A handling jig for fixing unit curtain wall hanging parts

By designing a handling fixture for fixing unit curtain wall hangings, and using the combined structure of the installation base plate and cylinder, the positioning and clamping of multiple hanging parts is achieved, the inefficiency problem caused by replacing the material clamping platform in the prior art is solved, and processing efficiency is improved and costs are reduced.

CN115744281BActive Publication Date: 2025-07-08SHANGHAI JANGHO CURTAIN WALL SYST ENG
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202211525171.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-11-30
Publication Date
2025-07-08
Estimated Expiration
2042-11-30

AI Technical Summary

Technical Problem

In the prior art, when processing Class A and Class B curtain wall hangings, the entire material clamping platform needs to be replaced, resulting in low processing efficiency.

Method used

A handling fixture for fixing unit curtain wall hangings is designed, and the base plate, the first cylinder and the second cylinder are installed. Through the hanging clamping area, rectangular grooves, pad plates, positioning blocks and other structures, the positioning and clamping of multiple hanging parts is realized, simplifying the replacement process.

Benefits of technology

It improves the efficiency of processing of a variety of pendants, reduces the waste of work hours when replacing workpieces, and has the advantages of simple structure, low cost and easy to use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115744281B_ABST
    Figure CN115744281B_ABST
Patent Text Reader

Abstract

The present invention provides a handling fixture for fixing unit curtain wall hanging parts, which relates to the field of processing and manufacturing. The handling fixture for fixing unit curtain wall hanging parts includes: a mounting base plate, a first cylinder and a second cylinder fixed on the mounting base plate; wherein, a hanging part clamping area is arranged on the mounting base plate, the first cylinder is arranged on a first side of the hanging part clamping area, and the second cylinder is arranged on a second side of the hanging part clamping area; the first cylinder and the second cylinder clamp and unload at least two types of hanging parts of the unit curtain wall in the hanging part clamping area. The solution of the present invention realizes the positioning during the processing of multiple types of hanging parts, and improves the efficiency during the processing of multiple types of hanging parts at the same time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of processing and manufacturing, and particularly to a handling fixture for fixing unit curtain wall hanging parts. Background Art

[0002] In recent years, with the rapid development of the curtain wall industry, the types of curtain wall hanging parts have become more and more, among which Type A and Type B hanging parts are used in relatively large quantities. When processing Type A and Type B hanging parts, both types of hanging parts need to be processed with a φ12 mounting hole. The existing process uses an automatic feeding device in cooperation with a punching machine for punching processing, which has a fast processing speed and does not require manual operation. The automatic feeding device needs to achieve clamping and positioning on the side of the part without holes. Because the differences between Type A and Type B hanging parts are very large, when changing between Type A or Type B products, the entire material clamping platform needs to be replaced, wasting a large amount of man-hours and thus affecting the processing efficiency. Summary of the Invention

[0003] The technical problem to be solved by the present invention is to provide a handling fixture for fixing unit curtain wall hanging parts to achieve positioning during the processing of multiple types of hanging parts and improve the efficiency during the processing of multiple types of hanging parts.

[0004] To solve the above technical problem, the technical solution of the present invention is as follows:

[0005] An embodiment of the present invention provides a handling fixture for fixing unit curtain wall hanging parts, including:

[0006] A mounting base plate, and a first cylinder and a second cylinder fixed on the mounting base plate;

[0007] Wherein, a hanging part clamping area is provided on the mounting base plate, the first cylinder is arranged on the first side of the hanging part clamping area, and the second cylinder is arranged on the second side of the hanging part clamping area; the first cylinder and the second cylinder clamp and unload at least two types of hanging parts of the unit curtain wall in the hanging part clamping area.

[0008] Optionally, a rectangular slot and a backing plate for limiting the first hanging part are provided in the hanging part clamping area of the mounting base plate, and the backing plate is fixed on one side of the rectangular slot;

[0009] The first hanging part is placed on the backing plate and fixed to the rectangular slot. The telescopic end of the first cylinder moves into the hanging part clamping area to fix the first hanging part. After the first hanging part is punched, the telescopic end of the second cylinder moves into the hanging part clamping area to push the first hanging part into the unloading cylinder.

[0010] Optionally, the first hanging part has a protrusion that is snap-fitted with the rectangular slot, and the first hanging part is snap-fitted into the rectangular slot through the protrusion and fixed to the rectangular slot.

[0011] Optionally, the telescopic end of the second cylinder has a second push plate, and when the telescopic end of the second cylinder moves into the hanging part clamping area, the first hanging part is pushed to the discharging cylinder through the second push plate.

[0012] Optionally, a first positioning block and a second positioning block for limiting the second hanging part are arranged on the mounting bottom plate;

[0013] The first positioning block is arranged on the first side of the hanging part clamping area, and the second positioning block is arranged on the third side of the hanging part clamping area;

[0014] The second hanging part is placed in the hanging part clamping area, and when the telescopic end of the second cylinder moves into the hanging part clamping area, the second hanging part is fixed on one side of the second positioning block. After the second hanging part is drilled, the telescopic end of the first cylinder moves into the hanging part clamping area to push out the second hanging part to the discharging cylinder.

[0015] Optionally, the surface of the second hanging part in contact with the mounting bottom plate is a plane, and a protrusion is arranged on the opposite surface of the plane of the second hanging part. The second cylinder fixes the second hanging part on one side of the second positioning block by pressing the protruding part of the second hanging part.

[0016] Optionally, a first groove is arranged on the first positioning block, and the telescopic end of the first cylinder passes through the first groove to push the second hanging part in the hanging part clamping area to the discharging cylinder.

[0017] Optionally, the telescopic end of the first cylinder is provided with a first push plate, and when the first cylinder moves into the hanging part clamping area, the second hanging part is pushed out to the discharging cylinder through the first push plate.

[0018] Optionally, the hanging part clamping area is a rectangular clamping area.

[0019] The above solution of the present invention has at least the following beneficial effects:

[0020] The handling fixture for fixing unit curtain wall hanging parts of the present invention includes: a mounting bottom plate, a first cylinder and a second cylinder fixed on the mounting bottom plate; wherein, a hanging part clamping area is arranged on the mounting bottom plate, the first cylinder is arranged on the first side of the hanging part clamping area, and the second cylinder is arranged on the second side of the hanging part clamping area; the first cylinder and the second cylinder clamp and discharge at least two types of hanging parts of the unit curtain wall in the hanging part clamping area. The positioning during the processing of multiple types of hanging parts is realized, and at the same time, the efficiency during the processing of multiple types of hanging parts is improved. Description of the Drawings

[0021] Figure 1It is a top view of the handling fixture for fixing unit curtain wall hanging parts of the present invention when the first positioning block and the second positioning block are not installed;

[0022] Figure 2 It is a front view of the handling fixture for fixing unit curtain wall hanging parts of the present invention when the first positioning block and the second positioning block are not installed;

[0023] Figure 3 It is a top view of the handling fixture for fixing unit curtain wall hanging parts of the present invention after clamping the first hanging part clamp;

[0024] Figure 4 It is a right view of the handling fixture for fixing unit curtain wall hanging parts of the present invention after clamping the first hanging part clamp;

[0025] Figure 5 It is a top view of the handling fixture for fixing unit curtain wall hanging parts of the present invention when discharging the first hanging part;

[0026] Figure 6 It is a top view of the handling fixture for fixing unit curtain wall hanging parts of the present invention when the backing plate is not installed;

[0027] Figure 7 It is a front view of the handling fixture for fixing unit curtain wall hanging parts of the present invention when the backing plate is not installed;

[0028] Figure 8 It is a top view of the handling fixture for fixing unit curtain wall hanging parts of the present invention after clamping the second hanging part clamp;

[0029] Figure 9 It is a top view of the handling fixture for fixing unit curtain wall hanging parts of the present invention when discharging the second hanging part;

[0030] Figure 10 It is a top view of the mounting base plate of the handling fixture for fixing unit curtain wall hanging parts of the present invention;

[0031] Figure 11 It is a front view of the first positioning block of the handling fixture for fixing unit curtain wall hanging parts of the present invention;

[0032] Figure 12 It is a front view of the second hanging part of the handling fixture for fixing unit curtain wall hanging parts of the present invention;

[0033] Figure 13 It is a front view of the first hanging part of the handling fixture for fixing unit curtain wall hanging parts of the present invention.

[0034] Explanation of reference numerals:

[0035] 1. Installation base plate; 2. First cylinder; 21. First push plate; 3. Second cylinder; 31. Second push plate; 4. First hanging part; 41. Rectangular slot; 42. Padding plate; 5. Second hanging part; 51. First positioning block; 52. Second positioning block. Detailed implementation manners

[0036] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided so that the present disclosure can be more thoroughly understood and the scope of the present disclosure can be fully conveyed to those skilled in the art.

[0037] As Figures 1 to 11 shown, an embodiment of the present invention provides a handling jig for fixing unit curtain wall hanging parts, including:

[0038] An installation base plate 1 and a first cylinder 2 and a second cylinder 3 fixed on the installation base plate 1;

[0039] Wherein, a hanging part clamping area is provided on the installation base plate 1, the first cylinder 2 is arranged on the first side of the hanging part clamping area, and the second cylinder 3 is arranged on the second side of the hanging part clamping area; the first cylinder 2 and the second cylinder 3 clamp and unload at least two types of hanging parts of the unit curtain wall in the hanging part clamping area. Here, the hanging part clamping area is preferably a rectangular clamping area.

[0040] In this embodiment, the first side and the second side of the hanging part clamping area are adjacent sides of the clamping area, and both the first cylinder 2 and the second cylinder 3 have clamping and unloading functions. When the first cylinder 2 uses the clamping function, the second cylinder 3 uses the unloading function.

[0041] As Figures 1 to 5 shown, in an alternative embodiment of the present invention, a rectangular slot 41 and a padding plate 42 for limiting the first hanging part 4 are provided in the hanging part clamping area of the installation base plate 1, and the padding plate 42 is fixed on one side of the rectangular slot 41;

[0042] The first hanging part 4 is placed on the padding plate 42 and fixed on the rectangular slot 41. The telescopic end of the first cylinder 2 moves into the hanging part clamping area to fix the first hanging part 4. After the first hanging part 4 is drilled, the telescopic end of the second cylinder 3 moves into the hanging part clamping area to push the first hanging part 4 to the unloading cylinder.

[0043] As Figure 4 and Figure 13As shown, the first hanging part 4 has a protrusion that is snap-fitted with the rectangular slot 41. The first hanging part 4 is snap-fitted into the rectangular slot 41 through the protrusion and fixed to the rectangular slot 41.

[0044] In this embodiment, the length direction of the rectangular slot 41 is parallel to the fourth side of the hanging part clamping area and perpendicular to the third side of the hanging part clamping area, and one end of the rectangular slot 41 penetrates the third side of the hanging part clamping area. Among them, the fourth side of the hanging part clamping area is adjacent to the second side of the hanging part clamping area, and the third side of the hanging part clamping area is adjacent to the first side of the hanging part clamping area; the backing plate 42 is arranged between the rectangular slot 41 and the fourth side of the hanging part clamping area and is fixedly connected to the mounting base plate 1 by screws.

[0045] In this embodiment, during the clamping process of the first hanging part 4, first place the first hanging part 4 on the backing plate 42 and make the protrusion part of the first hanging part 4 located in the rectangular slot 41 and snap-fitted with the rectangular slot 41. Then, the telescopic end of the first cylinder 2 moves into the hanging part clamping area to press the first hanging part 4, so that the protrusion part of the first hanging part 4 is in close contact with the side wall of the backing plate 42, thereby fixing the first hanging part 4 on the mounting base plate 1. Then, drill holes in the first hanging part 4. After drilling holes in the first hanging part 4, the telescopic end of the first cylinder 2 retracts, and the telescopic end of the second cylinder 3 moves into the hanging part clamping area to push the first hanging part 4 along the rectangular slot 41 from the third side of the hanging part clamping area to the discharge cylinder.

[0046] In an alternative embodiment of the present invention, the telescopic end of the second cylinder 3 has a second push plate 31. When the telescopic end of the second cylinder 3 moves into the hanging part clamping area, the first hanging part 4 is pushed to the discharge cylinder through the second push plate 31.

[0047] As Figures 6 to 9 shown, in an alternative embodiment of the present invention, a first positioning block 51 and a second positioning block 52 for limiting the second hanging part 5 are arranged on the mounting base plate 1;

[0048] The first positioning block 51 is arranged on the first side of the hanging part clamping area, and the second positioning block 52 is arranged on the third side of the hanging part clamping area;

[0049] The second hanging part 5 is placed in the hanging part clamping area. When the telescopic end of the second cylinder 3 moves into the hanging part clamping area, the second hanging part 5 is fixed to one side of the second positioning block 52. After the second hanging part 5 is drilled, the telescopic end of the first cylinder 2 moves into the hanging part clamping area to push the second hanging part 5 to the discharge cylinder.

[0050] AsFigure 12 As shown, the surface of the second hanging part 5 in contact with the mounting base plate 1 is a flat surface, and a protrusion is provided on the opposite surface of the flat surface of the second hanging part 5. The second air cylinder 3 fixes the second hanging part to one side of the second positioning block 52 by squeezing the protruding part of the second hanging part.

[0051] As Figure 6 and 11 shown, a first groove is provided on the first positioning block 51, and the telescopic end of the first air cylinder 2 passes through the first groove to push the second hanging part 5 in the hanging part clamping area to the discharge cylinder.

[0052] In this embodiment, when clamping the second hanging part, first, the backing plate 42 needs to be removed, and then the first positioning block 51 and the second positioning block 52 are respectively fixed to the first side and the third side of the hanging part clamping area by bolts. Then, the second hanging part 5 is placed in the hanging part clamping area, so that the flat surface of the second hanging part 5 contacts the mounting base plate 1, and the second hanging part 5 contacts the side walls of the first positioning block 51 and the second positioning block 52. Then, the telescopic end of the second air cylinder 3 moves into the hanging part clamping area and squeezes the second hanging part 5 through the second push plate 31, squeezing the second hanging part 5 against the side wall of the second positioning block 52, so that the second hanging part 5 is fixed on the mounting base plate 1. Then, after the second hanging part 5 is drilled, the telescopic end of the second air cylinder 3 retracts, and the telescopic end of the first air cylinder 2 moves into the hanging part clamping area to push out the second hanging part 5 to the discharge cylinder.

[0053] In an alternative embodiment of the present invention, a first push plate 21 is provided at the telescopic end of the first air cylinder 2, and the first air cylinder 2 moves into the hanging part clamping area and pushes out the second hanging part 5 to the discharge cylinder through the first push plate.

[0054] For the handling jig for fixing unit curtain wall hanging parts of the present invention, during the process of processing the first hanging part 4 (i.e., part A), when it is necessary to process the second hanging part 5 (i.e., part B), the backing plate 42 needs to be removed, and the first positioning block 51 and the second positioning block 52 need to be installed. Then, the second air cylinder 3 is used to clamp the second hanging part 5. After the second hanging part 5 is processed, the first air cylinder 2 is used to unload the second hanging part 5; similarly, for the handling jig for fixing unit curtain wall hanging parts, during the process of processing the second hanging part 5, when it is necessary to process the first hanging part 4, the first positioning block 51 and the second positioning block 52 need to be removed, and the backing plate 42 needs to be installed. Then, the first air cylinder 2 is used to clamp the first hanging part 4. After the first hanging part 4 is processed, the second air cylinder 3 is used to unload the first hanging part 4.

[0055] For the handling jig for fixing unit curtain wall hanging parts described in the present invention, during the processing, when it is necessary to replace different hanging parts for processing, it is only necessary to simply replace the parts on the mounting base according to the requirements of the hanging parts, which solves the problem in the prior art that when replacing the processed workpiece, the entire material clamping platform needs to be replaced, wasting a large amount of working hours and affecting the processing efficiency. The processing efficiency is improved, and at the same time, it has the advantages of simple structure, low production cost and convenient use.

[0056] The above is the preferred implementation manner of the present invention. It should be pointed out that for those of ordinary skill in the art of the present technology, without departing from the principle described in the present invention, several improvements and refinements can be made, and these improvements and refinements should also be regarded as the protection scope of the present invention.

Claims

1. A handling jig for fixing unit curtain wall hanging parts, characterized in that, Comprising: An installation base plate (1), a first cylinder (2) and a second cylinder (3) fixed on the installation base plate (1); Wherein, a hanger clamping area is provided on the installation base plate (1), the first cylinder (2) is arranged on the first side of the hanger clamping area, and the second cylinder (3) is arranged on the second side of the hanger clamping area; the first cylinder (2) and the second cylinder (3) clamp and unload at least two types of hangers of the unit curtain wall in the hanger clamping area; A rectangular slot (41) and a backing plate (42) for limiting the first hanger (4) are provided in the hanger clamping area of the installation base plate (1), and the backing plate (42) is fixed on one side of the rectangular slot (41); The first hanger (4) is placed on the backing plate (42) and fixed on the rectangular slot (41). The telescopic end of the first cylinder (2) moves into the hanger clamping area to fix the first hanger (4). After the first hanger (4) is punched, the telescopic end of the second cylinder (3) moves into the hanger clamping area to push the first hanger (4) into the unloading cylinder; The first hanger (4) has a protrusion that is snap-fitted with the rectangular slot (41), and the first hanger (4) is snap-fitted into the rectangular slot (41) through the protrusion and fixed to the rectangular slot (41); The telescopic end of the second cylinder (3) has a second push plate (31). When the telescopic end of the second cylinder (3) moves into the hanger clamping area, it pushes the first hanger (4) into the unloading cylinder through the second push plate (31); A first positioning block (51) and a second positioning block (52) for limiting the second hanger (5) are provided on the installation base plate (1); The first positioning block (51) is arranged on the first side of the hanger clamping area, and the second positioning block (52) is arranged on the third side of the hanger clamping area; The second hanger (5) is placed in the hanger clamping area. When the telescopic end of the second cylinder (3) moves into the hanger clamping area, the second hanger (5) is fixed on one side of the second positioning block (52). After the second hanger (5) is punched, the telescopic end of the first cylinder (2) moves into the hanger clamping area to push the second hanger (5) into the unloading cylinder.

2. The handling jig for fixing the unit curtain wall hanger according to claim 1, characterized in that, The surface of the second hanger (5) in contact with the installation base plate (1) is a plane, and a protrusion is provided on the opposite surface of the plane of the second hanger (5). The second cylinder (3) fixes the second hanger on one side of the second positioning block (52) by squeezing the protruding part of the second hanger.

3. The handling jig for fixing the unit curtain wall hanging piece according to claim 1, characterized in that, A first groove is provided on the first positioning block (51), and the telescopic end of the first cylinder (2) passes through the first groove to push the second hanger (5) in the hanger clamping area into the unloading cylinder.

4. The handling jig for fixing the unit curtain wall hanging parts according to claim 1, wherein, The telescopic end of the first cylinder (2) is provided with a first push plate (21). When the first cylinder (2) moves into the hanger clamping area, it pushes the second hanger (5) into the unloading cylinder through the first push plate.

5. The handling fixture for fixing the unit curtain wall hanging parts according to claim 1, wherein The hanger clamping area is a rectangular clamping area.

Citation Information

Patent Citations

  • Punching device convenient to position and used for curtain wall machining