper and lower column embedded H-shaped connectors 6 are arranged on the upper surface of the assembled concrete column 3. The upper and lower column embedded H-shaped connectors 6 are connected to the assembled upper column 17 through high-strength bolts 7.
[0042] A beam embedded T-shaped connector 5 is provided on one side of the assembled concrete column 3, and the beam embedded T-shaped connector 5 is connected to the assembled T-shaped beam 13 through a high-strength bolt 7. A fixing plate 19 is installed on the assembled concrete column 3, and a plurality of round rods 20 are slidably connected to the fixing plate 19. The round rods 20 are clamped with the assembled column embedded T-shaped connector 4, and the plurality of round rods 20 are connected through a rectangular plate 18. A rectangular rod 24 is fixedly connected to the rectangular plate 18, and the rectangular rod 24 is slidably connected to the fixing plate 19, and one end of the rectangular rod 24 is fixedly connected to a limiting block 25.
[0043] The fixed plate 19 is slidably connected with a moving rod 23, and the moving rod 23 is clamped with the rectangular rod 24. One end of the moving rod 23 is fixedly connected with a moving block 21, and the moving block 21 is connected to the fixing plate 19 by a screw 22, pushing the rectangular plate 18, the rectangular rod 24 and the fixing plate 19 to slide relatively until each round rod 20 is clamped with the pre-embedded T-shaped connector 4 of the assembly column, and then keeping the position of the rectangular rod 24 unchanged, pushing the moving rod 23 until one end of the moving rod 23 is clamped with the rectangular rod 24, and then using the screw 22 to connect the moving block 21 and the fixing plate 19, which can prevent the moving rod 23 from moving, and each round rod 20 is stably clamped with the pre-embedded T-shaped connector 4 of the assembly column, so that the pre-embedded T-shaped connector 4 of the assembly column is stably connected to the assembled concrete column 3. When the threaded hole on the pre-embedded T-shaped connector 4 of the assembly column connected with the high-strength bolt 7 is damaged, it is convenient to replace the pre-embedded T-shaped connector 4 of the assembly column.
[0044] A fully assembled shear wall beam, slab and column high-strength bolt connection system first installs a bottom plate 1 with a bottom plate embedded T-type connector 2, and then installs an assembled concrete column 3 with an assembled column embedded T-type connector 4, a beam embedded T-type connector 5, and upper and lower column embedded H-type connectors 6. Install the assembled shear wall 8 with the shear wall embedded T-column connector 9 and the shear wall embedded beam T-connector 10. The shear wall embedded T-column connector 9 and the assembled column embedded T-connector 4 are connected to the assembled concrete column 3 and the base plate 1 through the high-strength bolts 7. Install the assembled T-beam 13 with the assembled beam and shear wall embedded T-connector 11, the assembled beam and column embedded T-connector 12, and the assembled beam and shear wall T-connector 14; the assembled beam and shear wall embedded T-connector 11 and the assembled beam and shear wall T-connector 14 are connected through the high-strength bolts 7, the assembled floor slab embedded T-connector 15 installs the assembled floor slab 16, the assembled concrete column 3 and the assembled upper column 17 are connected through the upper and lower column embedded H-connector 6 using high-strength bolts 7, and then install the assembled shear wall 8 until the entire structure is installed.
[0045] A fully assembled shear wall beam-slab-column high-strength bolt connection system, and a construction method thereof, comprising the following steps:
[0046] S1: Connect the prefabricated column with the pre-buried anchor bolts of the foundation and fix the column after correction;
[0047] S2: Connect the pre-buried connectors of the assembled shear wall with the base plate and the pre-buried connectors of the column through high-strength bolts 7;
[0048] S3: Connecting the prefabricated beam embedded parts with the columns and shear wall embedded parts through high-strength bolts 7;
[0049] S4: Connecting the prefabricated T-shaped floor slab embedded parts and the beam embedded parts by means of high-strength bolts 7;
[0050] S5: Strip panels, strip panels and T-shaped floor panels are spliced by embedded parts;
[0051] S6: Connect the upper assembly column and the lower assembly column by high-strength bolts 7;
[0052] S7: Install shear walls, beams and slabs to carry out prefabricated installation of the new floor slab;
[0053] S8: The installation is completed until the top layer is assembled.
[0054] The present invention comprises four parts, namely, an assembled shear wall 8, an assembled beam, an assembled floor slab 16, and an assembled column. The assembled shear wall 8 comprises a concrete shear wall slab, a connecting column embedded part, and a connecting beam embedded part; the assembled beam comprises a concrete beam body, a connecting column embedded part, and a connecting shear wall embedded part; the assembled floor slab 16 comprises a concrete floor slab, a connecting beam embedded part, and a floor slab splicing embedded part; the assembled column comprises a concrete column and an upper and lower column splicing embedded part. The fully assembled shear wall beam-slab-column high-strength bolt connection system splices the shear wall with the beam, slab, and column, the beam with the column, the floor slab, the floor slab with the floor slab, and the upper and lower columns through the high-strength bolts 7, thereby realizing a fully assembled connection system of the concrete structure.
[0055] The fully assembled shear wall beam, slab and column high-strength bolt connection system realizes the pre-production of all structural components in the factory and on-site hoisting and installation, which improves the traditional system of partial assembly and partial cast-in-place of components. The high-strength bolt 7 connection replaces the traditional assembled system, the steel sleeve connection at the node connection, and the connection method of supporting the formwork and pouring concrete. The high-strength bolt 7 connection is fast, efficient and high-strength. Compared with the traditional method, it saves a lot of construction time, realizes the full assembly of components on-site construction, avoids common problems such as cracking and insufficient strength of on-site concrete pouring, and improves quality; it realizes the truly fully assembled connection of concrete structures.
[0056] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A fully assembled shear wall beam-slab-column high-strength bolt connection system, comprising a base plate (1), an assembled shear wall (8) and an assembled concrete column (3), characterized in that: A pre-buried T-shaped connector for an assembly column (4) is installed on one side of the assembled concrete column (3); a pre-buried T-shaped connector for a shear wall (9) is installed on one side of the assembled shear wall (8); the pre-buried T-shaped connector for a shear wall (9) is connected to the pre-buried T-shaped connector for an assembly column (4) via a high-strength bolt (7); The bottom plate (1) is provided with a bottom plate embedded T-shaped connector (2), the bottom plate embedded T-shaped connector (2) is connected to the assembled shear wall (8) via high-strength bolts (7), the upper surface of the assembled shear wall (8) is provided with a shear wall embedded beam T-shaped connector (10), an assembled T-shaped beam (13) is provided above the assembled shear wall (8), and the assembled beam and shear wall embedded T-shaped connector (11) is installed on the assembled T-shaped beam (13); A fixing plate (19) is installed on the assembled concrete column (3), a plurality of round rods (20) are slidably connected to the fixing plate (19), the round rods (20) are clamped with the pre-buried T-shaped connector (4) of the assembly column, and the plurality of round rods (20) are connected via a rectangular plate (18); A rectangular rod (24) is fixedly connected to the rectangular plate (18), the rectangular rod (24) and the fixed plate (19) are slidably connected, and one end of the rectangular rod (24) is fixedly connected to a limiting block (25); The fixed plate (19) is slidably connected to a moving rod (23), the moving rod (23) and the rectangular rod (24) are clamped together, one end of the moving rod (23) is fixedly connected to a moving block (21), and the moving block (21) is connected to the fixed plate (19) via a screw (22).
2. A fully assembled shear wall beam-slab-column high-strength bolt connection system according to claim 1, characterized in that: An assembled beam and shear wall T-shaped connector (14) is installed on the upper surface of the assembled T-shaped beam (13), assembled floor slabs (16) are arranged on both sides of the assembled T-shaped beam (13), and the two assembled floor slabs (16) are arranged symmetrically, and an assembled beam and column pre-buried T-shaped connector (12) is installed on one side of the assembled T-shaped beam (13).
3. A fully assembled shear wall beam-slab-column high-strength bolt connection system according to claim 2, characterized in that: A prefabricated floor slab embedded T-shaped connector (15) is installed on one side of each prefabricated floor slab (16), and each prefabricated floor slab embedded T-shaped connector (15) is connected to the prefabricated T-shaped beam (13) via a high-strength bolt (7).
4. A fully assembled shear wall beam-slab-column high-strength bolt connection system according to claim 1, characterized in that: An assembled upper column (17) is arranged above the assembled concrete column (3), and upper and lower column pre-buried H-shaped connecting pieces (6) are arranged on the upper surface of the assembled concrete column (3), and the upper and lower column pre-buried H-shaped connecting pieces (6) are connected to the assembled upper column (17) via high-strength bolts (7).
5. A fully assembled shear wall beam-slab-column high-strength bolt connection system according to claim 1, characterized in that: A beam pre-embedded T-shaped connector (5) is provided on one side of the assembled concrete column (3); the beam pre-embedded T-shaped connector (5) is connected to the assembled T-shaped beam (13) via a high-strength bolt (7).
6. A fully assembled shear wall beam-slab-column high-strength bolt connection system according to any one of claims 1 to 5, wherein the construction method comprises the following steps: S1: Connect the prefabricated column with the pre-buried anchor bolts of the foundation and fix the column after correction; S2: Connect the pre-buried connectors of the assembled shear wall with the pre-buried connectors of the base plate and column through high-strength bolts; S3: Connecting the prefabricated beam embedded parts with the columns and shear wall embedded parts by means of high-strength bolts (7); S4: Connecting the prefabricated T-shaped floor slab embedded parts and the beam embedded parts by means of high-strength bolts (7); S5: Strip panels, strip panels and T-shaped floor panels are spliced by embedded parts; S6: Connect the upper assembly column and the lower assembly column by high-strength bolts (7); S7: Install shear walls, beams and slabs to carry out prefabricated installation of the new floor slab; S8: The installation is completed until the top layer is assembled.
Citation Information
Patent Citations
Method for connecting assembly energy consumption shearing walls capable of being detached, moved and spliced with framework
CN108560767A
C-shaped sleeve detachable and replaceable reinforced concrete column-column connecting structure and construction method
CN113073746A